Wall material pulling jig and wall material pulling method
The wall material pulling jig uses a lever principle with a fulcrum end to efficiently apply force, addressing the difficulty in pulling large wall materials, ensuring stable and adjustable operation.
Patent Information
- Application Number
- JP2020193465
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-11-20
- Publication Date
- 2024-09-27
- Estimated Expiration
- 2040-11-20
AI Technical Summary
Large wall materials require significant force to be pulled, making it difficult for workers, and existing tools like crowbars or pulling devices may not reliably apply the necessary force.
A wall material pulling jig comprising a rod-shaped pulling rod, a fixing part, and a connecting member, where one end of the pulling rod serves as a fulcrum, allowing the application of force via a lever principle to pull the wall material.
The jig reliably applies the necessary force to pull wall materials efficiently, with a simple structure that is easy to install and operate, and allows for adjustable connection lengths and stable positioning.
Smart Images

Figure 0007557351000001 
Figure 0007557351000003 
Figure 0007557351000002
Abstract
Description
[Technical field]
[0001] The present invention relates to a wall material pulling jig and a wall material pulling method. [Background technology]
[0002] When a wall material such as an exterior wall material is installed at a location and is pulled in the width direction along its surface for position adjustment, a worker pushes the wall material in the width direction or inserts a crowbar into a hole formed in the frame of the wall material to move the wall material in the width direction by using the principle of leverage. Patent Document 1 discloses a device that is attached to a wall material and used to pull the wall material. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Japanese Patent Application Publication No. 3-241171 Summary of the Invention [Problem to be solved by the invention]
[0004] When the wall material is large, a large force is required to pull it over, which can make it difficult for workers to push the wall material. Also, when using a crowbar or pulling device, it is necessary to apply force reliably to the wall material.
[0005] Therefore, an object of the present invention is to provide a wall material pulling jig and a wall material pulling method that can reliably apply the force required for pulling to a wall material. [Means for solving the problem]
[0006] In order to achieve the above object, the present invention provides a wall material pulling jig for pulling a wall material to be provided in a structure, the wall material pulling jig comprising: Beam materialThe pulling rod is supported by a wall material and is held and operated by an operator, a fixing part is fixed to the wall material, and a connecting member is connected to the fixing part to the pulling rod, and one end of the pulling rod in the length direction is fixed to the structure. Beam material Rotatable And easily removable The one end portion is supported by a support member, and the other end portion in the length direction is configured to be displaceable with the one end portion as a fulcrum.
[0007] The wall material pulling method according to the present invention comprises the steps of: The wall material to be installed in the structure is pulled together using a wall material pulling jig. A wall material pulling method, comprising the steps of: The wall material pulling jig comprises a rod-shaped pulling rod supported by a beam of the structure and held and operated by a worker, a fixing part fixed to the wall material, and a connecting member connecting the fixing part to the pulling rod, wherein one end of the pulling rod in the length direction is rotatably supported by the beam of the structure and the other end side in the length direction is displaceable with the one end as a fulcrum, and the wall material pulling jig includes a structure installation step of supporting the pulling rod on the beam of the structure, a wall material fixing step of fixing the fixing part to the wall material, and a pulling step of gripping the other end side in the length direction of the pulling rod and pulling the wall material by tilting the pulling rod in the width direction of the wall material with the one end side in the length direction of the pulling rod as a fulcrum. And, it is equipped with.
[0008] In the present invention, the wall fixing member is fixed to the wall material, and one end of the pulling rod is used as a fulcrum, and the other end is moved in the desired direction to pull the wall material, so that a force is applied to the wall fixing member via the connecting member by the principle of leverage, and the wall material can be moved in the desired direction and pulled. In this way, the wall material pulling jig of the present invention can reliably apply the force required for pulling to the wall material. Furthermore, since the wall material pulling jig has a simple structure, it can be easily installed and operated, and can also be easily manufactured and maintained.
[0009] In the wall material pulling jig according to the present invention, the connection member may be configured so that a connection length between the fixing portion and the pulling rod is adjustable. With this configuration, the position of the pulling rod relative to the wall material is not limited, so that a common wall material pulling jig can be used even if the distance between the installation position of the pulling rod and the mounting position of the fixed part is different.
[0010] In addition, in the wall material pulling jig according to the present invention, Beam material and the one end of the pulling rod is Easy to put on and take off The pull rod may have a support portion formed with a hole into which the pull rod is inserted and capable of supporting the one end of the pull rod. With this configuration, one end of the pulling rod can be positioned at a fixed point when pulling the wall material, so that the one end of the pulling rod does not move and the wall material can be pulled efficiently in a stable state.
[0011] In addition, in the wall material pulling jig of the present invention, the pulling rod may have a connection portion to which the connecting member is connected in the middle of the length direction, and a gripping portion for being gripped by the worker on the other end side in the length direction further toward the connection portion. With this configuration, one end of the pull rod becomes the fulcrum in the principle of leverage, the gripping part becomes the force point in the principle of leverage, and the connection part becomes the point of action in the principle of leverage. Since the distance from the force point to the fulcrum is shorter than the distance from the force point to the fulcrum, force can be efficiently applied to the wall material via the wall fixing part connected to the connection part of the force point.
[0012] In the wall material pulling jig according to the present invention, the connecting member may be a chain formed by connecting a plurality of rings. With this configuration, the length of the connection member can be adjusted by adjusting the number of rings.
[0013] In addition, in the wall material pulling jig of the present invention, the pulling rod has a connection portion to which the connecting member is connected in the middle of the longitudinal direction, and the connection portion may be formed in a hook shape and configured to be able to hook the ring. With this configuration, the length of the connecting member can be easily adjusted by selecting the ring to be hooked onto the connecting portion according to the required length of the connecting member. Effect of the Invention
[0014] According to the present invention, the force required for pulling can be reliably applied to the wall material. [Brief description of the drawings]
[0015] [Figure 1]1A and 1B are diagrams illustrating a state in which a wall material pulling jig according to an embodiment of the present invention is used. [Diagram 2] FIG. 2 is a vertical cross-sectional view of the outer periphery of the building. [Diagram 3] FIG. [Figure 4] FIG. [Diagram 5] FIG. 13 is a front view of the wall material pulling jig during pulling. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] Hereinafter, a wall material pulling jig and a wall material pulling method according to an embodiment of the present invention will be described with reference to Figs. 1 to 4. As shown in Fig. 1, the wall material pulling jig 1 according to this embodiment is used when installing an exterior wall material (hereinafter referred to as wall material 12) of a building 11 (structure) by moving it in a horizontal direction (hereinafter referred to as width direction) along the wall surface of the wall material 12 to pull it closer. Here, the horizontal direction perpendicular to the width direction, i.e., the direction perpendicular to the wall surface of the wall material 12, is defined as the indoor / outdoor direction. In the drawing, the width direction is indicated by the direction of arrow A, and the indoor / outdoor direction is indicated by the direction of arrow B. In Fig. 2, the left side is the outdoor side in the indoor / outdoor direction, and the right side is the indoor side in the indoor / outdoor direction. As shown in Fig. 2, wall material 12 is placed on top of wall support metal fittings 14 joined to beam material 13. Beam material 13 is a steel beam such as an H-shaped steel or an I-shaped steel. Beam material 13 extends in the width direction. Wall support metal fittings 14 are long members, and are arranged in a direction extending in the length direction (width direction) of beam material 13. Floor material 15 (see Fig. 1) is placed on top of beam material 13.
[0017] As shown in Figures 1 and 2, the wall material 12 has a lower frame material 121 and a face material 122 fixed to the lower frame material 121. The lower frame material 121 is joined to the vicinity of the lower end of the face material 122. The lower frame material 121 has a joint 123 joined to the face material 122, and a protruding portion 124 protruding from the surface of the face material 122 on the indoor side. The protruding portion 124 is formed in a flat plate shape and is arranged so that the plate surface is a horizontal plane. The protruding portion 124 has holes 125 (see Figure 1) that penetrate in the vertical direction and are formed at intervals in the width direction.
[0018] The wall support metal fitting 14 has a fixed plate portion 141 which overlaps and is fixed to the upper flange 131 of the beam material 13 , and a back plate portion 142 which protrudes upward from the fixed plate portion 141 . The fixing plate portion 141 is formed in a flat plate shape and is joined onto the upper flange 131 with the plate surface oriented horizontally. The part of the fixing plate portion 141 facing the room is located vertically above the upper flange 131, and the part facing the room outside protrudes toward the outside of the room beyond the upper flange 131. The fixing plate portion 141 is joined to the upper flange 131 by bolts. The bolts 143 joining the fixing plate portion 141 and the upper flange 131 are arranged at intervals in the length direction, for example, at a pitch of 300 mm. The bolts 143 are oriented such that the head 145 faces downward and the threaded portion 146 faces upward. The tip side of the threaded portion 146 of the bolt 143, to which the nut 147 is attached, protrudes above the upper surface of the fixing plate portion 141. The tip side of the threaded portion of the bolt 143 protruding above the upper surface of the fixing plate portion 141 and the nut 147 attached thereto are called the bolt upper end portion 144.
[0019] The back plate portion 142 is a member having an L-shaped cross section. The back plate portion 142 has a flat first piece 142a and a flat second piece 142b that form an L shape. The first piece 142a is joined to the upper surface of the fixed plate portion with the plate surface oriented horizontally. The second piece 142b protrudes upward from the edge of the first piece 142a on the outdoor side. The second piece 142b has a vertical surface with the plate surface facing the indoor / outdoor direction. The back plate portion 142 is disposed above the middle portion of the fixed plate portion in the indoor / outdoor direction, and is located on the outdoor side of the outdoor side edge portion of the upper flange 131 of the beam material 13. In other words, the back plate portion 142 protrudes upward from the fixed plate portion 141 on the outdoor side of the bolts 143. A drip edge 16 is attached to the back plate portion 142 of the wall support metal fitting 14 and to the part of the fixed plate portion 141 on the outdoor side of the back plate portion 142.
[0020] The wall material 12 is installed on the outdoor side of the back panel portion 142, and is placed on the part of the fixed panel portion 141 that is on the outdoor side of the back panel portion 142 via the drip edge 16. The vicinity of the lower edge of the indoor side surface of the wall material 12 is in contact with the outdoor side surface of the second piece 142b of the back panel portion 142 via the drip edge 16.
[0021] As shown in Figs. 1 and 3, the wall material pulling jig 1 has a pulling rod 2, a fixing part 3, a connecting member 4, and a support plate 5 (support part). The support plate 5 is formed of a steel plate or the like in a flat plate shape with a rectangular plate surface. The support plate 5 is formed with a first hole portion 51 through which the bolt upper end portion 144 can be inserted, and a second hole portion 52 (hole portion) through which the end portion (support end portion 24 of the rod-shaped portion 21) of the pulling rod 2 can be rotatably inserted. Both the first hole portion 51 and the second hole portion 52 penetrate the support plate 5. In this embodiment, two first hole portions 51 and one second hole portion 52 are formed in one support plate 5. 1, 3 and 4, the support plate 5 is placed on the fixed plate portion 141 (see Figs. 1 and 3) with the plate surface oriented in a horizontal plane, and the bolt upper end portion 144 protruding upward from the upper surface of the fixed plate portion 141 is inserted into the first hole portion 51. An edge portion 53 corresponding to one of the four sides of the plate surface of the support plate 5 is disposed along the connection portion between the fixed plate portion 141 and the back plate portion 142 of the wall receiving hardware 14 (see Fig. 1).
[0022] As shown in FIGS. 1 and 3, the pulling rod 2 has a rod-shaped rod portion 21, a connection portion 22 connected to the rod portion 21, and an annular portion 23 connected to the rod portion 21. The rod-shaped portion 21 is made of steel and is formed into a rod shape extending linearly. The rod-shaped portion 21 is formed into a round rod shape with a uniform diameter except for the vicinity of one end in the length direction. The vicinity of one end in the length direction of the rod-shaped portion 21 has a tapered shape that gradually becomes thinner toward the end. One end of the rod-shaped portion 21 is formed with a diameter that can be inserted into the second hole portion 52 of the support plate 5. One end of the rod-shaped portion 21 is inserted into the second hole portion 52 of the support plate 5 and is supported by the support plate 5. One end in the length direction of the rod-shaped portion 21 is called the support end portion 24.
[0023] The connection part 22 is connected to a longitudinal intermediate part of the rod-shaped part 21. The connection part 22 is formed in a hook shape, and configured so that the connection member 4 can be hooked thereon. The annular portion 23 is connected to the other end 26 in the longitudinal direction of the rod-shaped portion 21 (the end opposite to the support end 24). The annular portion 23 is formed in a ring shape. The annular portion 23 is provided so that the pulling rod 2 can be hung on a wall or the like when not in use. The portion of the rod-shaped portion 21 between the connection portion 22 and the annular portion 23 (the portion on the other end side of the connection portion 22) serves as a gripping portion 25 that is gripped by a worker who pulls the wall material 12 together. The fixing part 3 is made of steel and formed in a C-shape. The fixing part 3 is configured so as to be able to be hooked into a hole 125 of a protruding part 124 of a lower frame material 121 of the wall material 12. The fixing part 3 is connected to a connecting member 4.
[0024] The connection member 4 is a chain of a predetermined length. The chain of the connection member 4 has multiple rings 41 connected to it. The connection member 4 has a ring 42 located at one end connected to the rod-shaped portion 21 of the pulling rod 2, and a ring 43 located at the other end connected to the fixed portion 3. Each of the multiple rings 41 of the connection member 4 can be hooked onto the connection portion 22 of the pulling rod 2. Depending on which of the multiple rings 41 of the connection member 4 is to be hooked onto the connection portion 22, the length from the connection portion 22 (rod-shaped portion 21) of the connection member 4 to the fixed portion 3 can be adjusted.
[0025] A method for pulling a wall material using the wall material pulling jig 1 will be described. First, a structure installation step is performed in which the pulling rod 2 is supported by the beam 13. In the structure installation step, the support plate 5 is installed on the fixed plate portion 141 on the beam 13. The support plate 5 is installed on the side of the wall material 12 that is the target of pulling, on the side that pulls the wall material 12. The bolt upper end portion 144 protruding upward from the upper surface of the fixed plate portion 141 is inserted into the first hole portion 51 of the support plate 5, and the edge portion of the support plate 5 is arranged along the connection portion between the fixed plate portion 141 and the back plate portion 142 of the wall receiving metal fitting 14. The edge portion on the outside of the room of the support plate 5 contacts the surface of the back plate portion 142 on the inside of the room. The support end portion 24 of the rod-shaped portion 21 of the pulling rod 2 is inserted into the second hole portion 52 of the support plate 5. The support end portion 24 contacts the upper surface of the upper flange 131 on the lower side of the support plate 5. The pulling bar 2 is supported by the beam 13 so as to be rotatable about the support end 24, although the position of the support end 24 is fixed.
[0026] Next, a wall material fixing step is performed in which the fixing part 3 is fixed to the wall material 12. In the fixing step, the fixing part 3 is hooked into the hole 125 of the protruding part 124 of the lower frame material 121 of the wall material 12. Then, the pulling rod 2 is placed in an upright position with the support end 24 on the lower side and the annular part 23 on the upper side. In this state, one of the multiple rings 41 of the connecting member 4 is hooked onto the connecting part 22 so that the connecting member 4 is not loose. The process of hooking the fixing part 3 into the hole 125 of the wall material 12 may be performed before inserting the support end 24 of the pulling rod 2 into the second hole 52 of the supporting plate 5 in the structure installation step.
[0027] Next, a pulling step is performed to pull the wall material. In the pulling step, as shown in Fig. 4, the gripping portion 25 of the pulling rod 2 is gripped and the supporting end portion 24 is used as a fulcrum to tilt the rod in the width direction. This causes the connecting member 4 to be pulled in the width direction, and the wall material 12 to be pulled in the width direction.
[0028] Next, the operation and effect of the wall material pulling jig 1 and the wall material pulling method according to the embodiment of the present invention described above will be described with reference to the drawings. In the wall material pulling jig 1 and wall material pulling method according to the embodiment of the present invention, the fixing part 3 is fixed to the wall material 12, and the supporting end 24, which is one end of the pulling rod 2, is used as a fulcrum, and the other end side is moved in the desired direction (width direction) in which the wall material 12 is to be pulled, whereby a force is applied to the fixing part 3 via the connecting member 4 using the principle of leverage, and the wall material 12 can be moved in the desired direction and pulled. In this way, the wall material pulling jig 1 according to this embodiment can reliably apply the force required for pulling to the wall material 12. Furthermore, since the wall material pulling jig 1 has a simple structure, it can be easily installed and operated, and can also be easily manufactured and maintained.
[0029] Moreover, in the wall material pulling jig 1 according to the embodiment of the present invention, the connection member 4 is configured so that the connection length between the fixing portion 3 and the pulling rod 2 is adjustable. With this configuration, the position of the pulling rod 2 relative to the wall material 12 is not limited, so that a common wall material pulling jig 1 can be used even if the distance between the installation position of the pulling rod 2 and the mounting position of the fixed part 3 is different.
[0030] In addition, the wall material pulling jig 1 according to an embodiment of the present invention has a support plate 5 that is installed on a beam material 13 (structure), has a second hole portion 52 formed therein into which one end of the pulling rod 2 is inserted, and is capable of supporting the support end portion 24 of the pulling rod 2. With this configuration, one end of the pulling rod 2 can be positioned at a fixed point when pulling the wall material 12. This prevents one end of the pulling rod 2 from moving, and allows the wall material 12 to be pulled efficiently in a stable state.
[0031] Furthermore, the support plate 5 has the bolt upper end portion 144 protruding upward from the top surface of the fixing plate portion 141 inserted into the first hole portion 51 and is in contact with the back plate portion 142 of the wall receiving hardware 14. Therefore, even if a force that moves the support plate 5 acts on the support plate 5 when a force is applied to the pulling rod 2, the support plate 5 is prevented from moving due to contact with the bolt upper end portion 144 or the back plate portion 142. This prevents the position of the support end portion 24 from shifting, and allows the wall material 12 to be pulled in a stable state.
[0032] In addition, in the wall material pulling jig 1 according to an embodiment of the present invention, the pulling rod 2 has a connection portion 22 in the middle of its length to which the ring 41 of the connecting member 4 is hooked, and has a gripping portion 25 on the other side of the length from the connection portion 22 to be gripped by the worker. With this configuration, the support end 24 of the pulling rod 2 becomes the fulcrum in the principle of leverage, the gripping portion 25 becomes the force point in the principle of leverage, and the connection portion 22 becomes the point of action in the principle of leverage. Since the distance from the point of action to the fulcrum is shorter than the distance from the force point to the fulcrum, force can be efficiently applied to the wall material 12 via the fixing portion 3 connected to the connection portion 22 of the point of action.
[0033] Moreover, in the wall material pulling jig 1 according to the embodiment of the present invention, the connection member 4 is a chain formed by connecting a plurality of rings 41 together. With this configuration, the length of the connection member 4 can be adjusted by adjusting the number of rings 41.
[0034] In addition, in the wall material pulling jig 1 according to an embodiment of the present invention, the pulling rod 2 has a connection portion 22 to which the connecting member 4 is connected at the middle portion in the longitudinal direction, and the connection portion 22 is formed in a hook shape and configured to be able to hook the ring 41. With this configuration, the length of the connection member 4 can be easily adjusted by selecting the ring 41 to be hooked onto the connection portion 22 according to the required length of the connection member 4.
[0035] The above describes the embodiment of the wall material pulling jig and wall material pulling method according to the present invention, but the present invention is not limited to the above embodiment and can be modified as appropriate without departing from the spirit of the present invention. For example, the wall material 12 to be pulled by the wall material pulling jig 1 according to this embodiment is an exterior wall material, but it may also be an interior wall material of a building. Furthermore, in the above embodiment, the connection member 4 is a chain formed by connecting a plurality of rings 41, but it may be a rope or the like other than a chain. Furthermore, in the above embodiment, the connection portion 22 is formed in a hook shape and configured to be able to hook the ring 41, but it does not have to be in a hook shape as long as it has a form that allows the connection member 4 to be connected. In addition, in the above embodiment, the connection member 4 is configured to be adjustable in the connection length between the fixed portion 3 and the pulling rod 2, but the connection length between the fixed portion 3 and the pulling rod 2 may be fixed. In addition, the shape of the fixed portion 3 and the manner in which the fixed portion 3 is fixed to the wall material 12 may be other than those described above.
[0036] In addition, in the above embodiment, the pulling rod 2 is supported by the support plate 5, but it may be supported directly by a member of the building 11, such as the beam 13 or the wall support metal fitting 14. In this case, the member of the building 11, such as the beam 13 or the wall support metal fitting 14, may be provided with a hole into which the support end 24 can be inserted. Further, in the above embodiment, the second hole portion 52 penetrates the support plate 5, but it may be a recess into which the support end portion 24 can be inserted. In the above embodiment, the first hole portion 51 into which the bolt upper end portion 144 is inserted is formed in the support plate 5, but if the bolt upper end portion 144 is not inserted, the first hole portion 51 does not have to be provided. Also, a convex portion other than the bolt upper end portion 144 may be inserted into the first hole portion 51. Also, the number and positions of the first hole portions 51 formed in one support plate 5 may be set appropriately.
[0037] In the above embodiment, the pulling rod 2 has a connection part 22 to which the connection member 4 is connected at a middle part in the longitudinal direction, and a grip part 25 to be gripped by an operator on the other longitudinal side of the connection part 22. Meanwhile, the arrangement of the grip part 25 and the connection member 4 in the rod-shaped part 21 of the pulling rod 2 may be set appropriately. In the above embodiment, the annular portion 23 is connected to the other end of the rod-shaped portion 21 of the pulling rod 2, but the annular portion 23 does not have to be connected. In addition, when the annular portion 23 is connected to the rod-shaped portion 21, the position of the annular portion 23 relative to the rod-shaped portion 21 may be set appropriately. [Explanation of symbols]
[0038] 1 Wall material pulling tool 2 Pull Rod 3 Fixed part 4 Connection parts 5 Support plate (support part) 11 Buildings (structures) 12 Wall Materials 22 Connection 24 Support end (one end) 25 Gripping part 41, 42, 43 Ring 52 2nd hole (hole)
Claims
1. A wall material pulling tool for pulling a wall material provided in a structure, A rod-shaped pulling rod supported by a beam material of the structure and held and operated by an operator; A fixing portion fixed to the wall material; A connecting member that connects the fixed portion to the pulling rod, The pulling rod is a wall material pulling jig in which one end in the longitudinal direction is supported rotatably and detachably on the beam material of the structure, and the other end in the longitudinal direction is configured to be displaceable with the one end as a fulcrum.
2. The wall material pulling jig according to claim 1 , wherein the connecting member is configured so that a connection length between the fixing portion and the pulling rod is adjustable.
3. A wall material pulling jig as described in claim 1 or 2, which is installed on a beam material of the structure, has a hole formed therein into which the one end of the pulling rod is removably inserted, and has a support portion capable of supporting the one end of the pulling rod.
4. The pulling rod has a connection portion at a middle portion in the longitudinal direction to which the connection member is connected, The wall material pulling jig according to any one of claims 1 to 3, further comprising a gripping portion for being gripped by the worker on the other end side in the length direction relative to the connection portion.
5. The wall material pulling jig according to any one of claims 1 to 4, wherein the connecting member is a chain formed by connecting a plurality of rings.
6. The pulling rod has a connection portion at a middle portion in the longitudinal direction to which the connection member is connected, The wall material pulling jig according to claim 5, wherein the connecting portion is formed in a hook shape so that the ring can be hooked thereon.
7. A wall material pulling method for pulling a wall material provided on a structure using a wall material pulling jig, comprising: The wall material pulling jig is A rod-shaped pulling rod supported by a beam material of the structure and held and operated by an operator; A fixing portion fixed to the wall material; A connecting member that connects the fixed portion to the pulling rod, The pulling rod is configured such that one end in the length direction is rotatably supported by a beam material of the structure, and the other end side in the length direction is displaceable with the one end as a fulcrum, A structure installation step in which the pulling rod is supported by a beam material of the structure; a wall material fixing step of fixing the fixing portion to the wall material; a pulling step of holding the other end side of the pulling rod in the length direction and pulling the wall material by tilting the pulling rod in the width direction of the wall material with one end of the pulling rod in the length direction as a fulcrum; A wall material pulling method comprising:
Citation Information
Patent Citations
JP1991052079U
Device for moving external panel in width direction
JP1991241171A
Framework go adjusting tool
JP1996158657A
Method for tightly fixing diaphragm in wood frame construction method
JP2000129923A
Wall-lifting systems
US8287221B1