Valve group applied to independent vacuum system

By arranging a variety of solenoid valves on the valve terminal busbar of an independent vacuum system and equipped with a hub and electrical connector, the problems of complex structure and many pipelines in the existing vacuum system are solved, and the effects of simple structure, integrated and space saving are achieved.

CN222772747UActive Publication Date: 2025-04-18HUNAN YIMING INTELLIGENT TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421786273.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2025-04-18
Estimated Expiration
2034-07-26

AI Technical Summary

Technical Problem

The control valves in the existing vacuum system have complex structures, many pipelines and large space, resulting in complex connections and inconvenient management.

Method used

A valve group applied to independent vacuum systems is designed. By arranging sewage solenoid valves, sewage solenoid valves, exhaust solenoid valves, pressurized solenoid valves, intake solenoid valves, and vacuum solenoid valves on the valve island bus plate, and accommodating electrical connectors, hubs, pressure gauges and check valves, the centralized connection and control of the solenoid valve circuit is realized.

Benefits of technology

The structure of the valve group is simplified, the complexity of external pipeline connection is reduced, integration and space saving is achieved, and the control convenience of the system is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222772747U_ABST
    Figure CN222772747U_ABST
Patent Text Reader

Abstract

The utility model is suitable for the technical field of valve banks, and provides a valve bank applied to an independent vacuum system. The sewage suction electromagnetic valve, the sewage discharge electromagnetic valve, the exhaust electromagnetic valve, the pressurization electromagnetic valve, the air inlet electromagnetic valve and the vacuumizing electromagnetic valve are respectively arranged on the valve terminal confluence plate; the pressure gauge is mounted on the valve terminal confluence plate; the electric connector is installed on the valve terminal confluence plate, the dirt suction electromagnetic valve, the dirt discharge electromagnetic valve, the exhaust electromagnetic valve, the pressurization electromagnetic valve, the air inlet electromagnetic valve and the vacuumizing electromagnetic valve are connected to the concentrator in an inserted mode, and the concentrator concentrates circuits to the electric connector; the pressurizing opening and the extraction opening are positioned on one side of the valve terminal confluence plate; the positive pressure port is positioned on the other side of the valve terminal confluence plate; and the check valve is arranged between the pressurizing port and the positive pressure port. The utility model has the advantages of simple structure, integration, space saving and the like, and external complex pipelines are connected and arranged in the valve terminal confluence plate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of valve groups, and in particular relates to a valve group applied to an independent vacuum system. Background Art

[0002] The vacuum system is composed of a vacuum pump, a control system, a gas storage tank, a vacuum pipe, a vacuum valve and other structures. It has a very wide range of applications. For example, in the sewage treatment of the bathroom, vacuum equipment is used to generate a certain degree of vacuum negative pressure in the drainage pipe, and the air pressure difference is used to quickly push the sewage in the vacuum interface unit into the pipe for discharge.

[0003] The control valve is an important structure in the vacuum system. However, since there are many control valves used in the vacuum system and the connections are complicated, it is easy to lead to complex structure, many pipelines and large space occupation. Utility Model Content

[0004] The purpose of the embodiments of the present utility model is to provide a valve group applied to an independent vacuum system, aiming to solve the problems raised in the above-mentioned background technology.

[0005] The utility model is implemented as follows: a valve group applied to an independent vacuum system includes:

[0006] Valve island manifold;

[0007] The sewage suction solenoid valve, sewage discharge solenoid valve, exhaust solenoid valve, pressurization solenoid valve, air intake solenoid valve, and vacuum solenoid valve are respectively installed on the valve island manifold;

[0008] A pressure gauge, installed on the valve island manifold;

[0009] An electrical connector is installed on the valve island manifold, and the sewage suction solenoid valve, sewage discharge solenoid valve, exhaust solenoid valve, pressurization solenoid valve, air intake solenoid valve and vacuum solenoid valve are plugged into the hub, and the hub concentrates the lines on the electrical connector;

[0010] The pressurization port and the air extraction port are located on one side of the valve island manifold. The P ports of the exhaust solenoid valve and the pressurization solenoid valve are connected to the pressurization port, and the P ports of the intake solenoid valve and the vacuum solenoid valve are connected to the air extraction port.

[0011] The positive pressure port is located on the other side of the valve island manifold, and the P port of the sewage suction solenoid valve and the sewage discharge solenoid valve is connected to the positive pressure port;

[0012] The check valve is arranged between the pressurized port and the positive pressure port.

[0013] Preferably, the sewage suction solenoid valve and sewage discharge solenoid valve are direct-acting normally open two-position three-way solenoid valves, and the sewage suction solenoid valve and sewage discharge solenoid valve are connected to the fully open sewage discharge valve.

[0014] Preferably, the exhaust solenoid valve, pressurizing solenoid valve, intake solenoid valve and vacuum solenoid valve are direct-acting two-position two-way solenoid valves, the pressurizing solenoid valve is connected to the pressure port of the transition tank, and the vacuum solenoid valve is connected to the vacuum port of the transition tank.

[0015] Preferably, the pressurizing port is connected to the pressurizing port of the positive and negative pressure pumps, the air extraction port is connected to the negative pressure port of the positive and negative pressure pumps, and the positive pressure port is connected to the pressure tank.

[0016] The utility model provides a valve group for an independent vacuum system to solve the problems in the prior art. From the sewage suction solenoid valve to the vacuum solenoid valve are arranged on the valve island manifold. At the same time, the valve island manifold is also arranged with an electrical connector, a hub, a pressure gauge and a check valve. The line connections of all the solenoid valves are connected to the check valve by plugging. The check valve concentrates all the lines on the electrical connector. The controller can control the action of the solenoid valve by connecting a corresponding multi-core cable. The pipeline connection only needs to connect the control components to the outside. There is no need to take over between the solenoid valves. The connection is completed in the valve island manifold. It has the advantages of simple structure, and the complex external pipeline connections are set in the valve island manifold. It is integrated and saves space. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A schematic diagram of the structure of a valve group applied to an independent vacuum system provided in an embodiment of the utility model;

[0018] Figure 2 A front view of a valve group applied to an independent vacuum system provided by an embodiment of the utility model;

[0019] Figure 3 A connection circuit diagram of a valve group applied to an independent vacuum system provided by an embodiment of the utility model;

[0020] Figure 4 A connection diagram of a valve group applied to an independent vacuum system provided in an embodiment of the utility model.

[0021] In the attached figure: 1-sewage suction solenoid valve; 2-sewage discharge solenoid valve; 3-exhaust solenoid valve; 4-pressurization solenoid valve; 5-intake solenoid valve; 6-vacuum extraction solenoid valve; 7-valve island manifold; 8-pressure gauge; 9-electrical connector; 10-pressurization port; 11-exhaust port; 12-positive pressure port; 13-check valve; 14, hub; 15-pressure tank. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.

[0023] The specific implementation of the present utility model is described in detail below in conjunction with specific embodiments.

[0024] like Figures 1 to 3 FIG. 1 is a structural diagram of a valve group applied to an independent vacuum system provided by an embodiment of the utility model, comprising:

[0025] Valve island manifold 7;

[0026] The sewage suction solenoid valve 1, the sewage discharge solenoid valve 2, the exhaust solenoid valve 3, the pressurization solenoid valve 4, the air intake solenoid valve 5, and the vacuum solenoid valve 6 are respectively installed on the valve island manifold 7;

[0027] A pressure gauge 8 is installed on the valve island manifold 7;

[0028] The electrical connector 9 is installed on the valve island manifold 7. The sewage suction solenoid valve 1, the sewage discharge solenoid valve 2, the exhaust solenoid valve 3, the pressurization solenoid valve 4, the air intake solenoid valve 5 and the vacuum solenoid valve 6 are plugged into the hub 14. The hub 14 concentrates the lines on the electrical connector 9.

[0029] The pressurizing port 10 and the exhaust port 11 are located on one side of the valve island manifold 7, the P ports of the exhaust solenoid valve 3 and the pressurizing solenoid valve 4 are connected to the pressurizing port 10, and the P ports of the intake solenoid valve 5 and the vacuum solenoid valve 6 are connected to the exhaust port 11;

[0030] The positive pressure port 12 is located on the other side of the valve island manifold 7, and the P ports of the sewage suction solenoid valve 1 and the sewage discharge solenoid valve 2 are connected to the positive pressure port 12;

[0031] The check valve 13 is provided between the pressurizing port 10 and the positive pressure port 12 .

[0032] In one embodiment of the utility model, the valve group applied to the independent vacuum system solves the problems in the prior art, and arranges the sewage suction solenoid valve 1 to the vacuum solenoid valve 6 on the valve island manifold 7. At the same time, the valve island manifold 7 is also provided with an electrical connector 9, a hub 14, a pressure gauge 8 and a check valve 13. The line connections of all the solenoid valves are connected to the check valve 13 by plugging. The check valve 13 concentrates all the lines on the electrical connector 9. The controller can control the action of the solenoid valve by connecting a corresponding multi-core cable. The pipeline connection only needs to connect the control components to the outside. There is no need to take over between the solenoid valves. The connection is completed in the valve island manifold 7. It has the advantages of simple structure, setting the external complex pipeline connection into the valve island manifold 7, integration, and space saving.

[0033] like Figure 3 to Figure 4 As shown, as a preferred embodiment of the utility model, the sewage suction solenoid valve 1 and the sewage discharge solenoid valve 2 are direct-acting normally open two-position three-way solenoid valves, and the sewage suction solenoid valve 1 and the sewage discharge solenoid valve 2 are connected to the fully open sewage discharge valve;

[0034] The exhaust solenoid valve 3, the pressurizing solenoid valve 4, the air intake solenoid valve 5 and the vacuum solenoid valve 6 are direct-acting two-position two-way solenoid valves. The pressurizing solenoid valve 4 is connected to the pressure port of the transition tank, and the vacuum solenoid valve 6 is connected to the vacuum port of the transition tank.

[0035] The pressurizing port 10 is connected to the pressurizing ports of the positive and negative pressure pumps, the air extraction port 11 is connected to the negative pressure ports of the positive and negative pressure pumps, and the positive pressure port 12 is connected to the pressure tank 15 .

[0036] The sewage suction solenoid valve 1 and the sewage discharge solenoid valve 2 are direct-acting normally open (PA) two-position three-way solenoid valves, with the R port at the coil port. The exhaust solenoid valve 3, the pressurizing solenoid valve 4, the air intake solenoid valve 5, and the vacuum solenoid valve 6 are direct-acting two-position two-way solenoid valves. When the valve group is used in an independent vacuum system, the action logic is as follows:

[0037] Positive pressure: The system monitors the pressure signal first. If the pressure signal is lower than the set value, the vacuum solenoid valve 6 is opened and the positive and negative pressure pumps pressurize the pressure tank 15. When the pressure signal reaches the set value, the pump is stopped.

[0038] Vacuuming: Check the negative pressure value in the transition tank. If it does not reach the set value, start the positive and negative pressure pumps, open the exhaust solenoid valve 3 and the intake solenoid valve 5, and close them when the pressure reaches the set value; wait for flushing;

[0039] Flushing: Press the flushing button, the sewage suction solenoid valve 1 opens (sewage suction fully opens the sewage discharge valve), and the sewage is pumped to the transition tank; the sewage suction solenoid valve 1 closes, and the pressurization solenoid valve 4 opens to pressurize the transition tank;

[0040] When the pressure is increased to 0.1MPa, the sewage solenoid valve 2 is opened (the sewage discharge valve is fully opened), the sewage solenoid valve 2 is closed with a delay, and the pressurized solenoid valve 4 discharges the sewage to the designated location.

[0041] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A valve group for an independent vacuum system, characterized in that: include: Valve island manifold (7); A sewage suction solenoid valve (1), a sewage discharge solenoid valve (2), an exhaust solenoid valve (3), a pressurizing solenoid valve (4), an air intake solenoid valve (5), and a vacuum solenoid valve (6) are respectively mounted on the valve island manifold (7); A pressure gauge (8) mounted on the valve island manifold (7); An electrical connector (9) is mounted on the valve island manifold (7); a sewage suction solenoid valve (1), a sewage discharge solenoid valve (2), an exhaust solenoid valve (3), a pressurizing solenoid valve (4), an air intake solenoid valve (5) and a vacuum solenoid valve (6) are plugged into a hub (14); and the hub (14) centralizes the lines to the electrical connector (9); The pressurizing port (10) and the exhaust port (11) are located on one side of the valve island manifold (7); the P ports of the exhaust solenoid valve (3) and the pressurizing solenoid valve (4) are in communication with the pressurizing port (10); and the P ports of the intake solenoid valve (5) and the vacuum solenoid valve (6) are in communication with the exhaust port (11); The positive pressure port (12) is located on the other side of the valve island manifold (7), and the P ports of the sewage suction solenoid valve (1) and the sewage discharge solenoid valve (2) are in communication with the positive pressure port (12); The check valve (13) is arranged between the pressurizing port (10) and the positive pressure port (12).

2. The valve group for an independent vacuum system according to claim 1, characterized in that: The sewage suction solenoid valve (1) and the sewage discharge solenoid valve (2) are direct-acting normally open two-position three-way solenoid valves, and the sewage suction solenoid valve (1) and the sewage discharge solenoid valve (2) are connected to a fully open sewage discharge valve.

3. The valve group for independent vacuum system according to claim 1, characterized in that: The exhaust solenoid valve (3), the pressurizing solenoid valve (4), the air intake solenoid valve (5) and the vacuum pumping solenoid valve (6) are direct-acting two-position two-way solenoid valves; the pressurizing solenoid valve (4) is connected to the pressure-injection port of the transition tank, and the vacuum pumping solenoid valve (6) is connected to the vacuum pumping port of the transition tank.

4. The valve group for an independent vacuum system according to claim 1, characterized in that: The pressurizing port (10) is connected to the pressurizing ports of the positive and negative pressure pumps, the air extraction port (11) is connected to the negative pressure ports of the positive and negative pressure pumps, and the positive pressure port (12) is connected to the pressure tank (15).