Side pile positioning device for roadbed and pavement construction

By designing vertical frames and positioning components to adjust the traction rope height, the problem of positioning line deviation in the prior art is solved, automatic positioning is achieved, construction errors are reduced, and construction efficiency is improved.

CN223047859UActive Publication Date: 2025-07-01陕西省交通规划设计研究院有限公司
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421766327.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2025-07-01
Estimated Expiration
2034-07-24

AI Technical Summary

Technical Problem

During the use of the existing roadbed construction side pile positioning device, the positioning line is prone to deflection, resulting in construction errors, and construction personnel need to hold the positioning line and cannot leave, which affects construction efficiency.

Method used

A side pile positioning device for roadbed construction is designed. Through the cooperation of the vertical frame and the positioning components, the height of the traction rope is adjusted and the compressed state is maintained, thereby reducing positioning deviations and realizing automatic positioning.

Benefits of technology

It reduces construction errors, improves construction efficiency, reduces manual intervention, and ensures the stability and accuracy of the positioning line.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223047859U_ABST
    Figure CN223047859U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of roadbed pavement construction side pile positioning, and discloses a roadbed pavement construction side pile positioning device which comprises a first base, a first vertical frame is fixedly arranged at the top end of the first base, and a positioning assembly is further arranged at the top end of the first vertical frame. The positioning assembly comprises a protective cover fixedly arranged at the top end of the vertical frame, a winding rotating shaft is rotationally arranged in the protective cover, a torsional spring is fixedly arranged above the outer side of the winding rotating shaft, the other end of the torsional spring and the protective cover are fixedly arranged, and a traction rope is arranged on the outer side of the winding rotating shaft in a winding mode; through cooperation of a first vertical frame, a second positioning ring in a positioning assembly and a long screw rod, after the construction height of a traction rope to a side pile on the surface of a road surface and a roadbed is adjusted, the long screw rod structure located in the first vertical frame is moved to be pressed downwards and positioned to the height of the traction rope, the traction rope is pressed tightly, and the height stably close to the road surface and the roadbed is kept for use; therefore, construction errors caused by positioning deviation of the traction rope are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of subgrade and pavement construction side pile positioning, and specifically relates to a subgrade and pavement construction side pile positioning device. Background Technique

[0002] The side piles for subgrade and pavement construction are marked with wooden stakes at the intersection of the subgrade slope line and the ground on the ground. The construction side piles need to be guided and positioned using positioning lines, which are generally directly placed on the ground and are prone to deviation.

[0003] At the same time, a subgrade and pavement construction side pile positioning device with the application number CN202221392708.2, "comprises a rod body and a wire hanging frame. The wire hanging frame includes a cross bar and a slider for hanging a steel strand. The slider is slidably arranged on the cross bar. The sliding direction of the slider is along the length direction of the cross bar. A fixing component for fixing the slider is arranged on the cross bar, and a tensioning component for presetting the tension of the steel strand is arranged on the slider";

[0004] During the use of the existing subgrade and pavement construction side pile positioning devices, due to the different lengths of the positioning devices, during subgrade and pavement construction, after height adjustment, construction workers need to hold the positioning line by hand and cannot leave, otherwise the positioning line will deviate, resulting in errors in side pile construction.

[0005] Therefore, a subgrade and pavement construction side pile positioning device is proposed for the above problems. Content of the Utility Model

[0006] To solve the problems raised in the above background technique, the utility model provides a subgrade and pavement construction side pile positioning device, which has the advantages of pressing the traction rope close to the road surface and maintaining a pressed state, without the need for construction workers to assist in construction.

[0007] To achieve the above object, the utility model provides the following technical solution: A subgrade and pavement construction side pile positioning device, comprising a first base, a first vertical frame is fixedly arranged at the top of the first base, and a positioning component is further included at the top of the first vertical frame;

[0008] The positioning component includes a protective cover fixedly arranged at the top of the first vertical frame. A winding rotating shaft is rotatably arranged inside the protective cover. A torsion spring is fixedly arranged above the outer side of the winding rotating shaft, and the other end of the torsion spring is fixedly arranged with the protective cover. A traction rope is wound around the outer side of the winding rotating shaft. A second positioning ring is slidably arranged on the outer side of the traction rope. A first clamping piece is fixedly arranged on the left side of the second positioning ring. A long screw rod is fixedly arranged on the left side of the first clamping piece, and the long screw rod is slidably arranged with the first vertical frame. A second clamping piece is slidably arranged on the outer side of the long screw rod, and the second clamping piece is attached to the outer side of the first vertical frame.

[0009] Preferably, a first positioning ring is fixedly arranged on the outer side of the protective cover, and the first positioning ring is slidably arranged with the towing rope.

[0010] Preferably, a first spring is tightly abutted against the left side of the second clamping piece, and the first spring is sleeved on the outer side of the long screw rod. The other end of the first spring is tightly abutted against a compression nut, and the compression nut is helically arranged with the long screw rod.

[0011] Preferably, a limiting ball is fixedly arranged at the other end of the towing rope. A clamping ball is fixedly arranged on the outer side of the limiting ball, and a pull ring is fixedly arranged on the outer side of the clamping ball.

[0012] Preferably, a second vertical frame is slidably arranged on the outer side of the clamping ball. A slider is fixedly arranged at the bottom end of the second vertical frame. A second base is slidably arranged on the outer side of the slider, and a positioning pin penetrates through the second base.

[0013] Preferably, a horizontal shaft penetrates through the slider, and the horizontal shaft is fixedly arranged with the second base. A second spring is sleeved on the outer side of the horizontal shaft, and the second spring is located between the second base and the slider.

[0014] Compared with the prior art, the beneficial effects of the present utility model are as follows:

[0015] 1. By cooperating the first vertical frame, the second positioning ring and the long screw rod in the positioning assembly of the present utility model, after adjusting the construction height of the towing rope to the surface side piles of the road surface and the roadbed, the long screw rod structure located inside the first vertical frame is moved downward to position the height of the towing rope, and the towing rope is pressed to keep it stably close to the height of the road surface and the roadbed for use, thereby reducing the construction error caused by the positioning deviation of the towing rope.

[0016] 2. By cooperating the second vertical frame with the second spring, the height matching the second positioning ring can be adjusted, and the horizontal traction of the towing rope can be maintained by the push of the second spring, reducing the inclination situation. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 is a schematic diagram of the overall structure of the present utility model;

[0018] Figure 2 is a schematic diagram of the installation structure of the positioning assembly of the present utility model;

[0019] Figure 3 is a schematic diagram of the installation structure of the winding rotating shaft of the present utility model;

[0020] Figure 4 is a schematic diagram of the installation structure of the second base of the present utility model.

[0021] In the figure: 1. First base; 2. First vertical frame;

[0022] 3. Positioning component; 31. Protective cover; 32. Rewinding rotating shaft; 33. Torsion spring; 34. Towing rope; 35. Limit ball; 36. First positioning ring; 37. Second positioning ring; 38. Long screw; 39. First clamping piece; 310. Second clamping piece; 311. Compression nut; 312. First spring

[0023] 4. Second base; 5. Positioning nail; 6. Second vertical frame; 7. Ball catch; 8. Pulling ring; 9. Slide block; 10. Horizontal shaft; 11. Second spring Detailed implementation manner

[0024] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0025] As Figures 1 to 4 shown, the present invention provides a roadbed and pavement construction side pile positioning device, including a first base 1. A first vertical frame 2 is fixedly arranged at the top of the first base 1, and a positioning component 3 is further included at the top of the first vertical frame 2;

[0026] The positioning component 3 includes a protective cover 31 fixedly arranged at the top of the first vertical frame 2. A rewinding rotating shaft 32 is rotatably arranged inside the protective cover 31. A torsion spring 33 is fixedly arranged above the outer side of the rewinding rotating shaft 32, and the other end of the torsion spring 33 is fixedly arranged with the protective cover 31. The rewinding rotating shaft 32 rotates inside the protective cover 31, and cooperates with the torsion spring 33 to drive the rewinding rotating shaft 32 to wind up the towing rope 34 to keep it in a taut state. The towing rope 34 is wound around the outer side of the rewinding rotating shaft 32. A second positioning ring 37 is slidably arranged on the outer side of the towing rope 34. A first clamping piece 39 is fixedly arranged on the left side of the second positioning ring 37. A long screw 38 is fixedly arranged on the left side of the first clamping piece 39, and the long screw 38 is slidably arranged with the first vertical frame 2. A second clamping piece 310 is slidably arranged on the outer side of the long screw 38, and the second clamping piece 310 is attached to the outer side of the first vertical frame 2. The long screw 38 can move up and down inside the first vertical frame 2 to control the descent of the second positioning ring 37.

[0027] Specifically, a first positioning ring 36 is fixedly arranged on the outer side of the protective cover 31, and the first positioning ring 36 is slidably arranged with the towing rope 34. The towing rope 34 moves inside the first positioning ring 36, which can achieve the effect of stable towing.

[0028] Further, a first spring 312 is tightly abutted against the left side of the second clamping piece 310, and the first spring 312 is sleeved outside the long screw 38. The other end of the first spring 312 is tightly abutted against a compression nut 311, and the compression nut 311 is helically arranged with the long screw 38. Rotating the compression nut 311 can push the first spring 312 to push the second clamping piece 310 to be positioned in a state outside the first vertical frame 2.

[0029] Furthermore, a limiting ball 35 is fixedly arranged at the other end of the towing rope 34. A clamping ball 7 is fixedly arranged outside the limiting ball 35, and a pull ring 8 is fixedly arranged outside the clamping ball 7. During the winding process of the towing rope 34, it can be positioned under the bottom opening of the second positioning ring 37 through the limiting ball 35.

[0030] It should be noted that a second vertical frame 6 is slidably arranged outside the clamping ball 7. A slider 9 is fixedly arranged at the bottom end of the second vertical frame 6. A second base 4 is slidably arranged outside the slider 9. A positioning pin 5 penetrates through the inside of the second base 4. The clamping ball 7 can be slid into the inside of the second vertical frame 6, thereby positioning the towing rope 34.

[0031] It should be noted that a horizontal shaft 10 penetrates through the inside of the slider 9, and the horizontal shaft 10 is fixedly arranged with the second base 4. A second spring 11 is sleeved outside the horizontal shaft 10, and the second spring 11 is located between the second base 4 and the slider 9. The second spring 11 can push the slider 9 outside the horizontal shaft 10 to move, pushing the upper second vertical frame 6 for towing and tightening the towing rope 34.

[0032] Among them, the towing rope 34 is a prior art and will not be elaborated; at the same time, the present utility model also includes a power source, a controller, a switch, etc., which are not the main technical points of this patent and will not be elaborated.

[0033] Working principle and process:

[0034] The construction workers move the positioning component 3 to the construction road surface. According to the route of the construction of the roadside piles on the road surface, first place the first base 1 at the starting point on the ground, and then tow and place the second base 4 at the end point of the roadside pile construction. Move the towing ring 8, drive the clamping ball 7 and the towing rope 34 to pull out from the outside of the winding shaft 32. After the torsion spring 33 on the outside of the winding shaft 32 rotates and opens, the towing rope 34 can be pulled out of the protective cover 31. Place the clamping ball 7 outside the limiting ball 35 of the towing rope 34 into the vertical groove of the second vertical frame 6 to position the clamping ball 7. Cooperate with the slider 9 at the bottom of the second vertical frame 6 inside the second base 4, and push through the horizontal shaft 10 and the spring two 11 on the outside to tighten the second vertical frame 6 and the towing rope 34 between the first vertical frame 2 and the second vertical frame 6 to maintain the stability of the positioning. At the same time, when the road surface height is not level enough, when the towing rope 34 needs to be moved up to a high point position, the long screw 38 can be pulled to rise along the vertical groove of the first vertical frame 2. Through the elastic pressing state of the spring one 312, it can cooperate with the clip one 39 and the clip two 310 on the outside of the long screw 38 to maintain the stability after the lifting height. After moving to the required height, tighten the pressing nut 311 structure to maintain the stable clamping state of the clip one 39, which is more stable to use. The excess towing rope 34 enters the protective cover 31 through the positioning ring one 36, and is towed and wound by the winding shaft 32 and the torsion spring 33 to store the excess towing rope 34 inside the protective cover 31, and always maintain the tension state of the towing rope 34 to maintain the stability of the positioning.

[0035] It should be noted that in this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variant thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements not only includes those elements, but also includes other elements not expressly listed, or also includes elements inherent to such process, method, article or device.

[0036] Although the embodiments of the present invention have been shown and described, those of ordinary skill in the art can understand that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principle and spirit of the present invention. The scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A roadbed and pavement construction side pile positioning device, comprising a base (1), characterized in that: A stand frame (2) is fixedly disposed on the top of the base frame (1), and a positioning assembly (3) is also provided on the top of the stand frame (2); The positioning assembly (3) includes a protective cover (31) fixedly arranged at the top of the vertical frame (2), a winding shaft (32) rotatably arranged inside the protective cover (31), a torsion spring (33) fixedly arranged on the upper outer side of the winding shaft (32), and the other end of the torsion spring (33) is fixedly arranged on the protective cover (31), a traction rope (34) is wound around the outer side of the winding shaft (32), a positioning ring (37) is slidably arranged on the outer side of the traction rope (34), a clamping piece (39) is fixedly arranged on the left side of the positioning ring (37), a long screw (38) is fixedly arranged on the left side of the clamping piece (39), and the long screw (38) is slidably arranged with the vertical frame (2), a clamping piece (310) is slidably arranged on the outer side of the long screw (38), and the clamping piece (310) is fitted with the outer side of the vertical frame (2).

2. A roadbed and pavement construction side pile positioning device according to claim 1, characterized in that: A positioning ring (36) is fixedly arranged on the outer side of the protective cover (31), and the positioning ring (36) and the traction rope (34) are slidably arranged.

3. A roadbed and pavement construction side pile positioning device according to claim 1, characterized in that: A spring (312) is tightly arranged on the left side of the second clamp (310), and the spring (312) is sleeved on the outside of the long screw (38). A clamping nut (311) is tightly arranged on the other end of the spring (312), and the clamping nut (311) and the long screw (38) are spirally arranged.

4. A roadbed and pavement construction side pile positioning device according to claim 1, characterized in that: A limiting ball (35) is fixedly arranged at the other end of the traction rope (34), a locking ball (7) is fixedly arranged on the outer side of the limiting ball (35), and a pull ring (8) is fixedly arranged on the outer side of the locking ball (7).

5. A roadbed and pavement construction side pile positioning device according to claim 4, characterized in that: A second stand (6) is slidably disposed on the outer side of the clamping ball (7), a slider (9) is fixedly disposed at the bottom end of the second stand (6), a second base (4) is slidably disposed on the outer side of the slider (9), and a positioning pin (5) is penetrated inside the second base (4).

6. A roadbed and pavement construction side pile positioning device according to claim 5, characterized in that: A transverse axis (10) passes through the interior of the slider (9), and the transverse axis (10) is fixedly arranged with the second base (4). A second spring (11) is sleeved on the outer side of the transverse axis (10), and the second spring (11) is located between the second base (4) and the slider (9).

Citation Information

Patent Citations

  • Side pile positioning device for roadbed and pavement construction

    CN217629312U