Full-automatic carton handle mounting equipment

By introducing smoothing mechanisms and pushing mechanisms into the carton handle automatic installation equipment, the problem of untidy carton stacking is solved, fully automatic sorting and alignment is achieved, and production efficiency and product quality are improved.

CN222792930UActive Publication Date: 2025-04-25WUHAN PENGHENG PACKAGING & PRINTING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420525205.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-18
Publication Date
2025-04-25
Estimated Expiration
2034-03-18

AI Technical Summary

Technical Problem

The existing carton handle automatic installation equipment is prone to irregularity when stacking cartons and requires manual alignment, especially in high output conditions.

Method used

A fully automatic carton handle installation equipment is designed, using a smoothing mechanism and a pushing mechanism to smooth the carton through the smoothing mechanism, and the carton is organized and aligned by the pushing mechanism to reduce manual operation.

Benefits of technology

Automatic carton sorting and alignment of cartons is realized, reducing the need for manual operation, and improving production efficiency and product neatness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222792930U_ABST
    Figure CN222792930U_ABST
Patent Text Reader

Abstract

The utility model discloses full-automatic carton handle mounting equipment, and relates to the technical field of mounting equipment. Full-automatic carton handle mounting equipment comprises a machine body, supporting legs are fixed to the four corners of the lower end of the machine body, a first conveying belt is mounted in the machine body, a handle mounting box is fixed to the machine body, a first motor is fixed to the side face of the machine body, and the output end of the first motor extends into the machine body to be in transmission connection with the first conveying belt. A baffle is fixed to the supporting table and corresponds to the first conveying belt, a second conveying belt is installed in the supporting table, a second motor is fixed to the side face of the supporting table, the output end of the second motor extends into the supporting table to be in transmission connection with the second conveying belt, two symmetrically-arranged fixing blocks are fixed to the machine body, and a smoothing mechanism is arranged between the two fixing blocks. A pushing mechanism is arranged between the baffle and the supporting table. And through the pushing mechanism, the cartons can be conveniently arranged and aligned, and the situation of manual alignment operation is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of installation equipment, and in particular to a fully automatic carton handle installation device. Background Art

[0002] The handle installation equipment is an auxiliary device used to install handles on boxes. It has been widely used in the processing fields of cartons, gift boxes, corrugated packaging boxes, etc. Installing handles on boxes facilitates the transportation of cartons.

[0003] An automatic installation device for the handles of a carton gift box mentioned in an existing Chinese public patent (authorization announcement number: CN216708531U) improves the efficiency of installing the handles of the carton board, reduces the labor cost, and reduces the production cost; it includes a supporting mechanism, a conveying mechanism, a driving mechanism, a feeding mechanism and a handle installation mechanism, the handle installation mechanism is installed on the conveying mechanism, the conveying mechanism is installed on the supporting mechanism, the conveying mechanism conveys the carton board for the handle installation mechanism, the driving mechanism is installed on the transmission mechanism, the driving mechanism enables the conveying mechanism to perform intermittent transmission, and the feeding mechanism is installed at the right end of the conveying mechanism for intermittently conveying the carton board for the conveying mechanism; the conveying mechanism includes a conveying frame, a No. 1 roller, a No. 2 roller, a conveyor belt, a guide plate and a guide wheel, the No. 1 roller and the No. 2 roller are both rotatably installed on the conveying frame, the No. 1 roller and the No. 2 roller are driven by the conveyor belt, and the handle installation mechanism is installed on the top of the conveying frame.

[0004] When the equipment is installed for use, handles are installed on the cartons to facilitate the lifting and transportation of the cartons. The cartons with handles installed are transported to the next process via a conveyor belt. When transported to the destination, the cartons are stacked together due to the height difference and the speed of the conveyor belt. When stacking, the cartons are easily made uneven and need to be manually aligned. However, the overall output of cartons is large, and manual alignment is inconvenient. Utility Model Content

[0005] The purpose of the present application is to solve the problem of inconvenience in manual alignment of carton stacking, and to provide a fully automatic carton handle installation device.

[0006] In order to achieve the above-mentioned purpose, this application specifically adopts the following technical solutions:

[0007] A fully automatic carton handle installation device comprises a body, support legs are fixed at the four corners of the lower end of the body, a conveyor belt 1 is installed in the body, a handle installation box is fixed on the body, a motor 1 is fixed on the side of the body, the output end of the motor 1 extends into the body and is connected to the conveyor belt transmission, a support platform is provided at one end of the body, a baffle is fixed on the support platform, the baffle corresponds to the conveyor belt 1, a conveyor belt 2 is installed in the support platform, a motor 2 is fixed on the side of the support platform, the output end of the motor 2 extends into the support platform and is connected to the conveyor belt 2 transmission, two symmetrically arranged fixed blocks are fixed on the body, a smoothing mechanism is provided between the two fixed blocks, and a pushing mechanism is provided between the baffle and the support platform.

[0008] By adopting the above technical solution, the cartons are smoothed by the smoothing mechanism, and the cartons are easily arranged and aligned by the pushing mechanism, thereby reducing the need for manual alignment operations.

[0009] Furthermore, the pushing mechanism includes a second cylinder fixed on the side of the baffle, a fixing rod is fixed on the telescopic end of the second cylinder, a cylinder one is fixed on the fixing rod, a push plate is fixed on the telescopic end of the cylinder one, and a limiting component is arranged between the fixing rod and the baffle.

[0010] By adopting the above technical solution, the cylinder is started to drive the push plate to move and push the carton, and the pushed carton is aligned with the support plate, and the cartons are aligned and sorted. When the cartons are stacked to the specified position, the second cylinder is started to drive the fixed rod to rise, thereby reducing the need for manual alignment.

[0011] Furthermore, the limiting assembly includes a guide column slidably arranged at one end of the fixed rod away from the second cylinder, the guide column is fixedly connected to the support platform, a support plate is fixed to the side of the baffle, and the lower end of the support plate is rotatably connected to a rotating column and contacts with the second conveyor belt.

[0012] By adopting the above technical solution, the fixing rod slides on the guide column to limit and guide the fixing rod, and the support column assists in the alignment of the carton, thereby reducing the need for manual alignment.

[0013] Furthermore, the smoothing mechanism includes a fixed plate arranged on a fixed block, two symmetrical fixed columns are slidably arranged on the fixed plate, a limiting block is fixed to the upper end of the fixed column, a spring is sleeved on the fixed column, the spring is fixedly connected to the limiting block and the fixed plate, the lower end of the fixed column passes through the fixed plate and is rotatably connected to a smoothing column, and a cleaning assembly is arranged between the fixed block and the smoothing column.

[0014] By adopting the above technical solution, the elastic force of the spring causes the fixed column to be stressed, so that the smoothing column exerts force on the carton to rotate, thereby smoothing the carton and reducing wrinkles.

[0015] Furthermore, the cleaning assembly includes a cleaning plate arranged between two fixed blocks, the cleaning plate is fixedly connected to the fixed blocks, and a cleaning brush is fixed to the lower end of the cleaning plate.

[0016] By adopting the above technical solution, the cleaning brush cleans the surface of the carton to reduce the residue of debris.

[0017] Furthermore, a screw rod is threadedly connected to the fixing plate, the screw rod passes through the fixing plate and is rotatably connected to the fixing block, and a handle is fixed to the upper end of the screw rod.

[0018] By adopting the above technical solution, the screw drives the fixed plate to move so as to adapt to the smoothing of cardboards with different thicknesses.

[0019] Furthermore, a limiting column is slidably arranged on the fixing plate away from one end of the screw rod, and the limiting column is fixedly connected to the fixing block.

[0020] By adopting the above technical solution, the smoothing column is away from the conveyor belt, and at the same time the fixed plate slides on the limiting column to limit the fixed plate to adapt to the smoothing of cardboards with different thicknesses.

[0021] Furthermore, two symmetrical fixing frames are arranged on the side of the cleaning plate, the fixing frames are fixedly connected to the machine body, rolling columns are rotatably connected inside the fixing frames and are distributed in an array, and the rolling columns are in contact with the conveyor belt.

[0022] By adopting the above technical solution, the rolling columns on one or two sides of the conveyor belt limit and guide the carton.

[0023] In summary, the present application includes at least one of the following beneficial effects:

[0024] 1. Start the cylinder to drive the push plate to move and push the carton. The pushed carton is aligned with the support plate and the carton is sorted. When the carton is stacked to the specified position, start the second cylinder to drive the fixed rod to rise, so that the cylinder one and the push plate are away from the conveyor belt two. When moving, the fixed rod slides on the guide column to limit and guide the fixed rod, reducing the situation of manual alignment and facilitating the sorting and alignment of the cartons.

[0025] 2. When the equipment is installed and used, the carton contacts the smoothing column, causing the smoothing column to rotate and drive the fixed column to move. The elastic force of the spring causes the fixed column to be stressed, causing the smoothing column to apply force to the carton to rotate, thereby smoothing the carton and reducing wrinkles. When passing through the cleaning plate, the cleaning brush cleans the surface of the carton to reduce dust and debris left behind. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the first three-dimensional structure of the installation equipment in this application.

[0027] Figure 2It is a schematic diagram of the second three-dimensional structure of the installation equipment in this application.

[0028] Figure 3 This application Figure 2 Enlarged view of point A in the middle.

[0029] Figure 4 It is a schematic diagram of the third three-dimensional structure of the installation equipment in this application.

[0030] Description of reference numerals:

[0031] 1. Machine body; 2. Support legs; 3. Conveyor belt 1; 4. Motor 1; 5. Support platform; 6. Motor 2; 7. Conveyor belt 2; 8. Baffle; 9. Support plate; 10. Rotating column; 11. Cylinder 1; 12. Push plate; 13. Cylinder 2; 14. Fixed rod; 15. Guide column; 16. Fixed plate; 17. Fixed column; 18. Limiting block; 19. Spring; 20. Screw; 21. Fixed block; 22. Smoothing column; 23. Cleaning plate; 24. Cleaning brush; 25. Fixed frame; 26. Rolling column; 27. Limiting column. DETAILED DESCRIPTION

[0032] The following is combined with Figure 1-Figure 4 This application is described in further detail.

[0033] The embodiment of the present application discloses a fully automatic carton handle installation device.

[0034] Reference Figure 1 A fully automatic carton handle installation device comprises a body 1, support legs 2 are fixed at the four corners of the lower end of the body 1, a conveyor belt 3 is installed in the body 1, a handle installation box is fixed on the body 1, a motor 4 is fixed on the side of the body 1, the output end of the motor 4 extends into the body 1 and is connected to the conveyor belt 3 for transmission, a support platform 5 is arranged at one end of the body 1, a baffle 8 is fixed on the support platform 5, the baffle 8 corresponds to the conveyor belt 3, a conveyor belt 2 7 is installed in the support platform 5, a motor 2 6 is fixed on the side of the support platform 5, the output end of the motor 26 extends into the support platform 5 and is connected to the conveyor belt 2 7 for transmission, two symmetrically arranged fixed blocks 21 are fixed on the body 1, a smoothing mechanism is arranged between the two fixed blocks 21, and a pushing mechanism is arranged between the baffle 8 and the support platform 5.

[0035] When the installation equipment is used, the motor 14 is turned on to drive the conveyor belt 13 to rotate. The conveyor belt 13 transports the cartons that need to be installed with handles, and then the cartons are smoothed by the smoothing mechanism to remove the debris on the surface. The handle installation box is a prior art. The handle is installed on the cartons through the handle installation box. The cartons are transported from the conveyor belt 13 to the conveyor belt 27. During the process, the baffle 8 restricts the cartons. Then, the pushing mechanism is used to sort the cartons. The sorted cartons are transported through the conveyor belt 27. The pushing mechanism facilitates the sorting and alignment of the cartons, reducing the situation of manual alignment.

[0036] Reference Figure 2 and Figure 4 The pushing mechanism includes a cylinder 2 13 fixed to the side of the baffle 8, a fixed rod 14 is fixed to the telescopic end of the cylinder 2 13, a cylinder 11 is fixed to the fixed rod 14, a push plate 12 is fixed to the telescopic end of the cylinder 11, after the push plate 12 moves downward, its lower end contacts the conveyor belt 2 7, and a limiting component is arranged between the fixed rod 14 and the baffle 8. The limiting component includes a guide column 15 slidably arranged at the end of the fixed rod 14 away from the cylinder 2 13, the guide column 15 is fixedly connected to the support platform 5, a support plate 9 is fixed to the side of the baffle 8, and the lower end of the support plate 9 is rotatably connected to the rotating column 10 and contacts the conveyor belt 2 7.

[0037] When the equipment is installed and used, when the carton transported by the conveyor belt 13 falls on the conveyor belt 27, the cylinder is started to drive the push plate 12 to move and push the carton, and the pushed carton is aligned with the support plate 9. When the carton is stacked to the specified position, the cylinder 213 is started to drive the fixed rod 14 to rise, so that the cylinder 11 and the push plate 12 are away from the conveyor belt 27. When moving, the fixed rod 14 slides on the guide column 15 to limit and guide the fixed rod 14, and the motor 26 is started to drive the conveyor belt 27 to rotate, and the cardboard is transported to the specified position. When the conveyor belt 27 is transported, the rotating column 10 is driven to rotate, and the rotating column 10 is used to block the gap between the support plate 9 and the conveyor belt 27. After the transportation is completed, the motor 26 is turned off, the cylinder 213 drives the cylinder 11 to move, so that the push plate 12 contacts the conveyor belt 27, and the cylinder 11 is started to continue to sort the carton, reducing the situation of manual operation alignment, and facilitating the sorting and alignment of the carton.

[0038] Reference Figure 2 and Figure 3The smoothing mechanism includes a fixed plate 16 arranged on a fixed block 21, two symmetrical fixed columns 17 are slidably arranged on the fixed plate 16, a limiting block 18 is fixed to the upper end of the fixed column 17, a spring 19 is sleeved on the fixed column 17, the spring 19 is fixedly connected to the limiting block 18 and the fixed plate 16, the lower end of the fixed column 17 passes through the fixed plate 16 and is rotatably connected to a smoothing column 22, and a cleaning component is arranged between the fixed block 21 and the smoothing column 22. The cleaning component includes a cleaning plate 23 arranged between the two fixed blocks 21, the cleaning plate 23 is fixedly connected to the fixed block 21, and a cleaning brush 24 is fixed to the lower end of the cleaning plate 23. A screw 20 is threadedly connected to the fixed plate 16, the screw 20 passes through the fixed plate 16 and is rotatably connected to the fixed block 21, and a handle is fixed to the upper end of the screw 20. A limiting column 27 is slidably arranged at one end of the fixed plate 16 away from the screw 20, and the limiting column 27 is fixedly connected to the fixed block 21.

[0039] When the equipment is installed and used, when the carton moves on the conveyor belt 3, the carton contacts the smoothing column 22, causing the smoothing column 22 to rotate, driving the fixed column 17 to move, and the elastic force of the spring 19 causes the fixed column 17 to be stressed, so that the smoothing column 22 applies force to the carton to rotate, smoothes the carton, and reduces wrinkles. When passing through the cleaning plate 23, the cleaning brush 24 cleans the surface of the carton to reduce the residue of dust and debris. When it is necessary to adjust the distance between the smoothing column 22 and the conveyor belt 3, the screw 20 can be turned, and the screw 20 drives the fixed plate 16 to move. When the fixed plate 16 moves, it drives the fixed column 17 to move, so that the smoothing column 22 is away from the conveyor belt 3. At the same time, the fixed plate 16 slides on the limiting column 27 to limit the fixed plate 16 to adapt to the smoothing of cardboards of different thicknesses.

[0040] Reference Figure 1 Two symmetrical fixing frames 25 are arranged on the side of the cleaning plate 23, and the fixing frames 25 are fixedly connected to the machine body 1. Rolling columns 26 are rotatably connected in the fixing frames 25 and are distributed in an array, and the rolling columns 26 are in contact with the conveyor belt 27.

[0041] When the carton moves on the conveyor belt 3, the rolling posts 26 on both sides of the conveyor belt 3 restrict and guide the carton.

[0042] The implementation principle of the fully automatic carton handle installation device of this embodiment is as follows: when the installation device is used, the motor 4 is turned on to drive the conveyor belt 3 to rotate, and the conveyor belt 3 transports the cartons that need to be installed with handles. When the cartons move on the conveyor belt 3, the cartons contact the smoothing column 22, so that the smoothing column 22 rotates, driving the fixed column 17 to move. The elastic force of the spring 19 causes the fixed column 17 to be stressed, so that the smoothing column 22 applies force to the carton to rotate, smoothes the carton, reduces wrinkles, and passes through When cleaning the plate 23, the cleaning brush 24 cleans the surface of the carton to reduce the debris left. When the distance between the smoothing column 22 and the conveyor belt 3 needs to be adjusted, the screw 20 can be turned, and the screw 20 drives the fixed plate 16 to move. When the fixed plate 16 moves, it drives the fixed column 17 to move, so that the smoothing column 22 is away from the conveyor belt 3. At the same time, the fixed plate 16 slides on the limiting column 27 to limit the fixed plate 16. During transportation, the rolling columns 26 on both sides of the conveyor belt 3 limit and guide the carton;

[0043] When the box is installed by the handle, the handle is installed on the carton, and the carton is transported from conveyor belt 13 to conveyor belt 2 7. During the process, the carton is restricted by baffle 8. When the carton transported by conveyor belt 13 falls on conveyor belt 2 7, the cylinder is started to drive the push plate 12 to move and push the carton. The pushed carton is aligned with the support plate 9 and the carton is sorted. When the carton is stacked to the specified position, the cylinder 2 13 is started to drive the fixed rod 14 to rise, so that the cylinder 11 and the push plate 12 are away from the conveyor belt 2 7. During the movement, the fixed rod 14 slides on the guide column 15 to restrict and guide the fixed rod 14, and the motor 2 6 is started to drive the conveyor belt 2 7 to rotate, and the cardboard is transported to the specified position. After the transportation is completed, the motor 2 6 is turned off, and the cylinder 2 13 drives the cylinder 11 to move, so that the push plate 12 contacts the conveyor belt 2 7, and the cylinder 11 is started to continue to sort the carton. After the end, the equipment is turned off.

Claims

1. A fully automatic carton handle installation device, comprising a body (1), characterized in that: Support legs (2) are fixed at the four corners of the lower end of the body (1), a conveyor belt (3) is installed in the body (1), a handle installation box is fixed on the body (1), a motor (4) is fixed on the side of the body (1), the output end of the motor (4) extends into the body (1) and is connected to the conveyor belt for transmission, a support platform (5) is provided at one end of the body (1), a baffle (8) is fixed on the support platform (5), the baffle (8) corresponds to the conveyor belt (3), a conveyor belt (7) is installed in the support platform (5), a motor (6) is fixed on the side of the support platform (5), the output end of the motor (6) extends into the support platform (5) and is connected to the conveyor belt (7) for transmission, two symmetrically arranged fixed blocks (21) are fixed on the body (1), a smoothing mechanism is provided between the two fixed blocks (21), and a pushing mechanism is provided between the baffle (8) and the support platform (5).

2. The fully automatic carton handle installation device according to claim 1, characterized in that: The pushing mechanism comprises a second cylinder (13) fixed to the side of the baffle (8); a fixing rod (14) is fixed to the telescopic end of the second cylinder (13); a first cylinder (11) is fixed to the fixing rod (14); a push plate (12) is fixed to the telescopic end of the first cylinder (11); and a limiting component is provided between the fixing rod (14) and the baffle (8).

3. The fully automatic carton handle installation device according to claim 2, characterized in that: The limiting assembly comprises a guide column (15) slidably arranged at one end of the fixed rod (14) away from the second cylinder (13), the guide column (15) being fixedly connected to the support platform (5), a support plate (9) being fixedly arranged on the side of the baffle (8), and a rotating column (10) being rotatably connected at the lower end of the support plate (9) and being in contact with the second conveyor belt (7).

4. The fully automatic carton handle installation device according to claim 3 is characterized by: The smoothing mechanism comprises a fixed plate (16) arranged on a fixed block (21), two symmetrical fixed columns (17) are slidably arranged on the fixed plate (16), a limiting block (18) is fixed to the upper end of the fixed column (17), a spring (19) is sleeved on the fixed column (17), the spring (19) is fixedly connected to the limiting block (18) and the fixed plate (16), the lower end of the fixed column (17) passes through the fixed plate (16) and is rotatably connected to a smoothing column (22), and a cleaning component is arranged between the fixed block (21) and the smoothing column (22).

5. The fully automatic carton handle installation device according to claim 4, characterized in that: The cleaning assembly comprises a cleaning plate (23) arranged between two fixed blocks (21), the cleaning plate (23) being fixedly connected to the fixed blocks (21), and a cleaning brush (24) being fixed at the lower end of the cleaning plate (23).

6. The fully automatic carton handle installation device according to claim 4, characterized in that: A screw rod (20) is threadedly connected to the fixing plate (16), the screw rod (20) passes through the fixing plate (16) and is rotatably connected to the fixing block (21), and a handle is fixed to the upper end of the screw rod (20).

7. The fully automatic carton handle installation device according to claim 6, characterized in that: A limiting column (27) is slidably disposed at one end of the fixing plate (16) away from the screw rod (20), and the limiting column (27) is fixedly connected to the fixing block (21).

8. The fully automatic carton handle installation device according to claim 5, characterized in that: Two symmetrical fixing frames (25) are arranged on the side of the cleaning plate (23); the fixing frames (25) are fixedly connected to the machine body (1); and rolling columns (26) are rotatably connected inside the fixing frames (25) and are distributed in an array.

Citation Information

Patent Citations

  • Automatic mounting equipment for carton gift box handles

    CN216708531U