Information processing device, information processing method, and program

The information processing device optimizes suspension positions and patterns in three-phase power lines to mitigate voltage imbalance by calculating unbalance rates and using adjusted probability settings, effectively addressing irregular load and generation fluctuations.

JP2024168159AActive Publication Date: 2024-12-05FUJI ELECTRIC CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023084599
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-23
Publication Date
2024-12-05
Estimated Expiration
2043-05-23

AI Technical Summary

Technical Problem

Existing technologies fail to accurately determine the suspension position and pattern in three-phase power transmission and distribution lines to mitigate voltage imbalance caused by irregular load fluctuations and power generation fluctuations from devices like solar power generation and electric vehicle chargers.

Method used

An information processing device that calculates the voltage unbalance rate at each node of a power system, optimizing the suspension position and pattern using a combinatorial optimization method with adjusted probability settings to minimize voltage unbalance.

Benefits of technology

Accurately determines the suspension state to improve voltage unbalance, reducing calculation time and efficiently addressing voltage imbalance in power systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024168159000001_ABST
    Figure 2024168159000001_ABST
Patent Text Reader

Abstract

To provide an information processing device capable of determining with excellent accuracy a state of transposition which can improve a voltage imbalance rate of a three-phase transmission / distribution line.SOLUTION: An information processing device has, based on a plurality of combinations obtained by making a state of a three-phase transmission / distribution line in each of m nodes in a power system any of a first state of no transposition, a second state of transposition with a first pattern, and a third state of transposition with a second pattern different from the first pattern, power transmitted / received to / from the power system in each of n nodes, and system configuration information indicating a configuration of the power system, a calculation unit calculating an imbalance rate of voltage of each of the n nodes, and a determination unit optimizing an object function determined based on the imbalance rate of the voltage of each of the n nodes with the state of the three-phase transmission / distribution line in each of the m nodes being made a decision variable.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an information processing device, an information processing method, and a program. [Background technology]

[0002] In a power system transmission line or distribution line (hereinafter referred to as "power transmission / distribution line"), the voltage variation for each phase is calculated by the voltage unbalance rate (hereinafter referred to as "unbalance rate"), and it is desirable for the unbalance rate to be small. In order to eliminate the unbalance rate of the power system, twisting is sometimes performed on three-phase distribution lines.

[0003] Patent Document 1 describes a cable rack position determining device that determines the cable rack position in a three-phase power transmission and distribution line. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2015-126679 A Summary of the Invention [Problem to be solved by the invention]

[0005] In recent years, devices such as photovoltaic power generation devices and electric vehicle chargers are sometimes installed in power systems. Irregular load fluctuations or power generation fluctuations caused by these devices increase the voltage imbalance. However, the technology described in Patent Document 1 does not take into account actual load fluctuations or power generation fluctuations, and therefore it is not always possible to determine the position of the rack that can improve the voltage unbalance rate and the rack pattern (how to switch phases) at that position.

[0006] The present invention has been made in consideration of the above-mentioned conventional problems, and aims to provide an information processing device, an information processing method, and a program that can accurately determine the racking state (the racking position and the racking pattern at that position) that can improve the voltage imbalance rate of a three-phase transmission and distribution line. [Means for solving the problem]

[0007] The main present invention for solving the above-mentioned problems includes an information processing device comprising: a calculation unit that calculates a voltage unbalance rate of each of m nodes in a power system based on a plurality of combinations obtained by obtaining a state of a three-phase transmission / distribution line at each of the m nodes as one of a first state in which the three-phase transmission / distribution line is not crossed, a second state in which the three-phase transmission / distribution line is crossed in a first pattern, or a third state in which the three-phase transmission / distribution line is crossed in a second pattern different from the first pattern, power exchanged with the power system at each of the n nodes, and system configuration information indicating a configuration of the power system; and a decision unit that determines the state of the three-phase transmission / distribution line at each of the m nodes by optimizing an objective function determined based on the voltage unbalance rate of each of the n nodes using the state of the three-phase transmission / distribution line at each of the m nodes as a decision variable, and the decision unit generates an initial value of the decision variable such that the first state occurs with a probability of occurrence different from the respective probabilities of occurrence of the second state and the third state. Effect of the Invention

[0008] According to the present invention, it is possible to accurately determine the state of a cable rack capable of improving the voltage unbalance rate of a three-phase power transmission / distribution line. [Brief description of the drawings]

[0009] [Figure 1] 1 is a diagram illustrating a hardware configuration of an information processing device 10 according to a first embodiment of the present invention. [Diagram 2] 1 is a diagram illustrating an example of a power system 20 in which an information processing device 10 according to a first embodiment determines a rack state. [Diagram 3]1 is a configuration diagram showing an example of functions and databases included in an information processing device 10 according to a first embodiment. [Figure 4] 3 is a schematic diagram showing a data configuration and an example of data of system configuration information according to the first embodiment. FIG. [Diagram 5] 4 is a schematic diagram showing a data configuration and an example of data of accessory device information according to the first embodiment. FIG. [Figure 6] 3 is a schematic diagram showing a data configuration and an example of data of the smart meter master according to the first embodiment. FIG. [Figure 7] 4 is a schematic diagram showing a data configuration and an example of data in a smart meter measurement value table according to the first embodiment. FIG. [Figure 8] 3 is a schematic diagram showing an example of transformer power data output by a transformer power calculation unit 13 according to the first embodiment. FIG. [Figure 9] FIG. 2 is a diagram showing an example of detailed functional blocks of an optimum rack calculation unit 15 according to the first embodiment. [Figure 10] FIG. 4 is a diagram for explaining a decision process according to the first embodiment. [Figure 11] FIG. 4 is a diagram for explaining a decision process according to the first embodiment. [Figure 12] FIG. 4 is a schematic diagram showing an example of an unbalance rate calculation result table generated by an optimal rack calculation unit 15 according to the first embodiment. [Figure 13] FIG. 4 is a schematic diagram showing an example of an objective function calculation result table generated by an optimal sheave calculation unit 15 according to the first embodiment. [Figure 14] 13 is a flowchart illustrating an example of an imbalance resolution process according to the first embodiment. [Figure 15] FIG. 13 is a diagram showing an example of an initial population generated by random numbers. [Figure 16] 4 is a schematic diagram showing a data structure and an example of data of an occurrence probability table 153 according to the first embodiment. FIG. [Figure 17] FIG. 2 is a schematic diagram showing an example of an initial group generated by an optimal twist calculation unit 15 according to the first embodiment. [Figure 18]10 is a schematic diagram illustrating an example of an occurrence probability table 153 for each node N according to the first embodiment. FIG. [Figure 19] 13 is a graph comparing calculation times in the decision process. [Figure 20] FIG. 13 is a schematic diagram showing a data configuration and an example of data in an optimal laying calculation result record table according to the third embodiment of the present invention. [Figure 21] FIG. 13 is a configuration diagram showing an example of functions and databases included in an information processing device 10A according to a fourth embodiment of the present invention. [Figure 22] 13 is a schematic diagram showing a data configuration and an example of data in a sensor measurement value table according to the fourth embodiment. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0010] At least the following points will become apparent from the description of this specification and the accompanying drawings.

[0011] =====First embodiment===== <<<Configuration of information processing device 10>>> First, the first embodiment will be described. FIG. 1 is a diagram showing a hardware configuration of an information processing device 10 according to an embodiment of the present invention. The information processing device 10 is, for example, a device that determines a state of a twisting for a three-phase transmission and distribution line of a power system 20 (described later) shown in FIG. 2. The twisting state refers to a twisting position and a twisting pattern at that position. The twisting pattern refers to a manner of switching (twisting) each phase. The information processing device 10 is a computer including a CPU (Central Processing Unit) 101, a memory 102, an input unit 103, an output unit 104, a storage unit 105, a recording medium drive unit 106, and a network connection unit 107. The CPU 101, the memory 102, the input unit 103, the output unit 104, the storage unit 105, the recording medium drive unit 106, and the network connection unit 107 are connected to each other for communication via a bus.

[0012] The CPU 101 executes programs stored in the memory 102 or the storage unit 105 to realize various functions of the information processing device 10 . The memory 102 is, for example, a RAM (Random-Access Memory) and is used as a temporary storage area for programs and data for determining the state of the rack.

[0013] The input unit 103 is a device that accepts commands and data input by a user, and includes an input interface such as a keyboard and a touch sensor that detects a touch position on a touch panel display. The output unit 104 is, for example, a display device such as a display, or an output device such as a printer.

[0014] The storage unit 105 is a non-volatile storage device that is configured by, for example, a hard disk, a USB (Universal Serial Bus) memory, a memory card, or the like, and stores programs to be executed or processed by the CPU 101 or various data.

[0015] The recording medium drive unit 106 is connected to a recording medium 6 such as an optical disk or a compact disk, and reads data from the recording medium 6 or writes data thereto.

[0016] A network connection unit 107 exchanges various programs and data with other computers via a network (not shown).

[0017] <<<An example of power system 20>>> 2 is a diagram showing an example of a power system 20 in which the information processing device 10 determines the state of the rack. The power system 20 is, for example, a 6.6 kV power transmission and distribution line system, and includes a transformer 21, a power transmission and distribution line 22, a sensor-integrated switch 23, multiple pole transformers TR (TR1 to TR5), and multiple watt-hour meters SM (SM1 to SM5). The power transmission and distribution line 22 is provided with nodes N (N0 to N5) to which the sensor-integrated switch 23 or the multiple pole transformers TR are connected, respectively. Note that the power system 20 may also be composed of a private line.

[0018] The transformer 21 transforms the voltage supplied from a power transmission line (not shown) and outputs a voltage of 6.6 kV to the power transmission / distribution line 22 .

[0019] The power transmission / distribution line 22 is a three-phase power transmission / distribution line for supplying power from the transformer 21 to each consumer, and extends from the transformer 21 on the upstream side toward the downstream side. The power transmission / distribution line 22 is a power line for supplying three-phase AC power of U-phase, V-phase, and W-phase from the transformer 21. The power transmission / distribution line 22 has a power transmission / distribution line 221 for supplying U-phase power, a power transmission / distribution line 222 for supplying V-phase power, and a power transmission / distribution line 223 for supplying W-phase power.

[0020] A node N is an arbitrary management unit provided on the power transmission / distribution line 22. In this embodiment, the node N is an aggregate unit managed on a pole transformer TR basis. The node N is a candidate for a rack position. For ease of explanation, the node N with node number "i (i is an integer)" will be referred to as node Ni below. The node number is an identification number that identifies each node N. For example, the node N with node number "0" will be referred to as node N0. Note that for matters common to each node N, the node number will be omitted and it will be simply referred to as "node N" or "each node N."

[0021] The sensor-embedded switch 23 is a switch having a sensor capable of periodically measuring at least the measured values ​​of the voltage and current at a point of installation. The point of installation of the sensor-embedded switch 23 is the node N0.

[0022] The pole transformer TR is a transformer connected to the power transmission / distribution line 22. The pole transformer TR is a transformer that transforms, for example, a voltage on the primary side at a predetermined transformation ratio and outputs the transformed voltage from the secondary side. The primary sides of the pole transformers TR1 to TR4 are each connected to any two-phase (two lines) power transmission / distribution line 22 of the power transmission / distribution lines 221 to 223, and the primary side of the transformer TR5 is connected to the power transmission / distribution lines 221 to 223. The secondary sides of the pole transformers TR1 to TR5 are each connected to a consumer. The consumer is a person who uses the power supplied from the power transmission / distribution line 22, and each has a load that consumes the power. The power output by the transformer 21 to the power transmission / distribution line 22 is distributed to the consumer via the pole transformer TR. For ease of explanation, hereinafter, a pole transformer TR with an ancillary device ID "TRi" will be referred to as a pole transformer TRi. The ancillary device ID is identification information that identifies each ancillary device (sensor-integrated switch 23 or pole transformer TR). For example, a pole transformer TR with an ancillary device ID "TR1" will be referred to as a pole transformer TR1. Note that numbers will be omitted for matters common to each pole transformer TR, and they will simply be referred to as "pole transformer TR" or "each pole transformer TR."

[0023] The watt-hour meter SM is installed at a consumer at a predetermined node N of the power transmission / distribution line 22. A so-called smart meter can be used as the watt-hour meter SM. The watt-hour meter SM measures the measured value of the amount of power used (load or power generation) of the consumer at a predetermined period. Hereinafter, for convenience of explanation, the watt-hour meter SM with the smart meter ID "SMi" is referred to as the watt-hour meter SMi. The smart meter ID is identification information for identifying each watt-hour meter SM. For example, the watt-hour meter SM with the smart meter ID "SM1" is referred to as the watt-hour meter SM1. Note that, for matters common to each watt-hour meter SM, the numbers are omitted and it is simply referred to as the "watt-hour meter SM" or "each watt-hour meter SM." Note that, in this figure, a configuration in which one watt-hour meter SM is connected to each pole transformer TR is illustrated, but multiple watt-hour meters SM (i.e., consumers) may be connected to one pole transformer TR.

[0024] <<<Details of information processing device 10>>> FIG. 3 is a configuration diagram showing an example of functions and databases included in the information processing device 10. As shown in FIG.

[0025] The information processing device 10 is communicatively connected to each of the watt-hour meters SM in the power system 20 via a communication line 30. The information processing device 10 has a system configuration database 11, a smart meter information database 12, a transformer power calculation unit 13, a data generation unit 14, an optimal rack calculation unit 15, and a result output unit 16. The system configuration database 11 and the smart meter information database 12 are stored in advance in a storage unit 105 of the information processing device 10. In addition, the CPU 101 reads a predetermined program stored in the storage unit 105 into the memory 102 and executes or processes the program, thereby realizing the functions of the transformer power calculation unit 13, the data generation unit 14, the optimal rack calculation unit 15, and the result output unit 16 in the information processing device 10.

[0026] The system configuration database 11 is a database that stores system configuration information indicating the configuration of the power system 20, and auxiliary equipment information indicating information on the auxiliary equipment (sensor-integrated switch 23 and pole transformer TR) that the power system 20 has.

[0027] FIG. 4 is a schematic diagram showing a data structure and an example of data of the system configuration information. As shown in the figure, the system configuration information has the following items: node number, utility pole number, latitude, longitude, connected utility pole number, distribution line R (U phase), distribution line X (U phase), distribution line R (V phase), distribution line X (V phase), distribution line R (W phase), distribution line X (W phase), and ancillary device ID. The node number is identification information for identifying each node N. The utility pole number is the identification number of the utility pole on which the node N is located. The latitude is the latitude of the position where the utility pole is installed. The longitude is the longitude of the position where the utility pole is installed. The connection pole number is the utility pole number of the upstream utility pole to which the utility pole is connected via the transmission / distribution line 22. The distribution line R (U phase) is the resistance of the line in the U phase (unit: Ω (ohms)). The distribution line X (U phase) is the reactance in the U phase (unit: Ω). The distribution line R (V phase) is the resistance of the line in the V phase (unit: Ω). The distribution line X (V phase) is the reactance in the V phase (unit: Ω). The distribution line R (W phase) is the resistance of the line in the W phase (unit: Ω). The distribution line X (W phase) is the reactance (unit: Ω) in the W phase. The auxiliary device ID is identification information of the auxiliary device arranged at the node N.

[0028] FIG. 5 is a schematic diagram showing a data structure and an example of the accessory device information. As shown in the figure, the accessory device information includes the following items: accessory device ID, accessory device type, and connection phase. The accessory device ID is identification information for identifying each accessory device (sensor-embedded switch 23 or pole transformer TR). The accessory device type is the type of the accessory device. For example, the accessory device ID "SE1" is the sensor-embedded switch 23, and the accessory device IDs "TR1" to "TR5" are pole transformers TR. The connection phase is the phase of the power transmission / distribution line 22 to which the accessory device is connected. In the illustrated example, for example, the sensor-embedded switch 23 is connected to the UVW phase (i.e., all phases of the U phase, V phase, and W phase). Also, the pole transformer TR1 is connected to the UV phase (i.e., two phases of the U phase and the V phase).

[0029] Returning to FIG. 3, the functional configuration of the information processing device 10 will be further described. The smart meter information database 12 is a database that stores a smart meter master indicating information relating to each of the watt-hour meters SM, and a smart meter measurement value table indicating periodic measurement values ​​measured by each of the watt-hour meters SM.

[0030] FIG. 6 is a schematic diagram showing a data configuration and an example of data in the smart meter master. As shown in the figure, the smart meter master has the following items: smart meter ID, connected pole transformer ID, model, and rated voltage. The smart meter ID is identification information for identifying each watt-hour meter SM. The connected pole transformer ID is the accessory device ID of the pole transformer TR to which the watt-hour meter SM is connected. The model is the model of the watt-hour meter SM. The rated voltage is the rated voltage of the watt-hour meter SM.

[0031] FIG. 7 is a schematic diagram showing a data configuration and an example of data in a smart meter measurement value table. As shown in the figure, the smart meter measurement value table has fields for measurement date and time, smart meter ID, and meter measurement value. The measurement date and time is the date and time (year, month, day, hour, minute) when the meter measurement value was measured. The meter measurement value is the measured value (in units of kWh (kilowatt hours)) of the amount of electricity used by the consumer measured by the power meter SM. In the illustrated example, the measurement value of each watt-hour meter SM every 30 minutes is stored in the smart meter measurement value table. That is, in this example, each watt-hour meter SM measures the amount of power used by a consumer at a fixed cycle of every 30 minutes. The data stored in the smart meter measurement value table may be pre-stored in the memory unit 105, or may be updated at any time by the CPU 101 acquiring meter measurement values ​​from each electricity meter SM via the communication line 30 and writing the acquired meter measurement values ​​to the smart meter measurement value table.

[0032] Returning to FIG. 3, the functional configuration of the information processing device 10 will be further described. The transformer power calculation unit 13 calculates the distribution of the power state (load or power generation) (hereinafter referred to as "load distribution") for each pole transformer TR based on the information stored in the system configuration database 11 and the smart meter information database 12. In this embodiment, the transformer power calculation unit 13 calculates the average power consumption of each pole transformer TR as the load distribution.

[0033] Hereinafter, a method for calculating the average power consumption will be specifically described using an example of data shown in FIG. 7, taking as an example a case where the average power consumption of the pole transformer TR1 for 30 minutes from the measurement date and time "2019 / 12 / 10 9:00" to the measurement date and time "2019 / 12 / 10 9:30". First, the transformer power calculation unit 13 refers to the smart meter master in FIG. 6 to identify the watt-hour meter SM1 connected to the pole transformer TR1. Then, the transformer power calculation unit 13 subtracts the meter measurement value "1500" of the watt-hour meter SM1 at the measurement date and time "2019 / 12 / 10 9:00" from the meter measurement value "1550" of the watt-hour meter SM1 at the measurement date and time "2019 / 12 / 10 9:30" to calculate the 30-minute power measurement value "50 kWh (= 1550 - 1500)". Then, the transformer power calculation unit 13 divides the power measurement value "50 kWh" by "0.5 hours (30 minutes)" to calculate the average power consumption of the pole transformer TR1 for 30 minutes "100 kW (kilowatts) (= 50 kWh ÷ 0.5 h)". Similarly, the transformer power calculation unit 13 calculates the average power consumption of the pole transformer TR2 "150 kW", the average power consumption of the pole transformer TR3 "50 kW", the average power consumption of the pole transformer TR4 "80 kW", and the average power consumption of the pole transformer TR5 "200 kW". The transformer power calculation unit 13 then outputs transformer power data indicating the calculated average power consumption of each pole transformer TR to the data generation unit 14.

[0034] FIG. 8 is a schematic diagram showing an example of the transformer power data output by the transformer power calculation unit 13. As shown in FIG. The transformer power data includes the following fields: measurement date and time, accessory device ID, and transformer power. The measurement date and time is the date and time (year, month, day, hour, minute) when the meter measurement value used to calculate the transformer power was measured. The transformer power is the average power consumption (unit: kW) of the pole transformer TR for the 30 minutes immediately preceding the measurement date and time.

[0035] In the illustrated example, the load distribution is shown in a single time section at "2019 / 12 / 10 9:30", but multiple time sections may be used. In the present embodiment, the load distribution is described using only active power, but reactive power may also be set.

[0036] Returning to FIG. 3, the functional configuration of the information processing device 10 will be further described. The data generating unit 14 generates input data based on the system configuration database 11 and the transformer power data. The input data indicates the load of each phase at each node N. First, the data generating unit 14 refers to the system configuration information and the auxiliary equipment information stored in the system configuration database 11 to identify the utility pole on which each pole transformer TR is installed, the connection relationship of each utility pole, and the impedance of each distribution line. For example, the data generating unit 14 identifies the phase to which the pole transformer TR arranged at each node N is connected based on the system configuration information and the auxiliary equipment information, and sets the load for the identified phase as the transformer power of the pole transformer TR. In the data example shown in FIG. 4 and FIG. 5, for example, the data generating unit 14 identifies that the pole transformer TR1 arranged at the node N1 is connected to the UV-phase distribution line. Then, the data generating unit 14 refers to the transformer power data, and sets the load of the UV phase at node N1 to the transformer power of pole transformer TR1 "100", the load of the VW phase to "0", and the load of the WU phase to "0". The data generating unit 14 then outputs input data indicating the load of each phase at each of all nodes N to the optimal rack calculating unit 15.

[0037] The optimal rack calculation unit 15 executes a determination process to determine the racking state (racking position and racking pattern at each racking position) of the transmission / distribution line 22 that reduces the unbalance rate in the power system 20, based on the input data. The racking position is the position where the transmission / distribution line 22 is racked (in this embodiment, any one of a plurality of nodes N). The racking pattern is the way of swapping phases in the transmission / distribution line 22.

[0038] FIG. 9 is a diagram showing an example of detailed functional blocks of the optimum rack calculation unit 15. As shown in FIG. The optimum rack calculation unit 15 includes a calculation unit 151, a determination unit 152, and an occurrence probability table 153. The occurrence probability table 153 is stored in advance in the storage unit 105 of the information processing device 10.

[0039] The calculation unit 151 executes a calculation process to calculate the voltage unbalance rate of each of n nodes N based on a plurality of combinations obtained by taking the state of the transmission / distribution line 22 at each of m (m is a positive integer) nodes N in the power system 20 as any one of a first state to a third state, the power exchanged with the power system at each of n (n is a positive integer) nodes N, and system configuration information.

[0040] Here, the first state is a state in which the transmission / distribution line 22 is not crossed, the second state is a state in which the transmission / distribution line 22 is crossed in a first pattern, and the third state is a state in which the transmission / distribution line 22 is crossed in a second pattern different from the first pattern. The first pattern and the second pattern will be described in detail later. In addition, the m nodes N in this embodiment are all the nodes N provided in the transmission / distribution line 22, but are not limited to this and may be a plurality of nodes N selected in advance from the nodes N provided in the transmission / distribution line 22. In addition, the n nodes N in this embodiment are nodes N to which the watt-hour meter SM (pole transformer TR) is connected (i.e., all the nodes N other than the node NO where the sensor-integrated switch 23 is arranged). In addition, in this embodiment, the calculation unit 151 calculates the power exchanged with the power system 20 at each of the n nodes by using the measurement value of the watt-hour meter SM connected to each of the n nodes.

[0041] The determination unit 152 executes a determination process for determining the state of the power transmission / distribution line 22 at each of the m nodes based on the calculation result of the voltage unbalance rate. That is, the determination unit 152 determines the state of the rack in the power system 20. Specifically, the determination unit 152 determines the state of the power transmission / distribution line 22 at each of the m nodes by optimizing an objective function determined based on at least one of the average value of the voltage unbalance rate of each of the n nodes or the maximum value of the voltage unbalance rate of each of the n nodes, with the state of the power transmission / distribution line 22 at each of the m nodes as a decision variable. At this time, the determination unit 152 refers to the occurrence probability table 153 and generates an initial value of the decision variable at which the first state occurs with an occurrence probability different from the occurrence probability of each of the second state and the third state. For example, the determination unit 152 generates an initial value at which the occurrence probability of the first state is greater than the occurrence probability of each of the second state and the third state.

[0042] The occurrence probability table 153 is information indicating the occurrence probability of each of the first state, the second state, and the third state for the initial value of the decision variable. The occurrence probability table 153 will be described in detail later.

[0043] The determination process executed by the optimum rack calculation unit 15 will be described in detail with reference to Fig. 10 to Fig. 13. Fig. 10 and Fig. 11 are diagrams for explaining the determination process.

[0044] First, the optimum shelving calculation unit 15 substitutes the load of each phase at each node N into the variable "node[i].load setting[j]" based on the input data, as shown in table T100 in FIG. 10. Here, the index "i" of the array "node" indicates the node number. Also, the index "j" of the array "load setting" takes three values ​​of 0, 1, and 2, with "0" indicating the UV phase, "1" indicating the VW phase, and "2" indicating the WU phase. For example, node[i].load setting "0" indicates the load of the UV phase at node N with node number "i", node[i].load setting "1" indicates the load of the VW phase at node N with node number "i", and node[i].load setting "2" indicates the load of the WU phase at node N with node number "i". Also, the load in this embodiment is the transformer power of the pole transformer TR arranged at node N. The optimal wiring calculation unit 15 assigns the transformer power of the pole transformer TR to the "load setting" corresponding to the phase to which the pole transformer TR is connected. For example, since the pole transformer TR1 located at the node N1 is connected to the UV phase, the optimal wiring calculation unit 15 sets the node[1].load setting[0] to the transformer power of the pole transformer TR1 "100" (node[1].load setting[0]=100).

[0045] Next, the optimal twisting calculation unit 15 generates combinations of states of the power transmission / distribution line 22 at each of the m nodes N (hereinafter, referred to as "twisting pattern combinations"), and defines the generated twisting pattern combinations by using an array of discrete values ​​with the variable "node[n].twisting pattern" as shown in table T200 in Fig. 10. The variable "twisting pattern" has three values ​​of 0, 1, and 2, where "0" indicates that the power transmission / distribution line 22 is not twisted (not twisted), "1" indicates a first pattern in which the U phase is replaced with the V phase, the V phase with the W phase, and the W phase with the U phase, and "2" indicates a second pattern in which the U phase is replaced with the W phase, the V phase with the U phase, and the W phase with the V phase. For example, node[0].twisting pattern=0 indicates that twisting is not performed at node N0. Moreover, node [2].wire pattern=2 indicates that the U phase is swapped with the W phase, the V phase with the U phase, and the W phase with the V phase at node N2 (wired in the second pattern). Moreover, node [4].wire pattern=1 indicates that the U phase is swapped with the V phase, the V phase with the W phase, and the W phase with the U phase at node N4 (wired in the first pattern). Note that in power system 20 that supplies three-phase AC power, the order of the phases cannot be changed, so the wire pattern is limited to these three values.

[0046] When the power system 20 shown in FIG. 10 is racked using a combination of racking patterns shown in table T200, as in power system 20A shown in FIG. 11, at node N2, the U phase is connected to the V phase, the V phase is connected to the W phase, and the W phase is connected to the U phase, and at node N4, the U phase is connected to the W phase, the V phase is connected to the U phase, and the W phase is connected to the V phase.

[0047] Next, the optimum rack calculation unit 15 calculates the phase rotation at each node N using the variable "node[i].rack pattern" as in table T300 shown in FIG. 11, and substitutes it into the variable "node[i].phase rotation". The variable "phase rotation" indicates how the phases are switched at each of the m nodes N when the transmission / distribution lines 22 are racked using a combination of the generated rack patterns. The variable "phase rotation", like the variable "rack pattern", takes three values ​​of 0, 1, and 2, with "0" indicating that the state of the transmission / distribution line 22 does not change, "1" indicating that the U phase is switched to the V phase, the V phase is switched to the W phase, and the W phase is switched to the U phase, and "2" indicating that the U phase is switched to the W phase, the V phase is switched to the U phase, and the W phase is switched to the V phase. For example, at node N3, the phase rotation is set to "2" because the U phase is replaced with the W phase, the V phase is replaced with the U phase, and the W phase is replaced with the V phase as a result of the crosslinking in the second pattern at node N2. At node N5, the phase rotation is set to "0" because the state of the power transmission / distribution line 22 does not change as a result of the node N2 being crosslinked in the second pattern and the node N4 being crosslinked in the first pattern.

[0048] Specifically, first, the optimum twist calculation unit 15 sets the phase rotation of node N0 to 0 (node[0].phase rotation=0). Then, when i is 1 or more, the optimum twist calculation unit 15 sets node[i].phase rotation to the remainder of node[i-1].phase rotation+node[i].twist pattern modulo 3 (i.e., remainder when divided by 3). In other words, the optimum twist calculation unit 15 sets "node[i].phase rotation=node[i-1].phase rotation+node[i].twist pattern%3". Here, "%" indicates a remainder.

[0049] Next, the optimum rack calculation unit 15 uses the calculated phase rotation to calculate the load after racking with the combination of the generated rack patterns. Specifically, the optimum rack calculation unit 15 assigns the load at each node N after racking to the variable "node [i]. rack load setting [j]" according to the following formulas (1) to (3).

[0050] Node[i].loadsettings[(0+node[i].phaserotation)%3] = node[i].loadsettings[0]…(1)

[0051] Node[i].loadsettings[(1+node[i].phaserotation)%3] = node[i].loadsettings[1]…(2)

[0052] Node[i].loadsettings[(2+node[i].phaserotation)%3] = node[i].loadsettings[2]…(3)

[0053] The index of the array "load setting for wiring" takes three values, 0, 1, and 2, with "0" indicating the UV phase, "1" indicating the VW phase, and "2" indicating the WU phase. For example, node[i].load setting "0" indicates the load of the UV phase after wiring at node N with node number "i", node[i].load setting "1" indicates the load of the VW phase after wiring at node N with node number "i", and node[i].load setting "2" indicates the load of the WU phase after wiring at node N with node number "i".

[0054] Taking the load of node N2 as an example, a specific description will be given using the above-mentioned formula (1). The above-mentioned formula (1) at node N2 becomes the following formula (1A).

[0055] Node[2].load setting[(0+node[2].phase rotation)%3] = node[2].load setting[0]...(1A)

[0056] Then, by substituting node[2].phase rotation=2 into equation (1A), the following equation (1B) can be obtained.

[0057] Node[2].Load setting[(0+2)%3] = Node[2].Load setting[0]...(1B)

[0058] As a result, the following equation (1C) is obtained, and it can be calculated that the load of the UV phase of node N2 is connected to the WU phase by the twisted connection.

[0059] Node[2].loadsettings[2] = Node[2].loadsettings[0]…(1C)

[0060] Then, by substituting node[2].load setting[0]=150.0 into equation (1C), the load on the WU phase of node N2 after installation can be calculated as shown in the following equation (1D).

[0061] Node[2]. Load setting[2]=150.0…(1D)

[0062] In this way, by using equation (1), it is possible to set in the variable "twisted load setting" that the load "150.0" of the UV phase of the node N2 is changed to the WU phase by the twisted rack.

[0063] Then, the optimum wiring calculation unit 15 executes a simulation by three-phase power flow calculation using the variable "node [i]. wiring load setting [j]" indicating the load after wiring, and calculates the voltage and unbalance rate for each phase of each node N after wiring with the combination of the generated wiring patterns. Specifically, the optimum wiring calculation unit 15 calculates the positive-sequence voltage and the negative-sequence voltage from the voltages of each of the three phases, and multiplies the value obtained by dividing the negative-sequence voltage by the positive-sequence voltage by 100 (i.e., "negative-sequence voltage ÷ positive-sequence voltage × 100").

[0064] FIG. 12 is a schematic diagram showing an example of an unbalance rate calculation result table generated by the optimum rack calculation unit 15. As shown in FIG. The optimum rack calculation unit 15 generates an unbalance rate calculation result table including the calculated voltage and unbalance rate for each phase of each node N. For example, the optimum rack calculation unit 15 writes the values ​​of the variables of rack pattern, phase rotation, load setting [0] to load setting [2], rack load setting [0] to rack load setting [2], voltage [0] to voltage [2], and unbalance rate for each of the m nodes N in the unbalance rate calculation result table. Here, voltage [0] indicates the voltage of the UV phase, voltage [1] indicates the voltage of the VW phase, and voltage [2] indicates the voltage of the WU phase. FIG. 12 shows an example of data when the node N2 is racked in the second pattern and the node N4 is racked in the first pattern as shown in table T200 for the power system 20 as shown in FIG. 11. The optimum rack calculation unit 15 generates an unbalance rate calculation result table for each combination of rack patterns for each of the m nodes N. Furthermore, the optimum rack calculation unit 15 generates an unbalance rate calculation result table for each of a plurality of time sections (for example, all time sections for each measurement cycle (for example, 30 minutes) of the watt-hour meter SM within a predetermined period).

[0065] Next, the optimal wiring calculation unit 15 calculates an objective function from the voltage unbalance rate of each of the n nodes N. For example, the optimal wiring calculation unit 15 calculates an objective function that selectively combines the average value of the voltage unbalance rate of each of the n nodes N (hereinafter referred to as the "average unbalance rate", which is "1.07" in the case of the data example shown in FIG. 12), the maximum value of the voltage unbalance rate of each of the n nodes N (hereinafter referred to as the "maximum unbalance rate", which is "1.95" in the case of the data example shown in FIG. 12), and the number of nodes N that wire the transmission / distribution line 22 (hereinafter referred to as the "number of wires", which is "2" in the case of the data example shown in FIG. 12). In this embodiment, the optimal wiring calculation unit 15 calculates the objective function F(p) by the following formula (4).

[0066] F(p) = X×f(p) + Y×g(p) + Z×h(p) …(4)

[0067] Here, p is a combination of the racking patterns shown in the following equation (5). The combination p of the racking patterns is a decision variable.

[0068] p ∈ {x1, x2, , x m-1 , x m} , x i ∈ {0, 1, 2}…(5)

[0069] Here, m is the number of nodes N. Function f(p) is a function that takes rack pattern combination p as input and calculates the average unbalance rate of all nodes N at all time cross sections. Function g(p) is a function that takes rack pattern combination p as input and extracts the maximum unbalance rate from among all nodes N at all time cross sections. Function h(p) is a function that takes rack pattern p as input and counts the number of racks.

[0070] In addition, "X" is the weight of the average unbalance rate, "Y" is the weight of the maximum unbalance rate, and "Z" is the weight of the number of runs. By changing the values ​​of X, Y, and Z, the weight of each element (average unbalance rate, maximum unbalance rate, and number of runs) can be changed. For example, by making the value of X larger than the values ​​of Y and Z, the weight of the average unbalance rate can be made heavier than the weight of the maximum unbalance rate and the number of runs. In other words, by making the value of X larger, the weight of the average unbalance rate can be made heavier, and by making the value of X smaller, the weight of the average unbalance rate can be made smaller. Similarly, by making the value of Y larger, the weight of the maximum unbalance rate can be made heavier, and by making the value of Y smaller, the weight of the maximum unbalance rate can be made smaller. Similarly, by making the value of Z larger, the weight of the number of runs can be made heavier, and by making the value of Z smaller, the weight of the number of runs can be made smaller. In addition, by setting the values ​​of X, Y, and Z to 0, each element (average unbalance rate, maximum unbalance rate, or number of runs) can be excluded from the objective function. For example, the number of twists can be excluded from the objective function by setting Z to 0. In this embodiment, the objective function is determined based on at least one of the average unbalance rate and the maximum unbalance rate, but is not limited thereto. For example, the objective function may be determined based on the unbalance rate of each of the voltages of the n nodes N, such as the median of the unbalance rates of the voltages of the n nodes N.

[0071] Then, the optimal rack calculation unit 15 determines a constraint condition for each element of the objective function (average unbalance rate, maximum unbalance rate, or number of racks) using preset thresholds α to γ. For example, the constraint condition for the average unbalance rate is that it is smaller than the threshold α, the constraint condition for the maximum unbalance rate is that it is smaller than the threshold β, and the constraint condition for the number of racks is that it is smaller than the threshold γ. Specifically, the optimal rack calculation unit 15 determines the weight value for each element of the objective function as follows.

[0072] When f(p)<threshold α, X=A When f(p) ≧ threshold α, X=A′ (where A′≫A) Here, A and A' are preset constants, and A' is sufficiently larger than A.

[0073] When g(p)<threshold β, Y=B When g(p) ≧ threshold β, Y = B′ (where B′ ≫ B) Here, B and B' are preset constants. Also, B' is sufficiently larger than B.

[0074] When h(p)<threshold γ, Z=C When h(p) ≧ threshold γ, Z = C′ (where C′≫C) Here, C and C' are preset constants, and C' is sufficiently larger than C.

[0075] By determining the weighting value for each element of the objective function in this way, it is possible to prevent a combination of twisting patterns that does not satisfy each constraint condition from being selected as a twisting state that reduces the unbalance rate. For example, when the threshold value γ is set to 2, in the data example shown in Fig. 13 described later, No. 3 and No. 5, which have twisting numbers of 2 or more, will not be selected as a twisting state that reduces the unbalance rate because the objective function has a very large value.

[0076] Thereafter, the optimal racking calculation unit 15 changes the combination of racking patterns and calculates the objective function for the changed combination of racking patterns until the termination condition is satisfied. The termination condition is, for example, that the number of combinations of racking patterns (the number of calculated objective functions) exceeds a predetermined threshold value, or the value of the calculated objective function becomes smaller than a predetermined threshold value. The termination condition can be defined arbitrarily.

[0077] FIG. 13 is a schematic diagram showing an example of an objective function calculation result table generated by the optimum sheave calculation unit 15. As shown in FIG. Each time the optimal rack calculation unit 15 calculates an objective function, it writes in an objective function calculation result table a No. that identifies the combination of rack patterns, the value of the variable “node[n].rack pattern” that indicates the combination of rack patterns, the average unbalance rate (unit: %), the maximum unbalance rate (unit: %), the number of racks, and the calculated objective function in association with each other.

[0078] Then, when the termination condition is satisfied, the optimal rack calculation unit 15 optimizes the objective function. Specifically, the optimal rack calculation unit 15 refers to the objective function calculation result table and selects the combination of rack states with the smallest objective function (i.e., min F(p)) as the rack state that reduces the unbalance rate. For example, in the illustrated data example, the optimal rack calculation unit 15 selects the combination of rack patterns No. 4 with the smallest objective function (racking in the second pattern at node N5) as the rack state that reduces the unbalance rate. Then, the optimal rack calculation unit 15 outputs data indicating the selected rack state (hereinafter, referred to as the "determination result") to the result output unit 16.

[0079] The result output unit 16 outputs the determination result input from the optimal rack calculation unit 15 by displaying it on a display or printing it on a printer. The result output unit 16 may transmit the determination result to another computer or the like via the network connection unit 107.

[0080] ==An example of an imbalance resolution process executed by the information processing device 10== FIG. 14 is a flowchart showing an example of an imbalance resolution process for the power system 20, which is executed by the information processing device 10. First, the data generating unit 14 generates input data based on the system configuration information, the auxiliary device information, and the transformer power data (step S100). Next, the optimal wiring calculation unit 15 reads the input data generated by the data generating unit 14 (step S200). Then, the optimal wiring calculation unit 15 executes a simulation using a three-phase power flow calculation based on the input data, and calculates the voltage for each phase at each node N (step S300). Next, the optimal wiring calculation unit 15 calculates the current unbalance rate of each node N based on the calculated voltage for each phase at each node N (step S400).

[0081] Next, the optimal rack calculation unit 15 determines whether or not unbalance measures by racking are necessary based on the calculated unbalance rate of each node N (step S500). For example, the optimal rack calculation unit 15 determines that unbalance measures are necessary when the average unbalance rate, the maximum unbalance rate, or both of the average and maximum unbalance rates of each node N calculated in step S400 exceed preset thresholds. When it is determined that unbalance measures are not necessary (step S500: No), the information processing device 10 ends this unbalance resolution process.

[0082] On the other hand, when it is determined that an unbalance measure is necessary (step S500: Yes), the optimum rack calculation unit 15 executes a decision process shown in steps S601 to S608 (step S600).

[0083] The optimal rack state calculation unit 15 determines the rack state that reduces the unbalance rate by using a combinatorial optimization method using metaheuristics. In the optimization method using metaheuristics, an initial population is generally generated by using random numbers.

[0084] FIG. 15 is a diagram showing an example of an initial population generated by random numbers. In this figure, the generated initial population is illustrated in table format. The item "initial individual" in the illustrated table is set with identification information of the individual in the initial population. In the illustrated example, n individuals are included in the initial population. The item "node [i] (i is the node number)" in the illustrated table is set with the shelving pattern of node Ni in each individual. Hereinafter, the squares in the initial population illustrated in table format in which the shelving pattern is set are referred to as "cells." When the initial population is generated using random numbers, the shelving pattern is randomly set with the first state "0", the second state "1", and the third state "2" with equal probability (one third). Therefore, when the initial population is generated using random numbers, individuals with a relatively large number of shelvings are also included in the initial population.

[0085] On the other hand, since the above-mentioned objective function is determined based on the number of twists, the value of the objective function increases as the number of twists increases. Therefore, when the initial population is generated using random numbers, relatively many individuals with low evaluation values ​​(large objective function values) are included in the initial population. Therefore, when the initial population is generated using random numbers, the calculation time for optimizing the objective function (decision process for deciding the twist state that improves the voltage unbalance rate) increases. In general, it is known that in a combinatorial optimization method using metaheuristics, if an individual with a high evaluation value is included in the initial population, the convergence becomes faster (the calculation time becomes shorter). Therefore, the optimal twist calculation unit 15 in this embodiment adjusts the occurrence probability of each twist pattern (first state to third state) of each node N in the initial population, and generates an initial population that includes many individuals with high evaluation values ​​(small objective function values), thereby shortening the calculation time for optimizing the objective function.

[0086] Therefore, in the determination process, the optimal shelving calculation unit 15 in this embodiment first adjusts the occurrence probability of each shelving pattern (first state to third state) of each node N in the initial group (n, p) (step S601). Specifically, first, the optimal shelving calculation unit 15 reads out the occurrence probability of each shelving pattern "0", "1", and "2" from the occurrence probability table 153.

[0087] FIG. 16 is a schematic diagram showing a data structure and an example of data in the occurrence probability table 153. As shown in FIG. As shown in the figure, the occurrence probability table 153 has items of value and occurrence probability. The value indicates each crisscross pattern (first state "0", second state "1", or third state "2"). The occurrence probability is the occurrence probability of a value in an initial population. In the example shown in the figure, the occurrence probability of the first state "0" is "0.750", the occurrence probability of the second state "1" is "0.125", and the occurrence probability of the third state "2" is "0.125". In this embodiment, the user sets the occurrence probability of each value in the occurrence probability table 153 in advance so that the occurrence probability of the first state "0" is different from the occurrence probability of the second state "1" and the third state "2". In the example shown in FIG. 16, the occurrence probability of the first state "0" is greater than the second state "1" and the third state "2". In addition, the occurrence probabilities of the second state "1" and the third state "2" are equal.

[0088] Next, the optimal shelving calculation unit 15 generates an initial population (n, p) including n initial individuals having different combinations p of shelving patterns (shelving states) in each of the m nodes N (step S602). At this time, the optimal shelving calculation unit 15 generates the initial population (n, p) such that the occurrence probabilities of the first state "0" to the third state "2" in the entire initial population (n, p) are the occurrence probabilities of the first state to the third state that have been read out.

[0089] FIG. 17 is a schematic diagram showing an example of an initial group generated by the optimum twist calculation unit 15. As shown in FIG. In this figure, the generated initial population is illustrated in a table format. The optimal cross-linking calculation unit 15 sets the first state "0" with a probability of occurrence of "0.750", the second state "1" with a probability of occurrence of "0.125", and the third state "2" with a probability of occurrence of "0.125" to each cell in the initial population. As a result, an initial population is generated in which the probability of occurrence of the first state "0" is "0.750", the probability of occurrence of the second state "1" is "0.125", and the probability of occurrence of the third state "2" is "0.125". Therefore, the occurrence ratio of the first state "0" in each initial individual is higher than the second state "1" and the third state "2". For example, in the initial individual "n" illustrated in FIG. 17, the cross-linked node N is only one, node N4 (second state "1"), and the other four nodes N are in the first state "0" that is not cross-linked. In this way, the optimal twist calculation unit 15 can generate an initial population that includes more initial individuals with relatively small values ​​of the objective function compared to a case where the initial population is generated using random numbers, by adjusting the occurrence probability of the first state "0" to the third state "2" in the initial population. That is, at the stage of the initial population, it is possible to generate individuals that are close to the twist state of the optimal solution that optimizes the objective function.

[0090] Next, the optimal rack calculation unit 15 executes the processes of the following steps S603 to S604 for each of the multiple individuals (rack states) included in the generated population. That is, the processes of steps S603 to S604 are repeatedly executed the number of times equal to the number n of individuals included in the population.

[0091] The optimal wiring calculation unit 15 executes a simulation by three-phase power flow calculation using the load at the time slice t for each of the multiple time slices t, and calculates the voltage unbalance rate at each of the m nodes N when the wiring pattern p is applied to each of the nodes N (step S603: calculation step). That is, the optimal wiring calculation unit 15 repeatedly executes the process of step S603 for all the loads at the multiple time slices t.

[0092] Next, the optimal lattice calculation unit 15 calculates an objective function based on the unbalance rate of each node N at all time cross sections t (step S604). Here, the optimal lattice calculation unit 15 calculates an objective function for each of all individuals (lattice states) included in the generated population.

[0093] Thereafter, the optimal cross-link calculation unit 15 performs genetic operations such as crossover, mutation, or selection on the generated population (step S605).

[0094] After that, the optimum rack calculation unit 15 judges whether or not the above-mentioned termination condition is satisfied (step S606).

[0095] If it is determined that the termination condition is not satisfied (step S606: No), a new generation is generated by the genetic operation performed in step S605, the population is replaced (step S607), and the process returns to step S603. That is, the optimal sheave calculation unit 15 replaces the population and repeats the processes of steps S603 to S605 until the termination condition is satisfied.

[0096] On the other hand, when it is determined that the termination condition is satisfied (step S606: Yes), the optimal rack calculation unit 15 outputs the rack state in which the objective function is smallest as the determination result to the result output unit 16 (step S608: determination step). The result output unit 16 outputs the determination result by displaying it on a display or printing it on a printer. After that, the information processing device 10 ends the imbalance resolution process.

[0097] In this embodiment, a genetic algorithm is used as an example of a combinatorial optimization method using metaheuristics. However, the present invention is not limited to this, and other methods such as particle swarm optimization or tabu search can also be applied.

[0098] In addition, in this embodiment, the optimal sheave calculation unit 15 adjusts the occurrence probability of the first state “0” to the third state “2” in the entire initial population using the occurrence probability table 153, but this is not limited to this, and the occurrence probability may be adjusted for each initial individual, or the occurrence probability may be adjusted for each node N.

[0099] FIG. 18 is a schematic diagram showing an example of the occurrence probability table 153 for each node N. The occurrence probability table 153 for each node N has items of a value and the occurrence probability of each node N. In the illustrated example, the occurrence probability of the first state "0" is "0.750", the occurrence probability of the second state "1" is "0.125", and the occurrence probability of the third state "2" is "0.125" in all nodes N, but this is not limited to this, and a different occurrence probability may be set for each node N. The optimal shelving calculation unit 15 adjusts the occurrence probability for each node N in the initial population by referring to the occurrence probability table 153 for each node N. For example, the optimal shelving calculation unit 15 sets the first state "0" with an occurrence probability of "0.750", the second state "1" with an occurrence probability of "0.125", and the third state "2" with an occurrence probability of "0.125" in the cell in the column of node N0 in the initial population. As a result, the probability of occurrence of the first state "0" at node N0 of the initial population becomes "0.750", the probability of occurrence of the second state "1" becomes "0.125", and the probability of occurrence of the third state "2" becomes "0.125".

[0100] There are many combinatorial optimization methods using metaheuristics. For algorithms that generate a population of initial individuals as initial values, such as genetic algorithms (GA), tabu search (TS), and particle swarm optimization (PSO), data of the initial population in which the occurrence probabilities of the first state "0" to the third state "2" are adjusted using the occurrence probability table 153 is used as an input value. On the other hand, in the case of a distribution estimation algorithm (EDA) such as Population-Based Incremental Learning (PBIL), since the algorithm provides initial probabilities as initial values, the values ​​in the occurrence probability table 153 are set as initial values ​​as they are. Therefore, the method disclosed in this embodiment for adjusting the occurrence probabilities of the first state "0" to the third state "3" in the initial population is not limited to the algorithms specifically listed above, and can be applied to a metaheuristic method having a step of generating an initial population using initial individuals or initial probabilities, or both.

[0101] FIG. 19 is a graph comparing the calculation times in the decision process. In the graph shown in the figure, the vertical axis is the value of the objective function, and the horizontal axis is the number of generations. The calculation time of the determination process for optimizing the objective function is proportional to the number of generations. In addition, the solid line L1 indicates the transition of the value of the objective function when the occurrence probability of the first state "0" to the third state "2" in the initial population is adjusted using the occurrence probability table 153, and the dashed line L2 indicates the transition of the value of the objective function when the initial population is generated using random numbers. As shown in the figure, the number of generations T1 at which the initial population converges when the occurrence probability is adjusted and generated is less than half the number of generations T2 at which the initial population converges when the initial population is generated using random numbers. That is, in the information processing device 10 in this embodiment, by adjusting the occurrence probability and generating the initial population, the calculation time for optimizing the objective function (calculating the state of the shelving the imbalance rate) can be shortened compared to the case of generating the initial population using random numbers.

[0102] ===== Second embodiment ===== Next, a second embodiment of the present invention will be described. In the first embodiment, the user manually sets the occurrence probability table 153, but in this embodiment, the information processing device 10 uses an objective function to set the occurrence probability table 153, which is different from the first embodiment. The hardware configuration and functional configuration of the information processing device 10 are similar to those of the first embodiment, and therefore the description thereof will be omitted.

[0103] In the objective function shown in the above-mentioned formula (4), for example, a case where each weight X, Y, Z is X=0.5, Y=0.5, Z=0.01 will be specifically described. When the average unbalance rate f(0) of the power system 20 before installation (present) is 0.01 (average unbalance rate before installation is 1%) and the maximum unbalance rate g(0) is 0.01666 (maximum unbalance rate before installation is 1.666%), the value F(0) of the objective function before installation is 0.01333 as shown in the following formula (6) because the number of installations h(0)=0.

[0104] F(0) = X×f (0) + Y×g(0) = 0.01333…(6)

[0105] Since f(p) and g(p) can only take values ​​equal to or greater than 0, when h(p)>1.333, the objective function value F(p) exceeds the objective function value F(0) before the shelving, regardless of the values ​​of f(p) and g(p). That is, if the shelving number h(p)=1, there is a possibility that the objective function can be made smaller, but when h(p)>1.333, the objective function is always larger than before the shelving. Since the shelving number is an integer, it can be estimated that the shelving number that minimizes the objective function is 1 or less. Therefore, in this example, the optimal shelving calculation unit 15 sets the occurrence probability in the initial individuals so that there are many initial individuals with a shelving number of 1. Specifically, the optimal shelving calculation unit 15 uses the objective function to calculate the occurrence probability P(0) of the first state "0" by the following formula (7).

[0106] TIFF2024168159000002.tif9170

[0107] Here, the denominator (X×f(0)+Y×g(0)) is the objective function value F(0) before installation. The numerator Z is the weight of the number of installations in the objective function, and is the evaluation value per installation work (number of installations: 1). That is, the occurrence ratio P(0) of the first state "0" is determined based on the ratio between the objective function value F(0) when the decision variable is set to the current state of the transmission and distribution line 22 and the weight Z in the objective function of the number of installations. However, the optimal installation calculation unit 15 sets P(0)=1 when the value calculated by the above-mentioned formula (7) is 1 or more. When the evaluation value Z (numerator) per installation work is larger than the objective function value F(0) (denominator) before installation, installation causes the evaluation value to deteriorate compared to before installation (the objective function value becomes larger). For this reason, when the numerator Z>denominator (X×f(0)+Y×g(0)), the optimal shelving calculation unit 15 sets the probability of not shelving to 1 (the occurrence probability P(0) of the first state "0" is 1). On the other hand, when the numerator Z<denominator (X×f(0)+Y×g(0)), the optimal shelving calculation unit 15 determines the probability of not shelving according to the ratio of the numerator Z to the denominator (X×f(0)+Y×g(0)). Specifically, the more the numerator Z is smaller than the denominator (X×f(0)+Y×g(0)), the less the influence of the shelving number on the objective function, so the optimal shelving calculation unit 15 brings the probability of not shelving closer to 0 (the occurrence probability P(0) of the first state "0" is 0).

[0108] Moreover, the optimum rack calculation unit 15 calculates the occurrence probability P(1) of the second state “1” by the following formula (8).

[0109] TIFF2024168159000003.tif11170

[0110] Moreover, the optimum rack calculation unit 15 calculates the occurrence probability P(2) of the third state “2” by the following formula (9).

[0111] TIFF2024168159000004.tif11170

[0112] In the above example, when X=0.5, Y=0.5, and Z=0.01, the average unbalance rate before installation f(0)=0.01, and the maximum unbalance rate before installation g(0)=0.01666, the occurrence probabilities P(0) to P(2) of the first state "0" to the third state "2" are calculated using the following equations (10) to (12), respectively.

[0113] TIFF2024168159000005.tif9170

[0114] TIFF2024168159000006.tif11170

[0115] TIFF2024168159000007.tif11170

[0116] The optimal rack calculation unit 15 writes the calculated occurrence probabilities P(0) to P(2) of the first state "0" to the third state "2", respectively, in the occurrence probability table 153. The method of adjusting the initial population using the occurrence probability table 153 is the same as in the first embodiment, and therefore the description thereof will be omitted.

[0117] The above-mentioned formulas (7) to (9) show an example of a means for adjusting the occurrence probability based on the objective function, and the present invention is not limited to this, and any method may be used as long as it adjusts the occurrence probability of each of the first state "0" to the third state "2" in the initial population by utilizing the objective function, such as further performing arithmetic operations on the above-mentioned formulas (7) to (9). For example, as in the above-mentioned example, if the objective function value F(p) becomes greater than 1.333 and exceeds the objective function value F(0) before enumeration, it is only necessary to adjust the initial population so as to generate many initial individuals whose enumeration number is 1 (a positive integer equal to or less than 1.333).

[0118] =====Third embodiment===== Next, a third embodiment of the present invention will be described. In the first embodiment, the user manually sets the occurrence probability table 153, but in this embodiment, the information processing device 10 or another information processing device sets the occurrence probability table 153 using actual values ​​of the determination results (stack state) of the unbalance rate resolution process for another power system different from the power system 20, which is different from the first embodiment. The information processing device 10 in this embodiment stores in advance in the storage unit 105 an optimal stack calculation result table that stores actual values ​​of the determination results of the unbalance rate resolution process for a power system for which the objective function is optimized (actual values ​​with the objective function optimized). Other hardware configurations and functional configurations of the information processing device 10 are similar to those of the first embodiment, and therefore description thereof will be omitted.

[0119] FIG. 20 is a schematic diagram showing a data configuration and an example of data in the optimum rack calculation result performance table. As shown in the figure, the optimal rack calculation result performance table has the following items: system number, number of nodes, average unbalance rate (unit: "%)", maximum unbalance rate (unit: "%)", rack number, and number of racks ÷ number of nodes. The system number is identification information that identifies each power system. The number of nodes is the number of nodes N included in the power system. The average unbalance rate is the average unbalance rate in the determination result obtained by optimizing the objective function. The maximum unbalance rate is the maximum unbalance rate in the determination result obtained by optimizing the objective function. The number of racks is the number of racks in the determination result obtained by optimizing the objective function. The number of racks ÷ number of nodes is the value obtained by dividing the number of racks by the number of nodes. In other words, the number of racks ÷ number of nodes is a ratio determined by the number of nodes and the number of racks in the power system for which the objective function is optimized.

[0120] The ratio of the number of nodes included in each power system to the number of nodes determined by optimizing the objective function can be estimated from the actual results. For example, in the example shown in FIG. 20, the average value of "number of nodes divided by number of nodes" in each power system is "0.25". Therefore, in this example, it can be seen that the optimal solution (the objective function can be optimized) is obtained when the number of nodes is about one-fourth (0.25) of the number of nodes. In other words, the first state "0" in which three-fourths (0.75) of all nodes are not cross-connected is the optimal solution. Therefore, in this embodiment, the optimal cross-connect calculation unit 15 reads out "number of nodes divided by number of nodes" in each power system from the optimal cross-connect calculation result actual results table, and substitutes the read out (number of nodes divided by number of nodes) into the following formulas (13) to (15) to calculate the occurrence probabilities P(0) to P(2) of the first state "0" to the third state "2", respectively.

[0121] P(0) = 1 - (average value of (number of entries ÷ number of nodes)) (13)

[0122] P(1) = (average value of (number of nodes / number of nodes)) / 2 (14)

[0123] P(2) = (average value of (number of nodes / number of nodes)) / 2 (15)

[0124] For example, when the average value of (number of shelving units / number of nodes) is 0.25, P(0)=1-0.25=0.75, P(1)=0.25÷2=0.125, and P(2)=0.25÷2=0.125. The optimal shelving unit calculation unit 15 writes the calculated occurrence probabilities P(0) to P(2) of the first state "0" to the third state "2" into the occurrence probability table 153. The method of adjusting the initial population using the occurrence probability table 153 is the same as in the first embodiment, and therefore the description thereof will be omitted.

[0125] The above-mentioned equations (13) to (15) show an example of a means for adjusting the occurrence probability based on the actual value of the determination result of the unbalance rate calculation process in another power system, and the present invention is not limited to this. Any means may be used as long as it adjusts the occurrence probability of each of the first state "0" to the third state "2" in the initial population based on the actual value of the determination result that optimizes the objective function, such as by further performing arithmetic operations on the above-mentioned equations (13) to (15).

[0126] Furthermore, the occurrence probability table 153 may be generated at S601 described above, or during offline processing before the start of the imbalance calculation processing.

[0127] In addition, in this embodiment, an example has been described in which the information processing device 10 generates the occurrence probability table 153, but this is not limited to the above, and a device other than the information processing device 10 may generate the occurrence probability table 153 based on the optimal twist calculation result performance table and transmit it to the information processing device 10.

[0128] =====Fourth embodiment===== Next, a fourth embodiment of the present invention will be described. In the first to third embodiments, the load distribution of each node N is calculated based on the measurement value of the power meter SM. However, in this embodiment, the load distribution is calculated using the measurement value of the sensor-integrated switch 23, which is different from the first to third embodiments.

[0129] FIG. 21 is a configuration diagram showing an example of functions and databases included in an information processing device 10A according to this embodiment. In this figure, the same components as those of the information processing device 10 according to the first embodiment are given the same reference numerals, and the description thereof will be omitted. Also, since the hardware configuration of the information processing device 10A is the same as that of the first embodiment, the description thereof will be omitted. The information processing device 10A according to this embodiment includes a sensor switch measurement database 17 in addition to the configuration of the information processing device 10 according to the first embodiment. The sensor switch measurement database 17 is pre-stored in the memory unit 105 of the information processing device 10A.

[0130] The sensor switch measurement database 17 is a database that stores a sensor measurement value table indicating periodic measurement values ​​measured by the sensor-embedded switch 23. The measurement values ​​of the sensor-embedded switch 23 include at least the voltage and current at the installation point. The data stored in the sensor measurement value table may be stored in advance in the storage unit 105, or may be updated as needed by the CPU 101 acquiring the measurement values ​​from the sensor-embedded switch 23 via the communication line 30 and writing the acquired measurement values ​​to the sensor measurement value table.

[0131] FIG. 22 is a schematic diagram showing a data structure and an example of data in the sensor measurement value table. As shown in the figure, the sensor measurement value table has the following items: sensor-embedded switch ID, measurement date and time, voltage Vuv, voltage Vvw, voltage Vwu, current Iu0, current Iv0, current Iw0, power factor u, power factor v, and power factor w. The sensor-embedded switch ID is an accessory device ID that identifies the sensor-embedded switch 23. The measurement date and time is the date and time (year, month, day, hour, minute) when the measurement values ​​(voltage Vuv, voltage Vvw, voltage Vwu, current Iu0, current Iv0, current Iw0, power factor u, power factor v, and power factor w) were measured. The voltage Vuv is the voltage of the UV phase (unit: V (volts)). The voltage Vvw is the voltage of the VW phase. The voltage Vwu is the voltage of the WU phase. The current Iu0 is the current (unit: A (amperes)) flowing through the U phase. The current Iv0 is the current flowing through the V phase. The current Iw0 is the current flowing through the W phase. The power factor u is the power factor of the U phase. The power factor v is the power factor of the V phase. The power factor w is the power factor of the W phase. In the illustrated example, the measurement value table stores the measurement value of the sensor-embedded switch 23 every minute. That is, in this example, the sensor-embedded switch 23 measures the measurement value at a fixed cycle of every minute.

[0132] The data generating unit 14A estimates the load distribution at each node N based on the information stored in the system configuration database 11 and the sensor measurement value table, and generates input data based on the estimated load distribution. For example, the data generating unit 14A performs a three-phase power flow calculation by changing the average power consumption of each pole transformer TR (or the amount of power used by each consumer) so that it matches the measurement value of the sensor-integrated switch 23. As a result, the data generating unit 14A can estimate the load distribution at each node N.

[0133] In the present embodiment, the information processing device 10A estimates the load distribution at each node N using only the measurement value of the sensor-embedded switch 23, but the present invention is not limited thereto, and the load distribution at each node N may be estimated using both the measurement value of each watt-hour meter SM and the measurement value of the sensor-embedded switch 23. In general, the measurement period of the watt-hour meter SM (e.g., 30 minutes) is longer than the measurement period of the sensor-embedded switch 23 (e.g., 1 minute). Therefore, the information processing device 10A can estimate the load distribution of each node N in a period shorter than the measurement period of the watt-hour meter SM by using the measurement value of the sensor-embedded switch 23 in addition to the measurement value of each watt-hour meter SM. This allows the information processing device 10A to accurately estimate the load distribution of each node N in a time series. That is, the information processing device 10A can generate the load distribution of each node N in a finer time section.

[0134] =====Summary===== The information processing device 10 of the present invention has been described above. The information processing device 10 of the present invention calculates the voltage unbalance rate of each of the n nodes N based on a plurality of combinations of the states of the transmission / distribution lines 22 at each of the m nodes in the power system 20, which are obtained as any one of a first state in which the transmission / distribution lines 22 are not crossed, a second state in which the transmission / distribution lines 22 are crossed in a first pattern, or a third state in which the transmission / distribution lines 22 are crossed in a second pattern different from the first pattern, the power exchanged with the power system 20 at each of the n nodes N, and system configuration information indicating the configuration of the power system 20, and determines the state of the transmission / distribution lines 22 at each of the m nodes N by optimizing an objective function determined based on at least one of the average value of the voltage unbalance rate of each of the n nodes N or the maximum value of the voltage unbalance rate of each of the n nodes N, with the state of the transmission / distribution lines 22 at each of the m nodes N as a decision variable.

[0135] With this configuration, the information processing device 10 according to the present invention can accurately determine the state of the twisted wires that can improve the voltage unbalance rate of the power transmission / distribution line 22.

[0136] In addition, when determining the state of the power transmission / distribution line 22 at each of the m nodes N, the information processing device 10 according to the present invention generates initial values ​​of decision variables such that the first state occurs with a probability of occurrence different from the respective occurrence probabilities of the second state and the third state.

[0137] With this configuration, the information processing device 10 according to the present invention can set an initial value with a high evaluation value of the objective function. Therefore, compared to setting the initial value using random numbers, the calculation time for optimizing the objective function can be shortened. In other words, the state of the power transmission / distribution line 22 at each of the m nodes N can be determined in a shorter time.

[0138] The objective function is a function determined based on at least one of the average value of the voltage unbalance rate of each of the n nodes or the maximum value of the voltage unbalance rate of each of the n nodes and the number of nodes crossing the three-phase transmission / distribution line, and the information processing device 10 according to the present invention calculates the occurrence probability of each of the first state, the second state, and the third state using the objective function. More specifically, the information processing device 10 calculates the occurrence probability of each of the first state, the second state, and the third state based on the ratio between the value of the objective function when the decision variable is set to the current state of the transmission / distribution line 22 and the weight in the objective function of the number of nodes crossed.

[0139] With this configuration, the information processing device 10 according to the present invention can accurately calculate the occurrence probability of each of the first state, the second state, and the third state, which have relatively high evaluation values ​​of the objective function. This makes it possible to set an initial value with a high evaluation value of the objective function, and therefore to determine the state of the power transmission / distribution line 22 at each of the m nodes N in a shorter time.

[0140] In addition, the information processing device 10 according to the present invention generates initial values ​​with the occurrence probability of each of the first state, the second state, and the third state calculated based on a ratio determined by the number of nodes and the number of racks in the power system for which the objective function is optimized.

[0141] With this configuration, the information processing device 10 according to the present invention can accurately calculate the occurrence probability of each of the first state, the second state, and the third state, which have relatively high evaluation values ​​of the objective function. This makes it possible to set an initial value with a high evaluation value of the objective function, and therefore to determine the state of the power transmission / distribution line 22 at each of the m nodes N in a shorter time.

[0142] Moreover, the information processing device 10 according to the present invention generates an initial value in which the occurrence probability of the first state is greater than the occurrence probability of each of the second state and the third state.

[0143] With this configuration, the information processing device 10 according to the present invention can set an initial value that includes more nodes N in the first state that are not crossed among the m nodes N than the crossed nodes N. Since the objective function is determined based on the number of nodes N crossing the power transmission / distribution line 22, it is possible to set an initial value with a relatively high evaluation value of the objective function by setting an initial value that includes many nodes N that are not crossed. This makes it possible to determine the state of the power transmission / distribution line 22 at each of the m nodes N in a shorter time.

[0144] Moreover, the information processing device 10 according to the present invention optimizes an objective function by a combinatorial optimization method using metaheuristics, and determines the state of the power transmission / distribution line 22 at each of the m nodes N.

[0145] With this configuration, it is possible to reduce calculation costs and efficiently and accurately determine the state of the twisted rack that reduces the unbalance factor.

[0146] In addition, the information processing device 10 according to the present invention calculates the power exchanged with the power system 20 at each of the n nodes N using at least one of the measurement values ​​of a sensor-embedded switch 23 that measures the voltage and current at a predetermined position in the power system 20, or the measurement values ​​of a power meter SM connected to each of the n nodes N.

[0147] With this configuration, the information processing device 10 according to the present invention can generate a load distribution that reflects the actual load fluctuation or power generation fluctuation at each node N, using the measurement values ​​of the sensor-integrated switch 23 or each watthour meter SM.

[0148] The above-mentioned embodiment is for the purpose of facilitating understanding of the present invention, and is not intended to limit the present invention. Furthermore, the present invention can be modified or improved without departing from the spirit of the present invention, and it goes without saying that the present invention includes equivalents thereof.

[0149] For example, each data stored in the above-mentioned system configuration database 11, smart meter information database 12, or sensor switch measurement database 17 may be read by the CPU 101 via the recording medium drive unit 106 as data stored in the recording medium 6, or may be obtained from an external computer or server via the network connection unit 107.

[0150] In addition, various data generated by each function of the information processing device 10, 10A, such as the above-mentioned transformer power data, the unbalance rate calculation result table for each rack, or the objective function calculation result table, may be stored in the memory unit 105 by the CPU 101, may be written to the recording medium 6 via the recording medium driving unit 106, may be stored as a structure on the memory 102, or may be output to the output unit 104 together with the calculated decision result. [Explanation of symbols]

[0151] 10, 10A Information processing device 11 Power System Configuration Database 12 Smart Meter Information Database 13 Transformer power calculation section 14,14A Data Generation Section 15 Optimal Laying Calculation Section 16 Result output section 17 Sensor switch measurement database 101 CPU 102 Memory 103 Input section 104 Output section 105 Storage section 106 Recording medium drive unit 107 Network connection 20 Power system 21 Transformer 22 Transmission and distribution lines 23 Sensor-integrated switch 30 Communication lines N-node SM electricity meter TR Pole Transformer

Claims

1. a calculation unit that calculates a voltage unbalance rate of each of m nodes in a power system based on a plurality of combinations of states of three-phase transmission / distribution lines at each of the n nodes in the power system, the combination being a first state in which the lines are not crossed, a second state in which the lines are crossed in a first pattern, or a third state in which the lines are crossed in a second pattern different from the first pattern, power exchanged with the power system at each of the n nodes, and system configuration information indicating a configuration of the power system; a decision unit that determines a state of the three-phase transmission / distribution line at each of the m nodes, the decision unit optimizing an objective function that is determined based on a voltage unbalance rate of each of the n nodes, using a state of the three-phase transmission / distribution line at each of the m nodes as a decision variable; Equipped with The determination unit is generating initial values ​​of the decision variables such that the first state occurs with a probability different from the respective probabilities of occurrence of the second state and the third state; Information processing device.

2. 2. The information processing device according to claim 1, the objective function is a function determined based on at least one of an average value of a voltage unbalance rate of each of the n nodes or a maximum value of a voltage unbalance rate of each of the n nodes, and a number of nodes spanning the three-phase transmission and distribution line; The determination unit is Using the objective function, the occurrence probabilities of the first state, the second state, and the third state are calculated. Information processing device.

3. 3. The information processing device according to claim 2, The determination unit is Calculating the occurrence probability of each of the first state, the second state, and the third state based on a ratio between a value of the objective function when the decision variable is set to a current state of the three-phase transmission / distribution line and a weight in the objective function of the number of nodes to be crossed. Information processing device.

4. 2. The information processing device according to claim 1, The determination unit is The initial value is generated based on the occurrence probability of each of the first state, the second state, and the third state calculated based on a ratio determined by the number of nodes and the number of racks of the power system for which the objective function is optimized. Information processing device.

5. 5. The information processing device according to claim 1, The determination unit is generating the initial value such that the occurrence probability of the first state is greater than the occurrence probability of each of the second state and the third state; Information processing device.

6. 2. The information processing device according to claim 1, The determination unit is The objective function is optimized by a combinatorial optimization method using metaheuristics, and the state of the three-phase transmission / distribution line at each of the m nodes is determined. Information processing device.

7. 2. The information processing device according to claim 1, The calculation unit is Calculating power exchanged with the power system at each of the n nodes using at least one of the measurement values ​​of a sensor that measures voltage and current at a predetermined position in the power system and the measurement values ​​of a smart meter connected to each of the n nodes. Information processing device.

8. 2. The information processing device according to claim 1, The objective function is a function determined based on at least one of an average value of the voltage unbalance rate of each of the n nodes or a maximum value of the voltage unbalance rate of each of the n nodes. Information processing device.

9. An information processing device, a calculation step of calculating a voltage unbalance rate of each of m nodes in the power system based on a plurality of combinations of states of three-phase transmission / distribution lines at each of the m nodes in the power system, the combination being a first state in which the lines are not crossed, a second state in which the lines are crossed in a first pattern, or a third state in which the lines are crossed in a second pattern different from the first pattern, power exchanged with the power system at each of the n nodes, and system configuration information indicating a configuration of the power system; a determination step of determining a state of the three-phase transmission / distribution line at each of the m nodes, the determination step optimizing an objective function determined based on a voltage unbalance rate of each of the n nodes, with the state of the three-phase transmission / distribution line at each of the m nodes being a decision variable; Including, In the determining step, generating initial values ​​of the decision variables such that the first state occurs with a probability different from the respective probabilities of occurrence of the second state and the third state; Information processing methods.

10. On the computer, a calculation process for calculating a voltage unbalance rate of each of m nodes in the power system based on a plurality of combinations of states of three-phase transmission / distribution lines at each of the m nodes in the power system, the combination being a first state in which the lines are not crossed, a second state in which the lines are crossed in a first pattern, or a third state in which the lines are crossed in a second pattern different from the first pattern, power exchanged with the power system at each of the n nodes, and system configuration information indicating a configuration of the power system; a determination process for determining a state of the three-phase transmission / distribution line at each of the m nodes, the determination process optimizing an objective function determined based on a voltage unbalance rate of each of the n nodes, with the state of the three-phase transmission / distribution line at each of the m nodes being a decision variable; Run the command, In the determination process, generating initial values ​​of the decision variables such that the first state occurs with a probability different from the respective probabilities of occurrence of the second state and the third state; program.

Citation Information

Patent Citations

  • Voltage unbalance suppression support method, and voltage unbalance suppression support device

    JP2016182008A

  • Information processing device, information processing method, and program

    JP2024063461A

  • Device for determining cause of occurrence of voltage imbalance and method for determining cause of occurrence of voltage imbalance

    WO2015072038A1

  • Transposition position determining device and transposition position determining method

    JP2015126679A