Water supply device for construction engineering
By designing the trough body, cleaning chamber, water storage chamber, tank body, chemical layer, solenoid valve, pump body and branch pipe in the water supply device, the problem of insufficient chemical storage is solved, the continuous supply of chemical and the effective treatment of sewage are achieved, and the stable operation of the water supply equipment and the reuse of sewage are ensured.
Patent Information
- Application Number
- CN202422737121.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-11
- Publication Date
- 2025-09-26
- Estimated Expiration
- 2034-11-11
AI Technical Summary
Existing construction project water supply equipment has limited storage capacity for chemicals when treating sewage and cannot continuously and effectively treat wastewater.
A water supply device is designed, which includes a trough body, a cleaning chamber, a water storage chamber, a tank body, a medicine layer, a solenoid valve, a pump body and a branch pipe. The medicine layer in the tank body is extracted by the pump body and guided into the water storage chamber. The check valve and the filter cover are combined to prevent backflow and the entry of debris, thereby realizing the continuous use of the medicine.
It realizes the continuous supply of chemicals and the effective treatment of sewage, reduces the possibility of water backflow and the entry of debris, and ensures the stable operation of water supply equipment and the reuse of sewage.
Smart Images

Figure CN223386727U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water supply equipment for construction projects, in particular to a water supply device for construction projects. Background Art
[0002] Construction projects refer to a general term for various buildings and engineering facilities that provide the material and technological foundation for human life and production. Construction projects are organized, purposeful, and large-scale economic activities of mankind. According to their natural attributes, construction projects can be divided into three categories: architectural engineering, civil engineering, and electromechanical engineering. They are engineering projects that form comprehensive production capacity or realize engineering benefits during the reproduction of fixed assets. Construction projects refer to the construction of new or the renovation of existing fixed assets. Patent No. CN202222554183.4 discloses a water supply device for construction projects. When the user needs to fully purify the wastewater entering the processing box, the first motor drives the rotor, which then drives the stirring rod to rotate, thereby completing the rapid mixing of the wastewater and the reagent attached to the inner wall surface of the processing box. However, the reagent inside the processing box is limited, and the wastewater cannot be continuously treated. To this end, we propose a water supply device for construction projects. Utility Model Content
[0003] In view of the problems in the prior art, the utility model provides a water supply device for construction projects.
[0004] The technical solution adopted by the utility model to solve the technical problem is a water supply device for construction projects, comprising a trough body, wherein a cleaning chamber and a water storage chamber are provided in the trough body, a tank body for containing a pharmaceutical layer is mounted on the top surface of the trough body, and a solenoid valve is mounted on the discharge end of the bottom of the tank body, a pump body located between the trough body and the tank body is mounted on the end of the solenoid valve away from the tank body, and a branch pipe located on the inner wall surface of the water storage chamber is mounted on the discharge end of the pump body;
[0005] The end of the branch pipe located in the water storage cavity is equipped with a ring sleeve, and a check valve is installed in the ring sleeve. The end of the ring sleeve away from the branch pipe is screwed with a rotary seat, and the end of the rotary seat away from the ring sleeve is equipped with a filter cover.
[0006] By adopting the above technical solution, when the water supply equipment for construction projects is used, the tank body at the top of the tank body can be used to store the agent layer for treating sewage. When the agent needs to be used, the pump body and the solenoid valve at the bottom of the tank body can be operated, and the pump body can extract the agent layer in the tank body, so that the agent layer can enter the water storage chamber through the guidance of the branch pipe, thereby facilitating the use of the agent when treating sewage and facilitating the subsequent reuse of the treated sewage.
[0007] When the drug layer passes through the branch pipe and enters the water source in the water storage chamber, the check valve in the ring sleeve at the bottom of the branch pipe can easily reduce the backflow of the water source in the water storage chamber. At the same time, the filter cover screwed on the outer periphery of the ring sleeve can easily protect the debris in the water source and reduce the situation where the debris in the water source enters the branch pipe. At the same time, the rotary seat is convenient for disassembly and assembly, and it is convenient to replace the filter cover, so that the filter cover can continue to protect the ring sleeve and the branch pipe.
[0008] Specifically, the outer wall surface of the tank is equipped with a glass plate for observation, and the outer wall surface of the glass plate is coated with scale lines for measurement.
[0009] By adopting the above technical solution, the glass plate makes it convenient for the staff to observe the content of the medicine inside the tank, and the scale lines on the surface of the glass plate enable the staff to understand the amount of medicine more clearly.
[0010] Specifically, the top feed end of the tank body is equipped with a cover plate.
[0011] By adopting the above technical solution, the cover plate is convenient for sealing and protecting the feed port on the top of the tank body, and is also convenient for disassembly and assembly, so as to facilitate the replenishment of medicine in the tank body.
[0012] Specifically, a controller is installed on the outer wall surface of the tank.
[0013] By adopting the above technical solution, the controller can conveniently control the operation of the solenoid valve and the pump body.
[0014] Specifically, the top surface of the tank body is equipped with a grid plate located at the top of the cleaning chamber.
[0015] By adopting the above technical solution, the grid plate can conveniently protect the cleaning chamber and can support the workpiece to be flushed, making it convenient to flush it.
[0016] Compared with the prior art, the present invention has the following beneficial effects:
[0017] 1. The technical solution of the present application, through the design of the cleaning chamber, water storage chamber, tank body, chemical layer, solenoid valve, pump body and branch pipe, can utilize the tank body at the top of the tank body to store the chemical layer for treating sewage when using the water supply equipment for construction projects. When the chemical needs to be used, the pump body and solenoid valve at the bottom of the tank body can be operated, and the pump body can extract the chemical layer in the tank body, so that the chemical layer can enter the water storage chamber through the guidance of the branch pipe, thereby facilitating its use when treating sewage and facilitating the subsequent reuse of the treated sewage.
[0018] 2. The technical solution of the present application is designed with a ring sleeve, a check valve, a rotary seat and a filter cover. When the drug layer passes through the branch pipe and enters the water source in the water storage chamber, the check valve in the ring sleeve at the bottom of the branch pipe can easily reduce the backflow of the water source in the water storage chamber. At the same time, the filter cover screwed on the outer periphery of the ring sleeve can easily protect the debris in the water source and reduce the situation where the debris in the water source enters the branch pipe. At the same time, the rotary seat is easy to disassemble and assemble, and it is easy to replace the filter cover, so that the filter cover can continue to protect the ring sleeve and the branch pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0020] Figure 1 This is an axonometric drawing of the present utility model;
[0021] Figure 2 It is a schematic plan view of the connection structure between the tank body and the water storage chamber of the utility model;
[0022] Figure 3 This is a schematic diagram of the connection structure between the branch pipe and the filter cover of the utility model;
[0023] In the figure: 1. trough body; 2. cleaning chamber; 3. water storage chamber; 4. tank body; 5. reagent layer; 6. solenoid valve; 7. pump body; 8. branch pipe; 9. ring sleeve; 10. check valve; 11. rotary seat; 12. filter cover; 13. glass plate; 14. scale line; 15. controller; 16. cover plate; 17. grid plate. DETAILED DESCRIPTION
[0024] In order to make the technical means, creative features, objectives and effects achieved by the present invention easier to understand, the present invention is further described below in conjunction with specific implementation methods.
[0025] See also Figure 1-3 The embodiment of the utility model provides a technical solution: a water supply device for construction projects, comprising a trough body 1, a cleaning chamber 2 and a water storage chamber 3 are provided in the trough body 1, a tank body 4 for containing a medicinal layer 5 is mounted on the top surface of the trough body 1, and a solenoid valve 6 is mounted on the bottom discharge end of the tank body 4, an end of the solenoid valve 6 away from the tank body 4 is mounted with a pump body 7 located between the trough body 1 and the tank body 4, and a branch pipe 8 is mounted on the inner wall surface of the water storage chamber 3 at the discharge end of the pump body 7; an end of the branch pipe 8 located in the water storage chamber 3 is mounted with a ring sleeve 9, and a check valve 10 is mounted in the ring sleeve 9, an end of the ring sleeve 9 away from the branch pipe 8 is threadedly mounted with a rotary seat 11, and an end of the rotary seat 11 away from the ring sleeve 9 is mounted with a filter cover 12.
[0026] During use, when the water supply equipment for construction projects is used, the tank body 4 on the top of the tank body 1 can be used to store the agent layer 5 for treating sewage. When the agent needs to be used, the pump body 7 and the solenoid valve 6 at the bottom of the tank body 4 can be operated, and the pump body 7 can extract the agent layer 5 in the tank body 4, so that the agent layer 5 can enter the water storage chamber 3 through the guidance of the branch pipe 8, thereby facilitating the use when treating sewage and facilitating the subsequent reuse of the treated sewage.
[0027] When the drug layer 5 passes through the branch pipe 8 and enters the water source in the water storage chamber 3, the check valve 10 in the ring sleeve 9 at the bottom of the branch pipe 8 is convenient for reducing the backflow of the water source in the water storage chamber 3. At the same time, the filter cover 12 screwed on the outer periphery of the ring sleeve 9 is convenient for protecting the debris in the water source and reducing the debris in the water source from entering the branch pipe 8. At the same time, the rotary seat 11 is convenient for disassembly and assembly, and it is convenient to replace the filter cover 12, so that the filter cover 12 can continue to protect the ring sleeve 9 and the branch pipe 8.
[0028] like Figure 1 As shown, the outer wall surface of the tank body 4 is equipped with a glass plate 13 for observation, and the outer wall surface of the glass plate 13 is coated with scale lines 14 for measurement.
[0029] When in use, the glass plate 13 facilitates the staff to observe the content of the medicine inside the tank body 4, and the scale lines 14 on the surface of the glass plate 13 enable the staff to understand the content of the medicine more clearly.
[0030] like Figure 1 As shown, the top feed end of the tank body 4 is equipped with a cover plate 16.
[0031] When in use, the cover plate 16 is convenient for sealing and protecting the feed port at the top of the tank body 4 , and is also convenient for assembly and disassembly, so as to facilitate replenishing the medicine in the tank body 4 .
[0032] like Figure 1 As shown, a controller 15 is mounted on the outer wall surface of the tank body 4 .
[0033] When in use, the controller 15 facilitates the control of the operation of the solenoid valve 6 and the pump body 7 .
[0034] like Figure 1 As shown, the top surface of the tank body 1 is equipped with a grid plate 17 located at the top of the cleaning chamber 2.
[0035] When in use, the grid plate 17 can conveniently protect the cleaning chamber 2 and can support the workpiece to be flushed, making it convenient to flush it.
[0036] The working principle and use process of the utility model are as follows: when in use, first install the corresponding structural components in the appropriate position. When using the water supply equipment for construction projects, the tank body 4 on the top of the tank body 1 can be used to store the pharmaceutical layer 5 for treating sewage. When the pharmaceutical needs to be used, the pump body 7 and the electromagnetic valve 6 at the bottom of the tank body 4 can be operated. The pump body 7 can extract the pharmaceutical layer 5 in the tank body 4, so that the pharmaceutical layer 5 can enter the water storage chamber 3 through the guidance of the branch pipe 8, so as to facilitate the use when treating sewage and facilitate the subsequent reuse of the treated sewage. At the same time, when the pharmaceutical layer 5 passes through the branch pipe 8 When the water enters the water source in the water storage chamber 3, the check valve 10 in the ring sleeve 9 at the bottom of the branch pipe 8 is convenient for reducing the backflow of the water source in the water storage chamber 3. At the same time, the filter cover 12 screwed on the outer periphery of the ring sleeve 9 is convenient for protecting the debris in the water source, which is convenient for reducing the debris in the water source from entering the branch pipe 8. At the same time, the rotary seat 11 is convenient for disassembly and assembly, and it is convenient to replace the filter cover 12, so that the filter cover 12 can continue to protect the ring sleeve 9 and the branch pipe 8, thereby making the construction project water supply equipment more stable. It can also continue to use chemicals to treat the water source in the water storage chamber 3, which is convenient for its reuse.
[0037] The above shows and describes the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are merely illustrative of the principles of the present invention. Various changes and improvements may be made to the present invention without departing from the spirit and scope of the present invention. Such changes and improvements are intended to fall within the scope of the present invention. The scope of protection claimed in the present invention is defined by the appended claims and their equivalents.
Claims
1. A water supply device for construction engineering, characterized in that: The invention comprises a tank body (1), wherein a cleaning chamber (2) and a water storage chamber (3) are provided in the tank body (1), a tank body (4) for containing a drug layer (5) is mounted on the top surface of the tank body (1), and a solenoid valve (6) is mounted on the bottom discharge end of the tank body (4), and a pump body (7) located between the tank body (1) and the tank body (4) is mounted on the end of the solenoid valve (6) away from the tank body (4), and a branch pipe (8) located on the inner wall surface of the water storage chamber (3) is mounted on the discharge end of the pump body (7); One end of the branch pipe (8) located in the water storage chamber (3) is equipped with a ring sleeve (9), and a check valve (10) is equipped in the ring sleeve (9); one end of the ring sleeve (9) away from the branch pipe (8) is screwed with a rotary seat (11), and the end of the rotary seat (11) away from the ring sleeve (9) is equipped with a filter cover (12).
2. A water supply device for construction engineering according to claim 1, characterized in that: The outer wall surface of the tank body (4) is equipped with a glass plate (13) for observation, and the outer wall surface of the glass plate (13) is coated with scale lines (14) for measurement.
3. A water supply device for construction engineering according to claim 1, characterized in that: The top feed end of the tank body (4) is equipped with a cover plate (16).
4. A water supply device for construction engineering according to claim 1, characterized in that: The outer wall surface of the tank body (4) is equipped with a controller (15).
5. A water supply device for construction engineering according to claim 1, characterized in that: The top surface of the tank body (1) is equipped with a grid plate (17) located at the top of the cleaning chamber (2).