Building engineering material hoister
By introducing the design of detachable connection and adjustment rods into the construction project material elevator, the problem of interference between the hoisting arm and the building roof is solved, and the hoisting arm is assembled indoors and angle adjustment is realized, which improves the convenience and safety of construction.
Patent Information
- Application Number
- CN202422792298.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-08-22
- Estimated Expiration
- 2034-11-15
AI Technical Summary
When existing construction project material elevators are installed on site, the lifting arms are prone to interfere with the roof of the building, resulting in inconvenient operation and complex assembly.
A construction engineering material elevator is designed, including a placement rack, a vertical pole, a fixing rack and a lifting arm. Through the arrangement of removable connection and adjustment rods, the lifting arm is allowed to be assembled indoors and adjust the angle according to the building structure to avoid interference with the roof.
The assembly of the hoisting arm is achieved indoors, simplified the operation process, avoid interference between the hoisting arm and the building, and improve the convenience and safety of construction.
Smart Images

Figure CN223254759U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction equipment, and in particular relates to a building material hoist. Background Art
[0002] During the construction of high-rise buildings, materials need to be transported to higher floors. Currently, hoists are typically used to lift materials onto the structure. To use the hoist, it must be set up on the floor where the materials are needed. However, when setting up the hoist on-site, the hoist arm must be extended to the exterior of the building to lift the materials. However, the hoist arm on most hoists currently has a fixed tilt angle and height. Due to the layout of the on-site buildings, the hoist arm can easily interfere with the roof during indoor assembly. Therefore, the arm must be extended to the exterior of the building before assembly. This makes hoist operation inconvenient during on-site installation. Utility Model Content
[0003] The embodiment of the utility model provides a construction material hoist, which aims to solve the problem that the existing construction material hoists are complicated to operate and inconvenient to assemble during on-site construction.
[0004] To achieve the above-mentioned purpose, the technical solution adopted by the present invention is to provide a construction material hoist, comprising:
[0005] Placement rack;
[0006] A vertical pole is detachably mounted on the placement rack, and the length direction of the vertical pole is arranged along the vertical direction;
[0007] A fixing frame, detachably mounted on the top of the vertical pole;
[0008] A lifting arm, one end of which is fixedly connected to a support arm, a connection between the lifting arm and the support arm being hingedly provided on the fixing frame, an end of the lifting arm being rotatably provided with a guide wheel away from the support arm, and an axis of a hinge shaft of the lifting arm on the fixing frame being defined as a first direction;
[0009] An adjusting rod, one end of which is hingedly disposed on the support arm, wherein the axis of the rotating shaft of the adjusting rod on the support arm is arranged along the first direction, and a connecting sleeve for connecting the adjusting rod is further rotatably disposed on the fixing frame;
[0010] There are two limiting members, which are threadedly connected to the adjusting rod and are respectively located at two ends of the connecting sleeve;
[0011] A winch is installed on the placement rack, and a steel wire rope on the winch is wound around the outer side of the guide wheel for hoisting materials.
[0012] In a possible implementation, there are two adjustment rods, and the two adjustment rods are respectively located on both sides of the support arm along the first direction.
[0013] In a possible implementation, a rotating rod is rotatably provided on the fixing frame, an axis of the rotating rod is arranged along a first direction, and the connecting sleeves are installed at both ends of the rotating rod.
[0014] In a possible implementation, a guide rope pulley for guiding the winch wire rope is rotatably provided at one end of the support arm away from the hoisting arm and at the top of the fixing frame.
[0015] In one possible implementation, a first flange is fixedly mounted on the bottom of the fixing frame, a guide column is fixedly mounted on the bottom of the first flange, a second flange detachably connected to the first flange is mounted on the top of the vertical pole, and a guide hole that slides with the guide column is also provided on the top of the vertical pole.
[0016] In one possible implementation, guide sleeves are fixedly installed on both sides of the placement rack along the first direction, the axis of the guide sleeve is arranged perpendicular to the first direction, and an extension rod is slidably arranged inside the guide sleeve, the extension rod can be moved to the outside of the placement rack, and the guide sleeve is also threadedly connected to a tightening member for fixing the extension rod to the inside of the guide sleeve.
[0017] In a possible implementation, an extension rod is provided on one side of the placement rack close to the lifting arm for sliding along the first direction. There are two extension rods, and the two extension rods can slide out of both sides of the placement rack along the first direction.
[0018] In a possible implementation, opposite ends of the two extension rods are detachably connected, and a limiting plate for clamping between the two extension rods is installed in the middle of the placement rack.
[0019] Compared with the prior art, the solution shown in the embodiment of the present application is provided with a placement frame, a winch is fixedly mounted on the top of the placement frame, and a vertical pole is detachably mounted on one side of the winch via bolts. A fixing frame is detachably mounted on the top of the vertical pole. A lifting arm is hingedly mounted on the fixing frame, and one end of the lifting arm provided with a hinged shaft is fixedly connected to a support arm. The support arm and the fixing frame are connected by an adjustment rod. The length direction of the adjustment rod is set perpendicular to the first direction, and the other end of the adjustment rod is slidably set inside the connecting sleeve. The relative position of the adjustment rod and the connecting sleeve is limited by two threaded limiters. In the present application, when setting up the hoist, the lifting arm can be installed on the placement frame via the vertical pole and the fixing frame. The placement frame is then moved to extend the lifting arm to the outside of the building. The inclination angle of the lifting arm can be adjusted by adjusting the position of the limiter on the adjustment rod according to the structure of the building. The assembly of the lifting arm can be completed indoors or on a building, which is convenient for supporting and assisting the installation of the lifting arm. Finally, when one end of the lifting arm moves to the outside of the wall, the angle of the lifting arm can be adjusted to meet the on-site construction requirements without being affected by the roof and wall of the building. It has a simple structure and is easy to operate. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A schematic structural diagram of a construction material hoist provided by an embodiment of the present utility model;
[0021] Figure 2 A schematic diagram of the installation structure of the fixing bracket provided in an embodiment of the present utility model;
[0022] Figure 3 This is a schematic structural diagram of a placement rack provided in an embodiment of the present utility model.
[0023] Description of reference numerals:
[0024] 1. Placement frame; 2. Vertical pole; 21. Second flange; 3. Fixed frame; 31. Guide rope pulley; 32. First flange; 321. Guide column; 4. Lifting arm; 41. Support arm; 42. Guide wheel; 5. Adjusting rod; 51. Connecting sleeve; 511. Rotating rod; 52. Limiting piece; 6. Winch; 7. Guide sleeve; 71. Clamping piece; 8. Extension rod; 9. Extension rod; 91. Limiting plate. DETAILED DESCRIPTION
[0025] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0026] Please also refer to Figures 1 to 3The construction material hoist provided by the present invention is now described. The construction material hoist comprises a placement frame 1, a vertical pole 2, a fixing frame 3, and a hoisting arm 4. The vertical pole 2 can be detachably mounted on the placement frame 1, and the length direction of the vertical pole 2 is set along the vertical direction; the fixing frame 3 can be detachably mounted on the top of the vertical pole 2; one end of the lifting arm 4 is fixedly connected to the support arm 41, and the connection between the lifting arm 4 and the support arm 41 is hingedly set on the fixing frame 3, and the end of the lifting arm 4 away from the support arm 41 is rotatably set with a guide wheel 42, and the axis of the hinge axis of the lifting arm 4 on the fixing frame 3 is defined as the first direction; one end of the adjusting rod 5 is hingedly set on the support arm 41, and the axis of the rotating shaft of the adjusting rod 5 on the support arm 41 is set along the first direction, and a connecting sleeve 51 for connecting the adjusting rod 5 is also rotatably set on the fixing frame 3; there are two limit members 52, and the two limit members 52 are threadedly connected to the adjusting rod 5, and the two limit members 52 are respectively located at both ends of the connecting sleeve 51; the winch 6 is installed on the placement frame 1, and the wire rope on the winch 6 is wound around the outside of the guide wheel 42 for lifting materials.
[0027] Compared to the prior art, the construction material hoist provided in this embodiment comprises a support frame 1, a winch 6 fixedly mounted on the top of the support frame 1, a vertical pole 2 detachably mounted on one side of the winch 6 via bolts, a fixing frame 3 detachably mounted on the top of the vertical pole 2, a hoisting arm 4 hingedly mounted on the fixing frame 3, one end of the hoisting arm 4, provided with a hinged axis, fixedly connected to a support arm 41. The support arm 41 and the fixing frame 3 are connected by an adjustment rod 5. The length of the adjustment rod 5 is arranged perpendicular to the first direction, and the other end of the adjustment rod 5 is slidably mounted within a connecting sleeve 51. The relative position of the adjustment rod 5 and the connecting sleeve 51 is limited by two threaded limiters 52. In this application, when setting up the hoist, the hoisting arm 4 can be mounted on the support frame 1 via the vertical pole 2 and the fixing frame 3. The support arm 4 can then be extended to the outside of the building by moving the support arm 4. The inclination angle of the hoisting arm 4 can be adjusted by adjusting the position of the limiter 52 on the adjustment rod 5 according to the structure of the building. The assembly of the lifting arm 4 can be completed indoors or on a building, which is convenient for supporting and assisting the installation of the lifting arm 4. Finally, when one end of the lifting arm 4 moves to the outside of the wall, the angle of the lifting arm 4 is adjusted to meet the on-site construction requirements without being affected by the roof and wall of the building. The structure is simple and the operation is convenient.
[0028] Specifically, in this embodiment, the winch 6 is of existing technology, and the specific structure is not further described here.
[0029] In some embodiments, the adjusting rod 5 can be Figure 2 See the structure shown. Figure 2There are two adjustment rods 5, one located on either side of the support arm 41 along the first direction. An adjustment rod 5 is hingedly mounted on both sides of the support arm 41 along the first direction. Connecting sleeves 51 corresponding to the connecting rods are rotatably mounted on both sides of the fixing frame 3. The two adjustment rods 5 are slidably mounted within the connecting sleeves 51. Two stoppers 52 are threadedly mounted on each adjustment rod 5. The provision of two adjustment rods 5 enhances the support strength of the support arm 41, ensuring the safety of the hoist during use.
[0030] In some embodiments, the connecting sleeve 51 may be Figure 2 See the structure shown. Figure 2 A rotating rod 511 is rotatably mounted on the fixed frame 3. The axis of the rotating rod 511 is arranged along the first direction, and connecting sleeves 51 are mounted on both ends of the rotating rod 511. The middle portion of the rotating rod 511 is rotatably mounted on the fixed frame 3, and the ends of the rotating rod 511 extend beyond the fixed frame 3 along the first direction. Connecting sleeves 51 are fixedly mounted on both sides of the rotating rod 511, and the axes of the connecting sleeves 51 at both ends of the rotating rod 511 are arranged parallel to each other. This facilitates adjustment of the relative positions of the two adjustment rods 5.
[0031] Specifically, in this embodiment, the connecting sleeve 51 and the rotating rod 511 are integrally formed, and the axis of the connecting sleeve 51 and the axis of the rotating rod 511 are perpendicular to each other. The rotating rod 511 is rotatably mounted on the fixing frame 3 around its axis.
[0032] In some embodiments, the support arm 41 may be configured as follows: Figure 1 、 Figure 2 See also Figure 1 、 Figure 2 The end of the support arm 41 away from the hoisting arm 4 and the top of the fixed frame 3 are both rotatably provided with a guide pulley 31 for guiding the wire rope of the hoist 6. The guide pulleys 31 are rotatably provided at the ends of the support arm 41 and the fixed frame 3. The axes of the two guide pulleys 31 are both arranged along the first direction. The wire rope on the hoist 6 is sequentially overlapped on the guide pulley 42 on the support arm 41 from the hoist 6, and then transported to the guide pulley 31 on the fixed frame 3, and finally transported to the guide pulley 42 at the end of the hoisting arm 4. It extends downward under the guidance of the guide pulley 42 to hoist the material. It can effectively guide the wire rope on the hoist 6. At the same time, the guide pulleys 31 installed on the support arm 41 and the fixed frame 3 can improve the support effect of the wire rope during the material hoisting process.
[0033] In some embodiments, the fixing frame 3 may be configured as follows: Figure 1 、 Figure 2 See also Figure 1 、 Figure 2The bottom of the fixing frame 3 is fixedly mounted with a first flange 32, the bottom of the first flange 32 is fixedly mounted with a guide column 321, the top of the vertical pole 2 is mounted with a second flange 21 that is detachably connected to the first flange 32, and the top of the vertical pole 2 is also provided with a guide hole that slidably cooperates with the guide column 321. The first flange 32 is fixedly mounted on the bottom of the fixing frame 3, and the guide column 321 is fixedly mounted on the first flange 32. The guide column 321 is coaxially arranged with the first flange 32. When the fixing frame 3 is mounted on the vertical pole 2, the guide column 321 on the fixing frame 3 is slid into the guide hole, and the fixing frame 3 can be mounted on the vertical pole 2 through the connection between the first flange 32 and the second flange 21. The structure is simple and the operation is convenient.
[0034] Preferably, in this embodiment, the guide post 321 is rotatably mounted within the guide hole. The first flange 32 is provided with an oblong hole for connection to the second flange 21. The length of the oblong hole extends along the circumference of the first flange 32. When installing the fixing bracket 3, the extension direction of the suspension arm 4 can be adjusted by rotating the fixing bracket 3. This provides a simple structure and easy operation.
[0035] In some embodiments, the above-mentioned placement rack 1 can be used as follows Figure 1 、 Figure 3 See also Figure 1 、 Figure 3 , guide sleeves 7 are fixedly installed on both sides of the placement frame 1 along the first direction, the axis of the guide sleeve 7 is set perpendicular to the first direction, and an extension rod 8 is slidably set inside the guide sleeve 7, the extension rod 8 can be moved to the outside of the placement frame 1, and the guide sleeve 7 is also threadedly connected with a tightening member 71 for fixing the extension rod 8 to the inside of the guide sleeve 7. When the lifting arm 4 is installed on the fixed frame 3, the lifting arm 4 is extended to the outside of one side of the placement frame 1. The extension rod 8 can slide out from the placement frame 1 in the direction away from the side extending from the lifting arm 4. When in use, the extension rod 8 can be extended out of the placement frame 1 according to the size of the on-site erection site, and a gravity object can be used to press on the top of the extension rod 8, thereby fixing the extension rod 8 and further preventing the placement frame 1 from tipping over.
[0036] Specifically, in this embodiment, two guide sleeves 7 are provided on a single side of the placement rack 1. The two guide sleeves 7 are provided along the length direction of the extension rod 8. When the extension rod 8 is stored in the placement rack 1, the extension rod 8 is located inside the two guide sleeves 7 and is fixed to the two guide sleeves 7 by the tightening member 71. When the extension rod 8 is extended out of the placement rack 1, the extension rod 8 is located on a single guide sleeve 7 and is fixed to the single guide sleeve 7 by the tightening member 71.
[0037] Preferably, in this embodiment, a material receiving plate is fixedly connected between the two extension rods 8, and the two extension rods 8 can be fixed by placing a gravity object on the material receiving plate to prevent the placement rack 1 from tipping over when lifting materials.
[0038] In some embodiments, the above-mentioned placement rack 1 can be used as follows Figure 1 、 Figure 3 See also Figure 1 、 Figure 3 Extension rods 9 are provided on one side of the rack 1 near the lifting arm 4, allowing it to slide along the first direction. Two extension rods 9 are provided, each of which can slide out from either side of the rack 1 along the first direction. The extension rods 9 are arranged perpendicular to the extension rod 8 and are located on the side where the lifting arm 4 extends from the rack 1. The two extension rods 9 can slide out from either side of the rack 1 along the first direction, thereby increasing the width of the rack 1. Furthermore, heavy objects can be placed on the extension rods 9, enhancing the stability of the rack 1.
[0039] Specifically, in this embodiment, when setting up the placement rack 1, the extension rod 8 and the extension rod 9 can be pulled out from the inside of the placement rack 1 and compressed by gravity. During transportation, the extension rod 8 and the extension rod 9 can be stored on the placement rack 1 to reduce the space occupied by the placement rack 1.
[0040] Specifically, in this embodiment, the weight object is a sandbag or a large waste concrete block.
[0041] In some embodiments, the extension rod 9 may be Figure 1 、 Figure 3 See also Figure 1 、 Figure 3 The opposite ends of the two extension rods 9 are detachably connected, and a limiting plate 91 for clamping between the two extension rods 9 is installed in the middle of the placement rack 1. A connecting portion is fixedly installed at the opposite ends of the two extension rods 9. The connecting portion is arranged along the radial direction of the extension rods 9, and the connecting portions on the two extension rods 9 are correspondingly provided with through holes, and the two connecting portions can be connected together by bolts and nuts. A limiting portion is also fixedly installed on the placement rack 1. When the two extension rods 9 are accommodated in the placement rack 1 and connected together, the ends of the extension rods 9 rest against the limiting plate 91, so that the two extension rods 9 can be fixed to the placement rack 1 through the limiting plate 91, bolts and nuts.
[0042] Preferably, in this embodiment, a mounting sleeve is fixedly mounted on the placement rack 1 and fits over the outside of the extension rod 9. When the extension rod 9 abuts against the stop plate 91, the extension rod 9 is located within the mounting sleeve. Furthermore, an end plate is fixedly mounted on the end of the extension rod 9 near the stop plate 91 to prevent the extension rod 9 from sliding out of the mounting sleeve. The outer edge of the end plate protrudes beyond the outer wall of the extension rod 9.
[0043] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A construction material hoist, characterized in that: include: Placement rack (1); A vertical pole (2) is detachably mounted on the placement rack (1), and the length direction of the vertical pole (2) is arranged along the vertical direction; A fixing frame (3) is detachably mounted on the top of the vertical pole (2); A hoisting arm (4), one end of the hoisting arm (4) is fixedly connected to a support arm (41), a connection between the hoisting arm (4) and the support arm (41) is hingedly arranged on the fixing frame (3), an end of the hoisting arm (4) away from the support arm (41) is rotatably provided with a guide wheel (42), and an axis of a hinge shaft of the hoisting arm (4) on the fixing frame (3) is defined as a first direction; An adjusting rod (5) is hingedly mounted at one end on the support arm (41), the axis of the rotating shaft of the adjusting rod (5) on the support arm (41) is arranged along a first direction, and a connecting sleeve (51) for connecting the adjusting rod (5) is rotatably mounted on the fixing frame (3); There are two limiting members (52), the two limiting members (52) are threadedly connected to the adjusting rod (5), and the two limiting members (52) are respectively located at two ends of the connecting sleeve (51); A winch (6) is installed on the placement rack (1), and a steel wire rope on the winch (6) is wound around the outside of the guide wheel (42) for hoisting materials.
2. The construction material hoist according to claim 1, characterized in that: There are two adjusting rods (5), and the two adjusting rods (5) are respectively located on both sides of the support arm (41) along the first direction.
3. The construction material hoist according to claim 2, characterized in that: A rotating rod (511) is rotatably provided on the fixing frame (3), the axis of the rotating rod (511) is arranged along a first direction, and the connecting sleeves (51) are installed at both ends of the rotating rod (511).
4. The construction material hoist according to claim 1, characterized in that: The end of the support arm (41) away from the hoisting arm (4) and the top of the fixing frame (3) are both rotatably provided with a guide rope wheel (31) for guiding the wire rope of the hoist (6).
5. The construction material hoist according to claim 1, characterized in that: A first flange (32) is fixedly mounted on the bottom of the fixing frame (3), a guide column (321) is fixedly mounted on the bottom of the first flange (32), a second flange (21) detachably connected to the first flange (32) is mounted on the top of the vertical pole (2), and a guide hole is also provided on the top of the vertical pole (2) for sliding engagement with the guide column (321).
6. The construction material hoist according to claim 1, characterized in that: Guide sleeves (7) are fixedly installed on both sides of the placement rack (1) along the first direction, the axis of the guide sleeve (7) is arranged perpendicular to the first direction, and an extension rod (8) is slidably arranged inside the guide sleeve (7), the extension rod (8) can be moved to the outside of the placement rack (1), and the guide sleeve (7) is also threadedly connected to a tightening member (71) for fixing the extension rod (8) to the inside of the guide sleeve (7).
7. The construction material hoist according to claim 1, characterized in that: An extension rod (9) is provided on one side of the placement rack (1) close to the hoisting arm (4) so as to slide along a first direction. There are two extension rods (9), and the two extension rods (9) can slide out of both sides of the placement rack (1) along the first direction.
8. The construction material hoist according to claim 7, characterized in that: The two opposite ends of the two extension rods (9) are detachably connected, and a limiting plate (91) for clamping between the two extension rods (9) is installed in the middle of the placement rack (1).