Ships

The ship design addresses the high installation costs of double pipes by using single and double pipes strategically within watertight compartments, reducing installation effort and costs while ensuring efficient fuel supply to heat engines.

JP7580549B2Active Publication Date: 2024-11-11MITSUBISHI SHIPBUILDING CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
JP2023147612
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-09-12
Publication Date
2024-11-11
Estimated Expiration
2040-01-31

AI Technical Summary

Technical Problem

The installation of double pipes for liquefied gas fuel in ships, such as those using LPG, is time-consuming and costly due to the need for manufacturing, installation, and maintenance, especially in areas like engine rooms.

Method used

A ship design that includes a hull with bulkheads and partition walls forming watertight compartments, a liquefied gas tank outside the engine room, and pressure regulating valves with single and double pipes to supply fuel gas to heat engines, reducing the need for double pipes within these compartments.

Benefits of technology

This design reduces the effort and cost associated with installing double pipes by utilizing single pipes in certain compartments and minimizing the use of double pipes, while maintaining effective fuel supply to the engines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007580549000001
    Figure 0007580549000001
  • Figure 0007580549000002
    Figure 0007580549000002
  • Figure 0007580549000003
    Figure 0007580549000003
Patent Text Reader

Abstract

To reduce the effort and expense for installing a double pipe.SOLUTION: A vessel includes: a barrier forming an engine chamber where a heat engine is stored along with a pair of broadsides provided on a lower layer than freeboard deck in a hull; a partition wall arranged to surround a connection part of the barrier and the broadsides and forming a water tight section extending along the vertical range of the engine chamber; a liquefied gas tank provided on a same layer as the engine chamber as well as being provided outside the engine chamber for storing liquefied gas; a pressure adjustment valve stored in a valve chamber arranged adjacent to the water tight section for adjusting the pressure of fuel gas supplied to the heat engine; tank side piping that supplies the fuel gas which is gasified liquefied gas in the liquefied gas tank to the pressure adjustment valve and is provided with, at least partially, single piping arranged in the water tight section; and heat engine side piping that supplies the fuel gas through the pressure adjustment valve to the heat engine, and is composed of double layered piping extending in the engine chamber.SELECTED DRAWING: Figure 6
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to marine vessels. [Background technology]

[0002] Patent Document 1 discloses a ship that includes a fuel tank provided in the hull and a drive unit that is driven by LPG (liquefied petroleum gas) stored in the fuel tank. The ship in Patent Document 1 sends the LPG stored in the fuel tank through a pipe to the drive unit provided inside the hull. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2018-177012 A Summary of the Invention [Problem to be solved by the invention]

[0004] In a ship such as that described in Patent Document 1, when piping for sending LPG to a predetermined area inside the hull such as the engine room is provided, the piping for sending LPG needs to be enclosed with a duct or the like. For example, in an engine room that houses a drive unit, it may be difficult to install a duct. In such cases where it is difficult to install a duct, a double pipe having an inner pipe and an outer pipe may be used as the piping for sending liquefied gas fuel. However, when a double pipe is used as the piping for sending liquefied gas fuel, the installation of the double pipe requires time and effort, such as manufacturing, installation, post-installation inspection, and maintenance.

[0005] The present disclosure aims to provide a ship that can reduce the effort and cost associated with installing double pipes. [Means for solving the problem]

[0006] Another vessel according to the present disclosure includes a hull, a bulkhead, a pair of partition walls, a liquefied gas tank, a pressure regulating valve, a tank side piping, and a heat engine side piping. The hull has a pair of shipboard sides. The bulkhead is provided below the freeboard deck within the hull, and together with the pair of shipboard sides, forms an engine room in which a plurality of heat engines arranged in the ship width direction are housed. The pair of partition walls are arranged to surround the connection between the bulkhead and the pair of shipboard sides, respectively, and form a pair of watertight compartments extending across the upper and lower ranges of the engine room. The liquefied gas tank is provided on the same level as the engine room and is provided outside the engine room to store liquefied gas. The pressure regulating valves are provided in the same number as the heat engines, are housed in valve rooms arranged adjacent to the pair of watertight compartments, and adjust the pressure of the fuel gas supplied to the plurality of heat engines, respectively. The tank-side piping supplies the fuel gas obtained by vaporizing the liquefied gas in the liquefied gas tank to the pressure regulating valves, and at least a portion of the piping has single pipes that are respectively arranged in a pair of the watertight compartments. The heat engine-side piping The tank-side piping supplies the pressure to the pressure regulating valves. The fuel gas passing through the pressure regulating valve is supplied to the heat engine, and the fuel gas supply system comprises a double pipe extending within the engine room. Effect of the Invention

[0007] According to the ship of the present disclosure, the effort and cost associated with installing double pipes can be reduced. [Brief description of the drawings]

[0008] [Figure 1] 1 is a side view showing a schematic overall configuration of a vessel according to a reference example of the present disclosure. [Diagram 2] 1 is a plan view showing an example of the arrangement of an engine room, a watertight compartment, a first pipe, and a second pipe provided in a ship according to a reference example of the present disclosure. FIG. [Diagram 3] 1 is a side cross-sectional view showing an example of the arrangement of an engine room, a watertight compartment, a first pipe, and a second pipe provided in a ship according to a reference example of the present disclosure. FIG. [Figure 4] FIG. 2 is a functional block diagram showing the configuration of a liquid gas tank and a fuel supply device provided in a marine vessel according to a reference example of the present disclosure. [Diagram 5]1 is a plan view showing an example of the arrangement of an engine room, a watertight compartment, a first pipe, and a second pipe provided in a ship related to a modified example of a reference example of the present disclosure. FIG. [Figure 6] 1 is a plan view showing an example of the arrangement of an engine room, a watertight compartment, tank side piping, and a heat engine side piping provided in a ship according to an embodiment of the present disclosure. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] <Reference example> (Overall configuration of the ship) Hereinafter, a vessel according to a reference example and an embodiment of the present disclosure will be described with reference to Figs. 1 to 5. As shown in Fig. 1, the ship 1 of this reference example mainly comprises a hull 2, a heat engine 20, a liquefied gas tank 30A, pressure regulating valves 41M, 41G, first pipes 51M, 51G, and second pipes 52M, 52G. The type of the ship 1 is not limited to a specific one. Examples of the type of the ship 1 include a ferry, a RORO ship (Roll-on / Roll-off ship), and a PCTC (Pure Car & Truck Carrier).

[0010] The hull 2 ​​has a pair of side panels 3A, 3B that form its outer hull, and a ship bottom 4. The side panels 3A, 3B are made up of a pair of side panel shells that form the port and starboard sides, respectively. The ship bottom 4 has a bottom panel that connects the side panels 3A, 3B. The pair of side panels 3A, 3B and the ship bottom 4 give the outer hull 2 ​​a U-shape in a cross section perpendicular to the bow-stern direction FA.

[0011] The hull 2 ​​is equipped with multiple decks inside, including a freeboard deck 5 and an upper deck 8. The freeboard deck 5 in this reference example is the lowest of the full-length decks located above the load waterline. The upper deck 8 is the highest of the full-length decks. The upper deck 8 in this reference example can also be called an exposed deck that is exposed to the outside. The hull 2 ​​illustrated in this reference example further includes a deck 7 below the freeboard deck 5.

[0012] As shown in Figures 1 and 2, the hull 2 ​​is provided with bulkheads 11, 12, and 13 between the freeboard deck 5 and the deck 7. The bulkheads 11 and 12 are arranged at intervals in the bow-stern direction FA. Similarly, the bulkheads 12 and 13 are arranged at intervals in the bow-stern direction FA. The bulkheads 11, 12, and 13 each extend from the ship's side 3A to the ship's side 3B, and each extend from the freeboard deck 5 to the deck 7. In other words, the space between the freeboard deck 5 and the deck 7 is divided in the bow-stern direction by these bulkheads 11, 12, and 13.

[0013] (Engine Room Configuration) In this reference example, the section between the freeboard deck 5 and the deck 7 and between the bulkhead 11 and the bulkhead 13 is defined as an engine room 10. The engine room 10 includes a main engine room 10A and a generator room 10B. The main engine room 10A is formed by the ship's sides 3A and 3B, the freeboard deck 5 and the deck 7, the bulkhead 11, and the bulkhead 12. The generator room 10B is formed by the ship's sides 3A and 3B, the freeboard deck 5 and the deck 7, the bulkhead 12, and the bulkhead 13. The engine room 10 and the generator room 10B are adjacent to each other in the bow-stern direction FA. In this reference example, watertight compartments S11 and S12 (described later) between the bulkhead 11 and the bulkhead 13 are not included in the engine room 10 (this also applies to watertight compartments in the modified examples and the embodiments of the reference example below).

[0014] (Watertight compartment configuration) Watertight compartments S11, S12 are provided between the freeboard deck 5 and the deck 7. The watertight compartments S11, S12 are arranged symmetrically in the ship's width direction W across the center C of the ship's width direction W of the hull 2. The watertight compartments S11, S12 are surrounded by shipboard sides 3A, 3B and compartment walls 15A, 15B, and are formed across the entire upper and lower areas of the engine room 10 between the freeboard deck 5 and the deck 7. The compartment walls 15A, 15B in this reference example are formed by a part of the bulkhead 12 and partition walls 16A, 16B (described later).

[0015] The partition wall 12 includes a first partition wall portion 12a, a second partition wall portion 12b, a third partition wall portion 12c, a fourth partition wall portion 12d, and a fifth partition wall portion 12e. The first bulkhead portion 12a is connected to the ship's side 3A and extends inward from the ship's side 3A in the ship's width direction W. The second bulkhead portion 12b is provided so as to be continuous with the inner edge of the first bulkhead portion 12a in the ship's width direction W and extends to the stern side in the fore-aft direction FA. The second bulkhead portion 12b is provided at a distance inward in the ship's width direction W of the hull 2 ​​from the ship's side 3A.

[0016] The third bulkhead portion 12c is provided so as to be continuous with the aft end edge in the fore-aft direction FA of the second bulkhead portion 12b and extends in the ship's width direction W. The third bulkhead portion 12c is provided so as to extend from the watertight compartment S11 to the watertight compartment S12. The fourth bulkhead portion 12d is provided symmetrically with the second bulkhead portion 12b in the ship's width direction W. The fourth bulkhead portion 12d extends from the starboard end edge in the fore-aft direction FA of the third bulkhead portion 12c to the bow side in the fore-aft direction FA. The fifth bulkhead portion 12e is provided symmetrically with the first bulkhead portion 12a in the ship's width direction W. The fifth bulkhead portion 12e extends from the bow end edge in the fore-aft direction FA of the fourth bulkhead portion 12d outward in the ship's width direction W and is connected to the ship's side 3B.

[0017] The partition wall 16A on the port side (in other words, the side of the ship 3A) comprises a first partition wall portion 16a and a second partition wall portion 16b. The first partition wall portion 16a is provided at a distance from the first bulkhead portion 12a in the fore-aft direction FA. The first partition wall portion 16a is connected to the side of the ship 3A and extends inward in the ship width direction W from the side of the ship 3A in parallel with the first bulkhead portion 12a. The second partition wall portion 16b is provided continuously from the inner end edge of the first partition wall portion 16a in the ship width direction W. The second partition wall portion 16b is provided at a distance from the side of the ship 3A on the inner side in the ship width direction of the hull 2. The second partition wall portion 16b is provided so as to extend in the fore-aft direction FA so as to be continuous with the second bulkhead portion 12b.

[0018] The partition wall 16B on the starboard side (in other words, the side of the ship 3B) has a third partition wall portion 16c and a fourth partition wall portion 16d. The third partition wall portion 16c is provided at a distance from the fifth bulkhead portion 12e in the fore-aft direction FA. The third partition wall portion 16c is connected to the side of the ship 3B and extends inward in the ship width direction W from the side of the ship 3B in parallel with the fifth bulkhead portion 12e. The fourth partition wall portion 16d is provided so as to be continuous with the inner end edge of the third partition wall portion 16c in the ship width direction W. The fourth partition wall portion 16d is provided at a distance from the side of the ship 3B on the inner side in the ship width direction of the hull 2. The fourth partition wall portion 16d is provided so as to extend in the fore-aft direction FA so as to be continuous with the fourth bulkhead portion 12d.

[0019] The port-side partition wall 15A is formed by the first bulkhead portion 12a and the second bulkhead portion 12b which are part of the bulkhead 12, and the first partition wall portion 16a and the second partition wall portion 16b which constitute the partition wall 16A. The port-side watertight compartment S11 is formed by the port-side side 3A, the first bulkhead portion 12a and the second bulkhead portion 12b which are part of the bulkhead 12, and the first partition wall portion 16a and the second partition wall portion 16b which constitute the partition wall 16A.

[0020] The starboard-side partition wall 15B is formed by the fifth bulkhead portion 12e and the fourth bulkhead portion 12d which are part of the bulkhead 12, and the third partition wall portion 16c and the fourth partition wall portion 16d which constitute the partition wall 16B. The starboard-side watertight compartment S12 is formed by the starboard-side side 3B, the fifth bulkhead portion 12e and the fourth bulkhead portion 12d which are part of the bulkhead 12, and the third partition wall portion 16c and the fourth partition wall portion 16d which constitute the partition wall 16B.

[0021] The watertight compartments S11, S12 are provided to straddle both sides in the bow-stern direction FA of the third bulkhead portion 12c of the bulkhead 12. In the present disclosure, the watertight compartments S11, S12 function as watertight rooms Sa, Sb that prevent water from entering the engine room 10 from outside the ship in the event that the shipboard sides 3A, 3B are damaged.

[0022] (Duct configuration) As shown in FIG. 3, the hull 2 ​​is provided with ducts D1, D2 above the watertight compartments S11, S12. The ducts D1, D2 extend upward from the upper ends of the watertight compartments S11, S12 along the ship sides 3A, 3B. The lower ends of the ducts D1, D2 communicate with the watertight compartments S11, S12. The upper ends of the ducts D1, D2 open upward on the upper deck 8. Here, in this reference example, the watertight compartments S11, S12 have a larger horizontal cross-sectional area than the ducts D1, D2. In this reference example, the freeboard deck 5 is a vehicle deck on which vehicles can board. The ducts D1, D2 are provided to penetrate the compartments in which the vehicles are loaded in the height direction.

[0023] (Structure of a heat engine) 2 and 3, the heat engine 20 is accommodated in the engine room 10. The heat engine 20 is an internal combustion engine or an external combustion engine that uses liquefied gas as fuel. The ship 1 in this reference example is equipped with a main engine 21 and a generator engine 22 as the heat engine 20. The main engine 21 is disposed in the main engine room 10A. The main engine 21 exerts a propulsive force for sailing the ship 1. The main engine 21 rotates and drives a screw 9 (see FIG. 1) provided outside the rear part 2b of the hull 2. The main engine 21 may be, for example, a steam turbine, a gas turbine, a reciprocating engine, or the like. In the present disclosure, two sets of the main engine 21 and the screw 9 are provided at an interval in the ship's width direction W.

[0024] The generator engine 22 is disposed in the generator room 10B. The generator engine 22 drives a generator (not shown). The generator engine 22 may be, for example, a gas turbine or a reciprocating engine. Rotational energy generated by the generator engine 22 is converted into electrical energy by the generator and supplied to each part in the hull 2. In the present disclosure, three generator engines 22 are provided at intervals in the ship's width direction W.

[0025] (Configuration of liquefied gas tank) As shown in Fig. 1, the liquefied gas tank 30A is provided outside the engine room 10. In the present disclosure, the liquefied gas tank 30A is provided on the upper deck 8 of the rear part 2b of the hull 2. In the present disclosure, a plurality of liquefied gas tanks 30A (for example, two tanks) are provided at intervals in the ship's width direction W. The liquefied gas tank 30A in this reference example is a dedicated fuel tank for storing liquefied gas such as liquefied natural gas (LNG) that serves as fuel for the main engine 21, the generator engine 22, etc.

[0026] (Configuration of liquefied gas tank associated equipment) The hull 2 ​​further includes a vent riser 31, a bunker station 33, and a fuel supply device 35. The vent riser 31 is provided to extend upward. The vent riser 31 discharges boil-off gas vaporized in the liquefied gas tank 30A in an emergency or the like. The bunker station 33 loads and unloads the liquefied gas tank 30A between the bunker station 33 and land. The bunker station 33 includes a connection port that can be connected to a facility on the land side, a connection pipe that connects the connection port and the liquefied gas tank 30A, a loading and unloading pump (none of which are shown) for supplying liquefied gas through the connection pipe, and the like.

[0027] The fuel supply device 35 supplies the liquefied gas in the liquefied gas tank 30A to the heat engine 20 (the main engine 21, the generator engine 22). In the present disclosure, the fuel supply device 35 is provided on the upper deck 8.

[0028] As shown in FIG. 4, the fuel supply device 35 mainly includes a pump 35a, an evaporator 35b, a gas heater 35c, and a gas incinerator 35d. The pump 35a sends out the liquefied gas G1 in the liquefied gas tank 30A to the first pipes 51M and 51G described later. The evaporator 35b evaporates and vaporizes the liquefied gas G1 to generate the fuel gas G2. The gas heater 35c heats and pressurizes the boil-off gas G3 generated in the liquefied gas tank 30A. The gas incinerator 35d combusts the boil-off gas G3 pressurized by the gas heater 35c.

[0029] (Configuration of pressure regulating valve) 3, the pressure regulating valves 41M, 41G respectively regulate the pressure of the fuel gas G2 supplied to the main engine 21 of the heat engine 20 and the pressure of the fuel gas G2 supplied to the generator engine 22. The pressure regulating valves 41M, 41G are accommodated in a valve chamber 40G provided in the engine room 10.

[0030] As shown in Figures 2 and 3, the valve chamber 40M is disposed in the main engine room 10A. The valve chamber 40M has an airtight structure. The valve chamber 40M accommodates therein the same number of pressure regulating valves 41M as the main engines 21. The valve chamber 40M illustrated in this reference example is disposed on the stern side of the bulkhead 12 in the bow-stern direction FA, and is provided adjacent to the bulkhead 12. The valve chamber 40M is formed by the third bulkhead portion 12c of the bulkhead 12, the second partition wall portion 16b of the partition wall 16A, the fourth partition wall portion 16d of the partition wall 16B, and a valve chamber wall 42M.

[0031] The valve chamber wall 42M is provided at a distance from the third bulkhead portion 12c on the stern side in the bow-stern direction FA. The valve chamber wall 42M extends from the second partition wall portion 16b to the fourth partition wall portion 16d, and also extends from the freeboard deck 5 to the deck 7. In this way, the valve chamber 40M is provided adjacent to the watertight compartments S11, S12 via the second partition wall portion 16b (partition wall 16A) and the fourth partition wall portion 16d (partition wall 16B).

[0032] The valve chamber 40G is disposed within the generator chamber 10B. Like the valve chamber 40M, the valve chamber 40G has an airtight structure. The valve chamber 40G accommodates therein the same number of pressure regulating valves 41G as the generator engines 22. The valve chamber 40G illustrated in this reference example is disposed on the bow side of the bulkhead 12 in the bow-stern direction FA, and is provided adjacent to the bulkhead 12. The valve chamber 40M is formed by the third bulkhead portion 12c, the second bulkhead portion 12b, and the fourth bulkhead portion 12d of the bulkhead 12, and a valve chamber wall 42G.

[0033] The valve chamber wall 42G is provided at a distance from the third bulkhead portion 12c on the bow side in the fore-aft direction FA. The valve chamber wall 42G extends from the second bulkhead portion 12b to the fourth bulkhead portion 12d, and also extends from the freeboard deck 5 to the deck 7. In this way, the valve chamber 40G is provided adjacent to the watertight compartments S11, S12 via the second bulkhead portion 12b and the fourth bulkhead portion 12d of the bulkhead 12.

[0034] (First piping configuration) As shown in Figures 2 and 3, the first pipes 51M, 51G supply fuel gas G2, which is vaporized from the liquefied gas G1 in the liquefied gas tank 30A, to the pressure regulating valves 41M, 41G. The first pipes 51M, 51G connect the gas heater 35c of the fuel supply device 35 to the pressure regulating valves 41M, 41G. The first pipes 51M, 51G are single pipes that do not have a protective pipe (in other words, an outer pipe) that covers the outside. The first pipes 51M, 51G are provided on the upper deck 8 in an exposed state where they are exposed to the outside air.

[0035] The first pipe 51M is laid in the duct D1 and the watertight compartment S11 in the hull 2 ​​(below the upper deck 8). The first pipe 51M is installed in the duct D1 between the upper deck 8 and the freeboard deck 5, and extends from the duct D1 through the freeboard deck 5 into the watertight compartment S11. The first pipe 51M extends downward from the freeboard deck 5 in the watertight compartment S11, then extends inward in the ship width direction W, penetrates the second partition wall portion 16b, and is led into the valve chamber 40M. The first pipe 51M is connected to each pressure regulating valve 41M in the valve chamber 40M. The first pipe 51M further extends from the pressure regulating valve 41M to the valve chamber wall 42M. Although not shown in the figure, the points where the first piping 51M penetrates the freeboard deck 5 and the points where the first piping 51M penetrates the second partition wall portion 16b have been treated to ensure the watertightness of the watertight compartment S11 (the same applies to the points where the piping penetrates in the watertight compartments of the modified examples and embodiments below).

[0036] The first pipe 51G is laid in the duct D2 and the watertight compartment S12 in the hull 2, similarly to the first pipe 51M. The first pipe 51G is installed in the duct D2 between the upper deck 8 and the freeboard deck 5, and extends from the duct D2 through the freeboard deck 5 into the watertight compartment S12. The first pipe 51G extends downward from the freeboard deck 5 in the watertight compartment S12, and then extends inward in the ship width direction W, penetrates the fourth bulkhead portion 12d, and is led into the valve chamber 40G. The first pipe 51G is connected to each pressure regulating valve 41G in the valve chamber 40G. The first pipe 51G further extends from the pressure regulating valve 41G to the valve chamber wall 42G.

[0037] (Second piping configuration) The second pipes 52M, 52G feed the fuel gas G2 that has passed through the pressure regulating valves 41M, 41G to the main engine 21 and the generator engine 22, which are the heat engine 20. The second pipes 52M, 52G are laid outside the valve chambers 40M, 40G. The second pipes 52M, 52G illustrated in this reference example each extend in the bow-stern direction. Each of the second pipes 52M, 52G forms a double pipe.

[0038] The second pipe 52M includes an inner pipe 53M and an outer pipe 54M. The inner pipe 53M connects the end of the first pipe 51M, which extends to the valve chamber wall 42M inside the valve chamber 40M, to the main engine 21. The outer pipe 54M is formed with a larger diameter than the inner pipe 53M and covers the inner pipe 53M from the outside. This outer pipe 54M is airtight. Therefore, even if the fuel gas G2 leaks from the inner pipe 53M, the fuel gas G2 will remain in the outer pipe 54M.

[0039] The second pipe 52G, like the second pipe 52M, includes an inner pipe 53G and an outer pipe 54G. The inner pipe 53G connects the end of the first pipe 51G that extends to the valve chamber wall 42G in the valve chamber 40M to the generator engine 22. The outer pipe 54G is formed with a larger diameter than the inner pipe 53G and covers the inner pipe 53G from the outside. This outer pipe 54G is configured to be airtight so that the fuel gas G2 remains in the outer pipe 54M even if the fuel gas G2 leaks from the inner pipe 53G.

[0040] (Flow of fuel gas supply from liquefied gas tank to heat engine) In the ship 1, to supply the fuel gas G2 from the liquefied gas tank 30A to the heat engine 20, first, the pump 35a of the fuel supply device 35 sucks out the liquefied gas G1 in the liquefied gas tank 30A. The liquefied gas G1 sucked out by the pump 35a is vaporized by evaporation in the evaporator 35b to become the fuel gas G2. The fuel gas G2 is sent to the pressure regulating valves 41M, 41G in the valve chambers 40M, 40G through the first pipes 51M, 51G.

[0041] The fuel gas G2 sent through the first pipes 51M, 51G to the pressure regulating valves 41M, 41G is pressure-regulated by the pressure regulating valves 41M, 41G, and then supplied to the main engine 21 and the generator engine 22 of the heat engine 20. The main engine 21 combusts the supplied fuel gas G2 to generate driving force for rotating the screw 9. The generator engine 22 drives a generator (not shown) by combusting the supplied fuel gas G2.

[0042] (Action and effect) In the ship 1 of the above-mentioned reference example, a portion of the first pipes 51M, 51G is arranged inside the watertight compartments S11, S12. As a result, it is not necessary to make the first pipes 51M, 51G double pipes in the portions arranged inside the watertight compartments S11, S12. Furthermore, since the valve chambers 40M, 40G are provided adjacent to the watertight compartments S11, S12, there is no need to form the first pipes 51M, 51G as double pipes between the watertight compartments S11, S12 and the valve chambers 40M, 40G. Therefore, according to the ship 1 of the reference example, the amount of double-walled pipes used can be reduced, and the effort and cost involved in installing the double-walled pipes can be reduced.

[0043] In the ship 1 of the reference example, the liquefied gas tank 30A is provided above the engine room 10, and at least a portion of the first pipes 51M, 51G is arranged to extend in the vertical direction Dv within the watertight compartments S11, S12. Therefore, according to the reference example ship 1, when the liquefied gas tank 30A is provided above the engine room 10 and the first piping 51M, 51G extends in the vertical direction Dv, by arranging at least a portion of it within the watertight compartments S11, S12, the amount of double pipe used can be reduced and the effort and cost associated with installing the double pipe can be saved.

[0044] The ship 1 of the reference example further includes ducts D1, D2 that communicate with the upper ends of the watertight compartments S11, S12 and extend upward from the watertight compartments S11, S12 within the hull 2. The first pipes 51M, 51G are disposed in the ducts D1, D2 above the watertight compartments S11, S12. Therefore, according to the reference example ship 1, by arranging the first piping 51M, 51G within the ducts D1, D2 above the watertight compartments S11, S12, the amount of double pipe used can be reduced and the effort and cost associated with installing the double pipe can be saved.

[0045] In the ship 1 of the reference example, the horizontal cross-sectional areas of the watertight compartments S11, S12 are larger than the horizontal cross-sectional areas of the ducts D1, D2. Therefore, according to the ship 1 of the embodiment, the watertight compartments S11, S12 in which the first pipes 51M, 51G are arranged can be utilized as watertight rooms Sa, Sb having a large volume.

[0046] (Modification of the Reference Example) In the above-mentioned reference example, the bulkhead 12 is provided with the first bulkhead portion 12a, the second bulkhead portion 12b, the fourth bulkhead portion 12d and the fifth bulkhead portion 12e on both sides in the ship width direction W, but this is not limited to the above. For example, the bulkhead 12A may be formed in a straight line extending in the ship width direction W and connecting a pair of ship sides 3A, 3B in the cross-sectional view of FIG. 5. In this modified example of the reference example, the case where the watertight compartments S13, S14, S15, and S16 are provided is illustrated. The watertight compartments S13, S14, S15, and S16 are provided between the freeboard deck 5 and the deck 7. The watertight compartments S13 and S15 are arranged symmetrically in the ship width direction W with the center C of the hull 2 ​​in between. The watertight compartments S14 and S16 are arranged symmetrically in the ship width direction W with the center C of the hull 2 ​​in between. The port side watertight compartments S13 and S14 are arranged symmetrically adjacent to the bulkhead 12A on both sides in the bow-stern direction FA. The starboard side watertight compartments S15, S16 are arranged symmetrically adjacent to the bulkhead 12A on both sides in the bow-stern direction FA.

[0047] The port-side watertight compartments S13, S14 are surrounded by the ship's side 3A, the first side portion 12f of the bulkhead 12A in the ship's width direction W, and the partitions 16C, 16D, and are formed across the entire upper and lower areas of the engine room 10 between the freeboard deck 5 and the deck 7. The partition 16C is arranged to surround the connection portion J3 between the ship's side 3A and the first side portion 12f of the bulkhead 12A. The partition 16D is arranged to surround the connection portion J4 between the ship's side 3B and the second side portion 12g of the bulkhead 12A. The partition 16C includes a first partition portion 16e and a second partition portion 16f. The partition 16D includes a first partition portion 16g and a second partition portion 16h.

[0048] The first partition wall portions 16e, 16g are provided on both sides of the first side portion 12f in the fore-aft direction FA with a gap therebetween. The first partition wall portions 16e, 16g are connected to the ship's side 3A and extend inward in the ship's width direction W from the ship's side 3A in parallel with the first side portion 12f. The second partition wall portions 16f, 16h are provided on the ship's width direction W with a gap therebetween with the ship's side 3A. The second partition wall portions 16f, 16h connect the inner end edges of the first partition wall portions 16e, 16g in the ship's width direction W to the first side portion 12f.

[0049] The starboard watertight compartments S15, S16 are surrounded by the ship's side 3B, the second side portion 12g of the bulkhead 12A on the starboard side in the ship's width direction W, and the partitions 16E, 16F, and are formed across the entire upper and lower areas of the engine room 10 between the freeboard deck 5 and the deck 7. The partitions 16E, 16F are each disposed so as to surround the connection portion J4 between the ship's side 3B and the second side portion 12g of the bulkhead 12A. The partitions 16E, 16F each include a first partition portion 16i, 16k and a second partition portion 16j, 16m.

[0050] The first partition wall portions 16i, 16k are provided at a distance from the second side portion 12g in the bow-stern direction FA. The first partition wall portions 16i, 16k are connected to the ship's side 3B and extend inward in the ship's width direction W from the ship's side 3B in parallel with the second side portion 12g. The second partition wall portions 16j, 16m are provided at a distance from the ship's side 3B on the inner side in the ship's width direction W of the hull 2. The second partition wall portions 16j, 16m are provided so as to connect the inner end edges of the first partition wall portions 16i, 16k in the ship's width direction W to the second side portion 12g.

[0051] The watertight compartments S13, S14, S15, and S16 are provided adjacent to the bulkhead 12A. The watertight compartments S13, S14, S15, and S16 in this modified example of the reference example function as watertight rooms Sc, Sd, Se, and Sf that prevent water from entering the engine room 10 from outside the ship in the event that the ship sides 3A and 3B are damaged.

[0052] <Embodiment> Next, an embodiment of a ship according to the present invention will be described. The embodiment described below differs from the reference example in the arrangement of the liquefied gas tank. Therefore, the same parts as in the reference example will be denoted by the same reference symbols, and duplicated explanations will be omitted.

[0053] (Overall configuration of the ship) As shown in FIG. 6, a ship 1B of this embodiment includes, within its hull 2, a heat engine 20, a liquefied gas tank 30B, pressure regulating valves 41M, 41G, tank side piping 55M, 55G, and heat engine side piping 56M, 56G.

[0054] The hull 2 ​​is provided with bulkhead 11, bulkheads 12B, 12C, and bulkheads 13B, 13C, in that order from the stern to the bow, between the freeboard deck 5 and the deck 7, with a gap in the fore-aft direction FA. Bulkhead 11, bulkheads 12B, 12C, and bulkheads 13B, 13C each extend in the ship's width direction W, reaching from shipside 3A to shipside 3B, and also reaching from the freeboard deck 5 to the deck 7. In other words, the space between the freeboard deck 5 and the deck 7 is divided in the fore-aft direction by these bulkheads 11, bulkheads 12B, 12C, and bulkheads 13B, 13C.

[0055] (Watertight compartment configuration) The ship 1B of the embodiment includes watertight compartments S21, S22, S23, S24, S31, S32, S33, and S34. The watertight compartments S21, S22, S23, S24, S31, S32, S33, and S34 are provided between the freeboard deck 5 and the deck 7.

[0056] The watertight compartments S21 and S22 are arranged symmetrically in the ship width direction with the center C of the hull 2 ​​in between. The watertight compartments S21 and S22 are surrounded by the ship sides 3A and 3B and the partition walls 15G and 15H, and are formed over the entire upper and lower areas of the engine room 10 (in other words, the main engine room 10A) between the freeboard deck 5 and the deck 7. The partition walls 15G and 15H in this embodiment are formed by the first side portion 12h and the second side portion 12i on both sides of the ship width direction W of the bulkhead 12B, and the partition walls 16G and 16H. The partition wall 16G is arranged so as to surround the connection part J5 between the ship side 3A and the bulkhead 12B from the stern side. The partition wall 16H is arranged so as to surround the connection part J6 between the ship side 3B and the bulkhead 12B from the stern side.

[0057] The port-side partition wall 16G includes a first partition wall portion 16p and a second partition wall portion 16q. The first partition wall portion 16p is provided at a distance from the first side portion 12h in the bow-stern direction FA. The first partition wall portion 16p is connected to the ship side 3A and extends inward in the ship width direction W from the ship side 3A in parallel with the first side portion 12h. The second partition wall portion 16q is provided so as to connect the first partition wall portion 16p and the first side portion 12h. The second partition wall portion 16q is provided at a distance from the ship side 3A on the inside in the ship width direction W of the hull 2.

[0058] The starboard-side partition wall 16H includes a third partition wall portion 16r and a fourth partition wall portion 16s. The third partition wall portion 16r is provided at a distance from the second side portion 12i in the bow-stern direction FA. The third partition wall portion 16r is connected to the ship's side 3B and extends inward in the ship's width direction W from the ship's side 3B in parallel with the second side portion 12i. The fourth partition wall portion 16s is provided so as to connect the inner ends of the third partition wall portion 16r and the second side portion 12i in the ship's width direction W to each other. The fourth partition wall portion 16s is provided at a distance from the ship's side 3B on the inner side in the ship's width direction of the hull 2.

[0059] The port-side partition wall 15G is formed by a first side portion 12h which is a part of the bulkhead 12B, and a first partition wall portion 16p and a second partition wall portion 16q which constitute the partition wall 16G. The port-side watertight compartment S21 is formed by being surrounded by the port-side side 3A, the first side portion 12h which is a part of the bulkhead 12B, and the first partition wall portion 16p and the second partition wall portion 16q which constitute the partition wall 16G.

[0060] The starboard-side partition wall 15H is formed by the second side portion 12i which is a part of the bulkhead 12B, and the third partition wall portion 16r and the fourth partition wall portion 16s which constitute the partition wall 16H. The starboard-side watertight compartment S22 is formed by being surrounded by the starboard side 3B, the second side portion 12i which is a part of the bulkhead 12B, and the third partition wall portion 16r and the fourth partition wall portion 16s which constitute the partition wall 16H.

[0061] The watertight compartments S23, S24 are surrounded by the ship's side 3A, 3B and the partitions 16Ca, 16Ea, and are formed over the entire upper and lower areas of the generator room 10B between the freeboard deck 5 and the deck 7. The partition 16Ca is arranged to surround the connection J5 between the ship's side 3A and the first side portion 12h of the bulkhead 12B from the bow side. The partition 16Ea is arranged to surround the connection J6 between the ship's side 3B and the second side portion 12i of the bulkhead 12B from the bow side. The partition 16Ca includes a first partition portion 16e and a second partition portion 16f. The first partition portion 16e forms a part of the bulkhead 12C on the side closer to the ship's side 3A. The second partition wall portion 16f is provided to connect the first partition wall portion 16e and the first side portion 12h on the inside of the ship width direction W of the hull 2 ​​relative to the ship side 3A. The partition wall 16Ea includes a first partition wall portion 16i and a second partition wall portion 16j. The first partition wall portion 16i forms a part of the bulkhead 12C on the side closer to the ship side 3B. The second partition wall portion 16j is provided to connect the first partition wall portion 16i and the second side portion 12i on the inside of the ship width direction W of the hull 2 ​​relative to the ship side 3A.

[0062] The watertight compartments S31, S32, S33, and S34 are formed in the same manner as the above-mentioned watertight compartments S21, S22, S23, and S24. While the watertight compartments S21, S22, S23, and S24 are formed adjacent to the bulkhead 12B, the watertight compartments S31, S32, S33, and S34 are formed adjacent to the bulkhead 13B.

[0063] The watertight compartments S31, S32 are surrounded by the shipboard sides 3A, 3B and the partitions 16I, 16J, and are formed across the entire upper and lower areas of the generator room 10B between the freeboard deck 5 and the deck 7. The partition 16I is arranged so as to surround the connection J7 between the shipboard side 3A and the first side portion 13h of the bulkhead 13B from the stern side. The partition 16J is arranged so as to surround the connection J8 between the shipboard side 3B and the second side portion 13i of the bulkhead 13B from the stern side. The port side partition 16I includes a first partition portion 16t and a second partition portion 16u. The starboard side partition 16J includes a first partition portion 16v and a second partition portion 16w.

[0064] The first partition wall portion 16t is provided at a distance from the first side portion 13h in the bow-stern direction FA. The first partition wall portion 16t is connected to the ship's side 3A and extends inward in the ship's width direction W from the ship's side 3A in parallel with the first side portion 13h. The second partition wall portion 16q is provided so as to connect the first partition wall portion 16p and the first side portion 12h. The second partition wall portion 16q is provided at a distance from the ship's side 3A on the inner side in the ship's width direction W of the hull 2.

[0065] The first partition wall portion 16v is provided at a distance from the second side portion 13i in the bow-stern direction FA. The first partition wall portion 16v is connected to the ship's side 3B and extends inward in the ship's width direction W from the ship's side 3B in parallel with the second side portion 13i. The second partition wall portion 16w is provided so as to connect the first partition wall portion 16v and the second side portion 12i. The second partition wall portion 16w is provided at a distance from the ship's side 3B on the inner side in the ship's width direction W of the hull 2.

[0066] The watertight compartments S33, S34 are surrounded by the ship's sides 3A, 3B and the partitions 16Cb, 16Eb, and are formed between the freeboard deck 5 and the deck 7 across the entire upper and lower areas of the tank room 60 (described later). The partition 16Cb is arranged to surround the connection J7 between the ship's side 3A and the first side portion 13h of the bulkhead 13B from the bow side. The partition 16Eb is arranged to surround the connection J8 between the ship's side 3B and the second side portion 13i of the bulkhead 13B from the bow side. The partition 16Cb includes a first partition portion 16e and a second partition portion 16f. The first partition portion 16e forms a part of the bulkhead 13C on the side closer to the ship's side 3A. The second partition wall portion 16f is provided to connect the first partition wall portion 16e and the first side portion 13h on the inside in the ship width direction W of the hull 2 ​​relative to the ship side 3A. The partition wall 16Ea includes a first partition wall portion 16i and a second partition wall portion 16j. The first partition wall portion 16i forms a part of the bulkhead 13C on the side closer to the ship side 3B. The second partition wall portion 16j is provided to connect the first partition wall portion 16i and the second side portion 13i on the inside in the ship width direction W of the hull 2 ​​relative to the ship side 3A.

[0067] The watertight compartments S21, S22, S23, and S24 are provided adjacent to the bulkhead 12B. The watertight compartments S31, S32, S33, and S34 are provided adjacent to the bulkhead 13B. In this embodiment, the watertight compartments S21, S22, S23, S24, S31, S32, S33, and S34 function as watertight prevention rooms Sg and Sh that prevent water from entering the engine room 10 (and the tank room 60 described later) from outside the ship in the event that the ship sides 3A and 3B are damaged.

[0068] In this embodiment, the valve chamber 40M for the main engine 21 is disposed between the bulkheads 12B and 12C, spanning the watertight compartments S23 and S24. The valve chamber 40G for the generator engine 22 is disposed between the bulkheads 13B and 13C, spanning the watertight compartments S33 and S34.

[0069] (Configuration of liquefied gas tank) The hull 2 ​​includes a tank room 60 adjacent to the bow side in the bow-stern direction FA of the engine room 10. That is, the tank room 60 in this embodiment is provided below the freeboard deck 5. The tank room 60 accommodates a liquefied gas tank 30B and a fuel supply device 35B. In other words, the liquefied gas tank 30B and the fuel supply device 35B are provided outside the engine room 10. The liquefied gas tanks 30B illustrated in this embodiment are installed in the tank room 60 at intervals in the ship width direction W.

[0070] (Configuration of liquefied gas tank associated equipment) The fuel supply device 35B supplies the liquefied gas G1 in the liquefied gas tank 30B to the heat engine 20 (the main engine 21, the generator engine 22). The fuel supply device 35B mainly includes a pump 35a, an evaporator 35b, a gas heater 35c, and a gas incinerator 35d, similar to the fuel supply device 35 of the above-mentioned reference example. The tank chamber 60 is structured to be airtight so that the liquefied gas G1 and the like do not leak outside the tank chamber 60.

[0071] (First piping configuration) The tank side piping 55M supplies the fuel gas G2 obtained by vaporizing the liquefied gas G1 in the liquefied gas tank 30B to the pressure regulating valve 41M in the valve chamber 40M. Similarly, the tank side piping 55G supplies the fuel gas G2 obtained by vaporizing the liquefied gas G1 in the liquefied gas tank 30B to the pressure regulating valve 41G in the valve chamber 40G. In other words, the tank side piping 55M connects the fuel supply device 35B and the pressure regulating valve 41M, and the tank side piping 55G connects the fuel supply device 35B and the pressure regulating valve 41G. At least a part of the tank side piping 55M is disposed in the watertight compartments S21 and S22. At least a part of the tank side piping 55G is disposed in the watertight compartments S31 and S32.

[0072] The tank side piping 55M includes a first tank side piping 55Ma and a second tank side piping 55Mb. In this embodiment, the first tank side piping 55Ma is laid in a range from the fuel supply device 35B through the tank chamber 60, the watertight compartment S33, and the watertight compartment S31 to the first partition wall portion 16t. The first tank side piping 55Ma further extends from the first partition wall portion 16e to the watertight compartment S23 and the valve chamber 40M, and branches in the valve chamber 40M to be connected to two pressure regulating valves 41M. Then, the two pressure regulating valves 41M extend from the two pressure regulating valves 41M to the first partition wall portion 16p and the third partition wall portion 16r through the watertight compartments S21 and S22, respectively. In other words, the first tank side piping 55Ma is laid only in a space that is separated from the space in which the heat engine 20 is housed and has watertight and airtight properties. This first tank side piping 55Ma is a single pipe that does not have an outer pipe (protective pipe).

[0073] The second tank side piping 55Mb in this embodiment is laid in the range from the first partition wall portion 16t to the first partition wall portion 16e. In other words, the second tank side piping 55Mb is laid in the range from the watertight compartment S31 to the watertight compartment S23, that is, in the space accommodating the generator engine 22. This second tank side piping 55Mb connects the first tank side piping 55Ma in the watertight compartment S31 and the first tank side piping 55Ma in the watertight compartment S23. This second tank side piping 55Mb is a double pipe having an inner pipe 55Mc (in other words, a solid pipe) and an outer pipe 55Md (in other words, a protective pipe).

[0074] The tank side piping 55G extends from the fuel supply device 35B through the tank chamber 60 into the valve chamber 40G, and branches according to the number of generator engines 22 and is connected to the pressure regulating valve 41G. In this embodiment, the tank side piping 55G branches and is connected to three pressure regulating valves 41G. Furthermore, in this embodiment, the tank side piping 55G extends from two of the three pressure regulating valves 41G that are arranged on both sides in the ship's width direction W to the first partition wall portions 16t, 16v through the watertight compartments S31, S32. Furthermore, the tank side piping 55G extends from the pressure regulating valve 41G that is arranged in the center of the ship's width direction W to the bulkhead 13B.

[0075] (Second piping configuration) The heat engine side pipes 56M, 56G feed the fuel gas G2 from the tank side pipes 55M, 55G to the main engine 21 and the generator engine 22 which are the heat engine 20.

[0076] The heat engine side piping 56M connects the tank side piping 55M in the watertight compartments S21, S22 to the two main engines 21. The two heat engine side piping 56M each extend from the first partition wall portion 16p toward the port side main engine 21 in the main engine room 10A, and also extend from the third partition wall portion 16r toward the starboard side main engine 21. These heat engine side piping 56M are double pipes including an inner pipe 58a and an outer pipe 58b that covers the inner pipe 58a from the radial outside.

[0077] The heat engine side piping 56G connects the tank side piping 55G in the watertight compartments S31, S32 to the generator engine 22. The heat engine side piping 56G further connects the tank side piping 55G in the valve chamber 40G to the generator engine 22 at the center between the watertight compartments S31, S32 in the ship's width direction W. That is, in this embodiment, three heat engine side pipings 56G are provided. These heat engine side pipings 56G extend from the first partition wall portion 16t to the port side generator engine 22, from the first partition wall portion 16v to the starboard side generator engine 22, and from the bulkhead 13B at the center in the ship's width direction W to the generator engine 22 at the center in the ship's width direction W, respectively, in the generator room 10B. These heat engine side pipings 56G are double pipes including an inner pipe 58a and an outer pipe 58b that covers the inner pipe 58a from the radial outside.

[0078] (Flow of fuel gas supply from liquefied gas tank to heat engine) In the ship 1B, to supply fuel gas G2 from the liquefied gas tank 30B to the heat engine 20, first, the pump 35a of the fuel supply device 35B sucks out the liquefied gas G1 in the liquefied gas tank 30B. The liquefied gas G1 sucked out by the pump 35a is vaporized by evaporation in the evaporator 35b to become fuel gas G2. The fuel gas G2 is sent to the pressure regulating valves 41M, 41G in the valve chambers 40M, 40G through the tank side pipes 55M, 55G.

[0079] The fuel gas G2 sent to the pressure regulating valves 41M, 41G through the tank side piping 55M, 55G has its pressure adjusted by the pressure regulating valves 41M, 41G, and is then supplied to the main engine 21 and generator engine 22 of the heat engine 20. The main engine 21 combusts the supplied fuel gas G2 to generate driving force for rotating the screw 9. The generator engine 22 combusts the supplied fuel gas G2 to drive a generator (not shown).

[0080] (Action and effect) In the ship 1B of the above embodiment, a portion of the heat engine side piping 56M is disposed in the watertight compartments S21, S22, S23, and S31 formed in the engine room 10. Therefore, according to the ship 1B of the embodiment, the heat engine side piping 56M does not need to be a double pipe in the portion arranged in the watertight compartments S21, S22, S23, and S31. As a result, the amount of double pipe used can be reduced, and the labor and cost associated with installing the double pipe can be suppressed. Also, in the ship 1B of the embodiment, a portion of the heat engine side piping 56G is arranged in the watertight compartments S31 and S32 formed in the engine room 10. Therefore, according to the ship 1B of the embodiment, it is not necessary to make the heat engine side piping 56G a double pipe in the portion arranged in the watertight compartments S31 and S32. As a result, the amount of double pipe used can be reduced, and the effort and cost associated with installing the double pipe can be suppressed.

[0081] (Other embodiments) Although the embodiment of the present disclosure has been described in detail above with reference to the drawings, the specific configuration is not limited to this embodiment, and design changes and the like are also included within the scope that does not depart from the gist of the present disclosure.

[0082] In the reference example, the first pipes 51M, 51G are arranged in the ducts D1, D2. The first pipes 51M, 51G and the ducts D1, D2 do not necessarily extend straight in the vertical direction Dv. For example, the first pipes 51M, 51G may be arranged in the ducts D1, D2 that extend horizontally or obliquely.

[0083] In the reference example, the horizontal cross-sectional area of ​​the watertight compartments S11, S12 is larger than that of the ducts D1, D2, but this is not limited to the above. The horizontal cross-sectional area of ​​the watertight compartments S11, S12 may be equal to or larger than that of the ducts D1, D2.

[0084] In the reference example, the liquefied gas tank 30A is provided on the upper deck 8 above the engine room 10. However, the liquefied gas tank 30A may be located on a layer lower than the upper deck 8. In the reference example, the valve chamber 40M for the main engine 21 and the valve chamber 40G for the generator engine 22 are provided separately, but the pressure regulating valve 41M of the main engine 21 and the pressure regulating valve 41G of the generator engine 22 may be accommodated in a single valve chamber.

[0085] In the reference example and the embodiment, the valve chambers 40M and 40G are provided so as to contact both of the watertight compartments S11, S12, S13, S14, S15, S16, S21, and S22 on both sides in the ship width direction W, but this is not limited thereto. The valve chambers 40M and 40G may be provided so as to contact only one of the watertight compartments S11, S12, S13, S14, S15, S16, S21, and S22.

[0086] In the reference examples and embodiments, the valve chambers 40M, 40G may have a watertight structure similar to the watertight compartments S11, S12, S13, S14, S15, S16, S21, and S22. In that case, the partition walls 16A, 16B, 16C, 16D, 16E, 16F, 16G, and 16H do not need to have a watertight structure in the portions where the valve chambers 40M, 40G contact the watertight compartments S11, S12, S13, S14, S15, S16, S21, and S22.

[0087] In the embodiment and the modified embodiment of the embodiment, the valve chambers 40M, 40G are provided inside the engine room 10, but the present invention is not limited to this. The valve chambers 40M, 40G may be provided outside the engine room 10.

[0088] In the reference examples and the embodiment, the main engine 21 and the generator engine 22 are shown as the heat engine 20, but the present invention is not limited thereto. The heat engine 20 to which the fuel gas G2 is supplied from the liquefied gas tanks 30A and 30B may be only one of the main engine 21 and the generator engine 22. In that case, the other to which the fuel gas G2 is not supplied may be a heat engine using a fuel other than the fuel gas G2, an electric motor, or the like.

[0089] In the embodiment, the tank side piping 55M passes through the watertight compartments S23, S33. However, the tank side piping 55M may pass through, for example, the valve chambers 40M, 40G without passing through the watertight compartments S23, S33. Also, the heat engine side piping 56G arranged in the center of the ship width direction W among the three heat engine side pipings 56G extends from the bulkhead 13B toward the generator engine 22. However, when the distance from the generator engine 22 to the watertight compartments S31 and S32 is shorter than the distance from the generator engine 22 to the bulkhead 13B, the tank side piping 55G and the heat engine side piping 56G may pass through the watertight compartments S31 and S32.

[0090] <Additional Notes> The ship 1 described in each embodiment can be understood, for example, as follows.

[0091] (1) A ship 1 according to a first embodiment includes a hull 2B having a pair of shipboard sides 3A, 3B, bulkheads 12B, 13B that are provided below the freeboard deck 5 within the hull 2 ​​and form an engine room 10 in which a heat engine 20 is housed together with the pair of shipboard sides 3A, 3B, partition walls 16G, 16H, 16I, 16J that are arranged to surround connection parts J5, J6, J7, J8 between the bulkheads 12B, 13B and the shipboard sides 3A, 3B and form watertight compartments S21, S22, S31, S32 extending across the upper and lower ranges of the engine room 10, and a liquefied gas tank 30B that is provided on the same level as the engine room 10 and is provided outside the engine room 10 and stores liquefied gas G1. the pressure regulating valve 41M, 41G being accommodated in a valve chamber 40M, 40G arranged adjacent to the watertight compartments S21, S22, S31, S32 and adjusting the pressure of the fuel gas G2 supplied to the heat engine 20; tank side piping 55M, 55G, at least a portion of which is arranged in the watertight compartments S21, S22, S31, S32, for supplying the fuel gas G2 vaporized from the liquefied gas G1 in the liquefied gas tank 30B to the pressure regulating valve 41M, 41G; and heat engine side piping 56M, 56G consisting of a double pipe arranged in a space in which the heat engine 20 is accommodated and for supplying the fuel gas G2 that has passed through the pressure regulating valve 41M, 41G to the heat engine 20.

[0092] In the ship 1B, at least a portion of the tank side piping 55M, 55G is disposed in the watertight compartments S21, S22, S31, and S32. The portions disposed in the watertight compartments S21, S22, S31, and S32 do not need to be double pipes. Therefore, the amount of the heat engine side pipes 56M, 56G, which are double-piped, used can be reduced, and the effort and cost involved in installing the double-pipes can be reduced. Examples of the heat engine 20 include a main engine 21 and a generator engine 22 .

[0093] (2) The ship 1 of a second aspect is the ship 1 of (1), in which the heat engine side piping 56M, 56G connects the tank side piping 55M, 55G in the watertight compartments S21, S22, S31, S32 to the heat engine 20.

[0094] This reduces the amount of double-walled pipes used and reduces the labor and costs involved in installing the double-walled pipes.

[0095] (3) The ship 1 of the third aspect is the ship 1 of (1) or (2), and is provided with an airtight tank room 60 adjacent to the bow side in the bow-stern direction from the engine room 10 and accommodating the liquefied gas tank 30B.

[0096] As a result, when the liquefied gas tank 30B is arranged in the tank room 60 on the bow side of the engine room 10, the amount of double pipe used can be reduced, and the effort and cost associated with installing the double pipe can be suppressed.

[0097] (4) The ship 1 of a fourth aspect is the ship 1 of (3), in which the tank chamber 60 accommodates a fuel supply device 35B that supplies the liquefied gas in the liquefied gas tank 30B to the heat engine 20. [Explanation of symbols]

[0098] 1, 1B...Ship 2, 2B...Hull 2b...Aft 3A, 3B...Side 4...Bottom 5...Freeboard deck 7...Deck 8...Upper deck 9...Screw 10...Engine room 10A...Main engine room 10B...Generator room 11...Bulkhead 12, 12A, 12B, 12C...Bulkhead 12a...First bulkhead 12b...Second partition part 12c...Third partition part 12d...Fourth partition part 12e...Fifth partition part 12f, 12h...First side part 12g, 12i...Second side part 13, 13B, 13C...Partition wall 15A, 15B, 15G, 15H...Partition wall 16A~16H...Partition wall 16a, 16e, 16g, 16i, 16k, 16p...First partition wall section 16b, 16f, 16h, 16j, 16m, 16q...Second partition wall section 16c, 16r...Third partition wall section 16d, 16s...Fourth partition wall section 20...Heat engine 21...Main engine 22...Generator engine 30A, 30B...Liquefied gas tank 31...Vent riser 33...Bunker station 35, 35B...Fuel supply device 35a...Pump 35b...Evaporator 35c...Gas heater 35d...Gas incinerator 40G, 40M...Valve chamber 41G, 41M...Pressure regulating valve 42G, 42M...Valve chamber wall 51G, 51M...First piping 52G, 52M...Second piping 54G, 54M...Outer pipe 55G, 55M…Tank side piping 56G, 56M…Heat engine side piping 58b…Outer pipe 60…Tank room D1, D2…Duct G1…Liquefied gas G2…Fuel gas G3…Boil-off gas J1~J6…Connections S11~S16…Watertight compartments S21~S24…Watertight compartments S31~S34…Watertight compartments Sa~Sh…Flood prevention room W…Beam direction

Claims

1. A hull having a pair of sides; A bulkhead provided below the freeboard deck in the hull and forming an engine room together with the pair of shipboard sides in which a plurality of heat engines arranged in the ship width direction are housed; a pair of partition walls that are arranged to surround the connection portions between the bulkhead and the pair of ship sides, respectively, and form a pair of watertight compartments extending across the vertical range of the engine room; a liquefied gas tank provided on the same floor as the engine room and outside the engine room, the liquefied gas tank storing liquefied gas; pressure regulating valves, the number of which is equal to the number of the heat engines, each of which is accommodated in a valve chamber disposed adjacent to the pair of watertight compartments and which adjust the pressure of the fuel gas supplied to each of the heat engines; a tank side pipe that supplies the fuel gas produced by vaporizing the liquefied gas in the liquefied gas tank to the plurality of pressure regulating valves and has a single pipe at least a part of which is disposed in each of the pair of watertight compartments; a plurality of heat engine side pipes each consisting of a double pipe extending in the engine room, the fuel gas being supplied to the plurality of pressure regulating valves by the tank side pipe and passing through each pressure regulating valve to each of the heat engines; A vessel equipped with:

2. The heat engine side piping is The tank side piping in the watertight compartment is connected to the heat engine.

2. The watercraft of claim 1.

3. a tank room adjacent to the engine room on the bow side in the bow-stern direction and having airtightness for accommodating the liquefied gas tank; 2. The watercraft of claim 1.

4. The tank chamber accommodates a fuel supply device that supplies the liquefied gas in the liquefied gas tank to the heat engine.

4. The watercraft of claim 3.

Citation Information

Patent Citations

  • Boil-off gas line in lng carrier

    JP1995149284A

  • Fuel Systems for Gas-Powered Marine Vessels

    JP2009541140A

  • Liquefied gas fuel ship

    JP2018069934A

  • Ship having a plurality of fuel lines

    JP2018069981A

  • vessel

    JP2018177012A