An integrated connection node structure of floor deck and ceiling hanger
By designing an integrated connection node structure between floor bearing plate and ceiling boom in a large span steel concrete roof structure, using full welding connection between nails and keels, and anchoring in the concrete, the structural damage and water leakage caused by ceiling installation are solved, and higher safety and economic benefits are achieved.
Patent Information
- Application Number
- CN202421477030.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-26
- Publication Date
- 2025-04-11
- Estimated Expiration
- 2034-06-26
AI Technical Summary
In large-span steel concrete roof structures, the installation of ceiling booms will cause damage to the roof structure and water leakage, affecting safe use.
A integrated connection node structure between the floor bearing plate and the ceiling hoist is designed. By setting bolts on the keel and anchoring the bolts after concrete is poured, the stable connection between the boom and the floor bearing plate is achieved.
This structure can significantly improve the safety of the ceiling and the waterproofing performance of the roof, reduce the time for later decoration, speed up the construction progress, and increase economic benefits.
Smart Images

Figure CN222745423U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical fields of roof structure construction, roof waterproofing and decoration, and specifically to an integrated connection node structure of a floor deck and a ceiling hanger. Background Art
[0002] At present, floor slab structures are often used in large-span steel-concrete roof structures, such as theaters or conference halls. The decoration standards of these places are often high, and their suspended ceilings are the highlights of the decoration. If the suspended ceiling hangers open holes in the floor slab during decoration, it will cause damage to the roof structure and there will be hidden dangers of leakage. Once leaking, it will cause damage to the suspended ceiling, thus affecting safe use.
[0003] However, in construction sites such as theaters or conference halls, floor deck structures are often used in large-span steel-concrete roof structures. The decoration standards of such sites are relatively high, and ceiling projects usually drill holes at the bottom of the roof to install hangers. Improper operation will affect the structural safety and roof waterproofing performance. Therefore, it is necessary to improve the hanger installation construction. Utility Model Content
[0004] The utility model aims to provide an integrated connection node structure of a floor deck and a ceiling hanger to solve the problems raised in the above-mentioned background technology.
[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0006] A node structure for an integrated connection between a floor deck and a ceiling hanger, comprising a keel frame, wherein the keel frame comprises a steel plate and a steel frame, the top surface of the steel plate is provided with a steel frame, the steel frame is formed by splicing a plurality of steel bars, a plurality of first nodes are provided at the bottom of the keel frame, hangers are provided inside a plurality of the first nodes, a plurality of second nodes are provided at the bottom steel plate of the keel frame, the top of each of the hangers is in the same horizontal plane as the top of the second node, mounting ears are provided at both ends of the top opening surfaces of a plurality of the first nodes, ear holes are provided at the top and bottom of the mounting ears, fixing bolts are provided inside the ear holes, the mounting ears are fixedly connected to the keel frame by fixing bolts, and a ceiling is provided at the bottom of a plurality of the hangers.
[0007] Preferably, a bolt is provided on the top of the suspension rod, and the suspension rod is fully welded to the keel frame via the bolt.
[0008] Preferably, the interior of the keel frame is filled with concrete.
[0009] Preferably, the first node is formed by welding a plurality of steel plates.
[0010] Compared with the prior art, the beneficial effects of the utility model are:
[0011] The utility model is an integrated connection node structure between floor decking and ceiling hanger. In the process of floor decking production, holes are opened at the location of the bolts according to the hanger spacing, the length of the bolts is increased so that the length of the bolts below meets the requirements of ceiling installation, the bolts are fully welded around the holes, and anti-rust and anti-corrosion paint is applied after welding to ensure the quality of use. After the roof concrete is poured, the bolts are anchored in the concrete, and the bearing capacity far exceeds the ceiling load, greatly improving safety. This node can greatly reduce the time for later decoration, speed up the construction progress, and increase economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0013] Figure 2 It is a schematic diagram of the overall exploded view structure of the utility model.
[0014] In the figure: 1, keel frame; 2, first node; 3, suspension rod; 4, bolt; 5, mounting ear; 6, second node. DETAILED DESCRIPTION
[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0016] In the description of the present invention, it should be noted that the terms "vertical", "up", "down", "horizontal", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0017] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0018] See also Figure 1-2 , the utility model provides a technical solution:
[0019] A node structure for integrating a floor deck and a ceiling hanger, comprising a keel frame 1, wherein the keel frame 1 comprises a steel plate and a steel frame, wherein a steel frame is arranged on the top surface of the steel plate, and the steel frame is formed by splicing a plurality of steel bars, wherein a plurality of first nodes 2 are arranged at the bottom of the keel frame 1, and hangers 3 are arranged inside the plurality of first nodes 2, and a plurality of second nodes 6 are provided on the bottom steel plate of the keel frame 1, and the tops of the plurality of hangers 3 are in the same horizontal plane as the tops of the second nodes 6, and mounting ears 5 are provided at both ends of the top opening surfaces of the plurality of first nodes 2, and ear holes are provided at the top and bottom of the mounting ears 5, and fixing bolts are arranged inside the ear holes, and the mounting ears 5 are fixedly connected to the keel frame 1 by fixing bolts, and a ceiling is provided at the bottom of the plurality of hangers 3.
[0020] Furthermore, a bolt 4 is provided on the top of the suspension rod 3 , and the suspension rod 3 is fully welded to the keel frame 1 via the bolt 4 .
[0021] In addition, after the stud 4 is welded, anti-rust and anti-corrosion paint is applied to ensure the quality of use and prevent rust.
[0022] Furthermore, the interior of the keel frame 1 is filled with concrete.
[0023] Specifically, after the roof concrete is poured, the bolts 4 are anchored in the concrete, and the bearing capacity far exceeds the ceiling load, thereby greatly improving the safety.
[0024] Furthermore, the first node 2 is formed by welding a plurality of steel plates.
[0025] Specifically, the height of the first node 2 will be set according to actual conditions. When the height of the first node 2 is higher, the hanger 3 located inside the first node 2 will be higher, because the bottoms of several hangers 3 are set to the ceiling, and the distance between the ceiling and the bottom of the first node 2 is also set according to actual conditions.
[0026] It should be noted that the utility model produces the keel frame 1 and the first node 2 separately, which can make the production more convenient, and then connect the keel frame 1 and the first node 2 by fixing bolts after the separate production is completed. In addition, in the prior art, in order to make the ceiling look good, the height of the ceiling is different, which will make the height of the first node 2 and the distance between the ceiling and the bottom of the first node 2 different. Producing the keel frame 1 and the first node 2 separately can facilitate the production of first nodes 2 of different heights, which has certain practicality.
[0027] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An integrated connection node structure of a floor deck and a ceiling hanger, comprising a keel frame (1), characterized in that: The keel frame (1) comprises a steel plate and a steel frame. The top surface of the steel plate is provided with a steel frame, which is formed by splicing a plurality of steel bars. The bottom of the keel frame (1) is provided with a plurality of first nodes (2), and a plurality of suspension rods (3) are provided inside the first nodes (2). The bottom steel plate of the keel frame (1) is provided with a plurality of second nodes (6), and the tops of the plurality of suspension rods (3) are in the same horizontal plane as the tops of the second nodes (6). Mounting ears (5) are provided at both ends of the top opening surfaces of the plurality of first nodes (2), and ear holes are provided at the top and bottom of the mounting ears (5), and fixing bolts are provided inside the ear holes. The mounting ears (5) are fixedly connected to the keel frame (1) by fixing bolts, and a ceiling is provided at the bottom of the plurality of suspension rods (3).
2. The integrated connection node structure of floor deck and ceiling hanger according to claim 1, characterized in that: A bolt (4) is provided at the top of the suspension rod (3), and the suspension rod (3) is fully welded to the keel frame (1) via the bolt (4).
3. The integrated connection node structure of floor deck and ceiling hanger according to claim 1, characterized in that: The interior of the keel frame (1) is filled with concrete.
4. The integrated connection node structure of floor deck and ceiling hanger according to claim 1, characterized in that: The first node (2) is formed by welding a plurality of steel plates.