Water-impermeable structure of seawall at marine disposal site

The water-blocking structure addresses the challenge of maintaining sufficient penetration path lengths and water-tightness at sheet ends and joints by using a foot-hardening layer and intermediate sheets, enhancing the seawall's water-blocking performance.

JP7564685B2Active Publication Date: 2024-10-09TAIYO KOGYO CORP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2020183350
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2020-01-23
Filing Date
2020-10-30
Publication Date
2024-10-09
Estimated Expiration
2040-10-30

AI Technical Summary

Technical Problem

Existing water-blocking structures in marine disposal sites face challenges in maintaining sufficient penetration path lengths and water-blocking properties at the ends of water-shielding sheets, particularly at joints and anchoring points, due to limitations in construction dimensions and discontinuities between construction sections.

Method used

A water-blocking structure is implemented by using a combination of a foot-hardening layer and intermediate water-shielding sheets that extend beyond the base of the seawall structure, ensuring a prolonged penetration path length through welding and bonding, and incorporating additional sheets to maintain water-tightness at joints and divisions.

Benefits of technology

The solution enhances water-blocking performance by extending the penetration path length and ensuring stable adhesion at sheet ends and joints, thereby improving the overall water-tightness of the seawall structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007564685000001
    Figure 0007564685000001
  • Figure 0007564685000002
    Figure 0007564685000002
  • Figure 0007564685000003
    Figure 0007564685000003
Patent Text Reader

Abstract

To secure water-shielding properties of a sheet end in a base part, a dividing part and a structure fixing part of a water-shielding sheet of a vertical water-shielding structure of a control type revetment for a sea surface disposal field.SOLUTION: In a base part water-shielding layer in a vertical water-shielding work constructed so as to partition a sea surface disposal field revetment, a dividing part of a water-shielding sheet, and a fixing part of a caisson 4, a lower end of an intermediate water-shielding sheet 21 is welded and joined to the upper surface of the water-shielding sheet 20 so as to be brought into contact with and held to a foot protection water-shielding layer 30, a penetration passage length of the surface of the foot protection water-shielding layer 30 and the water-shielding sheet 20 is extended, a space including the end of the water-shielding sheet 20 and the branched water-shielding sheet in a sheet division part and a part fixed to the surface of the caisson 4 are divided by a steel sheet pile and a cover member, and a water-shielding block is formed which is obtained by filling the space with asphalt mastic and cooling and solidifying the same.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a waterproof structure for a seawall at a sea surface disposal site, and in particular to a waterproof structure for a seawall at a sea surface disposal site that ensures waterproofing at the seawall base of a waterproof sheet provided on a waterproof seawall constructed to surround a landfill area when constructing a sea surface disposal site, at the waterproof sheet joints in vertical waterproofing works, and at the fixed parts to the waterproof seawall structure. [Background technology]

[0002] Conventionally, marine final disposal sites for municipal and industrial waste are constructed by dividing the area into sections using multiple caissons, cells, and other revetment structures with waterproof joints to create a waterproof revetment. On the landfill side, various waterproof structures using waterproof sheets, etc. are constructed to prevent the leakage of waste and retained water from the managed waste final disposal site, which is surrounded by the revetment structure and foundation ground after operation, into the surrounding sea and land areas.

[0003] The basic structure of these waterproof structures is specified in the "Ministry Ordinance Prescribing Technical Standards for Final Disposal Sites for Municipal Waste and Industrial Waste (hereinafter, Standards Ministerial Ordinance)" (Non-Patent Document 1). Figure 15 is a schematic cross-sectional view showing the completed state of landfill with waste 58 in an example of a sea surface disposal site constructed in which the sea surface is partitioned by a waterproof revetment 50 using solidified treated soil 59 as backfill soil. The landfill area 62 that will become this sea surface disposal site is partitioned by a caisson-type composite embankment on the front side of the waterproof revetment and steel sheet piles 56 on the back side, with the interior backfilled with solidified treated soil 59 and partitioned by the waterproof revetment 50.

[0004] The caisson-type composite embankment has a caisson 64 installed on a rubble mound 53 constructed on a deep mixed treated soil layer 52, and a surface waterproofing work 70 made of a waterproof sheet 71 is formed along the slope on the landfill area 62 side of the rubble mound 53. On top of the surface waterproofing work 70, a riprap 57 is constructed as an upper covering layer so as to cover the entire surface waterproofing work 70.

[0005] On the other hand, an outer vertical waterproofing work 75 consisting of a waterproof sheet 71 having the same configuration as the surface waterproofing work 70 is applied over the entire surface of the outer side (landfill area 62 side) of the steel sheet pile 56 on the rear side, and the landfill area 62 behind it (inland side) is filled with the transported waste 58.

[0006] In this way, a sea surface disposal site is generally constructed as a managed waste landfill revetment with waterproofing works added to each part of the landfill revetment structure. For example, as a waterproofing work for each part, an asphalt mastic foot protection layer 30 is formed between a surface waterproofing work 70 laid so as to cover the slope and top of the rubble mound 53 and the base of the caisson 64. In such a surface waterproofing work 70, in order to ensure waterproofing at the joints between the holding block 33 installed to hold down the waterproof sheet 71 and the waterproof sheet 71 and the caisson 64, it is necessary to ensure the minimum length (seepage path length) required for the asphalt mastic foot protection layer 30 and the waterproof sheet 71 to come into close contact with each other.

[0007] Of these components, the steel sheet piles 56 on the rear side of the waterproof embankment 50 are erected in the deep mixed treated soil layer 52 with a specified embedment length ensured, and the landfill area 62 is defined with the top portion supported by a tie rod T with a caisson 64 as a retaining structure.

[0008] In this way, the steel sheet pile 56 is required to function as an impermeable wall, and in order to prevent deterioration of the structural performance due to aging, an outer vertical waterproof structure 75 is attached to the entire surface of the outer side (the reclaimed area 62 side) of the steel sheet pile 56. The outer vertical waterproof structure 75 uses a waterproof sheet 71 having a laminated sheet structure.

[0009] Incidentally, in the outer surface vertical waterproofing work 75 of the steel sheet pile 56, the erection of the steel sheet pile 56 and the installation of the waterproof sheet 71 on the surface of the steel sheet pile 56 are not carried out in the winter but are carried out across fiscal years. At this time, at the boundary between each work section (for example, between the work section of the current year and the work section of the next year), it is necessary to keep the end 71a (FIGS. 16 and 17) of the waterproof sheet fixed to the caisson 64 in a stable state at all water depths in the sea during the construction suspension period. In addition, since a divided portion 15 where the waterproof sheet 71 is not continuous occurs at the work section boundary, it is necessary to ensure the waterproofing at the end 71b of the waterproof sheet 71 divided at the work section boundary.

[0010] In order to ensure watertightness at the sheet ends in the divided parts of such waterproof sheets, a sheet connection structure has been proposed (Patent Document 1). At the joints of the waterproof sheets provided in this sheet connection structure, the frame of the connector is placed over the sheet ends so as to cover each end of the waterproof sheets to be joined, and the inside is filled with a waterproof material such as an asphalt mixture. [Prior art documents] [Patent documents]

[0011] [Patent Document 1] Patent No. 4441240 [Non-patent literature]

[0012] [Non-Patent Document 1] Environment Agency, Laws, Notifications, and Notices, "Ministry Ordinance on Technical Standards for Final Disposal Sites for General Waste and Final Disposal Sites for Industrial Waste", [online], last updated: Amended and published on June 9, 2017, Ministry of the Environment, [Retrieved March 6, 2020], Internet <URL:https: / / elaws.e-gov.go.jp / search / elawsSearch / elaws_search / lsg0500 / detail?lawId=352M50000102001&openerCode=1> Summary of the Invention [Problem to be solved by the invention]

[0013] The asphalt mastic footing layer 30, in which the end of the waterproof sheet 71 is held, is formed by filling a compartment surrounded by a holding concrete block 33 as a partition formwork with asphalt mastic in a fluid state, and then cooling and solidifying. In the asphalt mastic footing layer 30 at this time, the seepage path length L corresponds to, for example, the bottom length of the footing layer 30, and it is required to ensure L>1,250 mm (for example, 1,250 mm = required contact length 500 mm x safety factor 2.5). Also, even at the base of the steel sheet pile 56, the surface of which is covered with the vertical waterproofing work 75, the end of the waterproof sheet 20 needs to be brought into contact with the waterproof sheet 20, the asphalt mastic footing layer 30, and the treated soil surface with the holding block 33 or the like to exhibit sufficient waterproofing performance.

[0014] However, there are cases where the distance between the base of the caisson 64 installed on the rubble mound 53 and the toe of the rubble mound 53 is short, making it impossible to secure the bottom length of the asphalt mastic foot protection layer, or where the seepage path length cannot be secured due to the structure of the joint of the waterproof sheet 71.

[0015] In the sheet connection structure disclosed in Patent Document 1, it is possible to maintain the waterproofing performance at the ends of each waterproof sheet at the joints of the waterproof sheets, but in cases where a process of joining each waterproof sheet is included, no consideration is given to maintaining the ends of the waterproof sheets in a stable state at the separated points or ensuring waterproofing in that state.

[0016] Furthermore, in the vertical waterproofing structure 75, as shown in Figures 16 and 17, it is necessary to reliably perform waterproofing at the sheet end 71a of the waterproof sheet 71, which is the fixed part to the structure such as the caisson 64, and at the sheet end 71b at the joint of the waterproof sheet 71, over the entire height in the depth direction.

[0017] Therefore, in order to solve the problems associated with the above-mentioned conventional technology, the object of the present invention is to provide a waterproof structure for a seawall at a sea surface disposal site which ensures sufficient seepage length between the ends of each part of a waterproof sheet fixed within an asphalt mastic waterproof section and the asphalt mastic, thereby ensuring sufficient waterproofing at the ends of the waterproof sheet at the base fixing section, the ends of the sheet at the fixed section to a structure, and the ends of the waterproof sheet at the divided sections. [Means for solving the problem]

[0018] In order to achieve the above object, the waterproof structure of the present invention for a seawall at a sea surface disposal site is a waterproof structure in which an end portion of a waterproof sheet constituting a waterproof layer laid on a waterproof base surface supporting the seawall structure is fixed to a base of the seawall structure constructed to divide the seawall at the sea surface disposal site via a foot-blocking waterproof layer formed by filling the said seawall structure with an impermeable waterproof material, The foot-proofing waterproof layer is composed of a cooled and solidified asphalt mastic foot-proofing layer filled in a space between a holding work provided on the waterproof sheet and the revetment structure, The waterproof sheet is laid so that its end portion extends to the base of the revetment structure, a first intermediate waterproof sheet is in close contact between the foot-proofing waterproof layer on the waterproof sheet and the holding work, and is welded and joined to the waterproof sheet so that the shape of the waterproof sheet of the waterproof layer is maintained, and in addition to the first intermediate waterproof sheet, at least one second intermediate waterproof sheet is welded and joined to the waterproof sheet between the first intermediate waterproof sheet and the revetment structure so that the shape of the waterproof sheet standing up from the waterproof sheet within the foot-proofing waterproof layer is maintained, The seepage path length between the surface of the foot-proofing water-proof layer and the water-proof sheet is 1. Intermediate waterproof sheet and the second intermediate waterproof sheet The present invention is characterized in that the extension is via the surface of the

[0022] The second intermediate waterproof sheet is 1. It is preferable that the length of the intermediate waterproof sheet is shorter than that of the intermediate waterproof sheet, and that the erected shape is maintained by being embedded in the foot protection waterproof layer.

[0023] The length of the second intermediate waterproof sheet is 1. It is preferable that the length be 1 / 2 of the intermediate waterproof sheet.

[0024] The waterproof layer preferably comprises a laminated sheet of a waterproof sheet and protective mats sandwiching the waterproof sheet on both sides.

[0025] The impermeable water-proof material is preferably selected from asphalt-based materials, concrete-based materials, soil-based materials, and chemical-based materials having a predetermined water-proofing performance. [Brief description of the drawings]

[0031] [Figure 1] A side cross-sectional view showing the caisson and rubble mound near the top of a caisson-type composite breakwater at a marine disposal site (see Figure 15 as an example of the overall structure) in which one embodiment of the waterproofing structure for a marine disposal site embankment of the present invention is used. [Diagram 2] 2 is an enlarged cross-sectional side view showing a base portion of the waterproof structure shown in FIG. 1. [Diagram 3] FIG. 16 is an enlarged cross-sectional side view showing an embodiment in which the waterproof structure of the present invention is applied to the upper end of the embedded portion of the steel sheet pile shown in FIG. [Figure 4] 2 is an enlarged cross-sectional side view showing another embodiment of the water impermeable structure shown in FIG. 1. [Diagram 5] FIG. 11 is an enlarged cross-sectional side view showing a waterproof structure according to still another embodiment. [Figure 6] FIG. 11 is a side cross-sectional view showing the overall structure of another embodiment of a water-proof structure for a steel sheet pile. [Figure 7] An enlarged side cross-sectional view showing the waterproof structure near the upper end of the embedded part of the steel sheet pile. [Figure 8] FIG. 16 is a partial plan view showing an embodiment in which the waterproof structure of the seawall of a sea surface disposal site of the present invention is applied to a caisson-type composite breakwater at a sea surface disposal site (FIG. 16 is an example of the waterproof structure). [Figure 9] 9 is an enlarged partial plan view showing one embodiment of a waterproof structure of an end portion of a waterproof sheet at a divided portion (IX) of the waterproof sheet shown in FIG. 8. [Figure 10] FIG. 10 is a partial plan view showing a modified example of the branched waterproof sheet shown in FIG. [Figure 11] FIG. 4 is a partial plan view showing another embodiment of the waterproof structure at the end of the waterproof sheet. [Figure 12] 9 is an enlarged partial plan view showing one embodiment of the waterproof structure of the end of the waterproof sheet at the caisson side anchorage (XII) shown in FIG. 8. [Figure 13] FIG. 4 is a partial plan view showing another embodiment of the waterproof structure at the end of the waterproof sheet. [Figure 14] FIG. 4 is a partial plan view showing yet another embodiment of the waterproof structure at the end of the waterproof sheet. [Figure 15] FIG. 1 is a side cross-sectional view showing the overall structure of an example of a conventional waterproof structure for a seawall at a sea surface disposal site. [Figure 16] A partial plan view showing the installation state of caissons and steel sheet piles in a vertical waterproofing structure of a conventional seawall at a marine disposal site, as well as examples of the positions of the caisson side anchorages and waterproof sheet separation parts. [Figure 17] A partial front view showing the installation state of the caisson and steel sheet piles shown in Figure 16, the caisson side anchorage parts, and examples of the positions of the waterproof sheet division parts. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0032] Hereinafter, an embodiment of a waterproof structure for a seawall at a sea surface disposal site according to the present invention will be described with reference to the accompanying drawings.

[0033] [Configuration of the waterproof structure at the base of the surface waterproof structure] Fig. 1 shows an embodiment in which the waterproof structure of the present invention is applied to the joint between the base of a caisson 4 of a waterproof revetment and the end of a rubble mound 3 of a sea surface disposal site of the same scale as the sea surface disposal site illustrated in Fig. 15. Fig. 2 shows an enlarged view of the waterproof structure between the base of the caisson 4 at the top end portion of the rubble mound 3 in Fig. 1.

[0034] The caissons 4 shown in Fig. 1 are installed on a rubble mound 3 constructed on a deep mixed treated soil layer 52 (Fig. 15) as a structure on the front side (ocean side) of the waterproof revetment 1 that divides the sea surface disposal site. The caissons 4 are made of known reinforced concrete, steel or hybrid boxes filled with filler sand inside, and multiple caissons 4 of the same shape are arranged in a row on the rubble mound 3, with their backsides backfilled to a treatment level of 9. This allows them to function as a structure on the front side of the waterproof revetment 1 that divides a landfill area 11 (Fig. 15) of a specified area and width in the coastal waters.

[0035] As shown in Figures 1 and 2, the caisson 4 is installed at approximately the center in the width direction of the top of the rubble mound 3. A surface waterproofing work 10 is laid on the slope of the rubble mound 3 so as to cover the entire slope from the top to the bottom of the slope of the rubble mound 3, and a prescribed layer of riprap 5 is piled up on top of the work to protect the surface waterproofing work 10. Furthermore, the upper end of the surface waterproofing work 10 is extended to reach the base of the caisson 4, covering the top surface of the rubble mound 3, on which a prescribed layer of crushed stone 7 for preventing asphalt mastic seepage has been laid.

[0036] The surface waterproofing work 10 is composed of a three-layered laminated sheet in which both sides of the waterproof sheet 20 as a core material are laminated with protective mats 22. The waterproof sheet 20 is composed of a low-density polyethylene sheet (LLDPE: thickness 3 mm), and a nonwoven fabric as a protective mat 22 is laminated integrally on the top and bottom surfaces of the sheet to form a three-layered laminated sheet. By arranging the nonwoven fabric as the protective mat 22 laminated on both sides of the waterproof sheet in this way, the nonwoven fabric comes into contact with the surface of the backfill material of the riprap mound 3, and a large static friction force and a buffering effect can be secured between the backfill material and the waterproof layer. Other materials suitable for the waterproof sheet include polyvinyl chloride (PVC) sheets, laminated sheets of nonwoven fabric and PVC sheets, thermoplastic elastomer (TPE) sheets, and single sheets of high-density polyethylene sheets (HDPE), and these can be appropriately selected and used. The sheet thickness is preferably about 1.5 to 3.0 mm, taking into consideration elongation due to settlement, etc.

[0037] In this embodiment, the protective mat 22 is made of polyethylene terephthalate (PET) nonwoven fabric (500 g / m 2 ) is used. The waterproof sheet 20 is sandwiched between two protective mats 22 to form the surface waterproof work 10. Other suitable materials for the protective mat 22 include polyethylene (PE) and polypropylene (PP), but the protective mat 22 may be used on only one side of the waterproof sheet 20 depending on the on-site conditions in contact with each side of the waterproof sheet.

[0038] Here, the configuration of the end of the waterproof structure 1 of the present invention will be described with reference to Fig. 2 and Fig. 3. The surface waterproofing work 10 of the general part is composed of a three-layer integrated laminated sheet in which both sides of the waterproof sheet 20 are sandwiched between protective mats 22, but at the end fixed to the base position of the caisson 4, as shown in Fig. 2, the lower protective mat 22L and the waterproof sheet 20 are laid on the crushed stone 7, and an asphalt mastic footing layer 30 is formed on the waterproof sheet 20. This asphalt mastic footing layer 30 is a block body constructed by filling asphalt mastic between the holding concrete block 33 installed on the slope side and the caisson 4, and between this asphalt mastic footing layer 30 and the holding concrete block 33, a rising waterproof sheet 21 that is joined to the upper surface of the waterproof sheet 20 at the middle position in the width direction and functions as an intermediate waterproof sheet is provided so as to be sandwiched in close contact with the rising protective mat 23 between the asphalt mastic footing layer 30 and the holding concrete block 33. By adding a rising waterproof sheet 21 to this boundary portion, a predetermined seepage path length is ensured at the end of the surface waterproof work 10, thereby ensuring waterproofing at this boundary portion.

[0039] The rising waterproof sheet 21 is a waterproof sheet having the same thickness and specifications as the general waterproof sheet 20, which is welded and joined while maintaining waterproofness so as to branch out upward from the upper surface of the waterproof sheet 20 laid on the top surface of the riprap mound 3. A rising protective mat 23 is in close contact with the outer surface of this rising waterproof sheet 21 (the side opposite the asphalt mastic foot protection layer 30) by folding up the end of the protective mat 22 on the upper surface side of the general part and extending it.

[0040] Conventionally, when setting the bottom width D of the asphalt mastic foot protection layer 30, in order to ensure water impermeability between the waterproof sheet 20 and the asphalt mastic foot protection layer 30, it is necessary to ensure a seepage path length L (for example, 1,250 mm = necessary contact length 500 mm × safety factor 2.5) equivalent to the bottom width D in a normal structure. However, in the present invention, since the rising waterproof sheet 21 is joined to the waterproof sheet 20 while maintaining water impermeability, the height H of this rising waterproof sheet 21 is added as the seepage path length to determine the seepage path length L. L=D+H It can be considered as: Therefore, even if there are limitations on the dimensions of the top surface of the rubble mound 3 and the required infiltration path length L cannot be secured with the bottom width D of the asphalt mastic foot protection layer 30, the water-tight specifications at the end of the water-tight work can be secured.

[0041] Fig. 3 shows an enlarged view of the waterproof structure at the boundary 6a (hereinafter referred to as the embedment boundary 6a) between the upper end of the embedded part of the steel sheet pile 6 on the back side of the waterproof revetment 1 shown in Fig. 15 and the ground surface. As shown in Fig. 3, the tip of the steel sheet pile 6 is embedded in the deep mixed soil (CDM) 2 that was constructed as a waterproof base, but the inside of the waterproof revetment 1 sandwiching the steel sheet pile 6 and the surface of the mixed soil 2 on both sides of the reclaimed area 11 are poured with underwater non-separable concrete 36 for uneven leveling, so that the surface is almost flattened, and further, an asphalt mastic adhesion layer 35 with a thickness of about 15 cm is formed on the concrete surface, so that the waterproofness at the embedment boundary 6a of the steel sheet pile 6 is ensured.

[0042] On the surface of the asphalt mastic adhesive layer 35 inside the waterproof revetment 1, the ends of the waterproof sheet 20 and upper protective mat 22U of the surface waterproof work 10 laid on the riprap mound 3 are extended to the embedment boundary 6a position of the steel sheet pile 6, and a foot-proofing asphalt mastic foot-proofing layer 30 is formed over a predetermined range of the end of the upper protective mat 22U. Meanwhile, an outer vertical waterproof work 27 is provided on the side of the steel sheet pile 6 facing the landfill area 11. In the outer vertical waterproof work 27, as in the surface waterproof work 10 of the riprap mound 3, a three-layer integrated laminated sheet in which the waterproof sheet 20 is sandwiched between the protective mats 20 is used.

[0043] A bedrock surface waterproofing work 15 consisting of a three-layer integrated laminated sheet is also formed on the bedrock surface extending over a predetermined range from the steel sheet pile 6 on the reclaimed area 11 side. As shown in FIG. 3, the base of the outer vertical waterproofing work 27 of the steel sheet pile 6 and the end of the bedrock surface waterproofing work 15 are secured in waterproofing performance by the asphalt mastic footing layer 30 filled in the area partitioned by the holding concrete block 33. In this case, in the bedrock surface waterproofing work 15, the rising waterproofing sheet 21 and the rising protective mat 23 joined to the upper surface of the waterproofing sheet 20 having the same configuration as that shown in FIG. 2 are provided in close contact with the side surfaces of the asphalt mastic footing layer 30 and the holding concrete block 33. The infiltration path length of this bedrock surface waterproofing work 15 can also be the sum of the sheet lengths of the waterproofing sheet 20 and the rising waterproofing sheet 21 of the bedrock surface waterproofing work 15. As a result, waterproofing is secured even in the bedrock surface waterproofing work 15 at the embedment boundary 6a of the steel sheet pile 6.

[0044] 4 shows a modified example of the rising waterproof sheet 21 joined to the waterproof sheet 20 of the surface waterproof work 10 at the top of the above-mentioned rubble mound 3. As shown in the figure, in the asphalt mastic foot protection layer 30 formed in the area defined by the back side base of the caisson 4 at the top of the rubble mound 3 and the holding concrete block 33, , as the first intermediate waterproof sheet Rising waterproof sheet 21 A is placed at the approximate center of the width of the asphalt mastic foot protection layer 30, and the height (length) of the waterproof sheet is raised. 21 It is 1 / 2 of A. , as a second intermediate waterproof sheet Rising waterproof sheet 21 The seepage path length L at the end of the surface waterproofing work 10 is extended by disposing the two rising waterproofing sheets 21A and 21B vertically from the waterproofing sheet 20 of the surface waterproofing work 10, as shown by the dashed line in FIG. 20 , 21 A, 21In other words, if the bottom width of the asphalt mastic foot protection layer 30 is D and the height is H, L = D + H + (H / 2) + (H / 2) This allows the asphalt mastic foot protection layer 30 to exhibit better water-proofing performance. 21 The length of B is the rising waterproof sheet 21 It was 1 / 2 of A, but the rising waterproof sheet 21 The length of B is the rising waterproof sheet 21 As long as B is short enough to be able to be embedded and self-supporting within the asphalt mastic foot protection layer 30, the length can be changed as appropriate.

[0045] Each diagram in Fig. 5 shows a modified example in which the number of rising waterproof sheets 21B is increased to three or five and joined to the waterproof sheet 20 of the surface waterproof work 10 in an asphalt mastic foot protection layer 30 having the same structure as in Fig. 4. In these modified examples, the height of each sheet required to ensure the required adhesion length (seepage path length) can be reduced by the amount of the increased number of rising waterproof sheets 21B, and therefore it is also possible to reduce the amount of asphalt mastic filled by lowering the height H of the asphalt mastic foot protection layer 30.

[0046] Like the example of a sea surface disposal site shown in Figure 15, Figure 6 shows a waterproof revetment 1 in which the interior, partitioned by a caisson-type composite breakwater on the front side of the revetment and steel sheet piles 6 on the rear side, is backfilled with solidification-treated soil 9. The configuration of this example differs from that of the waterproof revetment 1 in Figure 15 in that an inner vertical waterproof structure 26 is provided over the entire surface of the inner side (solidification-treated soil side) of the steel sheet pile 6 on the rear side. The waterproof structure of this waterproof revetment 1 is composed of a surface waterproof structure 10 and an inner vertical waterproof structure 26.

[0047] Fig. 7 shows an enlarged view of the base of the inner vertical waterproofing work 26 of the steel sheet pile 6 of the waterproof revetment 1 shown in Fig. 6 and the tip part on the toe side of the slope of the surface waterproofing work 10. In this case, as in the case shown in Fig. 3, the tip part of the steel sheet pile 6 is embedded in the deep mixed treated soil 2 constructed as a waterproof base, and underwater non-separating concrete 36 for uneven leveling is poured on the inner surface of the mixed treated soil, and an asphalt mastic adhesive layer 35 of a specified thickness is formed on the surface.

[0048] On the surface of the asphalt mastic adhesive layer 35, the tip of the waterproof sheet 20 of the surface waterproof work 10 laid on the rubble mound 3 (Fig. 6) is extended to the embedment boundary 6a of the steel sheet pile 6, and in order to ensure waterproofing of this tip, an asphalt mastic foot protection layer 30 is formed in a predetermined area partitioned by a retaining concrete block 33 placed on a protective mat 22. At this time, an inner vertical waterproof work 26 consisting of a three-layer integrated laminated sheet is applied to the inner side surface of the steel sheet pile 6.

[0049] At the base of the inner vertical waterproofing work 26 and the tip of the surface waterproofing work 10 at the embedment boundary 6a of the steel sheet pile 6, as in the configuration shown in FIG. 3, between the asphalt mastic footing layer 30 and the holding concrete block 33, a rising waterproof sheet 21 and a rising protective mat 23 are provided so as to rise along the side of the asphalt mastic footing layer 30 and the holding concrete block 33. This allows waterproofing to be maintained between the inner vertical waterproofing work 26 and the surface waterproofing work 10. When the inner vertical waterproofing work 26 shown in FIG. 6 is adopted, there is an advantage that it is not affected by the step with the mixed treated soil layer 2 caused by the future subsidence of the existing ground 12 located outside the mixed treated soil layer 2, as compared with the case of the outer vertical waterproofing work 27 shown in FIG. 3.

[0050] [Configuration of the waterproof structure in vertical waterproof construction] Figure 8 shows As another inventionThis shows an embodiment in which the waterproof structure of the seawall of an offshore disposal site is applied to the divided portion 15 of the waterproof sheet 20 installed as the outer vertical waterproof structure 27 (71) of the steel sheet pile of the waterproof seawall of an offshore disposal site of a similar scale to the offshore disposal site illustrated in Figures 15 and 16, and to the caisson side fixed portion 4A as the waterproof seawall.

[0051] As shown in Figure 8 and supplementary Figures 15 and 16, caissons 4 (64) are installed on a rubble mound 53 constructed on a deep mixed treated soil layer 52 as a structure on the front side (ocean side) of the waterproof seawall 1 that defines the landfill area 11 (62) that will be the sea surface disposal site. The caissons 4 (64) are made of known reinforced concrete boxes filled with filler sand (not shown), and multiple caissons 4 of the same shape are installed in a row (L-shaped in Figure 8) on the rubble mound 53 (Figure 15), and function as a structure on the front side of the waterproof seawall 1 that defines the landfill area 11 (62) of a specified area and width in the coastal waters.

[0052] Meanwhile, as the structure on the rear side of the impermeable revetment 1, a steel sheet pile 6 (56) is erected at a position that secures a certain distance from the caisson 4, whose rear side is backed with solidified treated soil 9 (59), so as to form an impermeable wall. The top of the steel sheet pile 6 (56) is supported by a tie rod T that uses the caisson 4 (64) on the front side as a retaining structure. An outer vertical impermeable work 27 (71) is provided on the outer surface of the steel sheet pile 6 (on the reclaimed area 11 (62) side) so as to cover the entire surface.

[0053] (Configuration of the waterproof structure of the sheet end in the waterproof sheet divided part) As shown in Fig. 8, the laminated waterproof sheet 20 of the outer vertical waterproof structure 27 (71) has a different construction period for each work section, so it is attached in a divided state to the steel sheet pile 6 (56) at the boundary between each work section (hereinafter referred to as the dividing section 15). Below, the configuration of the waterproof structure of the sheet end of the waterproof sheet of the present invention at this dividing section 15 will be explained. Below, the symbols in parentheses will be omitted.

[0054] Fig. 9 is an enlarged view showing one embodiment of the waterproof structure of the present invention in the divided portion 15 ((Fig. 8-IX)) of the outer vertical waterproof structure 27. The figure shows a plan view of the end of the laminated waterproof sheet 20 attached along the outer surface of the steel sheet pile 6 and divided at the boundary of the construction area. As shown in the figure, the end of the three-layer laminated waterproof sheet 20 has a two-layer waterproof sheet consisting of the protective sheet 22 and the waterproof sheet 21, excluding the protective sheet 22 on one side, attached to the surface of the steel sheet pile 6. In addition, a waterproof sheet 25 (hereinafter referred to as a branched waterproof sheet 25) is added, which extends laterally in a branched shape from the bent portion of the steel sheet pile 6. This branched waterproof sheet 25 is a two-layer waterproof sheet consisting of a protective sheet 22 and a waterproof sheet 21, which have the same thickness and specifications as the waterproof sheet 21, and its root portion is welded and joined to the surface of the waterproof sheet 21 so that it branches out at the bend between the waterproof sheet 21 and the steel sheet pile 6, and is extended to a predetermined range within the dividing portion 15, thereby ensuring a sufficient seepage path length within the dividing portion 15.

[0055] As shown in Fig. 9, the branched waterproof sheet 25 is arranged in a straight line at the dividing section 15 (the boundary between the adjacent construction sections) with the branched waterproof sheet 25 attached to the waterproof sheet 21 constructed in the adjacent construction section, so as to be substantially symmetrical with respect to the dividing section 15. Furthermore, as shown in the figure, the landfill area 11 (Fig. 8) side of the steel sheet pile 6 on which the waterproof sheet end section 21a and the branched waterproof sheet 25 are arranged is covered with a cover plate 31, so as to form a space of a predetermined volume (hereinafter referred to as the dividing section space 38).

[0056] As shown in Figure 9, the cover plate 31 is a processed steel plate with flange portions 31b bent into a crank shape on both sides of the plate body 31a. The cover plate 31 covers the dividing portion 15 using the position of the bolt 32, the head of which has been attached in advance to a predetermined position on the steel sheet pile 6 by welding or the like, as a guide, and the cover plate 31 can be attached to the predetermined position by tightening the nut on the bolt 32 emerging from the through hole in the flange portion 31b.

[0057] 9, the separation space 38 surrounded by the steel sheet pile 6 and the cover plate 31 is filled with asphalt mastic As that is filled in a molten state and then cooled and solidified, and the waterproof sheet end 21a and the branch waterproof sheet 25 are completely buried in a state of being in close contact with the asphalt mastic As. This ensures a sufficient seepage path length for the waterproof sheet end of each of the adjacent work sections located in the separation 15, and ensures the waterproofing of the waterproof sheet at the separation 15.

[0058] 10(a) to 10(d) are partial enlarged views showing modified examples of the branched waterproof sheet 25. The branched waterproof sheet 25 shown in FIG. 9 has a shape extending linearly from the surface of the waterproof sheet 21, but various modified examples can be adopted in order to extend the seepage path length at the waterproof sheet end 21a by the branched waterproof sheet 25, i.e., to improve the waterproof performance. For example, FIG. 10(a) shows an example in which a flange 25a is provided at the tip of the branched waterproof sheet 25 to form a T-shape as a whole. By welding or integrally forming a sheet piece equivalent to the flange 25a at the tip of the branched waterproof sheet 25 to form the tip into a T-shape or an L-shape, the seepage path length at the tip of the branched waterproof sheet 25 can be extended. FIG. 10(b) shows a modified example in which a resin rod-shaped body 25b is integrally formed at the tip of the branched waterproof sheet 25. 14(c) and (d) show examples in which second and third branched waterproof sheets 25B and 25C, which have a shorter sheet length, are provided in multiple locations on the waterproof sheet 21. In these examples, the seepage path length of the second and third branched waterproof sheets 25B and 25C is added to the seepage path length along the first branched waterproof sheet 25A, so that a more sufficient seepage path length can be ensured.

[0059] Fig. 11 shows another embodiment of the waterproof structure for the seawall of the sea surface disposal site. As shown in the figure, in this embodiment, two long connecting bolts 32 that connect and fix the cover plate 35 and the steel sheet pile 6 are welded to the inner surface of the steel sheet pile 6 in the separation space 38. By inserting the tips of these connecting bolts 32 into connecting holes (not shown) in the flat cover plate 35, the positioning and fixing of the cover plate 35 can be performed simply and accurately. In addition, the waterproof sheet 21 extending from both sides of the separation part 15 can be reliably pressed and held by both ends 35a of the cover plate 35.

[0060] (Configuration of the waterproof structure of the sheet end at the caisson side anchorage) FIG. 12 shows an embodiment of the waterproof structure of the waterproof sheet end 21a at the anchoring part in the caisson 4 of the outer vertical waterproof structure 27 of the steel sheet pile 6 shown in FIG. 8 (hereinafter, referred to as the caisson side anchoring part 4A). In the caisson side anchoring part 4A, it is also necessary to secure the seepage path length of the waterproof sheet end 21a by reliably bringing the waterproof sheet end 21a into close contact with the caisson surface 4a. For this purpose, an anchoring part space 40 is secured in the part where the waterproof sheet end 21a is anchored to the caisson surface 4a, and the seepage path length is extended by providing a branch waterproof sheet 25 extending from the waterproof sheet side to the anchoring part space 40. At this time, one side of the anchoring part space 40 is covered with a cover plate 41. The cover plate 41 is L-shaped with a flange 41a at its end, and is fixed to the caisson surface 4a by an anchor bolt 42 at the position of the flange 41a. The other end of the cover plate 41 is fastened to the steel sheet pile 6 with bolts 43 so as to sandwich the waterproof sheet end 21a and make intimate contact with the steel sheet pile 6. At this time, rubber packing 44 or the like is attached to the mounting positions of the bolts 42, 43 to improve watertightness. Furthermore, the anchoring space 40 is filled with molten asphalt mastic As, forming a reliable waterproof structure at the caisson side anchoring part 4A of the waterproof sheet end 21a.

[0061] FIG. 13 shows another embodiment in which the fixing end of the waterproof sheet end 21a is positioned within the fixing space 40 in the caisson side fixing portion 4A. As shown in the figure, in this embodiment, the fixing space 40 is partitioned by the steel sheet pile 6 and the cover plate 45 covering the open side of the steel sheet pile 6. The cover plate 45 has a substantially Z-shaped cross section with a bent portion forming a right angle in a plan view, and rib plates 45a are attached to each bent portion at both ends of the plate at a predetermined interval in the longitudinal direction (depth direction), thereby maintaining the right angle shape of the bent portion. The root portion 45b of the cover plate 45 is fixed and held to the caisson surface 4a by the anchor bolt 46. The waterproof sheet end 21a extended from the general portion to the fixing space 40 is extended to the caisson surface 4a along the inner surface of the steel sheet pile 6 in the fixing space 40, and is fixed to the caisson surface 4a by the anchor pin 47. In addition, near the sheet end 21a along the caisson surface 4a, a branched waterproof sheet 25 for extending the seepage path length is welded. Asphalt mastic As is also filled into the anchoring space 40 and cooled and solidified, forming a reliable waterproof structure at the caisson side anchoring part 4A of the waterproof sheet end 21a.

[0062] Fig. 14 shows another embodiment in which the anchoring end of the waterproof sheet end 21a in the caisson-side anchoring portion 4A is located in an anchoring portion space 40 surrounded by a steel sheet pile 6C as an anchoring end cover and the caisson surface 4a. As shown in the figure, the anchoring portion space 40 is partitioned by the caisson surface 4a and a steel sheet pile 6C fixed to the caisson surface 4a along the height direction of the caisson with a fixing metal fitting (not shown). In addition, an asphalt block 48 is sandwiched between the caisson surface 4a and the end of the steel sheet pile 6C to improve adhesion, and the gap between the caisson surface 4a and the steel sheet pile 6C is blocked to maintain waterproofing.

[0063] On the other hand, the waterproof sheet end 21a extended from the general part to the anchoring space 40 is further stretched along the surface of the gap adjustment plate 49 and the caisson surface 4a, and the tip part is led into the anchoring space 40 from one end of the steel sheet pile 6C. The root part 49a of the gap adjustment plate 49 is fixed and held on the caisson surface 4a by the anchor bolt 46. The waterproof sheet end 21a is extended along the caisson surface 4a in the anchoring space 40 and is extended by a predetermined length along the inner surface of the steel sheet pile 6C. In addition, at the end position of the steel sheet pile 6C, a branch waterproof sheet 25 for extending the seepage path length is welded to the surface of the waterproof sheet end 21a. In addition, asphalt mastic As is filled in the anchoring space 40, and in a cooled and solidified state, a reliable waterproof structure is formed at the caisson side anchoring part 4A of the waterproof sheet end 21a.

[0064] As described above, in each embodiment of the present invention, the molten asphalt mastic is densely filled in the space partitioned by the holding concrete block 33 as a partition formwork material installed at a predetermined position on the waterproof sheet 20 of the asphalt mastic layer of each base, the space surrounded by the upper surface of the waterproof sheet 20 and the side of the rising waterproof sheet 21, and the dividing space 38, the anchoring space 40, or the space surrounded by the end 21a of the waterproof sheet 21 and the side of the branched waterproof sheet 25, and the watertightness is ensured in each part by cooling and solidifying while retaining its function as a viscoelastic body. Note that instead of asphalt mastic as a water-impermeable filling waterproof material, various asphalt-based mixtures that can be expected to have the same handling properties and waterproofness during use, as well as concrete-based materials, soil-based materials, chemical-based materials, etc. may be used.

[0065] In the above description, the present invention is not limited to the various embodiments, and various modifications are possible within the scope of the claims. In other words, the embodiments obtained by combining technical means appropriately modified within the scope of the claims are also included in the technical scope of the present invention. [Explanation of symbols]

[0066] 1. Sea surface disposal site 2 Mixed treated soil layer 3. Sacrifice Mound 4. Caisson 4A Caisson side anchorage 6,6C Steel sheet pile 10 Surface waterproofing 11 Reclaimed land 15. Foundation surface waterproofing 20. Waterproof sheet 22 Protective Mat 22U Upper protection mat 22L Lower protection mat 25 Branched waterproof sheet 26 Inside vertical water shielding 27 External vertical water shielding work 30 Divided Space 30 Asphalt mastic base layer 33 Reinforced concrete block 35 Asphalt mastic adhesion layer 38 Divided Space 31,35,41,45 Cover plate 40 Fixture space Asphalt mastic

Claims

1. A waterproof structure in which an end of a waterproof sheet constituting a waterproof layer laid on a waterproof base surface supporting a revetment structure is fixed to a base of the revetment structure constructed to divide a sea surface disposal site revetment via a foot-blocking waterproof layer formed by filling the foot-blocking waterproof layer with an impermeable waterproof material, the end of the waterproof sheet constituting the waterproof layer being laid on a waterproof base surface supporting the revetment structure, The foot-proofing waterproof layer is composed of a cooled and solidified asphalt mastic foot-proofing layer filled in a space between a holding work provided on the waterproof sheet and the revetment structure, The waterproof sheet is laid so that an end portion thereof extends to the base of the revetment structure, and a first intermediate waterproof sheet is welded and joined to the waterproof sheet so that the first intermediate waterproof sheet is in close contact between the foot protection waterproof layer on the waterproof sheet and the supporting work, and the shape of the first intermediate waterproof sheet raised from the waterproof sheet is maintained. In addition to the first intermediate waterproof sheet, at least one second intermediate waterproof sheet is welded and joined to the waterproof sheet between the first intermediate waterproof sheet and the revetment structure so as to be held in a shape raised from the waterproof sheet within the foot protection waterproof layer; A waterproof structure for a seawall at a sea surface disposal site, characterized in that the seepage path length between the surface of the foot-proofing waterproof layer and the waterproof sheet is extended via the surfaces of the first intermediate waterproof sheet and the second intermediate waterproof sheet.

2. The waterproof structure of a seawall at a marine disposal site as described in claim 1, wherein the second intermediate waterproof sheet has a length shorter than that of the first intermediate waterproof sheet and is buried within the root reinforcement waterproof layer to maintain its erected shape.

3. 3. The waterproof structure for a seawall at a sea surface disposal site according to claim 2, wherein the length of the second intermediate waterproof sheet is half the length of the first intermediate waterproof sheet.

4. 2. The waterproof structure for a seawall at a sea surface disposal site according to claim 1, wherein the waterproof layer is made of a laminated sheet of the waterproof sheet and protective mats sandwiching both sides of the waterproof sheet.

5. 2. The waterproof structure for a seawall at a sea surface disposal site according to claim 1, wherein the impermeable waterproof material is selected from the group consisting of asphalt-based materials, concrete-based materials, soil-based materials, and chemical-based materials, all of which have a predetermined waterproofing performance.

Citation Information

Patent Citations

  • Water-barrier structure and water-barrier construction for maritime disposal station

    JP2004181393A

  • Junction structure of impervious sheet in water bottom and junction method of imperious sheet

    JP2008023487A

  • Method of constructing impervious layer

    JP2008080325A

  • Construction method of water shield sheet and water shield liner

    JP2019107603A

  • Water shielding structure for control type revetment and water shielding structure for water shielding sheet end

    JP2021101063A