Pile cap and bolt positioning set tool in photo-thermal environment

By designing a set of tools for positioning pile caps and bolts in solar thermal power plants, the problems of accuracy and efficiency in pile cap construction were solved, enabling efficient and precise installation of pile caps and anchor bolts, reducing costs and improving work efficiency.

CN223984026UActive Publication Date: 2026-03-10SEPCOIII ELECTRIC POWER CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-24
Publication Date
2026-03-10

AI Technical Summary

Technical Problem

In concentrated solar power plants, the construction of pile caps and the installation of embedded bolts require high precision and involve a large workload. Existing technologies are insufficient to efficiently control installation accuracy and improve work efficiency.

Method used

Design a tool kit for positioning pile caps and bolts in a photothermal environment, including a concrete template for the pile cap and an anchor bolt support frame. Through precise positioning and fixing, ensure the installation accuracy of the pile cap and anchor bolts, and reduce manual adjustment steps.

Benefits of technology

It improves the installation accuracy and first-time acceptance rate of pile caps and anchor bolts, simplifies the operation process, reduces process and labor costs, and is suitable for repeated use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223984026U_ABST
    Figure CN223984026U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of pile cap construction, in particular to a photo-thermal environment pile cap and bolt positioning sleeving tool which comprises a pile cap concrete formwork and a foundation bolt supporting frame erected in the middle of the pile cap concrete formwork. The pile cap concrete formwork comprises two semi-circular formworks, and each semi-circular formwork comprises a semi-circular bottom plate and a semi-circular vertical plate. The foundation bolt supporting frame comprises a pile cap bolt positioning plate, a pile cap bolt fixing plate arranged below the pile cap bolt positioning plate and a foundation bolt sequentially penetrating through the pile cap bolt positioning plate and the pile cap bolt fixing plate. According to the utility model, repeated positioning and adjustment by personnel are not needed, the working efficiency and the process quality are improved, the mounting precision of the pile cap and the foundation bolt is ensured, the one-time acceptance qualification rate is improved, and the application range is wider.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of pile cap construction technology, specifically to a photothermal field pile cap and bolt positioning kit. Background Technology

[0002] Currently, solar thermal power (CSP) projects are increasingly common in power plant construction. The efficiency of a CSP plant mainly depends on the solar thermal efficiency of the mirrors and collectors. High solar thermal efficiency ensures high lava temperatures, which in turn lead to higher power generation efficiency. Therefore, the installation accuracy of the mirrors and supports in a CSP plant project is of paramount importance. A 4MW unit typically has approximately 9500 mirrors, each requiring a pile foundation, and each pile foundation has four anchor bolts to secure the mirror and support. Based on this calculation, 9500 * 4 = 38000 pile cap bolts are needed for this type of unit. Therefore, pile cap installation and the installation of pre-embedded pile cap bolts are characterized by high precision and a large workload.

[0003] Based on the above characteristics, and considering that the installation accuracy of the mirrors and supports determines the power generation efficiency of the solar thermal power project, the construction of the pile caps and the precision requirements for the pre-embedded bolts in the pile caps are even higher, since the mirror supports are installed on the pile caps. To ensure this, the installation accuracy of all 38,000 bolts on the pile caps of the entire unit must be controlled within 5mm, while simultaneously improving work efficiency, reducing procedures, reducing labor costs, and controlling the overall quality of the pile cap bolts. Utility Model Content

[0004] In response to the shortcomings of existing technologies, the inventors have developed a photothermal field pile cap and bolt positioning kit through long-term practice. This kit eliminates the need for repeated positioning and adjustment by personnel, thereby improving work efficiency and process quality, and ensuring the installation accuracy of the pile cap and anchor bolts.

[0005] To achieve the above objectives, this utility model provides the following technical solution:

[0006] A set of tools for positioning pile caps and bolts in a photothermal environment includes a pile cap concrete template and an anchor bolt support frame erected in the middle of the pile cap concrete template. The pile cap concrete template includes two semi-circular templates, each of which includes a semi-circular base plate and a semi-circular vertical plate. The anchor bolt support frame includes a pile cap bolt positioning plate, a pile cap bolt fixing plate located below the positioning plate, and anchor bolts that pass through the positioning plate and fixing plate in sequence.

[0007] The vertical plate is fixed vertically to the inner edge of the base plate, and both ends of the vertical plate are provided with connecting plates, with a connecting hole in the middle of the connecting plate.

[0008] The pile cap bolt positioning plate has a first central circular hole in the center and two first square grooves along the length of the pile cap bolt positioning plate. The pile cap bolt positioning plate has four first anchor bolt holes, which are evenly distributed along the four corners of the pile cap bolt positioning plate.

[0009] The pile cap bolt fixing plate has a second central circular hole in the center and two second square grooves along the length of the pile cap bolt fixing plate. The pile cap bolt fixing plate has four second anchor bolt holes, which are evenly distributed along the four corners of the pile cap bolt fixing plate.

[0010] There are four anchor bolts, which pass through the corresponding second anchor bolt holes and the first anchor bolt holes in sequence. A first nut is provided at the bottom of each anchor bolt, two second nuts are provided above the first nut, and two third nuts are provided above the second nuts.

[0011] Furthermore, the two semi-circular templates are fitted together, and bolts are passed through the two fitted connecting holes to fix the two semi-circular templates.

[0012] Furthermore, the base plate is provided with two fixing round holes, the diameter of which is 10-25mm.

[0013] Furthermore, both the base plate and the vertical plate are made of 2mm thick carbon steel plates, and the height of the vertical plate is 40cm.

[0014] Furthermore, the diameters of both the first central circular hole and the second central circular hole are 6 mm.

[0015] Furthermore, the two first square slots are symmetrically arranged with the first central circular hole as the center, and the two second square slots are symmetrically arranged with the second central circular hole as the center.

[0016] Furthermore, the diameter of both the first anchor bolt hole and the second anchor bolt hole is 36mm.

[0017] Furthermore, both the pile cap bolt positioning plate and the pile cap bolt fixing plate are made of 4mm thick carbon steel plates.

[0018] Furthermore, the anchor bolt has a diameter of 36mm and a length of 80cm.

[0019] Furthermore, the two second nuts are welded and fixed to the anchor bolts, thereby non-removably fixing the pile cap bolt fixing plate to the anchor bolts.

[0020] The beneficial effects of this utility model are:

[0021] This utility model positioning kit eliminates the need for repeated positioning and adjustment by personnel, which improves work efficiency and process quality, ensures the installation accuracy of pile caps and anchor bolts, and increases the first-time acceptance rate. Moreover, some accessories of this utility model positioning kit are reusable, sturdy and not easily damaged, and are suitable for all photovoltaic field pile cap construction and pile cap pre-embedded anchor bolt positioning construction. It is simple to operate, convenient to transport and carry, and has a wider range of applications. Attached Figure Description

[0022] Figure 1 This is a schematic diagram of the structure of this utility model.

[0023] Figure 2 This is a structural schematic diagram of the concrete formwork for pile caps of this utility model.

[0024] Figure 3 This is a structural schematic diagram of the concrete formwork for pile caps from another perspective.

[0025] Figure 4 This is a structural schematic diagram of the pile anchor bolt support frame of this utility model.

[0026] Figure 5 This is a schematic diagram of the present invention installed on the pile cap steel cage.

[0027] In the attached image:

[0028] 1-Pile cap concrete formwork, 11-Base plate, 12-Vertical plate, 13-Connecting plate, 14-Fixing round hole, 2-Pile cap bolt positioning plate, 21-First square groove, 22-First central round hole, 3-Pile cap bolt fixing plate, 31-Second square groove, 32-Second central hole, 4-Anchor bolt, 41-First nut, 42-Second nut, 43-Third nut. Detailed Implementation

[0029] To enable those skilled in the art to better understand the technical solution of this utility model, the technical solution of this utility model will be clearly and completely described below with reference to the accompanying drawings. Based on the embodiments in this application, other similar embodiments obtained by those skilled in the art without creative effort should all fall within the scope of protection of this application. Furthermore, directional terms mentioned in the following embodiments, such as "up," "down," "left," and "right," are only for reference to the directions in the accompanying drawings; therefore, the directional terms used are for illustrative purposes and not for limiting the scope of this utility model.

[0030] The present invention will be further described below with reference to the accompanying drawings and preferred embodiments.

[0031] See Figures 1-4The present invention relates to a photothermal field pile cap and bolt positioning kit, comprising a pile cap concrete template 1 and an anchor bolt support frame erected in the middle of the pile cap concrete template 1.

[0032] The pile cap concrete formwork 1 comprises two semi-circular templates. Each semi-circular template includes a semi-circular base plate 11 and a semi-circular vertical plate 12. The vertical plate 12 is vertically fixed to the inner edge of the base plate 11. Connecting plates 13 are provided at both ends of the vertical plate 12, with connecting holes in the middle of the connecting plates 13. The two semi-circular templates are fitted together, and bolts are passed through the two fitted connecting holes to fix the two semi-circular templates, thus forming the pile cap concrete formwork 1. The pile cap concrete formwork 1 can be repeatedly disassembled and reused.

[0033] The base plate 11 of this utility model has two fixing holes 14, which are used to reinforce the installation when installing a mirror. The diameter of the fixing holes 14 is 10-25mm. Both the base plate 11 and the vertical plate 12 are made of 2mm thick carbon steel plates, and the height of the vertical plate 12 is 40cm.

[0034] The anchor bolt support frame includes a pile cap bolt positioning plate 2, a pile cap bolt fixing plate 3 located below the pile cap bolt positioning plate 2, and anchor bolts 4 passing through the pile cap bolt positioning plate 2 and the pile cap bolt fixing plate 3 in sequence.

[0035] The pile cap bolt positioning plate 2 is a square plate with a first central circular hole 22 at its center, the diameter of which is 6mm. Two first square slots 21 are formed along the length of the pile cap bolt positioning plate 2, symmetrically arranged around the first central circular hole 22. Four first anchor bolt holes, each 36mm in diameter, are evenly distributed along the four corners of the pile cap bolt positioning plate 2 for the anchor bolts 4 to pass through.

[0036] The pile cap bolt fixing plate 3 is a square plate with a second central circular hole 32 at its center. The diameter of the second central circular hole 32 is 6mm. Two second square slots 31 are formed along the length of the pile cap bolt fixing plate 3, and the two second square slots 31 are symmetrically arranged with the second central circular hole 32 as the center. Four second anchor bolt holes are provided on the pile cap bolt fixing plate 3, with a diameter of 36mm. The four second anchor bolt holes are evenly distributed along the four corners of the pile cap bolt fixing plate 3 for the anchor bolts 4 to pass through.

[0037] Both the pile cap bolt positioning plate 2 and the pile cap bolt fixing plate 3 of this utility model are made of 4mm thick carbon steel plates.

[0038] This utility model has four anchor bolts 4, which pass sequentially through the corresponding second anchor bolt holes and first anchor bolt holes. A first nut 41 is provided at the bottom of the anchor bolt 4, which is used for welding to the internal reinforcing bars of the pile cap reinforcement cage within the site. Two second nuts 42 are provided above the first nut 41, and are respectively fixed at the points where the anchor bolt 4 enters and exits the pile cap bolt fixing plate 3. Two third nuts 43 are provided above the second nuts 42, and are respectively fixed at the points where the anchor bolt 4 enters and exits the pile cap bolt positioning plate 2.

[0039] The anchor bolt 4 of this utility model has a diameter of 36mm and a length of 80cm. Two second nuts 42 are welded and fixed to the anchor bolt 4, thereby fixing the pile cap bolt fixing plate 3 to the anchor bolt 4 in a non-detachable manner. Since the first nut 41 is welded and fixed to the internal steel bars of the pile cap steel cage, the pile cap bolt fixing plate 3, together with the anchor bolt 4, is fixed in the pile cap steel cage in a non-detachable manner, providing a stable and powerful guarantee for the subsequent installation of the mirror support.

[0040] See Figure 5 The positioning kit of this utility model is installed after the pile foundation and pile cap reinforcement cage are constructed. First, place four anchor bolts 4 in appropriate positions inside the pile cap reinforcement cage, and weld the first nut 41 at the bottom of the anchor bolts to the internal reinforcement of the pile cap reinforcement cage. Then, place the first set of four second nuts 42 in the required positions of the four anchor bolts 4. Next, insert four anchor bolts 4 into the four second anchor bolt holes of the pile cap bolt fixing plate 3. Place the pile cap bolt fixing plate 3 on the upper part of the pile cap reinforcement cage, and then place the second set of four second nuts 42 on the four anchor bolts 4. At this time, the pile cap bolts are positioned according to latitude, longitude, and height. After positioning, tighten the two sets of second nuts 42 and weld them to the anchor bolts 4. In this way, the anchor bolts 4, together with the pile cap bolt fixing plate 3, are irremovably fixed to the pile cap reinforcement cage. Next, place the first set of four third nuts 43 onto the four anchor bolts 4 respectively. Then, insert the four anchor bolts 4 into the four first anchor bolt holes of the pile cap bolt positioning plate 2 respectively. Place the second set of four third nuts 43 onto the four anchor bolts 4 respectively. At this point, the latitude and height of the anchor bolts 4 need to be checked again. After positioning, tighten the third nuts 43. Finally, with the first central circular hole 22 of the pile cap bolt positioning plate 2 as the center, the pile cap concrete template 1 is surrounded by this center. The pile cap concrete template 1 is mainly used for shaping after the pile cap is poured. The bottom surface of the bottom plate 11 of the pile cap concrete template 1 is placed against the ground. Concrete is poured inside and below the vertical plate 12 until it is flush with the height of the vertical plate 12. This completes the pile cap construction and the pre-embedded installation of the anchor bolts.

[0041] This utility model's positioning kit eliminates the need for repeated positioning and adjustments by personnel. This tool improves work efficiency and process quality, ensures the installation accuracy of pile caps and anchor bolts, and increases the first-time acceptance rate. The pile cap concrete formwork 1 is reusable, sturdy, and not easily damaged, suitable for all photovoltaic field pile cap construction and pre-embedded anchor bolt positioning construction. This tool, without increasing workload, is simple to operate, fast, and easy to transport and carry, achieving standardized, safe, convenient, and efficient work requirements.

[0042] The present invention has been described in detail above. The above description is only a preferred embodiment of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made in accordance with the scope of this application should still fall within the scope of the present invention.

Claims

1. A photothermal environment pile cap and bolt positioning set tool, characterized in that, The utility model provides a pile cap concrete formwork (1) and the anchor bolt support frame of erecting in the middle of pile cap concrete formwork (1), the pile cap concrete formwork (1) includes two semicircular formworks, and each semicircular formwork includes a semicircular bottom plate (11), a semicircular vertical plate (12), the anchor bolt support frame includes pile cap bolt positioning plate (2), the pile cap bolt fixed plate (3) of setting below pile cap bolt positioning plate (2), the anchor bolt (4) of sequentially passing through pile cap bolt positioning plate (2) and pile cap bolt fixed plate (3), The vertical plate (12) is vertically fixed on the inner edge of the bottom plate (11), both ends of the vertical plate (12) are provided with a connecting plate (13), and a connecting circular hole is arranged in the middle of the connecting plate (13). The first center circular hole (22) is arranged in the center of the pile cap bolt positioning plate (2), two first square grooves (21) are arranged along the length direction of the pile cap bolt positioning plate (2), and four first anchor bolt holes are arranged on the pile cap bolt positioning plate (2) and uniformly distributed along the four corners of the pile cap bolt positioning plate (2). The second center circular hole (32) is arranged in the center of the pile cap bolt fixed plate (3), two second square grooves (31) are arranged along the length direction of the pile cap bolt fixed plate (3), and four second anchor bolt holes are arranged on the pile cap bolt fixed plate (3) and uniformly distributed along the four corners of the pile cap bolt fixed plate (3). The anchor bolt (4) has four, sequentially passes through the corresponding second anchor bolt hole and first anchor bolt hole; the bottom of the anchor bolt (4) is provided with a first nut (41), two second nuts (42) are arranged above the first nut (41), and two third nuts (43) are arranged above the second nuts (42).

2. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, The two semicircular formworks are abutted, and the two semicircular formworks are fixed by the bolt passing through the two abutted connecting circular holes.

3. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, Two fixing circular holes (14) are arranged on the bottom plate (11), and the diameter of the fixing circular hole (14) is 10-25 mm.

4. A photothermal moat cap and bolt positioning kit tool according to claim 3, wherein, The bottom plate (11) and the vertical plate (12) are both 2 mm thick carbon steel plates, and the height of the vertical plate (12) is 40 cm.

5. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, The diameters of the first center circular hole (22) and the second center circular hole (32) are both 6 mm.

6. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, The two first square grooves (21) are symmetrically arranged with the first center circular hole (22) as the center, and the two second square grooves (31) are symmetrically arranged with the second center circular hole (32) as the center.

7. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, The diameters of the first anchor bolt hole and the second anchor bolt hole are both 36 mm.

8. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, The pile cap bolt positioning plate (2) and the pile cap bolt fixed plate (3) are both 4 mm thick carbon steel plates.

9. A photothermal moat cap and bolt positioning kit tool according to claim 1, wherein, The diameter of the anchor bolt (4) is 36 mm, and the length is 80 cm.

10. A photothermal moat cap and bolt positioning kit tool according to claim 9, wherein, The two second nuts (42) are welded and fixed on the anchor bolt (4), and then the pile cap bolt fixed plate (3) is fixed on the anchor bolt (4) in a non-detachable manner.