A horizontal moving device for transporting end-hole beam construction trusses
By designing a transverse movement device for transporting the truss used in the construction of the final span beam, the overall movement of the truss is achieved using guide rails and hydraulic cylinder assemblies. This solves the problem of difficult truss dismantling after the construction of the final span beam, and improves construction safety and flexibility.
Patent Information
- Application Number
- CN202522245041.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-23
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-10-23
AI Technical Summary
In the construction of viaducts, after the completion of the last span beam, the truss dismantling is difficult, especially in space-constrained environments, where construction safety risks are high and traditional dismantling methods are difficult to implement.
Design a transverse movement device for transporting the construction truss of the final span beam, including a guide rail, a pin assembly, and a hydraulic cylinder. The hydraulic cylinder pushes the construction truss of the final span beam along the guide rail, which is composed of multiple U-shaped steel rail beams. The pin assembly is detachable, and the hydraulic cylinder provides a smooth thrust to realize the overall transport of the truss.
It reduces the risk of construction workers working at heights in confined spaces, improves construction safety and flexibility, and allows the trusses to be safely dismantled in open areas, reducing construction difficulty and time costs.
Smart Images

Figure CN224953739U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of elevated bridge construction facilities, and more specifically, relates to a transverse movement device for transferring the construction truss of the final span beam. Background Technology
[0002] In the field of elevated bridge construction, trusses, as an important temporary support structure, are widely used in the construction of the final span due to their superior load-bearing performance, small construction site footprint, and convenient modular assembly. However, with the development of modern elevated bridge construction technology and the increasing complexity of the construction environment, existing truss construction technology has gradually revealed some problems that urgently need to be solved in practical applications. Especially when the construction site space is limited, the difficulty of truss dismantling increases significantly after the completion of the final span construction, and the construction safety risks also rise accordingly.
[0003] The main function of the truss is to provide temporary support for the pouring and curing of concrete beams, and to provide an operating platform for construction personnel and equipment. When assembling the truss, firstly, the required number of columns and the length of the crossbeams are calculated based on the design dimensions and weight of the final span beam; then, the length and dimensions of the support foundation, columns, and hydraulic cylinders are designed according to the actual clearance to meet the design elevation requirements. The support foundation must meet the load-bearing capacity requirements, the columns are assembled from standard components of different heights, and the hydraulic cylinders must not exceed their design stroke; finally, the truss is assembled on-site according to the design drawings, and construction begins after acceptance. After construction is completed, it is dismantled according to regulations. The existing technical solution has the following problems: In the construction of single-track or double-track segmental beams, especially in space-constrained environments, the space between the top of the truss and the upper end of the beam is extremely narrow after the final span is constructed. This spatial limitation makes traditional demolition methods difficult to implement. Construction personnel and equipment are easily obstructed by surrounding structures during demolition, and the insufficient operating space increases the difficulty and time cost of the demolition work. For example, in the construction of some urban viaducts, due to the limited space under the bridge, large lifting equipment cannot enter, and construction personnel can only rely on small equipment and manual operation for demolition. During the demolition process, due to the narrow operating space, construction personnel are prone to accidental falls or collisions while working on the truss. Utility Model Content
[0004] To address the aforementioned deficiencies or improvement needs of existing technologies, this utility model provides a transverse movement device for transporting the construction truss of the final hole beam. The construction truss of the final hole beam can be erected on the guide rail of this transverse movement device. After the construction of the final hole beam is completed, the entire construction truss of the final hole beam can be pushed to a sufficiently large space for disassembly using a hydraulic cylinder. The operation is simple and the safety risks are reduced.
[0005] To achieve the above objectives, according to this utility model, a transverse movement device for transferring the construction truss of the final span beam is provided, comprising a jacking assembly, wherein the jacking assembly includes a guide rail, a pin assembly, and a hydraulic cylinder, wherein: The guide rail includes multiple steel rail beams arranged on the same straight line. Each steel rail beam is a U-shaped steel with its opening facing upwards to accommodate the lower end of the final hole beam construction truss and to support the final hole beam construction truss. Any two adjacent steel rail beams are fixedly connected together. Each of the rail beams has two parallel vertical plates and a horizontal plate connecting the two vertical plates. Each vertical plate is provided with at least one row of pin holes, and the pin holes on the two vertical plates are arranged symmetrically. The pin assembly includes a pin and a pin fixing component. One end of the pin passes through a pin hole in a vertical plate, and the other end of the pin passes through a pin hole in another vertical plate. The pin is detachably mounted on the rail beam via the pin fixing component so that the pin can be repositioned on the guide rail. The hydraulic cylinder is placed on the guide rail, the outer shell of the hydraulic cylinder is in contact with the pin, and the output shaft of the hydraulic cylinder is horizontally set and faces the end-hole beam construction truss supported by the guide rail, so as to push the end-hole beam construction truss to move along the length direction of the guide rail.
[0006] Preferably, each rail beam is welded with a connecting block, and any two adjacent rail beams are fixedly connected together by the connecting blocks.
[0007] Preferably, the connecting block is disposed at the end of the rail beam.
[0008] Preferably, the connecting blocks on any two adjacent rail beams are fixedly connected together by bolts.
[0009] Preferably, each of the rail beams has a bolt fixing assembly installed on its vertical plate. The bolt fixing assembly includes a bracket and anchor bolts. The bracket is welded to the rail beam, and the anchor bolts are installed on the bracket to fix the rail beam to a concrete foundation or an I-beam.
[0010] Preferably, multiple sets of bolt fixing assemblies are installed on the vertical plate of each rail beam.
[0011] Preferably, there are multiple hydraulic cylinders and these cylinders are each connected to the same hydraulic pump station.
[0012] Preferably, the pin has through holes at both ends, and a resilient cotter pin is installed at each through hole.
[0013] Preferably, the groove of the guide rail is coated with lubricating oil to facilitate the movement of the construction truss of the final hole beam.
[0014] Preferably, the jacking assembly has two sets, and the two guide rails are parallel to each other.
[0015] In summary, compared with the prior art, the above-described technical solution conceived by this utility model can achieve the following beneficial effects: 1) The present invention provides a transverse movement device for transporting the construction truss of the final hole beam. The device can move the construction truss of the final hole beam as a whole by pushing it with a hydraulic cylinder. The transverse movement device can move the construction truss of the final hole beam to a place with sufficient space for disassembly, avoiding complex operations by construction personnel in a confined space, reducing the risks of high-altitude operations and heavy lifting, and effectively reducing construction safety risks.
[0016] 2) This utility model discloses a transverse movement device for transporting the construction truss of the final span beam. The guide rail is composed of multiple steel rail beams, and its length and arrangement can be flexibly adjusted according to actual construction needs. The detachable design of the pin assembly allows the pin to be moved on the guide rail, enhancing the flexibility and adaptability of construction.
[0017] 3) The present invention provides a transverse movement device for transporting the construction truss of the final span beam. The rail beam is U-shaped steel. The horizontal plate supports the construction truss of the final span beam, providing stable and reliable vertical support for the truss. The two vertical plates accommodate the lower end of the truss, providing crucial lateral guidance and constraint, ensuring that the truss will not overturn or deviate from the track during movement. This integrated support and accommodation design provides a high-rigidity and high-stability track foundation for the smooth movement of heavy trusses.
[0018] 4) This utility model discloses a transverse movement device for transporting the construction truss of the final span beam. The coordinated work of the pin assembly and the hydraulic cylinder cleverly solves the problem of how an actuator with a limited stroke can achieve long-distance translation. The hydraulic cylinder, as a power source, provides a powerful, stable, and easily precisely controllable horizontal thrust. By setting at least one row of pin holes on the vertical plate and a detachable pin assembly, a movable reaction point is provided for the housing of the hydraulic cylinder, enabling the hydraulic cylinder to perform step-by-step pushing of the construction truss of the final span beam, and to transport the construction truss of the final span beam over long distances. Attached Figure Description
[0019] Figure 1 This is a schematic diagram of the truss for the construction of the transfer end-hole beam of this utility model; Figure 2 This is a partial schematic diagram of the hydraulic cylinder connecting pin and the construction truss of the end hole beam in this utility model; Figure 3 This is a schematic diagram of a bolt fixing assembly installed on a steel rail beam in this utility model.
[0020] In all the accompanying drawings, the same reference numerals denote the same technical features, specifically: 1. Guide rail; 2. Rail beam; 3. Connecting block; 4. Pin assembly; 5. Hydraulic cylinder; 6. Bolt fixing assembly; 61. Bracket; 62. Anchor bolt; 7. Construction truss for the final hole beam. Detailed Implementation
[0021] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present utility model and are not intended to limit the present utility model. Furthermore, the technical features involved in the various embodiments of the present utility model described below can be combined with each other as long as they do not conflict with each other.
[0022] Reference Figures 1-3 A transverse movement device for transporting the construction truss of the final hole beam includes a jacking assembly, which includes a guide rail 1, a pin assembly 4, and a hydraulic cylinder 5.
[0023] The guide rail 1 includes multiple steel rail beams 2 arranged on the same straight line. Each steel rail beam 2 is a U-shaped steel with its opening facing upward, used to accommodate the lower end of the final hole beam construction truss 7 and to support the final hole beam construction truss 7. Any two adjacent steel rail beams 2 are fixedly connected together.
[0024] Each of the rail beams 2 has two parallel vertical plates and a horizontal plate connecting the two vertical plates. Each vertical plate is provided with at least one row of pin holes. The pin holes on the two vertical plates are arranged symmetrically. Therefore, the pin holes on the two vertical plates can be used in pairs, which is convenient for installing the two ends of the pin shaft.
[0025] The pin assembly 4 includes a pin and a pin fixing component. One end of the pin passes through a pin hole in a vertical plate, and the other end of the pin passes through a pin hole in another vertical plate. The pin is detachably mounted on the rail beam 2 via the pin fixing component so that the pin can be repositioned on the guide rail 1.
[0026] The hydraulic cylinder 5 is placed on the guide rail 1. The outer shell of the hydraulic cylinder 5 is in contact with the pin. The output shaft of the hydraulic cylinder 5 is horizontally set and faces the end-hole beam construction truss 7 supported by the guide rail 1, so as to push the end-hole beam construction truss 7 to move along the length direction of the guide rail 1.
[0027] When the pin and the hydraulic cylinder 5 work together, the pin is inserted into a pair of pin holes, and the hydraulic cylinder 5 uses this pin as a reaction point to push the truss for one stroke. Then, the hydraulic cylinder 5 retracts, disassembles the pin, and moves it to the next pair of pin holes. By repeating this cycle of pushing, retracting, and changing the reaction point, the construction truss 7 of the last hole beam can be transferred to a place with enough space to facilitate the disassembly of the construction truss 7 of the last hole beam.
[0028] By combining the upward-opening guide rail 1, the adjustable pin, and the hydraulic cylinder 5, the construction team can move the entire end-span beam construction truss 7 from the narrow construction area under the bridge, which is limited by space, to an open dismantling site in a whole, safely, and smoothly. This fundamentally avoids the need to carry out dismantling operations in the small space under the end-span beam, greatly reduces the difficulty of construction, and significantly improves the safety of construction.
[0029] Furthermore, each of the rail beams 2 is welded with a connecting block 3, and any two adjacent rail beams 2 are fixedly connected together by the connecting block 3.
[0030] The connecting block 3 serves as the interface for connecting two steel rail beams 2, and its flatness and positioning holes can be precisely machined in the factory. This ensures that after any two adjacent steel rail beams 2 are connected, the internal elevation and axis of their U-shaped channels can be precisely aligned, forming a smooth and continuous track, which provides the necessary conditions for the smooth movement of the end-span beam construction truss 7.
[0031] Furthermore, the connecting block 3 is disposed at the end of the rail beam 2. By placing the connecting block 3 at the end of the rail beam 2, an end-to-end rigid connection is achieved between adjacent rail beams 2. This connection method allows both pressure and thrust to be transmitted directly from one beam to the next along the axis of the rail beam 2.
[0032] Furthermore, the connecting blocks 3 on any two adjacent rail beams 2 are fixedly connected together by bolts. The use of bolts means that the rail beams 2 can be recycled intact after disassembly. These standard modular rail beams 2 can be transferred to the next contract section or the next project for reuse.
[0033] Furthermore, each of the rail beams 2 has a bolt fixing assembly 6 installed on its vertical plate. The bolt fixing assembly 6 includes a bracket 61 and anchor bolts 62. The bracket 61 is welded to the rail beam 2, and the anchor bolts 62 are installed on the bracket 61 to fix the rail beam 2 to a concrete foundation or I-beam. The anchor bolts 62 anchor the guide rail 1 to the concrete foundation or I-beam below it. The anchor bolts 62 (whether pre-embedded or chemically anchored) provide strong pull-out and shear resistance, effectively transferring the horizontal thrust from the hydraulic cylinder 5 and the vertical load of the truss to the concrete foundation or I-beam.
[0034] This invention forms a structural interface specifically for anchoring by welding a bracket 61 onto the rail beam 2 (especially the vertical plate). This bracket 61 can effectively apply the locking force of the anchor bolts 62 to the rail beam 2.
[0035] Furthermore, multiple sets of bolt fixing assemblies 6 are installed on the vertical plates of each rail beam 2. Through multi-point, distributed anchoring, the overall stability, deformation resistance, and safety redundancy of the guide rail 1 are greatly improved.
[0036] Furthermore, there are multiple hydraulic cylinders 5, each connected to the same hydraulic pump station. By simultaneously applying thrust to multiple support points of the final beam construction truss 7 using multiple hydraulic cylinders 5, the total thrust is ensured to be rationally distributed to the various support structures of the truss, avoiding stress concentration and eccentric force. The connection of these hydraulic cylinders 5 to the same hydraulic pump station ensures simultaneous operation, preventing jamming or overturning accidents caused by asynchronous movement of the two columns. The synchronous jacking of the final beam construction truss 7 by multiple hydraulic cylinders 5 ensures that the truss 7 maintains its original posture throughout the entire movement, moving smoothly and straight along the guide rail 1, eliminating the risk of deflection, jamming, or instability due to asynchronous movement.
[0037] Furthermore, each end of the pin has a through hole, and a resilient cotter pin is installed in each through hole. The resilient cotter pin, relying on its own elasticity, provides strong anti-loosening capability, is vibration-resistant, and prevents the pin from coming out of the pin hole. The resilient cotter pin makes the installation and removal of the pin extremely quick and efficient, which is crucial for pins that need frequent repositioning. Workers can quickly insert or remove the cotter pin using only their hands or a pair of pliers, without any complicated tools. This minimizes the auxiliary work time required for workers to disassemble, move, and reinstall the pin after the hydraulic cylinder 5 completes one stroke, greatly improving the overall efficiency of the stepping jacking mechanism.
[0038] Furthermore, the groove of the guide rail 1 is coated with lubricating oil to facilitate the movement of the final beam construction truss 7. The lubricating oil forms an oil film between the two steel surfaces, transforming dry friction into boundary friction or mixed friction. The coefficient of friction can be easily reduced, which means that the jacking force required by the hydraulic cylinder 5 can be reduced by a factor of two, and also ensures the smooth movement of the final beam construction truss 7.
[0039] Furthermore, the jacking assembly has two sets, with the two guide rails 1 parallel to each other. This allows the lateral movement device to push larger end-hole beam construction trusses 7, such as end-hole beam construction trusses 7 with four columns arranged in a rectangular pattern. The hydraulic cylinders 5 on the two guide rails 1 extend simultaneously. Under the reaction force of the hydraulic cylinders 5, the steel columns of the end-hole beam construction truss 7 slide along the guide rails 1, driving the end-hole beam construction truss 7 to move until the safe stroke of the hydraulic cylinders 5 ends, completing one travel distance of the end-hole beam construction truss 7. By changing the pin holes connected to the pin shafts, the above-mentioned travel process continues until the end-hole beam construction truss 7 travels to the designated position.
[0040] Before installing the rail beam 2, the height of each rail beam 2 should be adjusted by adjusting the height of the concrete foundation below to ensure that the height and linearity are consistent. If necessary, a grouting layer can be used for precise adjustment. The length of the guide rail 1 is determined according to the site conditions until it extends to a place with sufficient space. By moving the end-hole beam construction truss 7 as a whole to an open area, the problem of the difficulty in dismantling the single-rail segment beam truss in the existing technology is solved, and the safety of dismantling construction is improved.
[0041] The specifications and models of the rail beam 2, connecting block 3, pin assembly 4 and bolt fixing device should be reasonably selected according to the overall weight of the truss and the stress of the hydraulic cylinder 5, and regular inspections should be carried out. If necessary, a testing agency can be arranged to conduct systematic testing on each component to ensure the overall structure is safe and reliable.
[0042] Those skilled in the art will readily understand that the above description is merely a preferred embodiment of the present utility model and is not intended to limit the present utility model. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present utility model should be included within the protection scope of the present utility model.
Claims
1. A transverse movement device for transferring a construction truss for a final-span beam, characterized in that, The system includes a jacking assembly, which comprises a guide rail, a pin assembly, and a hydraulic cylinder, wherein: The guide rail includes multiple steel rail beams arranged on the same straight line. Each steel rail beam is a U-shaped steel with its opening facing upwards to accommodate the lower end of the final hole beam construction truss and to support the final hole beam construction truss. Any two adjacent steel rail beams are fixedly connected together. Each of the rail beams has two parallel vertical plates and a horizontal plate connecting the two vertical plates. Each vertical plate is provided with at least one row of pin holes, and the pin holes on the two vertical plates are arranged symmetrically. The pin assembly includes a pin and a pin fixing component. One end of the pin passes through a pin hole in a vertical plate, and the other end of the pin passes through a pin hole in another vertical plate. The pin is detachably mounted on the rail beam via the pin fixing component so that the pin can be repositioned on the guide rail. The hydraulic cylinder is placed on the guide rail, the outer shell of the hydraulic cylinder is in contact with the pin, and the output shaft of the hydraulic cylinder is horizontally set and faces the end-hole beam construction truss supported by the guide rail, so as to push the end-hole beam construction truss to move along the length direction of the guide rail.
2. The transverse movement device for transferring the construction truss of the final span beam according to claim 1, characterized in that, Each rail beam is welded with a connecting block, and any two adjacent rail beams are fixedly connected together by the connecting blocks.
3. A transverse movement device for transferring the construction truss of the final span beam according to claim 2, characterized in that, The connecting block is located at the end of the rail beam.
4. A transverse movement device for transferring the construction truss of the final span beam according to claim 1, characterized in that, Connecting blocks on any two adjacent rail beams are fixed together by bolts and fasteners.
5. A transverse movement device for transferring the construction truss of the final span beam according to claim 1, characterized in that, Each of the rail beams has a bolt fixing assembly installed on its vertical plate. The bolt fixing assembly includes a bracket and anchor bolts. The bracket is welded to the rail beam, and the anchor bolts are installed on the bracket to fix the rail beam to a concrete foundation or an I-beam.
6. A transverse movement device for transferring the construction truss of the final span beam according to claim 5, characterized in that, Multiple sets of bolt fixing assemblies are installed on the vertical plates of each rail beam.
7. A transverse movement device for transferring a construction truss for a final-hole beam according to claim 1, characterized in that, There are multiple hydraulic cylinders, and each of these cylinders is connected to the same hydraulic pump station.
8. A transverse movement device for transferring a construction truss for a final-hole beam according to claim 1, characterized in that, The pin has through holes at both ends, and a resilient cotter pin is installed at each through hole.
9. A transverse movement device for transferring a construction truss for a final-hole beam according to claim 1, characterized in that, The guide rail is coated with lubricating oil to facilitate the movement of the truss used for the construction of the final beam.
10. A transverse movement device for transferring a construction truss for a final-hole beam according to claim 1, characterized in that, The jacking assembly has two sets, and the two guide rails are parallel to each other.