Evaluation supporting device, evaluation supporting method, and evaluation supporting program

The evaluation support device addresses the challenge of multi-functional green infrastructure evaluation by generating environment maps with scored indicators for biodiversity, usage environment, and wind environment, enabling comprehensive assessment.

JP2024148442APending Publication Date: 2024-10-18OHBAYASHI GUMI LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2023061566
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-05
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

Green infrastructure lacks a unified evaluation method due to its multiple functions, making it difficult for users to compare and evaluate its various impacts effectively.

Method used

An evaluation support device that includes a control unit to generate an environment map with environmental elements, calculating scores for biodiversity, usage environment, and wind environment based on their arrangement, and outputting a user screen with listed scores.

Benefits of technology

The device efficiently evaluates green infrastructure by providing comprehensive scores for biodiversity, usage environment, and wind environment, allowing users to compare and understand its impacts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024148442000001_ABST
    Figure 2024148442000001_ABST
Patent Text Reader

Abstract

To provide an evaluation supporting device, an evaluation supporting method, and an evaluation supporting program to efficiently evaluate a green infrastructure.SOLUTION: An evaluation supporting device A1 comprises a control unit 21 to support the assessment of an environmental impact. The control unit 21 acquires an environment map in which multiple environment components are placed in a user screen. The control unit 21 calculates the multiple scores of an evaluation index for the environment map based on the arrangement relation of environment components in the environment map and outputs a user screen showing the scores aligned.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to an evaluation support device, an evaluation support method, and an evaluation support program for evaluating green infrastructure. [Background technology]

[0002] Techniques for evaluating the environment have been studied (see Patent Documents 1 to 4 and Non-Patent Document 1). For example, the technique described in Patent Document 1 quantitatively predicts the effect of improving the diversity of inhabiting species. In addition, the technique described in Patent Document 2 calculates a predicted movement route and movement difficulty from the surrounding green space to the planned site. Furthermore, the occurrence rate is evaluated by generating an occurrence map according to the design layout. Then, an evaluation is made including the predicted movement route and movement difficulty, and the occurrence rate map in the design layout. In addition, the technique described in Patent Document 3 and Non-Patent Document 1 applies fluid calculation to three-dimensional data for fluid calculation and wind data, thereby calculating a wind environment prediction for a simulation area and presenting the calculation results of the wind environment prediction.

[0003] Furthermore, in the technology described in Patent Document 4, a simulation program for improving game playability such as city-building elements is considered. In the technology described in this document, a game object is placed in a predetermined area on a virtual plane by a user operation. The state of the predetermined area in which the game object is placed is determined by increasing or decreasing game points associated with the game object. Then, the degree of increase or decrease in game points is controlled according to the result of the determination.

[0004] In addition, green infrastructure is attracting attention as an initiative to realize a more sustainable society in response to social issues. Green infrastructure utilizes the diverse functions of the natural environment in both hard and soft aspects such as social capital development and land use. As a result, it promotes the creation of sustainable and attractive nations and regions. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2009-136265 A [Patent Document 2] JP 2015-228817 A [Patent Document 3] JP 2003-203194 A [Patent Document 4] JP 2017-035280 A [Non-patent literature]

[0006] [Non-Patent Document 1] Tomoko Kinashi et al., “Prediction and Evaluation Technology for Urban Wind Environments”, December 2005, Obayashi Corporation Technical Research Institute Report, No. 69, pp. 1-8, [Retrieved April 1, 2023], Internet<URL:https: / / www.obayashi.co.jp / technology / shoho / 069 / 2005_069_11.pdf> Summary of the Invention [Problem to be solved by the invention]

[0007] Unlike conventional infrastructure, green infrastructure does not have a single function. In other words, because it has multiple functions, it is difficult to evaluate it in a uniform manner. Furthermore, it is difficult for users to evaluate functions unless they can compare multiple functions, rather than evaluating them in a centralized manner as good or bad. For example, there are many different types of users, including those who place importance on biodiversity and those who only value the wind environment. There was no tool available to carry out evaluations that reflected such intentions and wishes. [Means for solving the problem]

[0008] The evaluation support device for solving the above problem includes a control unit that supports the evaluation of an impact on an environment, and the control unit acquires an environment map in which a plurality of environmental elements are arranged on a user screen, calculates scores of a plurality of evaluation indexes for the environment map based on the arrangement relationship of the environmental elements on the environment map, and outputs a user screen in which the scores are arranged. Effect of the Invention

[0009] The present invention makes it possible to efficiently evaluate green infrastructure. [Brief description of the drawings]

[0010] [Figure 1] FIG. 1 is an explanatory diagram of a system according to an embodiment. [Diagram 2] FIG. 2 is an explanatory diagram of a hardware configuration of the embodiment. [Diagram 3] FIG. 13 is an explanatory diagram of a wind speed scoring table according to the embodiment. [Figure 4] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Diagram 5] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 6] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 7] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 8] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 9] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 10] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 11] FIG. 2 is an explanatory diagram of a processing procedure according to an embodiment. [Figure 12] FIG. 4 is an explanatory diagram of a screen according to an embodiment. [Figure 13] 5A and 5B are explanatory diagrams of a processing procedure according to the embodiment, in which FIG. 5A is an analysis grid, and FIG. 5B is an explanatory diagram of an environment map of an evaluation height. [Figure 14] FIG. 4 is an explanatory diagram of a screen according to an embodiment. [Figure 15]FIG. 4 is an explanatory diagram of a screen according to an embodiment. [Figure 16] FIG. 4 is an explanatory diagram of a screen according to an embodiment. [Figure 17] FIG. 13 is an explanatory diagram of another example of a wind speed scoring table. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] An embodiment in which an evaluation support device, an evaluation support method, and an evaluation support program are embodied will be described below with reference to Figs. 1 to 16. In this embodiment, a user performs a screen operation (game) to place environmental elements (element objects) in an outdoor public space. This will be described as an evaluation support device, an evaluation support method, and an evaluation support program used to support the evaluation of the impact on the natural environment, social environment, etc. (green infrastructure). Here, biodiversity, utilization environment, and wind environment are evaluated as indicators of green infrastructure. As shown in FIG. 1, an evaluation support device A1 of this embodiment uses a user terminal 10 and a support server 20 that are connected to each other via a network.

[0012] (Hardware configuration description) 2, a hardware configuration of the information processing device H10 constituting the user terminal 10 and the support server 20 will be described. The information processing device H10 includes a communication device H11, an input device H12, a display device H13, a storage device H14, and a processor H15. Note that this hardware configuration is an example, and it can also be realized by other hardware.

[0013] The communication device H11 is an interface that establishes a communication path with other devices and transmits and receives data, and is, for example, a network interface or a wireless interface.

[0014] The input device H12 is a device that accepts input of various information, such as a mouse, a keyboard, etc. The display device H13 is a display or the like that displays various information. The storage device H14 is a storage device that stores data and various programs for executing various functions of the user terminal 10 and the support server 20. Examples of the storage device H14 include a ROM, a RAM, and a hard disk.

[0015] The processor H15 uses the programs and data stored in the storage device H14 to control each process in the user terminal 10 and the support server 20. Examples of the processor H15 include a CPU and an MPU. The processor H15 expands the programs stored in the ROM, etc., into the RAM and executes various processes for each process.

[0016] The processor H15 is not limited to a processor that performs software processing for all the processes it executes. For example, the processor H15 may include a dedicated hardware circuit (e.g., an application specific integrated circuit (ASIC)) that performs hardware processing for at least a part of the processes it executes. That is, the processor H15 may be configured as follows:

[0017] [1] One or more processors that operate according to a computer program (software). [2] One or more dedicated hardware circuits that perform at least some of the various processes [3] Circuits that include combinations of these The processor includes a CPU and memory, such as RAM and ROM, that stores program codes or instructions configured to cause the CPU to execute processes. Memory, i.e., computer-readable media, includes any available media that can be accessed by a general-purpose or special-purpose computer.

[0018] (Specific configuration) The user terminal 10 is a computer terminal used by a user. The support server 20 is a computer system that evaluates indicators of green infrastructure. The support server 20 includes a control unit 21, a layout information storage unit 22, a pattern information storage unit 23, a score information storage unit 24, and an evaluation result storage unit 25.

[0019] The control unit 21 performs processes (including a management stage, a first evaluation stage, a second evaluation stage, a third evaluation stage, etc.) to be described later. By executing a processing program for this purpose, the control unit 21 functions as a management unit 210, a first evaluation unit 211, a second evaluation unit 212, a third evaluation unit 213, etc.

[0020] The management unit 210 manages the first evaluation unit 211 to the third evaluation unit 213. Furthermore, the management unit 210 provides a game screen to the user. The first evaluation unit 211 evaluates biodiversity as an index.

[0021] The second evaluation unit 212 evaluates the usage environment (usability) as an index. Here, the second evaluation unit 212 evaluates the walkability, the versatility of usage, the shade condition, and the relaxation. The third evaluation unit 213 evaluates the wind environment as an index. Using a three-dimensional model, a process is executed to analytically calculate the wind speed distribution (wind direction and wind speed). Here, an analysis is performed using computational fluid dynamics (CFD). Specifically, the wind environment simulator "Zephyrus (registered trademark)" is used.

[0022] The layout information storage unit 22 records a map used in the simulation. This map includes a public space model in which element objects are arranged, and a building model showing the building shape. This model is created using, for example, BIM (Building Information Modeling) technology. In this model, not only the public space model in which optional elements are arranged, but also a city block model including surrounding structures is set around the public space model. For example, a city block model of 1 to 2 km square is used for a public space model of several tens of meters square. By using such a wide city block model centered on the public space model to perform a numerical simulation for wind environment evaluation, the wind situation affected by surrounding buildings, etc. can be predicted. As a result, the wind (wind speed, wind direction) in the public space can be calculated in a more realistic manner.

[0023] The public space model is also divided into multiple sections. 12, the map 500 includes a plurality of sections A to E. The sections A to E are configured by a mesh made up of a plurality of cells. An optional element (element object), which will be described later, is placed in each cell.

[0024] A plurality of patterns in which optional elements are arranged in each section are recorded in the pattern information storage unit 23. The optional elements include tall trees, low trees, grassland (lawn), water areas (ponds, waterside), paved surfaces, and the like.

[0025] As shown in FIG. 12, pattern sets 501 to 505 are prepared for sections A to E, respectively. Each of the pattern sets 501 to 505 has three selectable patterns. In each pattern, optional elements are arranged in different positions. Here, the patterns are classified into "mainly arranged in forest", "mainly arranged in grass", "mainly arranged in pond", and "mainly arranged in square" according to the optional elements arranged.

[0026] The point information storage unit 24 stores point information for evaluating the environment. The biodiversity scores evaluated by the first evaluation unit 211 are set, for example, as follows: tall trees: 100 points, shrubs: 80 points, grasslands: 30 points, water areas: 60 points, paved surfaces: -30 points, and buildings: -10 points. It is also possible to calculate the scores described in Patent Document 2 and normalize them for use.

[0027] The score of the usage environment evaluated by the second evaluation unit 212 is set for walkability, versatility of use, shade conditions, and relaxation. Regarding walkability, the ease of walking is rated on a three-point scale: "1 point," "0.5 point," or "0 point."

[0028] The diversity of use is evaluated using the number of classifications of patterns used in the environmental map, such as "mainly forests," "mainly grass," "mainly ponds," and "mainly open spaces."

[0029] Regarding shade conditions, in order to evaluate the degree of shade, the degree of shade is rated on a three-point scale: "1 point," "0.5 point," or "0 point."

[0030] The wind environment evaluated by the third evaluation unit 213 is evaluated using a wind speed ratio calculated by a simulation. Here, a wind speed ratio at a predetermined evaluation height is used. The evaluation height is, for example, "1.5 m above ground." Then, the wind environment score table T1 shown in Fig. 3 is used. In this wind environment score table T1, a score is assigned to the wind speed ratio.

[0031] Furthermore, the third evaluation unit 213 calculates the average wind speed, the instantaneous wind speed, and the wind direction from the wind speed ratio calculated by the simulation and the meteorological data.

[0032] As weather data, for example, data from the Tokyo Regional Meteorological Observatory is used. Specifically, it is statistical values ​​of 10-minute average wind speed, most common wind direction, and temperature observed in August over the past 10 years. Here, the 10-minute average wind speed = 3 m / s, most common wind direction = south, and temperature with a cumulative frequency of 50% = 29 degrees are used. The weather data and the evaluation level can be determined for each case.

[0033] Moreover, the third evaluation unit 213 calculates the sensible temperature at the evaluation point using the following Linke's calculation formula. [Feeling temperature] = [air temperature] - 4 x [average wind speed] 0.5

[0034] The evaluation result storage unit 25 records the evaluation results of biodiversity, utilization environment, and wind environment for each environmental map generated by combining patterns. Here, the scores of biodiversity, utilization environment, and wind environment are recorded as evaluation results in association with a map identifier for identifying each environmental map. For biodiversity, a heat map is recorded in which the scores are color-coded for each cell. For wind environment, a heat map image is recorded in which the cells are color-coded. Furthermore, a radar chart is recorded with the scores of biodiversity, utilization environment, and wind environment on each axis. Also, a slogan according to the score balance of the radar chart is recorded.

[0035] (Preparation process) Next, the preparation process will be described with reference to FIGS.

[0036] (Overview of preparation process) An overview of the preparation process will be given with reference to Figure 4. This preparation process is carried out before the game is provided.

[0037] First, the control unit 21 of the support server 20 executes a process for generating combinations of options (step S11). Specifically, the management unit 210 of the control unit 21 generates environmental maps to be options by combining the patterns included in the pattern sets 501 to 505 recorded in the pattern information storage unit 23. In this embodiment, three types of patterns are used for each of the sections A to E, so that 243 environmental maps are generated.

[0038] Next, the control unit 21 of the support server 20 executes a biodiversity evaluation process (step S12). Specifically, the first evaluation unit 211 of the control unit 21 evaluates the biodiversity of the environment map generated by combining the patterns. The evaluation method will be described later with reference to FIG. 5.

[0039] Furthermore, the control unit 21 of the support server 20 executes a usage environment evaluation process (step S13). Specifically, the second evaluation unit 212 of the control unit 21 evaluates the usage environment for the environmental map generated by combining patterns. The usage environment is evaluated in terms of walkability, versatility of use, shade conditions, and relaxation. The evaluation method will be described later with reference to Figs. 6 to 9.

[0040] Furthermore, the control unit 21 of the support server 20 executes a wind environment evaluation process (step S14). Specifically, the second evaluation unit 212 of the control unit 21 evaluates the wind environment for the environmental map generated by combining the patterns. The evaluation method will be described later with reference to FIG. 10.

[0041] Then, the control unit 21 of the support server 20 executes a comprehensive evaluation process (step S15). Specifically, the management unit 215 of the control unit 21 generates a radar chart with the scores of biodiversity, utilization environment, and wind environment as the respective axes, and records the generated chart in the evaluation result storage unit 25. Next, the management unit 215 generates a slogan according to the score balance of the radar chart, and records the generated slogan in the evaluation result storage unit 25. For example, if the score of any one of biodiversity, utilization environment, and wind environment is significantly higher than the other indices by a standard ratio or more, a slogan that emphasizes this index is set.

[0042] (Biodiversity assessment processing) The biodiversity evaluation process (step S12) will be described with reference to FIG. First, the control unit 21 of the support server 20 repeats the following process for each environmental map.

[0043] Here, the control unit 21 of the support server 20 executes a score allocation process for each cell (step S21). Specifically, the first evaluation unit 211 of the control unit 21 allocates the scores of each environmental element recorded in the score allocation information storage unit 24 to the cells in which each optional element included in the environmental map to be evaluated is allocated.

[0044] Next, the control unit 21 of the support server 20 executes a process of adding points to the surrounding cells (step S22). Specifically, the first evaluation unit 211 of the control unit 21 adds the scores of the environmental elements to the surrounding cells for each cell. The weighting when adding points is set according to the distance between the cells.

[0045] For example, a weighting table T2 is used, in which the added points are set inversely proportional to the distance so that the added points become smaller as the distance from the evaluation target cell increases. Through this process, the first evaluation unit 211 generates a heat map in which the scores of each cell of the environment map are arranged, and records this in the evaluation result storage unit 25.

[0046] Next, the control unit 21 of the support server 20 executes a scoring process according to the arrangement (step S23). Specifically, the first evaluation unit 211 of the control unit 21 calculates a biodiversity score by summing up the scores of all cells in the environmental map. Then, the first evaluation unit 211 records the calculated score in association with the map identifier.

[0047] The control unit 21 of the support server 20 repeats the above process for all environmental maps. Then, the control unit 21 of the support server 20 executes a normalization process (step S24). Specifically, the first evaluation unit 211 of the control unit 21 normalizes the scores associated with the map identifiers so that the scores of each environmental map fall within a predetermined score range. Here, each score is converted so that all scores fall within a predetermined score range while maintaining the magnitude relationship of each score.

[0048] (Usage environment evaluation process) Next, the utilization environment evaluation process (step S13) will be described. Here, a walkability evaluation process, a utilization diversity evaluation process, a shade condition evaluation process, and a relaxation evaluation process are performed.

[0049] (Walkability evaluation process) The walkability evaluation process will be described with reference to FIG. First, the control unit 21 of the support server 20 repeats the following process for each environmental map.

[0050] Here, the control unit 21 of the support server 20 executes a process of setting a flow line (step S31). Specifically, the second evaluation unit 212 of the control unit 21 sets a flow line from the outside of the exterior part to the center in the environmental map to be evaluated. In FIG. 12, flow lines are set from entrances 511 to 514 to the center.

[0051] Next, the control unit 21 of the support server 20 executes a process of evaluating the ease of walking (step S32). Specifically, the second evaluation unit 212 of the control unit 21 calculates a score for each optional element arranged in the environmental map to be evaluated for each flow line. For example, when optional elements of tall trees, shrubs, and water areas (ponds and watersides) are arranged, a detour is required, so the second evaluation unit 212 gives a low score. On the other hand, when optional elements of grassland (lawn) and paved surfaces are arranged, a straight line can be traveled, so the second evaluation unit 212 gives a high score. Then, the second evaluation unit 212 sums up the scores for each flow line. Then, the second evaluation unit 212 records the calculated score in association with the map identifier. The control unit 21 of the support server 20 repeats the above process for all environmental maps.

[0052] Then, the control unit 21 of the support server 20 executes a normalization process (step S33). Specifically, the second evaluation unit 212 of the control unit 21 normalizes the score associated with the map identifier so that the score of each environmental map falls within a predetermined score range.

[0053] (Utilization diversity evaluation process) The utilization diversity evaluation process will be described with reference to FIG. First, the control unit 21 of the support server 20 repeats the following process for each environmental map.

[0054] Here, the control unit 21 of the support server 20 executes a classification diversity evaluation process (step S41). Specifically, the second evaluation unit 212 of the control unit 21 identifies the classification of each pattern for each section in the environmental map to be evaluated ("mainly forests," "mainly grass," "mainly ponds," "mainly squares"). Then, the second evaluation unit 212 calculates the types of classifications (number of classifications) used in the entire environmental map. For example, if the same classification pattern is used in multiple sections, the number of classifications is "1." Furthermore, since squares are an element that promotes diverse uses, the second evaluation unit 212 gives additional points if the map includes a pattern classified as "mainly squares."

[0055] Next, the control unit 21 of the support server 20 executes a diversity demerit evaluation process (step S42). Specifically, the second evaluation unit 212 of the control unit 21 performs a demerit evaluation process when patterns of the same classification are arranged in three or more sections. Then, the second evaluation unit 212 records the calculated score in association with the map identifier. The control unit 21 of the support server 20 repeats the above process for all environmental maps.

[0056] Then, the control unit 21 of the support server 20 executes a normalization process (step S43). Specifically, the second evaluation unit 212 of the control unit 21 normalizes the score associated with the map identifier so that the score of each environmental map falls within a predetermined score range.

[0057] (Shade condition evaluation processing) The shade evaluation process will be described with reference to FIG. First, the control unit 21 of the support server 20 repeats the following process for each environmental map.

[0058] Here, the control unit 21 of the support server 20 executes a shade evaluation process according to the arrangement of the environmental elements (step S51). Specifically, the second evaluation unit 212 of the control unit 21 performs scoring according to the arrangement of the optional elements in the pattern that constitutes the environmental map to be evaluated. Here, when tall trees are arranged within a predetermined range of grassland (lawn) or paved surface, a high score is given because shade is generated. The control unit 21 of the support server 20 repeats the above process for all environmental maps.

[0059] Then, the control unit 21 of the support server 20 executes a normalization process (step S52). Specifically, the second evaluation unit 212 of the control unit 21 normalizes the score associated with the map identifier so that the score of each environmental map falls within a predetermined score range.

[0060] (Relaxation evaluation process) The relaxation evaluation process will be described with reference to FIG. First, the control unit 21 of the support server 20 repeats the following process for each environmental map.

[0061] Here, the control unit 21 of the support server 20 executes a scoring process according to the classification (step S61). Specifically, the second evaluation unit 212 of the control unit 21 specifies the classification of each pattern for each section in the environmental map to be evaluated ("mainly grass", "mainly pond", "mainly open space"), and then the second evaluation unit 212 calculates a score according to the number of types of classification used in the entire environmental map.

[0062] Next, the control unit 21 of the support server 20 executes a diversity demerit evaluation process (step S62). Specifically, the second evaluation unit 212 of the control unit 21 performs a demerit evaluation process when patterns of the same classification are arranged in three or more sections. Then, the second evaluation unit 212 records the calculated score in association with the map identifier. The control unit 21 of the support server 20 repeats the above process for all environmental maps.

[0063] Next, the control unit 21 of the support server 20 executes a normalization process (step S63). Specifically, the second evaluation unit 212 of the control unit 21 performs normalization so that the score of each combination falls within a predetermined score range.

[0064] (Wind environment evaluation processing) The wind environment evaluation process (step S14) will be described with reference to FIG. Here, as shown in Fig. 13(a), an analytical grid 600 is used. In the analytical grid 600, a public space model in which optional elements are arranged is set for a city block model.

[0065] First, the control unit 21 of the assistance server 20 executes an initial simulation process (step S71). Specifically, the third evaluation unit 213 of the control unit 21 acquires an environment map of an initial state.

[0066] 13(b) shows a two-dimensional initial state environment map 601 at an evaluation height (1.5 m in this case). Optional elements (tall trees, low trees, grassland, water area, etc.) that the user places are not placed on this environment map 601. Then, the third evaluation unit 213 performs a wind condition simulation (numerical simulation) on the three-dimensional environment map.

[0067] Next, the control unit 21 of the support server 20 executes a calculation process of the wind speed ratio, etc. (Step S72). Specifically, the third evaluation unit 213 of the control unit 21 calculates the wind speed ratio Wr(0) at a predetermined height (here, 1.5 m), vectors, etc. for each analysis grid by the initial simulation process. This wind speed ratio Wr(0) is used as one of the grounds for determining the score of the wind environment allocation table T1.

[0068] Next, the control unit 21 of the support server 20 repeats the following process for each environmental map. In this case, an environmental map in which a combination of optional elements is set is used. Here, the control unit 21 of the support server 20 executes a simulation process in which the optional elements are arranged (step S73). Specifically, the third evaluation unit 213 of the control unit 21 performs a wind condition simulation in the three-dimensional environmental map of the evaluation target in which the optional elements are arranged.

[0069] Next, the control unit 21 of the support server 20 executes a calculation process of the wind speed ratio, etc. (Step S74). Specifically, the third evaluation unit 213 of the control unit 21 calculates the wind speed ratio Wr(i) at a predetermined height (here, 1.5 m), vectors, etc. for each analysis grid by a simulation process of the environmental map to be evaluated.

[0070] Next, the control unit 21 of the support server 20 executes a calculation process of the average wind speed and the instantaneous wind speed (step S75). Specifically, the third evaluation unit 213 of the control unit 21 calculates the average wind speed Wa(i) from the wind speed ratio Wr(i) and meteorological data. Furthermore, the third evaluation unit 213 calculates the instantaneous wind speed Wm(i) from the average wind speed Wa(i) and the gust rate. This gust rate is calculated from a numerical simulation using a function for the wind speed ratio Wr(i) using, for example, the technology described in Non-Patent Document 1.

[0071] Next, the control unit 21 of the support server 20 executes a process of calculating the sensible temperature (step S76). Specifically, the third evaluation unit 213 of the control unit 21 calculates the sensible temperature Ts(i) by substituting the average wind speed into the Linke formula for each analysis grid.

[0072] Next, the control unit 21 of the support server 20 executes the wind environment evaluation and scoring process (step S77). Specifically, the third evaluation unit 213 of the control unit 21 calculates the score of each analysis grid from the wind speed ratio Wr(i) by using the wind environment score table T1 recorded in the score information storage unit 24.

[0073] Furthermore, the score is adjusted for each analysis grid under the following conditions. - Points will be deducted if "wind speed ratio Wr(i) ≧ 0.6" and "wind speed ratio Wr(i) ≧ wind speed ratio Wr(0)" If "wind speed ratio Wr(i)<0.6" and "wind speed ratio Wr(i)<wind speed ratio Wr(0)", add points. -Add points if "wind speed ratio Wr(i)<0.5" and "wind speed ratio Wr(0)<0.5" - Points will be deducted if the instantaneous wind speed Wm(i)>5m / s - If "Feeling temperature Ts(i)>26 degrees" then points will be deducted Next, the third evaluation unit 213 sums up the scores of all the analysis grids.

[0074] Then, the third evaluation unit 213 generates a heat map in which the wind speeds of the analysis grids of the environment map are arranged, and records the heat map in the evaluation result storage unit 25. The control unit 21 of the support server 20 repeats the above process for all environmental maps.

[0075] Then, the control unit 21 of the support server 20 executes a normalization process (step S78). Specifically, the third evaluation unit 213 of the control unit 21 performs normalization so that the score of each combination falls within a predetermined score range.

[0076] (Green Infrastructure Evaluation Processing) A green infrastructure evaluation process for evaluating the impact on the natural environment and the social environment will be described with reference to Fig. 11. In this embodiment, as an example, a game is used to learn the evaluation results of the impact on the natural environment and the social environment.

[0077] Here, first, the control unit 21 of the support server 20 executes an environment setting process for each section (step S81). Specifically, the management unit 210 of the control unit 21 outputs a game screen (user screen) to the display device H13 of the user terminal 10. In this game screen, a pattern for each section is set.

[0078] As shown in Fig. 14, a game screen 700 is output to the user terminal 10. In this game screen 700, the pattern of section A can be set. Then, by selecting one of three patterns, setting of the pattern of section A is completed. Then, in the same manner, the patterns of sections B to E are set in sequence to complete the environment map.

[0079] 15, a game screen 710 is output to the user terminal 10. This game screen 710 includes buttons for selecting a pattern reset or analysis. When the analysis button is selected and the settings of all sections are completed, the control unit 21 of the support server 20 executes an evaluation result acquisition process (step S82). Specifically, the management unit 210 of the control unit 21 acquires the evaluation result from the evaluation result storage unit 25 by using the map identifier of the completed environment map.

[0080] Next, the control unit 21 of the support server 20 executes an output process (step S83). Specifically, the management unit 210 of the control unit 21 outputs an evaluation result screen to the display device H13 of the user terminal 10.

[0081] As shown in FIG. 16, the assessment result screen 720 includes an environment map 721 , a biodiversity assessment result 722 , a utilization diversity assessment result 723 , a wind environment assessment result 724 , a radar chart 725 , and a slogan 726 .

[0082] Next, the control unit 21 of the support server 20 executes a determination process as to whether or not to end the process (step S84). Specifically, the management unit 210 of the control unit 21 makes the determination based on the selection of a button displayed on the evaluation result screen 720.

[0083] When the end button is selected and it is determined that the process is to end (YES in step S84), the green infrastructure evaluation process ends. On the other hand, if the button to rearrange the layout is selected ("NO" in step S84), the management unit 210 outputs a game screen 710 shown in Fig. 15. Using this game screen 710, the pattern of each section can be reselected. Then, the pattern of the selected section can be changed.

[0084] According to this embodiment, the following effects can be obtained. (1) In this embodiment, the control unit 21 of the support server 20 executes a process for generating combinations of options (step S11). This makes it possible to efficiently generate an environmental map in which a variety of patterns are set.

[0085] (2) In this embodiment, the control unit 21 of the support server 20 executes a biodiversity evaluation process (step S12), which makes it possible to evaluate the impact on living things in a public space in an environmental map set by the user.

[0086] (3) In this embodiment, the control unit 21 of the assistance server 20 executes a process of adding points to the surrounding cells (step S22), thereby making it possible to evaluate each area while taking into account the influence of the surrounding environment.

[0087] (4) In this embodiment, the control unit 21 of the support server 20 executes a usage environment evaluation process (step S13). This makes it possible to evaluate the impact on various uses of a public space in an environmental map set by the user.

[0088] (5) In this embodiment, the control unit 21 of the support server 20 executes a process of setting a flow line (step S31) and a process of evaluating walkability (step S32), thereby making it possible to evaluate the ease of movement in a public space.

[0089] (6) In this embodiment, the control unit 21 of the support server 20 executes a classification diversity evaluation process (step S41) and a diversity point reduction evaluation process (step S42). This makes it possible to evaluate the possibility of responding to various needs.

[0090] (7) In this embodiment, the control unit 21 of the support server 20 executes a shade evaluation process according to the arrangement of environmental elements (step S51), thereby making it possible to evaluate the comfort of public spaces in midsummer.

[0091] (8) In this embodiment, the control unit 21 of the support server 20 executes a scoring process according to the classification (step S61) and a diversity demerit evaluation process (step S62). This makes it possible to evaluate the psychological impact of the public space on users.

[0092] (9) In this embodiment, the control unit 21 of the support server 20 executes a wind environment evaluation process (step S14). This makes it possible to evaluate the effect of wind in a public space on an environmental map set by the user.

[0093] (10) In this embodiment, the control unit 21 of the support server 20 executes an initial simulation process (step S71) and a calculation process for the wind speed ratio, etc. (step S72). This makes it possible to calculate the wind direction and wind speed using meteorological data.

[0094] (11) In this embodiment, the control unit 21 of the support server 20 executes a calculation process of the average wind speed and the instantaneous wind speed (step S75). If the wind is strong, it is a psychological burden for the users. This allows the comfort of the public space to be evaluated taking into account the influence of the wind.

[0095] (12) In this embodiment, the control unit 21 of the support server 20 executes a process of calculating the sensible temperature (step S76). In midsummer, when there is little wind, comfort decreases. This allows the comfort of a public space to be evaluated using the sensible temperature.

[0096] (13) In this embodiment, the control unit 21 of the support server 20 executes normalization processing (steps S24, S33, S43, S52, S63, and S78). This makes it possible to evaluate multiple indexes within the same score range.

[0097] (14) In this embodiment, the control unit 21 of the support server 20 executes a preparation process. As a result, once the environment map is determined, the evaluation result can be output promptly. (15) In this embodiment, the control unit 21 of the support server 20 executes a green infrastructure evaluation process. This allows the user to learn about the impact of the layout of public spaces on the natural and social environments through the game.

[0098] This embodiment can be modified as follows: This embodiment and the following modifications can be combined with each other to the extent that there is no technical contradiction. In the above embodiment, the green infrastructure evaluation process is performed using a game. However, as long as the green infrastructure can be evaluated, the process is not limited to a game format.

[0099] In the above embodiment, biodiversity, utilization environment, and wind environment are used as indicators for evaluation. The evaluation indicators for green infrastructure are not limited to these. For example, there may be more than one indicator, such as two or more of biodiversity, utilization environment, and wind environment.

[0100] In the above embodiment, the control unit 21 of the support server 20 executes the preparation process. Alternatively, the calculation may be performed sequentially in the green infrastructure evaluation process. In this case, instead of selecting from a predetermined pattern, the user may be allowed to set optional elements in any location.

[0101] In the above embodiment, the control unit 21 of the support server 20 executes the evaluation process for each of biodiversity, utilization environment, and wind environment. In addition, the evaluation result of one index may be reflected in the other indexes. For example, the evaluation result of biodiversity may be used to adjust the score of utilization diversity. Also, the evaluation result of wind environment may be used to adjust the score of biodiversity.

[0102] In the above embodiment, the sensible temperature is calculated by the Linke formula. The calculation method is not limited to the Linke formula, and the Misnar sensible temperature formula may be used as long as the sensible temperature can be calculated. In the above embodiment, the weather data used is the wind direction (south), average wind speed (3 m), and temperature (29 degrees) for a specific month (e.g., August) of a specific year from the Tokyo Metropolitan Weather Observatory. Alternatively, the user may be allowed to select a region or season. In this case, weather data is also obtained from a weather information site or the like based on the selected region and season.

[0103] In the above embodiment, the control unit 21 of the support server 20 executes the wind environment evaluation and scoring process (step S76). Specifically, the third evaluation unit 213 of the control unit 21 calculates a score from the wind speed ratio Wr(i) by using the wind environment scoring table T1 recorded in the scoring information storage unit 24. The method of calculating the score is not limited to this. For example, the instantaneous wind speed Wm(i) or the average wind speed Wa(i) may be used.

[0104] In this case, in the initial simulation process (step S71), the average wind speed Wa(0) is calculated for each analysis grid. Furthermore, the third evaluation unit 213 performs a wind condition simulation for each environmental map in which a combination of optional elements is set, and calculates the average wind speed Wa(i) and the instantaneous wind speed Wm(i) for each analysis grid.

[0105] Next, in the wind environment evaluation and scoring process (step S76), a wind environment scoring table in which scores are recorded for instantaneous wind speed or average wind speed is used. 17 is an example of the wind environment score table T3 in this case. In the wind environment score table T3, a score is recorded for each value obtained by sequentially changing the instantaneous wind speed or the average wind speed.

[0106] Then, using the wind environment score table T3, a score is calculated from the instantaneous wind speed or the average wind speed. Furthermore, the score is adjusted for each analysis grid under the following conditions.

[0107] - Points will be deducted if "average wind speed Wa(i) ≧ average wind speed Wa(0)" - Points will be deducted if the instantaneous wind speed Wm(i)>5m / s - If "Feeling temperature Ts(i)>26 degrees" then points will be deducted

[0108] Next, the technical ideas that can be understood from the above-described embodiment and other examples will be described below. (a) the control unit, outputting a pattern set including a plurality of patterns to the user terminal; 3. The evaluation support device according to claim 1, further comprising: a device for generating an environment map by using a pattern selected from the pattern set.

[0109] (b) The evaluation support device described in any one of (a), 2, or 3, characterized in that the control unit evaluates the environmental map by assigning scores according to indexes to optional elements included in the environmental map.

[0110] (c) The evaluation support device described in (b), characterized in that the control unit evaluates biodiversity by adding points assigned to optional elements included in the environmental map to the surrounding area. (d) The evaluation support device described in (b), characterized in that the control unit sets a traffic line on the environmental map and evaluates walkability based on a positional relationship between the traffic line and optional elements.

[0111] (e) The evaluation support device described in any one of (a), 2, and 3, characterized in that the control unit executes a wind condition simulation using optional elements included in the environmental map, and evaluates the wind environment using an average wind speed calculated by the simulation.

[0112] (f) The evaluation support device described in (e), characterized in that the control unit calculates an instantaneous wind speed in the wind condition simulation and evaluates the wind environment based on the instantaneous wind speed. (g) the control unit, Using the average wind speed, predict the perceived temperature; The evaluation support device described in (e) is characterized in that the wind environment is evaluated based on the sensible temperature. [Explanation of symbols]

[0113] A1...evaluation support device, 10...user terminal, 20...support server, 21...control unit, 210...management unit, 211...first evaluation unit, 212...second evaluation unit, 213...third evaluation unit, 22...layout information storage unit, 23...pattern information storage unit, 24...evaluation result storage unit.

Claims

1. An assessment support device having a control unit that supports assessment of environmental impact, The control unit: Obtaining an environmental map on a user screen in which a plurality of environmental elements are arranged; calculating scores of a plurality of evaluation indices for the environmental map based on the arrangement relationship of the environmental elements in the environmental map; The evaluation support device outputs a user screen on which the scores are arranged.

2. 2. The evaluation support device according to claim 1, wherein the evaluation indexes include at least two of biodiversity, utilization environment, and wind environment.

3. A method for providing assessment support using an assessment support device having a control unit that supports an assessment of an impact on the environment, comprising: The control unit: Obtaining an environmental map on a user screen in which a plurality of environmental elements are arranged; calculating scores of a plurality of evaluation indices for the environmental map based on the arrangement relationship of the environmental elements in the environmental map; An evaluation support method comprising: outputting a user screen on which the scores are arranged.

4. A program for performing evaluation support using an evaluation support device having a control unit that supports an evaluation of an impact on the environment, The control unit, Obtaining an environmental map on a user screen in which a plurality of environmental elements are arranged; calculating scores of a plurality of evaluation indices for the environmental map based on the arrangement relationship of the environmental elements in the environmental map; an evaluation support program that functions as a means for outputting a user screen on which the scores are arranged;

Citation Information

Patent Citations

  • Wind environment predicting program, medium storing this program and wind environment predicting method

    JP2003203194A

  • Natural environment introduction planning support system

    JP2003250345A

  • Predicting system for biodiversity progress effect of city greening

    JP2009136265A

  • Design support device and program

    JP2013097200A

  • Ecological environment formulation method and device therefor

    JP2013250485A