Methods for securing a structure
The double-head drilling method creates irregular surfaces in the grouting body's receiving space, enhancing anchoring and load-bearing capacity in cohesive soils by interlocking with the soil, addressing the limitations of smooth-surfaced grouting bodies in existing technologies.
Patent Information
- Application Number
- DE102020131395
- Authority / Receiving Office
- DE · DE
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-11-26
- Publication Date
- 2024-11-21
- Estimated Expiration
- 2040-11-26
AI Technical Summary
Existing methods for securing structures in cohesive soils, such as clay or silt, result in grouting bodies with smooth surfaces, leading to low skin friction and inadequate anchoring, requiring costly and effort-intensive subsequent grouting to enhance load-bearing capacity.
A double-head drilling method is employed using an outer and inner drill pipe, where the inner pipe is advanced beyond the outer pipe's drill bit to flush cohesive soil, creating a receiving space with irregular surfaces for the grouting body, enhancing interlocking with the soil.
This method achieves high skin friction and improved anchoring of the grouting body in cohesive soils with minimal effort, eliminating the need for subsequent grouting, thereby increasing load-bearing capacity effectively.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[0001] The invention relates to a method for securing a structure designed to retain terrain, using at least one securing device. The structure is accessible to a drilling rig from a first side, and a second side abuts the ground. A borehole for the securing device is created in the ground through an opening formed in the structure using the drilling rig. The drilling rig used to create the borehole has an outer tube with a drill bit and an inner drill string arranged inside the outer tube, which is movable relative to the outer tube in an axial direction of the borehole. A drilling fluid can be introduced into the borehole via the inner drill string. Drill cuttings can be removed by means of the drilling fluid via an annular space formed between the outer tube and the inner drill string.Using the drilling rig, a receiving space for a grout body of the safety device is created in the ground by drilling the borehole.
[0002] DE 42 42 668 A1 describes a method for producing a grouted anchor, in which a borehole is drilled into the ground and in which a setting grout is injected into the lower part of the borehole to create the grout body of the anchor. The surrounding soil is cut, forming drill cuttings, and the setting grout is mixed with the drill cuttings remaining in the borehole.
[0003] EP 0 543 140 A2 describes a drilling device with a pipe shell having a ring crown and an inner pipe which on the one hand has a percussion crown with a cutting attachment and on the other hand has nozzles in a section projecting beyond the ring crown for introducing a suspension with binder into soil masses to be drilled through.
[0004] JP 2001-140 253 A describes the introduction of a soil improvement material in the form of a cement suspension into a soil material via nozzles which are part of an internal string of a drilling rig.
[0005] JP H06-248 645 A describes a method in which, during the withdrawal of a drill string, a borehole previously produced by means of a drill string is enlarged in a radial direction by means of water escaping from the drill string under high pressure.
[0006] In civil engineering, it is common practice to secure structures designed to retain terrain, such as excavation walls, using stabilizing devices like grouted anchors or micropiles. The use of grouted anchors was regulated by DIN EN 1537 at the time of filing this patent application, while the use of micropiles, i.e., piles with small diameters or micropiles, is currently regulated by DIN EN 14199.
[0007] A borehole for installing such a support device, for example a grouted anchor or a micropile, into the ground supported by the structure can be created, in particular, using the so-called double-head drilling method or overburden drilling method. In the double-head drilling method or overburden drilling method, two concentrically arranged drill strings are inserted into the ground or terrain, namely an outer casing with a drill bit and an inner casing located inside the outer casing, which also has a drill bit or drill head, using a rotating or rotating / percussive action. Water is introduced into the borehole via the inner casing as a flushing medium to remove the drill cuttings.The water then flows back upwards together with the drill cuttings or drill dust in a ring-shaped cavity and thus out of the borehole, which is formed between the outer pipe and the inner drill string.
[0008] DE 10 2006 059 171 B3 describes a drilling device for double-head drilling and a method for creating a borehole in the ground using such a drilling device. It is stated that, in double-head drilling, the two drill strings of the drilling device can be set into rotation independently of each other, and that the inner drill string, together with its drilling tool, is axially displaceable relative to the outer drill pipe or outer tube.
[0009] Another method and device for double-head superimposed drilling are described in EP 0 860 582 A1.
[0010] Other drilling methods for creating boreholes for safety devices such as grouted anchors or micro-piles in the field include simple cased methods or rotary drilling methods, uncased self-drilling methods or direct drilling methods, auger drilling methods, deep drilling methods, or down-the-hole hammer drilling methods.
[0011] When a borehole for a grouted body, such as a grouted anchor, is created in soil using the double-head drilling method, the grouted body exhibits varying surface roughness depending on the grain size of the soil material. Therefore, if the borehole is created in granular soil such as gravel or sand, the grouted body will have a comparatively irregular surface. This generally results in good bonding between the soil surrounding the borehole and the grouted body.
[0012] In cohesive soils, particularly stiff and firm cohesive soils such as consolidated clay soils, but also loam or silt soils, the grout body of the sealing device formed in the borehole is expected to have a comparatively smooth outer surface due to the double-head drilling method used to create the borehole. With such a smooth exterior, relatively low skin friction between the grout body and the surrounding cohesive soil is to be expected.
[0013] In civil engineering, it is known to increase the load-bearing capacity or skin friction of the grout body of a grouted anchor by performing a post-grouting procedure. In this process, a grout suspension is injected at high pressure into the not yet fully hardened grout body via a post-grouting line attached to a tension member or load-bearing member of the grouted anchor, thus locally fracturing the grout body. This aims to increase the skin friction of the grout body, at least at specific points or in certain areas.
[0014] On the one hand, such regrouting is only of limited effectiveness with regard to the desired increase in the load-bearing capacity of the grouted anchor. On the other hand, such regrouting is associated with an undesirably high level of effort.
[0015] The object of the present invention is to provide a method of the type mentioned above by which improved anchoring of the grout body in a cohesive soil can be achieved in a particularly cost-effective manner.
[0016] This problem is solved by a method with the features of claim 1. Advantageous embodiments with expedient further developments of the invention are specified in the dependent claims and in the following description.
[0017] In the inventive method for securing a structure by means of at least one securing device, the structure is designed to retain a slope. The structure is accessible to a drilling rig from a first side. A second side of the structure borders a cohesive soil of the slope. Using the drilling rig, a borehole for the securing device is created in the cohesive soil via at least one opening formed in the structure. The drilling rig used to create the borehole has an outer tube with a drill bit and an inner drill string arranged inside the outer tube. The inner drill string is movable relative to the outer tube in an axial direction of the borehole. A drilling fluid can be introduced into the borehole via the inner drill string. Drill cuttings can be removed by means of the drilling fluid via an annular space formed between the outer tube and the inner drill string.During the drilling process, the drilling rig creates a receiving space in the cohesive soil for a grout body of the sealing device. During this process, the position of the outer casing is temporarily maintained at least once along the axial direction of the borehole. Meanwhile, a free end of the inner drill string is advanced beyond the drill bit of the outer casing into the cohesive soil. The drilling fluid, in the form of water, flushes cohesive soil from the surrounding area at the free end of the inner drill string. This enlarges a portion of the receiving space radially beyond the outer surface of the outer casing.
[0018] After temporarily maintaining the position of the outer pipe, a second section of the receiving chamber is created by inserting both the outer pipe and the inner drill string into an end wall of the section. The diameter of this second section essentially corresponds to the outer diameter of the outer pipe. Thus, the second section, whose diameter again essentially corresponds to the outer diameter of the outer pipe, adjoins the at least one section of the receiving chamber, which is enlarged radially beyond the outer surface of the outer pipe. In this way, the second section also contributes to anchoring the grout body in the cohesive soil after the grout material has been introduced into the receiving chamber, which, after hardening, forms the grout body.
[0019] After creating the second section of the receiving chamber, the position of the outer casing is temporarily maintained at least once more in the axial direction of the borehole, while the free end of the inner drill string is advanced further into the cohesive soil beyond the drill bit of the outer casing. During this process, cohesive soil is again flushed from the surrounding area by the drilling fluid in the region of the free end. This creates a third section of the receiving chamber extending radially beyond the outer surface of the outer casing. Subsequent injection of grout into this third section of the receiving chamber then forms a grout body that fills two sections of the receiving chamber that extend radially beyond the outer surface of the outer casing.This allows for a particularly good interlocking of the grout body with the cohesive soil surrounding the grout body.
[0020] When, after the grouting material has been introduced into the receiving chamber and hardened, the grout body of the securing device is formed, which also fills the section of the receiving chamber that extends radially beyond the outer pipe's outer surface, the grout body is particularly well anchored in the cohesive soil. This is because, despite the borehole's formation in the cohesive soil, the receiving chamber for the grout body does not have a smooth or axially flat surface. Rather, the wall of the receiving chamber for the grout body, and thus also the surface of the grout body itself, is stepped. At least in the section where the receiving chamber for the grout body extends radially beyond the outer pipe's outer surface, the grout body formed in the receiving chamber interlocks with the cohesive soil.
[0021] This interlocking of the grout body with the cohesive soil results in exceptionally high skin friction between the grout body and the cohesive soil. This, in turn, leads to improved anchorage of the grout body in the cohesive soil and increased load-bearing capacity of the stabilizing device. Furthermore, this improved anchorage can be achieved in a particularly cost-effective manner, as it eliminates the need for the time-consuming process of subsequent grouting, which, in principle, can also be used in cohesive soil to increase the load-bearing capacity of the stabilizing device or the grout body itself.
[0022] Consequently, in cohesive soils such as clay soils, loam soils or silt soils, the grout body of the safety device can be produced in a very cost-effective and simple manner by forming at least one part of the receiving space, which is enlarged in the radial direction beyond the outside of the outer pipe, and which has the increased skin friction with the cohesive soil and the improved anchoring in the cohesive soil by which the grout body is surrounded.
[0023] The method is based, in particular, on the understanding that, in the double-head drilling method achievable with the drilling rig, it is fundamentally possible for the inner drill string to advance, i.e., to continue its advance in the axial direction of the borehole beyond the drill bit of the outer casing. For example, such advance of the inner drill string can be carried out in double-head drilling if an obstacle is encountered in the ground to be drilled. Otherwise, in the double-head drilling method, care is usually taken to ensure that the outer casing or drill string and the inner drill string run essentially parallel or are at the same level while the borehole is being constructed.
[0024] Especially when a borehole for the grouting device is created in granular soil such as sand or gravel using the double-head drilling method, every effort is made to prevent the inner drill string from advancing. This is because it is feared that otherwise, the soil surface in the granular soil could collapse axially in front of the drill bit of the outer casing. This is undesirable, as such a collapse is accompanied by local soil disturbance. And local disturbance can, in turn, lead to undesirable soil loosening. The latter is detrimental to the secure anchoring of the grouting element in the soil in which the borehole is being constructed.
[0025] However, when creating the receiving space for the grout body in cohesive soil, such an axial collapse of the soil surface in front of the drill bit of the outer pipe is not, or hardly, a concern. This is especially true if the cohesive soil is relatively stiff and firm.
[0026] When creating the receiving space for the grout body using the drilling rig designed for the double-head drilling method, it can be provided, in particular, that the outer pipe or outer drill string and the inner drill string rotate in opposite directions while these drilling elements of the rig are inserted into the cohesive soil, either rotating or rotating and impacting. In this way, the receiving space with the irregular outer contour for the respective grout body of the securing device can be created particularly easily, both when the at least one securing device is designed as a grouted anchor and when the at least one securing device is designed as a grouted pile or micro-grouted pile.
[0027] Preferably, after temporarily maintaining the position of the outer casing, the drill bit of the outer casing is first brought to a substantially equal height with the free end of the inner drill string in the axial direction of the borehole. Subsequently, the second section of the receiving chamber is constructed. This method ensures particularly well that the drill cuttings generated during the construction of the second section are reliably discharged via the annular space formed between the outer casing and the inner drill string. Consequently, it is largely prevented that the previously constructed section of the receiving chamber, which extends radially beyond the outer surface of the outer casing, is partially refilled with drill cuttings generated during the construction of the second section.
[0028] Preferably, in the axial direction of the borehole, a plurality of radially enlarged sections of the receiving chamber are produced in an alternating sequence with sections of the receiving chamber whose diameter essentially corresponds to the outer diameter of the outer pipe. In this way, it can be achieved that the grout body occupies a correspondingly large number of radially enlarged sections of the receiving chamber, as well as a similarly large number of intermediate sections in which the diameter of the receiving chamber essentially corresponds to the outer diameter of the outer pipe. This promotes very good interlocking of the grout body with the cohesive soil.
[0029] Preferably, at least one section of the receiving chamber, enlarged radially beyond the outer diameter of the outer pipe, is manufactured with a maximum equivalent diameter that is at least 10% larger than the outer diameter of the outer pipe. This results in a significant expansion of the receiving chamber in this section compared to the outer diameter of the outer pipe. Consequently, the grout material arranged in this section becomes very firmly embedded in the cohesive soil once the grout is manufactured or formed.
[0030] In this context, the equivalent diameter is understood to be the clear cross-section of the recording space in the radially enlarged section which corresponds to the area of a circle with the same area as that of the clear cross-section.
[0031] Due to the creation of the enlarged diameter section of the receiving chamber by flushing or excavating cohesive soil from the site, it can be assumed that this radially enlarged section of the receiving chamber has a less uniform external shape than would be the case if a section of the receiving chamber were formed in the cohesive soil using a rotating outer pipe. An irregular inner surface of the enlarged section of the receiving chamber, and consequently an irregular outer surface of the grout body within this radially enlarged section, is advantageous with regard to the anchoring of the grout body in the cohesive soil and / or the interlocking of the grout body with the cohesive soil.
[0032] The improved anchoring of the grout body in the cohesive soil can be achieved particularly well if at least one section of the receiving space, enlarged in the radial direction beyond the outside of the outer pipe, is produced with a maximum equivalent diameter that is at least 25%, preferably at least 50%, larger than the outer diameter of the outer pipe.
[0033] In particular, it can be provided that at least one section of the receiving chamber, enlarged radially beyond the outer surface of the outer pipe, is manufactured with a maximum equivalent diameter approximately twice the outer diameter of the outer pipe. This ensures, on the one hand, very good interlocking of the grout body with the cohesive soil. On the other hand, the radially enlarged section of the receiving chamber does not have such a large volume that significant incursion of the surrounding cohesive soil into this section of the receiving chamber would be a concern.
[0034] Preferably, the at least one section of the receiving chamber, enlarged radially beyond the outer surface of the outer pipe, is manufactured with a length in the axial direction of the borehole that is essentially equal to the length of the at least one further section, the diameter of which essentially corresponds to the outer diameter of the outer pipe. This ensures, firstly, a very regular interlocking of the grout body with the soil. Secondly, it ensures that the radially enlarged sections of the receiving chamber are not formed at excessively close intervals along the axial direction of the borehole. This is also advantageous with regard to anchoring the grout body formed in the receiving chamber to the surrounding cohesive soil.
[0035] For example, the length of the radially enlarged section of the receiving chamber, extending beyond the outer casing, can be approximately 50 cm to 60 cm. This is advantageous with regard to the axial displacement of the inner drill string relative to the outer casing, a feature of conventional or standard drilling rigs suitable for double-head drilling. Furthermore, this provides a length or extent of the radially enlarged section of the receiving chamber in the axial direction of the borehole that is beneficial for anchoring the grout body in the cohesive soil and thus for increasing the load-bearing capacity of the grout body or the securing device.
[0036] Preferably, at least one section of the receiving space, enlarged radially beyond the outer surface of the outer tube, is formed at least in the region of a free end of a load-bearing member of the securing device. This is because anchoring in the cohesive soil in this end region of the load-bearing or tension member of the securing device is particularly advantageous for securing the structure designed to retain the terrain. This is especially true if the securing device is designed as a grouted anchor.
[0037] When the securing device is designed as a grouted pile or micro-grouted pile, the load-bearing or tension member of the grouted pile can be provided with the grout body along its entire length. Here, too, preferably at least in the area of the free end of the load-bearing or tension member, at least one section of the receiving space, enlarged radially beyond the outside of the outer tube, is filled by a corresponding section of the grout body.
[0038] Preferably, at least a partial area of the load-bearing member is surrounded by the grout body, which is formed by the hardened grout material, after a grouting material has been introduced into the receiving space.
[0039] Particularly when the securing device is designed as a grouted anchor, it is sufficient to embed only that portion of the load-bearing or tension member in the grout body which encompasses the free end of the load-bearing or tension member. In contrast, when securing a structure designed to retain the terrain using a grouted pile or micropile, the grout body can extend over the entire length of the load-bearing or tension member of this securing device. Accordingly, the specific structural conditions can be appropriately considered with regard to surrounding at least the portion of the load-bearing member with the grout body.
[0040] Preferably, another free end of the load-bearing element is fixed to the structure in the area of the opening. In this way, the securing device can fulfill its function of securing or anchoring the structure.
[0041] When the securing device is designed as a grouted anchor, the load-bearing or tension member can be tensioned as soon as the grout has hardened. In contrast, when the securing device is designed as a grouted pile or micro-grouted pile, the tensile load on the load-bearing or tension member is achieved primarily by movement of the free end of the load-bearing or tension member that is connected to the structure.
[0042] The structure can, for example, be designed as an excavation wall, which supports or reinforces the terrain adjacent to the excavation wall. Additionally or alternatively, the structure can be designed as a retaining wall at a drop in elevation. In this case, the structure ensures the stable slope of the drop. Furthermore, the structure can be designed as a quay wall or bank reinforcement, for example, in the area of a landing stage on a waterway or similar. Additionally or alternatively, a structure designed as a quay wall can be secured or anchored by means of at least one securing device. In such a case, the improved anchoring of the grout body in the cohesive soil of the terrain supported by the quay wall can also be advantageously utilized.
[0043] However, beyond the exemplary uses or applications of the structure mentioned here, it is also possible to design the structure in ways that allow the advantages of the method to be used in a particularly favorable manner.
[0044] When a structure is situated on a terrain, it is designed to retain the terrain. The structure is secured by at least one stabilizing device and is accessible from a first side of the structure to a drilling rig. The drilling rig comprises an outer casing with a drill bit and an inner drill string arranged inside the outer casing. The inner drill string is movable relative to the outer casing in the axial direction of a borehole created by the drilling rig. A drilling fluid can be introduced into the borehole via the inner drill string, allowing the removal of drill cuttings through an annular space formed between the outer casing and the inner drill string. A second side of the structure borders a cohesive soil. The structure has at least one through-hole through which the borehole for the stabilizing device is created in the cohesive soil using the drilling rig.A receiving chamber for a grout body of the sealing device is formed in the cohesive soil. At least one section of this receiving chamber extends radially beyond the outer surface of the outer casing. This section is created by temporarily maintaining a fixed position of the outer casing in the axial direction of the borehole at least once during the formation of the receiving chamber, while a free end of the inner drill string is advanced further into the cohesive soil beyond the drill bit of the outer casing. During this process, cohesive soil is flushed out from the surrounding area by means of the drilling fluid, which is water, in the region of the free end of the inner drill string.
[0045] The creation of at least one section of the receiving chamber, which is enlarged radially beyond the outer surface of the outer tube, is based on flushing out the cohesive soil from the surrounding terrain. As a result, the inner surface of the receiving chamber in this radially enlarged section exhibits a surface texture attributable to the flushing out of the cohesive soil. Accordingly, this surface texture differs from that of an inner surface of the receiving chamber created by inserting or driving the rotating outer tube into the cohesive soil. Consequently, the method of its creation can be determined from the surface texture of the inner surface of the receiving chamber.
[0046] With this type of structure placement on the terrain, improved anchoring of the grout body in the cohesive soil within the receiving area is achieved in a particularly cost-effective manner. This is because subsequent grouting of the grout body is unnecessary, yet the skin friction of the grout body is exceptionally high, primarily due to the interlocking of the grout body with the cohesive soil.
[0047] The features and combinations of features mentioned above in the description, as well as those subsequently mentioned in the figure description and / or shown in the figures alone, are not only usable in the combinations specified, but also in other combinations or on their own, without departing from the scope of the invention. Thus, embodiments that are not explicitly shown or explained in the figures, but which can be derived and generated from the explained embodiments by separate combinations of features, are also to be considered as encompassed and disclosed by the invention. Thus, embodiments and combinations of features that do not exhibit all the features of an originally formulated independent claim are also to be considered disclosed.Furthermore, embodiments and combinations of features, in particular those set out above, are to be considered disclosed which go beyond or deviate from the combinations of features set out in the cross-references of the claims.
[0048] Further advantages, features and details of the invention will become apparent from the claims, the following description of preferred embodiments, and the drawings. These show: Fig. 1 schematically the creation of a borehole in terrain supported or retained by means of an excavation wall, wherein a drilling rig designed to carry out a double-head drilling process is used to create the borehole; Fig. 2 in an enlarged partial view the drill strings of the drilling rig according to Fig. 1; Fig. 3 in a schematic view the production of a toothed grout body in the borehole, which is formed in the terrain by means of the drilling rig designed to carry out the double-head drilling method; Fig. 4 one of the steps in the construction of the borehole according to Fig. 3, wherein a section of a receiving space for the grout body is produced by flushing out soil material, which is enlarged in the radial direction; Fig. 5 a further step during the production of the borehole for the toothed grouting body according to Fig. 3; Fig. 6 a further step in the production of the borehole for the toothed grouting body according to Fig. 3; Fig. 7. Partially inserted into the borehole according to Fig. 3 inserted grouted anchors, which comprise the grouted body interlocked with the ground and a load-bearing element; and Fig. 8 in a schematic view the excavation wall secured or anchored by means of the grouted anchor, wherein the grouted anchor engages the toothed grout body according to Fig. 7.
[0049] In Fig. Figure 1 shows how a borehole 18 is created in terrain 10, which is retained or supported by a structure. As an example of the structure designed to retain or support the terrain 10, the following is shown in Fig. Figure 1 schematically shows a construction pit wall 12. However, the following explanations also apply if the structure is, for example, a retaining structure to support a drop in elevation, a riverbank wall, a quay wall, or the like.
[0050] In a manner known per se, the following is carried out in a cohesive soil 14 of the site 10, for example in a clay soil, in particular in a comparatively strongly consolidated and stiff clay soil, by means of a Fig. The borehole 18 was created using the drilling rig 16 shown in Figure 1. A securing device, for example in the form of a grouted anchor 20 (see Figure 1), is then installed in the borehole 18. Fig. 8) arranged, which serves to anchor or secure the excavation wall 12.
[0051] The drilling rig 16 is designed to perform a so-called double-head drilling process or overburden drilling process. Accordingly, the drilling rig 16 comprises drilling elements or drill strings in the form of an outer tube 22, which has a drill bit 24 designed as a ring drill bit at its free end, and in the form of an inner drill string 26. The inner drill string 26 is thus arranged inside the outer drill string or outer tube 22, and it also has a drill bit or drill head 28 at its free end (compare Fig. 2).
[0052] In Fig. Figure 8 shows a passage opening 78 formed in the excavation wall 12. Through such a passage opening 78, the drilling elements of the drilling rig 16, in the form of the outer casing 22 and the inner drill string 26, can be inserted into the cohesive soil 14 during the construction of the borehole 18 (compare Figure 8). Fig. 3) Depending on the material or materials from which the structure intended to retain the terrain 10 is formed, this passage opening 78 can be produced in different ways in the structure, in this case in the excavation wall 12.
[0053] For example, from Fig. 3 and out Fig. It is further evident from Figure 8 that the structure in the present case, designed as the excavation wall 12, is accessible from a first side 72 for the drilling rig 16, while the cohesive soil 14 of the site 10 borders on a second side 74 of the excavation wall 12.
[0054] As in Fig. 1 and in Fig. As illustrated by arrows 30, when drilling with the drilling rig 16, the outer pipe 22 and the inner drill string 26 can rotate in opposite directions. The outer pipe 22 and the inner drill string 26 can be inserted into the ground 14 by rotating or by rotating and impact.
[0055] In the double-head drilling method described below, a flushing medium, in this case water 32, is introduced into the borehole 18 via the inner drill string 26 of the drilling rig 16 to flush out drill cuttings from the borehole 18. This water 32 is in Fig. 2 schematically illustrated by an arrow, however in Fig. 3 is not shown separately for the sake of clarity. Using water 32, drill cuttings or drill dust are carried away from the borehole 18 via an annular space 34, which is formed between the outer casing 22 and the inner drill string 26 (compare Fig. 2 and Fig. 3).
[0056] For the production of the grouted anchor 20, by means of which the excavation wall 12 is to be secured, in the cohesive soil 14 of the site 10, the double-head drilling method, which can be carried out using the drilling rig 16, is employed in a particularly advantageous manner. This will first be shown schematically using the following: Fig. 3 and then explained in more detail with reference to the other characters.
[0057] In Fig. Figure 3 schematically shows both the grouted anchor 20, which is placed in the borehole 18 after the borehole 18 has been drilled for the purpose of securing or anchoring the excavation wall 12, and the drilling rig 16 during the drilling of the borehole 18. In reality, the grouted anchor 20 is inserted into the borehole 18 after the borehole 18 has been completed.
[0058] The grouted anchor 20 comprises a tension member or load-bearing member 36 and a grout body 38. The grout body 38 is formed from a hardened grout material 40, which can be provided, for example, in the form of a cement mortar suspension or the like, and which is injected at least into a bottom or end area of the borehole 18.
[0059] When constructing the borehole 18 in the cohesive soil 14, the problem arises that the outer wall of the grout body 38 is typically relatively smooth. Such a smooth-surfaced grout body 38 exhibits low surface friction. Therefore, using a grout anchor 20, which has a grout body 38 with a smooth outer surface, a less effective anchorage of the excavation wall 12 can be achieved in the cohesive soil 14 than with the [other method]. Fig. The case is as shown schematically in the 3 grout bodies 38. Because the one in Fig. The grout body 38 of the grouted anchor 20 shown in Figure 3 is designed as a grout body interlocking with the cohesive soil 14. Accordingly, an outer surface of the grout body 38 is stepped. The production of this grout body 38 with the stepped surface is intended to be particularly advantageous with regard to Fig. 4 to Fig. 6 will be explained in more detail.
[0060] According to Fig. 4. During the construction of the borehole 18 in the cohesive soil 14, the outer drill string or outer casing 22 is deliberately held in place for a period of time. In other words, while forming a receiving space 42 for the grout body 38, the position of the outer casing 22 in the axial direction 44 of the borehole 18 is temporarily maintained unchanged, with the axial direction 44 being approximately in Fig. 3 and in Fig. 4 is illustrated by an arrow. In contrast, a free end 46 of the inner drill string 26, formed by the drill head 28 of the inner drill string 26, is inserted further into the cohesive soil 14 beyond the drill bit 24 of the outer pipe 22. This is shown schematically in Fig. 4 illustrates in which of the in Fig. The drill head 28 shown is not illustrated in detail for the sake of clarity.
[0061] By means of the flushing medium, in the form of water 32, cohesive soil 14 is flushed or washed out of the ground 10 in the area of the free end 46 or the drill head 28 of the inner drill string 26. In this way, a section 48 of the receiving chamber 42 is enlarged radially in the borehole 18 or the outer casing 22 beyond an outer surface 50 of the outer casing 22. The inner drill string 26 is thus temporarily advanced, and cohesive soil 14 located in front of the drill bit 24 of the outer casing 22 is flushed out of the ground 10 with high water pressure, for example, with a water pressure of more than 20 bar. This creates a section 48 of the receiving chamber 42 which is enlarged radially.In this first section 48 of the receiving space 42, a radially enlarged section or area of the grouting body 38 is formed by introducing the grouting material 40 into the bore 18 (compare . Fig. 7 and Fig. 8).
[0062] In another, schematically in Fig. In step 5 of the borehole production process shown, the drill bit 24 of the outer casing 22 is first brought to a substantially equal height with the free end 46 of the inner drill string 26. Therefore, preferably the outer casing 22 is also first advanced in the axial direction 44 of the borehole 18, so that the drill head 28 of the inner drill string 26 and the drill bit 24 of the outer casing 22 or outer drill string are again running almost parallel.
[0063] Subsequently, both the outer tube 22 and the inner drill string 26 are inserted into an end-face boundary wall 52 of the section 48 (compare Fig. 4), and the drilling of the borehole 18 in the cohesive soil 14 is continued using the double-head drilling method. Accordingly, a second section 54 of the receiving space 42 for the grout body 38 is produced in the cohesive soil 14 (compare Fig. 5) Here, a diameter 56 of the second section 54 essentially corresponds to an outer diameter of the outer tube 22.
[0064] In contrast, the equivalent diameter 58 of the first section 48 is significantly larger than the outer diameter of the outer tube 22. In the figures, the first section 48 is schematically depicted as having a very regular shape, so that the equivalent diameter 58 corresponds approximately to the diameter of the outer tube 22. Fig. The diameter of the receiving chamber 42 in the first section 48, shown in Figure 5 and depicted in cross-section, corresponds to the actual diameter. However, it is likely that the leaching or flushing out of the cohesive soil 14 from the terrain 10 in the first section 48 forms a chamber for the grout material 40, which has an irregularly shaped interior and thus a substantially non-constant diameter.
[0065] In Fig. Figure 6 shows a further step in the production of the borehole 18 in the cohesive soil 14. Here, the outer casing 22 is again temporarily held in place with respect to the axial direction 44 of the borehole 18, or rather, the position of the outer casing 22 in the axial direction 44 of the borehole 18 is temporarily maintained unchanged. Meanwhile, the free end 46 of the inner drill string 26 is again drilled further into the cohesive soil 14 beyond the drill bit 24 of the outer casing 22.
[0066] By means of the water 32 emerging from the inner drill string 26 (compare Fig. 2) Another section 60 of the receiving space 42 for the grout body 38 is now produced by flushing or washing out cohesive soil 14 from the site 10. In this, according to Fig. In the third section 60 of the receiving chamber 42, the receiving chamber 42 is again enlarged radially beyond the outer surface 50 of the outer tube 22. In this third section 60, the receiving chamber 42 again has the equivalent diameter 58, which is larger than the diameter 56 of the second section 54 (compare Fig. 5).
[0067] The one with reference to Fig. 4 to Fig. The process described in section 6 for creating borehole 18 can be repeated several times. This is due to Fig. Figure 7 shows a schematic representation of the receiving space 42 of the borehole 18 filled by the grout body 38. Fig. Figure 7 also shows the load-bearing member 36 or tension member of the grouted anchor 20.
[0068] Furthermore, it is from Fig. Figure 7 shows how the grout body 38 of the grout anchor 20 fills the chambers of the receiving space 42, which have different sizes or diameters in the radial direction. Accordingly, in Fig. 7 showed that the first section 48, the second section 54 and the third section 60 of recording space 42 (compare Fig. 6) are filled with the grouting material 40, which after hardening forms the grouting body 38.
[0069] Similarly, beyond the third section 60, further sections 62 of the receiving space 42 are filled with the grouting material 40, which, like the second section 54, have a diameter 56 that essentially corresponds to the outer diameter of the outer pipe 22. Additionally, according to Fig. 7 in the cohesive soil 14 further sections 64 of the receiving space 42 produced, as is done with reference to Fig. 4 to Fig. Section 6 explains the first section 48 and the third section 60. Accordingly, these sections 64 are also enlarged radially beyond the outer surface 50 of the outer tube 22.
[0070] In Fig. Figure 7 shows an alternating sequence of radially enlarged sections 48, 60, 64 and further sections 54, 62, whose diameter 56 essentially corresponds to the outer diameter of the outer tube 22. The number of sections 48, 60, 64 with the enlarged equivalent diameter 58 (compare Figure 7) is shown in Figure 7. Fig. 5) and the number of the sections 54, 62 arranged in the axial direction 44 between them, whose diameter 56 essentially corresponds to the outer diameter of the outer tube 22, can vary, in particular depending on the structural conditions.
[0071] In the present case, the length 66 of the sections 48, 60, 64 of the receiving chamber 42, which are enlarged radially beyond the outer surface 50 of the outer tube 22, can be in the range of approximately 50 cm to approximately 60 cm. Similarly, the length 68 of the sections 54, 62 of the receiving chamber 42, whose diameter 56 essentially corresponds to the outer diameter of the outer tube 22, can also be in the range of approximately 50 cm to approximately 60 cm.
[0072] Regarding Fig. 4 to Fig. 6. These exemplary length specifications mean that after a thrust of the inner drill string 26 of approximately 50 cm to approximately 60 cm (compare Fig. 4) following a twice as large thrust of the outer tube 22 (compare Fig. 5), i.e. following a thrust of the outer tube 22 of approximately 100 cm to approximately 120 cm, the third section 60 of the receiving chamber 42 is produced by a further advance of the inner drill string 26 (compare Fig. 6).
[0073] As from Fig. As can be seen in Figure 7, this procedure for producing the borehole 18 results in the formation of the grout body 38, which interlocks with the cohesive soil 14, by introducing the grout material 40, which hardens after grouting, into the receiving chamber 42. The skin friction of the grout body 38, which interlocks with the cohesive soil 14, is advantageously particularly high in this case.
[0074] After the tension member or support member 36 of the grouted anchor 20 has been inserted into the borehole 18, the injection of the grout material 40 into the borehole 18 can begin. Meanwhile, the outer casing 22 or the outer drill string can be withdrawn from the borehole 18. After the grout material 40 has hardened and thus the grout body 38 has been formed, interlocking with the cohesive soil 14, the grouted anchor 20 is particularly securely anchored in the cohesive soil 14 (compare Fig. 8) In a manner known per se, the support member 36 is also formed in the area of a free end 70 of the support member 36, which according to Fig. 8 protrudes from the excavation wall 12 within the passage opening 78, fixed to the excavation wall 12.
[0075] For example, in Fig. 7 and in Fig. Figure 8 is further illustrated by arrows 76, showing how, in particular, the widened or radially enlarged areas of the grout body 38 are subjected to tensile stress in the cohesive soil 14 when the excavation wall 12 is anchored back into the cohesive soil 14 by means of the grout anchor 20. These widened areas of the grout body 38 are thus designed in the manner of barbs of the grout body 38 or of the grout anchor 20 circumferentially around the load-bearing member 36.
[0076] For the sake of clarity, not all arrows indicating the direction of tensile stress are shown in 76. Fig. 7 and in Fig. 8 is provided with a reference numeral. The radially widened areas of the grout body 38 correspond, in terms of their position in the cohesive soil 14, to the sections 48, 60, 64 of the receiving space 42, in which the receiving space 42 has the enlarged equivalent diameter 58.
[0077] Out of Fig.8 also shows the arrangement of the structure in the form of the excavation wall 12 shown here as an example in the terrain 10, wherein the structure designed to support or stabilize the terrain 10 is secured or anchored back by means of at least one securing device, in this case in the form of the grouted anchor 20.
Claims
[1] Method for securing a structure (12) designed to support a terrain (10) by means of at least one securing device (20), in which the structure (12) is accessible from a first side (72) of the structure (12) for a drilling device (16) and a second side (74) of the structure (12) adjoins a cohesive soil (14) of the terrain (10), in which a borehole (18) for the securing device (20) is produced by means of the drilling device (16) via at least one passage opening (78) formed in the structure (12) in the cohesive soil (14), wherein the drilling device (16) used to produce the borehole (18) has an outer tube (22) with a drill bit (24) and an inner drill rod (26) arranged within the outer tube (22), which inner drill rod is arranged relative to the outer tube (22) in a axial direction (44) of the borehole (18), wherein a flushing medium (32) can be introduced into the borehole (18) via the inner drill rod (26),by means of which drilling material can be removed via an annular space (34) formed between the outer tube (22) and the inner drill rod (26), and wherein by means of the drilling device (16) by producing the borehole (18) in the cohesive soil (14) a receiving space (42) for a grouting body (38) of the securing device (20) is formed, , characterized bythat during the formation of the receiving space (42), a position of the outer tube (22) in the axial direction (44) of the borehole (18) is temporarily maintained unchanged at least once, while a free end (28, 46) of the inner drill rod (26) is introduced beyond the drill bit (24) of the outer tube (22) further into the cohesive soil (14), wherein by means of the flushing medium (32) in the form of water in the region of the free end (28, 46) of the inner drill rod (26), cohesive soil (14) is flushed out of the terrain (10) and thereby a section (48) of the receiving space (42) is enlarged in the radial direction beyond an outer side (50) of the outer tube (22), wherein after the temporarily unchanged maintenance of the position of the outer tube (22) by introducing both the outer tube (22) and the inner drill rod (26) a second section (54) of the receiving space (42) is produced in a front-side boundary wall (52) of the section (48),whose diameter (56) substantially corresponds to an outer diameter of the outer tube (22), and wherein, after the production of the second section (54) of the receiving space (42), the position of the outer tube (22) in the axial direction (44) of the borehole (18) is temporarily maintained unchanged at least once more, while the free end (28, 46) of the inner drill rod (26) is inserted further into the cohesive soil (14) beyond the drill bit (24) of the outer tube (22) and cohesive soil (14) is again flushed out of the terrain (10) by means of the flushing medium (32) in the region of the free end (28, 46), wherein a third section (60) of the receiving space (42) is enlarged in the radial direction beyond the outer side (50) of the outer tube (22). [2] Method according to claim 1, characterized bythat after temporarily maintaining the position of the outer tube (22) unchanged, the drill bit (24) of the outer tube (22) is first brought in the axial direction (44) of the borehole (18) to a substantially equal height with the free end (28, 46) of the inner drill rod (26) and then the second section (54) of the receiving space (42) is produced. [3] Method according to one of claims 1 to 2, characterized by that in the axial direction (44) of the borehole (18) a plurality of sections (48, 60, 64) of the receiving space (42) which are enlarged in the radial direction beyond the outer side (50) of the outer tube (22) are produced in an alternating sequence with sections (54, 62) of the receiving space (42), the diameter (56) of which sections substantially correspond to the outer diameter of the outer tube (22). [4] Method according to one of claims 1 to 3, characterized bythat the at least one section (48, 60, 64) of the receiving space (42) which is enlarged in the radial direction beyond the outer side (50) of the outer tube (22) is produced with a maximum equivalent diameter (58) which is at least 10%, in particular at least 25%, preferably at least 50% larger than an outer diameter of the outer tube (22), in particular the at least one section (48, 60, 64) of the receiving space (42) which is enlarged in the radial direction beyond the outer side (50) of the outer tube (22) is produced with a maximum equivalent diameter (58) which is approximately twice as large as the outer diameter of the outer tube (22). [5] Method according to one of claims 1 to 4, characterized bythat the at least one section (48, 60, 64) of the receiving space (42) which is enlarged in the radial direction beyond the outer side (50) of the outer tube (22) is produced with a length (66) in the axial direction (44) of the borehole (18) which is substantially equal to a length (68) of the at least one further section (54, 62) whose diameter (56) corresponds to the outer diameter of the outer tube (22). [6] Method according to one of claims 1 to 5, characterized by that the at least one section (48, 60, 64) of the receiving space (42) which is enlarged in the radial direction beyond the outer side (50) of the outer tube (22) is formed at least in the region of a free end of a support member (36) of the securing device (20), wherein at least a partial region of the support member (20) is surrounded by the grouting body (38) formed by the hardened grouting material (40) after the grouting material (40) has been introduced into the receiving space (42). [7] Method according to claim 6, characterized by that a further free end (70) of the support member (36) is fixed in the region of the passage opening (78) on the structure (12), which is designed in particular as an excavation wall and / or as a supporting structure on a terrain jump and / or as a bank wall and / or as a quay wall.
Citation Information
Patent Citations
Double drilling-rod type drilling installation, has connection on outer rod for forming liquid connection to annular cavity between rods
DE102006059171B3
Forming compression anchor with tensile member (5), anchor head, and compression body
DE4242668A1
Drilling device for civil engineering and method for making stabilizing columns or similar structures in the ground
EP0543140A2
Method and apparatus for drilling with dual tube drillstring
EP0860582A1
Construction of ground anchor in hole expanded by high-pressure jet
JP1994248645A