Iron tower foundation bolt elevation adjusting device

By designing a anchor bolt elevation adjustment device for tower installation, the problem of difficulty in controlling the anchor bolt elevation is solved, and fast and accurate elevation adjustment is achieved, ensuring the quality and construction efficiency of tower installation.

CN222835396UActive Publication Date: 2025-05-06中国电建集团贵州工程有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421779129.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2025-05-06
Estimated Expiration
2034-07-25

AI Technical Summary

Technical Problem

During the installation of the tower, the elevation of anchor bolts is not easy to control, it is not stable enough when pre-embedded in the early stage, and it remains unchanged when pre-embedded in the late stage, which is easy to destroy the spacing and relative size of the group anchor bolts during the knocking process, resulting in inconsistent elevation during the later stage.

Method used

A tower anchor bolt elevation adjustment device is designed, including a leveling steel plate, an upper support part, a lower support part, an upper adjustment support arm and a lower adjustment support arm. By adjusting components (such as threaded columns and connecting blocks), the leveling steel plate is moved up and down, and the elevation of the anchor bolt is adjusted.

Benefits of technology

The rapid adjustment of anchor bolt elevation is achieved, the quality of tower installation is ensured, and construction waste and construction period delays are avoided due to inconsistent elevation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222835396U_ABST
    Figure CN222835396U_ABST
Patent Text Reader

Abstract

The iron tower foundation bolt elevation adjusting device comprises a leveling steel plate, a plurality of upper supporting parts, a plurality of lower supporting parts, an upper adjusting supporting arm and a lower adjusting supporting arm, the leveling steel plate is provided with a plurality of through holes, the upper supporting parts are symmetrically connected to the two sides of the bottom of the leveling steel plate, and the lower supporting parts are symmetrically connected to the two sides of the bottom of the leveling steel plate. The lower supporting parts are connected to the ground and vertically correspond to the upper supporting parts respectively, the upper adjusting supporting arms are connected with the upper supporting parts in pairs, the lower adjusting supporting arms are connected with the lower supporting parts in pairs, and an adjusting assembly for controlling the leveling steel plate to ascend and descend is connected between the upper adjusting supporting arms and the lower adjusting supporting arms in one group.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building engineering construction, in particular to a device for adjusting the elevation of an iron tower foundation bolt. Background Art

[0002] New energy projects have been the general trend in recent years and are part of the green energy construction encouraged by the state. In new energy power generation construction projects, various power generation units will gather their own electricity and transmit it to the substation, or the substation will send it to the power grid after the electricity is gathered. From an economic perspective, this is inseparable from the construction of towers. The number of towers is also doubling. How to ensure the quality of tower installation requires starting from the basics.

[0003] During the installation of the tower, it was found that the height of the anchor bolts was not easy to control and the exposed length could not be uniform. In addition, during the construction process, when the concrete was poured to the ground, the anchor bolts were installed. At this time, the anchor bolts were covered with a pile casing template for slow-setting soil pouring. Due to the slump and initial setting characteristics of the concrete, the anchor bolts were not stable enough during the early pre-embedded installation, and they were not adjusted during the late pre-embedded installation. It was easy to damage the spacing and relative size of the grouped anchor bolts during the hammering process, resulting in inconsistent heights during the later installation of the tower, which greatly wasted the construction period and occupied human resources, becoming an important factor restricting the construction period. Utility Model Content

[0004] The utility model is intended to provide a tower anchor bolt elevation adjustment device to solve the problem that the anchor bolts are not stable enough during early pre-embedded installation, and are not adjusted during late pre-embedded installation, and the spacing and relative size of the grouped anchor bolts are easily destroyed during the hammering process.

[0005] In order to solve the above technical problems, the utility model provides the following technical solutions: a tower anchor bolt elevation adjustment device, comprising a leveling steel plate, multiple upper support parts, a lower support part, an upper adjustment support arm and a lower adjustment support arm, the leveling steel plate is provided with multiple through holes, the multiple upper support parts are symmetrically connected to the two sides of the bottom of the leveling steel plate, the multiple lower support parts are connected to the ground and vertically correspond to the multiple upper support parts respectively, the multiple upper adjustment support arms are connected to the upper support parts in groups of two, the multiple lower adjustment support arms are connected to the lower support parts in groups of two, and an adjustment component for controlling the up and down lifting of the leveling steel plate is connected between a group of upper adjustment support arms and the lower adjustment support arms.

[0006] The working principle of the utility model: when in use, align the through hole on the leveling steel plate with the anchor bolt, place the lower support part horizontally on the ground, fix the exposed length of the anchor bolt by two layers of nuts to prevent loosening when vibrating the concrete, adjust the adjustment component to make multiple upper adjustment support arms and lower adjustment support arms change, drive the leveling steel plate to move up and down to adjust the upper and lower elevations, and after the adjustment is completed, pour concrete and vibrate. The concrete passes through the through hole on the leveling steel plate and enters the pile casing template. When the base top elevation is reached, the adjustment component is controlled to adjust the anchor bolt elevation to the final state and lock it. When the concrete is initially solidified, the double-layer nuts can be removed and the device can be removed for final maintenance.

[0007] The beneficial effects of the utility model are as follows: 1. The structure is simple, the finished product device is easy to manufacture and portable; 2. It can be directly dismantled in a short time after use, which does not affect the quality of the finished product and can continue to be used; 3. By using this device, the elevation of the anchor bolts can be quickly adjusted to ensure quality.

[0008] Furthermore, the adjustment assembly includes a threaded column and a plurality of connection blocks, wherein the connection blocks are connected between an upper adjustment support arm and a lower adjustment support arm, the plurality of connection blocks are located on the same horizontal line, the threaded column is connected between the plurality of connection blocks and the threaded column passes through the connection blocks. By setting the threaded column, the upper adjustment support arm and the lower adjustment support arm can be driven to change their displacement by rotating the threaded column, thereby driving the adjustment steel plate to move up and down.

[0009] Furthermore, one end of the threaded column is connected with a screwing ring. The threaded column can be screwed more easily by the provision of the screwing ring.

[0010] Furthermore, the leveling steel plate is of a "U" shape, and through holes are provided on opposite sides of the leveling steel plate, and the upper support portion is located on the opposite side of the leveling steel plate away from the through holes. By limiting the shape of the leveling steel plate, the concrete pouring can start from the center of the hole pile casing template, making the concrete pouring more uniform.

[0011] Furthermore, the upper support portion and the lower support portion are double-pin couplings.

[0012] Furthermore, the length of the leveling steel plate is longer than the diameter of the pile casing template. By setting the leveling steel plate longer than the diameter of the pile casing template, the pile casing template will not be touched during the disassembly process of the device, which will affect the final curing process of the concrete. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 This is a front view of a device for adjusting the height of an iron tower anchor bolt according to the utility model;

[0014] Figure 2 for Figure 1 Left view of

[0015] Figure 3for Figure 1 Top view of the . DETAILED DESCRIPTION

[0016] The following is further described in detail through specific implementation methods:

[0017] The reference numerals in the drawings of the specification include: anchor bolt 1, double-layer nut 2, leveling steel plate 3, pile casing template 4, upper support part 5, upper adjustment support arm 6, lower adjustment support arm 7, screw ring 8, threaded column 9, lower support part 10.

[0018] The embodiment is basically as shown in the attached Figure 1 -Attached Figure 3 As shown: a device for adjusting the height of an iron tower foundation bolt 1, comprising a leveling steel plate 3, two upper support parts 5, two lower support parts 10, four upper adjustment support arms 6 and a lower adjustment support arm 7, the leveling steel plate 3 is a "return" type, the length of the leveling steel plate 3 is longer than the diameter of the pile casing template 4, the left and right sides of the leveling steel plate 3 are stacked with four through holes, the diameter of the foundation bolt 1 is smaller than the through hole, the foundation bolt 1 is threadedly connected with a double-layer nut 2, the diameter of the double-layer nut 2 is larger than the through hole, the two upper support parts 5 are fixedly connected to the bottom of the leveling steel plate 3, the two upper support parts 5 is located at the upper and lower sides of the leveling steel plate 3, the two lower support parts 10 are slidably connected to the ground and vertically correspond to the two upper support parts 5 respectively, the four upper adjustment support arms 6 are rotatably connected to the upper support parts 5 in groups of two, and the four lower adjustment support arms 7 are rotatably connected to the lower support parts 10 in groups of two. A connection block is rotatably connected to the bottom of an upper adjustment support arm 6, and the connection block is rotatably connected to the corresponding lower adjustment support arm 7. The connection block is provided with a horizontally penetrating spiral hole, and a threaded column 9 is threadedly connected between the two horizontal connection blocks, and a screw ring 8 is fixedly connected to the right end of the threaded column 9.

[0019] The upper support part 5 and the lower support part 10 are double-pin couplings.

[0020] The specific implementation process is as follows: when in use, align the through hole on the leveling steel plate 3 with the anchor bolt 1, place the double-pin coupling below horizontally on the ground, fix the exposed length of the anchor bolt 1 by two layers of nuts to prevent loosening during vibrating the concrete, turn the screw ring 8 to change the upper and lower adjustment support arms 6 and 7, and drive the leveling steel plate 3 to move up and down to adjust the upper and lower elevations. After the adjustment, pour the concrete and vibrate. The concrete passes through the center position on the leveling steel plate 3 and enters the pile casing template 4. When it reaches the base top elevation, turn the screw ring 8 again, adjust the anchor bolt 1 elevation to the final state and then lock it. When the concrete is initially set, the double-layer nut 2 can be removed and the device can be removed for final maintenance.

[0021] The above is only an embodiment of the utility model, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the utility model, which should also be regarded as the protection scope of the utility model, and these will not affect the effect of the implementation of the utility model and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. A device for adjusting the height of an iron tower anchor bolt, characterized in that: It includes a leveling steel plate, multiple upper support parts, a lower support part, an upper adjustment support arm and a lower adjustment support arm. The leveling steel plate is provided with multiple through holes. The multiple upper support parts are symmetrically connected to both sides of the bottom of the leveling steel plate. The multiple lower support parts are connected to the ground and vertically correspond to the multiple upper support parts respectively. The multiple upper adjustment support arms are connected to the upper support parts in groups of two, and the multiple lower adjustment support arms are connected to the lower support parts in groups of two. An adjustment component for controlling the up and down lifting of the leveling steel plate is connected between a group of upper adjustment support arms and lower adjustment support arms.

2. The device for adjusting the height of an iron tower anchor bolt according to claim 1, characterized in that: The adjustment assembly includes a threaded column and multiple connecting blocks, wherein the connecting blocks are connected between an upper adjustment support arm and a lower adjustment support arm, the multiple connecting blocks are located on the same horizontal line, the threaded column is connected between the multiple connecting blocks and the threaded column passes through the connecting blocks.

3. The device for adjusting the height of an iron tower anchor bolt according to claim 2, characterized in that: One end of the threaded column is connected with a screw ring.

4. The device for adjusting the height of an iron tower anchor bolt according to claim 3, characterized in that: The leveling steel plate is of a "U" shape, and through holes are provided on opposite sides of the leveling steel plate, and the upper support portion is located on the opposite side of the leveling steel plate away from the through holes.

5. The device for adjusting the height of an iron tower anchor bolt according to claim 4, characterized in that: The upper supporting part and the lower supporting part are double-pin couplings.