Advanced drilling machine device of shield tunneling machine
By designing the fixed structure of the support device and the advance drilling rig on the shield machine, the advance drilling rig is easily installed in the tunnel, solving the problems of long transportation distance and difficult installation, and improving work efficiency and safety.
Patent Information
- Application Number
- CN202422597248.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-28
- Publication Date
- 2025-07-25
- Estimated Expiration
- 2034-10-28
AI Technical Summary
When the existing shield machine is excavated, the advance drilling rig is generally placed outside the tunnel, and is transported from outside the tunnel to install in the tunnel when used. The space inside the tunnel is small, the transportation distance is long, the installation is difficult and time-consuming.
A shield machine advance drilling rig device is designed, including a support device and a forward drilling rig. The forward drilling rig is fixed on the connecting bridge by using the fixed block of the support frame of the drilling rig, and moves the bottom wheel on the support device to achieve the conversion of working and standby positions.
It solves the problems of long transportation distance and difficult installation of the advance drilling rig, improves work efficiency and safety, and ensures that the normal excavation of the shield machine is not affected.
Smart Images

Figure CN223152058U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of shield machines, in particular to an advance drilling device for a shield machine. Background Art
[0002] The shield machine, whose full name is shield tunnel boring machine, is a special engineering machinery for tunnel excavation. Modern shield tunnel boring machines integrate optical, mechanical, electrical, hydraulic, sensor and information technology. They have the functions of excavating and cutting soil, transporting soil and ballast, assembling tunnel lining, measuring and guiding deviation correction, etc., and are highly reliable. The advance drill is an important part of the shield machine. When the shield machine advances forward, it encounters complex formations such as cavities, water bodies, rock fracture zones or rock burst formations. The advance drill can conduct advance drilling to explore the geological conditions ahead and determine whether there are geological disasters. If there are disasters, the advance drill will conduct advance grouting and carry out geological reinforcement treatment, and the shield machine will continue to advance the tunnel.
[0003] At present, when the shield machine is excavating, the advance drill is generally placed outside the tunnel. When the advance drill is used, it is transported from outside the tunnel to the installation position for installation inside the tunnel. The space inside the tunnel is small, the transportation distance is long, the installation is difficult, and it takes a long time.
[0004] Therefore, the present invention provides a shield machine advance drilling device to solve the above problems. Utility Model Content
[0005] The technical problem to be solved by the utility model is that when the existing shield machine is excavating, the advance drilling rig is generally placed outside the tunnel. When the advance drilling rig is used, it is transported from outside the tunnel to the installation position for installation in the tunnel. The space in the tunnel is small, the transportation distance is long, the installation is difficult, and it takes a long time.
[0006] The utility model provides the following technical solutions: a shield machine advance drilling device, comprising a supporting device and an advance drilling rig, wherein the supporting device is installed on the shield machine, and the supporting device is used to fix the advance drilling rig on a connecting bridge by using a fixing block of a drilling rig fixing support frame, and when the advance drilling rig is used, the advance drilling rig is transported to a working position for work; the advance drilling rig is installed on the supporting device, and the advance drilling rig is used to move on the supporting device through wheels at its bottom, thereby realizing position conversion during work and standby.
[0007] Preferably, the supporting device comprises a drilling rig working support frame, a detachable track and a drilling rig fixed support frame, the drilling rig working support frame is fixed on the shield machine, the detachable track is installed at one end of the drilling rig working support frame, and the drilling rig fixed support frame is installed at one end of the detachable track.
[0008] Preferably, the working support frame of the drilling rig is a frame structure, with working tracks for walking on both sides, and the working tracks communicate with the detachable connection tracks.
[0009] Preferably, the fixed support frame of the drilling rig is a frame structure, with a fixed track on the upper part connected to the detachable connection track, and fixing blocks are arranged on both sides at the same time, and the fixing blocks can fix the advanced drilling rig.
[0010] Preferably, wheels are arranged on both sides of the lower part of the advanced drilling rig, a front arm and a rear arm are arranged in the middle of the lower part, and a pin shaft and a shear pin are arranged at the bottom at the same time; when the front arm and the rear arm move the advanced drilling rig onto the working support frame of the drilling rig, they are connected to the frame of the working support frame of the drilling rig through the pin shaft, and the axial working angle of the advanced drilling rig is adjusted and locked with the shear pin.
[0011] The beneficial effects of the present utility model are as follows:
[0012] 1. The present utility model provides an advanced drilling rig device for a shield machine. When the shield machine is tunneling, the advanced drilling rig is fixed on the connection bridge by the fixing blocks of the fixed support frame of the drilling rig. When using the advanced drill, the advanced drilling rig is transported to the working position, solving the problems of long transportation distance and high installation difficulty of the advanced drilling rig, with higher safety and reliability, and effectively improving the working efficiency of the advanced drilling rig.
[0013] 2. The present utility model provides an advanced drilling rig device for a shield machine. After the advanced drilling rig finishes working, the advanced drilling rig retreats to the fixed support frame of the drilling rig for fixation, and the working support frame of the drilling rig and the detachable connection track can be removed, which not only does not affect the normal tunneling of the shield machine, but also makes the working efficiency of the advanced drilling rig higher. Description of the Drawings
[0014] In order to more clearly illustrate the specific embodiments of the present utility model or the technical solutions in the prior art, the following will briefly introduce the drawings required to be used in the description of the specific embodiments or the prior art. Obviously, the drawings in the following description are some embodiments of the present utility model. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative efforts.
[0015] Figure 1 It is the overall structure diagram of the present utility model;
[0016] Figure 2 It is the top view of the structure of the working support frame of the drilling rig of the present utility model;
[0017] Figure 3 It is the structure diagram of the fixed support frame of the drilling rig of the present utility model;
[0018] Figure 4 It is the structure diagram of the advanced drilling rig of the present utility model;
[0019] Figure 5 This is the sectional view of the advanced drill of the present utility model;
[0020] Figure 6 This is the schematic diagram of adjusting the working angle of the advanced drill of the present utility model.
[0021] In the figure: 1. Support device; 11. Drill working support frame; 111. Working track; 12. Demountable track; 13. Drill fixing support frame; 131. Fixing track; 132. Fixing block; 2. Advanced drill; 21. Wheels; 22. Forearm; 23. Rear arm; 24. Pin shaft; 25. Shear pin. Specific embodiments
[0022] To make the objectives, technical solutions and advantages of the embodiments of the present utility model clearer, the technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings. Apparently, the described embodiments are some but not all of the embodiments of the present utility model. Therefore, the detailed description of the embodiments of the present utility model below is not intended to limit the scope of the claimed present utility model, but merely represents some embodiments of the present utility model. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present utility model without creative efforts shall fall within the scope of protection of the present utility model.
[0023] It should be noted that like reference numerals and letters denote like items in the following drawings. Therefore, once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings.
[0024] In the description of the present utility model, it should be noted that the orientation or positional relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", "rear", etc. is based on the orientation or positional relationship shown in the drawings, or the orientation or positional relationship in which the inventive product is customarily placed during use. Such terms are only for the convenience of describing the present utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present utility model.
[0025] It should also be noted that in the description of the present utility model, unless otherwise clearly specified and defined, the terms "set", "installed", "connected", and "coupled" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium, and it can be the communication inside two components. For those skilled in the art, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.
[0026] The embodiments of the present disclosure aim to solve the problems that when the existing shield machine is tunneling, the advanced drill is generally placed outside the tunnel. When the advanced drill is used, it is transported from outside the tunnel to the installation position inside the tunnel for installation. The space inside the tunnel is narrow, the transportation distance is long, the installation difficulty is large, and it takes a long time. In view of this, the embodiments of the present disclosure propose a shield machine advanced drill device. By adopting a new shield machine advanced drill device, when the shield machine is tunneling, the advanced drill is fixed on the connecting bridge by the fixing block of the drill fixing support frame, and when the advanced drill is used, the advanced drill is transported to the working position, solving the problems of long transportation distance and large installation difficulty of the advanced drill, with higher safety and reliability, and effectively improving the working efficiency of the advanced drill.
[0027] As Figures 1 to 6 shown, a shield machine advanced drill device includes a support device 1 and an advanced drill 2. The support device 1 is installed on the shield machine. The support device 1 is used to fix the advanced drill 2 on the connecting bridge by the fixing block 132 of the drill fixing support frame 13. When the advanced drill 2 is used, the advanced drill 2 is transported to the working position for work. The advanced drill 2 is installed on the support device 1. The advanced drill 2 is used to move on the support device 1 through its bottom wheels 21, so as to realize the position conversion during work and standby.
[0028] By adopting the above support device 1 and advanced drill 2, when the shield machine is tunneling, the advanced drill 2 is fixed on the connecting bridge by the fixing block 132 of the drill fixing support frame 13. When the advanced drill 2 is used, the advanced drill 2 is transported to the working position, solving the problems of long transportation distance and large installation difficulty of the advanced drill 2, with higher safety and reliability, and effectively improving the working efficiency of the advanced drill 2. After the advanced drill 2 finishes working, the advanced drill 2 retreats to be fixed on the drill fixing support frame 13, and the drill working support frame 11 and the detachable connecting track can be removed, which not only does not affect the normal tunneling of the shield machine, but also makes the working efficiency of the advanced drill 2 higher.
[0029] As Figures 1 to 3As shown in the figure, the support device 1 includes a drilling rig working support frame 11, a detachable track 12, and a drilling rig fixed support frame 13. The drilling rig working support frame 11 is fixed on the shield machine. One end of the drilling rig working support frame 11 is equipped with the detachable track 12, and one end of the detachable track 12 is equipped with the drilling rig fixed support frame 13. The detachable connection track is installed before the advanced drilling rig 2 works. One end is connected to the track of the drilling rig working support frame 11, and the other end is connected to the track of the drilling rig fixed support frame 13, serving as the track for the advanced drilling rig 2 to be transported between the drilling rig working support frame 11 and the drilling rig fixed support frame 13. After the advanced drilling rig 2 completes the work and returns to the drilling rig fixed support frame 13 and is fixed, it is removed.
[0030] Through the design of the support device 1, when the advanced drilling rig 2 is not working, the advanced drilling rig 2 is fixed on the drilling rig fixed support frame 13, and the support device 1 can effectively support the advanced drilling rig 2. When the advanced drilling rig 2 is working, the drilling rig working support frame 11 and the detachable connection track are installed, the fixing block 132 on the drilling rig fixed support frame 13 is opened, and the advanced drilling rig 2 is transported from the drilling rig fixed support frame 13 along the track to the drilling rig working support frame 11 by using the traction device, and the advanced drilling rig 2 is connected to the drilling rig working support frame 11 through the pin shaft 24.
[0031] Therefore, through the above support device 1, when the shield machine is tunneling, the advanced drilling rig 2 is fixed on the connecting bridge by using the fixing block 132 of the drilling rig fixed support frame 13. When using the advanced drill, the advanced drilling rig 2 is transported to the working position again, solving the problems of long transportation distance and large installation difficulty of the advanced drilling rig 2, with higher safety and reliability, and effectively improving the working efficiency of the advanced drilling rig 2.
[0032] As Figure 2 shown in the figure, the drilling rig working support frame 11 is a frame structure, with working tracks 111 for walking on both sides, and the working tracks 111 are connected to the detachable connection track; there are tracks for walking on both sides of the drilling rig working support frame 11, the tracks are connected to the detachable connection track, and the tracks are of a sharp-corner structure to prevent movement deviation.
[0033] As Figure 3 shown in the figure, the drilling rig fixed support frame 13 is a frame structure, with a fixed track 131 on the upper part connected to the detachable connection track, and fixing blocks 132 are arranged on both sides at the same time. The fixing blocks 132 can fix the advanced drilling rig 2; when the advanced drilling rig 2 is not working, the fixing blocks 132 fix the advanced drilling rig 2 on the drilling rig fixed support frame 13 to prevent the advanced drilling rig 2 from moving during the tunneling of the shield machine; by adopting the above drilling rig fixed support frame 13, the advanced drilling rig 2 can be retracted and removed after being fixed on the drilling rig fixed support frame 13 when it is not working.
[0034] As Figure 5 and Figure 6As shown in the figure, wheels 21 are provided on both sides of the lower part of the advanced drill 2, a front arm 22 and a rear arm 23 are provided in the middle of the lower part, and a pin shaft 24 and a shear pin 25 are provided at the bottom. When the front arm 22 and the rear arm 23 move the advanced drill 2 onto the drill working support frame 11, they are connected to the frame of the drill working support frame 11 through the pin shaft 24 to adjust the axial working angle of the advanced drill 2 and lock it with the shear pin 25.
[0035] The overall working process is as follows: When the shield machine advances forward, the advanced drill 2 does not work and is fixed on the drill fixed support frame 13. When the advanced drill 2 needs to work, the shield machine stops advancing, the drill working support frame 11 and the detachable connecting track are installed, the fixing block 132 on the drill fixed support frame 13 is opened, and the advanced drill 2 is transported from the drill fixed support frame 13 to the drill working support frame 11 along the track by using the traction device. The advanced drill 2 is connected to the drill working support frame 11 through the pin shaft 24. The traction device adjusts the axial angle of the advanced drill 2, and the segment erector rotates to adjust the radial angle. After the angles are adjusted, the shear pin 25 is locked, and the advanced drill 2 starts to work. After the advanced drill 2 finishes working, it is transported back to the drill fixed support frame 13 by the traction device and fixed on the drill fixed support frame 13. The drill working support frame 11 and the detachable connecting track are removed, and the shield machine can normally advance forward. This structure solves the disadvantages of small installation space and difficult installation of the advanced drill 2, and long installation time, and improves the working efficiency of the advanced drill 2.
[0036] Those skilled in the art should understand that the present invention is not limited by the above embodiments. What is described in the above embodiments and the specification only illustrates the principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention will have various changes and improvements, and these changes and improvements all fall within the scope of the present invention claimed. The scope of protection claimed by the present invention is defined by the appended claims and their equivalents.
Claims
1. A shield machine advanced drilling rig device, characterized in that, It includes a support device (1) and an advanced drill (2). The support device (1) is installed on the shield machine. The support device (1) is used to fix the advanced drill (2) on the connecting bridge by using the fixing block (132) of the drill support frame (13) with a drill. When using the advanced drill (2), the advanced drill (2) is transported to the working position for work. The advanced drill (2) is installed on the support device (1). The advanced drill (2) is used to move on the support device (1) through its bottom wheels (21), so as to realize the position conversion during work and standby.
2. The advanced drilling rig device of a shield machine according to claim 1, characterized in that: The support device (1) includes a drill working support frame (11), a detachable track (12) and a drill fixing support frame (13). The drill working support frame (11) is fixed on the shield machine. One end of the drill working support frame (11) is provided with the detachable track (12). One end of the detachable track (12) is provided with the drill fixing support frame (13).
3. The advanced drilling rig device of a shield machine according to claim 2, characterized in that: The drill working support frame (11) is a frame structure, with working tracks (111) for walking on both sides. The working tracks (111) are communicated with the detachable connecting track.
4. The advanced drilling rig device of a shield machine according to claim 3, characterized in that: The drill fixing support frame (13) is a frame structure, with a fixing track (131) on the upper part connected to the detachable connecting track. At the same time, fixing blocks (132) are arranged on both sides. The fixing blocks (132) can fix the advanced drill (2).
5. The advanced drilling rig device of a shield machine according to claim 4, characterized in that: Wheels (21) are arranged on both sides of the lower part of the advanced drill (2), a front arm (22) and a rear arm (23) are arranged in the middle of the lower part. At the same time, a pin shaft (24) and a shear pin (25) are arranged at the bottom. When the advanced drill (2) moves to the drill working support frame (11), the front arm (22) and the rear arm (23) are connected to the frame of the drill working support frame (11) through the pin shaft (24) to adjust the axial working angle of the advanced drill (2) and lock it with the shear pin (25).