Modularized filler bin for waste gas treatment spray tower

The modular packing bin quick-release assembly solves the problem of difficult disassembly of the spray tower packing bin, enabling rapid connection and disassembly of the material pipe, improving maintenance efficiency and the adaptability of the spray tower.

CN224221050UActive Publication Date: 2026-05-12CHANGZHOU TIANXIANG SOUTHERN FRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
CHANGZHOU TIANXIANG SOUTHERN FRP CO LTD
Filing Date
2025-05-14
Publication Date
2026-05-12

AI Technical Summary

Technical Problem

The existing spray tower packing silos are difficult to disassemble, the operation is complicated and time-consuming, and it is difficult to adapt to different waste gas treatment needs.

Method used

A modular filling chamber is designed, employing quick-release components including a top ring, a rising pipe, and a screw. The screw drives the rotation of the top ring and the pressure ring to achieve modular connection and disassembly of the material pipe, and a sealing ring is used to achieve sealing.

Benefits of technology

It enables quick connection and disassembly of the material pipe, improves maintenance efficiency and the adaptability of the spray tower, and simplifies the operation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224221050U_ABST
    Figure CN224221050U_ABST
Patent Text Reader

Abstract

The utility model relates to a modularized packing bin for a waste gas treatment spray tower, which comprises a tower body, a material pipe and a quick release component arranged at the top ends of the tower body and the material pipe, the quick release component comprises a top ring, a lifting pipe and a screw rod, the material pipe is arranged above the tower body, and the screw rod is arranged above the lifting pipe. Fixing rings are fixedly installed at the upper end and the lower end of the material pipe and the edge of the top end of the tower body, the fixing ring at the bottom of the material pipe is attached to the fixing ring at the top end of the tower body, the tower body and the outer wall of the top of the material pipe are sleeved with the top ring, the screw rod is movably installed on the outer wall of the tower body and the outer wall of the material pipe, and a lifting pipe is attached to the outer wall of the bottom of the top ring. And the screw rod is fixedly connected with the outer wall of the bottom of the lifting pipe. According to the amount of waste gas needing to be treated, the material pipes can be stacked, the connecting positions of the material pipes can be in butt joint through the pressing rings and the top rings, sealing and quick disassembling are achieved, the material pipes are modularized, assembling is easy and convenient, and the overhaul efficiency and the adaptability of the spray tower are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of spray tower technology, and in particular to a modular packing bin for a waste gas treatment spray tower. Background Technology

[0002] A spray tower is an environmentally friendly waste gas treatment device. The spray tower contains multiple packing chambers. Waste gas passes through the packing materials in these chambers and undergoes purification. Because the packing materials can filter impurities in the waste gas, they need to be replaced regularly to ensure good purification results. Due to the large size of the spray tower equipment and the fact that the outer shell is essentially welded together with multiple pipes, disassembling the layers of filter plates and the packing material inside the spray tower is difficult, involves a large amount of work, and is very time-consuming. Therefore, designing a modular packing chamber is essential. Utility Model Content

[0003] The purpose of this application is to provide a modular packing bin for a waste gas treatment spray tower to solve the problems mentioned in the background art.

[0004] To achieve the above objectives, this application provides the following technical solution:

[0005] A modular packing bin for a waste gas treatment spray tower includes a tower body, a feed pipe, and a quick-release assembly installed at the top of the tower body and the feed pipe. The quick-release assembly includes a top ring, a lifting pipe, and a screw. The feed pipe is installed above the tower body. Fixing rings are fixedly installed at both ends of the feed pipe and at the top edge of the tower body. The fixing ring at the bottom of the feed pipe fits into the fixing ring at the top of the tower body. The top ring is sleeved on the top outer wall of the tower body and the feed pipe. The screw is movably installed on the outer wall of the tower body and the feed pipe. A lifting pipe is fitted against the bottom outer wall of the top ring, and the screw is fixedly connected to the bottom outer wall of the lifting pipe. Multiple guide pipes are fixedly installed on the bottom outer wall of the fixing ring at the top of the tower body and the feed pipe. The multiple guide pipes are evenly distributed on the bottom outer wall of the fixing ring, and the lifting pipe is sleeved outside the guide pipes.

[0006] Preferably, a fixing block is fixedly installed on the outer wall of the tower body and the feed pipe. A threaded hole is formed through the fixing block, and a screw is threaded into the threaded hole. A spring is installed between the fixing block and the bottom surface of the lifting pipe, and the spring is sleeved on the outside of the screw. Multiple mounting holes are formed on the fixing ring, all of which communicate with the guide pipe. A thread is formed on the inner wall of the guide pipe. A pressure ring is fitted onto the lower part of the outer wall of the feed pipe, and multiple round holes are formed on the pressure ring, communicating with the mounting holes. Sealing rings are fitted tightly inside both the top ring and the pressure ring, and the shape of the sealing ring is adapted to the outer wall of the fixing ring.

[0007] The beneficial effects of this utility model are: by setting up quick-release components, the material pipes can be stacked according to the amount of waste gas to be treated, and the connection of the material pipes can also be connected by pressure rings and top rings to achieve sealing and quick release, so that the material pipes can be modularized, the assembly is simple, the maintenance efficiency is improved, and the adaptability of the spray tower is enhanced. Attached Figure Description

[0008] Figure 1 This is a schematic diagram of the overall structure of this utility model;

[0009] Figure 2 This is a schematic diagram of the overall structure of the quick-release component in this utility model.

[0010] In the diagram: 1. Tower body; 2. Material pipe; 3. Top ring; 4. Pressure ring; 5. Fixing ring; 6. Sealing ring; 7. Guide pipe; 8. Lifting pipe; 9. Fixing block; 10. Screw; 11. Spring; 12. Mounting hole. Detailed Implementation

[0011] The preferred embodiments of this utility model will now be described in detail with reference to the accompanying drawings, so that the advantages and features of this utility model can be more easily understood by those skilled in the art, thereby providing a clearer and more definite definition of the scope of protection of this utility model. The directional terms mentioned in this utility model, such as "up," "down," "front," "back," "left," "right," "top," and "bottom," are only for reference to the accompanying drawings. Therefore, the directional terms used are for the purpose of explaining and understanding this utility model, and not for limiting this utility model.

[0012] like Figure 1-2 The diagram shows a modular packing silo for a waste gas treatment spray tower, comprising a tower body 1, a feed pipe 2, and a quick-release assembly installed at the top of the tower body 1 and the feed pipe 2. The quick-release assembly includes a top ring 3, a lifting pipe 8, and a screw 10. The feed pipe 2 is installed above the tower body 1. Fixing rings 5 ​​are fixedly installed at both ends of the feed pipe 2 and at the top edge of the tower body 1. The fixing ring 5 at the bottom of the feed pipe 2 fits into the fixing ring 5 at the top of the tower body 1. The top ring 3 is fitted onto the top outer wall of the tower body 1 and the feed pipe 2. The screw 10 is movably installed on the outer wall of the tower body 1 and the feed pipe 2. The lifting pipe 8 is fitted into the bottom outer wall of the top ring 3, and the screw 10 is fixedly connected to the bottom outer wall of the lifting pipe 8. Multiple guide pipes 7 are fixedly installed on the bottom outer wall of the fixing ring 5 at the top of the tower body 1 and the feed pipe 2. The multiple guide pipes 7 are evenly distributed on the bottom outer wall of the fixing ring 5. The lifting pipe 8 is fitted onto the outside of the guide pipes 7.

[0013] A fixing block 9 is fixedly installed on the outer wall of the tower body 1 and the material pipe 2. A threaded hole is opened through the fixing block 9, and a screw 10 is threaded into the threaded hole. A spring 11 is installed between the fixing block 9 and the bottom surface of the lifting pipe 8, and the spring 11 is sleeved on the outside of the screw 10. Multiple mounting holes 12 are opened on the fixing ring 5, and all the mounting holes 12 are connected to the guide pipe 7. The inner wall of the guide pipe 7 is threaded. A pressure ring 4 is sleeved on the lower part of the outer wall of the material pipe 2. Multiple round holes are opened on the pressure ring 4, and the round holes are connected to the mounting holes 12. A sealing ring 6 is fitted inside the top ring 3 and the pressure ring 4. The shape of the sealing ring 6 is adapted to the outer wall of the fixing ring 5.

[0014] Example: Multiple material pipes 2 can be stacked above the tower body 1 according to the waste gas treatment requirements. The material pipes 2 are connected to the tower body 1 via quick-release components. After the fixing ring 5 of the material pipe 2 is aligned with the fixing ring 5 of the tower body 1, the operator rotates the screw 10. The screw 10 rotates on the fixing block 9, which drives the lifting pipe 8 to rotate and pushes the top ring 3 upward. The spring 11 is stretched and deformed. After all the screws 10 have rotated to their positions, the top ring 3 is lifted up. The top ring 3, together with the sealing ring 6 on the inner wall, fits against the fixing ring 5, and the top ring 3 rises. At this time, the lifting tube 8 rotates on the outer wall of the guide tube 7, and then presses down the pressure ring 4 on the outer wall of the material tube 2, so that the round hole of the pressure ring 4 is connected with the mounting hole 12 and the guide tube 7. Then, the bolt is driven into the round hole of the pressure ring 4 to fix the pressure ring 4 and the top ring 3 together. The upper and lower sealing rings 6 are fitted together to seal the connection of the two fixing rings 5. The pressure ring 4 and the top ring 3 are pressed tightly together to completely seal the gap between the two fixing rings 5. When disassembling, it is only necessary to remove the bolt on the pressure ring 4 and rotate the screw 10 at the bottom of the top ring 3.

[0015] Depending on the amount of waste gas to be treated, the material pipes 2 can be stacked. The connection of the material pipes 2 can also be made by using the pressure ring 4 and the top ring 3 to achieve sealing and quick disassembly, so that the material pipes 2 can be modularized, easy to assemble, improve maintenance efficiency and the adaptability of the spray tower.

[0016] It should be noted that the parts not covered in this utility model are the same as or can be implemented using existing technology; the various drives in this utility model can be implemented by corresponding power structures such as cylinders, oil cylinders, electric cylinders, and motors in conjunction with connecting rods, guide rods, etc., and are not limited to the structures described in the specification and the drawings.

Claims

1. A modular packing bin for a waste gas treatment spray tower, comprising a tower body (1) and a feed pipe (2) and a quick-release assembly installed at the top of the tower body (1) and the feed pipe (2), characterized in that: The quick-release assembly includes a top ring (3), a lifting tube (8), and a screw (10). The material tube (2) is installed above the tower body (1). Fixing rings (5) are fixedly installed at both ends of the material tube (2) and at the top edge of the tower body (1). The fixing ring (5) at the bottom of the material tube (2) and the fixing ring (5) at the top of the tower body (1) are fitted together. The top ring (3) is sleeved on the top outer wall of the tower body (1) and the material tube (2). The screw (10) is movably installed on the outer wall of the tower body (1) and the material tube (2). The lifting tube (8) is fitted to the bottom outer wall of the top ring (3). The screw (10) is fixedly connected to the bottom outer wall of the lifting tube (8).

2. The modular packing bin for the waste gas treatment spray tower according to claim 1, characterized in that: Multiple guide tubes (7) are fixedly installed on the bottom outer wall of the fixing ring (5) at the top of the tower body (1) and the material pipe (2). The multiple guide tubes (7) are evenly distributed on the bottom outer wall of the fixing ring (5). The lifting pipe (8) is sleeved on the outside of the guide tubes (7).

3. The modular packing bin for the waste gas treatment spray tower according to claim 2, characterized in that: A fixing block (9) is fixedly installed on the outer wall of the tower body (1) and the material pipe (2). A threaded hole is opened through the fixing block (9). The screw (10) is threaded inside the threaded hole. A spring (11) is installed between the fixing block (9) and the bottom surface of the lifting pipe (8). The spring (11) is sleeved on the outside of the screw (10).

4. The modular packing bin for the waste gas treatment spray tower according to claim 2, characterized in that: The fixing ring (5) has multiple mounting holes (12), all of which are connected to the guide tube (7). The inner wall of the guide tube (7) is threaded. A pressure ring (4) is fitted on the lower part of the outer wall of the material tube (2). The pressure ring (4) has multiple round holes, which are connected to the mounting holes (12).