Method for monitoring the electrical power consumption of a crane

The surveillance process addresses the inefficiency in crane electrical power consumption by using a control-command system to monitor and manage equipment usage, resulting in reduced energy wastage and improved energy efficiency.

FR3153342A1Active Publication Date: 2025-03-28MANITOWOC CRANE GROUP FRANCE
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
FR2023010071
Authority / Receiving Office
FR · FR
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-09-22
Publication Date
2025-03-28
Estimated Expiration
2043-09-22

AI Technical Summary

Technical Problem

Crane electrical equipment often consumes more power than necessary, leading to inefficiencies and increased energy costs, as equipment like heating and air conditioning systems continue to operate even when not in use.

Method used

A surveillance process utilizing a control-command system to monitor and manage the electrical power consumption of crane equipment over a defined time period. The system distinguishes between actuation and accessory equipment, determining their active states and calculating power consumption based on predefined models, allowing for the identification of unnecessary power usage.

Benefits of technology

The surveillance process effectively reduces energy wastage by identifying and optimizing the power usage of crane equipment, enabling operators to determine the energy efficiency of the crane and pinpoint areas for improvement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

The invention relates to a monitoring method initially configured for monitoring and evaluating the electrical power consumption of the electrical equipment of a crane (1) over a given time period. The electrical equipment includes: actuation equipment contributing to at least one movement of the crane, and auxiliary equipment not participating in a movement of the crane but responsible for power-consuming functions. Once the time period has elapsed, the monitoring method is configured to determine whether, during the time period, the crane consumed excessive power. This excessive consumption is deduced by comparing the power input (PI) supplied to the crane by at least one power source (2) with the electrical power consumed by the actuation equipment and the auxiliary equipment. Abstract figure: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

Title of the invention: Method for monitoring the electrical power consumption of a crane technical field

[0001] The invention relates to a monitoring method for cranes.

[0002] It relates more particularly to a monitoring method for controlling over a given time period the electrical power consumption of all the electrical equipment of a crane in order to optimize its use and ensure that it consumes as little energy as possible.

[0003] The invention finds a preferred, but not limiting, application for all types of cranes, for example: tower cranes, distribution jib cranes, luffing jib cranes, telescopic jib cranes, mobile cranes, port cranes. Prior art

[0004] Today, companies must positively comply with new regulations to initiate their ecological transition and put into practice behaviors in favour of sustainable development, with the aim of providing a comprehensive and lasting solution to the major environmental challenges of this century, in particular in the areas of reducing energy consumption and polluting emissions.

[0005] As is known, when used on a construction site, a crane is supplied with electrical power by one or more power sources (for example: the electrical network, a generator, a battery...) for the purpose of: - operating mainly electrical equipment that it includes, called actuation equipment, in order to implement a movement of a moving element of the crane to move it (i.e., a translational movement) or for the movement of a load (for example: a lifting, distribution, orientation or hoisting movement), - to heat or cool the crane operator's cab or the electrical cabinet, - etc.

[0006] Due to certain practices and usage habits, cranes generally consume far more electrical power than they need for their assigned tasks on the construction site, namely load handling. Indeed, electrical equipment on the crane may be powered while performing a task even though it is not directly or indirectly involved in that task.

[0007] By way of illustration, if the power supply of the actuation equipment implementing While the movement of a moving part of the crane is essential for this operation, powering the electrical equipment, known as auxiliary equipment, used to heat the crane operator's cab is unnecessary, especially if the temperature inside the cab is already comfortable for the operator. Furthermore, auxiliary equipment may be powered for extended periods when it is not required. For example, if the construction site is experiencing low outside temperatures, it is not necessarily useful to power the auxiliary equipment responsible for heating the cab all night to ensure the operator's comfort when arriving for work in the morning, but only for a few hours before the operator's arrival.

[0008] Thus, a portion of the electrical power supplied to the crane is consumed unnecessarily and wasted, significantly reducing the crane's energy efficiency. Sometimes, the wasted electrical power can be equivalent to the useful electrical power (i.e., a crane energy efficiency of 50%); the useful electrical power corresponding to the total actuation power resulting from the actions of the various actuation devices involved in the movements.

[0009] This decrease in energy efficiency is becoming problematic in light of current environmental challenges, particularly in terms of climate change. Therefore, crane manufacturers, in order to adopt an eco-responsible approach, must offer solutions for improving the energy efficiency of their cranes.

[0010] Known solutions, such as those in documents CN216997307U and CN215208123U, aim to determine the energy efficiency of the crane but only in the context of the execution of precise maneuvers (in this case, for both documents, the maneuver of lifting a load when the crane is in operation).

[0011] Thus, these solutions do not propose to determine the electrical power consumption for all the electrical equipment of the crane, and to determine precisely its energy efficiency during its deployment and use on the construction site. Summary of the invention

[0012] In order to address the problems described above, the invention proposes a monitoring method for monitoring, over a time period, the electrical power consumption of the electrical equipment of a crane, which crane is powered by a supply of power provided by at least one power source, which electrical equipment comprises: - actuation equipment, in which each of the equipment actuation includes at least one motor controlled by a speed variator and coupled to at least one moving element of the crane to actuate, in an active state, a movement of said at least one moving element, otherwise it is in an inactive state; and - accessory equipment which is not actuation equipment, in other words equipment which does not participate in the movement of a moving element of the crane, and in which each of the accessory equipment performs a power-consuming function which is its own when it is in an active state, otherwise it is in an inactive state; said monitoring process being implemented by a control system connected to the speed drives of the actuation equipment and connected to the accessory equipment to switch them from the inactive state to the active state and vice versa; said control system containing at least one memory and one processor defined by a cycle time, and implementing at least, for each cycle time included in the time period: - a determination of the state of each accessory equipment to determine whether it is in the active state or in the inactive state, and to deduce an accessory power consumed in the cycle time by said accessory equipment when it is in the active state, on the basis of an electrical consumption model associated with said accessory equipment which is contained in the control system; - monitoring of each actuation equipment including receiving, from the corresponding speed variator, an actuation power consumed in the cycle time by said actuation equipment when it is in the active state.

[0013] Advantageously, the monitoring method of the invention positively addresses the problem of knowledge of the power consumed by all the equipment of the crane by allowing, over a period of time (which may correspond for example to a day, a week, a month, or even a year): to monitor the electrical power consumption of a crane, more precisely of its electrical equipment, in comparison with the power supplied by at least one power source (for example: the electrical network, a generator, a rechargeable power source such as a battery).

[0014] The power consumed by the electrical equipment is determined by the crane's control system.

[0015] A distinction is made among electrical equipment between: - those known as actuation equipment contributing to the movement of moving parts of the crane for its assembly, its movement, or to allow the crane to moving a load (the crane being said to be in service, or in operation); and - those called accessories which do not contribute to the movement of moving parts of the crane, but still perform a power-consuming function, for example to heat or cool the crane operator's cab.

[0016] A non-exhaustive list of actuation equipment and accessory equipment is provided below.

[0017] An actuation device (respectively an accessory device) is said to be active when it contributes to the movement of the at least moving element to which it is associated (respectively when it implements the power-consuming function which is its responsibility); the actuation device (respectively the accessory device) is said to be inactive otherwise.

[0018] The control system comprises at least one memory and a processor defined by a cycle time; this cycle time being an intrinsic property of the control system's processor, which represents the time required to repeat a given operation and is related to the processor's calculation speed. More precisely, it is this processor that implements the monitoring process by executing a program containing a list of instructions relating to the latter.

[0019] In the context of implementing the monitoring method, the time period is considered to be segmented according to the processor cycle time. In other words, the time period consists of a plurality of time intervals that are equal to the cycle time. Hereafter, the time period is said to be composed of a plurality of cycle times.

[0020] During the cycle times segmenting the time period, the control system is aware of the state of the electrical equipment, i.e. whether they are active or inactive.

[0021] In the case of active actuation equipment, the control system is aware of the power consumed by said actuation equipment during the cycle time following receipt of a measurement of said power, which is measured by a variable speed drive included in the actuation equipment and to which the control system is connected. In fact, variable speed drives include energy consumption meters. The power consumed by the actuation equipment is called the actuation power.

[0022] In the case of active accessory equipment, the control system knows the power that said accessory equipment consumes during the cycle time by calculating it from a mathematical model corresponding to an electrical consumption model of the accessory equipment, which is contained in the control system. The power that the accessory equipment consumes is called auxiliary power.

[0023] Advantageously, the use of power consumption models eliminates the need to install measuring devices on the crane to measure auxiliary power, as these devices would require a power supply to perform the measurements. Consequently, the use of power consumption models reduces the crane's energy consumption. Power consumption models also reduce the costs associated with purchasing measuring devices.

[0024] According to one feature of the invention, the control system implements at least a posteriori of the time period: - a calculation, for each of the accessory equipment, of a cumulative accessory power consumed over the time period by said accessory equipment, by summing the accessory powers consumed in the cycle times when it was in the active state; - a calculation, for each of the actuation equipment, of a cumulative actuation power consumed over the time period by said actuation equipment, by summing the actuation powers consumed in the cycle times when it was in the active state; - a deduction of a total accessory power corresponding to the sum of the cumulative accessory powers consumed over the time period by all accessory equipment; - a deduction of a total actuation power corresponding to the sum of the cumulative actuation powers consumed over the time period by all the actuation equipment; - a comparison between the supply power, the total accessory power and the total actuation power.

[0025] Advantageously, the monitoring method allows an operator to know the total power consumed by each piece of electrical equipment during the past time period. This total power is called the cumulative actuation power when the electrical equipment is an actuation device, and the cumulative accessory power when the electrical equipment is an accessory device.

[0026] Also, the monitoring method allows an operator to know what the shares of the total actuation power (i.e. the useful power) and the total accessory power are in the electrical energy consumption of the crane (in other words, the supply power).

[0027] Thus, the operator is able to conclude whether, during the time period, the crane consumed excess power (i.e., when the total power ac waste is greater than the useful power in the electrical energy consumption of the crane), and to determine the origins of this excess (i.e. to identify the electrical equipment that has consumed power excessively).

[0028] The invention again addresses the problems raised previously by allowing the operator to accurately determine the energy efficiency of a crane during a time period during which said crane can be deployed and / or used on a construction site, which energy efficiency is equal, as specified below, to the total actuation power divided by the supply power.

[0029] According to a feature of the invention, after the time period, the control system constitutes a power data set comprising at least: - the cumulative power consumption of all accessory equipment during the time period, - the cumulative actuation powers of all actuation equipment during the time period, - the total accessory power, - the total actuation power, and - the power supply; which set of power data is time-stamped over the time period and then recorded in the memory of the control system.

[0030] In other words, the powers calculated by the control system and listed above are grouped by the latter into a set of power data which it timestamps and stores in its memory.

[0031] Advantageously, the power data sets are thus classified temporally according to the time period (day, week, month, or even a year) during which they were calculated. The calculated power values ​​are therefore not lost once the monitoring process is completed, and an operator can consult them later to analyze the energy behavior of the crane.

[0032] Also, it is planned that the memory of the control system can store power data sets from several time periods, thus allowing the operator to observe / analyze an evolution of the energy behavior of the crane over a long time period, which may, for example, correspond to several successive time periods, and potentially identify anomalies in energy consumption (the crane may have consumed more power over a given time period compared to others).

[0033] According to one feature of the invention, the power data set is exportable from the control system to a digital twin of the crane modeled in a remote IT infrastructure, the power data set being put into a data format compatible with the digital twin in order to be used by it.

[0034] Advantageously, the use of a digital twin for which at least one set of power data is used allows an operator to reproduce the deployment and / or use context of the crane over at least one time period. Thus, if excessive power consumption has been observed during at least one time period describing a given application context on a construction site, the operator can use the digital twin to develop scenarios in which the crane's power consumption is optimized for said at least one time period. Subsequently, these scenarios can then be used / exploited by being concretely reproduced on the construction site should said application context be encountered again, in order to better manage the crane's energy consumption.Optimizing power consumption can result, for example, from reduced activity of auxiliary equipment, better use of the crane when it is in service or working (optimization of crane movements), etc.

[0035] According to one embodiment of the invention, the control system calculates, after the time period, an energy efficiency which is equal to the total actuation power divided by the supply power.

[0036] According to one embodiment of the invention, the power data set also includes energy efficiency.

[0037] According to a feature of the invention, the control system determines, at each cycle time included in the time period, and as a function of at least one electrical equipment among the actuation equipment and accessory equipment in the active state, at least one state of the crane among at least one out-of-service state in which all the actuation elements are in the inactive state, and at least one in-service state in which at least one of the actuation elements is in the active state.

[0038] In other words, during each cycle time, the control system is able to determine whether the crane is in an out-of-service state or in an in-service state.

[0039] As previously stated, the crane is considered to be in an out-of-service state when no actuation element is active. Conversely, in the out-of-service state, auxiliary equipment may or may not be in operation. The out-of-service state may correspond to a time when the crane is inactive, for example: when it is in deep sleep; when no actuation equipment is active and the operator's cab is preheated or air-conditioned; etc.

[0040] The crane is considered to be in a service state when at least one actuating element is in the active state to contribute to the movement of a moving element. In other words, in the service state, the crane may: be being deployed on a construction site; or be operated by a crane operator for the purpose of being moved or moving a load.

[0041] According to one embodiment of the invention, at least one state of the crane corresponds to the state in operation for a given cycle time; the control system associates, for each of the actuation devices, a movement chosen at least from among: - a distribution movement associated with a distribution device among the actuation devices during which a load distribution maneuver is performed along a crane boom, - a lifting movement associated with a lifting device among the actuation devices during which a load is lifted, - an orientation movement associated with an orientation device among the actuation devices during which an orientation maneuver of a boom is performed, - a translational movement associated with a translational device among the actuation devices during which a translational maneuver of the crane is performed, - a lifting movement associated with a lifting device among the actuation equipment during which a lifting maneuver of a luffable boom is carried out, or - an assembly movement during which the crane is assembled, which assembly movement is associated with an assembly equipment from among the actuation equipment and chosen at least from: a folding / unfolding equipment for folding / unfolding a mast and a boom, a levelling equipment for levelling the crane on the ground, a slewing equipment for slewing a base of the crane, a jib equipment for actuation of an assembly jib.

[0042] According to one embodiment of the invention, when at least one state of the crane corresponds to the out-of-service state for a given cycle time, the control system associates, for each of the accessory equipment, the power-consuming function chosen from among: - a heating function associated with heating equipment among the accessory equipment for heating a crane operator's cab, and - an air conditioning function associated with air conditioning equipment among the accessory equipment to air condition a crane operator's cabin.

[0043] In other words, depending on the actuation equipment and / or accessory equipment in the active state during a cycle time, the control system is able to determine which movement implements the crane and / or which power-consuming function is currently active.

[0044] Advantageously, during a cycle time, the control system is able to associate a power consumption (an actuation power or an auxiliary power) with: a crane state (i.e., a crane state (in service or out of service)); as well as with a crane movement or an energy-consuming function. Thus, subsequently, when analyzing the power data set, the operator is able to deduce, for the given time period, the power consumed to implement a given movement or energy-consuming function.

[0045] Also, if several actuation equipment (respectively several accessory equipment) contribute during a time period to a movement of a moving element (respectively to an energy-consuming function), the operator can know, at the end of the time period, the power consumed by each of them to implement said movement (respectively said energy-consuming function).

[0046] Advantageously, the monitoring method therefore makes it possible to process and classify the cumulative power consumed by the electrical equipment of a crane temporally (i.e. according to the time period), according to the state of the crane, and the movement or energy-consuming function implemented; something that a measurement system external to the crane would be unable to do without integrating intelligence.

[0047] According to one embodiment of the invention, the electrical consumption model of each of the accessory equipment contains at least, in order to calculate the accessory power: - the cycle time, - a supply voltage to power said accessory equipment when in the active state, - the power consumption intensity of the accessory equipment.

[0048] In other words, the accessory power of an accessory equipment during a cycle time is calculated from: the cycle time; the supply voltage required to power the accessory equipment; and the current consumed by the accessory equipment during the cycle time, which is considered to be uniform.

[0049] According to one embodiment of the invention, the cycle time is equal to 50 milliseconds, plus or minus 20%.

[0050] According to one embodiment of the invention, the control system generates, after the time period, an analysis report containing at least the power data set of the time period.

[0051] Advantageously, the analysis report includes all the powers calculated during the time period (cumulative accessory powers of all accessory equipment, cumulative actuation powers of all actuation equipment, total accessory power, total actuation power, supply power) to allow the user to analyze the energy behavior of the crane during the time period.

[0052] It is conceivable that the analysis report will contain the energy efficiency calculated by the control system for the time period.

[0053] It is also conceivable that the analysis report may contain power data sets from several time periods.

[0054] It is then conceivable that the analysis report may contain a classification of the cumulative power of the electrical equipment of the crane according to: time periods; the state of the crane; and the movement or energy-consuming function implemented.

[0055] Finally, in connection with the previous point, it is conceivable that the analysis report may contain one or more graphical representations showing a distribution of the supply power as a function of: - the condition of the crane, - the movement or energy-consuming function implemented, - the actuation equipment and accessory equipment (i.e., based on the actuation powers, the cumulative actuation powers, the accessory powers, the cumulative accessory powers), and - of the total actuation power and the total accessory power.

[0056] According to one possibility, the supply power is measured by a global electricity meter in connection with the control system.

[0057] In other words, it is planned to measure the supply power, by means of the overall electricity meter (such as a meter supplied by an electricity provider), which can be positioned upstream of at least one power source or at the inlet of the crane, and the control system retrieves this measurement of the supply power. Brief description of the drawings

[0058] Other features and advantages of the present invention will become apparent from the following detailed description of a non-limiting example of implementation, made with reference to the accompanying figures in which:

[0059] [Fig-1] is an illustration of an application context in which the method of the invention is implemented, which shows in particular a crane deployed on a construction site, a power supply providing the crane with power for its operation, and a global electric meter measuring said power supply;

[0060] [Fig.2] is a schematic illustration of a crane comprising at least one control system installed in a driver's cab, electrical equipment including actuation equipment contributing to the implementation of crane movements, and accessory equipment not participating in a movement of the crane but ensuring a power-consuming function such as heating or air conditioning of the crane's driver's cab;

[0061] [Fig.3] is an operating diagram of the monitoring method of the invention, which evaluates over a given time period the power consumed by the various electrical equipment of the crane, in order to determine whether the crane has consumed excessive power in relation to the power supplied to it;

[0062] [Fig.4] shows examples, within the framework of an embodiment of the invention, of graphical representations showing a distribution, for a given time period, of the supply power: (a) as a function of the power consumed by all the actuation equipment and the power consumed by all the accessory equipment, respectively called total actuation power and total accessory power, or (b) as a function of the actuation equipment and the accessory equipment, or (c) as a function of the movements and the power-consuming functions implemented.

[0063] [Detailed description of one or more embodiments of the invention]

[0064] The invention relates to a monitoring method 100 for evaluating, over a given time period T (for example: a day, a week, a month...), the power consumed by all the equipment of a crane 1 deployed and operating on a construction site; this with the aim of subsequently analyzing this power consumption to determine whether the crane 1 has consumed excessive power according to its use during the time period T and, if so, to arrive at solutions to optimize its power consumption during its future uses.

[0065] The monitoring method is applicable to all types of crane 1: tower cranes, distributing jib cranes, luffing jib cranes, telescopic jib cranes, mobile cranes, port cranes.

[0066] In the following description, it is assumed that crane 1 is a distributing boom crane.

[0067] With reference to [Fig. 1] and 2, the crane 1 comprises at least one mast 102 and a rotating assembly that rotates about a vertical extension axis and is formed by a substantially aligned boom 16 and counter-jib 17, and optionally a jib bracket (or jib post) with tie rods. A counterweight 171 is carried by the counter-jib 17 to counterbalance the weight of a load that is lifted and / or moved by the crane 1.

[0068] The load is attached by means of a raised hook 191 located at the end of a pulley 192, which moves vertically in the direction of the boom 16 or down according to the winding or unwinding of a lifting cable 19.

[0069] The lifting cable 19 is suspended from a distribution trolley 18 which moves in translation on a track provided along the boom 16.

[0070] The crane 1 also includes a pilot's cabin 101 in which the crane operator sits and in which there is a control system 15 from which the crane operator operates the crane 1.

[0071] The control system 15 includes at least one memory 152, a processor 151 defined by a cycle time te, and a program 153 containing a list of instructions to launch and execute the monitoring process 100.

[0072] By definition, a crane also includes a plurality of electrical equipment 11, 12, 13, 14, which include, but are not limited to: a lifting winch 12; a distribution winch 11; a heating unit 13 and an air conditioning unit 14, both installed in the cab 101. These four electrical equipment 11, 12, 13, 14 are considered subsequently to explain the operating principle of the monitoring method 100. As just indicated, they constitute only a part of the electrical equipment that the crane 1 may actually include.

[0073] The implementation of the monitoring method 100 is based in part on a categorization of the electrical equipment 11, 12, 13, 14 according to their role / function. A distinction is thus made between electrical equipment referred to as actuation equipment 12, 13 and that referred to as accessory equipment 13, 14.

[0074] The actuation equipment 11, 12 are electrical devices comprising at least one motor controlled by a variable speed drive 111, 121, and coupled to at least one moving element 18, 19 of the crane to implement, when in an active state A11, A12, a displacement of said at least one moving element 18, 19 resulting in a movement M11, M112. The variable speed drives 111, 121 controlling the motors of the actuation equipment 11, 12 are connected to the control system 15.

[0075] With reference to [Fig. 2], the crane 1 comprises the following actuation equipment: - a distribution device 11, i.e. the distribution winch, which is coupled at least to a moving element 18, i.e. the distribution trolley 18, to implement a distribution movement Mvtl 1 during which the distribution trolley is mobile in translation from the front to the rear of the boom 16, and vice versa; - a lifting equipment 12, i.e. the lifting winch, which is coupled at least to a moving element 19, i.e. the lifting cable, to implement a lifting movement Mvtl2 during which the lifting winch winds or unwinds the lifting cable 19, in order to move the pulley 192 vertically in the direction of the boom 16 or the ground to lift or lower a load.

[0076] Not illustrated in [Fig.2] and not considered in the remainder of the description, may also be cited as actuation equipment: - a slewing equipment, for example an electric slewing motor, associated with a slewing ring to implement a slewing movement during which the boom 16, or more generally the rotating assembly of the crane 1, sweeps a circular area around the slewing axis, which circular area corresponds to the working area of ​​the crane; - a translation equipment designed to implement a translation maneuver of the crane 1, which can, for example, be mounted on rails if it is planned that it will move around the construction site; - Assembly equipment designed to implement a crane assembly movement, for example, but not limited to: folding / unfolding equipment for folding / unfolding the mast 102 and a boom 16, leveling equipment for leveling the crane 1 on the ground, slewing equipment for orienting a base of the crane 1, jib equipment for operating an assembly jib, etc. This assembly equipment can be selected, for example, but not limited to, from electric motors or hydraulic power units.

[0077] In the case of luffing jib cranes, the actuation equipment mentioned above does not include distribution equipment, since these cranes do not have a distribution trolley. Indeed, for this type of crane, the jib is lowered and raised angularly by means of at least one lifting cable. Thus, the load is lifted according to the jib's inclination and therefore the winding or unwinding of the lifting cable. In fact, the actuation equipment of a luffing jib crane does, however, include lifting equipment (such as a lifting winch) designed to perform a lifting movement of the luffing jib by winding and unwinding the lifting cable.

[0078] Accessory equipment 13, 14 are electrical equipment that does not by participate in the movement of a moving element 18, 19 of the crane 1, but which perform a power-consuming function F13, F14 of their own when they are in an active state A13, A14. With reference to [Fig.2], the illustrated accessory equipment corresponds to the heating equipment 13, which performs a heating function F13 to heat the cab 101, and to the air conditioning equipment 14, which performs an air conditioning function F14 to cool the cab 101.

[0079] The actuation equipment 11, 12 and accessories 13, 14, when they do not respectively implement a movement Mvtl 1, Mvtl2 and a consuming function F13, F14, are said to be in the inactive state NA11, NA12, NA13, NA14.

[0080] The transitions of electrical equipment 11, 12, 13, 14 from the active state A11, A12, A13, A14 to the inactive state NA11, NA12, NA13, NA14, and vice versa, are managed from and by the control system 15.

[0081] The crane 1 is said to be in an OP1 service state when at least one actuation equipment 11,12 is in the active state A11, A12; this is independent of the state of the accessory equipment 13, 14. In other words, in the OP1 service state, the crane 1 can: be being deployed on a construction site; or be operated by a crane operator in order to be moved or to move a load.

[0082] Otherwise, the crane is said to be in an out-of-service state NOP1 when all the actuation equipment 12, 13 are in the inactive state NA11, NA12, whether the accessory equipment 13, 14 are in the active state A13, A14 or inactive state NA13, NA14. Thus, the out-of-service state NOP1 can correspond to a time during which the crane 1 is inactive, for example: when it is in deep sleep (all the electrical equipment 11, 12, 13, 14 are in the inactive state NA11, NA12, NA13, NA14); when the actuation equipment 11, 12 are inactive but the operator's cab 101 is preheated or air-conditioned (meaning that the heating equipment 13 or the air-conditioning equipment 14 is performing its energy-consuming function F13, F14); etc.

[0083] During the time period T, in order to power its electrical equipment 11, 12, 13, 14 in the active state A11, A12, A13, A14, receives a supply power PI from at least one power source 2, the at least one power source 2 being able to correspond non-exhaustively to: the electrical network, a generator set, a rechargeable power source such as a battery.

[0084] The supply power PI is measured by at least one global electricity meter 3 in communication (via a wired or wireless link) with the control system 15. According to various embodiments of the invention, the global electricity meter 3 can be positioned upstream of at least one power supply 2, or at the input of the crane 1. Thus, the control system 15 retrieves the measurement of the supply power PI from the global electricity meter 3.

[0085] In addition to the categorization of electrical equipment 11, 12, 13, 14, the monitoring method 100 relies on a segmentation of the time period T according to the cycle time te of the processor 151. In one embodiment of the invention, the cycle time te is equal to 50 milliseconds, plus or minus 20%. Thus, the duration of the time period T is equal to a plurality of cycle times tel, ten occurring one after the other, the plurality of cycle times comprising at least a first cycle time tel and a last cycle time tcn.

[0086] A flow diagram of the monitoring process 100 is shown [Fig. 3], which begins to run following a launch E0. The time period T is considered to begin temporally following the implementation of the launch E0.

[0087] For each of the cycle times such as tcn, constituting the time period T, the monitoring process 100 will implement, for example in parallel as illustrated [Fig.3]: - a determination El of the state A13, NA13, A14, NA14 of each of the accessory equipment 13, 14. In the case where the accessory equipment 13, 14 is in the active state A13, A14, the monitoring process 100 (more precisely, the control system 15) will calculate an accessory power Pal3-1, Pal3-n, Pal4-1, Pal4-n consumed by the accessory equipment 13, 14 for the cycle time tel, tcn. This calculation is detailed further down in the text. In the case where the accessory equipment 13, 14 is in the active state NA13, NA14 during the cycle time such, tcn, the monitoring process 100 concludes that the accessory equipment 13, 14 does not consume accessory power Pal3-1, Pal3-n, Pal4-1, Pal4-n (in other words, the power consumption is zero); - an E2 monitoring of each actuation 11, 12 during which, when the actuation equipment 11,12 is in the active state A11, A12 during the cycle time tel, tcn, the control system 15 receives, from the speed variator 111, 121 associated with the actuation equipment 11, 12, a measurement corresponding to the actuation power Pmi 1-1, Pmi 1-n, Pml2-1, Pml2-n consumed by the actuation equipment 11,12 during the cycle time tel, tcn. The variable speed drives 111, 121 are capable of transmitting the actuation power Pmi 1-1, Pmi 1-n, Pml2-1, Pml2-n to the control system 15 because they include energy consumption meters. When the actuation equipment 11, 12 is in the inactive state NA11, NA12 for the cycle time tcn, its power consumption is zero.

[0088] The accessory powers Pal3-1, Pal3-n, Pal4-1, Pal4-n consumed by the accessory equipment 13, 14 are calculated from mathematical models known as Electrical consumption models M13 and M14 are contained within the control system 15, specifically within program 153. Each electrical consumption model M13 and M14 contains at least: - the value of the cycle time te (for example, as indicated above, equal to 50 ms), which also corresponds to the values ​​of the set of cycle times tel, ten of the time period); - a supply voltage U13, U14 necessarily to power the accessory equipment 13, 14 when it is in the active state A13, A14; - a consumption intensity 113,114 of the accessory equipment 13, 14.

[0089] The auxiliary powers Pal3-1, Pal3-n, Pal4-1, Pal4-n of the auxiliary equipment 13, 14 during a cycle time such, ten are then calculated according to the following equations: (PA13- L Pal3-rt) = tc*U13*I13 Eq.l (PA14-1, ^14- / 2)=^^14^14 Eq.2

[0090] The use of power consumption models M13, M14 for determining the auxiliary power Pal3-1, Pal3-n, Pal4-1, Pal4-n of the auxiliary equipment 13, 14 eliminates the need to install measuring devices on the crane 1 to measure this power, which would themselves require a power supply to perform the measurements. Consequently, the use of power consumption models M13, M14 reduces the energy consumption of the crane 1. These power consumption models also reduce the costs associated with purchasing measuring devices.

[0091] With reference to [Fig. 3], the monitoring method 100 comprises at least one set of steps EC1, EC2, EDI, ED2, Ecomp occurring after the time period T (for example, immediately after it has ended) and implemented by the control system 15. This set of steps EC1, EC2, EDI, ED2, Ecomp comprises: - an EC1 calculation, for each of the accessory equipment 13, 14 of a cumulative accessory power PaT13, PaT14 which it consumed during the time period T, which is equal to a sum of the accessory powers Pal3-1, Pal4-1, Pal3-n, Pal4-n consumed in the cycle times tel, ten when it was in the active state A13, A14. Optionally, this cumulative accessory power PaT13, PaT14 may be equal to zero if throughout the time period T, the accessory equipment 13, 14 was in the inactive state NA13, NA14; - an EC2 calculation, for each of the actuation equipment 11, 12, of a cumulative actuation power PmT11, PmT12 that it consumed during the time period T, which is equal to a sum of the actuation powers Pmi 1-1, Pmi 1-1, Pml2-n, Pml2-n consumed in the cycle times tel, ten where it was in the active state A11, A12. Optionally, this cumulative actuation power PmT1 1, PmT12 may be equal to zero if throughout the time period T, the actuation equipment 11, 12 was in the inactive state NA11, NA12; - an EDI deduction of a total accessory power TPA corresponding to the sum of the cumulative accessory powers PaT13, PaT14 consumed over the time period T by all accessory equipment 13, 14; - a deduction ED2 of a total actuation power TPM corresponding to the sum of the cumulative actuation powers PmT11, PmT12 consumed over the time period T by all the actuation equipment 11, 12; - an Ecomp comparison between the PI supply power measured by the global electricity meter 3, the total accessory power TPA and the total actuation power TPM.

[0092] In another embodiment of the invention, it is conceivable that the calculations EC1, EC2 are carried out in parallel and not successively, similarly for the deductions EDI, ED2.

[0093] In one embodiment of the invention, it is conceivable that before the launch E0 used to start the monitoring process 100 from the dedicated program 153 contained in the control system 15, an operator (for example the crane operator) enters in said program 153 the duration of the time period T. Thus, the steps EC1, EC2, EDI, ED2, Ecomp of the monitoring process 100 carried out after the time period T are implemented automatically by the control system 15 once the latter has ended.

[0094] In another embodiment of the invention, the time period may end following manual interaction by the operator with a menu / option offered by program 153. This interaction marks the termination by monitoring program 153 of the implementation of the determination El of the accessory powers Pal3-1, Pal3-n, Pal4-1, Pal4-n and the actuation powers Pmi 1-1, Pmll-n, Pml2-1, Pml2-n during several successive cycle times tel, ten. Following this manual termination, the steps EC1, EC2, EDI, ED2, Ecomp of the monitoring process are implemented by the control system 15.

[0095] By definition, the PI supply power is equal to the sum of the total accessory power TPA with the total actuation power TPM.

[0096] Thanks to the Ecomp comparison, an operator is able to conclude whether, during the time period T, crane 1 consumed excess power, this This can translate, in a given context, into a total accessory power TPA greater than the total actuation power TPM. Also, knowledge of the cumulative accessory powers PaT13, PaT14 and the cumulative actuation powers PmT11, PmT12 allows the operator to identify the electrical equipment 11, 12, 13, 14 responsible for this excessive power consumption.

[0097] Knowledge of the cumulative accessory power PaT13, PaT14 and the cumulative actuation power PmT11, PmT12 also allows the operator to determine whether, in a given application context, an electrical device 11, 12, 13, 14 has consumed power unnecessarily, even if the total accessory actuation power TPA is less than the total actuation power TPM. For example: the operation of the heating device 13 when, without heating, the temperature inside the operator's cab 101 is such that it already ensures the comfort of the crane operator.

[0098] In order for the operator to be able to draw conclusions about the operation of the electrical equipment 11, 12, 13, 14 during the time period T, the monitoring method 100 includes the constitution EB1 of a power data set pdata comprising at least:

[0099] - the combined accessory powers PaT13, PaT14 of all the equipment accessories 13, 14 during the time period T,

[0100] - the cumulative actuation powers PmTl 1, PmT12 of all the equipment actuation 11, 12 during the time period T,

[0101] - the total accessory power TPA,

[0102] - the total TPM actuation power, and

[0103] - the PI power supply.

[0104] The power data set pdata is time-stamped over the time period T (which can correspond to a day, a week, a month, a year, etc.) and then recorded in the memory 152 of the control system 15. Thus, an operator can use the control system to consult the power data set pdata later and thus analyze the energy behavior of the crane 1 during the time period T.

[0105] It is conceivable that the memory 152 of the control system 15 is configured to store several sets of power data pdata, each corresponding to a distinct time period T. Thus, the operator can observe / analyze the evolution of the energy behavior of the crane 1 over a long period, which could, for example, correspond to several successive time periods T, and potentially identify energy consumption anomalies during this long period; the crane having been able to consume more power over a given time period T compared to others.

[0106] In one embodiment, the analysis of the power data set pdata is also possible from a remote computing infrastructure 4, which may be located on the construction site or, as illustrated [Fig. 1], at another geographical location. In one embodiment of the invention, the control system 15 can communicate with the remote computing infrastructure 4 to send it the power data set pdata. In another embodiment, an operator may use a storage device, for example a USB key (USB for Universal Serial Bus), to retrieve the power data set pdata from the control system 15 and subsequently transfer it to the remote computing infrastructure 4.

[0107] In one embodiment of the invention, the remote computing infrastructure 4 is also provided to contain a digital twin M1 of the crane 1, enabling the simulation and reproduction of application contexts of cranes operating on construction sites. The advantage of such a digital twin M1 is its ability to reproduce the energy behavior of the crane 1 over a time period T during which excessive power consumption has been observed. To this end, in this embodiment, the power data set pdata is provided to be in a format compatible with the digital twin M1.Using the digital twin M1 and the power dataset pdata, an operator can simulate, for the specific application context of the construction site associated with this time period T, several power consumption scenarios until optimal scenarios are reached in which the electrical consumption of the electrical equipment 11, 12, 13, 14 of crane 1 is optimized. Consequently, if this specific application context were to occur again on the construction site, the optimal scenarios would then allow for better energy management of the electrical power consumption of crane 1. The optimization of the power consumption of crane 1 can result, for example, from reduced activity of the auxiliary equipment 13, 14, from better use of crane 1 when it is in service or working (optimization of the movements Mvt11, Mvt12), etc.

[0108] In one embodiment of the invention, as illustrated [Fig. 3], it is conceivable that the monitoring method 100 includes, in parallel with the Ecomp comparison, an optional EC3 calculation of an energy efficiency eta of the crane 1, this energy efficiency eta being equal to the total actuation power TPM divided by the supply power PL. This energy efficiency eta may even potentially be part of the power data contained in the pdata power dataset.

[0109] In one embodiment of the invention, the monitoring method 100, during each of the cycle times tel, ten of the time period T, is capable of determining a state S1-1, Sl-n of the crane among the state in service OP1 and the state out of service NOP1; this depending on whether the actuation equipment 11, 12 and the accessory equipment 13, 14 are in the active state A11, A12, A13, A14 or in the inactive state NA11, NA12, NA13, NA14. The states A11, A12, A13, A14, NA11, NA12, NA13, NA14 of the electrical equipment 11, 12, 13, 14 also allow the monitoring process 100 to determine which movements Mvt11, Mvt12 and / or consuming functions F13, F14 are implemented during cycle times tel, tcn.

[0110] Thus, a posteriori, during the analysis of the power data set pdata, the operator is able to deduce for the time period T the power consumed to implement a movement Mvtl 1, Mvtl2 or a consuming function F13, F14 given(s).

[0111] Also, if several actuation equipment 11,12 (respectively several accessory equipment 13, 14) contribute during a time period T to a movement Mvtl 1, Mvtl2 of a moving element 18, 19 (respectively to a power-consuming function F13, F14), the operator can know, at the end of the time period T, the power consumed by each of them to implement said movement Mvtl 1, Mvtl2 (respectively said power-consuming function F13, F14).

[0112] Advantageously, the monitoring method 100 allows the cumulative powers PmT11, PmT12, PaT13, PaT14 consumed by the electrical equipment 11, 12, 13, 14 of the crane 1 to be processed and classified as a function of: the state OP1, NOP1 of the crane 1, and the movement Mvtl 1, Mvtl2 or the power-consuming function F13, F14 implemented; which an external measurement system to the crane 1 would be unable to do without integrating intelligence.

[0113] In one embodiment of the invention, in order to facilitate the analysis for the operator of the power consumption of the electrical equipment 11, 12, 13, 14 during the time period T elapsed, the monitoring method 100 may include, after the time period T, in parallel with the constitution EB1 of the power data set pdata or following the latter, a generation EB2 of an analysis report rfile containing at least the power data set pdata of the time period T, which is contained in and can be consulted from the control system 15.

[0114] In one embodiment of the invention, the analysis report is transferable to one or more remote IT infrastructures 4.

[0115] Since the EB2 generation of the rfile analysis report is optional, it is conceivable that this could, for example, be associated with an option offered by program 153 to the operator. It is also conceivable that program 153 could also offer to generate an rfile analysis report containing the power dataset pdata for the last completed time period T, as well as the power datasets pdata for earlier time periods T.

[0116] In one embodiment of the invention, the analysis report rfile may contain a classification of the cumulative power PmT11, PmT12, PaT13, PaT14 of the electrical equipment 11, 12, 13, 14 as a function of: the time periods T; the state OP1, NOP1 of the crane 1; and the movements Mvt11, Mvt12 or the power-consuming functions F13, F14 implemented. It is also conceivable, with reference to [Fig. 4], that the analysis report rfile may contain, for the time period T, one or more graphical representations showing a distribution of the supply power PI, for example, but not limited to: - of the OP1, NOP1 state of crane 1; - of the total actuation power TPM and the total accessory power TPA ([Fig.4]-a);

[0117] - actuation equipment 11, 12 and accessory equipment 13, 14, that is, as a function of the cumulative actuation powers PmT11, PmT12 and the cumulative accessory powers PaT13, PaT14 ([Fig.4]-b); - movements Mvtll, Mvtl2 and / or power-consuming functions F13, F14 implemented ([Fig.4]-c).

Claims

Claims

1. Monitoring method (100) for monitoring over a time period (T) an electrical power consumption by electrical equipment (11, 12, 13, 14) of a crane (1), which crane is powered by a supply power (PI) provided by at least one power source (2), which electrical equipment (11, 12, 13, 14) comprises: - actuating equipment (11, 12), wherein each of the actuating equipment (11, 12) comprises at least one motor controlled by a speed variator (111, 121) and coupled to at least one movable element (18, 19) of the crane (1) to actuate, in an active state (A11, A12), a movement of said at least one movable element (18, 19), otherwise it is in an inactive state (NA11, NA12); and - accessory equipment (13, 14) which is not actuating equipment (11, 12), in other words equipment which does not participate in the movement of a mobile element of the crane (1), and in which each of the accessory equipment (13, 14) provides a power consuming function (F13, F14) which is specific to it when it is in an active state (A13, A14), otherwise it is in an inactive state (NA13, NA14); said monitoring method (100) being implemented by a control-command system (15) connected to the speed variators (111, 121) of the actuation equipment (11, 12) and connected to the accessory equipment (13, 14) to switch them from the inactive state (NA11, NA12, NA13, NA14) to the active state (Ail, A12, A13, A14) and vice versa; said control-command system (15) containing at least one memory (152) and a processor (151) defined by a cycle time (te, tel, ten), and implementing at least, for each cycle time (te, tel, ten) included in the time period (T): - a determination (El) of a state (A 13, A14, NA 13, NA 14) of each accessory equipment (13, 14) to determine whether it is in the active state (A 13, A14) or in the inactive state (NA 13, NA 14), and to deduce therefrom an accessory power (Pal3-1, Pal4-1, Pal3-n, Pal4-n) consumed in the cycle time (te, tel, ten) by said accessory equipment (13, 14) when it is in the active state (A13, A14), on the basis of a model of electrical consumption (M13, M14) associated with said accessory equipment (13, 14) which is contained in the control-command system (15); - monitoring (E2) of each actuating equipment (11, 12) comprising receiving, from the corresponding speed variator (111, 121), an actuating power (Pmi 1-1, Pml2-1, Pmll-n, Pml2-n) consumed in the cycle time (te, tel, ten) by said actuating equipment (11, 12) when it is in the active state (Ail, A12).

2. Monitoring method (100) according to claim 1, in which the control-command system (15) implements at least after the time period (T): - a calculation (EC1), for each of the accessory equipment (13, 14), of a cumulative accessory power (PaT13, PaT14) consumed over the time period (T) by said accessory equipment (13, 14), by summing the accessory powers (Pal3-1, Pal4-1, Pal3-n, Pal4-n) consumed in the cycle times (te, tel, ten) where it was in the active state (A13, A14); - a calculation (EC2), for each of the actuating equipment (11, 12), of a cumulative actuating power (PmTll, PmT12) consumed over the time period (T) by said actuating equipment (11, 12), by summing the actuating powers (Pmi 1-1, Pml2-1, Pmll-n, Pml2-n) consumed in the cycle times (te, tel, ten) where it was in the active state (Ail, A12); - a deduction (EDI) of a total accessory power (TPA) corresponding to the sum of the cumulative accessory powers (PaT13, PaT14) consumed over the time period (T) by all the accessory equipment (13, 14); - a deduction (ED2) of a total actuation power (TPM) corresponding to the sum of the cumulative actuation powers (PmTl 1, PmT12) consumed over the time period (T) by all the actuation equipment (11, 12); - a comparison (Ecomp) between the supply power (PI), the total accessory power (TPA) and the total actuation power (TPM).

3. Monitoring method (100) according to claim 2, in which, after the time period (T), the control-command system (15) constitutes a set of power data (pdata) comprising at least: - the cumulative accessory powers (PaT13, PaT14) of all the accessory equipment (13, 14) during the time period (T), - the cumulative actuation powers (PmTll, PmT12) of all the actuation equipment (11, 12) during the time period (T), - the total accessory power (TPA), - the total actuation power (TPM), and - the supply power (PI); which set of power data (pdata) is time-stamped over the time period (T) and then recorded in the memory (152) of the control-command system (15).

4. Monitoring method (100) according to claim 3, wherein the power data set (pdata) is exportable from the control-command system (15) to a digital twin (Ml) of the crane (1) modeled in a remote IT infrastructure (4), the power data set (pdata) being put into a data format compatible with the digital twin (Ml) in order to be exploited by the latter.

5. Monitoring method (100) according to any one of claims 2 to 4, in which the control-command system (15) calculates, after the time period (T), an energy efficiency (eta) which is equal to the total actuation power (TPM) divided by the supply power (PI).

6. A monitoring method (100) according to claims 3 and 5, wherein the power data set (pdata) also comprises the energy efficiency (eta).

7. Monitoring method (100) according to any one of the preceding claims, in which the control-command system (15) determines, at each cycle time (te, tel, ten) included in the time period (T), and as a function of at least one electrical equipment (11, 12, 13, 14) among the actuating equipment (11, 12) and the accessory equipment (13, 14) being in the active state (Ail, A12, A13, A14), at least one state (Sl-1, Sl-n) of the crane (1) among at least one out-of-service state (NOP1) in which all the actuating elements (11, 12) are in the inactive state (NA11, NA12), and at least one in-service state (OP1) in which at least one of the actuating elements (11, 12) is in the active state (Ail, A12).

8. Monitoring method (100) according to claim 7, wherein when the at least one state (SI) of the crane (1) corresponds to the in-service state (OP1) for a given cycle time (te, tel, ten), the control-command system (15) associates for each of the actuating equipment (11, 12) a movement (Mvtll, Mvtl2) chosen at least from: - a distribution movement (Mvtl 1) associated with a distribution equipment (11) among the actuating equipment (11, 12) during which a load distribution maneuver is carried out along a boom (16) of the crane (1), - a lifting movement (Mvtl2) associated with a lifting equipment (12) among the actuating equipment (11, 12) during which a load lifting maneuver is carried out, - an orientation movement associated with an orientation equipment among the actuating equipment (11, 12) during which an orientation maneuver of an arrow (16) is carried out, - a translation movement associated with a translation device among the actuating devices (11, 12) during which a translation maneuver of the crane (1) is carried out, - a lifting movement associated with a lifting equipment among the actuating equipment (11, 12) during which a lifting maneuver of a luffing boom is carried out, or - an assembly movement during which an assembly of the crane (1) is carried out, which assembly movement is associated with an assembly equipment among the actuating equipment (11, 12) and chosen at least from: folding / unfolding equipment for folding / unfolding a mast (102) and a boom (16), wedging equipment for wedging the crane (1) on the ground, orientation equipment for orienting a base of the crane (1), jib equipment for actuating an assembly jib.

9. Monitoring method (100) according to claim 7 or 8, wherein when the at least one state (SI) of the crane (1) corresponds to the out-of-service state (NOP1) for a given cycle time (te, tel, ten), the control-command system (15) associates for each of the accessory equipment (13, 14) the consumer function (F13, F14) chosen at least from: - a heating function (F13) associated with heating equipment (13) among the accessory equipment (13, 14) for heating a control cabin (101) of the crane (1), and - an air conditioning function (F 14) associated with air conditioning equipment (14) among the accessory equipment (13, 14) for air conditioning a control cabin (101) of the crane (1).

10. Monitoring method (100) according to any one of the preceding claims, wherein the power consumption model (Ml3, M14) of each of the accessory equipment (13, 14) contains at least, in order to calculate the accessory power (Pal3-1, Pal4-1, Pal3-n, Pal4-n): - the cycle time (te, tel, ten), - a supply voltage (U 13, U14) for powering said accessory equipment (13, 14) when in the active state (A13, A14), - a consumption intensity (113, 114) of the accessory equipment (13, 14).

11. A monitoring method (100) according to any preceding claim, wherein the cycle time (te, tel, ten) is equal to 50 milliseconds, plus or minus 20%.

12. Monitoring method (100) according to any one of the preceding claims, in which the supply power (PI) is measured by a global electric meter (3) in connection with the control-command system (15).

Citation Information

Patent Citations

  • Monitoring system for electric energy efficiency of hoisting mechanism of crane

    CN215208123U

  • Crane energy consumption detection device

    CN216997307U

  • Intelligent tallying video monitoring auxiliary device based on 5G

    CN217264364U

  • Method for managing the electrical power supply of a crane from a primary source and a rechargeable secondary source

    FR3120618A1

  • AU2020102123A4