Head upsetting die for galvanized pipe

By designing noise reduction lifting devices and temporary storage devices in the galvanized pipe pier mold, the problems of noise processing and base height adjustment during processing of the mold are solved, and temporary storage of galvanized pipes is realized, improving the working ability and practicality of the mold.

CN222957422UActive Publication Date: 2025-06-10SHANDONG HUITONGDA MACHINERY MANUFACTURING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421483431.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2025-06-10
Estimated Expiration
2034-06-26

AI Technical Summary

Technical Problem

The existing galvanized pipe pier head molds cannot effectively deal with noise during processing, and the base structure height is inconvenient to adjust, and the temporary storage of galvanized pipes cannot be carried out, which reduces the working ability and practicality of the mold.

Method used

A galvanized pipe pier head mold is designed, using noise reduction lifting device and temporary storage device. Through structures such as moving shells, sound-absorbing cotton, electric lifting rods, storage boxes, screws and pressing plates, noise reduction, base height adjustment and temporary storage of galvanized pipes are achieved.

Benefits of technology

It improves the working ability and practicality of the mold, can effectively reduce noise when needed, adjust the base height, and temporarily store galvanized pipes to meet the working needs in different situations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222957422U_ABST
    Figure CN222957422U_ABST
Patent Text Reader

Abstract

The utility model discloses a head upsetting die for a galvanized pipe, which belongs to the technical field of galvanized pipe processing and comprises a mounting plate, a base is arranged above the mounting plate, a punch component is mounted above the base, and a clamping component is arranged above the base and positioned on one side of the punch component. A fixing assembly is installed above the base and located at the position, close to the edge, of the side, away from the punch assembly, of the clamping assembly, the base and the clamping assembly are connected through a spring assembly, and a noise reduction lifting device is installed on the outer side of the base, the outer side of the clamping assembly and the outer side of the fixing assembly. By arranging the noise reduction lifting device, the mold can carry out certain noise reduction treatment on noise generated during machining through cooperation of a movable shell, sound absorption cotton and other structures when needed, and a worker can adjust the height of the base and other structures to a certain degree through an electric lifting rod when needed; and the working capability of the die is further improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of galvanized pipe processing, and particularly relates to a galvanized pipe pier head mold. Background Technique

[0002] Galvanized pipes, also known as galvanized steel pipes, are divided into two types: hot-dip galvanized and electro-galvanized. Hot-dip galvanized pipes have thick galvanized layers, with advantages such as uniform coating, strong adhesion, and long service life.

[0003] Chinese Patent Application No. 202222843949.0 discloses a mold for various pier head products, including a base. A clamping plate is slidably connected to the top of the base. A groove is provided on one side of the clamping plate, and a placement hole is provided on one side of the groove. A clamping mechanism is provided on the clamping plate. A fixing plate is fixedly installed on the top of the base. Four wedge-shaped ejector rods are fixedly installed on one side of the fixing plate, and the wedge-shaped ejector rods are in transmission connection with the clamping mechanism. A baffle is fixedly installed on the inner wall of the placement hole. The utility model is simple to operate and convenient to use, and can facilitate quick clamping and fixing of pipe fittings during stamping, and can also be quickly disassembled after stamping, facilitating feeding and discharging.

[0004] 1. The above-mentioned disclosed patent has problems that it cannot handle the noise generated during processing when needed and is inconvenient to adjust the height of structures such as the base, thus reducing the working ability of the mold; 2. The above-mentioned disclosed patent has the problem that it cannot temporarily store galvanized pipes when needed, thus reducing the practicality of the mold. Content of the Utility Model

[0005] To solve the problems raised in the above background technique. The utility model provides a galvanized pipe pier head mold, which has the characteristics of high working ability and strong practicality.

[0006] To achieve the above object, the utility model provides the following technical solution: A galvanized pipe pier head mold, including a mounting plate. A base is arranged above the mounting plate. A punch assembly is installed above the base. A clamping assembly is arranged above the base and on one side of the punch assembly. A fixing assembly is installed above the base and at a position on the edge away from the punch assembly on the side of the clamping assembly. The base and the clamping assembly are connected by a spring assembly. A noise reduction and lifting device is installed outside the base, the clamping assembly and the fixing assembly. The mounting plate and the noise reduction and lifting device are connected by a temporary storage device.

[0007] Preferably, the noise reduction and lifting device includes a connection box, a moving shell, sound-absorbing cotton, a moving plate and a moving component. A connection box is installed on one side of the base close to the mounting plate. A moving plate is arranged on one side of the connection box. A moving shell is installed above the moving plate and at a position outside the base, the clamping assembly and the fixing assembly. Sound-absorbing cotton is installed in the side wall of the moving shell. The connection box and the moving plate are connected by a moving component.

[0008] Preferably, the noise reduction lifting device further includes an electric lifting rod, and the electric lifting rod is installed on one side of the connection box close to the mounting plate.

[0009] Preferably, the moving component includes a moving block, a lead screw, and a knob. A knob is provided on one side of the connection box, the lead screw is installed on the side of the knob close to the connection box, and the moving block is installed on the moving plate at a position outside the lead screw and inside the connection box.

[0010] Preferably, the temporary storage device includes a storage box, a pressing plate, a rotating plate, and a screw. A storage box is installed between the mounting plate and the electric lifting rod. A screw is installed on the top of the storage box at a position away from the connection box side of the knob through threads. A rotating plate is installed above the screw, and a pressing plate is installed below the screw and inside the storage box through a bearing.

[0011] Preferably, the temporary storage device further includes a rubber layer, and the rubber layer is installed below the pressing plate.

[0012] Compared with the prior art, the beneficial effects of the present utility model are as follows:

[0013] 1. By setting the noise reduction lifting device, the present utility model enables the mold to perform a certain noise reduction treatment on the noise generated during processing through the cooperation of structures such as the moving shell and the sound-absorbing cotton when needed, and the staff can adjust the height of structures such as the base through the electric lifting rod when needed, thereby improving the working ability of the mold.

[0014] 2. By setting the temporary storage device, the present utility model enables the mold to temporarily store galvanized pipes through the storage box when needed, and the mold can fix the galvanized pipes in the storage box through the cooperation of structures such as the screw and the pressing plate when needed, thus better meeting the working needs in different situations and improving the practicality of the mold. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 is a three-dimensional view of the present utility model;

[0016] Figure 2 is a three-dimensional sectional view of the present utility model;

[0017] Figure 3 is a three-dimensional sectional view of the noise reduction lifting device of the present utility model;

[0018] Figure 4 is a three-dimensional sectional view of the temporary storage device of the present utility model.

[0019] In the figure: 1. Base; 2. Clamping assembly; 3. Fixing assembly; 4. Noise reduction lifting device; 41. Connection box; 42. Moving shell; 43. Sound-absorbing cotton; 44. Moving plate; 45. Moving assembly; 451. Moving block; 452. Lead screw; 453. Knob; 46. Electric lifting rod; 5. Mounting plate; 6. Spring assembly; 7. Temporary storage device; 71. Storage box; 72. Pressing plate; 73. Rotating plate; 74. Screw; 75. Rubber layer; 8. Punch assembly. Detailed implementation mode

[0020] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0021] Embodiment 1

[0022] Please refer to Figures 1-4 , the present invention provides the following technical solutions: a galvanized pipe head die, including a mounting plate 5, a base 1 is arranged above the mounting plate 5, a punch assembly 8 is installed above the base 1, a clamping assembly 2 is arranged above the base 1 and on one side of the punch assembly 8, and a fixing assembly 3 is installed above the base 1 and at a position near the edge on the side of the clamping assembly 2 away from the punch assembly 8. The base 1 and the clamping assembly 2 are connected by a spring assembly 6, and a noise reduction lifting device 4 is installed outside the base 1, the clamping assembly 2 and the fixing assembly 3. The mounting plate 5 and the noise reduction lifting device 4 are connected by a temporary storage device 7.

[0023] Specifically, the noise reduction lifting device 4 includes a connection box 41, a moving shell 42, sound-absorbing cotton 43, a moving plate 44 and a moving assembly 45. A connection box 41 is installed on one side of the base 1 close to the mounting plate 5. A moving plate 44 is arranged on one side of the connection box 41. A moving shell 42 is installed above the moving plate 44 and at a position outside the base 1, the clamping assembly 2 and the fixing assembly 3. Sound-absorbing cotton 43 is installed in the side wall of the moving shell 42. The connection box 41 and the moving plate 44 are connected by a moving assembly 45.

[0024] By adopting the above technical solutions, the die can perform a certain noise reduction treatment on the noise generated during processing through the cooperation of structures such as the moving shell 42 and the sound-absorbing cotton 43, thereby reducing the possibility of adverse effects on surrounding personnel.

[0025] Specifically, the noise reduction lifting device 4 further includes an electric lifting rod 46, and an electric lifting rod 46 is installed on one side of the connection box 41 close to the mounting plate 5.

[0026] By adopting the above technical solution, the staff can adjust the height of structures such as the base 1 through the electric lifting rod 46 when needed, so as to better meet the working needs in different situations.

[0027] Specifically, the moving component 45 includes a moving block 451, a lead screw 452 and a knob 453. A knob 453 is arranged on one side of the connection box 41. A lead screw 452 is installed on the side of the knob 453 close to the connection box 41. A moving block 451 is installed on the moving plate 44 at a position outside the lead screw 452 and inside the connection box 41.

[0028] By adopting the above technical solution, the staff can adjust the position of structures such as the moving shell 42 through the cooperation of structures such as the lead screw 452 and the moving block 451 when needed, so as to select whether to carry out noise reduction work.

[0029] When this embodiment is in use, when the staff needs to use the mold, the mounting plate 5 is installed at the working position through screws, and then the electric lifting rod 46 in the noise reduction lifting device 4 is started to adjust the height of structures such as the connection box 41 and the base 1. Then, the fixing component 3 is adjusted, and the knob 453 in the moving component 45 is rotated, so as to drive the lead screw 452 to rotate. The lead screw 452 is in threaded connection with the moving block 451, and the outside of the moving block 451 is closely attached to the inside of the connection box 41. Therefore, the lead screw 452 drives the moving block 451 to move, and then drives the moving shell 42 to move to the outside of the clamping component 2 and the fixing component 3 through the moving plate 44. Then, the galvanized pipe is inserted into the clamping component 2, and the punch component 8 on the base 1 is operated to cooperate with the clamping component 2 and the fixing component 3 to carry out upsetting processing on the galvanized pipe. During the processing, the sound-absorbing cotton 43 can carry out noise reduction treatment on the noise, and the spring component 6 plays a role of buffering and resetting.

[0030] Embodiment 2

[0031] The difference between this embodiment and Embodiment 1 is that the temporary storage device 7 includes a storage box 71, a pressing plate 72, a rotating plate 73 and a screw rod 74. A storage box 71 is installed between the mounting plate 5 and the electric lifting rod 46. A screw rod 74 is installed at the top of the storage box 71 at a position far from the connection box 41 of the knob 453 through threads. A rotating plate 73 is installed above the screw rod 74. A pressing plate 72 is installed below the screw rod 74 and inside the storage box 71 through a bearing.

[0032] By adopting the above technical solution, the mold can temporarily store the galvanized pipe through the storage box 71 when needed, and the mold can fix the galvanized pipe in the storage box 71 through the cooperation of structures such as the screw rod 74 and the pressing plate 72 when needed, so as to better meet the working needs in different situations.

[0033] Specifically, the temporary storage device 7 further includes a rubber layer 75, and the rubber layer 75 is installed below the pressing plate 72.

[0034] By adopting the above technical solution, the mold can prevent the pressing plate 72 and the galvanized pipe from colliding and damaging each other through the rubber layer 75, thus better meeting the needs of the staff and ensuring the normal progress of the work.

[0035] When in use in this embodiment, when it is necessary to temporarily store the galvanized pipe, the galvanized pipe is placed in the storage box 71 in the temporary storage device 7, and the rotating plate 73 is rotated, thereby driving the screw rod 74 to rotate. The screw rod 74 is threadedly connected to the storage box 71, and the screw rod 74 is connected to the pressing plate 72 through a bearing, and the pressing plate 72 is close to the storage box 71. Therefore, the screw rod 74 drives the pressing plate 72 and the rubber layer 75 below it to descend, and then presses the galvanized pipe, and the temporary storage is completed.

[0036] In the present utility model, the structures and principles of the base 1, the clamping assembly 2 composed of a clamping plate, a groove and a placement hole, the fixing assembly 3 composed of a fixing plate, a baffle, a wedge-shaped ejector rod, a positioning groove, a top block, a through hole, a buffer rod, an arc-shaped pressing plate, a buffer groove, a buffer spring and a screw rod, the spring assembly 6 composed of a sliding groove, a slider, a sliding rod and a return spring, and the punch assembly 8 composed of a fixing seat, a mounting plate, a punch and a cylinder have been disclosed in the molds of various pier products disclosed in Chinese Patent Application No. 202222843949.0. Its working principle is that during work, the pipe fitting is placed in the placement hole. When stamping, the cylinder switch is started, and the piston of the cylinder drives the punch to move through the mounting plate, thereby pushing the pipe fitting. The pipe fitting drives the clamping plate to move leftward, and the moving clamping plate drives the top block to move. The top block can drive the top block to move through the mutual cooperation of the wedge-shaped ejector rod and the through hole. The top block drives the arc-shaped pressing plate to press and fix the pipe fitting through the buffer rod. At the same time, the punch punches the pipe fitting to form a pier. When the cylinder drives the punch to return, the return spring can drive the clamping plate to buffer and reset through the slider, so that the wedge-shaped ejector rod moves out of the through hole.

[0037] Working principle and usage process of the utility model: When a worker needs to use the mold, the mounting plate 5 is installed at the working position through screws, and then the electric lifting rod 46 in the noise reduction lifting device 4 is started, so as to adjust the heights of structures such as the connection box 41 and the base 1. Then, the fixing component 3 is adjusted, and the knob 453 in the moving component 45 is rotated, thereby driving the screw rod 452 to rotate. The screw rod 452 is in threaded connection with the moving block 451, and the outer side of the moving block 451 is closely attached to the inner side of the connection box 41. Therefore, the screw rod 452 drives the moving block 451 to move, and then drives the moving shell 42 to move to the outside of the clamping component 2 and the fixing component 3 through the moving plate 44. Then, the galvanized pipe is inserted into the clamping component 2, and the punch component 8 on the base 1 is operated to cooperate with the clamping component 2 and the fixing component 3 to perform upsetting processing on the galvanized pipe. During the processing, the sound-absorbing cotton 43 can reduce the noise, and the spring component 6 plays a role of buffering and resetting; When the galvanized pipe needs to be temporarily stored, the galvanized pipe is placed in the storage box 71 in the temporary storage device 7, and the rotating plate 73 is rotated, thereby driving the screw rod 74 to rotate. The screw rod 74 is in threaded connection with the storage box 71, the screw rod 74 is in bearing connection with the pressing plate 72, and the pressing plate 72 is closely attached to the storage box 71. Therefore, the screw rod 74 drives the pressing plate 72 and the rubber layer 75 below it to descend, and then presses the galvanized pipe, and the temporary storage is completed.

[0038] Although the embodiments of the present utility model have been shown and described, for those of ordinary skill in the art, it can be understood that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and spirit of the present utility model. The scope of the present utility model is defined by the appended claims and their equivalents.

Claims

1. Galvanized pipe pier head mold, including a mounting plate, characterized by: A base is arranged above the mounting plate, a punch assembly is installed above the base, a clamping assembly is arranged above the base and at a position on one side of the punch assembly, a fixing assembly is installed above the base and at a position close to the edge of the clamping assembly away from the punch assembly, the base and the clamping assembly are connected by a spring assembly, a noise reduction lifting device is installed on the outer sides of the base, the clamping assembly and the fixing assembly, and the mounting plate and the noise reduction lifting device are connected by a temporary storage device.

2. The galvanized pipe pier head mold according to claim 1, characterized in that: The noise reduction lifting device includes a connecting box, a movable shell, sound-absorbing cotton, a movable plate and a movable assembly. A connecting box is installed on a side of the base close to the mounting plate, a movable plate is arranged on one side of the connecting box, a movable shell is installed above the movable plate and outside the base, the clamping assembly and the fixing assembly, sound-absorbing cotton is installed in the side wall of the movable shell, and the connecting box and the movable plate are connected through the movable assembly.

3. The galvanized pipe pier head mold according to claim 2, characterized in that: The noise reduction lifting device also includes an electric lifting rod, and the electric lifting rod is installed on one side of the connection box close to the mounting plate.

4. The galvanized pipe pier head mold according to claim 2, characterized in that: The moving assembly includes a moving block, a screw rod and a knob. A knob is provided on one side of the connection box, a screw rod is installed on the side of the knob close to the connection box, and a moving block is installed on the moving plate and located on the outside of the screw rod and the inside of the connection box.

5. The galvanized pipe pier head mold according to claim 4, characterized in that: The temporary storage device includes a storage box, a pressing plate, a rotating plate and a screw. The storage box is installed between the mounting plate and the electric lifting rod. The screw is installed through a thread at the top of the storage box and at a position on the side of the knob away from the connecting box. The rotating plate is installed above the screw. The pressing plate is installed through a bearing below the screw and at a position inside the storage box.

6. The galvanized pipe pier head mold according to claim 5, characterized in that: The temporary storage device also includes a rubber layer, and the rubber layer is installed below the pressing plate.

Citation Information

Patent Citations

  • Die for various pier head products

    CN219597791U