Comprehensive supporting structure with concrete wall serving as row pile water stopping and inter-pile soil retaining
Through the integrated support structure of concrete walls and pile rows, the tie bars between the wall piles and the prestressed anchor system are used to solve the problems of easy deformation and water-stopping of steel waist beams in traditional support, achieve a stable connection and water-stopping effect, and reduce construction costs and construction period.
Patent Information
- Application Number
- CN202422480831.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-14
- Publication Date
- 2025-09-12
- Estimated Expiration
- 2034-10-14
AI Technical Summary
Traditional pile-row prestressed anchor rod combined support technology has problems in stress and water stopping. The steel waist beam is easy to deform, the quality of the retaining wall between piles is difficult to guarantee, and when groundwater exists, a separate water-stop curtain or precipitation is required, which increases costs and construction time.
A comprehensive support structure using concrete walls as both pile waterstop and inter-pile retaining walls is adopted. The piles are connected to the cast-in-place concrete wall through tie bars and prestressed anchor rods between the wall piles. The steel waist beam is eliminated and the waterstop effect is achieved by utilizing the anti-seepage effect of the concrete wall.
The stable connection and water-stopping effect of the pile support are achieved, the deformation of the steel waist beam and the need to set up a separate water-stop curtain are avoided, and the construction cost and construction period are reduced.
Smart Images

Figure CN223329850U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of foundation pit support, in particular to a comprehensive support structure in which a concrete wall serves as a pile row water stop and a pile retaining wall. Background Art
[0002] Traditional support technology using prestressed anchors and piles is suitable for conditions with good soil quality and no groundwater within the excavation depth. The anchor structure utilizes prestressed anchors, which are connected by steel beams and tensioned against the piles. Shotcrete is typically used for simple support between the piles. If groundwater is present within the excavation depth, a waterstop curtain or pit dewatering may be necessary.
[0003] This combined support structure has the following problems in practical application:
[0004] From a force perspective: First, prestressed anchors act on the piles via steel beams, but these beams are easily deformed by collisions with construction equipment during excavation, affecting their force transmission. Second, the soil between the piles must be excavated before construction of the retaining walls between the piles. This often creates an uneven surface, making the quality of the retaining walls formed by the subsequent shotcrete injection impossible, thus affecting force transmission between the piles.
[0005] From the perspective of water stopping: when there is groundwater within the excavation depth of the foundation pit, shotcrete cannot serve as an independent water retaining structure. Setting up a water-stop curtain or dewatering the foundation pit alone will increase costs and construction period, and it is easy to affect the surrounding area during construction. Utility Model Content
[0006] The purpose of the utility model is to provide a comprehensive support structure of a concrete wall that serves as both a pile row water stop and a pile retaining wall, and to solve the problem that the existing pile row prestressed anchor rod combined support technology has two aspects, namely, the stress angle and the water stop angle, which affect the support stress and water stop.
[0007] In order to achieve the above purpose, the present invention adopts the following technical solutions:
[0008] A comprehensive support structure for a concrete wall that serves as both a pile row water stop and a pile retaining wall, comprising an inner pile row support, soil between the pile rows, and a cast-in-place concrete wall adjacent to the outer side of the pile row support. The cast-in-place concrete wall comprises wall reinforcement and wall concrete. The wall reinforcement is a steel cage comprising vertical force bars arranged in pairs and horizontal ladder bars arranged between each pair of vertical force bars.
[0009] The pile support and the cast-in-place concrete wall are connected by the tie bars between the piles. The inner half of the tie bars between the piles are embedded in the pile support, and the outer half of the tie bars between the piles are embedded in the cast-in-place concrete wall. The tie bars between the piles are arranged at intervals along the height direction of the pile support. The tie bars between the piles on each pile row are arranged in groups along the length direction of the cast-in-place concrete wall.
[0010] The soil between the piles and the cast-in-place concrete wall are connected by a set of prestressed anchor systems.
[0011] The prestressed anchor system includes a steel strand anchor rod. The steel strand anchor rod passes through the soil between piles and the cast-in-place concrete wall from the inside to the outside to form a three-part force transmission structure, namely the solidified part in the soil between piles, the embedded part in the wall, and the anchor part outside the wall. The steel strand anchor rod corresponds to the solidified soil section between piles, the free section in the wall, and the anchor head section outside the wall from the inside to the outside of the three-part force transmission structure.
[0012] The soil solidification section between piles is solidified in the soil between piles.
[0013] The embedded part in the wall includes a through-wall steel sleeve located in the cast-in-place concrete wall, which passes through the free section in the wall and is placed in the through-wall steel sleeve. The outer end of the free section in the wall passes through the through-wall steel sleeve.
[0014] The outside-wall anchor head section is anchored at the outside-wall anchoring portion.
[0015] The top surface of the cast-in-place concrete wall is at the same height as the pile row support. A pile row crown beam is provided on the top surface of the pile row support. The pile row crown beam is also provided on the top surface of the cast-in-place concrete wall and widened to be flush with the outer surface of the cast-in-place concrete wall.
[0016] Each pair of vertical stress-bearing reinforcement includes outer wall reinforcement and inner wall reinforcement correspondingly arranged along the inner and outer sides of the cast-in-place concrete wall.
[0017] The tie bars between the wall piles are fixedly connected to the outer and inner wall bars. The outer end faces of the tie bars between the wall piles are flush with the outer surface of the wall concrete. Each section of the cast-in-place concrete wall is equipped with two rows of tie bars between the wall piles, namely the upper row of tie bars and the lower row of tie bars.
[0018] The horizontal ladder reinforcement is fixedly connected between the outer and inner reinforcements of the wall along the thickness direction of the cast-in-place concrete wall.
[0019] The cast-in-place concrete wall is arranged in sections along the height direction. The horizontal ladder bars in each section of the cast-in-place concrete wall are arranged at intervals up and down along the height direction of the cast-in-place concrete wall. The horizontal ladder bars are located between the upper row of tie bars and the lower row of tie bars, namely the upper ladder bars and the lower ladder bars. The prestressed anchor rod system is located between the upper ladder bars and the lower ladder bars.
[0020] The through-wall steel sleeve is high on the outside and low on the inside and is pre-buried in the cast-in-place concrete wall. The outer end and inner end of the through-wall steel sleeve are fixedly connected to the outer reinforcement and inner reinforcement of the wall respectively.
[0021] The embedded part in the wall also includes horizontal structural reinforcement bars. The two ends of the horizontal structural reinforcement bars are fixedly connected to the outer sides of the outer wall reinforcement bars on the left and right sides of the wall-penetrating steel sleeve. The horizontal structural reinforcement bars are respectively fixedly connected to the upper and lower sides of the outer end of the wall-penetrating steel sleeve. The wall-penetrating steel sleeve and the horizontal structural reinforcement bars are fixedly connected to the wall steel bars in the cast-in-place concrete wall.
[0022] The embedded part in the wall also includes a steel plate, which is fixedly connected to the outer end face of the wall-penetrating steel sleeve. The outer surface of the steel plate is flush with the outer surface of the wall concrete. A rod hole is opened in the center of the steel plate, and the outer end of the free section passing through the wall passes through the rod hole.
[0023] The external wall anchoring part includes a wedge-shaped pressure plate and an anchor. The wedge-shaped pressure plate is provided with a through-plate hole. The external wall anchor head section passes through the through-plate hole and is anchored on the wedge-shaped pressure plate through the anchor.
[0024] The inter-pile soil solidification part includes an anchor hole formed on the inter-pile soil along the angle of the wall-penetrating steel sleeve. The inter-pile soil solidification section is placed in the anchor hole and forms a grouting solidification body with the grouting in the anchor hole.
[0025] When located below the groundwater level, the middle of the wall-penetrating steel sleeve is fixedly connected to a circular water-stop flange of the vertical cylinder.
[0026] Compared with the prior art, the present invention has the following features and beneficial effects:
[0027] In the utility model, the row pile support and the concrete wall on the pile side are specifically connected through the tie bars between the wall piles, and the concrete wall and the soil between the piles are connected and force is transmitted through the prestressed anchor rod system, so that the concrete wall, the row pile support and the soil between the piles are firmly connected.
[0028] The utility model eliminates the traditional method of transmitting force with a steel waist beam during pile prestressed anchor support. A steel sleeve is embedded in the concrete wall, and the prestressed anchor can be bored through the steel sleeve. A steel pad can also be installed at the hole of the steel sleeve to directly tension the anchor. The prestressed anchor can be directly anchored to the surface layer of the reinforced concrete wall through a pressure plate, thereby ensuring the overall force transmission of the support structure.
[0029] The utility model is a combined support of pile row support and pile side concrete wall. The reinforced concrete wall on the pile side replaces the sprayed concrete between the piles. The concrete wall is directly used as the retaining member between the piles to achieve soil support between the piles and ensure the force transmission effect between the piles. The anti-seepage effect of the concrete wall can also be used to achieve the groundwater interception requirement and achieve a water-stopping effect, so that the support structure does not need to be separately set up with a foundation pit dewatering or water-stopping curtain on the outside. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] The present invention will be further described in detail below with reference to the accompanying drawings.
[0031] Figure 1 It is a cross-sectional structural schematic diagram of the present utility model.
[0032] Figure 2 yes Figure 1 Schematic diagram of the side structure.
[0033] Figure 3 yes Figure 2 Schematic diagram of the longitudinal section structure showing the location of the prestressed anchor system.
[0034] Figure 4 It is a structural diagram of horizontal ladder reinforcement.
[0035] Figure 5 It is a structural diagram of the wall-penetrating steel sleeve and steel base plate.
[0036] Figure 6 yes Figure 5 Schematic diagram of the front view structure.
[0037] Figure 7 It is a structural diagram of a wedge-shaped pressure plate.
[0038] Figure 8 yes Figure 7 Schematic diagram of the front view structure.
[0039] Figure 9 It is a schematic diagram of the structure completed in step three of the construction method of the present invention.
[0040] Figure 10 It is a schematic diagram of the structure completed in step six of the construction method of the utility model.
[0041] Figure 11 It is a schematic diagram of the construction process of step seven of the construction method of the utility model.
[0042] Figure 12 It is a schematic diagram of the structure of the completion of step seven of the construction method of the utility model.
[0043] Figure 13 It is a structural schematic diagram of the completion of construction in step nine of the construction method of the utility model.
[0044] Figure numbers: 1 - pile support, 2 - soil between piles, 21 - anchor hole, 3 - cast-in-place concrete wall, 31 - completed upper wall, 32 - construction wall of this layer, 4 - vertical tension reinforcement, 41 - outer wall reinforcement, 42 - inner wall reinforcement, 5 - horizontal ladder reinforcement, 51 - upper ladder reinforcement, 52 - lower ladder reinforcement, 6 - tie reinforcement between wall piles, 61 - upper row tie reinforcement, 62 - lower row tie reinforcement, 7 - prestressed anchor system, 71 - steel strand Wire anchor rod, 711-soil solidification section between piles, 712-free section passing through the wall, 713-anchor head section outside the wall, 72-wall steel sleeve, 73-horizontal structural reinforcement, 74-steel pad, 741-rod hole, 8-pile crown beam, 75-wedge-shaped pressure plate, 751-plate hole, 76-anchor, 9-circular water stop flange, 10-upper section steel bar connection sleeve, 11-excavation surface of this layer, 12-steel bar connection sleeve of this layer. DETAILED DESCRIPTION
[0045] For example, see Figure 1-8 As shown, a comprehensive support structure with a concrete wall serving as both a pile row water stop and inter-pile retaining wall comprises an inner row of pile supports 1, inter-pile soil 2 between the rows of pile supports 1, and a cast-in-place concrete wall 3 immediately outside the row of pile supports. In this comprehensive support structure, the top surface of the cast-in-place concrete wall 3 is flush with the top surface of the pile row supports 1. A pile cap beam 8 is provided on the top surface of the pile row supports 1. This beam is also located on the top surface of the cast-in-place concrete wall 3 and widens to be flush with the outer surface of the cast-in-place concrete wall 3.
[0046] The cast-in-place concrete wall 3 includes wall reinforcement and wall concrete. The wall reinforcement is a reinforcement cage including vertical stress-bearing bars 4 arranged in pairs vertically and horizontal ladder bars 5 arranged between each pair of vertical stress-bearing bars 4 .
[0047] Each pair of vertical reinforcement bars 4 includes outer wall reinforcement bars 41 and inner wall reinforcement bars 42 disposed along the inner and outer sides of the cast-in-situ concrete wall 3. Horizontal ladder reinforcement bars 5 are fixedly connected between the outer wall reinforcement bars 41 and the inner wall reinforcement bars 42 along the thickness direction of the cast-in-situ concrete wall 3.
[0048] The pile support row 1 is connected to the cast-in-place concrete wall 3 via inter-pile tie bars 6. The inner half of the inter-pile tie bars 6 is embedded in the pile support row 1, while the outer half is embedded in the cast-in-place concrete wall 3. The inter-pile tie bars 6 are spaced apart along the height of the pile support row 1. The inter-pile tie bars 6 on each pile row are arranged in groups along the length of the cast-in-place concrete wall 3. The inter-pile tie bars 6 are fixedly connected to both the outer wall bars 41 and the inner wall bars 42. The outer end faces of the inter-pile tie bars 6 are flush with the outer surface of the wall concrete. Each section of the cast-in-place concrete wall 3 is provided with two rows of inter-pile tie bars 6: an upper row of tie bars 61 and a lower row of tie bars 62.
[0049] The cast-in-place concrete wall 3 is arranged in sections along its height. Within each section, horizontal ladder bars 5 are spaced vertically along the wall 3. These bars are located between the upper and lower rows of tie bars 61, 62, forming the upper and lower ladder bars 51, 52, respectively. The vertical spacing between the upper and lower ladder bars 51, 52 can be set to 1 meter. A prestressed anchor system 7 is located between the upper and lower ladder bars 51, 52.
[0050] The soil between the piles 2 is connected to the cast-in-place concrete wall 3 by a set of prestressed anchor systems 7.
[0051] The prestressed anchor rod system 7 includes a steel strand anchor rod 71. The steel strand anchor rod 71 passes through the pile soil 2 and the cast-in-place concrete wall 3 from the inside to the outside to form a three-part force transmission structure, namely the solidified part in the pile soil, the embedded part in the wall and the anchor part outside the wall. The steel strand anchor rod 71 corresponds to the pile soil solidified section 711, the free section 712 passing through the wall and the anchor head section 713 outside the wall in the three-part force transmission structure from the inside to the outside.
[0052] The embedded portion in the wall includes a through-wall steel sleeve 72 located within the cast-in-place concrete wall 3. A free section 712 extends through the wall and is inserted into the through-wall steel sleeve 72. The outer end of the free section 712 extends out of the through-wall steel sleeve 72. When located below the groundwater level, a vertical cylindrical circular waterstop flange 9 is fixedly connected to the center of the through-wall steel sleeve 72.
[0053] The wall-penetrating steel sleeve 72 is high on the outside and low on the inside and is pre-buried in the cast-in-place concrete wall 3. The outer end and the inner end of the wall-penetrating steel sleeve 72 are fixedly connected to the outer wall reinforcement 41 and the inner wall reinforcement 42 respectively.
[0054] The embedded part in the wall also includes horizontal structural reinforcement ribs 73. The two ends of the horizontal structural reinforcement ribs 73 are fixedly connected to the outer sides of the wall outer reinforcement 41 on the left and right sides of the wall-penetrating steel sleeve 72. The horizontal structural reinforcement ribs 73 are respectively fixedly connected to the upper and lower sides of the outer end of the wall-penetrating steel sleeve 72. The wall-penetrating steel sleeve 72 and the horizontal structural reinforcement ribs 73 are both fixedly connected to the wall steel bars in the cast-in-place concrete wall 3.
[0055] The embedded part in the wall also includes a steel plate 74, which is fixedly connected to the outer end face of the wall-penetrating steel sleeve 72. The outer surface of the steel plate 74 is flush with the outer surface of the wall concrete. A rod hole 741 is opened in the center of the steel plate 74, and the outer end of the free section 712 passing through the wall passes through the rod hole 741.
[0056] The inter-pile soil solidification section 711 solidifies within the inter-pile soil 2. The inter-pile soil solidification portion includes an anchor hole 21 formed in the inter-pile soil 2 along the angle of the through-wall steel sleeve 72. The inter-pile soil solidification section 711 is placed in the anchor hole 21 and forms a grouting solidification body with the grouting in the anchor hole 21.
[0057] The external wall anchor head section 713 is anchored in the external wall anchoring portion. The external wall anchoring portion includes a wedge-shaped pressure plate 75 and an anchor 76. The wedge-shaped pressure plate 75 has a through-plate hole 751. The external wall anchor head section 713 passes through the through-plate hole 751 and is anchored to the wedge-shaped pressure plate 75 through the anchor 76.
[0058] The cast-in-situ concrete wall 3 is arranged in sections along the height direction of the support body according to the construction excavation surface, including the completed wall 31 of the upper section and the construction wall 32 of the current layer. The thickness of the cast-in-situ concrete wall 3 is 300mm-400mm.
[0059] See also Figure 9-13 As shown, the bottom connection end of the upper steel bar connection sleeve 10 extends downward from the bottom surface of the upper completed wall 31, corresponding to the position of the vertical force reinforcement 4. The bottom surface of the current construction wall 32 is flush with the current earth excavation surface 11. The current steel bar connection sleeve 12 is pre-embedded on the current earth excavation surface 11, corresponding to the position of the vertical force reinforcement 4. The top connection end of the current steel bar connection sleeve 12 is exposed from the current earth excavation surface 11. The upper steel bar connection sleeve 10 corresponds to the current steel bar connection sleeve 12 in the upper and lower directions. In this embodiment, the upper steel bar connection sleeve 10 and the current steel bar connection sleeve 12 are both straight threaded sleeves. Both ends of the vertical force reinforcement 4 of the current construction wall 32 are threaded and threadedly connected to the top connection end of the current steel bar connection sleeve 12 and the bottom connection end of the upper steel bar connection sleeve 10, respectively.
[0060] This kind of concrete wall serves as a comprehensive support structure for pile water stop and soil retaining between piles. The basic construction steps are as follows:
[0061] Step 1: Position the pile support 1 outside the foundation pit according to the requirements of the design drawings, and then construct the pile support 1.
[0062] Step 2: Use excavation machinery to excavate the trench section step by step close to the side wall of the pile row. The excavation width is greater than the thickness of the cast-in-place concrete wall 2 and the wall reinforcement cage is placed below.
[0063] The excavation dimensions of the staged trench section are as follows:
[0064] First, excavate to 0.5m above the groundwater level, then use a telescopic arm grab to excavate in sections. Excavation length: each section excavation length is not more than 6m; excavation depth: not more than 2m; add a dewatering step, and drill a drainage well inside the foundation pit near the cast-in-place concrete wall 2; the drainage well is to facilitate the construction of the next concrete wall to reduce the amount of groundwater gushing out from the outside during excavation.
[0065] Step three, after the construction of the upper section of the completed wall 31 is completed, the earth within the range of the current construction wall 32 is excavated downwards, the bottom of the upper section of the completed wall 31 is chiseled out to expose the bottom connection end of the upper section of the steel bar connecting sleeve 10, and then excavation is carried out to the bottom excavation surface of the current construction wall 32, that is, the current earth excavation surface 11.
[0066] Step 4: Design and drill anchor holes on the pile body of the pile support 1 for implanting the tie bars 6 between the wall piles. The anchor holes are located at the top and bottom of the construction wall 32 of this layer; the anchor holes are divided into top anchor holes and bottom anchor holes. The top anchor holes are two in a row horizontally, and the bottom anchor holes are two in a row, that is, the two anchor holes in each row are at the same height on the corresponding pile row and are symmetrically arranged on the left and right.
[0067] Step 5: bury and install the current layer steel bar connection sleeve 12 at the position corresponding to the upper section steel bar connection sleeve 10 on the current layer earth excavation surface 11, and expose its top connection end.
[0068] Step six: implant the tie bars 6 between the wall piles in the anchor holes. The protruding length of the tie bars 6 between the wall piles is equal to the thickness of the cast-in-place concrete wall 2 .
[0069] Step 7: Install the wall reinforcement cage. The upper and lower ends of the vertical stress reinforcement of the wall reinforcement cage are threaded before installation. Then, the lower end of the vertical stress reinforcement is first threadedly connected to the current layer reinforcement connection sleeve 12, and then the upper end of the vertical stress reinforcement is threadedly connected to the upper section reinforcement connection sleeve 10;
[0070] The construction steps for installing the wall reinforcement cage in step seven are as follows:
[0071] Step a: first install the inner wall reinforcement 42 between the top connection end of the current layer steel bar connection sleeve 12 and the bottom connection end of the upper section steel bar connection sleeve 10;
[0072] Step b, then fix the outer wall reinforcement 41 and the double-layer horizontal ladder reinforcement 5 into a whole;
[0073] Step c: The middle part of the through-wall steel sleeve 72 is fixedly connected to the double-layer horizontal ladder reinforcement 5 by setting two vertical connectors, so that the through-wall steel sleeve 72 is fixedly connected to the outer wall reinforcement 41 and the double-layer horizontal ladder reinforcement 5 into a whole;
[0074] Step d: Weld a steel backing plate 74 to the front end surface of the wall-penetrating steel sleeve 72, and weld a circular water-stop flange 9 to the steel sleeve;
[0075] Step e: fix the horizontal structural reinforcement ribs 73 to the upper and lower sides of the front end of the through-wall steel sleeve 72 behind the steel backing plate 74 and the outer sides of the wall outer ribs 41 on the left and right sides of the through-wall steel sleeve 72;
[0076] Step f, lower the wall-penetrating steel sleeve 72, the outer wall reinforcement 41 and the double-layer horizontal ladder reinforcement 5 into the groove section as a whole, close to the inner wall reinforcement 42 when lowering, and fix the inner wall reinforcement 42 to the upper ladder reinforcement 51 after lowering to the design elevation; to prevent concrete from flowing into the interior of the wall-penetrating steel sleeve 72 during concrete pouring, foam should be filled inside the two ends of the wall-penetrating steel sleeve 72 after the wall-penetrating steel sleeve 72 is installed.
[0077] Step 8. Hoist the formwork for this layer into the outside of the groove section. After hoisting the formwork for this layer into the wall, first install the top form reinforcement to fix the formwork, and then backfill the soil on the outside of the formwork for this layer to prevent the formwork from shifting during concrete pouring.
[0078] Step nine: After the formwork of this layer is installed and fixed, plug the pouring hose to the bottom of the groove section, and then pour the wall concrete. After the age and strength of the wall concrete meet the requirements, remove the formwork of this layer.
[0079] Step 10. After the current layer of formwork is removed, the prestressed anchor system 7 is constructed. First, the hole of the through-wall steel sleeve 72 is cleaned, and the prestressed anchor system 7 is drilled into the soil 7 between the piles through the through-wall steel sleeve 72. After the drilling is completed, the steel strand anchor 71 is placed and grouting is performed to anchor it.
[0080] Step 11: After the age and strength of the grouting solidification body meet the requirements, install the wedge-shaped pressure plate 75, pass the steel strand anchor rod 71 through the wedge-shaped pressure plate 75, and then install the anchor 76 to tension the steel strand anchor rod 71.
[0081] In step 12, the construction wall 32 of this layer now becomes the upper section of the completed wall 31, and the next section of earthwork is excavated. The cast-in-place concrete wall 3 needs to be cast to 0.7m below the elevation of the prestressed anchor system 7 first. After the construction of the prestressed anchor system 7 is completed, the next section of earthwork is excavated. Repeat steps 3 to 9 until the earthwork is excavated to the base elevation, until all sections are constructed and the cast-in-place concrete wall 3 is formed as a whole.
Claims
1. A comprehensive support structure with a concrete wall serving as both a pile water stop and a pile retaining wall, characterized by: The invention comprises an inner row pile support (1), inter-pile soil (2) between the row pile support (1), and a cast-in-situ concrete wall (3) close to the outer side of the row pile support, wherein the cast-in-situ concrete wall (3) comprises wall reinforcement and wall concrete, wherein the wall reinforcement is a reinforcement cage, comprising vertical force reinforcement (4) arranged in pairs and horizontal ladder reinforcement (5) arranged between each pair of vertical force reinforcement (4). The row pile support (1) is connected to the cast-in-place concrete wall (3) through the wall pile tie bars (6), the inner half of the wall pile tie bars (6) are embedded in the row pile support (1), and the outer half of the wall pile tie bars (6) are embedded in the cast-in-place concrete wall (3). The wall pile tie bars (6) are arranged at intervals along the height direction of the row pile support (1), and the wall pile tie bars (6) on each row pile are arranged in groups along the length direction of the cast-in-place concrete wall (3). The soil between the piles (2) and the cast-in-place concrete wall (3) are connected by a set of prestressed anchor systems (7). The prestressed anchor rod system (7) includes a steel strand anchor rod (71). The steel strand anchor rod (71) passes through the soil between piles (2) and the cast-in-place concrete wall (3) from the inside to the outside to form a three-part force transmission structure, which includes a solidified part in the soil between piles, a pre-embedded part in the wall, and an anchoring part outside the wall. The steel strand anchor rod (71) corresponds to the solidified soil section between piles (711), the free section (712) passing through the wall, and the anchor head section (713) outside the wall in the three-part force transmission structure from the inside to the outside. The inter-pile soil solidification section (711) solidifies in the inter-pile soil (2). The embedded portion in the wall includes a through-wall steel sleeve (72) located in the cast-in-place concrete wall (3), a free section (712) passing through the wall, and being inserted into the through-wall steel sleeve (72), and an outer end portion of the free section (712) passing through the wall passes out of the through-wall steel sleeve (72). The outer wall anchor head section (713) is anchored at the outer wall anchoring portion.
2. The concrete wall according to claim 1 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The top surface of the cast-in-place concrete wall (3) is at the same height as the row pile support (1), and a row pile crown beam (8) is provided on the top surface of the row pile support (1). The row pile crown beam (8) is also provided on the top surface of the cast-in-place concrete wall (3) and widened to be flush with the outer surface of the cast-in-place concrete wall (3).
3. The concrete wall according to claim 1 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: Each pair of vertical force-bearing reinforcement bars (4) comprises outer wall reinforcement bars (41) and inner wall reinforcement bars (42) correspondingly arranged along the inner and outer sides of the cast-in-place concrete wall (3).
4. The concrete wall according to claim 3 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The tie bars (6) between the wall piles are fixedly connected to the outer wall reinforcements (41) and the inner wall reinforcements (42). The outer end faces of the tie bars (6) between the wall piles are flush with the outer surface of the wall concrete. Two rows of tie bars (6) between the wall piles are provided in each section of the cast-in-place concrete wall (3), namely, an upper row of tie bars (61) and a lower row of tie bars (62).
5. The concrete wall according to claim 4 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The horizontal ladder reinforcement (5) is fixedly connected between the outer wall reinforcement (41) and the inner wall reinforcement (42) along the thickness direction of the cast-in-place concrete wall (3). The cast-in-situ concrete wall (3) is arranged in sections along the height direction. The horizontal ladder bars (5) in each section of the cast-in-situ concrete wall (3) are arranged at intervals in the vertical direction of the cast-in-situ concrete wall (3). The horizontal ladder bars (5) are located between the upper row of tie bars (61) and the lower row of tie bars (62), namely the upper ladder bars (51) and the lower ladder bars (52). The prestressed anchor rod system (7) is located between the upper ladder bars (51) and the lower ladder bars (52).
6. The concrete wall according to claim 3 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The through-wall steel sleeve (72) is high on the outside and low on the inside and is pre-buried in the cast-in-place concrete wall (3). The outer end and the inner end of the through-wall steel sleeve (72) are fixedly connected to the outer wall reinforcement (41) and the inner wall reinforcement (42), respectively. The embedded portion in the wall further includes a horizontal structural reinforcement bar (73), both ends of which are fixedly connected to the outer sides of the wall outer reinforcement bars (41) on the left and right sides of the through-wall steel sleeve (72), and the horizontal structural reinforcement bar (73) is fixedly connected to the upper and lower sides of the outer end of the through-wall steel sleeve (72), respectively. The through-wall steel sleeve (72) and the horizontal structural reinforcement bar (73) are both fixedly connected to the wall reinforcement bars in the cast-in-place concrete wall (3).
7. The concrete wall according to claim 1 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The embedded portion in the wall further comprises a steel backing plate (74), which is fixedly connected to the outer end surface of the wall-penetrating steel sleeve (72). The outer surface of the steel backing plate (74) is flush with the outer surface of the wall concrete. A rod hole (741) is provided in the center of the steel backing plate (74), and the outer end of the free section (712) passing through the wall passes through the rod hole (741).
8. The concrete wall according to claim 1 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The external wall anchoring portion comprises a wedge-shaped pressure-bearing plate (75) and an anchor (76); a through-plate hole (751) is formed on the wedge-shaped pressure-bearing plate (75); the external wall anchor head section (713) passes through the through-plate hole (751) and is anchored to the wedge-shaped pressure-bearing plate (75) through the anchor (76).
9. The concrete wall according to claim 1 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: The inter-pile soil solidification portion includes an anchor hole (21) formed on the inter-pile soil (2) along the angle of the through-wall steel sleeve (72), and the inter-pile soil solidification section (711) is placed in the anchor hole (21) and forms a grouting solidification body with the grouting in the anchor hole (21).
10. The concrete wall according to claim 1 serves as a comprehensive supporting structure for pile row water stopping and retaining soil between piles, characterized in that: When located below the groundwater level, the middle portion of the through-wall steel sleeve (72) is fixedly connected to a circular water-stop flange (9) of the vertical cylinder.