Rapid positioning and mounting structure for photovoltaic power generation panel
By using concrete support columns and collar structures, combined with components such as right-angle positioning blocks and clamps, the problem of time-consuming photovoltaic panel installation has been solved, enabling rapid positioning and disassembly, and improving installation efficiency and support effect.
Patent Information
- Application Number
- CN202423088201.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-14
- Publication Date
- 2025-11-25
- Estimated Expiration
- 2034-12-14
AI Technical Summary
The existing photovoltaic panel installation process is time-consuming and inconvenient to disassemble, especially when connecting it to the bracket bolts using clamps, which is quite cumbersome.
The system employs concrete support columns and a collar structure, combined with components such as right-angle positioning blocks, clamps, and anti-slip positioning blocks, to achieve quick fixing and disassembly of photovoltaic panels via bolt connections and knob handles.
It enables rapid positioning, installation, and disassembly of photovoltaic panels. The installation method is simple, time-saving, and labor-saving, with good support and firm, reliable fixing.
Smart Images

Figure CN223599764U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to photovoltaic support installation technical field especially relates to a photovoltaic power generation panel quick positioning installation structure. BACKGROUND
[0002] The installation of photovoltaic cell panel array needs to consider the installation azimuth angle and the inclination angle. The cell panels need to avoid shielding, the support is fixed, the photovoltaic panel is placed on it and fixed. The wiring distance is as short as possible and average. The wiring is firm to prevent virtual connection or disconnection. The storage battery terminal is firm and cannot be short-circuited. The polarity is paid attention to during installation to avoid explosion and fire. The polarity reverse connection and short circuit are prevented during the controller wiring process. The angle of placement is paid attention to to avoid rainwater immersion. The placement site must be open. There must be no tall buildings or other things to block the sunlight at the installation site.
[0003] The existing photovoltaic power generation panel is connected with the support through the clamping device and the bolt. The disassembly is time-consuming. Therefore, the technical personnel in the field provide a photovoltaic power generation panel quick positioning installation structure to solve the problems in the background technology. SUMMARY
[0004] The utility model discloses a photovoltaic power generation panel quick positioning installation structure that is simple in structure, convenient to disassemble and convenient for the quick positioning and installation of the photovoltaic power generation panel.
[0005] To achieve the above object, the utility model provides the following technical scheme: a photovoltaic power generation panel quick positioning installation structure, including concrete support column, the outside installation of concrete support column has big ring, the outside installation of concrete support column has small ring, the inside bolt connection of big ring has support rod, the left and right sides of big ring all bolt connection has auxiliary rod, one end bolt connection of auxiliary rod has connecting rod, the upper one end bolt connection of connecting rod has first cross rod, the upper other end bolt connection of connecting rod has second cross rod.
[0006] The outside bolt connection of first cross rod has right angle positioning piece, one side of right angle positioning piece is equipped with fixed hole, the outside clamping connection of second cross rod has clamping device, the clamping device includes U type block, the inside of U type block is equipped with screw hole, the inside screw thread connection of screw hole has screw rod, one end fixed connection of screw rod has antiskid positioning piece, the other end fixed connection of screw rod has knob handle.
[0007] Further, the inner diameter of the big ring and the inner diameter of the small ring are same, the support rod is vertically installed on the left and right sides of the big ring and the small ring.
[0008] Further, the auxiliary rod is divided into two rods with different lengths, the first horizontal rod is vertically installed above the connecting rod, and the central axis of the second horizontal rod is parallel to the central axis of the first horizontal rod.
[0009] Further, the right-angle positioning block is symmetrically installed outside the first horizontal rod, and the fixing hole is symmetrically arranged on one side of the right-angle positioning block.
[0010] Further, the clamping device is symmetrically installed outside the second horizontal rod, and the threaded rod is vertically installed in the threaded hole.
[0011] Further, the anti-skid positioning block and the threaded rod form an integral structure, and the rotary knob handle is vertically arranged at one end of the threaded rod.
[0012] The utility model has the advantages of the following beneficial effects:
[0013] 1. The utility model discloses a photovoltaic power generation panel quick positioning installation structure, which is characterized in that the right-angle positioning block is bolted below the first horizontal rod, the photovoltaic power generation panel is first placed on the mounting rack in an inclined manner, then the U-shaped block is clamped at the front end of the photovoltaic power generation panel and the second horizontal rod, the anti-skid positioning block at the front end of the threaded rod is fixed to the lower end surface of the second horizontal rod by rotating the rotary knob handle, the photovoltaic power generation panel is fixed firmly, the installation mode is simple, and time and labor are saved.
[0014] 2. The utility model discloses a photovoltaic power generation panel quick positioning installation structure, which is characterized in that the anti-skid positioning block is arranged at one end of the threaded rod, the photovoltaic power generation panel can be effectively fixed by rotating the rotary knob handle, and the support rod and the auxiliary rod are fixed through the large ring and the small ring, so that the support effect of the photovoltaic power generation panel support is better. DRAWINGS
[0015] Figure 1 It is a perspective view of the utility model;
[0016] Figure 2 It is a right-angle positioning block structure schematic view of the utility model;
[0017] Figure 3 It is a clamping device structure schematic view of the utility model.
[0018] Legend:
[0019] 1, concrete support column; 2, small ring; 3, support rod; 4, auxiliary rod; 5, connecting rod; 6, first horizontal rod; 7, second horizontal rod; 8, right-angle positioning block; 9, fixing hole; 10, clamping device; 11, large ring; 1001, U-shaped block; 1002, threaded hole; 1003, threaded rod; 1004, anti-skid positioning block; 1005, rotary knob handle. DETAILED DESCRIPTION
[0020] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of the utility model.
[0021] With reference to Figure 1 and Figure 2 A photovoltaic power generation panel rapid positioning installation structure, including concrete support column 1, the outside of concrete support column 1 is provided with large ring 11, the outside of concrete support column 1 is provided with small ring 2, the inside of large ring 11 is bolted with support rod 3, the left and right sides of large ring 11 are bolted with auxiliary rod 4, one end of auxiliary rod 4 is bolted with connecting rod 5, the upper end of connecting rod 5 is bolted with first cross bar 6, the other end of connecting rod 5 is bolted with second cross bar 7.
[0022] Specifically, the inner diameter of large ring 11 is same with the inner diameter of small ring 2, support rod 3 is vertically installed on the left and right sides of large ring 11 and small ring 2, which enhances the support effect of photovoltaic power generation panel support, auxiliary rod 4 is divided into two rods with different lengths, so that the support is arranged in an inclined manner, which is convenient for solar energy collection, first cross bar 6 is vertically installed on the upper side of connecting rod 5, the central axis of second cross bar 7 is parallel with the central axis of first cross bar 6, which ensures that the photovoltaic power generation panel can be clamped and fixed by clamping device 10, right-angle positioning block 8 is symmetrically installed on the outside of first cross bar 6, and fixing hole 9 is symmetrically arranged on one side of right-angle positioning block 8, when installing, the length of photovoltaic power generation panel is measured first, then two right-angle positioning blocks 8 are bolted in the position within the length of photovoltaic power generation panel according to the length, and after being fixed, the photovoltaic power generation panel is first placed on right-angle positioning block 8 in an inclined manner.
[0023] With reference to Figure 3 , the outside of first cross bar 6 is bolted with right-angle positioning block 8, one side of right-angle positioning block 8 is provided with fixing hole 9, the outside of second cross bar 7 is clamped and connected with clamping device 10, clamping device 10 includes U-shaped block 1001, a threaded hole 1002 is formed in the inside of U-shaped block 1001, a threaded rod 1003 is screw-connected in the inside of threaded hole 1002, an anti-slip positioning block 1004 is fixedly connected to one end of threaded rod 1003, and a knob handle 1005 is fixedly connected to the other end of threaded rod 1003.
[0024] Specific, the engagement 10 is symmetrically installed on the outside of the second crossbar 7, the threaded rod 1003 is vertically installed in the threaded hole 1002, the anti-skid positioning block 1004 and the threaded rod 1003 form an integral structure, the knob handle 1005 is vertically arranged on one end of the threaded rod 1003, then the U-shaped block 1001 is clamped on the front end of the photovoltaic panel 1 and the second crossbar 7, and the knob handle 1005 is rotated, the anti-skid positioning block 1004 at the front end of the threaded rod 1003 is fixed with the lower end surface of the second crossbar 7, so that the photovoltaic panel is fixed firmly.
[0025] Working principle: first, when installing, the support rod 3 is vertically installed on the left and right sides of the small ring 2 and the large ring 11, and two auxiliary rods 4 with different lengths are installed on the left and right sides of the large ring 11, secondly, the connecting rod 5 is bolted with the auxiliary rod 4 and the support rod 3, and then the first crossbar 6 and the second crossbar 7 are fixed in parallel above the connecting rod 5.
[0026] When installing, first measure the length of the photovoltaic panel, according to the length, bolt the two right-angle positioning blocks 8 in the position within the length of the photovoltaic panel, after fixing, first place the photovoltaic panel on the right-angle positioning block 8, then clamp the U-shaped block 1001 on the front end of the photovoltaic panel 1 and the second crossbar 7, and rotate the knob handle 1005, fix the anti-skid positioning block 1004 at the front end of the threaded rod 1003 with the lower end surface of the second crossbar 7, so that the photovoltaic panel is fixed firmly.
[0027] Finally, it should be pointed out that: the above only for the preferred embodiments of the present application, and is not intended to limit the present application, although the foregoing embodiments of the present application are described in detail, for those skilled in the art, it still can be modified, or part of the technical features of the equivalent replacement, within the spirit and principles of the present application, any modification, equivalent replacement, improvement, etc., should be included in the scope of protection of the present application.
Claims
1. A rapid positioning and installation structure for photovoltaic panels, comprising concrete support columns (1), characterized in that: A large collar (11) is installed on the outside of the concrete support column (1), and a small collar (2) is installed on the outside of the concrete support column (1). A support rod (3) is bolted inside the large collar (11). Auxiliary rods (4) are bolted to both the left and right sides of the large collar (11). A connecting rod (5) is bolted to one end of the auxiliary rod (4). A first crossbar (6) is bolted to one end of the connecting rod (5). A second crossbar (7) is bolted to the other end of the connecting rod (5). The first crossbar (6) is bolted to a right-angle positioning block (8), and a fixing hole (9) is provided on one side of the right-angle positioning block (8). The second crossbar (7) is externally engaged with a locking device (10), which includes a U-shaped block (1001). The U-shaped block (1001) has a threaded hole (1002) inside, and a threaded rod (1003) is threaded inside the threaded hole (1002). One end of the threaded rod (1003) is fixedly connected to an anti-slip positioning block (1004), and the other end of the threaded rod (1003) is fixedly connected to a knob handle (1005).
2. The photovoltaic panel rapid positioning and installation structure according to claim 1, characterized in that: The inner diameter of the large collar (11) is the same as that of the small collar (2), and the support rod (3) is installed vertically on the left and right sides of the large collar (11) and the small collar (2).
3. The photovoltaic panel rapid positioning and installation structure according to claim 1, characterized in that: The auxiliary rod (4) is divided into two rods of different lengths. The first crossbar (6) is installed vertically above the connecting rod (5). The central axis of the second crossbar (7) is parallel to the central axis of the first crossbar (6).
4. The photovoltaic panel rapid positioning and installation structure according to claim 1, characterized in that: The right-angle positioning block (8) is symmetrically installed on the outside of the first crossbar (6), and the fixing hole (9) is symmetrically arranged on one side of the right-angle positioning block (8).
5. The photovoltaic panel rapid positioning and installation structure according to claim 1, characterized in that: The engaging device (10) is symmetrically installed on the outside of the second crossbar (7), and the threaded rod (1003) is vertically installed in the threaded hole (1002).
6. The photovoltaic panel rapid positioning and installation structure according to claim 1, characterized in that: The anti-slip positioning block (1004) and the threaded rod (1003) form an integral structure, and the knob handle (1005) is vertically arranged at one end of the threaded rod (1003).