A super-wide concrete main beam decoration hanging basket device for a cable-stayed bridge
By designing a decorative hanging basket device for the ultra-wide concrete main beam of the cable-stayed bridge, and utilizing pre-embedded steel plates and a walking system to achieve full coverage of the work platform, the problem that existing equipment cannot cover the work area was solved, thus improving construction efficiency and safety.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- 中国水利水电第七工程局有限公司
- Filing Date
- 2025-06-15
- Publication Date
- 2026-06-19
Smart Images

Figure CN224378707U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of bridge construction equipment technology, specifically the field of cable-stayed bridge construction equipment technology, and in particular, it relates to a decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges. Background Technology
[0002] Cable-stayed bridges are a type of long-span bridge structure. Due to their light weight, high stiffness, and good stability, they are widely used to span large rivers and canyons. Cable-stayed bridges come in a variety of structural styles, are highly aesthetically pleasing, and often serve as landmark structures, enjoying widespread popularity and admiration. Therefore, cable-stayed bridges, including their main beams, require aesthetic decoration, such as painting, installing lighting, and signage.
[0003] Common bridge decoration construction equipment includes aerial work platforms, bridge maintenance vehicles, and suspended platforms. However, these machines are often affected by factors such as the spacing of the stay cables, the height of the bridge, and the width of the main beam. Conventional equipment cannot cover the entire work area, thus failing to meet the needs of the operation.
[0004] Therefore, in order to solve this problem, this utility model proposes a decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges. Summary of the Invention
[0005] In view of the shortcomings of the prior art described above, the purpose of this utility model is to provide a decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges, which solves the technical problem that conventional bridge decoration construction equipment in the prior art cannot cover the entire working surface, thus failing to meet the operational requirements.
[0006] To achieve the above and other related objectives, this utility model provides a decorative hanging basket device for an ultra-wide concrete main beam of a cable-stayed bridge, including a pre-embedded steel plate embedded in the concrete main beam. Two to three sections of rail are welded onto the pre-embedded steel plate. A working platform is detachably connected to the bottom of the concrete main beam via a connecting assembly. Hanging basket hooks are detachably connected to both ends of the working platform. A walking system is fixedly connected to the upper end of each hanging basket hook. The walking system includes at least two rollers. The two rollers are set on the rails, and the two rollers are driven to move by a driving assembly.
[0007] In any of the above embodiments, the preferred embodiment is that the working platform includes a platform steel plate, which is disposed below the concrete main beam. Several distribution beams are welded to the bottom of the platform steel plate, and the distribution beams are arranged laterally on the Bailey beam and fixed to the Bailey beam by snap fasteners.
[0008] Preferably, in any of the above embodiments, a reinforcing rod is provided between the working platform and the hanging basket hook, one end of the reinforcing rod is welded to the platform distribution beam, and the other end is welded to the hanging basket hook.
[0009] In any of the above embodiments, it is preferred that the bottom of the main truss structure of the two hanging basket hooks is respectively welded with a socket beam and a spigot beam, and the socket beam and spigot beam are connected to the Bailey beam through Bailey beam pins.
[0010] In any of the above embodiments, it is preferred that at least two socket reinforcing steel plates are provided at the interface between the socket beam and the Bailey beam, the socket reinforcing steel plates are symmetrically arranged on both sides of the Bailey beam, and a pin hole is provided at the center of the socket reinforcing steel plate.
[0011] In any of the above embodiments, it is preferred that at least two reinforcing steel plates are provided at the interface between the socket beam and the Bailey beam, the reinforcing steel plates are disposed between the Bailey beams, and a pin hole is provided at the center of the reinforcing steel plate.
[0012] In any of the above embodiments, the preferred embodiment is that the connecting assembly includes a boom beam and a temporary boom. The boom beam is located below the work platform. Two sets of lifting holes are symmetrically opened at both ends of the boom beam. Pre-embedded holes are opened on the concrete main beam at positions corresponding to the lifting holes. The two ends of the temporary boom pass through the pre-embedded holes and the lifting openings respectively and are fixed by double nuts.
[0013] Preferably, in any of the above embodiments, the temporary suspension rod is made of threaded steel, and the suspension rod crossbeam is made of double-channel steel.
[0014] In any of the above embodiments, it is preferred that an upper crossbeam is welded to the inner top of each of the two hanging basket hooks, the two rollers are connected by a push seat, the upper crossbeam is welded and fixed to the push seat, and a wedge is provided in the middle of the roller, and a steel wedge is detachably installed in the wedge.
[0015] Preferably, in any of the above embodiments, the drive assembly includes a manual hoist, one end of which is a wire rope fixedly connected to a push base, and the other end is connected to a winch.
[0016] As described above, the decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges of this utility model has the following beneficial effects: the decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges has a simple structure, is easy to process and manufacture, has strong adaptability, low cost, and is not affected by the height of the concrete main beam and the spacing of the stay cables; at the same time, the working platform is located at the bottom of the main beam, is not affected by weather and strong winds, can completely cover the decorative range of the main beam, which is conducive to speeding up the construction progress, improving construction efficiency, and is easy to dismantle later, which can effectively save labor. Attached Figure Description
[0017] Figure 1 This is a side view of the decorative hanging basket device for the ultra-wide concrete main beam of the cable-stayed bridge according to this utility model;
[0018] Figure 2 This is a schematic diagram of the decorative hanging basket hook structure for the ultra-wide concrete main beam of a cable-stayed bridge according to this utility model.
[0019] Figure 3 This is a front view of the decorative hanging basket operation platform for the ultra-wide concrete main beam of the cable-stayed bridge, which is based on this utility model.
[0020] Figure 4 This is a schematic diagram of the decorative hanging basket Bailey beam structure of the ultra-wide concrete main beam of the cable-stayed bridge according to this utility model.
[0021] Figure 5 Front view of the decorative hanging basket walking system for the ultra-wide concrete main beam of the cable-stayed bridge of this utility model;
[0022] Figure 6 Side view of the decorative hanging basket walking system for the ultra-wide concrete main beam of the cable-stayed bridge of this utility model;
[0023] Figure 7 This is a top view of the decorative hanging basket bearing crossbeam of the ultra-wide concrete main beam of the cable-stayed bridge according to this utility model.
[0024] Figure 8 This is a schematic diagram of the decorative hanging basket bearing crossbeam structure of the ultra-wide concrete main beam of the cable-stayed bridge according to this utility model.
[0025] Figure 9 This is a top view of the decorative hanging basket insertion crossbeam of the ultra-wide concrete main beam of the cable-stayed bridge according to this utility model.
[0026] Figure 10 This is a schematic diagram of the decorative hanging basket insertion crossbeam structure of the ultra-wide concrete main beam of the cable-stayed bridge according to this utility model.
[0027] Component designation explanation
[0028] 1-Concrete main beam; 2-Traveling system; 201-Steel wedge; 202-Push seat; 203-Roller; 204-Rail; 205-Connecting steel plate; 206-Embedded steel plate; 207-Wire rope; 208-Manual hoist; 3-Bailey beam; 301-Bailey beam support frame; 302-Bolt hole; 303-Bailey beam pin; 4-Hanging basket hook; 5-Working platform; 501-Platform steel plate; 502-Distribution beam; 503-Guardrail; 6-Reinforcing tie rod; 7-Upper crossbeam; 8-Socket crossbeam; 801-Socket reinforcing steel plate; 9-Socket crossbeam; 901-Socket reinforcing steel plate; 10-Steel ladder; 11-Temporary lifting rod; 1101-Reserved hole; 1102-Double nut; 12-Lifting rod crossbeam. Detailed Implementation
[0029] The following specific embodiments illustrate the implementation of this utility model. Those skilled in the art can easily understand other advantages and effects of this utility model from the content disclosed in this specification.
[0030] Please see Figures 1 to 10 It should be understood that the structures, proportions, sizes, etc., illustrated in the accompanying drawings are merely for illustrative purposes to aid those skilled in the art and are not intended to limit the scope of this invention. Therefore, they have no substantial technical significance. Any modifications to the structure, changes in proportions, or adjustments to size, without affecting the effectiveness and purpose of this invention, should still fall within the scope of the disclosed technical content. Furthermore, the terms "upper," "lower," "left," "right," "middle," and "one" used in this specification are merely for clarity and not intended to limit the scope of this invention. Changes or adjustments to their relative relationships, without substantially altering the technical content, should also be considered within the scope of this invention.
[0031] Please see Figure 1-10 This utility model provides a decorative hanging basket device for an ultra-wide concrete main beam of a cable-stayed bridge, including a pre-embedded steel plate 206 embedded in the concrete main beam 1. Two to three sections of track 204 are welded on the pre-embedded steel plate 206. A working platform 5 is detachably connected to the bottom of the concrete main beam 1 through a connecting component. The two ends of the working platform 5 are detachably connected to hanging basket hooks 4. Each hanging basket hook 4 is fixedly connected to a walking system 2 at its upper end. The walking system 2 includes at least two rollers 203. The two rollers are set on the track 204. The two rollers 203 are driven to move by a driving component.
[0032] In this embodiment, during the construction of the concrete main beam 1, several embedded steel plates 206 are evenly embedded along its length on both sides of the concrete main beam 1. When decorating the concrete main beam 1, firstly, three sections of rail 204 are welded onto the embedded steel plates 206, and rollers 203 are connected to the rails 204. Then, a crane is used to hoist the work platform 5 to the designated height, and the work platform 5 is temporarily fixed below the concrete main beam 1 using a connecting assembly. Next, the hanging basket hook 4 is hoisted as a whole, connecting it to the work platform 5, and then fixedly connected to the walking system 2, completing the installation of the entire device. After installation, the connecting assembly is removed. The driving assembly moves the walking system 2, thereby moving the decorative hanging basket forward to meet the operational needs of all work surfaces. After the hanging basket hook 4 is used, the connecting assembly is reinstalled, and then the decorative hanging basket is removed.
[0033] In this embodiment, the working platform 5 is 2m above the bottom working space of the concrete main beam 1 to facilitate decoration work. The width of the working platform 5 can be set from 0.6 to 2m as needed.
[0034] In this embodiment, three sections of track 204 are used alternately as the decorative hanging basket moves, each section being 3m long. Of course, the use of three sections of track 204 is not limited to alternating use; the appropriate number of tracks 204 can be selected according to the actual construction situation, such as two sections of track 204. Similarly, the length of each section of track 204 is not limited to 3m; it can be within the range of 3 to 6m.
[0035] In this embodiment, in order to increase the stability of the connection between the working platform 5 and the hanging basket hook 4, a reinforcing tie rod 6 is provided between the working platform 5 and the hanging basket hook 4. The two ends of the reinforcing tie rod 6 are welded to the distribution beam 502 and the hanging basket hook 4, respectively.
[0036] In this embodiment, a steel ladder 10 is installed inside the hanging basket hook 4 to facilitate personnel access. The steel ladder 10 is made of φ20 steel bars in a U-shape and welded to the main truss structure of the hanging basket hook 4.
[0037] As a further description of the above embodiment, the working platform 5 includes a platform steel plate 501, which is disposed below the concrete main beam 1. Several distribution beams 502 are welded to the bottom of the platform steel plate 501. The distribution beams 502 are arranged laterally on the Bailey beams 3 and are fixed to the Bailey beams 3 by snap fasteners.
[0038] In this embodiment, the work platform 5, as one of the main load-bearing components, is composed of Bailey beam 3, distribution beam 502, platform steel plate 501, and guardrail 503.
[0039] Among them, Bailey beam 3 is composed of Bailey panels and support frames, and its assembly length is similar to the width of concrete main beam 1.
[0040] The support frame is made of angle steel processed into a rectangle. Bolt holes 302 are opened at both ends of the angle steel. The angle steel is connected into a rectangular support frame by bolts passing through the bolt holes 302.
[0041] The platform steel plate 501 is welded and fixed to the distribution beam 502. The distribution beam 502 is arranged horizontally above the Bailey beam 3 at a certain interval and fixed with buckles. The platform steel plate 501 is a non-slip patterned thin steel plate.
[0042] Meanwhile, to ensure the safety of workers, guardrails 503 are welded and fixed on both sides of the distribution beam 502. The guardrails 503 are 1.5m high.
[0043] As a further description of the above embodiment, the bottom of the main truss structure of the two hanging basket hooks 4 is respectively welded with a socket beam 8 and a socket beam 9, and the socket beam 8 and the socket beam 9 are connected to the Bailey beam 3 by a Bailey beam 3 pin.
[0044] In this embodiment, the hanging basket hook 4 is one of the main load-bearing components, which is welded from steel profiles and includes a main truss structure, a socket beam 8, and a spigot beam 9.
[0045] The bottom of the hanging basket hook 4 is sealed with platform steel plate 501 at the same height as the working platform 5. The platform steel plate 501 is directly welded to the main truss structure for fixation.
[0046] The main truss structure is a supporting beam structure made up of members of different lengths welded together, including vertical members, horizontal members, and diagonal members.
[0047] Both the socket beam 8 and the spigot beam 9 are made of channel steel and serve as the connection structure between the hanging basket hook 4 and the Bailey beam 3 of the working platform 5. The socket beam 8 and the spigot beam 9 are welded and fixed to the bottom of the two main truss structures.
[0048] Two reinforcing steel plates 801 are provided at the interface between the socket beam 8 and the Bailey beam 3. The reinforcing steel plates 801 are symmetrically arranged on both sides of the Bailey beam 3. A pin hole is provided at the center of the reinforcing steel plate 801. The Bailey beam pin 303 passes through the pin hole and connects the Bailey beam 3 to the hanging basket hook 4.
[0049] Two reinforcing steel plates 901 are provided at the interface between the crossbeam 9 and the Bailey beam 3. The reinforcing steel plates 901 are located between the Bailey beams 3. A pin hole is provided at the center of the reinforcing steel plate 901. The Bailey beam pin 303 passes through the pin hole and connects the Bailey beam 3 to the hanging basket hook 4.
[0050] In this embodiment, both the socket reinforcing steel plate 801 and the spigot reinforcing steel plate 901 are 150mm×150mm×20mm steel plates, and a φ50mm pin hole is provided at the center of the steel plate.
[0051] As a further description of the above embodiment, the connecting assembly includes a boom beam 12 and a temporary boom 11. The boom beam 12 is located below the working platform 5. Two sets of lifting holes are symmetrically opened at both ends of the boom beam 12. Pre-embedded holes are opened on the concrete main beam 1 at positions corresponding to the lifting holes. The two ends of the temporary boom 11 pass through the pre-embedded holes and the lifting opening respectively and are fixed by double nuts 1102.
[0052] In this embodiment, when the work platform 5 is installed, multiple sets of connecting components are set up, each set with two temporary hangers 11. The upper end of the temporary hanger 11 passes through the pre-embedded hole on the concrete main beam 1, and the upper part is anchored to the concrete main beam 1 by double nuts 1102. The lower part is anchored to the bottom of the concrete main beam 1 by the hanger beam 12.
[0053] In this embodiment, the temporary lifting rod 11 is made of threaded steel, and the lifting rod crossbeam 12 is made of double-channel steel.
[0054] As a further description of the above embodiment, an upper crossbeam 7 is welded to the inner top of each of the two hanging basket hooks 4, and the two rollers 203 are connected by a push seat 202. The upper crossbeam 7 is welded and fixed to the push seat 202. A wedge opening is provided in the middle of the roller 203, and a steel wedge 201 is detachably installed in the wedge opening.
[0055] In this embodiment, the upper crossbeam 7 is vertically welded to the top of the main truss structure. The upper crossbeam 7 is welded to the push seat 202 between the two rollers 203. The rollers 203 are moved by the drive assembly, thereby moving the work platform 5 to meet the work requirements of the entire work surface.
[0056] In this embodiment, the roller 203 is a steel pulley with an outer diameter of 140mm and an inner diameter of 68mm. Of course, the size of the roller 203 can be adjusted according to the size of the track 204.
[0057] A 67mm diameter wedge is provided in the middle of the roller 203. After the decorative hanging basket is pushed into place, a steel wedge 201 is used to plug the roller 203 to prevent it from continuing to slip, thereby ensuring the stability of the device during operation. The diameter of the wedge is adjusted accordingly based on the inner diameter of the roller 203.
[0058] In this embodiment, both the track 204 and the push seat 202 are made of double-section [20 channel steel. A connecting steel plate 205 is provided between the double-section channel steel. The connecting steel plate 205 is a 190mm×150mm×10mm steel plate with a φ50mm hole in the center.
[0059] As a further description of the above embodiment, the drive assembly includes a manual hoist 208, one end of which a wire rope 207 is fixedly connected to a push seat 202, and the other end is connected to a winch.
[0060] In this embodiment, the wire rope 207 at one end of the manual hoist 208 is connected to the hole in the center of the connecting steel plate 205, and the other end is connected to the winch. The winch drives the manual hoist 208 to pull the push seat 202, thereby driving the decorative hanging basket forward.
[0061] In this device, all the above-mentioned structural steel, channel steel, angle steel and steel plates are made of Q235 steel, and all welding is full welding.
[0062] In summary, the construction process of the decorative hanging basket device for the ultra-wide concrete main girder of the cable-stayed bridge is as follows:
[0063] 1. The hanging basket hook 4, the working platform 5, the walking system 2 and the drive components are processed on the platform below the concrete main beam 1.
[0064] 2. For example Figure 5 , 6 As shown, the track 204 is welded and fixed on the embedded steel plate 206, and the roller 203 and the push seat 202 are installed on the track 204.
[0065] 3. For example Figure 1 , 3 As shown, on the platform below the concrete main beam 1, two cranes are used to hoist the completed work platform 5 to the designated height.
[0066] 4. For example Figure 1 , 3 As shown, the working platform 5 is temporarily fixed below the concrete main beam 1 by the temporary hanger 11 arranged in advance through the hanger crossbeam 12.
[0067] 5. For example Figures 1-10 As shown, the basket hook 4 is hoisted as a whole. The socket beam 8 and the insertion beam 9 at the bottom of the basket hook 4 are aligned with the pin holes of the Bailey beam 3. After alignment, four Bailey beam pins 303 are installed to achieve the connection between the basket hook 4 and the Bailey beam 3.
[0068] 6. For example Figures 1-6 As shown, the upper crossbeam 7 of the hanging basket hook 4 is placed on the push seat 202 and welded firmly. If the gap between the upper crossbeam 7 and the push seat 202 is large during installation, a steel plate can be inserted between the upper crossbeam 7 and the push seat 202 and then welded and fixed.
[0069] 7. For example Figure 1 As shown, two reinforcing tie rods 6 are installed, and the two ends of the reinforcing tie rods 6 are welded and fixed to the distribution beam 502 and the hanging basket hook 4, respectively.
[0070] 8. For example Figure 1 , 3 As shown, remove the temporary hanging rod 11, and the installation of the decorative hanging basket is now complete.
[0071] 9. For example Figure 5 , 6 As shown, a manual hoist 208 is used to pull the pusher 202, which in turn moves the decorative hanging basket forward.
[0072] 10. For example Figures 1-10 As shown, after the decorative hanging basket is used, the temporary hanging rod 11 is reinstalled, and the decorative hanging basket is removed in the reverse order of installation steps 2 to 7.
[0073] In summary, the decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges of this utility model has a simple structure, is easy to process and manufacture, has strong adaptability, and low cost. It is not affected by the height of the concrete main beam or the spacing of the stay cables. Furthermore, the working platform is located at the bottom of the main beam, unaffected by weather and strong winds, and can completely cover the decorative area of the main beam, which helps to accelerate the construction progress, improve construction efficiency, and facilitates later dismantling, effectively saving labor. Therefore, this utility model effectively overcomes the various shortcomings of existing technologies and has high industrial application value.
[0074] The above embodiments are merely illustrative of the principles and effects of this utility model and are not intended to limit the scope of this utility model. Any person skilled in the art can modify or alter the above embodiments without departing from the spirit and scope of this utility model. Therefore, all equivalent modifications or alterations made by those skilled in the art without departing from the spirit and technical concept disclosed in this utility model should still be covered by the claims of this utility model.
Claims
1. A decorative hanging basket device for an ultra-wide concrete main beam of a cable-stayed bridge, comprising a pre-embedded steel plate (206) embedded in the concrete main beam (1), characterized in that: Two to three sections of track (204) are welded onto the pre-embedded steel plate (206). A working platform (5) is detachably connected to the bottom of the concrete main beam (1) via a connecting assembly. The two ends of the working platform (5) are detachably connected to hanging basket hooks (4). A walking system (2) is fixedly connected to the upper end of each hanging basket hook (4). The walking system (2) includes at least two rollers (203). The two rollers are set on the track (204). The two rollers (203) are driven to move by a driving assembly.
2. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 1, characterized in that: The working platform (5) includes a platform steel plate (501), which is located below the concrete main beam (1). Several distribution beams (502) are welded to the bottom of the platform steel plate (501). The distribution beams (502) are arranged laterally on the Bailey beam (3) and fixed to the Bailey beam (3) by buckles.
3. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 2, characterized in that: A reinforcing rod (6) is provided between the working platform (5) and the hanging basket hook (4). One end of the reinforcing rod (6) is welded to the distribution beam (502), and the other end is welded to the hanging basket hook (4).
4. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 2, characterized in that: The bottom of the main truss structure of the two hanging basket hooks (4) is respectively welded with a socket beam (8) and a socket beam (9), and the socket beam (8) and the socket beam (9) are connected to the Bailey beam (3) by a Bailey beam pin (303).
5. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 4, characterized in that: At least two reinforcing steel plates (801) are provided at the interface between the socket beam (8) and the Bailey beam (3). The reinforcing steel plates (801) are symmetrically arranged on both sides of the Bailey beam (3), and a pin hole is provided at the center of the reinforcing steel plate (801).
6. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 4, characterized in that: At least two reinforcing steel plates (901) are provided at the interface between the socket beam (9) and the Bailey beam (3). The reinforcing steel plates (901) are located between the Bailey beams (3), and a pin hole is provided at the center of the reinforcing steel plates (901).
7. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 1, characterized in that: The connecting assembly includes a boom beam (12) and a temporary boom (11). The boom beam (12) is located below the working platform (5). Two sets of lifting holes are symmetrically opened at both ends of the boom beam (12). Pre-embedded holes are opened on the concrete main beam (1) at positions corresponding to the lifting holes. The two ends of the temporary boom (11) pass through the pre-embedded holes and the lifting holes respectively and are fixed by double nuts (1102).
8. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 7, characterized in that: The temporary lifting rod (11) is made of threaded steel, and the lifting rod crossbeam (12) is made of double-channel steel.
9. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 1, characterized in that: The top inner sides of the two hanging basket hooks (4) are each welded with an upper crossbeam (7). The two rollers (203) are connected by a push seat (202). The upper crossbeam (7) is welded and fixed to the push seat (202). A wedge is opened in the middle of the roller (203), and a steel wedge (201) is detachably installed in the wedge.
10. The decorative hanging basket device for ultra-wide concrete main beams of cable-stayed bridges according to claim 9, characterized in that: The drive assembly includes a manual hoist (208), one end of which is a wire rope (207) fixedly connected to a pusher seat (202), and the other end is connected to a winch.