Gantry crane track beam supporting structure
By using a combination of suspended simple-supported I-shaped steel structure and SMW working pile H-shaped steel on the gantry crane track beam, the problem that the gantry crane cannot cross the deep foundation pit of the pump room is solved, and the convenience of material lifting and construction cost are achieved.
Patent Information
- Application Number
- CN202422225431.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-11
- Publication Date
- 2025-06-27
- Estimated Expiration
- 2034-09-11
AI Technical Summary
During the tunnel excavation construction, the existing gantry crane rail beam support structure cannot effectively cross the deep foundation pit at the pump room, resulting in difficulty in lifting materials and inconvenient lifting.
A rail beam with suspended simply supported combined I-shaped steel structure is used, and SMW working pile H-shaped steel is used as the support foundation to form a combined structure to achieve a safe leap of the rail beam.
It effectively solves the problem of gantry crane walking in the pump room, improves the convenience and safety of material lifting, and reduces construction costs.
Smart Images

Figure CN223032885U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of gantry crane track beam support structures, and particularly relates to a gantry crane track beam support structure. Background Technique
[0002] Gantry cranes are applicable to various fields such as industrial production and construction sites. Whether it is in infrastructure construction fields such as ports, docks, bridges, and tunnels, or in industrial production fields such as machinery manufacturing and automobile manufacturing, gantry cranes can be used to complete the lifting and handling of various heavy objects.
[0003] However, in the existing gantry crane track beam support structure, during the open cut method construction of the underpass tunnel in the municipal engineering, in order to facilitate the material transportation, formwork disassembly and transfer during the construction process. For example, when 4 gantry cranes of model MHE10+10-28.7 are installed in the project, due to the change in the form of the foundation pit curtain structure at the pump house, the forward extension of the gantry crane track is interrupted, and the gantry crane cannot cross the deep and large foundation pit at the pump house. The lifting of materials at the construction site is relatively difficult, and the lifting operation in the local construction area cannot be covered due to the lifting restriction of the construction site. Therefore, the technical personnel in this field provide a gantry crane track beam support structure to solve the problems existing above. Content of the Utility Model
[0004] The purpose of the utility model is to solve the disadvantages existing in the prior art, and a gantry crane track beam support structure is proposed. The track beam adopts a suspended simply supported combined I-beam steel structure form, the track adopts a combined structure of 63 channel steel and steel plate, and the support foundation adopts a combined structure with the H-shaped steel of the SMW method pile as the support foundation.
[0005] To achieve the above purpose, the utility model provides the following technical solution: A gantry crane track beam support structure includes a lower cover plate, and an I-shaped steel is installed at the middle position of the upper side wall of the lower cover plate. The I-shaped steel includes a joint reinforcement plate, and a plurality of I-beam webs are installed at the middle position of the inner side wall and on both sides close to the middle of the inner side wall. Reinforcing plates are installed on both side walls and the middle position of the plurality of I-beam webs, and the plurality of reinforcing plates are distributed in a rectangular array. A reinforcing steel plate is installed at the middle position of the upper side wall of the joint reinforcement plate;
[0006] Through the above technical solution, the application of this gantry crane track beam support structure effectively solves the problem of the gantry crane walking across the deep and large foundation pit of the pump house, provides great convenience for the lifting of materials at the site, ensures the safety of the lifting of construction materials at the pump house part, and reduces the construction cost.
[0007] Furthermore, a track lower backing plate is installed at the middle position of the upper side wall of the reinforcing steel plate, and a traveling wheel is installed at the middle position of the upper side wall of the track lower backing plate;
[0008] Through the above technical solution, the traveling wheel is a schematic diagram of the traveling mechanism of the gantry crane, and the traveling wheel is limited by the cooperation between the track underlay plate, the limit plate and the channel steel.
[0009] Furthermore, an upper cover plate is installed at a position on the middle of the upper side wall of the reinforcing steel plate close to the other side;
[0010] Through the above technical solution, a reinforcing steel plate is welded on the I-beam to bear the hoisted object. The upper cover plate is made of a rigid material and is used to cooperate with the position on the upper side wall of the reinforcing steel plate close to the other side to adapt to gantry cranes of different models and weights.
[0011] Furthermore, a partition plate is installed at a position on the middle of the upper side wall of the upper cover plate close to the other side, and a limit plate is installed at a position on the middle of the upper side wall of the upper cover plate close to one side. The partition plate and the limit plate are distributed in a mirror image opposition;
[0012] Through the above technical solution, the partition plate and the limit plate are used for limiting during the traveling of the gantry crane.
[0013] Furthermore, a connecting steel plate is installed at the end of the I-shaped steel, and an H-shaped steel of the SMW method pile is welded on the rear side wall of the connecting steel plate;
[0014] Through the above technical solution, the end of the triple-joined steel plate is fixed by welding the connecting steel plate on the H-shaped steel of the SMW method pile, forming a support system for the section of the gantry crane track beam spanning the deep and large foundation pit of the pump house, ensuring that the gantry crane track beam safely crosses the deep and large foundation pit at the pump house position.
[0015] Furthermore, a plurality of the I-shaped steel webs, a plurality of embedded steel plates, the reinforcing steel plate and the lower cover plate are all made of rigid materials;
[0016] Through the above technical solution, steel materials have high strength and good impact resistance. The strength of steel is high and it is widely used in various projects. Its impact resistance is strong, it can resist external impact forces, and its corrosion resistance is strong: the corrosion resistance of steel is good and it can be used for a long time in harsh environments. Good plasticity: Steel can be shaped into various shapes through various processing methods, greatly expanding the scope of use.
[0017] Furthermore, each group of the I-shaped steel webs and each group of the embedded steel plates are connected to form a triple-joined steel plate;
[0018] Through the above technical solution, the triple-joined steel plate is installed and temporarily fixed.
[0019] The utility model has the following beneficial effects:
[0020] 1. In the utility model, the H-shaped steel of the SMW method pile is used as the support foundation of the gantry crane track beam, ensuring the integrity of the function of the SMW method pile H-shaped steel curtain structure itself.
[0021] 2. In the present utility model, in the case where the foundation pit span at the pump house is large, the clearance of the gantry crane track beam and the track elevation are limited, a combined I-beam track beam is adopted to span the deep and large foundation pit of the pump house at one time, solving the problems of the safe operation and hoisting of the gantry crane track beam under the conditions of large span and simply supported working conditions.
[0022] 3. In the present utility model, the gantry crane track adopts a combined structure of channel steel and steel plate, solving the problems of limited track elevation, safe operation and hoisting of the gantry crane. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 is a three-dimensional schematic diagram of a support structure for a gantry crane track beam;
[0024] Figure 2 is a front sectional view of a support structure for a gantry crane track beam;
[0025] Figure 3 is a connection diagram of a connecting steel plate and an H-shaped steel of an SMW method pile;
[0026] Figure 4 is a front view of a support structure for a gantry crane track beam
[0027] Figure 5 is Figure 1 an enlarged schematic diagram of part A in
[0028] LEGEND DESCRIPTION:
[0029] 1. Lower cover plate; 2. I-shaped steel; 3. Joint reinforcement plate; 4. Embedded reinforcement plate; 5. I-beam web; 6. Traveling wheel; 7. Track bottom cushion plate; 8. Reinforcement steel plate; 9. Upper cover plate; 10. Partition plate; 11. Limit plate; 12. H-shaped steel of SMW method pile; 13. Connecting steel plate; 14. Three-piece steel plate. DETAILED DESCRIPTION OF THE EMBODIMENTS
[0030] Next, the technical solutions in the embodiments of the present utility model will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all of the embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present utility model.
[0031] Refer to Figures 1-5, an embodiment provided by the utility model: a support structure for a gantry crane track beam, including a lower cover plate 1. In the middle position of the upper side wall of the lower cover plate 1, an I-beam 2 is installed. The I-beam 2 includes a joint reinforcement plate 3. In the middle position of the inner side wall of the joint reinforcement plate 3 and on both sides near the middle position of the inner side wall, a number of I-beam webs 5 are installed. On both side walls and in the middle position of the number of I-beam webs 5, embedded rib plates 4 are installed. The number of embedded rib plates 4 are distributed in a rectangular array. In the middle position of the upper side wall of the joint reinforcement plate 3, a reinforcement steel plate 8 is installed. The application of this gantry crane track beam support structure effectively solves the problem of the gantry crane walking across the pump house, provides great convenience for the hoisting of materials on site, ensures the safety of material hoisting at the pump house part, and saves construction costs.
[0032] On the upper side wall of the reinforcement steel plate 8, near the middle position, a track lower backing plate 7 is installed. In the middle position of the upper side wall of the track lower backing plate 7, a traveling wheel 6 is installed. The traveling wheel 6 is a schematic diagram of the gantry crane traveling mechanism. Through the cooperation between the track lower backing plate 7 and the limit plate 11 and the channel steel, the traveling wheel 6 is limited. On the upper side wall of the reinforcement steel plate 8, in the middle position near the other side, an upper cover plate 9 is installed. The reinforcement steel plate 8 is welded to the I-beam, ensuring the overall force stability of the track beam structure. The upper cover plate 9 is made of a rigid material and is used to cooperate with the upper side wall of the reinforcement steel plate 8 near the other side to adapt to gantry cranes of different models and weights.
[0033] On the upper side wall of the upper cover plate 9, in the middle position near the other side, a partition plate 10 is installed. On the upper side wall of the upper cover plate 9, in the middle position near one side, a limit plate 11 is installed. The partition plate 10 and the limit plate 11 are mirror-image and oppositely distributed. The partition plate 10 and the limit plate 11 are used for the limit during the gantry crane walking. At the end of the I-beam 2, a triple-plate 14 is welded. One end of the connecting steel plate 13 is welded to the surface of the triple-plate 14. The inner side wall of the connecting steel plate 13 is welded to the outer side wall of the H-shaped steel flange of the SMW method pile H-shaped steel 12, forming a support system for the gantry crane track beam across the pump house section, ensuring that the gantry crane track beam can smoothly pass through the deep and large foundation pit at the pump house position.
[0034] A number of I-beam webs 5, a number of embedded rib plates 4, the reinforcement steel plate 8 and the lower cover plate 1 are all made of rigid materials. Steel materials have high strength, good impact resistance: The strength of steel is high and it is widely used in various projects. Its impact resistance is strong and it can resist external impact forces. It has strong corrosion resistance: The corrosion resistance of steel is good and it can be used for a long time in harsh environments. It has good plasticity: Steel can be shaped into various shapes through various processing methods, greatly broadening the scope of use. Each group of I-beam webs 5 and each group of embedded rib plates 4 are connected to form a triple-plate 14, and the triple-plate 14 is welded and temporarily fixed.
[0035] Working principle: Lay out lines on the bearing girder according to the gauge of the crane, pop out the center line of the track, and then pop out the bottom edge line of the track according to the bottom width of the track. Taking the track line on the conductive side as the benchmark, use a steel tape measure and a spring scale to determine the center line of the other side of the track according to the gauge, pop out the center line of the track and the installation lines at both ends, hoist the three-piece section steel and make temporary fixation. Adjust the elevation: Add the required shims according to the measured elevation. After the elevation is adjusted and in place, align, position, and fasten the track. Install and adjust the track of the gantry crane at the joint of the track spanning the pump house and the crown beams at both ends by pulling a wire. After the adjustment is in place, use connecting steel plates to fix and weld the section steel of the track beam spanning the pump house and the diaphragm wall pile, so that the track beam spanning the pump house and the diaphragm wall pile are connected into a whole. When the gantry crane at the pump house spanning the pump house is in operation, it is in a simply supported stress state. Through calculation, the deflection is 23.7 mm under the condition of the maximum load of 200 KN on one side. In order to make the traveling of the crane smooth, a 25-mm camber is reserved during the processing of the steel beam. Three lateral stabilizer bars are welded to the web of the steel beam at the center position of the steel beam to prevent the steel beam from losing stability due to the impact and vibration when the crane trolley moves. When conducting the re-inspection of the track, the track foundation is laid as required, and the horizontal distance between the center line of the track and the foundation is determined. The track is re-inspected and accepted by the on-site operation supervisor, technician, and project quality inspection department at three levels. Before installation, the actual situation of the track should be measured, and the best position should be selected as the installation reference position of the gantry crane. Tools used: level, steel tape measure, spring scale, feeler gauge. The specific inspection requirements are as follows: The gap between the track joints is not more than 2 mm, the height difference and lateral misalignment of the track joints are not more than 1 mm, the longitudinal inclination of the track top surface relative to its designed position is not more than 3 / 1000, the height difference within the whole stroke is not more than 10 mm, the elevation of the reference point on the track top surface allows a tolerance of ±10 mm relative to the designed elevation, and the elevation difference between the two parallel tracks in the same section is not more than 10 mm.
[0036] Finally, it should be noted that the above are only the preferred embodiments of the present invention and are not used to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some of the technical features. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A gantry crane track beam support structure, comprising a lower cover plate (1), characterized in that: An I-shaped steel (2) is installed in the middle of the upper side wall of the lower cover plate (1), the I-shaped steel (2) includes a joint reinforcement plate (3), a plurality of I-shaped steel webs (5) are installed in the middle of the inner side wall of the joint reinforcement plate (3) and at the positions on both sides of the middle of the inner side wall, a plurality of ribbed plates (4) are installed on the two side walls and the middle of the plurality of I-shaped steel webs (5), the plurality of ribbed plates (4) are distributed in a rectangular array, and a reinforcing steel plate (8) is installed in the middle of the upper side wall of the joint reinforcement plate (3).
2. A gantry crane track beam support structure according to claim 1, characterized in that: A track bottom pad (7) is installed at a middle position on the upper side wall of the reinforcing steel plate (8), and a running wheel (6) is installed at a middle position on the upper side wall of the track bottom pad (7).
3. A gantry crane track beam support structure according to claim 1, characterized in that: An upper cover plate (9) is installed in the middle of the upper side wall of the reinforcing steel plate (8) close to the other side.
4. A gantry crane track beam support structure according to claim 3, characterized in that: A partition plate (10) is installed in the middle of the upper side wall of the upper cover plate (9) near the other side, and a limit plate (11) is installed in the middle of the upper side wall of the upper cover plate (9) near one side, and the partition plate (10) and the limit plate (11) are distributed in a mirror-image manner.
5. The gantry crane track beam support structure according to claim 1, characterized in that: A connecting steel plate (13) is welded to the end of the I-shaped steel (2), and the inner side wall of the connecting steel plate (13) is welded to the outer side wall of the H-shaped steel flange plate of the SMW method pile H-shaped steel (12).
6. The gantry crane track beam support structure according to claim 1, characterized in that: The plurality of I-beam webs (5), the plurality of ribbed plates (4), the reinforcement steel plates (8) and the lower cover plate (1) are all welded with rigid materials.
7. The gantry crane track beam support structure according to claim 1, characterized in that: Each group of I-beam webs (5) and each group of ribbed plates (4) are connected to form a three-piece steel plate (14).