How to handle a phase-to-phase short circuit
By using control switches to create artificial grounding points and control current flow, phase-to-phase short circuits in three-phase power systems are quickly converted into single-phase ground faults, enabling automatic fault elimination and improving power supply safety.
Patent Information
- Application Number
- JP2023558925
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2020-12-12
- Filing Date
- 2021-12-02
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-12-02
AI Technical Summary
Conventional methods for handling phase-to-phase short circuits in three-phase non-active ground power supply systems are inefficient, taking time to process faults and causing damage due to prolonged exposure to short-circuit currents, and fail to automatically eliminate faults.
Implementing control switches in the power supply system to quickly locate and isolate phase-to-phase short-circuit faults by creating artificial grounding points and controlling current flow to convert faults into single-phase ground faults, which can be automatically tripped using control switches.
The method allows for rapid and accurate fault detection and elimination of phase-to-phase short circuits, minimizing system damage by converting faults into manageable single-phase ground faults, thereby enhancing power supply safety and reliability.
Smart Images

Figure 0007575619000001 
Figure 0007575619000002
Abstract
Description
[Technical field]
[0001] The present invention relates to the field of power supply system fault handling, and in particular to a method for handling a phase-to-phase short circuit fault in a three-phase non-effectively grounded power supply system. [Background technology]
[0002] At present, when a phase-to-phase short circuit occurs for a circuit in a three-phase non-effectively grounded power supply system, the usual methods are as follows: 1, the method of adopting reclosing: first disconnect the first circuit breaker on this circuit, and then close this first circuit breaker. If it is an instantaneous phase-to-phase short circuit, it will be eliminated after the first circuit breaker is closed, and normal power supply will continue. If this phase-to-phase short circuit fault still exists after the first circuit breaker is closed, disconnect the first circuit breaker and wait for inspection. 2, the method of adopting the time-step cooperation method: that is, the circuit breakers of the same circuit are different according to the distance from the power source, and adjust different overcurrent trip times, and the closer to the power source, the longer the trip time, and the generally settling step is 100ms, and this time is determined by the opening and closing time of the machine operation and the consumption time of the algorithm, this method can isolate the fault area, but for faults whose fault points are close to the power source, the power supply system has a longer time to withstand the short circuit current, and the impact on the power grid is greater. 3. Trip the first circuit breaker due to overcurrent, then trip the last circuit breaker. If the fault occurs after the last circuit breaker, the fault can be eliminated; otherwise, close the first circuit breaker; if there is still a fault current, trip the first circuit breaker due to overcurrent, then open the second circuit breaker; if a phase-to-phase short circuit occurs between the second circuit breaker and the last circuit breaker, the fault can be eliminated; by analogy, open the circuit breakers in order forward until the fault is eliminated. However, during this operation, the circuit breakers that have not been opened and the power supply system continue to be shocked by a large short-circuit current, and if the time is too long or the number of times is too large, it may cause damage to the circuit. If the duration of the phase-to-phase short circuit should not exceed 300 milliseconds and the trip time of the circuit breaker is 100 milliseconds, generally, it should not exceed three circuit breakers on the circuit, otherwise the above method may cause the circuit to be shocked for more than 300 milliseconds. For this reason, the conventional phase-to-phase short circuit processing methods all have the disadvantages of taking a long time to process the fault and not being able to automatically eliminate the fault. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] China Patent Application Publication No. 101505053 Summary of the Invention [Problem to be solved by the invention]
[0004] The present invention aims to provide a method for treating a phase-to-phase short circuit, which can quickly locate a phase-to-phase short circuit fault section in a three-phase non-effectively grounded power supply system, automatically and accurately remove the fault, effectively improve the quality of treating the phase-to-phase short circuit fault, and improve the safety of power supply. [Means for solving the problem]
[0005] In order to achieve the above object, the present invention employs the following embodiments. A plurality of control switches are distributed in a three-phase non-effective grounding power supply system, and the control switches can cut off a circuit according to a current time; When a simple two-phase or three-phase short circuit occurs in one circuit, (a) process according to the following method: maintain one faulty phase of the circuit in conduction, trip the other faulty phase, artificially ground another faulty phase that is in conduction with the one faulty phase, then ground one live phase or neutral point of the three-phase non-effectively grounded power supply system except for the one faulty phase so as to form a closed circuit with the one faulty phase and generate a current, set the current time for triggering the disconnection in the control switch downstream of the power source to be shorter than the current time for triggering the disconnection in the control switch upstream of the power source, and after a control switch reaches a trigger condition and disconnects the circuit, stop grounding the other fault and stop grounding the one live phase or the neutral point; A method for treating a phase-to-phase short circuit, characterized in that, when a ground fault occurs in one circuit due to a two-phase or three-phase short circuit, the method treats the fault in a manner similar to the above method (a), or (b) maintains one faulty phase of the circuit in conduction, trips another faulty phase, and then grounds one live phase or neutral point of the three-phase non-grounded power supply system excluding the one faulty phase so as to form a closed circuit with the one faulty phase to generate current, sets a current duration for triggering disconnection in a control switch downstream of a power source to be shorter than a current duration for triggering disconnection in a control switch upstream of a power source, and stops grounding the one live phase or neutral point after a control switch reaches a trigger condition and disconnects the circuit.
[0006] Preferably, in the method (a) and method (b), maintaining the continuity of the one faulted phase includes tripping the one faulted phase and then conducting the one faulted phase, and not tripping the one faulted phase.
[0007] Preferably, in the method (a), first, a first circuit breaker of the one circuit is tripped, then the one faulty phase is short-circuited at the first circuit breaker via a first switch to make the one faulty phase conductive, the first switch being the control switch, the other faulty phase is artificially grounded at the outlet of the first circuit breaker via a third switch, and the one live phase is artificially grounded at the inlet or outlet of the first circuit breaker via a second switch to form a closed circuit with the one fault and generate a current. At the neutral point Grounded, be After the control switch reaches a trigger condition and breaks the circuit, the first switch and the third switch are turned off, and the second switch is disconnected from the ground, and then the first circuit breaker is closed.
[0008] Preferably, the method (b) includes first tripping a first circuit breaker of the first line, then shorting the one faulty phase with the first circuit breaker through a first switch to make the one faulty phase conductive, the first switch being the control switch, and connecting the one live phase to the inlet or the second circuit breaker through a second switch to form a closed circuit with the one fault to generate a current. neutral point Grounded at be After the control switch reaches a trigger condition and breaks the circuit, the first switch is turned off and the second switch is de-grounded, and then the first circuit breaker is closed.
[0009] Preferably, the second switch is a power electronic switch.
[0010] Preferably, the power electronic switches are insulated gate bipolar transistors.
[0011] Preferably, the control switch can be disconnected in a timely manner after a trigger condition is reached, so as to avoid the current time detected in the previous control switch reaching the trigger condition of the previous control switch.
[0012] Preferably, the method (a) and method (b) 2. The method for treating a phase-to-phase short circuit according to claim 1, further comprising the step of connecting a current limiting resistor in series to the closed circuit.
[0013] Preferably, a current limiting resistor is connected in series between the second switch and ground.
[0014] Preferably, the current limiting resistor is a variable resistor. Effect of the Invention
[0015] The beneficial effects of the present invention are as follows: After the occurrence of phase-to-phase short circuit fault, first cut off the original fault current, and then a suitable current can be artificially created and flow through the new circuit of the original whole fault circuit or partial fault circuit, which is favorable for fault detection and elimination. Specifically, after one fault phase is single-phase grounded, another fault phase (two-phase short circuit) is cut off, or the third phase (three-phase short circuit) is cut off at the same time, one live phase of the power supply system or the neutral point of the system is grounded to form a closed circuit with the fault phase of the ground to generate a current of controllable magnitude, and the current time is detected through the control switch of the fault phase, and the control switch is turned off after reaching the trigger condition, and the current time of triggering the disconnection in the control switch downstream of the power supply is shorter than the current time of triggering the disconnection in the control switch upstream of the power supply, so the control switch after the phase-to-phase short circuit fault point on the fault phase does not enter a closed circuit and there is no current flowing, so the first control switch before the phase-to-phase short circuit fault point is turned off first to determine the elimination of the phase-to-phase short circuit fault. In the above case, if the single-phase grounding is caused by a phase-to-phase short circuit, the grounding point can be used as it is, or an artificially created grounding point can be used. If it is a simple phase-to-phase short circuit, an artificial grounding point must be created, that is, a grounding point must be created in another faulty phase through a third switch. This grounding point is preferably located at the outlet of the first circuit breaker, and can also be located at another location in this other faulty phase. In particular, if it is located after the phase-to-phase short circuit point, the control switch of this other faulty phase can be set accordingly so as not to detect the corresponding phase current, that is, it can be set in advance so as not to detect the phase distinction as a rule, for example, AB phase does not detect B phase, AC phase does not detect C phase, BC phase does not detect C phase, and ABC phase does not detect C phase, so that it is not cut off earlier than the control switch to be cut off. This method converts and processes the phase-to-phase fault into a single-phase ground fault, and can automatically trip using the control switch, quickly, accurately and automatically eliminate the fault, then stop the other fault grounding and then stop the grounding of the live phase, and finally close the first circuit breaker to restore power supply. [Brief description of the drawings]
[0016] [Figure 1]FIG. 2 is a wiring schematic diagram of one example of the method of the present invention. [Diagram 2] FIG. 2 is a wiring schematic diagram of another example of the method of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0017] The present invention will be further described with reference to the accompanying drawings and specific embodiments. A three-phase power supply system is a general non-effective ground system, and generally, a busbar of a three-phase power supply system has multiple lead wires, and each lead wire is provided with multiple control switches, and the control switches can detect the current time on one, two or three phases on the circuit according to their installation, and can be set to disconnect the three-phase circuit when the current time passing through any phase reaches a preset value. A specific example of the control switch includes a control unit, a current detection unit and an execution unit, and the current detection units can detect each phase current of the three-phase circuit respectively, and the control unit can compare the current time by the current detection unit with a preset value, and can be set to send a signal to disconnect the three-phase circuit by the execution unit when the current time of any phase reaches a preset value. For the preset value of the current time that triggers disconnection, the preset value of the current time of the control switch downstream in the power supply direction is shorter than the preset value upstream in the power supply direction, and the upstream in the power supply direction is relatively close to the power supply, and the downstream in the power supply direction is relatively far from the power supply, that is, the power is discharged from the power supply and transmitted from upstream to downstream. Or, along the upstream and downstream of the power supply, the shorter the preset value that triggers the disconnection of the control switch farther from the power supply, the earlier the trigger condition is reached and the more likely it is to be disconnected. In practice, the circuit breaker installed on each lead wire can detect the time that the current passes through the circuit breaker, and can be set to disconnect the circuit when a certain current passes through a certain phase or multiple phases for a certain time, so the circuit breaker can be considered as a control switch.
[0018] As shown in FIG. 1, in one specific embodiment, a first circuit breaker 90 is installed near the busbar in each of the three outgoing wires of the ABC three phases, and a first switch 1 is provided in the first circuit breaker 90, and the first switch 1 includes three switches KA1, KB1, and KC1 attached to the ABC three phases, and the first switch is the control switch, that is, the switches KA1, KB1, and KC1 are all disconnected according to a preset current time, and the first switch 1 can short-circuit a certain phase with the first circuit breaker 90 (for example, after the circuit is disconnected by the first circuit breaker 90, the switch KA1 of the first switch 1 can be closed, that is, the A phase can be short-circuited, so that the A phase can bypass the first circuit breaker 90 and re-conduct), so that the first circuit breaker is conductive and charged even if it is disconnected or short-circuited (of course, it is possible to keep the first circuit breaker from the beginning not to disconnect any one phase, and in this case, it will be charged from the beginning without the need to short-circuit using the first switch). A plurality of circuit breakers (these circuit breakers after the first circuit breaker are regarded as control switches) are provided after the first circuit breaker 90, and each circuit breaker can cut off the three-phase circuit according to the current time of a certain phase. A third switch 3 is installed at the outlet of the first circuit breaker 90 of each lead-out wire, and the three switches KA3, KB3, and KC3 of the third switch 3 can respectively conduct the three phases A, B, C to the earth, so that any one of the phases can be grounded. At the same time, a second switch 2 (i.e., the second switch 2 is located at the inlet of the first circuit breaker 90, or the second switch 2 is installed at the system neutral point, in this case only one phase needs to be opened and closed) is installed on the busbar, and the three switches KA2, KB2, and KC2 of the second switch 2 can respectively ground and cut off the three phases of the busbar. In one preferred example, the second switch 2 is provided in series with a variable resistance resistor to limit the current and prevent too high a phase-to-phase short circuit current from damaging the system.When a simple phase-to-phase short circuit (for example, a BC 2-phase short circuit or a 3-phase short circuit) occurs at point F, the first circuit breaker 90 is tripped to disconnect the 3-phase circuit, and then the first switch 1 is closed to make the faulty phase (for example, if it is phase B, switch KB1 is closed) conductive and charged, and then, at the outlet of the first circuit breaker 90, the third switch 3 is used to connect to another faulty phase (i.e., phase C, in which case switch KC3 is closed) at point D. In this way, phase B of this circuit is grounded to point D from short circuit point F through phase C, forming a single-phase ground. Then, by grounding phase A (in this case, phase A is the live phase) at the inlet of the first circuit breaker via one of the second switches, switch KA2, a current is generated that flows through the faulty phase B via the ground point E of the second switch, the ground point D of the third switch, and the phase-to-phase short circuit point F (or phase C may be grounded using switch KC2 to generate a current that forms a closed circuit), and when the current time reaches the trigger condition of the closest control switch 91 before the phase-to-phase short circuit point F, this control switch 91 cuts off the circuit and removes the phase-to-phase short circuit point F from the system (since it cuts off in a timely manner, the current time has not yet reached the trigger condition of the more upstream control switch 92 when it is cut off, so the control switch 92 is not cut off, and no current flows in the control switch 93 after the phase-to-phase short circuit point on phase B, so it does not operate). Then, switch KB1 on the first switch 1 is turned off, KC3 in the third switch 3 is disconnected from the ground, KA2 in the second switch is disconnected from the ground, and finally the first switch 90 is closed to restore the circuit power supply.
[0019] In one embodiment, the first circuit breaker can be controlled separately for three phases and have the function of a control switch, in which case the first circuit breaker can be directly used to hold the continuity of one fault and trip the other faulty phases. At the same time, the current time for the first circuit breaker to trigger disconnection can be set to the longest (i.e., longer than the second circuit breaker), indicating that if the circuit breaker after the first circuit breaker (used as a control switch) is not tripped, a phase-to-phase short circuit occurs between the first circuit breaker and the second circuit breaker, and based on the set trigger condition, the first circuit breaker will definitely trip and can isolate the fault.
[0020] As shown in Fig. 2, in another embodiment, when a phase-to-phase short circuit occurs at point F and is grounded at the short circuit point, the third switch of the above method can be used to create an artificial ground point, and then generate current through the second switch, that is, the above method is still applicable. In the case of such a ground-related fault, there is another method in which the first circuit breaker 90 is tripped to disconnect the three-phase circuit, and then the switch KB1 of the first switch is closed to directly use the ground point at the short circuit point to create a single-phase ground, and then the A phase (or C phase) is grounded at the inlet of the first circuit breaker through the second switch, generating current, which flows through the faulty phase B phase through the ground point E of the second switch and the ground point F at the phase-to-phase short circuit point, and when the current time reaches the trigger condition of the closest control switch 91 before the phase-to-phase short circuit point, the control switch 91 will break the circuit and eliminate the phase-to-phase short circuit point F from the system. Thereafter, the first switch KB1 is disconnected, the second switch KB2 stops grounding the live phase, and the first circuit breaker 90 is closed to restore circuit power.
[0021] In the above embodiment, the tripping of the control switch should be timely, and the current time of different control switches should be set to a sufficient difference so that the current time trigger condition of the previous control switch is also detected during the tripping of a control switch and turned off, to avoid unreasonable large-area power outage. After the control switch is tripped, the second switch can stop grounding.
[0022] The above processing method can also eliminate faults when a three-phase short circuit occurs simultaneously at the phase-to-phase short circuit point or when a ground is also involved.
[0023] In one specific embodiment, a power electronic switch, such as an insulated gate bipolar transistor, is used to provide momentary grounding.
[0024] The above examples are merely some illustrations of the concept and realization of the present invention, and are not intended to limit the same. Any technical solution that does not make any substantial transformation under the concept of the present invention is still within the scope of protection. [Industrial Applicability]
[0025] Through experiments in a three-phase power supply system, the above method is completely feasible.
Claims
1. A plurality of control switches are distributed in the three-phase non-effective grounding power supply system, and the control switches can cut off the circuit according to the current time; When a simple two-phase or three-phase short circuit occurs in one circuit, (a) keep one faulty phase of the circuit conductive, trip the other faulty phase, artificially ground another faulty phase conductive with the one faulty phase, then ground one live phase or neutral point of the three-phase non-effectively grounded power supply system except for the one faulty phase so as to form a closed circuit with the one faulty phase and generate a current, set the current time for triggering disconnection in the control switch downstream of the power source to be shorter than the current time for triggering disconnection in the control switch upstream of the power source, and after a control switch reaches a trigger condition and disconnects the circuit, stop grounding the other fault and stop grounding the one live phase or the neutral point; A method for treating a phase-to-phase short circuit, characterized in that, when a ground fault occurs in one circuit due to a two-phase or three-phase short circuit, the method is performed in accordance with the above method (a), or (b) the method is performed in accordance with the above method, in which one faulty phase of the circuit is maintained conductive, another faulty phase is tripped, and then one live phase or neutral point of the three-phase non-grounded power supply system other than the one faulty phase is grounded so as to form a closed circuit with the one faulty phase to generate a current, a current duration for triggering disconnection in a control switch downstream of a power source is set to be shorter than a current duration for triggering disconnection in a control switch upstream of a power source, and after a control switch reaches a trigger condition and disconnects the circuit, the grounding of the one live phase or the neutral point is stopped.
2. 2. The method of claim 1, wherein in the methods (a) and (b), maintaining the continuity of the one faulted phase includes tripping the one faulted phase and then enabling the one faulted phase, and not tripping the one faulted phase.
3. 2. The method for treating a phase-to-phase short circuit according to claim 1, wherein the method (a) includes: first tripping a first circuit breaker of the one circuit; then shorting the one faulty phase in the first circuit breaker via a first switch to make the one faulty phase conductive; the first switch is the control switch; artificially grounding the other faulty phase at the outlet of the first circuit breaker via a third switch; grounding the one live phase at the inlet or neutral of the first circuit breaker via a second switch to form a closed circuit with the one fault and generate a current; and after a trigger condition is reached and a control switch breaks the circuit, turning off the first switch and the third switch and stopping the grounding of the second switch; and then closing the first circuit breaker.
4. The method for handling a phase-to-phase short circuit according to claim 1, characterized in that in the method (b), first, a first circuit breaker of the one circuit is tripped, then the one faulty phase is short-circuited by the first circuit breaker via a first switch to make the one faulty phase conductive, the first switch is the control switch, and the one live phase is grounded at the inlet or neutral point of the first circuit breaker via a second switch to form a closed circuit with the one fault to generate a current, after a trigger condition is reached and a control switch breaks the circuit, the first switch is turned off and the second switch is stopped from being grounded, and then the first circuit breaker is closed.
5. 5. A method for handling a phase-to-phase short circuit as claimed in claim 3 or 4, characterized in that the second switch is a power electronic switch.
6. 6. The method for treating a phase-to-phase short circuit according to claim 5, wherein said power electronic switch is an insulated gate bipolar transistor.
7. 2. The method for handling a phase-to-phase short circuit according to claim 1, wherein the control switch can be disconnected in a timely manner after a trigger condition is reached, so as to avoid a current time detected in a previous control switch from reaching a trigger condition of the previous control switch.
8. 2. The method for treating a phase-to-phase short circuit according to claim 1, wherein in the method (a) and the method (b), a current limiting resistor is connected in series to the closed circuit.
9. 5. A method for treating an inter-phase short circuit according to claim 3, further comprising the step of connecting a current limiting resistor in series between said second switch and ground.
10. 10. The method for treating a phase-to-phase short circuit according to claim 9, wherein the current limiting resistor is a variable resistor.
Citation Information
Patent Citations
User demarcation circuit breaker set apparatus and protection method
CN101505053A
Method of reclosing circuit at high speed
JP1982135617A
Reclosing system
JP1996033186A
Load connection type distribution line
JP2005184945A