Power accommodation management system, and power accommodation management method

The power interchange management system optimizes the use of surplus renewable energy by integrating electric vehicle charging and power generation systems, enhancing self-consumption and reducing emissions through intelligent demand forecasting and vehicle dispatch strategies.

JP2024170255APending Publication Date: 2024-12-06HITACHI LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023087316
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-26
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

Existing systems face challenges in maximizing the self-consumption of surplus electricity generated by renewable sources, particularly in logistics companies with mixed fleets of internal combustion engine and electric vehicles, due to stringent demand and supply matching requirements and charging restrictions, leading to inefficiencies and penalties.

Method used

A power interchange management system that integrates electric vehicle charging and private power generation devices across multiple bases, utilizing machine learning for demand forecasting and optimizing vehicle dispatch to aggregate and prioritize surplus power usage, ensuring efficient utilization and reduction of CO2 emissions.

Benefits of technology

Enhances the self-consumption of surplus electricity, extends the range of electric vehicles, and reduces CO2 emissions by strategically managing power distribution and vehicle dispatch to align with demand patterns and contractual limits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024170255000001_ABST
    Figure 2024170255000001_ABST
Patent Text Reader

Abstract

To provide a power accommodation management system and a power accommodation management method for increasing a private consumption amount of surplus power of a business operator.SOLUTION: A power accommodation management system 1 includes an EV vehicle allocation / charging plan system 42 for managing a charger 43 of an EV vehicle 44 and a private power generation device, and planning charging and vehicle allocation of an electric vehicle, an EV vehicle allocation / charging plan system 46 for managing the charger 43 of the electric vehicle, and planning the charging and the vehicle allocation of the electric vehicle, and an accommodation plan unit 21 for aggregating surplus power from the EV vehicle allocation / charging plan system 42 to be accommodation possible power, and providing the EV vehicle allocation / charging plan system 46 with the accommodation possible power according to a predetermined priority.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an electric power interchange management system and an electric power interchange management method. [Background technology]

[0002] In recent years, major logistics companies have been promoting the introduction of renewable energy (PV: photovoltaic power generation) by utilizing the vast rooftops of their own warehouses. They are also considering the use of a self-consignment system that allows electricity to be shared between their own bases. At the same time, the use of electric vehicles (EVs) for last-mile trucks is also being promoted, and a mixture of internal combustion engine trucks and EV trucks are being operated.

[0003] Patent Document 1 describes a power transmission control method executed by a terminal connected to a communication network. This method includes a process of individually predicting the amount of electricity that each consumer using a power interchange service will receive from the power grid, and a process of controlling the amount of electricity generated by each consumer's private power generation facility and transmitted to the power grid in accordance with the predicted amount of electricity. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Patent No. 7202928 Summary of the Invention [Problem to be solved by the invention]

[0005] When a certain base has a warehouse, there may be cases where surplus electricity is generated in relation to the PV capacity that can be installed. In such a case, it is possible to transmit this surplus electricity to other bases of the company through the power transmission and distribution network by self-consignment. This will reduce the amount of electricity purchased from the power company and reduce CO2 emissions. In addition, surplus electricity that could not be self-consumed at one base can be used efficiently at other bases.

[0006] When using self-dispatch, the system of "same time and same amount of planned value" must be observed. With "same time and same amount of planned value", electricity demand and supply must be forecast in 30-minute increments and planned values ​​must be reported. In addition, self-dispatch cannot be for the purpose of selling electricity, and there must be a close relationship between the generator and the supply destination.

[0007] Self-dispatch of solar power generation makes it possible to use renewable energy even in places where it is difficult to secure rooftop or open space. However, self-dispatch requires forecasting electricity demand and generation in 30-minute increments, and matching actual supply and demand with planned values ​​to avoid any discrepancy. In the unlikely event that a discrepancy occurs between the planned and actual values, penalties will be imposed, so care must be taken.

[0008] In addition, simply forwarding surplus electricity from one base to another base is not linked to EV charging plans, and surplus electricity cannot be used to its full potential.In addition, the conversion of trucks to EVs (Electric Vehicles) at present can only be introduced in a limited way due to charging restrictions imposed by contracted power. Therefore, an object of the present invention is to increase the amount of surplus electricity consumed by businesses. [Means for solving the problem]

[0009] In order to solve the above-mentioned problems, the power interchange management system of the present invention is characterized by comprising: a first EV dispatch and charging planning system that manages electric vehicle charging equipment and private power generation equipment at a first location and plans charging and dispatch of the electric vehicles; a second EV dispatch and charging planning system that manages electric vehicle charging equipment at a second location and plans charging and dispatch of the electric vehicles; and an interchange planning unit that aggregates surplus power from each of the first EV dispatch and charging planning systems to make it interchangeable power and provides the interchangeable power to each of the second EV dispatch and charging planning systems in accordance with a predetermined priority order.

[0010] The power interchange management method of the present invention is characterized by comprising the steps of: a first EV dispatching and charging planning system managing electric vehicle charging equipment and private power generation equipment at a first location planning charging and dispatch of the electric vehicles; a second EV dispatching and charging planning system managing electric vehicle charging equipment at a second location planning charging and dispatch of the electric vehicles; an interchange planning unit aggregating surplus power from each of the first EV dispatching and charging planning systems to make it interchangeable power; and a step of providing the interchangeable power to each of the second EV dispatching and charging planning systems in accordance with a predetermined priority order. Other means will be described in the description of the embodiment of the invention. Effect of the Invention

[0011] According to the present invention, it is possible to increase the amount of surplus electricity consumed by a business operator. [Brief description of the drawings]

[0012] [Figure 1] 1 is an overall configuration diagram of a power interchange management system according to an embodiment of the present invention. [Figure 2A] This is a diagram of the EV dispatch and charging planning system. [Figure 2B] This is a diagram of the EV dispatch and charging planning system. [Diagram 3] FIG. 2 is a diagram illustrating an example of a sequence diagram executed by the power interchange management system. [Figure 4A] 1 is a graph showing the total power demand and charging amount at a base. [Figure 4B] 1 is a graph showing predicted solar power generation data for a site. [Figure 4C] 1 is a graph showing the final amount of purchased electricity and the amount of surplus electricity. [Figure 5A] 1 is a graph showing the total power demand and charging amount at a base. [Figure 5B] 1 is a graph of surplus power. [Figure 5C] 13 is a graph showing the results of subtracting surplus power from the total power demand and charging amount of a base. [Figure 6] This is a table showing the number of electric trucks owned at each location. [Figure 7] This is a table showing the total battery capacity of EV trucks at each location. [Figure 8] This is a table of the average total delivery distance for each base. [Figure 9] This is a table of average ICE fuel consumption at each location. [Figure 10] 13 is a table showing the average available capacity of the contracted power at each location. [Figure 11] This is a table showing the renewable energy electricity ratio for each site. [Figure 12] This is a table showing the average total EV charging volume per day at each location. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. FIG. 1 is a diagram showing the overall configuration of a power interchange management system 1 according to this embodiment. The power interchange management system 1 includes an interchange plan server 2, an EV dispatch and charging plan system 42 provided at a base 4a, etc., and an EV dispatch and charging plan system 46 provided at bases 5a and 5b. Here, the base 4a, etc., is equipped with a solar power generation panel 41, which is a private power generation device, and a charging device 43 for an EV 44, and is a first base where surplus power may be generated. The bases 5a, 5b, etc. are equipped with a charging device 43 for an EV 44, but are not equipped with a private power generation device, and are second bases where surplus power is not generated. Note that although three bases are illustrated here, in reality there are multiple first bases equipped with the solar power generation panel 41 and multiple second bases not equipped with the solar power generation panel 41.

[0014] The power interchange management system 1 aims to increase the in-house consumption of surplus power and reduce CO2 emissions by extending the driving range of EVs 44 by formulating an interchange plan linked to the EV dispatch plan when surplus power generated at base 4a or the like is interchanged with other bases 5a, 5b. For example, CO2 emissions can be reduced by assigning EVs 44 to routes with long delivery distances and engine vehicles 45 to routes with short delivery distances. Engine vehicles 45 are sometimes called ICEs (Internal Combustion Engines).

[0015] The interchange planning server 2 includes an interchange planning unit 21 that manages the amount of surplus power (total amount) at base 4a and other locations that have introduced renewable energy power generation devices such as solar power generation panels 41. The interchange planning unit 21 calculates and manages the amount of surplus power to be interchanged from the amount of surplus power at base 4a to bases 5a, 5b and other locations that do not generate surplus power. The interchange planning unit 21 sets priorities for bases 5a, 5b and other locations that do not generate surplus power, and notifies bases 5a, 5b and other locations of the amount of available surplus power in accordance with the priorities.

[0016] The EV dispatch and charging planning system 42 predicts the amount of power generated by the solar power generation panel 41 at the first base, and creates a dispatch plan and an EV charging plan for the EV vehicles 44 based on delivery route conditions, etc. There are cases where engine vehicles 45 and EV vehicles 44 are mixed, such as at the base 4a. The EV dispatch and charging planning system 42 creates a dispatch plan for which vehicles are to be assigned to which delivery route. When creating an EV charging plan, the EV dispatch and charging planning system 42 creates a charging plan so that the power consumption of the base does not exceed the contracted power (upper limit). This EV dispatch and charging planning system 42 functions as a first EV dispatch and charging planning system that manages the charging equipment and private power generation equipment of the electric vehicles and plans the charging and dispatch of the electric vehicles. The private power generation equipment installed at the base is not limited to renewable energy power generation equipment such as the solar power generation panel 41 and wind power generation equipment, and may be any type of power generation equipment.

[0017] The EV dispatch and charging planning system 46 receives the available surplus power from the interchange planning server 2, and creates a dispatch plan and an EV charging plan for the EV vehicles 44 based on the delivery route conditions of the second base. There are cases where engine vehicles 45 and EV vehicles 44 are mixed, such as at bases 5a and 5b. The EV dispatch and charging planning system 46 creates a dispatch plan for which vehicles are to be assigned to which delivery route. When creating an EV charging plan, the EV dispatch and charging planning system 46 creates a charging plan so that the power consumption of the base does not exceed the contracted power (upper limit). The EV dispatch and charging planning system 46 manages the charging equipment for electric vehicles at the second base, and functions as a second EV dispatch and charging planning system that plans the charging and dispatch of these electric vehicles. The interchange planning unit 21 then aggregates surplus power from each EV dispatch and charging planning system 42 to make it interchangeable power, and provides the interchangeable power to each EV dispatch and charging planning system 46 in accordance with a predetermined priority order.

[0018] FIG. 2A is a configuration diagram of the EV dispatch and charging planning system 42. The EV dispatch and charging planning system 42 includes a power generation prediction unit 421, a power demand prediction unit 422, a vehicle dispatch plan creation unit 423, an EV dispatch and charging plan creation unit 424, and a surplus power notification unit 425. The power generation prediction unit 421 predicts the power generation of the solar power generation panel 41. The power demand prediction unit 422 predicts the power demand including the charging power of the EV 44 at this base.

[0019] The vehicle allocation plan making unit 423 makes an allocation plan for which EV 44 should be allocated to which delivery route based on information about the delivery route, such as when and where to deliver. The EV allocation and charging plan making unit 424 makes an allocation plan and a charging plan for the EV 44 so as to satisfy the delivery information. The surplus power notification unit 425 notifies the interchange plan unit 21 of the surplus power obtained by subtracting the power demand at this base from the power generated by the solar power generation panel 41.

[0020] FIG. 2B is a configuration diagram of the EV dispatch and charging planning system 46. The EV dispatch / charging planning system 46 includes a surplus power receiving unit 461, a power demand forecasting unit 462, a vehicle dispatch planning unit 463, and a surplus power notifying unit 465. The surplus power receiving unit 461 receives surplus power. The power demand forecasting unit 462 forecasts power demand, including charging power for the EV 44 at this base.

[0021] The vehicle allocation plan creation unit 463 creates a vehicle allocation plan for allocating which EV 44 to which delivery route based on information regarding the delivery route, such as when and where to deliver. The EV allocation / charging plan creation unit 464 creates a vehicle allocation plan and a charging plan for the EV 44 so as to satisfy the delivery information. The surplus power notification unit 465 notifies the interchange plan unit 21 of new surplus power obtained by subtracting the power demand from the surplus power provided by the interchange plan unit 21.

[0022] FIG. 3 is a diagram showing an example of a sequence diagram executed by the power interchange management system 1. As shown in FIG. The power interchange management system 1 periodically executes this processing sequence to create a plan. The execution interval of this processing sequence is, for example, once every few hours to once a day.

[0023] The power generation prediction unit 421 predicts the amount of solar power generation in the future (for one day to several days, hourly, etc.) using a machine learning function or the like based on information such as the past power demand history, season, day of the week, time, and weather (step S10).

[0024] The power demand prediction unit 422 predicts the future (one day to several days, hourly, etc.) power demand of the base station by machine learning function based on information such as past power demand history, season, day of the week, time, weather, etc. (Step S11). The prediction function itself may be realized by a separate system and is not a necessary component of this patent.

[0025] The vehicle allocation plan making unit 423 acquires information about the delivery route, such as what time and where to deliver (step S12). Then, the vehicle allocation plan making unit 423 makes a vehicle allocation plan indicating which electric vehicle 44 should be assigned to which delivery route (step S13). As shown in FIG. 1, there are cases where engine vehicles 45 and electric vehicles 44 are mixed at a base. Even in this case, the vehicle allocation plan making unit 423 makes a vehicle allocation plan indicating which vehicle should be assigned to which delivery route.

[0026] Next, the EV dispatch / charging plan creation unit 424 creates a dispatch plan and a charging plan for the EVs 44 so as to satisfy the delivery information. The EV dispatch / charging plan creation unit 424 further creates a charging plan based on the constraints of equation (1).

number

[0027] The final amount of purchased power and the amount of surplus power at the site 4a where the surplus power is generated are shown in FIG. 4C and are calculated by the formula (2).

number

[0028] Thereafter, the surplus power notification unit 425 notifies the amount of surplus power to the interchange plan unit 21 (step S14). The surplus power notification units 425 of the other bases also notify the amount of surplus power to the interchange plan unit 21 (step S15). The interchange planning unit 21 repeats the process of receiving the amount of surplus power a number of times equal to the number of bases that have power generation facilities such as solar power generation and wind power generation and are capable of generating surplus power, and then calculates the total amount of surplus power (step S16).

[0029] The EV dispatch and charging planning system 42 determines the amount of purchased electricity based on the contracted electricity E n The EV truck charging plan is created so that the EV truck charging schedule does not exceed the contracted power E. nPlans are created by solving constraint satisfaction problems, which require satisfying the constraint that the time required to complete a task must not be exceeded, and optimization problems.

[0030] The power exchange planning unit 21 utilizes the total surplus power calculated in step S16 at the bases 5a, 5b, etc., where no surplus power is generated. The power exchange planning unit 21 checks the priority of the power exchange destinations (step S20), and notifies each base of the amount of surplus power according to the priority (step S21).

[0031] The power demand forecasting unit 462 forecasts the future (one day to several days, hourly, etc.) base power demand using a machine learning function or the like based on information such as past power demand history, season, day of the week, time, and weather (step S22).

[0032] The vehicle allocation plan making unit 463 acquires information about the delivery route, such as when and where to deliver the goods (step S23).Then, the vehicle allocation plan making unit 463 makes a vehicle allocation plan, which specifies which electric vehicle 44 should be assigned to which delivery route.

[0033] Next, the EV dispatch / charging plan creation unit 464 creates a dispatch plan and a charging plan for the EVs 44 so as to satisfy the delivery information (step S24). The EV dispatch / charging plan creation unit 464 further creates a charging plan based on the constraints of formula (1). Then, the surplus power notification unit 465 notifies the remaining surplus power amount to the interchange plan unit 21 (step S25).

[0034] The interchange planning unit 21 repeats the process of providing the new surplus power, obtained by subtracting the excess demand of the EV dispatch and charging planning system 46 of a base with a certain priority, to the EV dispatch and charging planning system 46 of the base with the next priority. The interchange planning unit 21 repeats this process until the creation of EV dispatch plans and EV charging plans is completed for all bases 5a, 5b, etc. where no surplus power is generated. If there is little or no surplus power, the bases where no surplus power is generated will create an EV dispatch plan without interchange power.

[0035] Figures 4A to 4C show an overview of EV dispatch and charging planning at locations where surplus power is generated. The final amount of purchased power or the amount of surplus power at the site 4a where the surplus power is generated is calculated based on the power demand E d and the charge level of the EV car E c From the sum of these, the solar power generation capacity of the site, E p It is calculated by subtracting

[0036] In the EV dispatch and charging planning system 42, the amount of purchased electricity is the contracted electricity E n The EV truck charging plan is created so that the EV truck charging schedule does not exceed the contracted power E. n Plans are devised by solving constraint satisfaction problems and optimization problems that satisfy the constraint that the time required to complete a task must not be exceeded.

[0037] FIG. 4A is a graph of the power demand and the total charging amount of a site. The horizontal axis of the graph indicates time. The vertical axis of the graph indicates the power demand E d and charge amount E c The total represents the sum of the above.

[0038] FIG. 4B is a graph of the predicted solar power generation data for the site. The horizontal axis of the graph indicates time. The vertical axis of the graph indicates the amount of solar power generation E p The predicted values ​​are shown.

[0039] FIG. 4C is a graph of the final amount of purchased energy or the amount of surplus energy. The horizontal axis of the graph indicates time. The vertical axis of the graph indicates the final amount of purchased energy or the amount of surplus energy. Note that when the vertical axis of the graph is positive, it indicates the amount of purchased energy, and when the vertical axis of the graph is negative, it indicates the amount of surplus energy. The final amount of purchased energy or the amount of surplus energy is calculated by the above-mentioned formula (2).

[0040] Figures 5A to 5C show an overview of EV dispatch and charging planning at bases where surplus power is not generated.

[0041] The final amount of purchased power or the amount of surplus power at the bases 5a and 5b where no surplus power is generated is expressed by formula (3).

number

[0042] In the EV dispatch and charging planning system 46, the amount of purchased electricity is the contracted electricity E n The EV truck charging plan is created so that the EV truck charging time does not exceed the contracted power. The EV dispatch and charging plan system 46 creates the plan by solving a constraint satisfaction problem or an optimization problem that satisfies the constraint condition that the delivery route is satisfied and the purchased power does not exceed the contracted power.

[0043] FIG. 5A is a graph of the power demand and the total amount of charging at the site. The horizontal axis of the graph indicates time. The vertical axis of the graph indicates the power demand E d and charge amount E c The total represents the sum of the above.

[0044] 5B is a graph of surplus power. The horizontal axis of the graph represents time. The vertical axis of the graph represents the amount of surplus power E0.

[0045] FIG. 5C is a graph showing the result of subtracting surplus power from the total of the power demand and charging amount of the site. The horizontal axis of the graph shows time. The vertical axis of the graph shows the result of subtracting the current surplus power amount E0 from the total of the power demand and charging amount of the site. Note that when the vertical axis of the graph is positive, it shows the amount of purchased power, and when the vertical axis of the graph is negative, it shows the new surplus power amount E1.

[0046] In step S20, the interchange planning unit 21 determines the priority order of each base as an interchange destination based on the parameters of each base. Examples of parameters for determining the priority order are shown in the following Figs. 6 to 12.

[0047] Figure 6 is a table showing the number of electric trucks owned at each location. The interchange planning unit 21 determines the priority order in descending order of the number of EV vehicles managed by the EV dispatch and charging planning system 46, based on the idea that the more EV trucks there are at a base, the more power consumption there is and the more power interchange is required.

[0048] Figure 7 is a table showing the total battery capacity of EV trucks at each location. The interchange planning unit 21 determines the priority of the EV trucks managed by the EV dispatch and charging planning system 46 in order of the total battery capacity, based on the idea that the larger the total battery capacity of the EV trucks at the base station, the more power they consume and the more power interchange is required.

[0049] Figure 8 is a table showing the average total delivery distance for each base station. The average total delivery distance of a base refers to the average sum of the distances (delivery distances) traveled by each truck at that base to deliver goods. The interchange planning unit 21 determines the priority in descending order of the average total delivery distances managed by the EV dispatch and charging planning system 46, based on the idea that the longer the average total delivery distance of a base per day, the more power consumed by EV trucks will be, and the more power interchange will be required.

[0050] Figure 9 is a table showing average ICE fuel efficiency at each location. The interchange planning unit 21 determines the priority order of the average fuel efficiency of the engine vehicles managed by the EV dispatch and charging planning system 46 in ascending order based on the idea that the lower the average fuel efficiency of the ICE (internal combustion engine vehicle) at the base, the higher the CO2 emissions, and the more EV trucks will be needed to drive, which will increase power consumption.

[0051] FIG. 10 is a table showing the average available capacity of the contracted power for each base station. The interchange planning unit 21 determines the priority in ascending order of the average available capacity value for the contracted power managed by the EV dispatch and charging planning system 46, based on the idea that the smaller the average available capacity of the contracted power of a base, the higher the risk of exceeding the contracted power and the greater the need for power interchange.

[0052] Figure 11 is a table showing the renewable energy electricity ratios at each site. The interchange planning unit 21 determines the priority order of the locations managed by the EV dispatch and charging planning system 46 in ascending order of the renewable energy electricity ratio value, based on the idea that the lower the renewable energy electricity ratio of the location, the more necessary the interchange of surplus renewable energy electricity is to reduce CO2 emissions. r is calculated using the following formula (4).

number

[0053] The amount of purchased renewable energy electricity refers to the amount of renewable energy electricity purchased from a retail electricity supplier.

[0054] Figure 12 is a table showing the average total EV charging amount per day at each location. The interchange planning unit 21 determines the priority order in descending order of the average average total EV charging amount, based on the idea that the higher the average total EV charging amount per day, the greater the power consumption at the base. In addition, the interchange planning unit 21 may determine the priority order of each EV dispatch and charging planning system 46 based on the CO2 intensity of the power plan contracted at the second base managed by this EV dispatch and charging planning system 46. In addition, the interchange planning unit 21 is not limited to each of the above parameters, and may determine the priority based on an evaluation value obtained by selecting and weighting any of these multiple parameters, and is not limited to this.

[0055] (Modification) The present invention is not limited to the above-described embodiment, and includes various modified examples. For example, the above-described embodiment has been described in detail to clearly explain the present invention, and is not necessarily limited to those having all of the configurations described. It is possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. In addition, it is also possible to add, delete, or replace a part of the configuration of each embodiment with another configuration.

[0056] The above configurations, functions, processing units, processing means, etc. may be realized in part or in whole by hardware such as an integrated circuit. The above configurations, functions, etc. may be realized by software by a processor interpreting and executing a program that realizes each function. Information such as the program, table, file, etc. that realizes each function can be stored in a recording device such as a memory, a hard disk, or an SSD (Solid State Drive), or a recording medium such as a flash memory card or a DVD (Digital Versatile Disk).

[0057] In each embodiment, the control lines and information lines are those that are considered necessary for the explanation, and not all control lines and information lines in the product are necessarily shown. In reality, it may be considered that almost all components are connected to each other. [Explanation of symbols]

[0058] 1. Power interchange management system 2. Consumption Planning Server 21 Conversion Planning Department 4a base (first base) 5a,5b base (second base) 41 Photovoltaic panels 42 EV dispatch and charging planning system (The first EV dispatch and charging planning system) 421 Power Generation Forecasting Department 422 Electricity Demand Forecasting Department 423 Vehicle Allocation Planning Department 424 EV Dispatch and Charging Planning Department 425 Surplus Power Notification Unit 43 Charging device 44 Electric vehicles 45 Engine Vehicle 46 EV dispatch and charging planning system (Second EV dispatch and charging planning system) 461 Surplus Power Receiver 462 Electricity Demand Forecasting Department 463 Vehicle Allocation Planning Department 464 EV Dispatch and Charging Planning Department 465 Surplus Power Notification Unit

Claims

1. a first EV dispatch and charging planning system that manages a charging device and a private power generation device for an electric vehicle at a first base and plans charging and dispatch of the electric vehicle; a second EV dispatch and charging planning system that manages an electric vehicle charging device at a second base and plans charging and dispatch of the electric vehicle; an interchange planning unit that aggregates surplus power from each of the first EV dispatching and charging planning systems to generate interchangeable power, and provides the interchangeable power to each of the second EV dispatching and charging planning systems in accordance with a predetermined priority order; A power interchange management system comprising:

2. the interchange planning unit repeats a process of providing new surplus power obtained by subtracting the excess demand at the second base managed by the second EV dispatching and charging planning system having a certain priority, to the second base managed by the second EV dispatching and charging planning system having a next priority; The power interchange management system according to claim 1 .

3. The second EV dispatch and charging planning system includes a surplus power notification unit that notifies the interchange planning unit of new surplus power obtained by subtracting power demand from the surplus power provided from the interchange planning unit. The power interchange management system according to claim 1 .

4. The first EV vehicle dispatch and charging planning system comprises: A power generation prediction unit that predicts the power generation power of the private power generation device; an electric power demand prediction unit that predicts electric power demand including charging power of the electric vehicle; and a surplus power notification unit that notifies the interchange planning unit of surplus power obtained by subtracting the power demand from the generated power. The power interchange management system according to claim 1 .

5. The interchange planning unit determines a priority order of each of the second EV dispatching and charging planning systems based on the number of electric vehicles at a second base managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

6. The interchange planning unit determines the priority order of each of the second EV dispatching and charging planning systems based on the total storage battery capacity of electric vehicles at the second bases managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

7. The interchange planning unit determines the priority of each of the second EV dispatching and charging planning systems based on an average total delivery distance of the second bases managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

8. The interchange planning unit determines the priority order of each of the second EV dispatching and charging planning systems based on the average fuel efficiency of engine vehicles at the second bases managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

9. The interchange planning unit determines a priority order of each of the second EV dispatching and charging planning systems based on an average available capacity with respect to a contracted power of a second base managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

10. The interchange planning unit determines a priority order of each of the second EV dispatching and charging planning systems based on a renewable energy power ratio of a second base managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

11. The interchange planning unit determines a priority order of each of the second EV dispatching and charging planning systems based on an average value of a total EV charging amount at a second base managed by the second EV dispatching and charging planning system. The power interchange management system according to claim 3 .

12. The interchange planning unit sets the priority of each of the second EV dispatching and charging planning systems based on the CO of an electric power plan contracted at a second base managed by the second EV dispatching and charging planning system. 2 Determined based on basic unit, The power interchange management system according to claim 3 .

13. The interchange planning unit sets the priority of each of the second EV vehicle dispatching and charging planning systems based on the number of electric vehicles at a second base managed by the second EV vehicle dispatching and charging planning system, the total storage battery capacity of electric vehicles at the second base managed by the second EV vehicle dispatching and charging planning system, the average total delivery distance of the second base managed by the second EV vehicle dispatching and charging planning system, the average fuel efficiency of engine vehicles managed by the second EV vehicle dispatching and charging planning system, the average available capacity relative to the contracted power of the second base managed by the second EV vehicle dispatching and charging planning system, the renewable energy power ratio of the second base managed by the second EV vehicle dispatching and charging planning system, the average total EV charging amount of the second base managed by the second EV vehicle dispatching and charging planning system, the CO2 of an electricity plan contracted at the second base managed by the second EV vehicle dispatching and charging planning system, 2 Select and weight multiple basic units to determine the value. The power interchange management system according to claim 3 .

14. A first EV dispatch / charging planning system that manages a charging device and a private power generation device for an electric vehicle at a first base plans charging and dispatch of the electric vehicle; A second EV dispatch / charging planning system that manages a charging device for an electric vehicle at a second base plans charging and dispatch of the electric vehicle; an interchange planning unit aggregating surplus power from each of the first EV dispatch and charging planning systems to obtain interchangeable power; Providing the interchangeable power to each of the second EV dispatch and charging planning systems according to a predetermined priority order; A power interchange management method comprising:

Citation Information

Patent Citations

  • Power transmission control method, power transmission management system and program

    JP7202928B2