A pressure test and sand washing integrated device

By integrating oil pipe pressure testing and sand flushing operations into a single device, the problem of having to perform these operations in multiple stages in existing technologies has been solved, resulting in reduced costs, shorter cycles, and improved operational efficiency.

CN224982893UActive Publication Date: 2026-11-17CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202522386713.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-11
Publication Date
2026-11-17
Estimated Expiration
2035-11-11

AI Technical Summary

Technical Problem

In existing technologies, tubing pressure testing and sand flushing operations need to be carried out in two separate processes, requiring two trips of tubing strings, which increases operating costs and time, and affects the efficiency and timeliness of operations.

Method used

Design an integrated pressure testing and sand flushing device. By combining pressure testing tools, sand flushing tools, and anti-loss flow tools, the device integrates oil pipe pressure testing and sand flushing operations. The device uses an impact component to open the drain valve to form a circulation channel, completing one cycle of pressure testing and sand flushing of the tubing.

Benefits of technology

The integration of pressure testing and sand flushing operations has reduced operating costs, shortened the construction cycle, and improved the efficiency and effectiveness of operations. It saves 20,000 yuan per well per operation and shortens the operation cycle by 1 day per operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982893U_ABST
    Figure CN224982893U_ABST
Patent Text Reader

Abstract

The utility model discloses a kind of pressure test sand washing integrated devices, including pressure test tool, sand washing tool, prevent losing flow tool, pressure test tool, prevent losing flow tool, sand washing tool are sequentially connected.Prevent losing flow tool includes middle section nipple, lotus plate, lotus plate is set in middle section nipple, and axial through-hole is equipped on lotus plate.Pressure test tool includes upper joint, oil drain, and oil drain is arranged in upper joint interior.Sand washing tool is sand washing pen nib.The device connects construction pipe column, pump truck injects wellbore water into wellbore through construction pipe column during construction, after wellbore is filled with liquid, tubing pressure test is carried out;After pressure test is finished, ground opens stopcock, invests iron bar, opens oil drain and forms circulating flow channel, carries out subsequent sand washing operation, maintains stable construction discharge capacity during sand washing operation, and liquid carries formation sand to ground, completes pressure test and sand washing one trip pipe column operation.The utility model is simple in structure, easy to install, strong in safety, improves time rate time efficiency, reduces operation cost, shortens operation cycle.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of oil (water) well workover technology, specifically to an integrated pressure testing and sand flushing device. Background Technology

[0002] We have now entered the late stage of development of ultra-high water-cut reservoirs. The main development method is strong extraction and strong injection of water-driven oil reservoirs. This development method will gradually lead to a decrease in the cementation strength of sand bodies, which is manifested in more serious formation sand production. Some oil wells have reached the point where they cannot produce without sand control.

[0003] Currently, conventional sand control methods include mechanical and chemical sand control. Mechanical sand control typically refers to directly blocking formation sand migration through filter pipes, or using a filter layer such as expanded clay or gravel around the casing combined with screens to block formation sand. Chemical sand control usually involves injecting resin, pre-coated gravel, or other chemical substances into the formation to fill pores and form a cementing layer, thereby increasing formation strength and inhibiting sand migration. Due to the limited applicability and short effective period of chemical sand control, mechanical sand control remains the primary method.

[0004] Currently, mechanical sand control requires two procedures before construction: First, tubing pressure testing, which aims to ensure the packer sets smoothly during sand control and ensures construction safety. Currently, on-site tubing pressure testing mainly uses a ball-drop pressure method. A check valve or pin-operated drain valve with a pre-fabricated ball seat is connected to the bottom of the tubing string. Well fluid is injected into the tubing to raise the tubing pressure. After pressurization, the design pressure is maintained within a specified time (generally 20-30 MPa, 5-10 minutes) to indicate a successful tubing pressure test. Second, well washing and sand flushing, currently mainly done on-site using reverse washing. A sand flushing pen tip is connected to the bottom of the tubing string. Well washing fluid is injected through the annulus to flush formation sand from the wellbore to the surface, facilitating the smooth insertion of the sand control tubing string.

[0005] Publication (Announcement) No.: CN203559900U, discloses an oil pipe pressure testing device;

[0006] Publication (Announcement) No.: CN223064781U, discloses an oil pipe pressure testing device;

[0007] Publication (Announcement) No.: CN221920898U, discloses a continuous sand flushing and carrying device for protecting oil layers;

[0008] Currently, the existing technology has several problems: the tubing pressure test and sand flushing operations need to be carried out in two separate operations, requiring two sets of tubing to be raised and lowered, and two sets of vehicles to be used. The total cost for these two operations is approximately 40,000 yuan, and the construction period is about 2 days. This affects the timeliness of the operation and generates additional operating costs.

[0009] In summary, the technical solutions, technical problems to be solved, and beneficial effects of the above-disclosed technologies are all different from those of this utility model. For more technical features, technical problems to be solved, and beneficial effects of this utility model, the above-disclosed technical documents do not provide any technical inspiration. Utility Model Content

[0010] In order to overcome the shortcomings of the prior art and solve at least one of the technical problems mentioned in the background art, this utility model provides an integrated pressure testing and sand flushing device.

[0011] To achieve the above objectives, the present invention adopts the following technical solution:

[0012] An integrated pressure testing and sand flushing device includes a pressure testing tool, a sand flushing tool, and an anti-loss flow tool. The pressure testing tool, the anti-loss flow tool, and the sand flushing tool are connected sequentially from top to bottom. The anti-loss flow tool can ensure the connection between the pressure testing tool and the sand flushing tool, and also ensure that the impact component used in the pressure testing device will not be thrown downwards into the well.

[0013] The anti-loss passage tool includes a middle section 3 and a connecting plate 4, with the connecting plate 4 housed within the middle section 3. The connecting plate 4 has an axial through hole 6, which ensures that impacting components cannot pass through the connecting plate 4.

[0014] The pressure testing tool includes an upper connector 1 and an oil drain 2, with the oil drain 2 located inside the upper connector 1. The oil drain 2 is a circular impact-type oil drain.

[0015] The sandblasting tool is a sandblasting pen tip 5.

[0016] The upper connector 1 has an external thread for the oil pipe, and the middle short section 3 has an internal thread for the oil pipe; the sandblasting pen tip 5 has an external thread for the oil pipe. The upper connector 1 is connected to the construction pipe column by threads, the middle short section 3 is connected to the upper connector 1 by threads, and the sandblasting pen tip 5 is connected to the middle short section 3 by threads.

[0017] The test tubing is lowered into the wellbore as per the construction design. The integrated test and sand flushing device is installed at the bottom of the tubing, and a stopcock valve is installed at the top. During construction, the tubing (including the stopcock valve) is connected to the surface construction tank via a large cross-connector at the wellhead to ensure normal operation. Maintaining the construction flow rate, the tubing is pressure tested using forward well-washing fluid. After the test, the stopcock valve is opened, and an iron bar is dropped in. The bar strikes and breaks the drain valve 2, opening it and creating a flow circulation channel. The surface pump truck then pumps the well-washing fluid into the wellbore through the annulus, completing the sand flushing operation through reverse circulation. The formation sand is backflushed to the surface through the tubing, completing the sand flushing operation. This integrated test and sand flushing construction reduces operating costs, shortens the operation cycle, and improves efficiency.

[0018] Compared with the prior art, the present invention has the following advantages:

[0019] This utility model's integrated pressure testing and sand flushing device features a simple structure, convenient installation, and high safety. After connecting the device to the construction tubing, the ground is connected to the ground construction tank via a stopcock valve. During construction, a pump truck injects well-washing water into the wellbore through the construction tubing. Once the wellbore is full of liquid, a tubing pressure test is performed. After the pressure test, the stopcock valve is opened on the ground, an iron rod is inserted, and the copper impact-type drain valve is opened to form a circulation channel, thus enabling subsequent sand flushing operations. During sand flushing, a stable discharge rate is maintained, and the liquid volume carries the formation sand to the surface, completing one tubing operation for pressure testing and sand flushing. This improves efficiency, reduces operating costs, and shortens the operation cycle. It is estimated that the application will be adopted by oilfields on 100 wells annually, saving 20,000 yuan per well in operating costs and shortening the operation cycle by 1 day per well, resulting in an estimated economic benefit of 5 million yuan.

[0020] This invention improves the efficiency and effectiveness of oil (water) well operations, reduces operating costs, shortens the operation cycle, is low-cost, safe to construct, and easy to use. At the same time, it makes the downhole operation technology of oil (water) wells more complete and highly applicable to the field. In the next step, it can be widely promoted and applied in conventional oil (water) well operations. Attached Figure Description

[0021] Figure 1 This is a schematic diagram of a pressure testing and sand flushing integrated device.

[0022] Figure 2 This is a front structural diagram of the oil drain device of an integrated pressure testing and sand flushing device.

[0023] Figure 3 A schematic diagram of the bottom structure of the oil drain device in an integrated pressure testing and sand flushing device.

[0024] Figure 4 This is a schematic diagram of the front structure of the ferrule plate of an integrated pressure testing and sand flushing device.

[0025] In the diagram: 1. Upper connector; 2. Oil drainer; 3. Middle section; 4. Connecting plate; 5. Sandblasting tip; 6. Axial through hole. Detailed Implementation

[0026] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0027] Please see Figures 1 to 4The present invention provides an integrated pressure testing and sand flushing device, which includes a pressure testing tool, a sand flushing tool, an anti-loss flow tool, and an iron bar. The pressure testing tool, the anti-loss flow tool, and the sand flushing tool are connected in sequence from top to bottom. The anti-loss flow tool can ensure the connection between the pressure testing tool and the sand flushing tool, and also ensure that the impact component used in the pressure testing device will not be thrown down into the well.

[0028] The anti-loss circulation tool includes a middle section 3 and a lotus plate 4, with the lotus plate 4 set inside the middle section 3.

[0029] The sandblasting tool is a sandblasting pen tip 5.

[0030] The axially oriented through-hole 4 is provided with axially equal-diameter through holes, which are circular with a diameter of 14mm and have no specific arrangement. The axially oriented through-hole 6 ensures that the impacting component cannot pass through the axially oriented through-hole 4. The axially oriented through-hole 4 has a diameter of 73mm and is connected to the sandblasting pen tip 5.

[0031] The pressure testing equipment includes an upper connector 1 and an oil drain 2, with the oil drain 2 located inside the upper connector 1. The oil drain 2 is a circular, copper impact-type oil drain with a diameter of 73mm.

[0032] The upper connector 1 is connected to the construction pipe column, the middle short section 3 is connected to the upper connector 1, and the sandblasting pen tip 5 is connected to the middle short section.

[0033] The upper connector 1 has an external thread for the oil pipe, the middle short section 3 has an internal thread for the oil pipe, and the sandblasting pen tip 5 has an external thread for the oil pipe. The upper connector 1 is connected to the construction pipe string by threads, the middle short section 3 is connected to the upper connector 1 by threads, and the sandblasting pen tip 5 is connected to the middle short section 3 by threads.

[0034] The oil drainer 2 can be made with different wall thicknesses according to the pressure of the oil pipe test to meet the test requirements. It also has an inner groove at the bottom. A 2m long, 25mm diameter iron rod is inserted and struck against the circular copper impact-type oil drainer 2, causing it to open smoothly. After the circular copper impact-type oil drainer 2 opens, because the diameter of the iron rod is larger than the diameter of the through hole in the coupling plate 4, the iron rod falls onto the coupling plate 4, at which point a circulation channel is formed inside the tubing.

[0035] After the pressure testing and sand flushing integrated device is installed at the bottom of the pressure testing string, the circular copper impact-type oil drain 2 is in the closed state. The circular copper impact-type oil drain 2 can be made with different wall thicknesses according to the pressure of the tubing test to meet the tubing pressure test requirements. The bottom of the circular copper impact-type oil drain 2 has an inner groove to facilitate smooth opening after the rod is dropped. During construction, the pump truck injects well washing water into the wellbore through the construction string. After the wellbore is filled with liquid, positive pressure is applied. After the tubing pressure test is completed, the surface stop valve is opened, and the iron rod is dropped. The circular copper impact-type oil drain 2 breaks after being hit by the iron rod, and the iron rod falls onto the coupling plate 4 and remains in the wellbore, forming a circulation channel. The well washing water sequentially passes through the upper connector 1, the middle short section 3, and the sand flushing pen tip 5 to form a complete flow channel, draining the remaining liquid in the tubing, and at the same time establishing circulation with the large surface tank. The pump truck reverses the flow to bring the well-washing fluid into the wellbore through the annulus of the casing. The fluid carries the formation sand through the sand-washing pen tip 5, the middle short section 3, the upper connector 1, and the construction tubing to the surface, where it enters the surface construction tank to complete the sand-washing operation. This allows the pressure test and sand-washing to be completed in one tubing run.

[0036] All components not discussed in detail in this application, as well as the connection methods of these components, are well-known technologies in this field. They can be directly applied and will not be elaborated further.

[0037] In this utility model, the term "multiple" refers to two or more unless otherwise explicitly defined. The terms "installation," "connection," "linking," and "fixing," etc., should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; "linking" can be a direct connection or an indirect connection through an intermediate medium. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.

[0038] In the description of this utility model, it should be understood that the terms "upper", "lower", "left", "right", "front", "rear", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or unit referred to must have a specific orientation or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.

[0039] In the description of this specification, the terms "one embodiment," "some embodiments," "specific embodiment," etc., refer to a specific feature, structure, material, or characteristic described in connection with that embodiment or example, which is included in at least one embodiment or example of the present invention. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.

[0040] The above description is merely a preferred embodiment of this utility model and is not intended to limit the utility model. Various modifications and variations can be made to this utility model by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this utility model should be included within the protection scope of this utility model.

Claims

1. A pressure testing and sand washing integrated device, comprising a pressure testing tool, a sand washing tool, characterized in that: The application also discloses a lost circulation prevention and circulation tool, and the pressure testing tool, the lost circulation prevention and circulation tool and the sand washing tool are sequentially connected from top to bottom.

2. The integrated pressure testing and sand washing device of claim 1, wherein: The lost circulation prevention and circulation tool comprises a middle short joint (3) and a coupling plate (4), and the coupling plate (4) is arranged in the middle short joint (3).

3. The integrated pressure testing and sand washing device of claim 2, wherein: An axial through hole (6) is arranged on the coupling plate (4), and the axial through hole (6) ensures that the impact piece cannot pass through the coupling plate (4).

4. The integrated pressure testing and sand washing device of claim 2 or 3, wherein: The pressure testing tool comprises an upper joint (1) and an oil bleeder (2), and the oil bleeder (2) is arranged in the upper joint (1).

5. The integrated pressure testing and sand washing device of claim 4, wherein: The upper end of the upper joint (1) is threadedly connected with a construction pipe column, and the upper end of the middle short joint (3) is threadedly connected with the upper joint (1).

6. The integrated pressure testing and sand washing device of claim 2 or 3, wherein: The sand washing tool is a sand washing pen tip (5).

7. The integrated pressure testing and sand washing device of claim 6, wherein: The upper end of the sand washing pen tip (5) is threadedly connected with the middle short joint (3).

Citation Information

Patent Citations

  • Oil pipe pressure test device

    CN203559900U

  • Oil layer protection type continuous sand washing and carrying device

    CN221920898U

  • Oil pipe pressure testing device

    CN223064781U