Fabricated beam storage buttress

By designing prefabricated beam support piers, using the combined structure of elastic components and locking components, flexible movement and locking of the support piers are achieved, which solves the problems of complex removal of support piers and difficult quantity adjustments in the prior art, and realizes efficient movement and flexible adjustment of the support piers.

CN222758735UActive Publication Date: 2025-04-15CHINA RAILWAY NO 3 GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421502002.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2025-04-15
Estimated Expiration
2034-06-28

AI Technical Summary

Technical Problem

After the box girder is prefabricated, support piers need to be installed when placing the box girder. The existing technology is made by pouring concrete, which leads to a large amount of workload for later reclamation and the difficulty in flexibly adjusting the number of support piers.

Method used

A prefabricated beam pier is designed, which adopts a combined structure of base, pier, placing plate, mounting frame, elastic component, mounting frame, locking component and pushing component. Through the cooperation of elastic component and locking component, flexible movement and locking of the pier is achieved.

Benefits of technology

The prefabricated beam piers facilitate the placement and removal of box beams by moving them, avoiding the complex demolition process caused by concrete pouring, and the number of piers can be flexibly adjusted according to the box beam specifications, and supporting the recycling of piers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222758735U_ABST
    Figure CN222758735U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type beam storage buttress which comprises a base, a buttress base is fixedly arranged at the top of the base through bolts, a placing plate is fixedly arranged at the top of the buttress base through bolts, an installation frame is fixedly arranged at the top of the base, and an elastic assembly is arranged in the installation frame. A mounting frame is arranged in the mounting frame through an elastic assembly, a locking assembly is arranged in the mounting frame, and a pushing assembly is arranged in the mounting frame. The vertical springs drive the moving rods to reset through the moving rings, so that the mounting frame drives the moving wheels to be separated from the ground through the mounting stand columns, the buttress can be conveniently moved, the box girder can be conveniently placed through the movable buttress, the situation that excessive concrete needs to be used for pouring the buttress is avoided, and the construction efficiency is improved. And in addition, the buttresses of different numbers can be placed according to the specifications of the box girders, and the buttresses can be recycled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of beam storage piers, in particular to an assembled beam storage pier. Background Art

[0002] Box girder is a type of beam in bridge engineering. It is hollow inside and has flanges on both sides of the upper part, similar to a box, hence the name. Box girders of reinforced concrete structures are divided into prefabricated box girders and cast-in-place box girders. Box girders prefabricated in an independent site can be erected in combination with a bridge erection machine after the completion of the lower project, which can speed up the progress of the project and save construction time; cast-in-place box girders are mostly used for large continuous bridges. There are two main types of common materials, one is prestressed reinforced concrete box girder, and the other is steel box girder. Among them, prestressed reinforced concrete box girders are constructed on-site. In addition to longitudinal prestress, some also have transverse prestress; steel box girders are generally processed in the factory and then transported to the site for installation. There are all-steel structures and some with reinforced concrete pavement layers. Among them, steel box girders, also called steel plate box girders, are a common structural form for large-span bridges. It is generally used on bridges with larger spans.

[0003] After the box girder is prefabricated, it is necessary to place the prefabricated box girder in a beam storage area. When the box girder is placed in the beam storage area, piers need to be set at the bottom of the box girder. The usual piers are made of concrete, and more foundation concrete is invested, which increases the workload of later reclamation and concrete removal. Therefore, an assembled beam storage pier is proposed. Utility Model Content

[0004] In view of the deficiencies in the prior art, the utility model provides an assembled beam storage pier for solving the problems raised in the above-mentioned background technology.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] A prefabricated beam storage pier comprises a base, a pier seat is fixedly provided on the top of the base by bolts, a placement plate is fixedly provided on the top of the pier seat by bolts, a mounting frame is fixedly provided on the top of the base, an elastic component is provided inside the mounting frame, a mounting frame is provided inside the mounting frame through the elastic component, a locking component is provided inside the mounting frame, a pushing component is provided inside the mounting frame, a mounting column is fixedly provided on the bottom of the mounting frame, and a moving wheel is fixedly provided on the bottom of the mounting column.

[0007] Preferably, the elastic component includes a movable hole, the movable hole passes through the top of the mounting frame, a movable rod is slidably arranged inside the movable hole, a limiting plate is fixedly arranged on the top of the movable rod, a movable ring is fixedly arranged on the surface of the movable rod, a vertical spring is fixedly arranged on the top of the movable ring, the top of the vertical spring is fixedly installed on the upper side wall of the mounting frame, and the mounting frame is fixedly installed on the bottom end of the movable rod.

[0008] Preferably, the locking assembly includes a limit block, which is slidably arranged inside the installation frame, the limit block overlaps with the installation frame, a transverse spring is fixedly arranged between the facing surfaces of the limit block, a locking block is overlapped on the top of the limit block, and the locking block is fixedly mounted on the inner wall of the installation frame.

[0009] Preferably, the pushing assembly comprises a moving plate, the moving plate is slidably arranged inside the mounting frame, a rectangular baffle is fixedly arranged at the bottom of the moving plate, and a placement groove for placing the rectangular baffle is opened inside the mounting frame.

[0010] Preferably, the bottom of the limit block is an inclined surface, the top of the locking block is an inclined surface, and the limit block and the locking block are both made of metal.

[0011] Preferably, a blocking plate is fixedly arranged inside the mounting frame, and the number of the blocking plates is several and symmetrically distributed.

[0012] Preferably, the mounting frame is in an inverted U-shaped structure, the mounting frame is made of metal material, and the number of the mounting frames is four and they are symmetrically distributed.

[0013] Compared with the prior art, the beneficial effects of the utility model are as follows: the assembled beam storage pier, through the limit plate, pushes the moving rod to drive the moving ring to stretch the vertical spring, so that the installation frame drives the limit block to insert into the bottom of the locking block, so that the installation frame pushes the moving wheel to contact the ground through the installation column, and the pier can be moved, and then the pushing component pushes the limit block to move out from the bottom of the locking block, and the vertical spring drives the moving rod to reset through the moving ring, so that the installation frame drives the moving wheel to separate from the ground through the installation column, thereby facilitating the movement of the pier, and the movable pier facilitates the placement of the box beam, avoiding the need to use too much concrete to cast the pier, resulting in a large amount of time spent on the subsequent dismantling of the pier, and different numbers of piers can be placed according to the specifications of the box beam, and the piers can be recycled. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is the structural survey drawing of the utility model;

[0015] Figure 2 It is a schematic diagram of the longitudinal section structure of the local structure of the utility model;

[0016] Figure 3 This is a schematic diagram of the structure of the elastic component of the utility model;

[0017] Figure 4 This is a schematic diagram of the structure of the structural locking component of the utility model.

[0018] In the figure: 1. base; 2. pier; 3. placement plate; 4. mounting frame; 5. moving hole; 6. moving rod; 7. limit plate; 8. vertical spring; 9. moving ring; 10. mounting frame; 11. limit block; 12. transverse spring; 13. locking block; 14. rectangular baffle; 15. mounting column; 16. moving wheel; 17. moving plate. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0020] Reference Figure 1-4A prefabricated beam storage pier comprises a base 1, a pier seat 2 is fixedly arranged on the top of the base 1 by bolts, a placing plate 3 is fixedly arranged on the top of the pier seat 2 by bolts, a mounting frame 4 is fixedly arranged on the top of the base 1, the mounting frame 4 is an inverted U-shaped structure, the mounting frame 4 is made of metal material, the number of the mounting frames 4 is four and they are symmetrically distributed, the mounting frames 4 made of metal have higher strength, so that the mounting frames 4 are more durable, and the service life of the mounting frames 4 is longer, an elastic component is arranged inside the mounting frame 4, the elastic component comprises a moving hole 5, the moving hole 5 runs through the top of the mounting frame 4, a moving rod 6 is slidably arranged inside the moving hole 5, a limiting plate 7 is fixedly arranged on the top of the moving rod 6, a moving ring 9 is fixedly arranged on the surface of the moving rod 6, and the top of the moving ring 9 A vertical spring 8 is fixedly provided, and the top of the vertical spring 8 is fixedly installed on the upper side wall of the mounting frame 4. The mounting frame 10 is fixedly installed on the bottom end of the moving rod 6. Through the setting of the elastic component, when the moving wheel 16 is retracted, the moving wheel 16 is driven to separate from the ground, so that the base 1 is in contact with the ground. The mounting frame 4 is provided with a mounting frame 10 through the elastic component. The mounting frame 10 is provided with a locking component. The locking component includes a limit block 11. The limit block 11 is slidably provided inside the mounting frame 10. The limit block 11 overlaps with the mounting frame 4. A transverse spring 12 is fixedly provided between the facing surfaces of the limit block 11. A locking block 13 is overlapped on the top of the limit block 11. A blocking plate is fixedly provided inside the mounting frame 4, and the number of the blocking plates is several and arranged in a row. The symmetrical distribution is achieved by setting the blocking plate so that when the limit block 11 compresses the transverse spring 12 and shrinks into the installation frame 10, there will be no shaking or deviation, so that the limit block 11 can be inserted into the bottom of the locking block 13, avoiding the limit block 11 and the locking block 13 from being locked and misaligned. The bottom of the limit block 11 is an inclined surface, and the top of the locking block 13 is an inclined surface. The limit block 11 and the locking block 13 are both made of metal. Through the inclined surface, the locking block 13 can squeeze the limit block 11, so that the limit block 11 compresses the transverse spring 12, thereby shrinking the limit block 11 into the installation frame 10, so that the limit block 11 can move to the bottom of the locking block 13, thereby facilitating the limit block 11 to be inserted into the bottom of the locking block 13, and the metal material The limit block 11 and the locking block 13 are not prone to breakage. The locking block 13 is fixedly mounted on the inner wall of the mounting frame 4. Through the setting of the locking assembly, the position of the moving wheel 16 is locked after the moving wheel 16 contacts the ground. A pushing assembly is arranged inside the mounting frame 4. A mounting column 15 is fixedly arranged at the bottom of the mounting frame 10. A moving wheel 16 is fixedly arranged at the bottom of the mounting column 15. The moving rod 6 is pushed by the limit plate 7 to drive the moving ring 9 to stretch the vertical spring 8, so that the mounting frame 10 drives the limit block 11 to insert into the bottom of the locking block 13, so that the mounting frame 10 pushes the moving wheel 16 to contact the ground through the mounting column 15, and the pier can be moved, and then the pushing assembly pushes the limit block 11 to move out from the bottom of the locking block 13.The vertical spring 8 drives the moving rod 6 to reset through the moving ring 9, so that the installation frame 10 drives the moving wheel 16 to separate from the ground through the installation column 15, so as to facilitate the movement of the piers. The movable piers are convenient for placing the box beam, avoiding the need to use too much concrete to cast the piers, resulting in a lot of time spent on the subsequent removal of the piers. Different numbers of piers can be placed according to the specifications of the box beam, and the piers can be recycled.

[0021] Specifically, the pushing component includes a moving plate 17, which is slidably arranged inside the mounting frame 4, and a rectangular baffle 14 is fixedly arranged at the bottom of the moving plate 17. A placement groove for placing the rectangular baffle 14 is opened inside the mounting frame 4. The moving plate 17 is pushed to drive the rectangular baffle 14 to move, so that the moving plate 17 pushes the limit block 11 away from the bottom of the locking block 13, thereby facilitating the moving rod 6 to drive the limit block 11 to move to the top of the locking block 13 through the mounting frame 10, thereby facilitating the retraction of the moving wheel 16.

[0022] When in use: assemble the base 1, pier 2 and placement plate 3 together by bolts, then push the limit plate 7 to drive the moving rod 6 to slide downward in the moving hole 5, push the moving ring 9 downward by the moving rod 6, so that the moving ring 9 stretches the vertical spring 8, and push the installation frame 10 downward by the moving rod 6, so that the limit block 11 squeezes the inclined surface of the locking block 13, and the limit block 11 squeezes the inclined surface of the locking block 13 by the limit block 11, so that the limit block 11 shrinks to the inside of the installation frame 10, so that the limit block 11 compresses the transverse spring 12, and when the top of the limit block 11 is horizontally aligned with the bottom of the locking block 13, the limit block 11 is pushed out of the installation frame 10 by the rebound effect of the transverse spring 12, so that the limit block 11 is inserted into the bottom of the locking block 13, and the limit block 11 contacts the inner wall of the installation frame 4, and at the same time 1 pushes the moving plate 17 to move, and makes the rectangular baffle 14 enter the interior of the mounting frame 4, so that the mounting frame 10 pushes the moving wheel 16 to contact the ground through the mounting column 15, so that the base 1 is separated from the bottom surface, and the base 1 can be moved by the moving wheel 16. When it moves to the placement position, the rectangular baffle 14 is driven to move by pushing the moving plate 17, so that the moving plate 17 pushes the limit block 11 to move out from the bottom of the locking block 13, and because the vertical spring 8 is in a stretched state, the vertical spring 8 drives the moving ring 9 to move upward, so that the moving ring 9 drives the moving rod 6 to reset, so that the moving rod 6 drives the moving wheel 16 to separate from the ground through the mounting frame 10 and the mounting column 15, and the base 1 is in contact with the ground, and at the same time, the mounting frame 10 drives the limit block 11 to move to the top of the locking block 13, and then the box beam is placed on the top of the placement plate 3.

[0023] To sum up, the assembled beam storage pier pushes the moving rod 6 to drive the moving ring 9 to stretch the vertical spring 8 through the limit plate 7, so that the installation frame 10 drives the limit block 11 to insert into the bottom of the locking block 13, so that the installation frame 10 pushes the moving wheel 16 to contact the ground through the installation column 15, and the pier can be moved, and then the pushing component pushes the limit block 11 out from the bottom of the locking block 13, and the vertical spring 8 drives the moving rod 6 to reset through the moving ring 9, so that the installation frame 10 drives the moving wheel 16 to separate from the ground through the installation column 15, thereby facilitating the movement of the pier, and the movable pier facilitates the placement of the box beam, avoiding the need to use too much concrete to cast the pier, resulting in a lot of time for the subsequent dismantling of the pier, and different numbers of piers can be placed according to the specifications of the box beam, and the piers can be recycled to solve the problems raised in the above-mentioned background technology.

[0024] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0025] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An assembled beam support pier, comprising a base (1), characterized in that: A pier seat (2) is fixedly provided on the top of the base (1) by means of bolts, a placement plate (3) is fixedly provided on the top of the pier seat (2) by means of bolts, a mounting frame (4) is fixedly provided on the top of the base (1), an elastic component is provided inside the mounting frame (4), a mounting frame (10) is provided inside the mounting frame (4) by means of the elastic component, a locking component is provided inside the mounting frame (10), a pushing component is provided inside the mounting frame (4), a mounting column (15) is fixedly provided on the bottom of the mounting frame (10), and a moving wheel (16) is fixedly provided on the bottom of the mounting column (15).

2. The assembled beam retaining pier according to claim 1, characterized in that: The elastic component comprises a moving hole (5), the moving hole (5) passes through the top of a mounting frame (4), a moving rod (6) is slidably arranged inside the moving hole (5), a limiting plate (7) is fixedly arranged at the top of the moving rod (6), a moving ring (9) is fixedly arranged on the surface of the moving rod (6), a vertical spring (8) is fixedly arranged at the top of the moving ring (9), the top of the vertical spring (8) is fixedly mounted on the upper side wall of the mounting frame (4), and the mounting frame (10) is fixedly mounted on the bottom end of the moving rod (6).

3. The assembled beam-retaining pier according to claim 1, characterized in that: The locking assembly comprises a limit block (11), the limit block (11) is slidably arranged inside the mounting frame (10), the limit block (11) overlaps with the mounting frame (4), a transverse spring (12) is fixedly arranged between the facing surfaces of the limit block (11), a locking block (13) is overlapped at the top of the limit block (11), and the locking block (13) is fixedly mounted on the inner wall of the mounting frame (4).

4. The assembled beam-retaining pier according to claim 1, characterized in that: The pushing assembly comprises a moving plate (17), the moving plate (17) being slidably arranged inside the mounting frame (4), a rectangular baffle (14) being fixedly arranged at the bottom of the moving plate (17), and a placement groove for placing the rectangular baffle (14) being provided inside the mounting frame (4).

5. The assembled beam-retaining pier according to claim 3 is characterized in that: The bottom of the limit block (11) is an inclined surface, the top of the locking block (13) is an inclined surface, and the limit block (11) and the locking block (13) are both made of metal material.

6. The assembled beam-retaining pier according to claim 1, characterized in that: A blocking plate is fixedly arranged inside the mounting frame (4), and the blocking plates are multiple and symmetrically distributed.

7. The assembled beam-retaining pier according to claim 1, characterized in that: The mounting frame (4) is in an inverted U-shaped structure, the mounting frame (4) is made of a metal material, and there are four mounting frames (4) which are symmetrically distributed.