Ceiling reinforcement structure and ceiling reinforcement method

The ceiling reinforcement structure addresses the limitations of existing systems by using a dual-hanging member system to securely support ceiling materials on complex shapes without scaffolding, ensuring stability even if primary supports fail.

JP7560828B2Active Publication Date: 2024-10-03TAKENAKA CORP +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
JP2020184649
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2020-11-04
Publication Date
2024-10-03
Estimated Expiration
2040-11-04

AI Technical Summary

Technical Problem

Existing ceiling material fall prevention structures are limited by the need for scaffolding during installation, lack versatility on complex ceiling shapes, and fail to prevent material fall if hanging members break.

Method used

A ceiling reinforcement structure using a first hanging member suspended from the building frame, with a shaft portion penetrating the ceiling material and a flange portion for support, and a second hanging member supporting an auxiliary member with a radial flange, allowing installation without scaffolding and preventing fall even if the first member breaks.

Benefits of technology

Enables installation on complex ceilings without scaffolding and ensures ceiling material stability by supporting the flange portion of the auxiliary member, preventing fall during earthquakes or other events.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007560828000001
    Figure 0007560828000001
  • Figure 0007560828000002
    Figure 0007560828000002
  • Figure 0007560828000003
    Figure 0007560828000003
Patent Text Reader

Abstract

To provide a ceiling reinforcement structure and a ceiling reinforcement method which do not use a scaffold, can be laid on a ceiling with a complicated shape, and can suppress a fall of a ceiling material even when a hanging member supporting the ceiling material is broken.SOLUTION: A ceiling reinforcement structure comprises: an auxiliary member 30 comprising a shaft portion vertically penetrating a ceiling material 26 supported by a first hanging member (a hanging bolt 16) hung from a skeleton (a beam 12) of a building, and a flange portion formed to protrude from a lower end of the shaft portion outwardly in a radial direction of the shaft portion; and a second hanging member (a wire 50) hung from the skeleton and hanging the auxiliary member 30 to support.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a ceiling reinforcement structure and a ceiling reinforcement method. [Background technology]

[0002] The following Patent Document 1 discloses a structure for preventing ceiling materials from falling. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2017-125367 A Summary of the Invention [Problem to be solved by the invention]

[0004] In the ceiling material fall prevention structure of Patent Document 1, a protection member disposed below a ceiling board is suspended and supported by a suspension support member that penetrates the ceiling board.

[0005] However, this suspension support member is fixed to the hanging bolt that suspends and supports the soffit and soffit support. Therefore, if the hanging bolt (hanging member) breaks, the protective function of the protective member will not work. In other words, it is difficult to prevent the ceiling material from falling.

[0006] In addition, the protective members are laid in a lattice pattern under the ceiling plate. Therefore, in order to lay the protective members, it is necessary to assemble scaffolding in the space under the ceiling plate, which makes the construction work difficult. Furthermore, if the shape of the ceiling is complex, it is difficult to lay the protective members along the shape. Therefore, it is not very versatile.

[0007] In consideration of the above-mentioned facts, the present invention aims to provide a ceiling reinforcement structure and a ceiling reinforcement method that can be installed on ceilings of complex shapes without the use of scaffolding, and can prevent the ceiling material from falling even if the hanging members supporting the ceiling material are broken. [Means for solving the problem]

[0008] The ceiling reinforcement structure of claim 1 includes a first hanging member suspended from the building frame. and the first hanging member a shaft portion that passes vertically through the ceiling material supported by the ceiling member; and a lower end portion of the shaft portion that is formed to extend radially outward from the shaft portion. under A flange portion; an upper flange portion that sandwiches the ceiling material between the lower flange portion and the upper flange portion and is integrated with the ceiling material and the lower flange portion; and a second hanging member that is suspended from the main body and supports the auxiliary member by suspending it.

[0009] In the ceiling reinforcement structure of claim 1, a ceiling material is supported by a first hanging member. Also, the shaft of an auxiliary member penetrates the ceiling material. This auxiliary member is supported by being suspended by a second hanging member, and a flange portion is formed at the lower end thereof, which protrudes radially outward from the shaft portion.

[0010] For example, if the first hanging member breaks during an earthquake, the ceiling material will tend to fall. However, the ceiling material is supported from below by the flanges of the auxiliary members suspended and supported by the second hanging member. This prevents the ceiling material from falling even if the first hanging member breaks.

[0011] In addition, because the ceiling material is suspended and supported by the shaft and flange, point support is possible and no parts need to be laid flat below the ceiling material. Therefore, this ceiling reinforcement structure can be installed on ceilings with complex shapes without using scaffolding.

[0012] The ceiling reinforcement structure of claim 2 is the ceiling reinforcement structure described in claim 1, in which the auxiliary member has a circular ring portion formed at the upper end of the shaft portion, and the second hanging member has a wire inserted into the circular ring portion.

[0013] In the ceiling reinforcement structure of claim 2, the auxiliary member is suspended and supported by a wire passed through the annular portion. Therefore, even if the ceiling is inclined, for example, there is no need to adjust the joint angle between the second suspension member and the auxiliary member to match the inclination. In other words, there is no need for a complex mechanism to accommodate the inclination of the ceiling. The ceiling reinforcement structure of claim 3 is the ceiling reinforcement structure described in claim 1 or 2, wherein the shaft portion is formed by a bolt, the lower flange portion is engaged with the head of the bolt below the ceiling material, and the upper flange portion is pressed by a nut screwed onto the bolt below the ceiling material to clamp the ceiling material.

[0014] Claim 4 The ceiling reinforcement method includes passing a wire through a through hole formed in a ceiling material supported by a first hanging member suspended from the building frame from above the ceiling, and attaching a shaft portion and a wire extending radially outward from the shaft portion to the tip of the wire in the lower space of the ceiling material. under a step of attaching an auxiliary member having a flange portion; and a step of pulling up the wire and inserting the shaft portion into the through hole. a step of sandwiching the ceiling material between an upper flange portion and a lower flange portion disposed above the ceiling material to integrate the ceiling material, the upper flange portion, and the lower flange portion; and supporting the auxiliary member by suspending it with a second suspending member suspended from the main body.

[0015] Claim 4 In the ceiling reinforcement method of the above, a wire is passed from the ceiling space through a through hole in the ceiling material, and an auxiliary member is attached to the end of the wire in the space below the ceiling material. By adjusting the length of the wire, workers can perform the installation work while standing on the floor of the space below. This means that there is no need to set up scaffolding in the space below. In other words, it is a simple method of reinforcing the ceiling.

[0016] In addition, this auxiliary member is formed with a flange portion that protrudes radially outward from the shaft portion and is supported by hanging. For example, if the first hanging member breaks during an earthquake, the ceiling material will attempt to fall. However, the ceiling material is supported from below by the flange portion of the auxiliary member that is supported by the second hanging member. This prevents the ceiling material from falling even if the first hanging member breaks. The ceiling reinforcement method of claim 5 is the ceiling reinforcement method of claim 4, wherein the shaft portion is formed by a bolt, and the auxiliary member is attached to the end of the wire by screwing the bolt into a cap nut attached to the end of the wire in the lower space of the ceiling material, and after the integrating process, the cap nut is removed from the bolt, and an attachment portion attached to the end of the second hanging member is screwed into the bolt to secure it. Effect of the Invention

[0017] According to the present invention, it is possible to install the ceiling material on ceilings of complex shapes without using scaffolding, and the ceiling material can be prevented from falling even if the hanging members supporting the ceiling material break. [Brief description of the drawings]

[0018] [Figure 1] 1 is an elevational sectional view showing an existing ceiling to which a ceiling reinforcement structure and a ceiling reinforcement method according to an embodiment of the present invention are applied. [Diagram 2] 1A is a vertical cross-sectional view showing a ceiling reinforcement structure according to an embodiment of the present invention, and FIG. 1B is a view taken along line BB in FIG. [Diagram 3] 2 is a cross-sectional view showing an auxiliary member of a ceiling reinforcement structure according to an embodiment of the present invention. [Figure 4] (A) is a cross-sectional view showing the state in which a through hole has been formed in a ceiling material in a ceiling reinforcement method according to an embodiment of the present invention, (B) is a cross-sectional view showing the state in which a wire has been inserted into the through hole, (C) is a cross-sectional view showing the state in which the shaft portion of an auxiliary member has been attached to the end of the wire, (D) is a cross-sectional view showing the state in which the wire has been pulled up to fix the auxiliary member to the ceiling material, and (E) is a cross-sectional view showing the state in which the attachment portion has been fixed to the auxiliary member. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0019] Hereinafter, a ceiling reinforcement structure and a ceiling reinforcement method according to an embodiment of the present invention will be described with reference to the drawings. Components indicated by the same reference numerals in each drawing are the same components. However, unless otherwise specified in the specification, each component is not limited to one, and may be present in multiple numbers. In addition, explanations of configurations and reference numerals that are duplicated in each drawing may be omitted. Note that the present invention is not limited to the following embodiments, and may be implemented by making appropriate modifications, such as omitting configurations or replacing them with different configurations, within the scope of the purpose of the present invention.

[0020] In each figure, the directions indicated by the arrows X and Y are directions along the horizontal plane and are perpendicular to each other. The direction indicated by the arrow Z is a direction along the vertical direction. The directions indicated by the arrows X, Y, and Z in each figure are assumed to be mutually consistent.

[0021] <Ceiling reinforcement structure> (Existing structure) The ceiling reinforcement structure according to the embodiment of the present invention is a reinforcement structure for an existing ceiling shown in Fig. 1. This existing ceiling includes a suspension bolt 16 as a first suspension member suspended from the building frame, and a ceiling material 26 supported by the suspension bolt 16.

[0022] Specifically, a hanger receiver 14 is suspended across an H-shaped steel beam 12, which is the building's framework. This hanger receiver 14 is a long member made of an H-shaped steel, a channel steel, or the like, and is fixed to the beam 12 by welding, bolts, or the like. As shown in Fig. 2(B) , a plurality of hanger receivers 14 are arranged at predetermined intervals in a direction (Y direction) intersecting with the extension direction (X direction) of the hanger receiver 14. Note that a small beam suspended across the beam 12 may also be used as the hanger receiver 14.

[0023] 1, the upper end of the hanging bolt 16 is fixed to the hanging tool receiver 14 using a nut (not shown). This allows the hanging bolt 16 to be suspended from the hanging tool receiver 14. A plurality of hanging bolts 16 are provided for each hanging tool receiver 14.

[0024] In addition, in the present invention, the "first hanging member suspended from the building structure" includes a hanging bolt suspended directly from the beam 12, sub-beam or slab which constitute the building structure, as well as a hanging bolt 16 suspended from the beam 12 via a hanging bracket 14, as in this embodiment.

[0025] A hanger 18 is fixed to the lower end of the hanging bolt 16. A siding support 22 extending along the X direction in a plan view is spanned across the multiple hangers 18. In other words, the siding support 22 is spanned across the multiple hangers 18 and supported.

[0026] A siding 24 is fixed to the siding support 22 via a clip (not shown). The siding 24 extends along the Y direction in a plan view and spans the multiple siding supporters 22. A plurality of the sidings 24 are provided at predetermined intervals in the X direction.

[0027] A ceiling material 26, which is a ceiling finishing material, is fixed to the rafters 24. The ceiling material 26 is fixed to the rafters 24 with screws or the like (not shown). The ceiling material 26 shown in Fig. 1 is disposed at an angle to the horizontal plane. Examples of uses of buildings in which ceiling materials are disposed at an angle in this manner include music halls and theaters, but the uses of buildings to which the present invention is applied are not particularly limited.

[0028] The ceiling material 26 has a folded-up portion that is folded up substantially upward. An opening 26B is formed in the folded-up portion. The opening 26B is used, for example, as a light transmitting portion when a spotlight is used to illuminate the stage.

[0029] In addition, in the present invention, "ceiling material supported by the first hanging member" includes not only a ceiling material directly fixed to the hanging bolt 16, but also a ceiling material 26 fixed via a soffit support 22 and a soffit 24, as in this embodiment.

[0030] (Reinforcement structure) As shown in FIGS. 2(A) and 2(B), the ceiling material 26 is supported (prevented from falling) by an auxiliary member 30 and a wire 50 serving as a second hanging member.

[0031] Specifically, the hanger receiver 52 is suspended across the hanger receiver 14, extending along a direction (Y direction) intersecting with the extension direction (X direction) of the hanger receiver 14. A plurality of the hanger receivers 52 are provided at predetermined intervals in the X direction. The hanger receiver 52 is fixed to the hanger receiver 14 by welding, bolts, or the like. The hanger receiver 52 may be disposed along the extension direction of the hanger receiver 14 and suspended across the beam 12.

[0032] In addition, in the present invention, the "second hanging member suspended from the building structure" includes not only the beams 12, joists and slabs that constitute the building structure, but also, as in this embodiment, the wire 50 suspended from the beam 12 via the hanging brackets 14, 52.

[0033] An upper end of the wire 50 is fixed to the hoisting tool receiver 52. This allows the wire 50 to be suspended from the hoisting tool receiver 52. A plurality of wires 50 are provided for each hoisting tool receiver 52. In addition, an auxiliary member 30 is attached to the tip of the wire 50.

[0034] During normal times other than when vibrations due to earthquakes or the like are occurring, there is no need to apply tension to the wire 50. When the suspension bolts 16 break during an earthquake or the like and the ceiling material 26 tries to fall, tension is applied to the wire 50 by the weight of the ceiling material 26 itself.

[0035] As shown in FIG. 3, the auxiliary member 30 is attached to the wire 50 in a state in which the ceiling material 26 is sandwiched therebetween.

[0036] Specifically, the auxiliary member 30 includes a shaft portion 32, an upper flange portion 34, a lower flange portion 36, and an attachment portion 38.

[0037] The shaft portion 32 is formed by a bolt (for example, a pan head screw). The shaft portion 32 is arranged such that, when the auxiliary member 30 is fixed to the ceiling material 26, the pan head 32A of the shaft portion 32 is located on the lower side with respect to the male screw.

[0038] A lower flange portion 36 made of a steel plate is engaged with the pan head 32A. A through hole is formed in the lower flange portion 36, and the male screw of the shaft portion 32 is inserted into this through hole. The lower flange portion 36 is sandwiched between a nut 32B screwed onto the shaft portion 32 and the pan head 32A, and is fixed to the shaft portion 32. As a result, the lower flange portion 36 is formed to protrude radially outward from the lower end of the shaft portion 32 while being fixed to the shaft portion 32.

[0039] The lower flange portion 36 is provided on the underside of the ceiling material 26, and is visible from the space below the ceiling material 26. Therefore, decoration can be applied to the lower flange portion 36 as necessary. Specific examples of decoration include making the shape of the steel plate forming the lower flange portion 36 into a shape that imitates some kind of figure, such as a cross, a star, or a flower.

[0040] Here, a through hole 26A is formed in the ceiling material 26. A shaft portion 32 of an auxiliary member 30 is inserted into the through hole 26A. A nut 32B screwed onto the shaft portion 32 is disposed inside the through hole 26A. With the shaft portion 32 inserted into the through hole 26A, the lower flange portion 36 is disposed in contact with the lower surface of the ceiling material 26.

[0041] The upper flange portion 34 of the auxiliary member 30 is disposed in contact with the upper surface of the ceiling material 26. A through hole is formed in the upper flange portion 34, and the male screw of the shaft portion 32 is inserted into this through hole. The upper flange portion 34 is sandwiched between the ceiling material 26 and a nut 32C screwed onto the shaft portion 32, and fixed to the upper surface of the ceiling material 26. Furthermore, by screwing the nut 32C, the ceiling material 26 is sandwiched and pressed between the upper flange portion 34 and the lower flange portion 36. A U-shaped washer 32D is disposed between the nut 32C and the upper flange portion 34. The washer 32D can be slid from a direction intersecting the axial direction of the shaft portion 32 to engage with the shaft portion 32.

[0042] A mounting portion 38 formed by an eye nut and a nut 38B are screwed onto the upper end of the shaft portion 32. A circular ring portion 38A is formed on the mounting portion 38, and a wire 50 is engaged with the circular ring portion 38A. The nut 38B and the mounting portion 38 form a double nut, preventing the mounting portion 38 from loosening.

[0043] <Ceiling reinforcement method> In the ceiling reinforcing method according to the embodiment of the present invention, first, as shown in Fig. 4(A), a through hole 26A is formed in a ceiling material 26. The through hole 26A is formed from above the ceiling, i.e., from the space above the ceiling material 26, using a router or the like.

[0044] A scaffold for work is provided above the ceiling. This scaffold will use existing ceiling spots and catwalks that are installed for lighting operation, etc. Although not shown in Fig. 4, the ceiling material 26 is supported by the hanging brackets 14, hanging bolts 16, joist brackets 22 and joists 24 as described above (see Fig. 1).

[0045] 4(B), the wire 52 is inserted through the upper flange portion 34 and the through hole 26A of the auxiliary member 30. It is preferable to attach a cap nut 54 to the tip of the wire 52, into which the shaft portion 32 of the auxiliary member 30 is screwed. The cap nut 54 also functions as a vibration prevention device for the wire 52.

[0046] The wire 52 may be suspended manually by an operator, or may be suspended using a hoist, winch, or other such hoisting machine 56. When using the hoisting machine 56, it is preferable to span a girder across the beam 12 or the like.

[0047] Next, as shown in Fig. 4(C), the shaft 32 of the auxiliary member 30 is screwed into the cap nut 54 in the lower space of the ceiling material 26. This attaches the shaft 32 to the cap nut 54. At this time, it is preferable that the wire 52 is lowered to a height of approximately 1.5 m or less from the floor surface in the lower space of the ceiling material 26 so that a worker standing on the floor can perform the installation work. The lower flange portion 36 and nuts 32B and 32C are attached to the shaft 32 in advance.

[0048] As long as the shaft portion 32 can be attached to the tip of the wire 52, it is not necessary to use a member having an internal thread such as the cap nut 54. For example, various members can be used as appropriate, such as a member that clamps the shaft portion 32, such as a clip, or a member that temporarily adheres the shaft portion 32, such as an adhesive tape.

[0049] After the shaft portion 32 is attached to the cap nut 54, the wire 52 is pulled up. Here, the through hole of the upper flange portion 34 arranged above the ceiling material 26 has a diameter that allows the cap nut 54 and the nut 32C to be inserted therethrough. This allows the shaft portion 32 to be inserted through the through hole 26A of the ceiling material 26, and the nut 32C to be positioned above the upper flange portion 34, as shown in Fig. 4(D). Note that the diameter of the through hole of the upper flange portion 34 and the diameter of the through hole of the lower flange portion 36 may be the same or different.

[0050] Next, slide washer 32D between nut 32C and upper flange portion 34, and screw in nut 32C. This fixes shaft portion 32 to ceiling material 26, and shaft portion 32 will not fall even if cap nut 54 is removed from shaft portion 32. Then, cap nut 54 is removed from shaft portion 32.

[0051] 4(E), the nut 38B and the mounting part 38 attached to the tip of the wire 50 are screwed and fixed onto the shaft part 32. Alternatively, the mounting part 38 is screwed onto the shaft part 32, and then the mounting part 38 is attached to the tip of the wire 50. In this way, the auxiliary member 30 is supported by being suspended from the wire 50.

[0052] The suspender receiver 52 for suspending the wire 50 is fixed to the suspender receiver 14 in advance, but this operation may be performed at any timing before or after forming the through hole 26A in the ceiling material 26. From the viewpoint of suppressing twisting of the wire 50, a swivel type eye bolt may be used as the eye bolt forming the mounting portion 38. Alternatively, the mounting portion 38 and the wire 50 may be connected via a carabiner or the like.

[0053] Through the above steps, the auxiliary member 30 can be safely fixed to the ceiling material 26. Note that this attachment method is just one example, and the auxiliary member 30 may be fixed to the ceiling material 26 by other methods.

[0054] <Action and Effects> In the ceiling reinforcement structure according to the embodiment of the present invention, as shown in Fig. 2(A), a ceiling material 26 is supported by a hanging bolt 16 serving as a first hanging member. Also, as shown in Fig. 3, a shaft 32 of an auxiliary member 30 penetrates the ceiling material 26. This auxiliary member 30 is supported by being suspended by a wire 50 serving as a second hanging member, and a lower flange 36 is formed at the lower end thereof, which protrudes radially outward from the shaft 32.

[0055] For example, if the hanging bolts 16 shown in Fig. 2(A) break during an earthquake, the ceiling material 26 will tend to fall. However, the ceiling material 26 is supported from below by the lower flange portion 36 of the auxiliary member 30 supported by the wire 50. This prevents the ceiling material 26 from falling even if the hanging bolts 16 break.

[0056] "The hanging bolt 16, etc. breaks" includes not only damage to the hanging bolt 16, but also damage to the hanger 18 that secures the hanging bolt 16 to the soffit support 22, and damage to the clip (not shown) that secures the soffit support 22 to the soffit 24.

[0057] The wire 50 may be suspended directly from the slab of the building. In this case, the suspension bracket 52 can be omitted.

[0058] In addition, in the ceiling reinforcement structure according to the embodiment of the present invention, as shown in Fig. 3, the auxiliary member 30 is suspended and supported by the wire 50 passed through the annular portion 38A of the mounting portion 38. Therefore, even in this embodiment in which the ceiling material 26 is arranged at an angle, there is no need to adjust the joint angle between the wire 50 and the auxiliary member 30 to match the angle. In other words, there is no need for a complex mechanism to accommodate the slope of the ceiling.

[0059] In this embodiment, the ceiling material 26 is disposed at an angle, but the embodiment of the present invention is not limited to this. The configuration and method of the present invention can be applied even if the ceiling material 26 is disposed along a horizontal plane.

[0060] In addition, in the ceiling reinforcing method according to the embodiment of the present invention, as shown in Fig. 4(B), a wire 52 is passed from above the ceiling through the through hole 26A of the ceiling material 26, and as shown in Fig. 4(C), the shaft 32 of the auxiliary member 30 is attached to the tip of the wire 52 in the lower space of the ceiling material 26. By adjusting the length of the wire 52, a worker can perform the installation work while standing on the floor of the lower space. Therefore, there is no need to set up scaffolding in the lower space. In other words, the ceiling can be reinforced in a simple manner. [Explanation of symbols]

[0061] 12 Beam (framework) 16 Hanging bolt (first hanging member) 26 Ceiling materials 26A through hole 30 Auxiliary Materials 32 Shaft 36 Lower flange part (flange part) 38A Circular Ring 50 Wire (second hanging member) 52 Wire

Claims

1. A first hanging member suspended from a building frame; an auxiliary member including: a shaft portion that vertically penetrates a ceiling material supported by the first hanging member; a lower flange portion formed by extending radially outward from a lower end portion of the shaft portion; and an upper flange portion that sandwiches the ceiling material between the lower flange portion and the upper flange portion and is integrated with the ceiling material and the lower flange portion; A second hanging member that is suspended from the body and suspends and supports the auxiliary member; Ceiling reinforcement structure equipped with

2. In the auxiliary member, a circular ring portion is formed at an upper end of the shaft portion, The second hanging member includes a wire inserted through the annular portion. The ceiling reinforcement structure according to claim 1.

3. The shaft portion is formed by a bolt, The lower flange portion is engaged with the head of the bolt below the ceiling material, The upper flange portion is pressed by a nut screwed onto the bolt below the ceiling material to clamp the ceiling material. The ceiling reinforcement structure according to claim 1 or 2.

4. a step of passing a wire through a through hole formed in a ceiling material supported by a first hanging member suspended from the building frame from above the ceiling, and attaching an auxiliary member having a shaft portion and a lower flange portion formed by projecting radially outward from the shaft portion to the tip of the wire in a lower space of the ceiling material; a step of pulling up the wire so that the shaft portion passes through the through hole; a step of sandwiching the ceiling material between an upper flange portion and a lower flange portion disposed above the ceiling material to integrate the ceiling material, the upper flange portion, and the lower flange portion; A step of suspending and supporting the auxiliary member by a second suspension member suspended from the body; A ceiling reinforcement method comprising:

5. The shaft portion is formed by a bolt, In the lower space of the ceiling material, the bolt is screwed into a cap nut attached to the end of the wire to attach the auxiliary member to the end of the wire; After the step of integrating, the cap nut is removed from the bolt; The mounting portion attached to the tip of the second hanging member is screwed into the bolt to be fixed. The ceiling reinforcing method according to claim 4.

Citation Information

Patent Citations

  • Ceiling fall prevention structure and construction method for the same

    JP2015183457A

  • Ceiling material fall prevention structure construction method

    JP2017008533A

  • Ceiling material fall prevention structure

    JP2017125367A