Hanging bracket for fabricated building construction
By designing a sliding displacement guardrail and displacement bottom plate, combined with the limit fixing technology of fastening bolts, the existing hanging frame is solved, and efficient construction efficiency and flexible applicability are achieved.
Patent Information
- Application Number
- CN202421605866.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-09
- Publication Date
- 2025-05-16
- Estimated Expiration
- 2034-07-09
AI Technical Summary
The existing hangers for construction of buildings are not easy to disassemble and install, resulting in inefficient utilization of space on the construction site, increasing the congestion at the construction site, and limiting the movement of other equipment or staff. The length of the hanger cannot be adjusted, limiting the construction progress and efficiency.
A prefabricated building construction hanger is designed, which slides inside the installation cavity and slides inside the fixed cavity through two displacement guardrails, so as to achieve convenient installation and disassembly of the hanger. The displacement guardrail plate and displacement base plate are fixed at the limit by the fastening bolts set in the installation hole, ensuring the stability of the hanger and the accuracy of length adjustment.
The construction efficiency is improved and the applicability and flexibility of the hanging frame is enhanced. Construction personnel can quickly adjust the size of the hanging frame according to the needs of the construction site to adapt to different construction scenarios.
Smart Images

Figure CN222879193U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to an assembled building construction hanger. Background Art
[0002] A construction hanging basket is a device that is suspended outside a building and carries workers or building materials for exterior wall construction through a hanging device such as a wire rope or chain. It is widely used in high-rise building construction, such as wall masonry, painting, decoration, cleaning and other operations. The use of a hanging basket greatly improves construction efficiency and safety and reduces the labor intensity of workers.
[0003] However, most of the existing construction hangers on the market are not easy to disassemble and install, which requires a large amount of space on the construction site, and the space utilization is not efficient. When it is necessary to move to the next area after completing a section of construction, this will increase the congestion on the construction site and may restrict the movement of other equipment or workers. The difficult-to-disassemble hanging basket requires more transportation and storage space, which increases transportation costs. In addition, most of the existing construction hanging baskets on the market cannot adjust the length. Fixed-length hanging baskets may limit construction progress and efficiency. Workers may need extra time and labor to adjust the position of the hanging basket, which will affect the overall construction progress.
[0004] Therefore, those skilled in the art provide a prefabricated hanger for building construction to solve the problems raised in the above background technology. Utility Model Content
[0005] The purpose of the utility model is to solve the shortcomings existing in the prior art, and to propose an assembled hanger for building construction, which slides in the installation cavity through two displacement guardrail plates and slides in the fixed cavity through the displacement base plate, thereby facilitating the installation and disassembly of the guardrail plates and the base plate of the hanger, thereby improving the construction efficiency. In addition, the fastening bolts arranged in the installation holes penetrate the installation holes at different positions on the displacement guardrail plates and the displacement base plate, so as to facilitate the limited fixation of the displacement guardrail plates and the displacement base plate, which not only ensures the stability of the hanger during use, but also makes the length adjustment of the hanger precise and simple, further enhancing the applicability and flexibility of the hanger, and the construction personnel can also quickly adjust the size of the hanger according to the specific needs of the construction site to adapt to the needs of different construction scenes.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] An assembled construction hanger comprises two bottom plates and two displacement guardrail plates, two guardrail plates are fixedly connected to both sides of the upper surface of the bottom plates, columns are fixedly connected to the outer walls of the rear ends of the guardrail plates, sliding cavities are provided on the outer walls of the adjacent sides of the two columns, and clamping blocks are slidably connected to the inside of the sliding cavities, and partition plates are fixedly connected to the outer walls of the adjacent sides of the two clamping blocks;
[0008] The front ends of the outer walls on both sides of the bottom plate are provided with second mounting holes, the middle part of the outer wall at the front end of the bottom plate is provided with a fixing cavity, the interior of the fixing cavity is slidably connected with a displacement bottom plate, the middle parts of the outer walls on both sides of the displacement bottom plate are provided with a plurality of fourth mounting holes, the middle part of the outer wall at the front end of the guardrail plate is provided with a mounting cavity, the interior of the mounting cavity is slidably connected with a displacement guardrail plate, the upper and lower ends of the outer walls on both sides of the displacement guardrail plate are provided with a plurality of fifth mounting holes, and the upper and lower ends of the outer walls on both sides of the guardrail plate close to the displacement guardrail plate are provided with third mounting holes;
[0009] Through the above technical solution, the hanger drives the partition to slide in the sliding cavity by pulling the handle, which is convenient for adjusting the height of the partition, thereby making the installation and disassembly of the partition more convenient. In addition, through the fastening bolts arranged in the first mounting hole and the sixth mounting hole, the partition can be fixed at different heights, thereby facilitating the cleaning and tidying up of the internal space of the hanger.
[0010] Furthermore, both sides of the lower surface of the bottom plate away from the displacement bottom plate are fixedly connected with connecting rods, and the lower ends of the connecting rods are fixedly connected with self-locking universal wheels;
[0011] Through the above technical solution, the overall movement of the hanger is facilitated by the self-locking universal wheels.
[0012] Furthermore, the upper surfaces of the columns are fixedly connected with traction rings;
[0013] Through the above technical solution, the hanger can be hung outside the building by the steel cable through the traction ring.
[0014] Furthermore, the inner walls on both sides of the sliding cavity are provided with a plurality of first mounting holes, and the outer walls on both sides of the front end of the partition are provided with a plurality of sixth mounting holes;
[0015] Through the above technical solution, the partition can be easily fixed at different heights through the sixth mounting hole and the first mounting hole, thereby facilitating cleaning of the internal space of the hanger.
[0016] Furthermore, a handle is fixedly connected to the outer wall of the front end of the partition;
[0017] Through the above technical solution, the partition can be easily driven to slide inside the sliding cavity by the handle, thereby facilitating disassembly and installation.
[0018] Furthermore, the second mounting hole and the fourth mounting hole are both provided with fastening bolts inside;
[0019] Through the above technical solution, the displacement base plate can be easily fixed in a limited position by tightening the bolts.
[0020] Furthermore, the first mounting hole and the sixth mounting hole are both provided with fastening bolts inside;
[0021] Through the above technical solution, the partition can be easily fixed in a limited position by tightening the bolts.
[0022] Furthermore, the third mounting hole and the fifth mounting hole are both provided with fastening bolts inside;
[0023] Through the above technical solution, the displacement guardrail plate can be easily fixed in position by tightening the bolts.
[0024] The utility model has the following beneficial effects:
[0025] 1. The utility model proposes an assembled hanger for building construction, which slides inside the installation cavity through two displacement guardrail plates and slides inside the fixed cavity through the displacement bottom plate, thereby facilitating the installation and disassembly of the guardrail plates and the bottom plate of the hanger, thereby improving the construction efficiency. In addition, the fastening bolts arranged in the installation holes penetrate the installation holes at different positions on the displacement guardrail plates and the displacement bottom plate, which facilitates the limited fixation of the displacement guardrail plates and the displacement bottom plate, which not only ensures the stability of the hanger during use, but also makes the length adjustment of the hanger precise and simple, further enhancing the applicability and flexibility of the hanger, and the construction personnel can also quickly adjust the size of the hanger according to the specific needs of the construction site to adapt to the needs of different construction scenes.
[0026] 2. The utility model proposes an assembled type construction hanger, which drives the partition to slide in the sliding cavity by pulling the handle, so as to facilitate the adjustment of the height of the partition, thereby making the installation and disassembly of the partition more convenient. In addition, the fastening bolts arranged in the first mounting hole and the sixth mounting hole facilitate the fixing of the partition at different heights, thereby facilitating the cleaning and tidying up of the internal space of the hanger.
[0027] 3. The utility model proposes an assembled building construction hanger, which has self-locking universal wheels arranged at the lower end of the base plate, thereby improving the mobility of the hanger, so that the hanger can be easily moved between different positions according to construction requirements, thereby improving construction efficiency and flexibility. The self-locking function ensures that the hanger can be firmly positioned after stopping moving, thereby ensuring construction safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is an axonometric diagram of a prefabricated building construction hanger proposed by the utility model;
[0029] Figure 2 This is a structural schematic diagram of a base plate, guardrail plate, and column of an assembled building construction hanger proposed by the utility model;
[0030] Figure 3 This is a structural schematic diagram of a partition plate and a clamping block of an assembled building construction hanger proposed by the utility model;
[0031] Figure 4 This is a structural schematic diagram of a column, a traction ring, and a sliding cavity of an assembled building construction hanger proposed by the utility model;
[0032] Figure 5 This is a structural schematic diagram of a displacement guardrail plate of an assembled building construction hanger proposed by the utility model;
[0033] Figure 6 The utility model is a schematic structural diagram of a displacement base plate of an assembled building construction hanger.
[0034] Legend:
[0035] 1. Base plate; 2. Post; 3. Sliding cavity; 4. Partition; 5. Guardrail plate; 6. Mounting cavity; 7. First mounting hole; 8. Fixed cavity; 9. Displacement base plate; 10. Displacement guardrail plate; 11. Towing ring; 12. Connecting rod; 13. Self-locking universal wheel; 14. Handle; 15. Snap-in block; 16. Second mounting hole; 17. Third mounting hole; 18. Fourth mounting hole; 19. Fifth mounting hole; 20. Sixth mounting hole. DETAILED DESCRIPTION
[0036] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0037] Reference Figure 1-6 , an embodiment provided by the utility model:
[0038] An assembled construction hanger comprises two bottom plates 1 and two displacement guardrail plates 10, two guardrail plates 5 are fixedly connected to both sides of the upper surface of the bottom plate 1, the outer wall of the rear end of the guardrail plate 5 is fixedly connected to the column 2, the outer wall of the adjacent side of the two columns 2 is provided with a sliding cavity 3, the inside of the sliding cavity 3 is slidably connected to a clamping block 15, and the outer wall of the adjacent side of the two clamping blocks 15 is fixedly connected to the partition plate 4;
[0039] A second mounting hole 16 is provided at the front end of the outer wall on both sides of the base plate 1, a fixed cavity 8 is provided in the middle of the outer wall at the front end of the base plate 1, a displacement base plate 9 is slidably connected inside the fixed cavity 8, a plurality of fourth mounting holes 18 are provided in the middle of the outer walls on both sides of the displacement base plate 9, a mounting cavity 6 is provided in the middle of the outer wall at the front end of the guardrail plate 5, a displacement guardrail plate 10 is slidably connected inside the mounting cavity 6, a plurality of fifth mounting holes 19 are provided at the upper and lower ends of the outer walls on both sides of the displacement guardrail plate 10, and a third mounting hole 17 is provided at the upper and lower ends of the outer walls on both sides of the guardrail plate 5 close to the displacement guardrail plate 10.
[0040] The hanger slides inside the installation cavity 6 through two displacement guardrail plates 10 and slides inside the fixed cavity 8 through the displacement base plate 9, thereby facilitating the installation and disassembly of the guardrail plates 5 and the base plate 1 of the hanger, thereby improving the construction efficiency. In addition, the fastening bolts arranged in the installation holes penetrate the installation holes at different positions on the displacement guardrail plates 10 and the displacement base plate 9, so as to facilitate the limited fixation of the displacement guardrail plates 10 and the displacement base plate 9, which not only ensures the stability of the hanger during use, but also makes the length adjustment of the hanger precise and simple, further enhancing the applicability and flexibility of the hanger, and the construction personnel can also quickly adjust the size of the hanger according to the specific needs of the construction site to adapt to the needs of different construction scenes.
[0041] The lower surface of the bottom plate 1 is fixedly connected to both sides of the displacement bottom plate 9, and the lower ends of the connecting rods 12 are fixedly connected to self-locking universal wheels 13, which facilitate the movement of the hanger as a whole. The upper surfaces of the columns 2 are fixedly connected to traction rings 11, which facilitate the steel cable to hang the hanger outside the building. The inner walls on both sides of the sliding cavity 3 are provided with a plurality of first mounting holes 7, and the outer walls on both sides of the front end of the partition 4 are provided with a plurality of sixth mounting holes 20. The sixth mounting holes 20 and the first mounting holes 7 are convenient for fixing the partition 4 at different heights, thereby facilitating the cleaning of the internal space of the hanger. The outer wall of the front end of the partition 4 is fixedly connected There is a handle 14, through which the partition 4 can be driven to slide inside the sliding cavity 3, which is convenient for disassembly and installation. The second mounting hole 16 and the fourth mounting hole 18 are both provided with fastening bolts, through which the displacement base plate 9 can be limited and fixed, which is convenient for overall stability. The first mounting hole 7 and the sixth mounting hole 20 are both provided with fastening bolts, through which the partition 4 can be limited and fixed, which is convenient for overall stability and firmness. The third mounting hole 17 and the fifth mounting hole 19 are both provided with fastening bolts, through which the displacement guardrail plate 10 can be limited and fixed, which is convenient for overall stability and firmness.
[0042] Working principle: When using the assembled building construction hanger, first, the hanger slides inside the installation cavity 6 through two displacement guardrail plates 10, and slides inside the fixed cavity 8 through the displacement bottom plate 9, so as to facilitate the installation and disassembly of the guardrail plates 5 and the bottom plate 1 of the hanger, thereby improving the construction efficiency. In addition, the fastening bolts set in the installation holes penetrate the installation holes at different positions on the displacement guardrail plates 10 and the displacement bottom plate 9, so as to facilitate the displacement guardrail plates 10 and the displacement bottom plate 9 to be limited and fixed, which not only ensures the stability of the hanger during use, but also makes the length adjustment of the hanger accurate and simple, and further enhances the applicability and flexibility of the hanger to meet the needs of different construction scenarios;
[0043] Secondly, the hanger drives the partition 4 to slide in the sliding cavity 3 by pulling the handle 14, so as to facilitate the adjustment of the height of the partition 4, thereby making the installation and removal of the partition 4 more convenient. In addition, the fastening bolts provided in the first mounting hole 7 and the sixth mounting hole 20 facilitate the fixing of the partition 4 at different heights, thereby facilitating the cleaning and tidying of the internal space of the hanger;
[0044] Then, the installed hanger is hung outside the building by passing the steel cable through the traction ring 11 fixedly connected to the upper end of the column 2.
[0045] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A prefabricated construction hanger, comprising two bottom plates (1) and two displacement guardrail plates (10), characterized in that: Two guardrail plates (5) are fixedly connected to both sides of the upper surface of the bottom plate (1); the outer walls of the rear ends of the guardrail plates (5) are fixedly connected to the columns (2); the outer walls of the adjacent sides of the two columns (2) are provided with sliding cavities (3); the interior of the sliding cavities (3) is slidably connected to the clamping blocks (15); and the outer walls of the adjacent sides of the two clamping blocks (15) are fixedly connected to the partition plates (4); The front ends of the outer walls on both sides of the base plate (1) are provided with second mounting holes (16); the middle part of the outer wall on the front end of the base plate (1) is provided with a fixing cavity (8); the interior of the fixing cavity (8) is slidably connected to a displacement base plate (9); the middle parts of the outer walls on both sides of the displacement base plate (9) are provided with a plurality of fourth mounting holes (18); the middle part of the outer wall on the front end of the guardrail plate (5) is provided with a mounting cavity (6); the interior of the mounting cavity (6) is slidably connected to a displacement guardrail plate (10); the upper and lower ends of the outer walls on both sides of the displacement guardrail plate (10) are provided with a plurality of fifth mounting holes (19); the upper and lower ends of the outer walls on both sides of the guardrail plate (5) close to the displacement guardrail plate (10) are provided with third mounting holes (17).
2. The assembled building construction hanger according to claim 1, characterized in that: Both sides of the lower surface of the base plate (1) away from the displacement base plate (9) are fixedly connected to connecting rods (12), and the lower ends of the connecting rods (12) are fixedly connected to self-locking universal wheels (13).
3. The assembled building construction hanger according to claim 1, characterized in that: The upper surfaces of the uprights (2) are fixedly connected with traction rings (11).
4. The assembled building construction hanger according to claim 1, characterized in that: The inner walls on both sides of the sliding cavity (3) are provided with a plurality of first mounting holes (7), and the outer walls on both sides of the front end of the partition plate (4) are provided with a plurality of sixth mounting holes (20).
5. The assembled building construction hanger according to claim 1, characterized in that: A handle (14) is fixedly connected to the outer wall of the front end of the partition (4).
6. The assembled building construction hanger according to claim 1, characterized in that: The second mounting hole (16) and the fourth mounting hole (18) are both provided with fastening bolts inside.
7. The assembled building construction hanger according to claim 4, characterized in that: The first mounting hole (7) and the sixth mounting hole (20) are both provided with fastening bolts inside.
8. The assembled building construction hanger according to claim 1, characterized in that: The third mounting hole (17) and the fifth mounting hole (19) are both provided with fastening bolts inside.