ENERGY CONSUMPTION PREDICTION DEVICE, ENERGY CONSUMPTION PREDICTION METHOD, AND ENERGY CONSUMPTION PREDICTION PROGRAM
The energy consumption prediction device improves prediction accuracy by associating past data with facility operation information and using user-defined conditions for data extraction and clustering, enabling precise energy consumption forecasting.
Patent Information
- Application Number
- JP2023525868
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2021-06-02
- Filing Date
- 2022-05-31
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-05-31
AI Technical Summary
Existing energy consumption prediction methods rely solely on past performance information, which may not accurately reflect conditions suitable for the target date, leading to inaccuracies in prediction.
An energy consumption prediction device that includes past energy consumption data associated with date and time of acquisition, additional facility operation information, and a system for extracting and clustering data based on user-specified conditions, generating prediction data through statistical processing and user-defined statistical methods.
Enhances the accuracy of energy consumption predictions by selecting more relevant data and grouping similar trends, allowing for precise energy consumption forecasting.
Smart Images

Figure 0007574923000001 
Figure 0007574923000002 
Figure 0007574923000003
Abstract
Description
[Technical field]
[0001] The present disclosure relates to an energy consumption prediction device, an energy consumption prediction method, and an energy consumption prediction program. [Background technology]
[0002] Conventionally, when predicting energy consumption, it has been considered to use past performance information of energy usage. For example, Patent Document 1 describes that when the performance information of past energy usage is displayed on a display means, a planned value setting means sets a planned value of future energy usage for each time period. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2011-10470 A Summary of the Invention [Problem to be solved by the invention]
[0004] In the method described in Patent Document 1, when using past performance information, the information is acquired by specifying a date. However, in reality, there is a possibility that the conditions suitable for the target date for predicting the consumption amount cannot be extracted simply by using the date, and there is room for improvement in terms of the prediction accuracy of the energy consumption amount.
[0005] The present disclosure has been made in consideration of the above, and aims to provide a technique that enables more accurate prediction of energy consumption. [Means for solving the problem]
[0006] An energy consumption prediction device according to one embodiment of the present disclosure has a memory unit that stores past energy consumption actual data of a target facility in association with information identifying the date and time when the data was acquired and additional information that is information related to the operating status of the target facility at the time the data was acquired, an extraction unit that extracts data from the energy consumption actual data stored in the memory unit, where the additional information matches extraction conditions specified by a user, and generates prediction data to be used for predicting energy consumption, and a prediction data generation unit that generates energy consumption prediction data based on the prediction data and instructions from the user. Effect of the Invention
[0007] According to the present disclosure, a technique is provided that enables more accurate prediction of energy consumption. [Brief description of the drawings]
[0008] [Figure 1] FIG. 1 is a diagram illustrating a usage state of an energy consumption prediction device according to an embodiment. [Diagram 2] FIG. 2 is a schematic diagram of an energy consumption prediction device according to an embodiment. [Diagram 3] 3(a) and 3(b) are examples of screens for inputting additional information, etc. [Figure 4] FIG. 4 is an example of a screen for setting extraction conditions. [Diagram 5] FIG. 5 shows an example of a screen for outputting the extraction results and predicted values. [Figure 6] FIG. 6 shows an example of a screen related to the output of extraction results and predicted values, in which a specific cluster is selected. [Figure 7] FIG. 7 is a diagram showing an example of a procedure for inputting auxiliary information to the energy consumption prediction device. [Figure 8] FIG. 8 is a diagram illustrating an example of a procedure for generating energy consumption prediction data. [Figure 9]FIG. 9 is a diagram illustrating an example of a hardware configuration of the energy consumption prediction device. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] An energy consumption prediction device according to one embodiment of the present disclosure has a memory unit that stores past energy consumption actual data of a target facility in association with information identifying the date and time when the data was acquired and additional information that is information related to the operating status of the target facility at the time the data was acquired, an extraction unit that extracts data from the energy consumption actual data stored in the memory unit, where the additional information matches extraction conditions specified by a user, and generates prediction data to be used for predicting energy consumption, and a prediction data generation unit that generates energy consumption prediction data based on the prediction data and instructions from the user.
[0010] An energy consumption prediction method according to one embodiment of the present disclosure includes storing in a memory unit past energy consumption actual data of a target facility in association with information identifying the date and time the data was acquired and additional information which is information related to the operating status of the target facility at the time the data was acquired; extracting data from the energy consumption actual data stored in the memory unit, the additional information of which matches extraction conditions specified by a user, to generate prediction data to be used for predicting energy consumption; and generating energy consumption prediction data based on the prediction data and instructions from the user.
[0011] An energy consumption prediction program according to one embodiment of the present disclosure causes a computer to perform the following operations: store in a memory unit past energy consumption actual data for a target facility in association with information identifying the date and time when the data was acquired and additional information that is information related to the operating status of the target facility at the time the data was acquired; extract data from the energy consumption actual data stored in the memory unit, where the additional information matches extraction conditions specified by a user, to generate prediction data to be used for predicting energy consumption; and generate energy consumption prediction data based on the prediction data and instructions from the user.
[0012] According to the above energy consumption prediction device, energy consumption prediction method, and energy consumption prediction program, past energy consumption actual data is stored in a storage unit in association with information specifying the date and time when the data was acquired and additional information, which is information related to the operating status of the target facility at the time when the data was acquired. Then, data whose additional information matches the extraction condition specified by the user is extracted from the data stored in the storage unit, prediction data used for predicting energy consumption is generated, and energy consumption prediction data is generated based on the instruction from the user using the prediction data. With this configuration, for example, by specifying a condition highly related to the target date for generating the energy consumption prediction data as the extraction condition from the additional information, more related data can be extracted as prediction data. Therefore, it is possible to perform energy consumption prediction with higher accuracy.
[0013] The present invention may further include a clustering unit that prepares data classified into a plurality of clusters by performing a clustering process on the data extracted by the extraction unit, and the prediction data generation unit may also use the data classified into the plurality of clusters as the prediction data.
[0014] It is conceivable that the extracted data may contain a large amount of variation when the extraction conditions are specified by the user alone. In response to this, the clustering process by the clustering unit classifies the data extracted by the extraction unit into multiple clusters, making it possible to consolidate data with similar tendencies from the extracted data. Therefore, by using this data, it is possible to more accurately predict energy consumption.
[0015] The prediction data generating unit may generate the energy consumption prediction data based on data classified into one of the plurality of clusters in accordance with an instruction from the user.
[0016] As described above, when generating energy consumption prediction data based on data classified into one of a plurality of clusters based on an instruction from a user, the energy consumption prediction data is generated from data classified into one cluster that is collected from the extracted data as data having a similar tendency. In this case, energy consumption prediction data that reflects the tendency of the cluster is created by using data having a more similar tendency classified into one cluster.
[0017] The prediction data generating unit may generate data by performing statistical processing on the prediction data, and generate the energy consumption prediction data from the statistically processed data based on a specification by the user.
[0018] As described above, by creating data by performing statistical processing on the prediction data, data reflecting the characteristics of the data contained in this prediction data is generated as energy consumption prediction data.
[0019] The prediction data generating unit may further include an input interface for allowing a user to specify the contents of statistical processing to be used for the energy consumption prediction data.
[0020] By allowing the user to specify the content of statistical processing when generating energy consumption prediction data, the user can flexibly specify the content of statistical processing, taking into consideration, for example, the conditions of use of the energy consumption prediction data, etc. Therefore, it becomes possible to create energy consumption prediction data suitable for the purpose with high accuracy.
[0021] The device may further include a display unit that displays data obtained by performing statistical processing on the prediction data as candidates for the energy consumption prediction data, and the user may use the input interface to select data to be used for the energy consumption prediction data from among the candidates.
[0022] In the above configuration, the user can check the data displayed on the display unit, which is obtained by performing statistical processing on the prediction data, as candidates for energy consumption prediction data. The user can also select data to be used as the energy consumption prediction data while checking the candidates. This improves user convenience.
[0023] The energy consumption amount calculating device may further include a display unit, and the display unit may present to a user supplementary information corresponding to the past energy consumption amount actual data in a time series manner.
[0024] In the above configuration, the user can grasp the time series change of the incidental information. In addition, the user can check whether or not the incidental information has been input, which can promote the input of the incidental information by the user.
[0025] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the accompanying drawings. In the description of the drawings, the same elements are given the same reference numerals and duplicated descriptions will be omitted.
[0026] [Energy consumption prediction device] First, a schematic configuration of an energy consumption prediction device 1 according to an embodiment will be described with reference to Fig. 1 and Fig. 2. The energy consumption prediction device 1 according to an embodiment has a function of predicting the amount of energy consumption in a target facility, etc., based on an instruction from a user. Examples of the facility, etc. (equipment / facility) to be predicted include a factory, a plant, etc.
[0027] As shown in FIG. 1, the energy consumption prediction device 1 predicts the energy consumption for a future target date and time period based on the actual energy consumption information from the energy demand meter 9. The energy demand meter 9 measures the total energy demand value, such as electricity and steam, for the entire target facility, and continuously transmits the result to the energy consumption prediction device 1. The timing of information transmission from the energy demand meter 9 to the energy consumption prediction device 1 is arbitrary, and the measurement value may be transmitted each time it is updated, or a method of providing a separate data storage means and transmitting the data collectively periodically (for example, every hour) may be adopted. The transmission means may be via an intranet within the facility, such as TCP / IP, or a method of uploading information to a server on the Internet and having the energy consumption prediction device download it. Also, the information stored in the energy demand meter 9 may be manually transmitted to the energy consumption prediction device 1 via a storage medium such as a USB memory.
[0028] Next, each unit of the energy consumption prediction device 1 will be described with reference to Fig. 2. Note that in the following embodiment, a configuration will be described that focuses on the amount of power consumption as the amount of energy consumption.
[0029] The energy consumption prediction device 1 includes, for example, a consumption record acquisition unit 11, an energy consumption record database 12, an extraction unit 13, a clustering unit 14, a statistical processing unit 15, an incidental information input unit 21, an extraction condition designation unit 22, a display switching unit 23, a predicted value output designation unit 24, a display unit 31, and a predicted value output unit 32. Of these, the incidental information input unit 21, the extraction condition designation unit 22, the display switching unit 23, and the predicted value output designation unit 24 may be configured as an input interface 20 that acquires information input by a user to acquire information designated by the user. Also, the display unit 31 and the predicted value output unit 32 may be configured as an output interface 30 that outputs a part of the information handled by the energy consumption prediction device 1 to the user.
[0030] The consumption record acquiring unit 11 has a function of acquiring information related to energy consumption transmitted from the energy demand meter 9 to the energy consumption prediction device 1. The consumption record acquiring unit 11 also has a function of storing the acquired energy consumption record in an energy consumption record database 12 described later. The consumption record acquiring unit 11 also has a role of acquiring information inputted in an additional information input unit 21 described later, and adding the information related to energy consumption to the energy consumption record database 12. The additional information will be described later.
[0031] The energy consumption record database 12 (storage unit) stores information on energy consumption throughout the target facility (e.g., power consumption record information) by day and time period. It also stores additional information added by the user. The information held in the energy consumption record database 12 is used to predict energy consumption for a future target day and time period.
[0032] The incidental information input unit 21 has a function of acquiring any incidental information that is assigned to information related to the energy consumption record. The incidental information is input by, for example, a user of the energy consumption prediction device 1. The incidental information is information that may affect the energy consumption record, and is, for example, information that can be set for each day and time period when the energy consumption record is acquired. Examples of the incidental information include information related to the operation status of a facility, weather information, etc.
[0033] When performing a process of predicting energy consumption for a future target date and time period, the extraction condition designation unit 22 acquires conditions (extraction conditions) for extracting specific data from the information stored in the energy consumption record database 12. The extraction conditions are designated, for example, by the user. The extraction conditions may include information contained in the supplementary information in addition to a date and time designation. When the user designates conditions similar to the target date and time period to be predicted as extraction conditions, information more suitable for the conditions of the prediction target may be extracted from the information stored in the energy consumption record database 12.
[0034] The extraction unit 13 has a function of extracting data relating to past energy consumption by time period from the energy consumption record database 12 based on extraction conditions acquired by user specification in the extraction condition specification unit 22. The extracted data can be used as prediction data that is the basis of energy consumption prediction data.
[0035] The clustering unit 14 has a function of performing clustering on the data extracted by the extraction unit 13. Clustering will be described later, but when there is a plurality of data extracted based on the extraction conditions, the clustering unit 14 has a function of classifying the data into clusters. Each of the data classified into clusters by the clustering unit 14 can be the basis of energy consumption prediction data. Note that clustering by the clustering unit 14 is not essential, and may be performed, for example, according to a user's specification.
[0036] The statistical processing unit 15 (prediction data generating unit) has a function of calculating various statistics by time period for the past energy consumption by time period extracted by the extraction unit 13 and / or the past energy consumption by time period classified into clusters by the clustering unit 14. In other words, the statistical processing unit 15 has a function of performing statistical processing on the prediction data prepared by the extraction unit 13 or the clustering unit 14. Examples of statistics include, but are not limited to, the average, maximum value, minimum value, ±nσ (standard deviation) of the actual energy consumption by time period. The calculated statistics can be used as a prediction value of energy consumption.
[0037] The display unit 31 displays on the screen the past energy consumption by time slot extracted by the extraction unit 13, the past energy consumption by time slot further classified by the clustering unit 14, and various statistics by time slot calculated by the statistical processing unit 15, in the form of a combination of graphs, tables, characters, etc. The display content on the display unit 31 may be controlled by an instruction from the user acquired by the display switching unit 23.
[0038] The display switching unit 23 has a function of acquiring an instruction to switch or change the contents and appearance displayed on the display unit. The instruction to switch the display contents is given, for example, by a user. The display switching unit 23 instructs the display unit 31 to change the display contents based on the contents instructed by the user.
[0039] The predicted value output designation unit 24 has a function of acquiring information specifying the data to be adopted as a predicted value from the user by presenting to the user candidates for data to be adopted as a predicted value by the user, such as the energy consumption by time period displayed on the display unit 31, various statistics, etc. As an example, the predicted value output designation unit 24 may be configured to present to the user buttons corresponding to the series that the user may adopt as a predicted value, such as "average", "maximum", "minimum", and "+1σ".
[0040] The predicted value output unit 32 (predicted data generating unit) has a function of outputting data related to the predicted value of energy consumption based on the user's designation acquired by the predicted value output designation unit 24. Examples of the output method include displaying on a screen, outputting to an external device or storage medium as a data file, etc.
[0041] An example of an output destination of data related to the predicted value of energy consumption by the predicted value output unit 32 is a management device that manages the equipment / facility that is the target of the prediction. In this case, the management device that is the output destination can adjust the amount of energy procurement for the target equipment / facility using data related to the predicted value of energy consumption. In equipment / facility that is difficult to stop operating, such as a factory or a plant, energy procurement to realize stable operation may be important. In such a case, more appropriate energy procurement can be performed by utilizing the data related to the predicted value of energy consumption.
[0042] [Input / output interface] The additional information input unit 21, extraction condition designation unit 22, display switching unit 23, and predicted value output designation unit 24 included in the input interface 20, and the display unit 31 and predicted value output unit 32 included in the output interface 30 will be further explained with reference to specific screen examples.
[0043] (1) Additional information input section As described above, the additional information input unit 21 is information that may be related to the actual energy consumption. Specifically, the additional information includes the production volume of products manufactured in the facility on each day, the number of times that major energy demand equipment (equipment that consumes energy) operates, and the operating time. FIG. 3(a) shows an example of an input screen for additional information. The screen example X1 shown in FIG. 3(a) shows a situation in which the date "2021 / 1 / 13" is selected from the calendar and additional information is input for that date. In addition, the items of the additional information D1 to be input for that date include the production volume, the number of times that the heat treatment furnaces 1 and 2 operate, and the number of times that the steam presses 1 and 2 operate. The items of this additional information may be common to each day. In addition, a configuration in which new additional information can be set via the new item addition button B1 as necessary may be used.
[0044] It should be noted that a setting for preventing forgetting to input information for each input date may be added to the incidental information input unit 21. For example, in the calendar shown in Fig. 3(a), the dates for which incidental information has not been input may be highlighted in color to draw the user's attention.
[0045] Also, when each item of the additional information D1 is selected, information related to the time series of the additional information that has already been input may be displayed together. In FIG. 3(b), the input values related to the production volume for each day in January, including January 13 selected by the user, are shown as a bar graph. When the user selects the "production volume" item from the additional information D1, a graph is displayed as in the example screen X2 shown in FIG. 3(b), so that the user can visually see the change in production volume for each day. In addition, for days for which no data has been input, such as January 17 shown in FIG. 3(b), the fact that the production volume is zero is also shown. Therefore, the user can refer to this graph to recognize dates that may have been forgotten to be input.
[0046] The incidental information may be configured to be input individually by the user by presenting a screen such as that shown in Fig. 3(a) to the user, or may be configured to be automatically acquired from an external device or the like. For example, the energy consumption prediction device 1 may be connected to an external device (e.g., a device that manages the operation and management of a facility) and information corresponding to the incidental information may be automatically downloaded from the external device, so that the incidental information input unit 21 acquires the information. In this case, the device configuration may become complicated, but in addition to being able to prevent forgetting to input the incidental information, it is also expected to improve work efficiency.
[0047] In addition to information related to production, external factors such as weather may be input as incidental information. Although it depends on the facility, temperature is considered to have a significant correlation with energy consumption related to air conditioning. Therefore, by using information such as weather, it is expected that the accuracy of predicting energy consumption can be improved. Regarding weather information, for example, past performance data is disclosed on the Internet, so this information may be configured to be automatically downloaded. In this way, the method of acquiring incidental information is not limited to user input, and can be changed as appropriate.
[0048] (2) Extraction condition specification section In order to extract time-zone-specific energy consumption data for a day close to the date and situation to be predicted, the extraction condition designation unit 22 specifies the data to be extracted from the past time-zone-specific energy consumption stored in the energy consumption record database 12 based on the date, day of the week, factory holiday information and additional information. Screen example X3 shown in Fig. 4 is an example of a screen for designating extraction conditions. As shown in Fig. 4, the screen for designating extraction conditions has items for designating extraction conditions for each of "date and day of the week input conditions" and "additional information conditions."
[0049] As a method for specifying the conditions to be used for extraction, for example, a check box labeled "Specify" or the like may be provided in the input field, so that the conditions described in each row can be switched to be used for extraction or not. This makes it possible to easily switch between enabled and disabled extraction conditions, regardless of whether or not items in each row are entered. In addition, in the example screen X3 shown in FIG. 4, the operation counts of steam press 1 and steam press 2 are excluded from the extraction conditions among the additional information. In this way, when "Specify" is unchecked (when excluded from the extraction conditions), the background color of each row (for example, the "Value" column) may be changed to intuitively express that the condition is not used. In addition, as shown in the example screen in FIG. 4, the lower and upper limits of each additional information in the specified period and the number of days that match the extraction conditions specified by the user (displayed as "relevant days" in FIG. 4) may be displayed. These values can be used as reference information when the user specifies the extraction conditions. In other words, the user can adjust (relax or strengthen) the extraction conditions by relying on this information. In this way, a configuration may be adopted in which information that the user can refer to is also displayed on the screen for specifying the extraction conditions, thereby assisting the user in specifying the extraction conditions.
[0050] (3) Display switching section and predicted value output designation section Once the extraction conditions are set, the extraction unit 13 extracts data that matches the extraction conditions from the information held in the energy consumption record database 12. The results are displayed on the display unit 31. Screen example X4 shown in Fig. 5 shows an example of a screen displayed by the display unit 31. Note that screen example X4 also displays the results of clustering by the clustering unit 14 and statistical processing by the statistical processing unit 15.
[0051] At the top of screen example X4 shown in FIG. 5, past energy consumption by time slot extracted under conditions specified by the user is displayed in graph A1 with time on the horizontal axis. In this graph A1, the extracted past energy consumption by time slot is drawn in a form that identifies the date. In the example shown in screen example X4, the energy consumption by time slot from April 1st to 6th is extracted and displayed. In addition, the same graph A1 also shows "average," "average +1σ," and "average -1σ." These statistics such as average are found by the statistical processing unit 15 and are calculated from the extracted data for 6 days.
[0052] FIG. 5 shows an example in which, when a point of data for "2021 / 4 / 6" is selected or mouse-overed, a pop-up display A2 is displayed with additional information such as production volume corresponding to the date. In this way, a configuration may be made in which the date, time, additional information, etc. can be displayed when each series in graph A1 is selected or mouse-overed. In this case, the user can grasp the fluctuations in the actual consumption amount over time in graph A1, while individually checking the relationship between each data item and the additional information of that data.
[0053] As described above, the graph A1 also shows the average energy consumption for each time period and a series of average ±nσ. n is a coefficient related to the standard deviation. Although the graph A1 shows a state where n=1, the value of n may be changeable. In the example screen X4, a coefficient n frame A3 for the standard deviation is provided as an example of a component of the display switching unit 23, and a slider that allows n to be changed is provided within this frame. When the user operates this slider, the "average value ±nσ" calculated using n according to the position of the slider may be displayed as a statistic to be displayed on the graph A1. In this way, the display unit 31 may change the display content displayed on the graph A1 based on the calculation result by the statistical processing unit 15 according to the position of the slider that functions as the display switching unit 23.
[0054] The display switching unit 23 may be configured to automatically update the graph A1 to reflect the operation of the slider in the coefficient n frame A3 for the standard deviation when the operation is detected.
[0055] In addition, the screen example X4 shows an automatic clustering result frame A4 as another element of the display switching unit 23. Inside this automatic clustering result frame A4, in addition to the conditions (all data) specified by the user, the number of data constituting the clusters (clusters 1 and 2) generated by the clustering unit 14 and the value of the all-time average standard deviation in each cluster are shown.
[0056] Here, the clustering process by the clustering unit 14 will be described. The clustering process is a process of classifying the consumption amount actual data extracted by the extraction conditions into a plurality of clusters. As described above, the consumption amount actual data used for predicting the consumption amount is extracted by the user setting various extraction conditions. However, when the conditions set by the user are not appropriate, such as when the range of conditions is wide, when the user does not set specific extraction setting conditions, or when the data changes significantly according to conditions not assumed by the energy consumption prediction device 1 in the first place, the extracted data may not all show the same tendency, and bias may occur. In such a case, by performing the clustering process to classify the extracted consumption amount actual data into a plurality of clusters, it is possible to present the user with the existence of bias in the extracted plurality of consumption amount actual data and each classified cluster.
[0057] There is no particular restriction on the algorithm used for the clustering process, but for example, the k-means method, which is an unsupervised machine learning method, can be used. When the k-means method is used, a vector is considered that combines the energy consumption by time period for each day and each additional information, and this is clustered. Specifically, for example, the time periods of a day are divided into 24 points, each for one hour, and five items of additional information are considered: production volume, number of times heat treatment furnace 1 is operated, number of times heat treatment furnace 2 is operated, number of times steam press 1 is operated, and number of times steam press 2 is operated. In this case, the dimension (number of elements) of each data vector is 24+5=29 dimensions. From the vectors of each data obtained in this way, the cluster classification is performed by repeatedly calculating the classification using the center of gravity of the cluster and the movement of the center of gravity. Note that when the k-means method is executed, since the results are affected by the range of the data, preprocessing (normalization of the value range, etc.) may be performed as necessary. In addition, when the k-means method is executed, the number of clusters must be specified. The number of clusters may be a program parameter, or may be determined by the user each time. In addition, the number of clusters may be set to be determined taking into account the degree of dispersion of the extracted data. In addition, taking into consideration the interpretability of the results, the number of clusters may be about 2 to 3.
[0058] 5 shows two clusters 1 and 2. When a user selects a specific cluster in this frame, the graph A1 may be redrawn so that only the time-of-day energy consumption data of the selected cluster is displayed.
[0059] 6 shows a state in which cluster 1 has been selected in the automatic clustering result frame A4 for the screen example X4. In the screen example X5, as a result of selecting cluster 1, the graph A1 shows three pieces of data (April 1st to 3rd) classified into cluster 1, and results relating to the average and the average ±1σ. In this way, when the user instructs to display the clusters obtained as a result of the clustering process, the display unit 31 may be configured to change the display contents displayed on the graph A1 based on the calculation results by the statistical processing unit 15 in accordance with the user's instructions.
[0060] The clustering results by the clustering unit 14 are particularly effective when the data varies due to factors not included in the extraction conditions specified by the user. With such a configuration, the user can confirm that the supplementary information of the data forming the cluster matches the situation on the target day, and then determine the time-slot energy consumption forecast value for the target day, for example, using only the data included in a specific cluster. In other words, when the extracted data varies due to factors not anticipated by the user, the data variation can be eliminated to some extent by clustering, making it possible to create data to be used for prediction.
[0061] Note that the example of the display switching unit 23 is not limited to that shown in the screen example X4 in Fig. 5. For example, the display switching unit 23 may be provided with various functions for improving the visibility of the graph, such as a function for enlarging / reducing / changing the scale of the graph, and a function for switching between displaying and hiding a specific series.
[0062] In the display example X4 of FIG. 5, there is a display value output frame A5 corresponding to the predicted value output designation unit 24. In this frame, a group of buttons is provided for outputting the predicted value of the energy consumption by time period for the target day with one click from the displayed series statistics. As an example, in the display example X4, "average", "minimum", "maximum", "average +nσ", and "average -nσ" are provided. When the user clicks any of these buttons, the corresponding hourly energy consumption is output as a predicted value by the predicted value output unit 32. The output destination may be on the screen or a file. Also, it may be configured to be recorded in the main memory of the computer, assuming that it will be linked with other programs.
[0063] In addition, buttons and the like different from the buttons shown in Fig. 5 may be set in the display value output frame A5. For example, when it is expected that data for a specific date, for example, from among the extracted energy consumption actual data, may be used as is as the energy consumption predicted value, the configuration of the predicted value output designation unit 24 may be changed so that the data can be output as the predicted value. In other words, the type of data output as the energy consumption predicted data is not limited to the data after statistical processing exemplified in the display value output frame A5, and any of the prediction data may be used as the energy consumption predicted data.
[0064] [Energy consumption prediction method] Next, an energy consumption prediction method by the energy consumption prediction device 1 will be described with reference to Fig. 7 and Fig. 8. Fig. 7 shows the procedure for inputting auxiliary information to the energy consumption prediction device 1, and Fig. 8 shows the procedure for creating energy consumption prediction data.
[0065] 7, a procedure for inputting incidental information to the energy consumption prediction device 1 will be described. First, it is assumed that actual data related to energy consumption is transmitted from an energy demand meter 9 to the energy consumption prediction device 1 and is stored in an energy consumption actual database 12. The procedure is as follows when incidental information is added by a user or the like.
[0066] First, the user starts the energy consumption prediction device 1 (step S01). Next, the user inputs an additional condition corresponding to the energy consumption achievement data through the additional information input unit 21 of the input interface 20 (step S02). After that, the user ends the energy consumption prediction device 1 (step S03).
[0067] 8, a procedure for generating energy consumption prediction data for an estimation target day using the energy consumption prediction device 1 will be described. First, it is assumed that data is stored in the energy consumption result database 12 of the energy consumption prediction device 1 in a state where the above-mentioned energy consumption result data is associated with additional information.
[0068] First, the user starts the energy consumption prediction device 1 (step S11). Next, the user sets extraction conditions for generating energy consumption prediction data for a target day through the extraction condition designation unit 22 of the input interface 20 (step S12).
[0069] Next, in the energy consumption prediction device 1, the extraction unit 13 extracts consumption actual data based on the extraction conditions specified by the extraction condition specification unit 22, and then performs clustering, and displays the results and the results of statistical processing (step S13). At this stage, the extraction unit 13 of the energy consumption prediction device 1 extracts consumption actual data necessary for creating prediction value data. In addition, the clustering unit 14 performs clustering on the extracted consumption actual data based on preset conditions as necessary. Furthermore, the statistical processing unit 15 performs statistical processing on the extracted consumption actual data and the data classified by clustering, and calculates statistical data such as the average, the average ±nσ, the maximum, and the minimum. These data are displayed by the display unit 31. As a result, the user can check the extracted data and the results of the statistical processing. At this time, the user may perform an operation such as changing the display content on the display unit 31 by operating the display switching unit 23.
[0070] In this way, in the energy consumption prediction device 1, the generation of prediction data in the extraction unit 13 and the clustering unit 14 and the statistical processing of the prediction data in the statistical processing unit 15 are performed simultaneously. In this way, in the case of a device configuration in which the user generates energy consumption prediction data while viewing the data displayed on the display unit 31, the generation of prediction data and the statistical processing may be performed simultaneously. The statistical processing by the statistical processing unit 15 may be performed repeatedly at the user's instruction until the user finally decides which data to output as the energy consumption prediction data (step S14).
[0071] Next, the user instructs the generation of predicted value data to be output through the predicted value output designation unit 24 of the input interface 20 (step S14). The designation through the predicted value output designation unit 24 is performed, for example, by the user operating the display value output frame A5 of the screen example X4. Based on this instruction from the user, the predicted value output unit 32 of the energy consumption prediction device 1 creates and outputs predicted value data. After that, the user ends the energy consumption prediction device 1 (step S15).
[0072] [Hardware configuration] The hardware configuration of the energy consumption prediction device 1 will be described with reference to Fig. 9. Fig. 9 is a diagram showing an example of the hardware configuration of the energy consumption prediction device 1. The energy consumption prediction device 1 includes one or more computers 100. The computer 100 has a CPU (Central Processing Unit) 101, a main memory unit 102, an auxiliary memory unit 103, a communication control unit 104, an input device 105, and an output device 106. The energy consumption prediction device 1 is configured by one or more computers 100 configured by these hardware units and software such as programs.
[0073] When the energy consumption prediction device 1 is composed of multiple computers 100, these computers 100 may be connected locally or via a communication network such as the Internet or an intranet. This connection logically constructs one energy consumption prediction device 1.
[0074] The CPU 101 executes an operating system, application programs, and the like. The main memory 102 is composed of a ROM (Read Only Memory) and a RAM (Random Access Memory). The auxiliary memory 103 is a storage medium composed of a hard disk, a flash memory, and the like. The auxiliary memory 103 generally stores a larger amount of data than the main memory 102. At least a part of each unit constituting the energy consumption prediction device 1 is realized by the auxiliary memory 103. The communication control unit 104 is composed of a network card or a wireless communication module. At least a part of each unit constituting the energy consumption prediction device 1 may be realized by the communication control unit 104. The input device 105 is composed of a keyboard, a mouse, a touch panel, a microphone for voice input, and the like. For example, at least a part of the input interface 20 is realized by the input device 105. The output device 106 is composed of a display, a printer, and the like. At least a part of the output unit 19 is realized by the output device 106. For example, the output device 106 may display the predicted value data, etc., output by the output interface 30 on a display or the like.
[0075] The auxiliary storage unit 103 stores in advance the program 110 and data necessary for processing. The program 110 causes the computer 100 to execute each functional element of the energy consumption prediction device 1. The program 110 causes the computer 100 to execute, for example, the processing relating to the above-mentioned steps S01 to S04. For example, the program 110 is read by the CPU 101 or the main storage unit 102, and causes at least one of the CPU 101, the main storage unit 102, the auxiliary storage unit 103, the communication control unit 104, the input device 105, and the output device 106 to operate. For example, the program 110 reads and writes data in the main storage unit 102 and the auxiliary storage unit 103.
[0076] The program 110 may be provided in a state recorded on a tangible recording medium such as a CD-ROM, a DVD-ROM, a semiconductor memory, etc. The program 110 may be provided as a data signal via a communication network.
[0077] [Effect] According to the above energy consumption prediction device 1, energy consumption prediction method, and energy consumption prediction program, past energy consumption actual data is stored in the storage unit in association with information specifying the date and time when the data was acquired and additional information, which is information related to the operation status of the target facility when the data was acquired. Then, data whose additional information matches the extraction condition specified by the user is extracted from the data stored in the storage unit, prediction data used for predicting energy consumption is generated, and energy consumption prediction data is generated based on the instruction from the user using the prediction data. With this configuration, more relevant data can be extracted as prediction data from the additional information by specifying, for example, a condition highly relevant to the target date for generating the energy consumption prediction data as an extraction condition. Therefore, it is possible to perform energy consumption prediction with higher accuracy.
[0078] Although a configuration for extracting energy consumption actual data by specifying a date and time has been known, it may be difficult to appropriately extract actual data that matches the situation for which energy consumption prediction data is to be created using date and time information alone. In this regard, by combining the supplementary information as described above, the accuracy of the data extracted as prediction data can be improved, making it possible to create more accurate energy consumption prediction data.
[0079] In addition, it is possible that the extracted data will contain a large amount of variation when the extraction conditions are only specified by the user. In response to this, the apparatus may further include a clustering unit 14 that performs a clustering process on the data extracted by the extraction unit 13 to prepare data classified into multiple clusters. In addition, the statistical processing unit 15 and the predicted value output unit 32 as the predicted data generating unit may also use the data classified into multiple clusters as prediction data. It is possible to consolidate data with similar tendencies from the data extracted by the clustering process by the clustering unit 14. Therefore, it is possible to more accurately predict energy consumption by using this data.
[0080] The prediction data generating unit may generate the energy consumption prediction data based on the data classified into one of a plurality of clusters based on an instruction from a user. In this case, the energy consumption prediction data is generated from the data classified into one cluster that is collected as data having a similar tendency from among the extracted data. With this configuration, the energy consumption prediction data that reflects the tendency of the cluster is generated by using the data having a more similar tendency classified into one cluster.
[0081] The statistical processing unit 15 and the predicted value output unit 32 functioning as the predicted data generating unit may generate data by performing statistical processing on the prediction data, and generate energy consumption predicted data from the statistically processed data based on the user's specification. By generating data by performing statistical processing on the prediction data, data reflecting the characteristics of the data included in the prediction data is generated as the energy consumption predicted data.
[0082] The device may also have an input interface 20 for the user to specify the contents of statistical processing to be used for the energy consumption prediction data. By allowing the user to specify the contents of statistical processing when generating the energy consumption prediction data, the user can flexibly specify the contents of statistical processing, for example, taking into consideration the conditions of use of the energy consumption prediction data. As a result, it becomes possible to create energy consumption prediction data suitable for the purpose with high accuracy.
[0083] The system may further include a display unit 31, which may display data obtained by performing statistical processing on the prediction data as candidates for the energy consumption prediction data. The user may use the input interface 20 to select data to be used for the energy consumption prediction data from among the candidates. In this configuration, the user can check the data obtained by performing statistical processing on the prediction data displayed on the display unit 31 as candidates for the energy consumption prediction data. The user can select data to be used as the energy consumption prediction data while checking the candidates. This improves user convenience.
[0084] The display unit 31 may further include a display unit 31, which may present to the user incidental information corresponding to past energy consumption actual data in a time series manner as shown in screen example X2. In this configuration, the user can grasp the time series change of the incidental information. In addition, the user can check whether or not incidental information has been input, which may encourage the user to input incidental information.
[0085] [Variations] As described above, the present disclosure is not necessarily limited to the above-described embodiment, and various modifications are possible without departing from the gist of the present disclosure.
[0086] For example, in the above embodiment, the case where electricity is handled as the energy has been described, but, for example, multiple types of energy may be handled simultaneously. As an example, it is possible to handle electricity and steam. In this case, for example, the graph A1 displayed in the screen example X4 may also be configured to display information on multiple types of energy simultaneously. Also, for example, when making predictions for two types of energy, electricity and steam, these graphs may be displayed side by side, or the two graphs may be switched by a button or the like. In this way, the screen example shown in the above embodiment is just an example, and can be flexibly changed depending on the prediction target, consumption amount actual data, supplementary information, and the like.
[0087] In addition, the energy to which the present disclosure is applicable may be anything that can be directly utilized as a motive power, such as the above-mentioned electricity or steam, or a substance that can be converted into or from these. Specific examples of energy include water and hydrogen. Furthermore, fuels synthesized from hydrogen, such as methane and ammonia, are also included in the energy in the present disclosure.
[0088] Furthermore, the equipment and facilities that are the subject of energy consumption prediction by the energy consumption prediction device 1 described in the above embodiment may be any equipment that handles a lot of energy consumption and generation, such as the factories and plants described in the above embodiment. Such equipment and facilities may be, for example, equipment and facilities that produce hydrogen, methane, ammonia, etc. in response to demand. Furthermore, energy equipment (equipment that handles energy) in such target equipment and facilities does not necessarily have to be physically close to each other. For example, when a facility that produces hydrogen using solar power generation is the subject of energy consumption prediction, the hydrogen production equipment and solar power generation equipment may be located apart from each other.
[0089] The time period corresponding to the energy consumption is not limited to one hour. For example, a 30-minute period, which is the standard for balancing control of power supply and demand, may be set as one time period. Also, a prediction may be made for one week (7 days) with one day as one time period.
[0090] In the above embodiment, the case where the user specifies the extraction conditions and the predicted value output each time has been described, but the user's operation details (extraction conditions and extraction results) may be stored and recalled.
[0091] The configuration described in the above embodiment may be incorporated as one function of an energy management system. Specifically, the operation plan of the energy equipment may be optimized based on the energy consumption prediction value obtained by the method described in the above embodiment. In this case, the energy consumption prediction value may be input to the energy management system, and a power generation plan in a power generation facility managed by the energy management system and a charge / discharge plan in a power storage facility may be created and changed based on the energy consumption prediction value. This allows the energy management system to realize control using a highly accurate energy consumption prediction value. In addition, the energy consumption prediction value obtained in the energy consumption prediction device 1 or the operation plan of the energy management system calculated based on the energy consumption prediction value may be directly transmitted from this device to other energy equipment (such as a storage battery, a gas turbine generator, or a boiler). In this case, the energy equipment to which the information is transmitted may change the control content based on the energy consumption prediction value or the operation plan.
[0092] [others] In response to prediction errors in the operation plan of energy equipment, fossil fuels such as gas turbine generators are often used as an adjustment, but in that case, it is necessary to operate at partial output with a margin for both up and down. This is not desirable from the perspective of power generation efficiency, and may lead to an increase in the cost of power generation and an increase in CO2 emissions. Therefore, this disclosure does not only relate to the economics and business profits of microgrids, but also relates to the economic energy supply and environmental load reduction of society as a whole, and contributes to Goal 7 "Ensure access to affordable, reliable, sustainable and modern energy for all" and Goal 13 "Take urgent action to mitigate climate change and its impacts" of the Sustainable Development Goals (SDGs) led by the United Nations.
[0093] [Note] The present disclosure includes the following configurations. [1] A storage unit that stores past energy consumption data of a target facility in association with information identifying the date and time when the data was acquired and supplementary information relating to the operating status of the target facility at the time the data was acquired; an extraction unit that extracts data, the auxiliary information of which matches an extraction condition specified by a user, from the energy consumption actual data stored in the storage unit, and generates prediction data to be used for predicting energy consumption; a prediction data generating unit that generates energy consumption prediction data based on the prediction data and an instruction from the user; An energy consumption prediction device comprising: [2] A clustering unit that performs a clustering process on the data extracted by the extraction unit to prepare data classified into a plurality of clusters; The energy consumption prediction device according to [1], wherein the prediction data generation unit also uses the data classified into the plurality of clusters as the prediction data. [3] The energy consumption prediction device described in [2], wherein the prediction data generation unit generates the energy consumption prediction data based on data classified into one of the multiple clusters based on instructions from the user. [4] The energy consumption prediction device according to any one of [1] to [3], wherein the prediction data generation unit creates data by performing statistical processing on the prediction data, and generates the energy consumption prediction data from the statistically processed data based on the user's specifications. [5] The energy consumption prediction device according to [4], further comprising an input interface for a user to specify the contents of statistical processing to be used for the energy consumption prediction data in the prediction data generation unit. [6] Further comprising a display unit; The display unit displays data obtained by performing statistical processing on the prediction data as a candidate for the energy consumption prediction data, The energy consumption prediction device according to [5], wherein the user uses the input interface to select data to be used for the energy consumption prediction data from among the candidates. [7] Further comprising a display unit; The energy consumption prediction device according to any one of [1] to [6], wherein the display unit presents to a user supplementary information corresponding to the past energy consumption actual data in a time series manner. [8] storing, in a storage unit, the past energy consumption performance data of the target facility in association with information specifying the date and time when the data was acquired and supplementary information which is information related to the operating status of the target facility at the time when the data was acquired; extracting data, the auxiliary information of which matches an extraction condition designated by a user, from the energy consumption actual data stored in the storage unit, and generating prediction data to be used for predicting energy consumption; generating energy consumption prediction data based on the prediction data and in accordance with an instruction from the user; The energy consumption prediction method includes: [9] storing, in a storage unit, the past energy consumption performance data of the target facility in association with information identifying the date and time when the data was acquired and supplementary information relating to the operating status of the target facility at the time when the data was acquired; extracting data, the auxiliary information of which matches an extraction condition designated by a user, from the energy consumption actual data stored in the storage unit, and generating prediction data to be used for predicting energy consumption; generating energy consumption prediction data based on the prediction data and in accordance with an instruction from the user; An energy consumption prediction program that causes a computer to execute the above. [Explanation of symbols]
[0094] 1. Energy consumption prediction device 11 Consumption Record Acquisition Department 12 Energy consumption record database (storage section) 13 Extraction part 14 Clustering Department 15 Statistical processing section (prediction data generation section) 20 Input Interface 21 Additional information input section 22 Extraction condition specification section 23 Display switching section 24 Prediction value output specification section 30 Output Interface 31 Display section 32 Prediction value output section
Claims
1. a storage unit that stores past energy consumption performance data of a target facility in association with information identifying the date and time when the data was acquired and supplementary information that is information related to the operating status of the target facility at the time the data was acquired; an extraction unit that extracts data, the auxiliary information of which matches an extraction condition specified by a user, from the energy consumption actual data stored in the storage unit, and generates prediction data to be used for predicting energy consumption; a prediction data generating unit that generates energy consumption prediction data based on the prediction data and an instruction from the user; a clustering unit that performs a clustering process on the data extracted by the extraction unit to prepare data classified into a plurality of clusters; having The prediction data generation unit also uses the data classified into the plurality of clusters as the prediction data. Energy consumption prediction device.
2. The energy consumption prediction device according to claim 1 , wherein the prediction data generating unit generates the energy consumption prediction data based on data classified into one of the plurality of clusters based on an instruction from the user.
3. A memory unit that stores past energy consumption performance data of a target facility in association with information identifying the date and time when the data was acquired and supplementary information that is information related to the operating status of the target facility at the time the data was acquired; an extraction unit that extracts data, the auxiliary information of which matches an extraction condition specified by a user, from the energy consumption actual data stored in the storage unit, and generates prediction data to be used for predicting energy consumption; a prediction data generating unit that generates energy consumption prediction data based on the prediction data and instructions from the user, the prediction data generating unit creating data by performing statistical processing on the prediction data, and generating the energy consumption prediction data from the statistically processed data based on instructions from the user; an input interface for a user to specify the content of statistical processing to be used for the energy consumption prediction data in the prediction data generating unit; An energy consumption prediction device comprising:
4. Further comprising a display unit, The display unit displays data obtained by performing statistical processing on the prediction data as a candidate for the energy consumption prediction data, The energy consumption prediction device according to claim 3 , wherein the user utilizes the input interface to select data to be used for the energy consumption prediction data from among the candidates.
5. Further comprising a display unit, The energy consumption prediction device according to claim 1 , wherein the display unit presents to the user supplementary information corresponding to the past energy consumption actual data in a time series manner.
6. storing, in a storage unit, past energy consumption performance data of the target facility in association with information specifying the date and time when the data was acquired and supplementary information which is information related to the operating status of the target facility at the time when the data was acquired; extracting data, the auxiliary information of which matches an extraction condition designated by a user, from the energy consumption actual data stored in the storage unit, and generating prediction data to be used for predicting energy consumption; preparing data classified into a plurality of clusters by performing a clustering process on the data extracted for generating the prediction data; generating energy consumption prediction data based on the prediction data and in accordance with an instruction from the user, the data classified into the plurality of clusters being also used as the prediction data; The energy consumption prediction method includes:
7. Storing in a memory unit the past energy consumption performance data of a target facility in association with information specifying the date and time when the data was acquired and supplementary information which is information related to the operating status of the target facility at the time when the data was acquired; extracting data, the auxiliary information of which matches an extraction condition designated by a user, from the energy consumption actual data stored in the storage unit, and generating prediction data to be used for predicting energy consumption; generating energy consumption prediction data based on the prediction data and instructions from the user, the data being subjected to statistical processing to generate data, and generating the energy consumption prediction data from the statistically processed data based on instructions from the user; The content of the statistical processing to be used for the energy consumption prediction data is specified by a user via an input interface. Energy consumption prediction methods.
8. storing, in a storage unit, past energy consumption performance data of the target facility in association with information specifying the date and time when the data was acquired and supplementary information which is information related to the operating status of the target facility at the time when the data was acquired; extracting data, the auxiliary information of which matches an extraction condition designated by a user, from the energy consumption actual data stored in the storage unit, and generating prediction data to be used for predicting energy consumption; preparing data classified into a plurality of clusters by performing a clustering process on the data extracted for generating the prediction data; generating energy consumption prediction data based on the prediction data and in accordance with an instruction from the user, the data classified into the plurality of clusters being also used as the prediction data; An energy consumption prediction program that causes a computer to execute the above.
9. Storing past energy consumption data of a target facility in a memory unit in association with information specifying the date and time when the data was acquired and supplementary information which is information related to the operating status of the target facility at the time when the data was acquired; extracting data, the auxiliary information of which matches an extraction condition designated by a user, from the energy consumption actual data stored in the storage unit, and generating prediction data to be used for predicting energy consumption; generating energy consumption prediction data based on the prediction data and instructions from the user, the energy consumption prediction data being generated from the statistically processed data based on instructions from the user; The content of the statistical processing to be used for the energy consumption prediction data is specified by a user via an input interface. Energy consumption prediction program.
Citation Information
Patent Citations
Method of making use of power supply network and system therefor
JP2003199249A
Display system of forecast information
JP2007072844A
Usage energy management device
JP2011010470A
Electric power charge optimization system
JP2015153349A