Temporary attachment device for climbing frame in overhanging area

By using steel columns made of channel steel and tie plates in the open area, multi-level height adjustment of the climbing frame attachment device was achieved, which solved the problem of low installation efficiency in the existing technology and improved the construction progress.

CN223984236UActive Publication Date: 2026-03-10CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
View PDF 1 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-01
Publication Date
2026-03-10

AI Technical Summary

Technical Problem

Existing technologies are not efficient in adjusting the height of attachment points in open areas, which affects the construction progress.

Method used

The steel column is made of two channel steels, combined with tie plate and limiting structure, and multi-level height adjustment is achieved by bolt connection, which simplifies the installation process.

Benefits of technology

It improves installation efficiency, meets the flexible adaptability requirements of the climbing formwork at different climbing stages, and shortens construction time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223984236U_ABST
    Figure CN223984236U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, and particularly discloses a temporary attachment device for a climbing frame in a hollow area, which comprises a steel stand column formed by oppositely arranging two pieces of channel steel and opposite-pulling connecting plates arranged on the two sides of the steel stand column respectively; the bottom end of the channel steel is welded with the base, the top end of the channel steel is welded with the upper limit, and the middle part of the channel steel is welded with the lower limit; two open holes are evenly distributed in the opposite-pulling connecting plate in the direction of the central axis. The steel stand column base is fixedly connected with a main body structural beam through a vertical beam penetrating bolt, the inner side of the top of the steel stand column is fixedly connected with an anchoring part, the anchoring part is fixedly connected with a floor penetrating bolt through an inclined strut, and the outer side of the steel stand column is fixedly connected with a climbing frame attachment device through an opposite-pulling connecting plate. The problem that under the condition that the height of a climbing frame attachment point can be adjusted, the installation efficiency of the device is not high is solved. The device is mainly used for temporary attachment of a climbing frame in a building construction hollow area.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of building construction technology, and in particular to a temporary attachment device for climbing scaffolding in open areas. Background Technology

[0002] Attached lifting scaffolding, also known as climbing scaffolding, is a new type of scaffolding system that has become increasingly popular in recent years. It is mainly used in high-rise buildings and can ascend or descend along the building. Due to the diversification of building shapes and the increasing complexity of building facades in recent years, climbing scaffolding requires attachment points during ascent or descent. In particular, when climbing scaffolding encounters open areas, the universality of traditional climbing scaffolding is relatively poor.

[0003] Chinese utility model patent CN213297080U discloses a temporary attachment component for a climbing scaffold in an open area. This device includes embedded parts in the structural floor slab, an adjustable attachment section, and a diagonal brace assembly. The lower end of the adjustable attachment section is fixed to the embedded parts with bolts. An inner anchor is hinged to the diagonal brace, and the other end of the diagonal brace is connected to the embedded parts in the floor slab. An attachment device for the climbing scaffold is installed on the outer side, supplemented by lateral reinforcement with steel wire ropes. By adjusting the height of the adjustable attachment section in conjunction with the climbing scaffold's ascent, the problem of no attachment points in open areas is solved, achieving stable lifting of the climbing scaffold.

[0004] However, the patented adjustable attachment section is assembled by stacking two or more standard attachment frame sections. The design of the standard attachment frame section realizes the function of adjusting the height of the temporary attachment component of the climbing frame. However, due to the design of the standard attachment frame section, the standard section needs to be installed repeatedly until the designed adjustable attachment section height is reached, which results in low installation efficiency and affects the construction progress. Utility Model Content

[0005] To address the shortcomings of existing technologies, this utility model provides a temporary attachment device for scaffolding in open areas, which solves the problem of low installation efficiency in existing technologies where the attachment point height is adjustable.

[0006] To solve the above problems, the technical solution adopted by this utility model is: a temporary attachment device for a climbing scaffold in an open area, comprising a steel column composed of two channel steels arranged opposite each other and a tie plate on each side of the steel column; the channel steel has an opening facing outward, a base welded to the bottom end, an upper limit welded to the top end, and a lower limit welded to the middle; the tie plate has two openings evenly distributed along the central axis; the base of the steel column is fixedly connected to the main structural beam by vertical through-beam bolts, the inner side of the top of the steel column is fixedly connected to anchors, the anchors are fixedly connected to the through-floor bolts by diagonal braces, and the climbing scaffold attachment device is fixedly connected to the outer side of the steel column by the tie plate.

[0007] Furthermore, a fastener is welded to the lower part of the steel column. The fastener further enhances the overall stability of the steel column.

[0008] Furthermore, the channel steel between the upper and lower limits is provided with a groove.

[0009] Furthermore, the tie plate is provided with a protrusion that matches the groove of the channel steel. The groove of the channel steel and the protrusion of the tie plate ensure that the channel steel and the tie plate fit tightly together, preventing relative slippage of the tie plate.

[0010] The beneficial effects of this plan are:

[0011] 1. The steel column has a groove structure between the upper and lower limit positions on the side of the channel steel, which allows the tie plate to be fixed at different height positions by bolts, forming a multi-level adjustment point, which can flexibly adapt to the needs of different climbing stages of the climbing frame.

[0012] 2. The steel columns, made of symmetrical channel steel, can be installed in one go, which improves installation efficiency and speeds up the construction progress. Attached Figure Description

[0013] Figure 1 This is a structural diagram of the present invention.

[0014] Figure 2 This utility model relates to a steel column.

[0015] Figure 3 This is a detailed drawing of the pull-out connecting plate of this utility model.

[0016] The reference numerals in the accompanying drawings of the instruction manual include: 1. diagonal brace; 2. steel column; 21. base; 22. channel steel; 23. fastener; 24. upper limit; 25. lower limit; 26. groove; 3. vertical through-beam bolt; 4. climbing formwork attachment device; 5. through-floor bolt; 6. anchor; 8. tie plate; 81. protrusion; 82. opening. Detailed Implementation

[0017] The following detailed description illustrates the specific implementation method:

[0018] Example 1

[0019] As attached Figure 1-3 As shown: A temporary attachment device for a climbing scaffold in an open area includes a steel column 2 consisting of two channel steels 22 arranged opposite each other, and a tie plate 8 on each side of the steel column 2; the channel steels 22 have outward openings, with a base 21 welded to the bottom, an upper limit 24 welded to the top, and a lower limit 25 welded to the middle; the tie plate 8 has two openings 82 evenly distributed along the central axis; the base 21 of the steel column 2 is fixedly connected to the main structural beam by vertical through-beam bolts 3, the inner side of the top of the steel column 2 is fixedly connected to an anchor 6, the anchor 6 is fixedly connected to the floor slab bolts 5 by diagonal braces 1, and the climbing scaffold attachment device 4 is fixedly connected to the outer side of the steel column 2 by the tie plate 8.

[0020] The lower part of the steel column is welded with fastener 23.

[0021] The channel steel 22 between the upper limit position 24 and the lower limit position 25 has a groove 26 on its side.

[0022] The tie plate 8 is provided with a protrusion 81 of the groove 26 of the matching channel steel 22. Detailed implementation method:

[0024] The steel column 2 is fixed to the top of the steel column 2 by positioning and pre-embedding bolts on the structural beam and fixing it with vertical through-beam bolts 3; the anchor 6 is welded and fixed to the top of the steel column 2; the steel column 2 is fixed to the top of the structural slab by positioning and pre-embedding bolts on the structural slab and hinged to one end of the diagonal brace 1 by through-floor bolts 5, and the other end of the diagonal brace 1 is hinged to the anchor 6; the two tie plates 8 are positioned opposite each other at the protrusions 81 and fixed in the groove 26 of the channel steel 22 by bolts. The installation of the temporary attachment device is completed.

[0025] The above description is merely an embodiment of this utility model, and common knowledge regarding specific structures and characteristics is not described in detail here. It should be noted that those skilled in the art can make various modifications and improvements without departing from the structure of this utility model, and these should also be considered within the scope of protection of this utility model. These modifications will not affect the effectiveness of the implementation of this utility model or the practicality of the patent. The scope of protection claimed in this application should be determined by the content of its claims, and the specific embodiments described in the specification can be used to interpret the content of the claims.

Claims

1. A temporary attachment device for a climbing frame in a voided area, characterized in that: The steel column is composed of two channel steels oppositely arranged, and one pull-connecting plate is arranged on each side of the steel column; the channel steel is outwardly opened, the bottom end is welded with a base, the top end is welded with an upper limiting part, and the middle part is welded with a lower limiting part; the pull-connecting plate is uniformly arranged with two openings along the central axis direction; the base of the steel column is fixedly connected with the main body structure beam through vertical beam-penetrating bolts, the inner side of the top end of the steel column is fixedly connected with an anchoring part, the anchoring part is fixedly connected with floor-penetrating bolts through a diagonal brace, and the outer side of the steel column is fixedly connected with a climbing frame attaching device through the pull-connecting plate.

2. The temporary attachment device for a climbing formwork of a hollowed area according to claim 1, characterized in that: The steel column is welded with a fixing part at the lower part.

3. The temporary attachment device for a climbing formwork of a hollowed area according to claim 1, characterized in that: The side surface of the channel steel between the upper limiting part and the lower limiting part is provided with a groove.

4. The temporary attachment device for a climbing formwork of a hollowed area according to claim 1, characterized in that: The pull-connecting plate is provided with a protrusion matched with the groove of the channel steel.

Citation Information

Patent Citations

  • Temporary attaching assembly for climbing frame in picking-up area

    CN213297080U