Program, production planning apparatus, and production planning method
The manufacturing planning device addresses the challenges of rescheduling tasks in dynamic production environments by using a task management system with conditional adjustments, enhancing task handling and production planning efficiency.
Patent Information
- Application Number
- JP2023109145
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-07-03
- Publication Date
- 2024-10-07
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Conventional manufacturing planning systems struggle with appropriately rescheduling tasks, especially in small-lot, high-mix production scenarios, handling emergency tasks, and displaying setup plans, leading to difficulties in managing manufacturing tasks effectively.
A manufacturing planning device that includes a task management section, schedule processing, rescheduling determining unit, and output units to manage and reschedule tasks based on various conditions, allowing for dynamic adjustments such as fixing or unfixing tasks based on static or dynamic conditions, inserting new tasks, and suspending tasks as needed.
Enables appropriate rescheduling of manufacturing tasks, allowing for better handling of emergency tasks, insertion of new tasks, and providing clear visual distinctions between fixed and non-fixed tasks, thereby improving production planning efficiency.
Smart Images

Figure 2024137592000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a manufacturing planning device that supports the scheduling of manufacturing tasks. [Background technology]
[0002] Conventionally, there has been an annual vehicle parts planning device that can produce parts in time for orders, produce parts on a priority line, and produce parts so as to reduce inventory (see Patent Document 1).
[0003] Furthermore, there has conventionally been a production plan display method that makes it possible to easily grasp the causal relationship between a production plan and a setup plan (see Patent Document 2). [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2020-140307 A [Patent Document 2] JP 2021-111092 A Summary of the Invention [Problem to be solved by the invention]
[0005] However, in the conventional technology, it is not possible to appropriately reschedule manufacturing tasks.
[0006] Furthermore, in the conventional technology, it was difficult to determine the optimal work sequence and also difficult to display a setup plan, particularly in the case of small-lot, high-mix production where new orders are placed many times a day.
[0007] In addition, for example, a task that must be given top priority in the work order, known as an "express" task, may arise, and on-site workers may decide to cancel the production of parts or materials that are in the middle of being worked on. In such cases, it would be difficult to deal with them using conventional technology. [Means for solving the problem]
[0008] The manufacturing planning device of the first invention includes a task management unit in which two or more task information, which is information that identifies a manufacturing task and corresponds to one or more task attribute values, is stored; a scheduling unit that performs schedule processing, which is processing to obtain schedule information that identifies a manufacturing schedule for the two or more task information based on one or more task attribute values of each of the two or more task information; a schedule output unit that outputs the schedule information; and a rescheduling determination unit that determines whether or not a rescheduling condition is met, wherein the scheduling unit performs schedule processing again when the rescheduling determination unit determines that the rescheduling condition is met, and the schedule output unit outputs schedule information that is a result of the rescheduling process.
[0009] With this configuration, manufacturing tasks can be appropriately rescheduled.
[0010] Further, the manufacturing planning device of the second invention differs from the first invention in that the rescheduling condition is that a certain amount of time or more than a certain amount of time has elapsed since the start of manufacturing, or that predetermined information has been accepted.
[0011] Such a configuration allows for better rescheduling of manufacturing tasks.
[0012] Furthermore, in the manufacturing planning device of the third invention, compared to the first or second invention, the scheduling unit is a manufacturing planning device in which, when the rescheduling determination unit determines that the rescheduling condition is met, the schedule of one or more task information that meets the fixed condition is fixed, and schedule information is acquired that specifies a manufacturing schedule for one or more task information that do not meet the fixed condition.
[0013] With this configuration, it is possible to more appropriately reschedule the production tasks by determining which tasks to fix. Note that by setting the tasks to fix as tasks that are scheduled to start within a predetermined time from the current time, for example, the workers can appropriately plan production.
[0014] Further, in contrast to the third invention, the manufacturing planning device of the fourth invention is a manufacturing planning device in which the fixed conditions are unchanging static fixed conditions.
[0015] With this configuration, the static fixation conditions can be used to better determine which tasks to fix, allowing for more appropriate rescheduling of manufacturing tasks.
[0016] Further, in contrast to the third invention, the manufacturing planning device of the fifth invention is a manufacturing planning device in which the fixed conditions are dynamic fixed conditions that change dynamically.
[0017] With this configuration, the dynamic fixation conditions can be used to more appropriately determine which tasks to fix, thereby allowing for more appropriate rescheduling of manufacturing tasks.
[0018] Furthermore, a manufacturing planning device of the sixth invention is a manufacturing planning device according to any one of the third to fifth inventions, further comprising an input receiving unit which receives input information from a user, and a special judgment unit which judges whether the input information matches a special condition for judging whether to unfix a task, and when the special judgment unit judges that the special condition is met, the scheduling unit performs schedule processing again, including one or more task information that matches the fixed condition.
[0019] Such an arrangement allows for better rescheduling of production tasks by not freezing tasks when special conditions are met.
[0020] In addition, the manufacturing planning device of the seventh invention is a manufacturing planning device according to any one of the first to fifth inventions, further comprising an input receiving unit that receives a hold instruction corresponding to task information, and a hold unit that performs hold processing to hold a task identified by the task information corresponding to the hold instruction.
[0021] Such an arrangement allows for better rescheduling of manufacturing tasks by deferring certain tasks to a later time.
[0022] In addition, the manufacturing planning device of the eighth invention is a manufacturing planning device according to any one of the first to fifth inventions, further comprising an input receiving unit that receives an instruction to insert task information into schedule information in which two or more pieces of task information are arranged, and a task generating unit that obtains one or more task attribute values of task information at a position preceding a position specified by the insertion instruction, obtains task information corresponding to the one or more task attribute values, and inserts the task information into the schedule information.
[0023] With this configuration, new task information can be easily inserted. Effect of the Invention
[0024] According to the manufacturing planning device of the present invention, it is possible to appropriately reschedule manufacturing tasks. [Brief description of the drawings]
[0025] [Figure 1] Conceptual diagram of information system A in embodiment 1. [Diagram 2] Block diagram of Information System A [Diagram 3] A flowchart illustrating an example of the operation of the manufacturing planning device 1. [Figure 4]A flowchart illustrating an example of the operation of the manufacturing planning device 1. [Diagram 5] A flowchart illustrating an example of the schedule process. [Figure 6] A flowchart illustrating an example of the task order determination process. [Figure 7] A flowchart illustrating an example of the rescheduling judgment process. [Figure 8] A flowchart illustrating an example of the special determination process. [Figure 9] A flowchart illustrating an example of the automatic rescheduling process. [Figure 10] A flowchart for explaining an example of the operation of the terminal device 2 [Figure 11] A diagram showing the task management table [Figure 12] A diagram showing the schedule management table [Figure 13] The fixed condition management table is shown in FIG. [Figure 14] A diagram showing an example of the output [Figure 15] Overview of the computer system [Figure 16] Block diagram of the computer system DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0026] Hereinafter, an embodiment of a manufacturing planning apparatus and the like will be described with reference to the drawings. In the embodiments, components with the same reference numerals perform similar operations, so that repeated description may be omitted.
[0027] (Embodiment 1) In this embodiment, a manufacturing planning device that performs rescheduling when there are two or more manufacturing tasks and a rescheduling condition, which is a condition for rescheduling the tasks, is met, will be described.
[0028] In this embodiment, a manufacturing planning device will be described that fixes the schedule of one or more tasks that meet a fixed condition and performs rescheduling.
[0029] In addition, in this embodiment, a manufacturing planning device that releases the fixation of a task and performs rescheduling when an input from a user matches a special condition will be described.
[0030] In addition, in this embodiment, a manufacturing planning device that reserves and postpones a specific task will be described.
[0031] Further, in this embodiment, a manufacturing planning device will be described that generates task information by utilizing the attribute value of a task preceding the task when inserting task information.
[0032] In this specification, information X being associated with information Y means that information Y can be obtained from information X, or information X can be obtained from information Y, and the method of association is not important. Information X and information Y may be linked, may exist in the same buffer, information X may be included in information Y, or information Y may be included in information X, etc.
[0033] 1 is a conceptual diagram of an information system A according to the present embodiment. The information system A includes a manufacturing planning device 1 and one or more terminal devices 2.
[0034] The manufacturing planning device 1 is a device that supports the scheduling of two or more tasks. A task is a task for manufacturing a product. In particular, the manufacturing planning device 1 is a scheduling support device that is effective for small-lot production of a wide variety of products. The scheduling support device may be considered to be a device that schedules two or more tasks. The manufacturing planning device 1 is, for example, a server. The manufacturing planning device 1 is, for example, a cloud server or an ASP server, but the type and location of the device are not important. The manufacturing planning device 1 may be a standalone device. When the manufacturing planning device 1 is a standalone device, the manufacturing planning device 1 is, for example, a mobile terminal such as a smartphone, a tablet terminal, or a mobile phone, or a personal computer, and the type is not important.
[0035] The terminal device 2 is a terminal used by a user. The terminal device 2 may be a mobile terminal such as a smartphone, a tablet terminal, or a mobile phone, or a personal computer, and the type of the terminal device 2 does not matter.
[0036] In this specification, a product is, for example, a part of a finished product, but may be a finished product of any type. A user is, for example, a production manager or a production supervisor, but may be a production staff member, but may be any type.
[0037] FIG. 2 is a block diagram of an information system A in this embodiment.
[0038] The manufacturing planning device 1 includes a storage unit 11, a reception unit 12, a processing unit 13, and an output unit 14. The storage unit 11 includes a task management unit 111, a schedule management unit 112, a reschedule condition management unit 113, a fixed condition management unit 114, and a special condition management unit 115. The reception unit 12 includes an input reception unit 121. The processing unit 13 includes a schedule unit 131, a special judgment unit 132, a reschedule judgment unit 133, a reservation unit 134, and a task generation unit 135. The output unit 14 includes a schedule output unit 141.
[0039] The terminal device 2 includes a terminal storage unit 21, a terminal reception unit 22, a terminal processing unit 23, a terminal transmission unit 24, a terminal reception unit 25, and a terminal output unit .
[0040] Various types of information are stored in the storage unit 11 constituting the manufacturing planning device 1. The various types of information are, for example, task information (to be described later), schedule information (to be described later), various conditions (to be described later), one or more pieces of worker information, and one or more pieces of target information.
[0041] The various conditions are, for example, a rescheduling condition, a fixed condition, a special condition, etc. It goes without saying that the rescheduling condition, the fixed condition, the special condition, etc. may be embedded in the program.
[0042] Worker information is information about a worker. A worker is usually a person who carries out production, but may also include a production manager or assistant. Worker information usually has a worker identifier and one or more worker attribute values. A worker identifier is information that identifies a worker. A worker identifier is, for example, a worker's ID, a worker's name, a telephone number, or an email address. A worker attribute value is information that specifies the attributes of a worker. A worker attribute value is, for example, level information that specifies the ability of a worker. Level information may be proficiency, years of work, etc.
[0043] Object information is information about an object to be manufactured. The object is typically a product. Object information typically has an object identifier and one or more object attribute values. An object identifier is information that identifies an object. An object identifier is, for example, an object ID or an object name. An object attribute value is information that specifies an attribute of an object. An object attribute value is, for example, the difficulty of manufacturing the object, the quantity of the object, or the size of the object.
[0044] Two or more pieces of task information are stored in the task management unit 111. Typically, task information for two or more tasks to be scheduled is stored in the task management unit 111. The task information is associated with, for example, a task identifier. The task management unit 111 may be provided in an external device.
[0045] Task information is information that identifies a task. Task information is information that corresponds to one or more task attribute values. Corresponding to one or more task attribute values may mean having one or more task attribute values. Task attribute values are information about a task. Task attribute values are, for example, the planned production quantity, color, information indicating whether it is an express order or not, jig information, deadline (which may be called delivery date), time, start time, end time, the number of workers who will perform the task, and the worker identifiers of one or more workers who will perform the task. Jig information is information about a jig used to perform a task. Jig information includes, for example, a jig identifier, a jig type, the number of hangers, and the number of hangers. The jig identifier is an identifier of a jig used to perform a task. The jig identifier is, for example, the name of the jig and the ID of the jig. The jig type is information that indicates the type of jig. The number of hangers is the number of hangers associated with the line. The number of hangers is the number of hangers to be hung on the hangers. The planned production quantity is the production quantity planned for this task. Color is the color of the object to be manufactured. Deadline is the deadline for completing the task (delivery date). Time indicates the time it takes to complete the task. Start time is the time when the task begins. End time is the time when the task ends. Task identifier is information that identifies a task. The task identifier is, for example, the ID or name of the task.
[0046] The schedule management unit 112 stores schedule information. The schedule information is information that specifies a schedule of a task for each of two or more pieces of task information. The schedule information is usually information that specifies the order of performance of two or more tasks. The schedule information has, for example, a task identifier, a start time, and an end time. The schedule information may have all or a part of each of two or more pieces of task information. The performance of a task is usually the manufacture of an object.
[0047] The rescheduling condition management unit 113 stores one or more rescheduling conditions. The rescheduling condition is a condition for performing a schedule process, which will be described later, again. The schedule process is a process of scheduling two or more tasks. The rescheduling condition is, for example, a time condition or an information condition. The time condition is a condition related to time. The time condition is, for example, that a certain amount of time or more has passed since the start of production or the previous scheduling, or that a certain amount of time has passed, or every certain amount of time, etc. The information condition is a condition related to the information that has been received. The information condition is, for example, that predetermined information has been received. The predetermined information is, for example, an instruction manual, defective product information. Note that the instruction manual is information in which instructions for production are written. The instruction manual is, in this case, usually electronic information. The instruction manual is, for example, one or more pieces of new task information. The defective product information is information regarding the occurrence of defects in production.
[0048] It should be noted that the received task information does not need to have all of the task attribute values of the task information stored in the task management unit 111 .
[0049] The fixed condition management unit 114 stores one or more fixed conditions. A fixed condition is a condition for specifying a task for which a schedule is to be fixed. A fixed condition may be a condition for specifying a non-fixed task. Since a fixed task is specified by a condition for specifying a non-fixed task, a condition for specifying a non-fixed task can also be said to be a condition for specifying a fixed task.
[0050] The fixed condition is, for example, a condition based on one or more task attribute values, a condition based on one or more worker attribute values, or a condition based on one or more target attribute values. The fixed condition is, for example, a static fixed condition or a dynamic fixed condition.
[0051] Static fixed conditions are static fixed conditions that do not change. For example, static fixed conditions are that the task is to be started within a specified time from the current time, or that the task is a record within a threshold from the current record. The current record is the record of the task currently being performed. Note that the reason that a task that is to be started within a specified time from the current time or a task with a record within a threshold from the current record is fixed (not subject to rescheduling) is, for example, to give workers more time for setup.
[0052] Dynamic fixed conditions are dynamic fixed conditions that can change. Dynamic fixed conditions are, for example, conditions that change based on task attribute values, conditions that change based on worker attribute values, and conditions that change based on target attribute values. Conditions that change based on task attribute values are, for example, conditions that change based on the number of workers involved in production. Conditions that change based on worker attribute values are, for example, conditions that change based on the level of the workers. Conditions that change based on target attribute values are, for example, conditions that change based on the difficulty of producing the target product.
[0053] The special condition management unit 115 stores one or more special conditions. The special condition is a condition for determining whether or not to unfix a task. The special condition is, for example, that task information corresponding to a task attribute value indicating an express has been accepted, or that a fixation removal instruction for unfixing a task has been accepted from a user.
[0054] The reception unit 12 receives various instructions and information. The various instructions and information are, for example, input information (to be described later), a hold instruction (to be described later), an insertion instruction (to be described later), task information corresponding to one or more task attribute values, a fixed removal instruction, an instruction sheet, defective product information, a hold instruction (to be described later), a hold release instruction (to be described later), and an output instruction. An output instruction is an instruction to output schedule information.
[0055] Here, acceptance typically refers to the reception of information transmitted via a wired or wireless communication line, but may also be a concept that includes the acceptance of information input from an input device such as a keyboard, mouse, or touch panel, and the acceptance of information read from a recording medium such as an optical disk, magnetic disk, or semiconductor memory.
[0056] The input receiving unit 121 receives input information. The input information is information input by a user. The input information is, for example, task information corresponding to a task attribute value indicating express, instructions, and defective product information. Note that the defective product information may not be input information, but may be information automatically received from an external device (for example, a manufacturing device, a quality control device).
[0057] The input receiving unit 121 receives a hold instruction. The hold instruction is an instruction to postpone a task. The hold instruction corresponds to task information. The hold instruction includes, for example, a task identifier.
[0058] The input receiving unit 121 receives an instruction to insert task information. The insertion instruction is an instruction to schedule information in which two or more pieces of task information are arranged. The insertion instruction has information specifying the position to insert. The information specifying the position to insert is, for example, a task identifier of the task information before insertion, but is not limited thereto.
[0059] The processing unit 13 performs various types of processing. The various types of processing are, for example, processing performed by a schedule unit 131, a special determination unit 132, a reschedule determination unit 133, a reservation unit 134, and a task generation unit 135.
[0060] The processing unit 13, for example, stores the information received by the input receiving unit 121. The information is usually stored in the storage unit 11, but the storage location is not critical.
[0061] The scheduler 131 performs a schedule process based on one or more task attribute values of two or more pieces of task information to be scheduled, and acquires the schedule information. Note that scheduling the task information is equivalent to scheduling the task. The two or more pieces of task information to be scheduled are usually stored in the task manager 111.
[0062] The schedule process is a process of acquiring schedule information that specifies the schedule for manufacturing two or more pieces of task information.
[0063] The scheduler 131 performs schedule processing using one or more task attribute values of two or more pieces of task information, usually to meet a deadline. The scheduler 131 performs schedule processing using one or more task attribute values of two or more pieces of task information, for example, to reduce the number of changes in the jig to be used and / or reduce the number of changes in the color of the product.
[0064] The scheduler 131 performs the schedule process so as to satisfy the following three conditions in the order of priority: (1) meeting the deadlines of all task information, (2) reducing the number of changes in the jigs used, and (3) reducing the number of color changes. The scheduler 131 performs the schedule process, for example, in accordance with the operations of the flowcharts in Figs. 5 and 6, which will be described later.
[0065] However, there is no restriction on the scheduling algorithm that the scheduler 131 uses for two or more pieces of task information to be scheduled.
[0066] The scheduler 131 may use, for example, a search-type algorithm called metaheuristics to perform scheduling for two or more pieces of task information and acquire the schedule information. Among the metaheuristics, it is preferable to use, for example, simulated annealing. More specifically, the scheduler 131 acquires the schedule information by a metaheuristic algorithm using, for example, one or more task attribute values (for example, deadline, production schedule, color, information indicating whether it is an express or not, jig information) of two or more pieces of task information, the jig quantity corresponding to each jig identifier stored in the storage unit 11, the quantity that can be applied to each jig, and the like. The schedule information here is information that specifies the order of the task information, and has, for example, the number of products to be applied to the jig. Since the metaheuristic algorithm is a known technique, a detailed description will be omitted.
[0067] The scheduler 131 may perform scheduling for two or more pieces of task information using, for example, a machine learning algorithm, and acquire the schedule information. The scheduler 131 or a learning unit (not shown) performs a machine learning learning process on two or more pieces of teacher data in which, for example, one or more task attribute values of two or more pieces of task information are used as explanatory variables, and schedule information specifying the order of two or more pieces of task information is used as a target variable, acquires a learning model, and accumulates it in the storage unit 11. In addition, the scheduler 131 provides, for example, one or more task attribute values of two or more pieces of task information to be scheduled and the learning model in the storage unit 11 to a prediction module that performs a machine learning prediction process, executes the prediction module, and acquires the schedule information.
[0068] The learning model is information configured by the learning process of machine learning, and is information used in the prediction process of machine learning. The learning model may be called a learner, a classifier, a classification model, or the like. The machine learning algorithm is preferably deep learning, but may be random forest, decision tree, or the like. For machine learning, for example, TensorFlow (registered trademark) library, random forest module of R language, various machine learning functions such as fastText, and various existing libraries can be used.
[0069] It is preferable that the scheduler 131 performs the schedule process again when the rescheduling judging unit 133 judges that the rescheduling conditions are met.
[0070] It is more preferable that, when the rescheduling determination unit 133 determines that the rescheduling conditions are met, the scheduling unit 131 fixes the schedule of one or more pieces of task information that meet the fixed conditions, and acquires schedule information that specifies a manufacturing schedule for one or more pieces of task information that do not meet the fixed conditions.
[0071] When the special determination unit 132 determines that the special condition is met, the schedule unit 131 preferably performs the schedule process again, including one or more pieces of task information that meet the fixed condition.
[0072] The special judgment unit 132 judges whether the input information accepted by the input acceptance unit 121 matches a special condition and acquires a judgment result. The judgment result is, for example, "remove the fix (e.g., "1")" or "do not remove the fix (e.g., "0")".
[0073] The rescheduling determination unit 133 determines whether or not the rescheduling condition is met, and acquires the determination result. The determination result is, for example, "scheduling is performed (e.g., "1")" or "scheduling is not performed (e.g., "0")".
[0074] The rescheduling determination unit 133, for example, obtains the current time from a clock (not shown) and determines whether the current time matches the time condition. For example, when the input receiving unit 121 receives information, the rescheduling determination unit 133 determines whether the information matches the information condition. There is no restriction on the timing at which the rescheduling determination unit 133 performs the above determination process. For example, the rescheduling determination unit 133 may perform the above determination process continuously (for example, constantly or periodically), or may perform the above determination process when the input receiving unit 121 receives information.
[0075] It is preferable that the reschedule determination unit 133 determines whether or not the reschedule condition is met during the execution of a task. Note that the execution of a task usually means that manufacturing is in progress.
[0076] The reservation unit 134 performs reservation processing to reserve a task identified by task information corresponding to the reservation instruction received by the reception unit 12. The reservation processing is, for example, processing to remove the task information from the schedule information. The reservation processing is, for example, processing to add a reservation flag to the task information. The reservation processing is, for example, processing to delete information (or task information) related to the task information corresponding to the reservation instruction from the task information. The reservation processing is, for example, processing to delete information related to the task information corresponding to the reservation instruction from the task information, and accumulate the task information corresponding to the reservation instruction in a predetermined buffer.
[0077] It is preferable that the holding unit 134 performs a hold release process for releasing the hold on task information corresponding to the hold release instruction received by the receiving unit 12. The hold release process is a process for releasing the hold. For example, the hold release process is a process for obtaining the task information to be released from the buffer and adding it to the schedule information. For example, the hold release process is a process for deleting the hold flag that pairs with the task information to be released. The hold release process may be any process that adds the task information to be released to the schedule information.
[0078] The task generation unit 135 acquires one or more task attribute values from task information at a position immediately before the position specified by the insertion instruction, acquires task information corresponding to the one or more task attribute values, and inserts the acquired information into the schedule information. For example, the task generation unit 135 acquires one or more task attribute values that are paired with a task identifier included in the insertion instruction (the task identifier of the task immediately before the task to be inserted) from the task management unit 111, and uses the one or more task attribute values to configure task information corresponding to the one or more task attribute values, and inserts the task information into the schedule information.
[0079] The output unit 14 outputs various types of information. The various types of information are, for example, schedule information and task information acquired by the task generation unit 135 etc. The output unit 14 transmits, for example, the schedule information to one or more terminal devices 2.
[0080] Here, output means transmission to terminal device 2, but it may also be a concept that includes display on a display, projection using a projector, printing on a printer, sound output, storage on a recording medium, and handing over the processing results to other processing devices or other programs, etc.
[0081] The schedule output unit 141 outputs schedule information. It is preferable that the schedule output unit 141 outputs schedule information that is a result of rescheduling.
[0082] Various types of information are stored in the terminal storage unit 21 constituting the terminal device 2. The various types of information are, for example, task information and schedule information.
[0083] The terminal reception unit 22 receives various instructions and information, such as task information, input information, hold instructions, insertion instructions, task information, fixed removal instructions, instruction sheets, defective product information, hold instructions, hold release instructions, and output instructions.
[0084] Here, reception is a concept that includes reception of information input from input devices such as a keyboard, mouse, or touch panel, reception of information transmitted via a wired or wireless communication line, and reception of information read from recording media such as an optical disk, magnetic disk, or semiconductor memory.
[0085] The means for inputting various instructions and information may be any means, such as a touch panel, a keyboard, a mouse, or a menu screen.
[0086] The device processing unit 23 performs various types of processing. For example, the various types of processing are processing for configuring information received by the device receiving unit 25 into data to be displayed. For example, the various types of processing are processing for configuring instructions, etc. accepted by the device accepting unit 22 into instructions, etc. to be transmitted.
[0087] The terminal transmitting unit 24 transmits various instructions, information, and the like to the manufacturing planning device 1. The various instructions, information, and the like are, for example, instructions configured by the terminal processing unit 23, instructions and information accepted by the terminal accepting unit 22, and the like.
[0088] The terminal receiving unit 25 receives various types of information from the manufacturing planning device 1. The various types of information include, for example, schedule information and task information.
[0089] The terminal output unit 26 acquires various types of information. The various types of information are, for example, information accepted by the terminal acceptance unit 22, information received by the terminal reception unit 25, and information configured by the device processing unit 23. The various types of information are, for example, schedule information and task information.
[0090] The storage unit 11, task management unit 111, schedule management unit 112, reschedule condition management unit 113, fixed condition management unit 114, special condition management unit 115, and terminal storage unit 21 are preferably non-volatile recording media, but can also be realized using volatile recording media.
[0091] There is no restriction on the process by which information is stored in the storage unit 11, etc. For example, information may be stored in the storage unit 11, etc. via a recording medium, information transmitted via a communication line, etc. may be stored in the storage unit 11, etc., or information inputted via an input device may be stored in the storage unit 11, etc.
[0092] It is preferable that the reception unit 12 and the input reception unit 121 are realized by wireless or wired communication means, but they may also be realized by a means for receiving broadcasts, a device driver for an input means such as a touch panel or keyboard, or control software for a menu screen.
[0093] The processing unit 13, the scheduler 131, the special judgment unit 132, the rescheduling judgment unit 133, the reservation unit 134, the task generation unit 135, and the terminal processing unit 23 can usually be realized by a processor, a memory, etc. The processing procedure of the processing unit 13, etc. is usually realized by software, and the software is recorded in a recording medium such as a ROM. However, it may be realized by hardware (dedicated circuit). The processor may be a CPU, an MPU, a GPU, etc., and the type is not important.
[0094] The output unit 14 and the schedule output unit 141 are usually realized by wireless or wired communication means, but may also be realized by driver software for an output device such as a display or speaker, or by a combination of driver software for an output device and the output device.
[0095] The terminal reception unit 22 can be realized by a device driver for an input means such as a touch panel or a keyboard, or control software for a menu screen.
[0096] The terminal transmitting unit 24 is usually realized by a wireless or wired communication means, but may also be realized by a broadcasting means.
[0097] The terminal receiving unit 25 is usually realized by a wireless or wired communication means, but may be realized by a means for receiving a broadcast.
[0098] The terminal output unit 26 may be considered to include, or may not include, an output device such as a display, a speaker, etc. The terminal output unit 26 may be realized by driver software for an output device, or a combination of driver software for an output device and an output device, etc.
[0099] Next, an example of the operation of the manufacturing planning device 1 constituting the information system A will be described with reference to the flowcharts of FIGS.
[0100] (Step S301) The input receiving unit 121 judges whether or not task information of a task to be executed has been received. If task information has been received, the process proceeds to step S301, and if task information has not been received, the process proceeds to step S303. Note that the task information received here is information of an unscheduled task. Also, in this step, the input receiving unit 121 receives task information from, for example, the terminal device 2.
[0101] (Step S302) The processing unit 13 accumulates the task information accepted in step S301 in the task management unit 111. Return to step S301. Note that the accumulated task information is task information to be scheduled in the future.
[0102] (Step S303) The input receiving unit 121 judges whether or not a schedule instruction has been received. If a schedule instruction has been received, the process proceeds to step S304, and if a schedule instruction has not been received, the process proceeds to step S306. In this step, the input receiving unit 121 receives a schedule instruction from, for example, the terminal device 2. The input receiving unit 121 may also receive a schedule instruction when a predetermined time is reached. In other words, for example, schedule processing may be started when a specific time is reached every day on the day when production is performed.
[0103] (Step S304) Scheduling unit 131 performs scheduling for two or more pieces of task information in task management unit 111. This processing is called scheduling processing. An example of scheduling processing will be described with reference to the flowchart of FIG.
[0104] (Step S305) The schedule output unit 141 outputs the schedule information acquired in step S304. Return to step S301. Note that in this step, the schedule output unit 141 transmits, for example, the schedule information acquired in step S304 to the terminal device 2.
[0105] (Step S306) The input receiving unit 121 judges whether or not an output instruction has been received. If an output instruction has been received, the process proceeds to step S307. If an output instruction has not been received, the process proceeds to step S309. In this step, the input receiving unit 121 receives the output instruction from, for example, the terminal device 2.
[0106] (Step S307) The processing unit 13 acquires schedule information corresponding to the output instruction from the schedule management unit 112. Next, the processing unit 13 configures the schedule information to be output.
[0107] (Step S308) The schedule output unit 141 outputs the schedule information acquired in step S307. Return to step S301. Note that in this step, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2, for example.
[0108] (Step S309) The input receiving unit 121 judges whether or not information has been received. If information has been received, the process proceeds to step S310. If information has not been received, the process proceeds to step S318. In this step, the input receiving unit 121 receives information from, for example, the terminal device 2.
[0109] (Step S310) The processing unit 13 accumulates the information received in step S309 in the storage unit 11. The processing unit 13 may or may not accumulate the information depending on the type of information. For example, if the information is an instruction manual or task information, it is preferable that the processing unit 13 accumulates the information.
[0110] (Step S311) The reschedule determination unit 133 performs a reschedule determination process using the information received in step S309. The reschedule determination process is a process for determining whether or not to reschedule. An example of the reschedule determination process will be described with reference to the flowchart of FIG.
[0111] (Step S312) The scheduler 131 judges whether the judgment result in step S311 was "perform rescheduling (for example, "1")" or "do not perform rescheduling (for example, "0")." If "perform rescheduling," the process proceeds to step S313, and if "do not perform rescheduling," the process proceeds to step S315.
[0112] (Step S313) The scheduler 131 performs rescheduling. An example of such a schedule process will be described with reference to the flowchart of FIG.
[0113] (Step S314) The schedule output unit 141 outputs the schedule information acquired in step S307. Return to step S301. Note that in this step, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2, for example.
[0114] (Step S315) The special judgment unit 132 performs a special judgment process. The special judgment process is a process for judging whether or not to unfix a fixed task in the task schedule. An example of the special judgment process will be described with reference to the flowchart of FIG. 8.
[0115] (Step S316) If the result of the determination in step S315 is "remove the fix (for example, "1")", the schedule unit 131 proceeds to step S317, and if the result is "do not remove the fix (for example, "0")", the schedule unit 131 returns to step S301.
[0116] (Step S317) The scheduler 131 turns off the fixed flag, and then proceeds to step S313.
[0117] (Step S318) The input reception unit 121 judges whether or not a hold instruction has been received. If a hold instruction has been received, the process proceeds to step S319. If a hold instruction has not been received, the process proceeds to step S322. In this step, the input reception unit 121 receives a hold instruction from, for example, the terminal device 2.
[0118] (Step S319) The reservation unit 134 performs reservation processing. The reservation unit 134 deletes the task information corresponding to the reservation instruction from the schedule information, and accumulates the task information in a predetermined buffer.
[0119] (Step S320) The scheduling unit 131 acquires schedule information excluding the reserved task information. The scheduling unit 131 may perform the schedule processing of Fig. 5 using two or more pieces of task information corresponding to the current schedule information excluding the reserved task information. This processing is a rescheduling processing.
[0120] (Step S321) The schedule output unit 141 outputs the schedule information acquired in step S320. Return to step S301. Note that in this step, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2, for example. Return to step S301.
[0121] (Step S322) The input reception unit 121 judges whether or not a hold-return instruction has been received. If a hold-return instruction has been received, the process proceeds to step S323. If a hold-return instruction has not been received, the process proceeds to step S326. In this step, the input reception unit 121 receives the hold-return instruction from, for example, the terminal device 2.
[0122] (Step S323) The reservation unit 134 performs reservation release processing. The reservation unit 134 performs processing to add a task corresponding to the reserved task information to the schedule. For example, the reservation unit 134 adds the reserved task information to the schedule information. For example, the reservation unit 134 instructs the schedule unit 131 to perform schedule processing again by using two or more pieces of task information including the reserved task information.
[0123] (Step S324) The scheduling unit 131 acquires schedule information that incorporates the information of the pending task that has been released from suspension into the schedule. The scheduling unit 131 may perform the schedule process of Fig. 5 using two or more pieces of task information including the information of the pending task that has been released from suspension. This process is a rescheduling process.
[0124] (Step S325) The schedule output unit 141 outputs the schedule information acquired in step S324. Return to step S301. Note that in this step, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2, for example. Return to step S301.
[0125] (Step S326) The input reception unit 121 judges whether or not an insertion instruction for task information has been received. If an insertion instruction has been received, the process proceeds to step S327. If an insertion instruction has not been received, the process proceeds to step S335. In this step, the input reception unit 121 receives the insertion instruction from, for example, the terminal device 2.
[0126] (Step S327) The task generation unit 135 obtains one or more task attribute values corresponding to the task information immediately before the inserted task information.
[0127] (Step S328) The task generating unit 135 generates task information by using the one or more task attribute values acquired in step S327.
[0128] (Step S329) The task generation unit 135 assigns 1 to a counter i.
[0129] (Step S330) The task generation unit 135 judges whether or not the i-th task information is present in the schedule information among the task information excluding the inserted task information. If the i-th task information is present, the process proceeds to step S331, and if not, the process proceeds to step S333.
[0130] (Step S331) The task generating unit 135 changes one or more attribute values that should be changed by inserting the task information, among one or more attribute values corresponding to the i-th task information. The attribute values that should be changed are, for example, the start time and the end time.
[0131] (Step S332) The task generation unit 135 increments the counter i by 1. The process returns to step S330.
[0132] (Step S333) The schedule unit 131 acquires new schedule information into which the new task information has been inserted.
[0133] (Step S334) The schedule output unit 141 outputs the schedule information acquired in step S324. Return to step S301. Note that in this step, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2, for example. Return to step S301.
[0134] (Step S335) The scheduler 131 performs an automatic rescheduling process. Return to step S301. The automatic rescheduling process is to automatically perform a rescheduling process. An example of the automatic rescheduling process will be described with reference to the flowchart of FIG.
[0135] Note that, instead of the processing of steps S329 to S333 in FIG. 4, the scheduler 131 may fix the task information up to the inserted task information, and perform rescheduling for two or more pieces of task information after the inserted task information, to obtain the schedule information to be output.
[0136] In the flowcharts of FIG. 3 and FIG. 4, the process ends when the power is turned off or an interrupt for ending the process occurs.
[0137] Next, an example of the schedule process in step S304 will be described with reference to the flowchart in FIG.
[0138] (Step S501) The scheduler 131 judges whether the fixed flag in the storage unit 11 is ON or OFF. If the fixed flag is ON, the process proceeds to step S502, and if it is OFF, the process proceeds to step S503.
[0139] (Step S502) The scheduler 131 acquires one or more pieces of non-fixed task information from the task manager 111 or the schedule manager 112 based on one or more fixed conditions.
[0140] (Step S503) The scheduler 131 acquires information on all tasks to be scheduled from the task manager 111 or the schedule manager 112.
[0141] (Step S504) The scheduler 131 performs a task order determination process for two or more pieces of acquired task information. An example of the task order determination process will be described with reference to the flowchart of FIG.
[0142] (Step S505) The schedule unit 131 acquires schedule information corresponding to two or more pieces of task information based on the order acquired in step S504, and returns to the upper process.
[0143] Next, an example of the task order determination process in step S504 will be described with reference to the flowchart in FIG.
[0144] (Step S601) The scheduler 131 acquires all task order combinations for two or more pieces of acquired task information. If three pieces of acquired task information are acquired, the number of task order combinations is six. Furthermore, a combination of task orders is appropriately referred to as a set.
[0145] (Step S602) The scheduler 131 assigns 1 to a counter i.
[0146] (Step S603) The scheduler 131 judges whether or not the i-th set exists. If the i-th set exists, the process proceeds to step S604, and if not, the process proceeds to step S614.
[0147] (Step S604) The scheduler 131 assigns 1 to a counter j.
[0148] (Step S605) The scheduler 131 judges whether or not the j-th task information exists in the i-th set. If the j-th task information exists, the process proceeds to step S606, and if not, the process proceeds to step S612.
[0149] (Step S606) The scheduler 131 assigns 1 to a counter ki.
[0150] (Step S607) The schedule unit 131 judges whether or not the kth necessary condition exists for adopting the i-th set. If the kth necessary condition exists, the process proceeds to step S608, and if not, the process proceeds to step S612. An example of the necessary condition is that the end time is within the deadline.
[0151] (Step S608) The scheduler 131 judges whether or not the j-th task information satisfies the k-th essential condition. If the j-th task information satisfies the k-th essential condition, the process proceeds to step S609. If the j-th task information does not satisfy the k-th essential condition, the process proceeds to step S610.
[0152] (Step S609) The scheduler 131 increments the counter k by 1. The process returns to step S607.
[0153] (Step S610) The scheduler 131 increments the counter i by 1. The process returns to step S603.
[0154] (Step S611) The scheduler 131 increments the counter j by 1. The process returns to step S605.
[0155] (Step S612) The scheduler 131 temporarily stores the i-th task order combination (set) in a buffer (not shown).
[0156] (Step S613) The scheduler 131 increments the counter i by 1. The process returns to step S603.
[0157] (Step S614) The scheduler 131 assigns 1 to the counter i.
[0158] (Step S615) The scheduler 131 judges whether or not the i-th set exists in a buffer (not shown). If the i-th set exists, the process proceeds to step S616, and if not, the process proceeds to step S621.
[0159] (Step S616) The scheduler 131 assigns 1 to the counter j.
[0160] (Step S617) The scheduler 131 judges whether or not the jth viewpoint for obtaining the score exists. If the jth viewpoint exists, the process proceeds to step S618, and if the jth viewpoint does not exist, the process proceeds to step S620. Note that the viewpoint may be, for example, a change of a jig in manufacturing, a change of color in manufacturing, or the like.
[0161] (Step S618) The schedule unit 131 acquires a viewpoint score that is a score related to the j-th viewpoint. Note that the viewpoint score has a larger value, for example, as the number of jig changes in the schedule is reduced, and as the number of color changes in the schedule is reduced.
[0162] (Step S619) The scheduler 131 increments the counter i by 1. The process returns to step S617.
[0163] (Step S620) The scheduling unit 131 acquires a score for the i-th set using a viewpoint score of 1 or more. Note that the score increases as the viewpoint score increases. The scheduling unit 131 acquires a score that is, for example, the sum of two or more viewpoint scores.
[0164] (Step S621) The scheduler 131 increments the counter i by 1. The process returns to step S615.
[0165] (Step S622) The schedule unit 131 acquires the task order combination (set) with the best score. Note that this set constitutes schedule information.
[0166] In the flowchart of FIG. 6, when a combination (set) of task orders having a score equal to or greater than a threshold is detected, the set may be adopted as the final set.
[0167] In the flowchart of FIG. 6, the schedule unit 131 may obtain the schedule information by using the above-mentioned metaheuristics algorithm or machine learning algorithm.
[0168] Next, an example of the rescheduling determination process in step S311 will be described with reference to the flowchart in FIG.
[0169] (Step S701) The reschedule determination unit 133 assigns 1 to a counter i.
[0170] (Step S702) The reschedule determination unit 133 determines whether or not the i-th reschedule condition exists in the reschedule condition management unit 113. If the i-th reschedule condition exists, the process proceeds to step S703, and if not, the process proceeds to step S707.
[0171] (Step S703) The reschedule determination unit 133 acquires the i-th reschedule condition from the reschedule condition management unit 113.
[0172] (Step S704) The rescheduling determination unit 133 determines whether or not the i-th rescheduling condition is met. If the i-th rescheduling condition is met, the process proceeds to step S705, and if not, the process proceeds to step S706.
[0173] (Step S705) The rescheduling judgment unit 133 assigns "scheduling is performed" to the variable "judgment result." Then, the process returns to the upper level process.
[0174] (Step S706) The reschedule determination unit 133 increments the counter i by 1. The process returns to step S702.
[0175] (Step S707) The reschedule determination unit 133 assigns "no scheduling" to the variable "determination result", and returns to the upper level process.
[0176] Next, an example of the special determination process in step S315 will be described with reference to the flowchart in FIG.
[0177] (Step S801) The special judgment unit 132 assigns 1 to a counter i.
[0178] (Step S802) The special judgment unit 132 judges whether or not the i-th special condition exists in the special condition management unit 115. If the i-th special condition exists, the process proceeds to step S703, and if not, the process proceeds to step S707.
[0179] (Step S803) The special judgment unit 132 acquires the i-th special condition from the special condition management unit 115.
[0180] (Step S804) The special judgment unit 132 judges whether or not the information accepted in step S309 matches the i-th special condition. If the information matches the i-th special condition, the process proceeds to step S705. If the information does not match the i-th special condition, the process proceeds to step S706.
[0181] (Step S805) The special judgment unit 132 assigns "unfix" to the variable "judgment result". Then, the process returns to the upper level process.
[0182] (Step S806) The special judgment unit 132 increments the counter i by 1. The process returns to step S702.
[0183] (Step S807) The special judgment unit 132 assigns "Do not remove fixation" to the variable "judgment result". Then, the process returns to the upper level process.
[0184] Next, an example of the automatic rescheduling process in step S33 will be described with reference to the flowchart in FIG.
[0185] (Step S901) The reschedule determination unit 133 assigns 1 to a counter i.
[0186] (Step S902) The reschedule determination unit 133 determines whether or not the i-th reschedule condition exists in the reschedule condition management unit 113. If the i-th reschedule condition exists, the process proceeds to step S903, and if not, the process returns to the upper process.
[0187] (Step S903) The rescheduling determination unit 133 acquires the i-th rescheduling condition from the rescheduling condition management unit 113.
[0188] (Step S904) The rescheduling determination unit 133 determines whether or not the i-th rescheduling condition is met. If the i-th rescheduling condition is met, the process proceeds to step S313, and if not, the process proceeds to step S905.
[0189] (Step S905) The scheduler 131 increments the counter i by 1. The process returns to step S902.
[0190] Next, an example of the operation of the terminal device 2 will be described with reference to the flowchart of FIG.
[0191] (Step S1001) The terminal reception unit 22 judges whether or not task information to be performed has been received. If task information has been received, the process proceeds to step S1002, and if not, the process proceeds to step S1003.
[0192] (Step S1002) The terminal processing unit 23 is configured to transmit the task information accepted by the terminal accepting unit 22. The terminal transmitting unit 24 transmits the task information to the manufacturing planning device 1.
[0193] (Step S1003) The terminal reception unit 22 judges whether or not a schedule instruction or an output instruction has been received. If a schedule instruction or an output instruction has been received, the process proceeds to step S1004, and if not, the process proceeds to step S1007.
[0194] (Step S1004) The terminal processing unit 23 is configured to transmit the instruction received in step S1003 by the terminal receiving unit 22. The terminal transmitting unit 24 transmits the instruction to the manufacturing planning device 1.
[0195] (Step S1005) The terminal receiving unit 25 judges whether or not the schedule information has been received. If the schedule information has been received, the process proceeds to step S1006, and if not, the process returns to step S1005.
[0196] (Step S1006) The terminal processing unit 23 is configured to output the schedule information received by the terminal receiving unit 25. The terminal output unit 26 outputs the schedule information. Return to step S1001.
[0197] (Step S1007) The terminal reception unit 22 judges whether or not information (for example, an instruction manual, defective product information) has been received. If task information has been received, the process proceeds to step S1008, and if no information has been received, the process proceeds to step S1011.
[0198] (Step S1008) The terminal processing unit 23 is configured to transmit the information received in step S1007 by the terminal receiving unit 22. The terminal transmitting unit 24 transmits the information to the manufacturing planning device 1.
[0199] (Step S1009) The terminal receiving unit 25 judges whether or not information has been received. If schedule information has been received, the process proceeds to step S1010, and if not, the process returns to step S1009.
[0200] (Step S1010) The terminal processing unit 23 is configured to output information (for example, schedule information) received by the terminal receiving unit 25. The terminal output unit 26 outputs the information. Return to step S1001.
[0201] (Step S1011) The terminal reception unit 22 judges whether or not a hold instruction has been received. If a hold instruction has been received, the process proceeds to step S1012, and if not, the process proceeds to step S1013.
[0202] (Step S1012) The terminal processing unit 23 is configured to transmit the hold instruction received in step S1011 by the terminal receiving unit 22. The terminal transmitting unit 24 transmits the hold instruction to the manufacturing planning device 1.
[0203] (Step S1013) The terminal reception unit 22 judges whether or not a hold-return instruction has been received. If a hold-return instruction has been received, the process proceeds to step S1014, and if not, the process proceeds to step S1015.
[0204] (Step S1014) The terminal processing unit 23 is configured to transmit the hold release instruction received in step S1013 by the terminal receiving unit 22. The terminal transmitting unit 24 transmits the hold release instruction to the manufacturing planning device 1.
[0205] (Step S1015) The terminal reception unit 22 judges whether or not an instruction to insert task information has been received. If an instruction to insert task information has been received, the process proceeds to step S1016, and if not, the process proceeds to step S1017.
[0206] (Step S1016) The terminal processing unit 23 is configured to transmit the insertion instruction received in step S1015 by the terminal receiving unit 22. The terminal transmitting unit 24 transmits the insertion instruction to the manufacturing planning device 1.
[0207] (Step S1017) The terminal receiving unit 25 judges whether or not the schedule information has been received. If the schedule information has been received, the process proceeds to step S1006, and if not, the process returns to step S1001.
[0208] In the flowchart of FIG. 10, the process ends when the power is turned off or an interrupt is issued to end the process.
[0209] A specific operation example of the information system A in this embodiment will be described below. It is assumed that today's worker level "3" is stored in the storage unit 11 of the manufacturing planning device 1. In addition, the storage unit 11 stores, for example, the number of jigs for each jig identifier (type of jig) and the specifications of the jig for each jig identifier (for example, the number of manufacturing objects that can be hung, etc.).
[0210] Furthermore, the task management unit 111 stores a task management table shown in FIG. 11. The task management table is a table for managing one or more pieces of task information. The task management table is a collection of task information transmitted from the terminal device 2 and accumulated in the task management unit 111. The task information in the task management unit 111 is task information that is the subject of scheduling. The task management table stores a large number of records each having a task identifier and a task attribute value. The task attribute values include "jig identifier," "number of hangers," "number of runs," "total number of times," "deadline," and "difficulty level."
[0211] Furthermore, the schedule management unit 112 stores a schedule management table having a structure shown in FIG. 12. The schedule management table is a table that specifies the order in which tasks are performed. The schedule management table has two or more records each having an "ID," "task identifier," "start time," and "end time." Each record corresponds to one task. The "ID" is information that identifies the record. The "start time" is the scheduled time to start the task, and the "end time" is the scheduled time to end the task. Each record may have one or more task attribute values.
[0212] Rescheduling condition management unit 113 stores, for example, rescheduling conditions such as a time condition "every two hours" and an information condition "an instruction sheet has been received."
[0213] The fixed condition management unit 114 stores a fixed condition management table shown in FIG. 13. The fixed condition management table has two or more records having [ID] "fixed condition information". The "fixed condition information" has "applicable condition" and "fixed condition". The "applicable condition" is a condition for applying the fixed condition. The fixed condition information of "ID=1" indicates that if the worker level is 3 or less, or if the difficulty level of the task to be fixed is 4 or more, the task to be started within 2 hours from the current time is fixed. The fixed condition information of "ID=2" indicates that if the applicable condition of "ID=1" is not met, the task to be started within 1 hour from the current time is fixed. As described above, if a special condition is met, the fixed condition is not applied. Fixing a task to be started within a predetermined time from the current time is preferable because it gives the worker time to make arrangements.
[0214] It is assumed that information indicating "task information including the task attribute value 'express' has been accepted" and "a fixed exclusion instruction has been accepted" is stored in the special condition management unit 115. The information indicating "a fixed exclusion instruction has been accepted" indicates that when a fixed exclusion instruction is accepted, the fixed task is to be unfixed.
[0215] Then, it is assumed that before the start of production today (for example, March 2), an operator inputs a schedule instruction to the terminal device 2. Next, the terminal device 2 accepts the schedule instruction and transmits it to the production planning device 1.
[0216] In such a case, the following five concrete examples will be described. Specific example 1 is an example of a scheduling process, and is an example of a schedule that clearly indicates a fixed task. Specific example 2 is a case in which rescheduling is performed when information received during production matches a rescheduling condition. Specific example 3 is a case in which a fixed task is unfixed and rescheduled when a special condition is met. Specific example 4 is a case in which a worker inputs a hold instruction. Specific example 5 is a case in which a worker inserts a new task.
[0217] (Example 1) Next, the input receiving unit 121 of the manufacturing planning device 1 receives the schedule instruction. Next, the schedule unit 131 acquires schedule information by the above-mentioned algorithm (for example, the processes in FIGS. 5 and 6) using the task attribute values in the task management table (FIG. 11).
[0218] Next, the schedule unit 131 writes the acquired schedule information into a schedule management table. Such schedule information is the schedule management table of FIG.
[0219] Next, the schedule unit 131 composes schedule information to be transmitted, using the schedule management table of Fig. 12 and the task management table of Fig. 11. Next, the schedule output unit 141 transmits the composed schedule information to the terminal device 2.
[0220] Next, the terminal device 2 receives and outputs the schedule information, and the worker carries out the work according to the schedule information.
[0221] According to the schedule information, the current time is "T 11 " and the worker starts production. Then, the reschedule determination unit 133 determines the task information to be fixed as follows. That is, the reschedule determination unit 133 reads out the level "3" of the worker for today from the storage unit 11. The reschedule determination unit 133 determines that the applied condition of "ID=1" in the fixed condition management table (FIG. 13) is met, and acquires the fixed condition of "ID=1". Next, the reschedule determination unit 133 acquires the current time. Next, the reschedule determination unit 133 determines that the task information to be started within two hours from the current time is information to be fixed. Next, the schedule unit 131 acquires schedule information that clearly indicates the task to be fixed. Next, the schedule output unit 141 transmits the schedule information to the terminal device 2.
[0222] Next, the terminal device 2 receives and outputs the schedule information. An example of such output is shown in FIG. 14. In FIG. 14, a boundary line 1401 is drawn between the fixed tasks and the non-fixed tasks. That is, the tasks in the range of 1402 are the fixed tasks. Furthermore, the tasks in the range of 1403 are the tasks to be scheduled when rescheduling. Note that there is no restriction on the method for making the worker recognize the fixed tasks. For example, the background color of the fixed tasks may be different from the background color of the non-fixed tasks. However, it is preferable that the fixed tasks and the non-fixed tasks are visually distinguishable.
[0223] Moreover, it is preferable that the terminal device 2 outputs the currently executed task in a manner that makes it possible to distinguish it from other tasks in Fig. 14. A task 1404 is currently being executed.
[0224] (Example 2) After the start of production, during production, the input receiving unit 121 of the production planning device 1 receives one or more new task information items from the terminal device 2, and the processing unit 13 accumulates the task information items in the task management unit 111.
[0225] It is now assumed that two hours have passed since the start of the work. The reschedule determination unit 133 acquires the time condition "every two hours" from the reschedule condition management unit 113. Next, the schedule unit 131 acquires the most recent scheduling time and the current time, and determines that two hours have passed. In other words, the reschedule determination unit 133 determines that rescheduling should be performed.
[0226] Next, the scheduler 131 performs rescheduling as follows. That is, the scheduler 131 determines that the fixation flag in the storage unit 11 is ON, which is the default. Next, the scheduler 131 acquires task information of tasks excluding fixed tasks whose task attribute values, namely, start times are within two hours from the current time, from the task management table (FIG. 11). Next, the scheduler 131 performs task order determination processing (for example, processing of the flowchart in FIG. 6) of the acquired two or more pieces of task information, and acquires schedule information. Next, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2.
[0227] Next, the terminal device 2 receives and outputs the schedule information. An image of such output is shown in Fig. 14. The output schedule information includes a line (1401) that clearly indicates a fixed task.
[0228] In this example, one or more specific tasks are fixed, and rescheduling is performed among the non-fixed tasks. In addition, rescheduling of tasks is performed at necessary timing. As a result, the worker can obtain appropriate schedule information according to the frequently changing task situation.
[0229] (Example 3) It is assumed that an urgent task has come in, and the worker inputs task information including the task attribute value “urgent” to the terminal device 2. Then, the terminal device 2 accepts the task information and transmits it to the manufacturing planning device 1.
[0230] The input receiving unit 121 of the manufacturing planning device 1 receives task information including the task attribute value "express". Next, the processing unit 13 accumulates the task information in the task management table. Next, the special judgment unit 132 judges that the task information including the task attribute value "express" matches a special condition. The special condition is that "task information including the task attribute value "express" has been accepted."
[0231] Next, the scheduler 131 turns off the fixation flag. Then, the scheduler 131 acquires all of the two or more pieces of task information that include the received task information and have not yet been executed. Next, the scheduler 131 performs the above-mentioned scheduling process on the acquired two or more pieces of task information to acquire the schedule information. The scheduling process is, for example, the process described with reference to Figs. 5 and 6. Note that using all of the two or more pieces of task information that have not yet been executed means that there is no task information to fix.
[0232] Next, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2.
[0233] Next, the terminal device 2 receives and outputs the schedule information.
[0234] As described above, in this specific example, the task is released from the pinning state and can be rescheduled.
[0235] (Example 4) Assume now that the list of tasks shown in FIG.
[0236] It is assumed that the worker then inputs a "hold instruction" for the line (task) 1405 in FIG. 14. Note that the method for inputting the hold instruction is not important. For example, although not shown, the hold instruction is input by checking the line 1405 in FIG. 14 and instructing the "hold" button. Note that the hold instruction includes the task identifier "T008" of the task 1405.
[0237] Next, the terminal receiving unit 22 receives a reservation instruction including the task identifier “T008”, and transmits it to the manufacturing planning device 1.
[0238] Next, the input receiving unit 121 of the manufacturing planning device 1 receives the reservation instruction. Next, the reservation unit 134 performs reservation processing. That is, the reservation unit 134 removes the task information corresponding to the task identifier "T008" from the schedule information. Also, the reservation unit 134 accumulates the task information corresponding to the task identifier "T008" in a predetermined buffer, which is a buffer for storing reserved task information. Then, the schedule unit 131 acquires two or more pieces of task information to be scheduled that do not include the task information corresponding to the task identifier "T008". Next, the schedule unit 131 performs a scheduling process again on the acquired two or more pieces of task information to acquire schedule information. The scheduling process is, for example, the process described with reference to FIG. 5 and FIG. 6. Here, the schedule unit 131 acquires the schedule information in which the fixed task has been changed. Next, the schedule output unit 141 transmits the schedule information to the terminal device 2.
[0239] Next, the terminal device 2 receives and outputs the schedule information. This schedule information is the schedule information in Fig. 14 without the line 1405. In addition, in the output of the schedule information, the fixed tasks have been changed compared to Fig. 14.
[0240] In this embodiment, certain task information may be put on hold, for example, according to changing conditions during production.
[0241] (Example 5) Assume now that the list of tasks shown in FIG.
[0242] Assume that the worker is performing the task of 1406. Assume that the worker is only able to perform the multiplier of "50" out of the multiplier of "56" while he / she should have performed the task of 1406.
[0243] Then, it is assumed that the worker inputs an instruction to insert task information so that new task information is inserted under task 1406 in FIG. 14. Next, the terminal receiving unit 22 of the terminal device 2 receives the instruction to insert task information. The insertion instruction includes the task identifier "T006" of the task information 1406. Next, the terminal transmitting unit 24 transmits an insertion instruction including the task identifier "T006" to the manufacturing planning device 1. Note that the task information to be inserted is the task information to be inserted immediately after the task identified by the task identifier "T006".
[0244] Next, the input receiving unit 121 of the manufacturing planning device 1 receives the insertion instruction. Next, the task generating unit 135 obtains one or more task attribute values that are paired with the task identifier "T006" included in the insertion instruction from the task management table (FIG. 11). The task identifier "T006" is information that identifies the task immediately before the newly generated task.
[0245] Next, the task generating unit 135 generates new task information using the one or more acquired task attribute values.
[0246] Next, the schedule unit 131 acquires new schedule information into which the newly generated task information has been inserted. Next, the schedule output unit 141 transmits the acquired schedule information to the terminal device 2.
[0247] Next, the terminal device 2 receives and outputs the schedule information. This schedule information is the schedule information in Fig. 14 with a line having the same task attribute value as line 1406 added to the line next to 1406. Then, the worker changes the task attribute value of the added line (task information) as necessary. It is assumed here that the worker changes the repetition number of the added line (task information) to the repetition number "6" that could not be worked on.
[0248] According to this example, new task information can be easily added depending on the manufacturing situation.
[0249] As described above, according to this embodiment, manufacturing tasks can be appropriately rescheduled.
[0250] Furthermore, according to the present embodiment, by providing fixed tasks, the rescheduling of manufacturing tasks can be performed more appropriately. More specifically, by providing fixed tasks, for example, the rescheduling of tasks can be performed appropriately while giving workers ample time for setup.
[0251] Furthermore, according to this embodiment, the tasks to be fixed are determined using the static fixing conditions or the dynamic fixing conditions, so that the rescheduling of the manufacturing tasks can be performed more appropriately.
[0252] Additionally, the present invention allows for better rescheduling of manufacturing tasks by not fixing tasks when special conditions are met.
[0253] Furthermore, according to this embodiment, by postponing (putting on hold) certain tasks, rescheduling of manufacturing tasks can be performed more appropriately.
[0254] Furthermore, according to this embodiment, new task information can be easily inserted.
[0255] In this embodiment, the manufacturing planning device 1 may be a standalone device. In such a case, the reception unit 12 and the input reception unit 121 usually receive information and instructions from a worker or the like. The output unit 14 and the schedule output unit 141 usually output information such as schedule information to a display.
[0256] The process in this embodiment may be realized by software. This software may be distributed by software download or the like. This software may be recorded on a recording medium such as a CD-ROM and distributed. This also applies to other embodiments in this specification. The software for realizing the information system A in this embodiment is a program as follows. That is, this program is a program for causing a computer that can access a task management unit in which two or more pieces of task information, which are information that specify a manufacturing task and correspond to one or more task attribute values, are stored, to function as a schedule unit that performs a schedule process that is a process of acquiring schedule information that specifies a manufacturing schedule for the two or more pieces of task information based on the one or more task attribute values of each of the two or more pieces of task information, a schedule output unit that outputs the schedule information, and a reschedule determination unit that determines whether or not a reschedule condition is met, and the schedule unit performs the schedule process again when the reschedule determination unit determines that the reschedule condition is met, and the schedule output unit outputs schedule information that is a result of the reschedule process. This is a program for causing the computer to function as follows.
[0257] Fig. 15 shows the appearance of a computer that executes the programs described in this specification to realize the manufacturing planning device 1 and the like of the various embodiments described above. The above-mentioned embodiments can be realized by computer hardware and a computer program executed thereon. Fig. 15 is an overview of this computer system 300, and Fig. 16 is a block diagram of the system 300.
[0258] In FIG. 15, a computer system 300 includes a computer 301 including a CD-ROM drive, a keyboard 302, a mouse 303, and a monitor 304.
[0259] 16, computer 301 includes, in addition to CD-ROM drive 3012, MPU 3013, bus 3014 connected to CD-ROM drive 3012 etc., ROM 3015 for storing programs such as a boot-up program, RAM 3016 connected to MPU 3013 for temporarily storing instructions of application programs and providing temporary storage space, and hard disk 3017 for storing application programs, system programs, and data. Although not shown here, computer 301 may further include a network card for providing connection to a LAN.
[0260] A program for causing computer system 300 to execute functions of the manufacturing planning apparatus 1 and the like of the above-described embodiment may be stored on CD-ROM 3101, inserted into CD-ROM drive 3012, and further transferred to hard disk 3017. Alternatively, the program may be transmitted to computer 301 via a network (not shown) and stored on hard disk 3017. The program is loaded into RAM 3016 when executed. The program may be loaded directly from CD-ROM 3101 or the network.
[0261] The program does not necessarily include an operating system (OS) or a third party program that causes the computer 301 to execute the functions of the manufacturing planning device 1 of the above-mentioned embodiment. The program may include only an instruction portion that calls appropriate functions (modules) in a controlled manner to obtain a desired result. How the computer system 300 operates is well known, and a detailed description thereof will be omitted.
[0262] In addition, in the above program, the steps of transmitting information and receiving information do not include processing performed by hardware, such as processing performed by a modem or interface card in the transmitting step (processing that is performed only by hardware).
[0263] The program may be executed by a single computer or a plurality of computers, that is, centralized processing or distributed processing may be performed.
[0264] Furthermore, in each of the above embodiments, it goes without saying that two or more communication means present in one device may be physically realized by one medium.
[0265] In each of the above embodiments, each process may be realized by centralized processing in a single device, or may be realized by distributed processing in a plurality of devices.
[0266] The present invention is not limited to the above-described embodiment, and various modifications are possible, and it goes without saying that these modifications are also included within the scope of the present invention. [Industrial Applicability]
[0267] As described above, the manufacturing planning device 1 according to the present invention has an effect of being able to appropriately reschedule manufacturing tasks, and is useful, for example, as a server that schedules manufacturing tasks. [Explanation of symbols]
[0268] A. Information Systems 1 Manufacturing planning device 2 Terminal Equipment 11 Storage area 12 Reception 13 Processing section 14 Output section 21 Terminal storage section 22 Terminal Reception 23 Terminal Processing Section 24 Terminal transmitter 25 Terminal receiving section 26 Terminal Output Section 111 Task Management Department 112 Schedule Management Department 113 Rescheduling Conditions Management Department 114 Fixed condition management department 115 Special Conditions Management Department 121 Input reception section 131 Schedule Department 132 Special Judgment Department 133 Rescheduling Judgment Department 134 Reservation Department 135 Task Generation Unit 141 Schedule output section
Claims
1. A computer that can access a task management unit that stores two or more pieces of task information, the task information being information for identifying a manufacturing task and corresponding to one or more task attribute values. a scheduler that performs a schedule process to acquire schedule information that identifies a schedule for manufacturing the two or more pieces of task information based on the one or more task attribute values of each of the two or more pieces of task information; a schedule output unit that outputs the schedule information; A program for causing a rescheduling determination unit to function as a rescheduling determination unit that determines whether a rescheduling condition is met, The schedule unit includes: When the rescheduling determination unit determines that the rescheduling condition is met, the schedule process is performed again; The schedule output unit includes: A program for causing the computer to function as an output device for outputting schedule information that is a result of the re-scheduling process.
2. 2. The program according to claim 1, wherein the rescheduling condition is that a certain period of time or more than a certain period of time has elapsed since the start of production, or that predetermined information has been received.
3. The schedule unit includes:
3. The program according to claim 1 or 2, which causes the computer to function as follows: when the rescheduling determination unit determines that the rescheduling conditions are met, fixes the schedule of one or more pieces of task information that meet the fixed conditions, and obtains schedule information that specifies a manufacturing schedule for one or more pieces of task information that do not meet the fixed conditions.
4. 4. The program according to claim 3, wherein the fixed condition is a static fixed condition that does not change dynamically.
5. 4. The program according to claim 3, wherein the fixed condition is a dynamically changing fixed condition.
6. an input receiving unit that receives input information from a user; a special determination unit that determines whether the input information matches a special condition for determining whether to release the fixation of a task, The schedule unit includes:
4. The program of claim 3, for causing the computer to function as if the schedule processing is to be performed again, including one or more task information that meets the fixed condition, when the special judgment unit judges that the special condition is met.
7. The computer, an input receiving unit that receives a hold instruction corresponding to the task information; The program according to claim 1 , further functioning as a suspension unit that performs suspension processing for suspending a task specified by the task information corresponding to the suspension instruction.
8. The computer, an input receiving unit that receives an instruction to insert task information into schedule information in which two or more pieces of task information are arranged; The program of claim 1, further functioning as a task generation unit that obtains one or more task attribute values of task information at a position before the position specified by the insertion instruction, obtains task information corresponding to the one or more task attribute values, and inserts the task information into the schedule information.
9. a task management unit in which two or more pieces of task information are stored, the task information being information for identifying a manufacturing task and corresponding to one or more task attribute values; a scheduler that performs a schedule process to acquire schedule information that identifies a schedule for manufacturing the two or more pieces of task information based on the one or more task attribute values of each of the two or more pieces of task information; a schedule output unit that outputs the schedule information; a rescheduling determination unit that determines whether or not a rescheduling condition is met; The schedule unit includes: When the rescheduling determination unit determines that the rescheduling condition is met, the schedule process is performed again; The schedule output unit includes: A manufacturing planning device that outputs schedule information that is a result of the re-scheduling process.
10. A manufacturing planning method implemented by a task management unit storing two or more pieces of task information, the task information being information for identifying a manufacturing task and corresponding to one or more task attribute values, a schedule unit, a schedule output unit, and a reschedule determination unit, a schedule step in which the schedule unit performs a schedule process that acquires schedule information that specifies a schedule for manufacturing the two or more pieces of task information based on the one or more task attribute values of each of the two or more pieces of task information; a schedule output step in which the schedule output unit outputs the schedule information; a rescheduling determination step in which the rescheduling determination unit determines whether or not a rescheduling condition is met; a step of the scheduler performing the schedule process again when the rescheduling determination unit determines that the rescheduling condition is met; and a step in which the schedule output unit outputs schedule information that is a result of the re-scheduling process.
Citation Information
Patent Citations
Annual plan drafter for vehicle components
JP2020140307A
Production plan display method, production plan display system, and production plan display program
JP2021111092A