Power management device and power supply system

The power management device addresses the issue of varying battery cell charges by implementing cell balancing within safe operating ranges, enhancing storage capacity and stability in power supply systems.

JP7583825B2Active Publication Date: 2024-11-14TDK CORP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2022552325
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-02-15
Publication Date
2024-11-14
Estimated Expiration
2041-02-15

AI Technical Summary

Technical Problem

In power supply systems using storage batteries, variations in the state of charge among battery cells lead to a decrease in effective storage capacity, which is not adequately addressed by existing battery management units due to safety considerations that prevent reaching end-of-charge or end-of-discharge states.

Method used

A power management device determines implementation conditions for cell balancing and adjusts the target voltage of converters to initiate cell balancing even within safe operating ranges, reducing maximum current values and utilizing auxiliary power supplies to maintain power balance and stabilize the system.

Benefits of technology

This approach effectively suppresses the decrease in storage battery capacity by enabling cell balancing within safe operating limits, ensuring stable power supply and efficient utilization of renewable energy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007583825000005
    Figure 0007583825000005
  • Figure 0007583825000006
    Figure 0007583825000006
  • Figure 0007583825000007
    Figure 0007583825000007
Patent Text Reader

Abstract

This power management device is provided with: a first determination unit for determining whether an implementation condition, according to which cell balancing should be implemented, has been satisfied, the cell balancing being for equalizing states of charge of a plurality of battery cells included in a storage cell connected to a direct-current bus via a converter; and a control unit for performing, if the implementation condition has been satisfied, cell balancing implementation control for causing the cell balancing to be implemented by a battery management device that manages the storage cell. The control unit modifies a target voltage of the converter so that, in the cell balancing implementation control, the state of charge of the storage cell will achieve a state in which the battery management device initiates the cell balancing.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a power management device and a power supply system. [Background technology]

[0002] In recent years, the introduction of power generation facilities using renewable energies such as wind and solar power has been progressing. In particular, in isolated and depopulated areas where power grid infrastructure is not in place, there is a high need for power supply systems that can improve economic efficiency and contribute to the realization of a low-carbon society. Even in areas where power grid infrastructure is already in place, there is a growing expectation for power supply systems that can stably and continuously supply power to load equipment in the event of a power grid outage due to a natural disaster or other reasons.

[0003] For example, Patent Document 1 describes a power supply system including a solar power generation device and a chargeable and dischargeable storage battery. In this power supply system, power is supplied from the solar power generation device to a load device, and the storage battery is charged and discharged according to the difference between the amount of power generated by the solar power generation device and the load power. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] International Publication No. 2012 / 057032 Summary of the Invention [Problem to be solved by the invention]

[0005] In the power supply system described in Patent Document 1, a plurality of battery cells are used as a storage battery. As the storage battery is used, variation occurs in the state of charge (amount of stored electricity) among the battery cells. As a result, the effective storage capacity of the storage battery may decrease. In general, a battery management unit (BMU) has a function (cell balancing function) for eliminating the variation in the state of charge in the final stage of charging or the final stage of discharging. However, in the power supply system described above, the storage battery is used within a range that does not reach the final stage of charging or the final stage of discharging, taking safety into consideration. Therefore, there is a risk that the variation in the state of charge among the battery cells may not be eliminated.

[0006] The present disclosure describes a power management device and a power supply system capable of suppressing a decrease in the effective power storage capacity of a storage battery. [Means for solving the problem]

[0007] A power management device according to one aspect of the present disclosure includes a first determination unit that determines whether or not an implementation condition for performing cell balancing to equalize the charge states of multiple battery cells included in a storage battery connected to a DC bus via a converter is satisfied, and a control unit that performs cell balancing implementation control to cause a battery management device that manages the storage battery to perform cell balancing when the implementation condition is satisfied. In the cell balancing implementation control, the control unit changes a target voltage of the converter so that the charge state of the storage battery becomes a state at which the battery management device starts cell balancing.

[0008] In this power management device, when an implementation condition for performing cell balancing is satisfied, the target voltage of the converter is changed so that the charging state of the storage battery becomes a state where the battery management device starts cell balancing. By changing the target voltage of the converter, the storage battery connected to the converter becomes more likely to be charged or discharged. Therefore, even if the storage battery is used in a range that does not reach an end-of-charge state or an end-of-discharge state during normal operation, cell balancing can be performed. As a result, it is possible to suppress a decrease in the effective storage capacity of the storage battery.

[0009] The control unit may reduce a maximum current value of a current between the converter and the storage battery in the cell balancing implementation control. Cell balancing is implemented when the charging state of the storage battery is a terminal charging state or a terminal discharging state. In the terminal charging state, if the storage battery is charged suddenly, it may be in an overcharged state. Therefore, by reducing the maximum current value, it is possible to reduce the charging speed and reduce the possibility of the storage battery being in an overcharged state. Similarly, in the terminal discharging state, if the storage battery is discharged suddenly, it may be in an overdischarged state. Therefore, by reducing the maximum current value, it is possible to reduce the discharging speed and reduce the possibility of the storage battery being in an overdischarged state.

[0010] In the cell balancing implementation control, the control unit may stop the power supply from the power generation device that supplies power to the DC bus. When the maximum current value of the current between the converter and the storage battery is reduced, the amount of power that can be charged to the storage battery via the converter is reduced. Therefore, by stopping the power supply from the power generation device, it is possible to maintain the power balance.

[0011] In the cell balancing implementation control, the control unit may cause an auxiliary power supply unit that supplies power to the DC bus to supply power. By implementing cell balancing, the amount of power that can be supplied from the storage battery may decrease. Therefore, by causing the auxiliary power supply unit to supply power, it is possible to compensate for the decrease in the power supplied from the storage battery.

[0012] The power management device may further include a second determination unit that determines whether the state of charge of the storage battery has reached a predetermined state. The control unit may perform cell balancing implementation control when an implementation condition is met and the state of charge has reached the predetermined state. When the implementation condition is met, the state of charge of the storage battery is not necessarily fully charged or completely discharged. According to the above configuration, for example, when the state of charge of the storage battery reaches a fully charged or completely discharged state, cell balancing implementation control is performed. Therefore, the power supply system including the storage battery can be operated as normally as possible, which makes it possible to improve the stability of the power supply system.

[0013] The second determination unit may determine whether the state of charge of the storage battery has reached a fully charged state. The control unit may lower the target voltage in cell balancing implementation control. When the storage battery reaches a terminal charging state, the battery management device may perform cell balancing. In this case, the storage battery is further charged from the fully charged state by lowering the target voltage of the converter. This allows the state of charge of the storage battery to be set to a charging state at which the battery management device starts cell balancing, making it possible to suppress a decrease in the effective storage capacity of the storage battery.

[0014] The second determination unit may determine whether the state of charge of the storage battery has reached a fully discharged state. The control unit may increase the target voltage in cell balancing implementation control. When the storage battery reaches a terminal discharge state, the battery management device may perform cell balancing. In this case, the storage battery is further discharged from the fully discharged state by increasing the target voltage of the converter. This allows the state of charge of the storage battery to be set to a charging state at which the battery management device starts cell balancing, making it possible to suppress a decrease in the effective storage capacity of the storage battery.

[0015] The first determination unit may determine whether or not the implementation condition is satisfied based on a maximum cell voltage and a minimum cell voltage among the cell voltages of the plurality of battery cells. It is considered that the greater the difference between the maximum cell voltage and the minimum cell voltage, the greater the variation in the state of charge among the plurality of battery cells. Therefore, by taking the maximum cell voltage and the minimum cell voltage into consideration, it is possible to improve the accuracy of determining whether or not cell balancing should be performed.

[0016] The first determination unit may determine that the implementation condition is satisfied when a ratio obtained by dividing the difference between the maximum cell voltage and the minimum cell voltage by the theoretical value of the cell voltage is greater than a preset ratio threshold. The magnitude of the difference between the maximum cell voltage and the minimum cell voltage, which may be determined as indicating variation in the state of charge among a plurality of battery cells, varies depending on the theoretical value of the cell voltage. For example, the greater the theoretical value of the cell voltage, the greater the magnitude of the difference, which may be determined as indicating variation. Therefore, by using the ratio obtained by dividing the difference between the maximum cell voltage and the minimum cell voltage by the theoretical value of the cell voltage, it is possible to further improve the accuracy of determining whether or not cell balancing should be performed.

[0017] The ratio threshold may be 0.3% or more, or 2.0% or less. When the ratio threshold is 2.0% or less, the possibility that the function of the battery cells is impaired can be reduced. For example, in a configuration in which a renewable energy power generation device supplies power to a DC bus, when the ratio threshold is 0.3% or more, the renewable energy can be effectively utilized. As a result, cell balancing can be performed while effectively utilizing the renewable energy without impairing the function of any of the battery cells. Therefore, it is possible to further suppress the decrease in the effective storage capacity of the storage battery.

[0018] The first determination unit may determine whether or not the implementation condition is satisfied based on the total power consumption per day consumed by the load devices receiving power from the DC bus and the total power supply per day supplied to the DC bus by the auxiliary power supply device that supplies power to the DC bus. When the power that can be supplied from the storage battery is insufficient for the power consumption, power is supplied from the auxiliary power supply device. Therefore, a value obtained by subtracting the total power supply per day supplied by the auxiliary power supply device from the total power consumption per day consumed by the load devices can be estimated as the effective power storage capacity of the storage battery. It is considered that the smaller the effective power storage capacity, the greater the variation in the state of charge among the multiple battery cells. Therefore, by considering the total power consumption per day consumed by the load devices and the total power supply per day supplied by the auxiliary power supply device, it is possible to improve the accuracy of determining whether or not cell balancing should be performed.

[0019] The first determination unit may determine that the implementation condition is satisfied when the storage capacity rate obtained by dividing the moving average value of the value obtained by subtracting the total power supply from the total power consumption by the theoretical value of the storage capacity of the storage battery is smaller than a preset capacity rate threshold. Since the power consumption, etc. may vary from day to day, the influence of the fluctuation can be reduced by using the moving average value of the value obtained by subtracting the total power supply per day supplied by the auxiliary power supply device from the total power consumption per day consumed by the load device. Furthermore, the size of the effective storage capacity at which it is possible to determine that the variation in the charging state between the multiple battery cells occurs varies depending on the theoretical value of the storage capacity of the storage battery. For example, the larger the theoretical value of the storage capacity, the larger the size of the effective storage capacity at which it is possible to determine that the variation occurs. Therefore, by using the storage capacity rate, it is possible to further improve the accuracy of determining whether or not cell balancing should be performed.

[0020] The capacity rate threshold may be 65% or more, or 90% or less. When the capacity rate threshold is 65% or more, the possibility that the function of the battery cells is impaired can be reduced. For example, in a configuration in which a renewable energy power generation device supplies power to a DC bus, when the capacity rate threshold is 90% or less, the renewable energy can be effectively utilized. As a result, cell balancing can be performed while effectively utilizing the renewable energy without impairing the function of any of the battery cells. Therefore, it is possible to further suppress the decrease in the effective storage capacity of the storage battery.

[0021] A power supply system according to another aspect of the present disclosure includes a DC bus for supplying DC power, a power supply device including a power generation device and supplying power to the DC bus, an auxiliary power supply device supplying power to the DC bus, a first converter connected to the DC bus and converting a bus voltage supplied to the DC bus into a load voltage supplied to a load device, a storage battery including a plurality of battery cells, a battery management device managing the storage battery, a second converter provided between the storage battery and the DC bus and capable of bidirectionally converting between the bus voltage and the battery voltage of the storage battery, and a power management device controlling the second converter to charge and discharge the storage battery. The power management device determines whether or not an implementation condition for performing cell balancing to equalize the states of charge of the plurality of battery cells is satisfied, and when the implementation condition is satisfied, changes a target voltage of the second converter so that the state of charge of the storage battery is in a state where the battery management device starts cell balancing.

[0022] In this power supply system, when an implementation condition for performing cell balancing is satisfied, the target voltage of the second converter is changed so that the state of charge of the storage battery becomes a state where the battery management device starts cell balancing. By changing the target voltage of the second converter, the storage battery connected to the second converter becomes more likely to be charged or discharged. Therefore, even if the storage battery is used within a range that does not reach an end-of-charge state or an end-of-discharge state during normal operation, cell balancing can be performed. As a result, it is possible to suppress a decrease in the effective storage capacity of the storage battery. Effect of the Invention

[0023] According to each aspect and embodiment of the present disclosure, it is possible to suppress a decrease in the effective power storage capacity of a storage battery. [Brief description of the drawings]

[0024] [Figure 1] FIG. 1 is a schematic diagram illustrating a power supply system including a power management device according to an embodiment. [Diagram 2] FIG. 2 is a hardware configuration diagram of the power management device shown in FIG. [Diagram 3] FIG. 3 is a functional block diagram of the power management device shown in FIG. [Figure 4] FIG. 4 is a diagram for explaining the relationship between the cell balancing function and the cell voltage of the battery cell. [Diagram 5] FIG. 5 is a flowchart showing a series of steps of the cell voltage equalization method performed by the power management device shown in FIG. [Figure 6] FIG. 6 is a flowchart showing a series of processes of another cell voltage equalization method performed by the power management device shown in FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0025] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the drawings. In the description of the drawings, the same elements are given the same reference numerals, and duplicated description will be omitted.

[0026] A power supply system including a power management device according to one embodiment will be described with reference to Fig. 1. Fig. 1 is a schematic configuration diagram of a power supply system including a power management device according to one embodiment. The power supply system 1 shown in Fig. 1 is a system that supplies load power WL (load voltage VL) to a load device L. In this embodiment, the power supply system 1 is a DC power supply system.

[0027] The load device L may be a DC load device that operates on a DC voltage, or an AC load device that operates on an AC voltage. Examples of DC load devices include an LED (Light Emission Diode) lighting device, a DC (Direct Current) fan, and a personal computer. Examples of AC load devices include a washing machine, a refrigerator, and an air conditioner. The power supply system 1 includes a DC bus 2, a power supply device 3, an auxiliary power supply device 5, a converter 6 (first converter), a power storage device 7, and a power management device 10.

[0028] The DC bus 2 is a bus that functions as a bus line for DC power supply to supply DC power. The DC bus 2 is laid across the locations where the power supply device 3, the auxiliary power supply device 5, the power storage device 7, and the load devices L are installed. A bus voltage Vbus is supplied to the DC bus 2. The bus voltage Vbus is a high-voltage DC voltage. The bus voltage Vbus is set so as to be included in the range of the input voltage of the converter 6. The bus voltage Vbus is, for example, a voltage of DC 250 V or more and DC 450 V or less. The voltage value of the bus voltage Vbus may be fixed or may vary.

[0029] The power supply device 3 is a device that supplies power to the DC bus 2. In this embodiment, the power supply system 1 includes two power supply devices 3. The number of power supply devices 3 is not limited to two and can be changed appropriately as necessary. The power supply device 3 includes a renewable energy power generation device 31 (power generation device) and a power conditioner 32.

[0030] The renewable energy power generation device 31 is a device that generates a generated power Wre. Examples of the renewable energy power generation device 31 include a solar power generation device, a wind power generation device, a hydroelectric power generation device, and a geothermal power generation device. The renewable energy power generation device 31 is connected to the DC bus 2 via a power conditioner 32. The renewable energy power generation device 31 generates a generated voltage Vre of a predetermined voltage value, and outputs a generated power Wre according to the generated voltage Vre. The generated voltage Vre may be a DC voltage or an AC voltage. Note that the voltage value of the generated voltage Vre and the magnitude of the generated power Wre generated by the two renewable energy power generation devices 31 may be different from each other, but for convenience of explanation, the same reference numerals are used.

[0031] The power conditioner 32 is connected to the DC bus 2 and is a device that converts the generated voltage Vre into a bus voltage Vbus. When the generated voltage Vre is a DC voltage, the power conditioner 32 includes a DC / DC converter. When the generated voltage Vre is an AC voltage, the power conditioner 32 includes an AC (Alternating Current) / DC converter. The power conditioner 32 operates, for example, with a DC voltage generated internally based on the generated voltage Vre. The power conditioner 32 controls the generated power Wre by controlling the power generation operation of the renewable energy power generation device 31 based on a command from the power management device 10.

[0032] When the power conditioner 32 receives a start command from the power management device 10, it converts the generated voltage Vre into a bus voltage Vbus and supplies the bus voltage Vbus to the DC bus 2, thereby supplying the generated power Wre to the DC bus 2. When the power conditioner 32 receives a stop command from the power management device 10, it stops the supply of the generated power Wre. The power conditioner 32 has a power measurement function that measures the generated power Wre supplied from the renewable energy power generation device 31 to the DC bus 2. The power conditioner 32 measures the generated power Wre, for example, periodically. The power conditioner 32 transmits the measurement value of the generated power Wre to the power management device 10.

[0033] The auxiliary power supply 5 is a device that supplies power to the DC bus 2. The auxiliary power supply 5 includes a commercial power supply 51 and an AC / DC converter 52. The commercial power supply 51 supplies system power Ws including a system voltage Vs of a predetermined voltage value. The system voltage Vs is an AC voltage. The commercial power supply 51 is connected to the DC bus 2 via the AC / DC converter 52.

[0034] The AC / DC converter 52 is connected to the DC bus 2 and is a device that converts the system voltage Vs into a bus voltage Vbus. The AC / DC converter 52 operates, for example, with a DC voltage generated internally based on the system voltage Vs. When the AC / DC converter 52 receives a start command from the power management device 10, the AC / DC converter 52 converts the system voltage Vs into a bus voltage Vbus and supplies the bus voltage Vbus to the DC bus 2, thereby supplying system power Ws to the DC bus 2. When the AC / DC converter 52 receives a stop command from the power management device 10, the AC / DC converter 52 stops supplying the system power Ws. The AC / DC converter 52 has a power measurement function that measures the system power Ws supplied from the commercial power source 51 to the DC bus 2. The AC / DC converter 52 measures the system power Ws, for example, periodically. The AC / DC converter 52 transmits a measurement value of the system power Ws to the power management device 10.

[0035] The auxiliary power supply device 5 is capable of supplying power stably, and is controlled to supply power when there is a power shortage in the entire power supply system 1. In order to maintain the power supply system 1, the grid power Ws is equal to or greater than the sum of the load powers WL and the standby power in the power supply system 1. The standby power includes the power consumption of the power management device 10 and the power consumption of auxiliary devices (such as a relay, a fan, and a small-capacity power supply, not shown).

[0036] The converter 6 is connected to the DC bus 2 and is a device that converts the bus voltage Vbus into a load voltage VL. The load voltage VL is a voltage supplied to the load device L. The load device L is connected to the DC bus 2 via the converter 6. The converter 6 operates on a DC voltage generated internally based on the bus voltage Vbus, for example. In this embodiment, the power supply system 1 includes four converters 6. The number of converters 6 is not limited to four and can be changed according to the number of load devices L.

[0037] When converter 6 receives a start command from power management device 10, it converts bus voltage Vbus to load voltage VL and supplies load voltage VL (load power WL) to load device L. If load device L is a DC load device, the load voltage VL is a DC voltage and converter 6 is a DC / DC converter. If load device L is an AC load device, the load voltage VL is an AC voltage and converter 6 is a DC / AC converter. When converter 6 receives a stop command from power management device 10, it stops supplying load voltage VL.

[0038] The converter 6 has a current limiting function that limits the load current supplied to the load device L from the DC bus 2 to an upper limit current value. The upper limit current value is set by the power management device 10. The converter 6 has a power measuring function that measures the load power WL supplied to the load device L from the DC bus 2 based on the load voltage VL and the load current. The converter 6 measures the load power WL, for example, periodically. The converter 6 transmits the measured value of the load power WL to the power management device 10.

[0039] The power storage device 7 is a device for storing surplus power generated in the power supply system 1 and supplying a power shortage generated in the power supply system 1. When a differential power obtained by subtracting the sum of the load powers WL from the sum of the supply powers is greater than 0, surplus power equal to the magnitude (power value) of the differential power is generated. The supply power is power supplied to the DC bus 2. In this embodiment, the supply power is the generated power Wre and the system power Ws. For example, each power storage device 7 is supplied with power Wc obtained by equally dividing the surplus power by the number of the power storage devices 7 from the DC bus 2. When the differential power is less than 0, a power shortage equal to the magnitude of the differential power is generated. For example, each power storage device 7 releases power Wc obtained by equally dividing the power shortage by the number of the power storage devices 7 to the DC bus 2.

[0040] The number of power storage devices 7 is not limited to three and can be changed appropriately as necessary. Each power storage device 7 includes a storage battery 71, a BMU (Battery Management Unit) 72, and a bidirectional DC / DC converter 73 (second converter).

[0041] The storage battery 71 is a device that can be charged and discharged. The storage battery 71 is connected to the DC bus 2 via a bidirectional DC / DC converter 73. Examples of the storage battery 71 include a lithium ion battery, a sodium sulfur (NAS) battery, a redox flow battery, a lead acid battery, and a nickel metal hydride battery. In this embodiment, the storage batteries 71 included in the multiple power storage devices 7 are of the same type and have the same storage capacity (charging capacity). The storage capacity is the maximum amount of storage that can be stored (charged). The storage batteries 71 included in the multiple power storage devices 7 may be of different types and may have different storage capacities. The storage battery 71 is a battery module including multiple battery cells. The multiple battery cells included in one storage battery 71 are of the same type and have the same storage capacity.

[0042] The BMU 72 is a device that manages the storage battery 71. The BMU 72 has a function of measuring the battery voltage Vbat of the storage battery 71, a function of measuring the cell voltages Vcell of the multiple battery cells that make up the storage battery 71, and a function of measuring the current value of the charge / discharge current of the storage battery 71 to calculate the SOC (State of charge: remaining capacity). The battery voltage Vbat is the voltage of the storage battery 71. The cell voltage Vcell is the voltage of a battery cell.

[0043] The BMU 72 transmits battery information of the storage battery 71 to the power management device 10. The battery information includes a measured value of the battery voltage Vbat, a measured value of the cell voltage Vcell of each battery cell, a current value of the charge / discharge current, and an SOC. The battery information may include only a measured value of the maximum cell voltage Vcellmax and a measured value of the minimum cell voltage Vcellmin, instead of the measured values ​​of all the cell voltages Vcell. The maximum cell voltage Vcellmax is the maximum cell voltage among the cell voltages Vcell of the multiple battery cells. The minimum cell voltage Vcellmin is the minimum cell voltage among the cell voltages Vcell of the multiple battery cells. The BMU 72 periodically transmits the battery information to the power management device 10.

[0044] The BMU 72 has a cell balancing function that equalizes the cell voltages (charge states) of the multiple battery cells included in the storage battery 71. The BMU 72 includes a BMU 72 whose cell balancing function operates in the final stage of charging the storage battery 71, and a BMU 72 whose cell balancing function operates in the final stage of discharging the storage battery 71. For example, when the BMU 72 receives a cell balancing permission signal from the power management device 10, the BMU 72 enables the cell balancing function. The BMU 72 performs cell balancing of the storage battery 71 while continuing to charge and discharge the storage battery 71. In other words, even while cell balancing is being performed, the storage battery 71 (power storage device 7) is charged and discharged via the bidirectional DC / DC converter 73 without being disconnected from the power supply system 1.

[0045] The bidirectional DC / DC converter 73 is connected to the DC bus 2 and is a device capable of bidirectionally converting between the bus voltage Vbus and the battery voltage Vbat. The bidirectional DC / DC converter 73 is provided between the storage battery 71 and the DC bus 2. A known bidirectional DC / DC converter may be used as the bidirectional DC / DC converter 73. The bidirectional DC / DC converter 73 operates, for example, with a DC voltage generated internally based on the bus voltage Vbus.

[0046] The bidirectional DC / DC converter 73 is controlled by the power management device 10. Specifically, when the bidirectional DC / DC converter 73 receives a charge command from the power management device 10, it converts the bus voltage Vbus to a battery voltage Vbat and flows a charging current from the DC bus 2 to the storage battery 71. This charges the storage battery 71. When the bidirectional DC / DC converter 73 receives a discharge command from the power management device 10, it converts the battery voltage Vbat to the bus voltage Vbus and flows a discharging current from the storage battery 71 to the DC bus 2. This discharges the storage battery 71. The bidirectional DC / DC converter 73 may charge or discharge the storage battery 71 by a constant current method, or may charge or discharge the storage battery 71 by a constant voltage method.

[0047] When the bidirectional DC / DC converter 73 receives a stop command from the power management device 10, it stops its operation and transitions to a sleep state in which power consumption is reduced. When the bidirectional DC / DC converter 73 receives a charge command or a discharge command in the sleep state, it leaves the sleep state and executes a charge process or a discharge process. The bidirectional DC / DC converter 73 has a current limiting function that limits each current value of the charge current supplied to the storage battery 71 and the discharge current discharged from the storage battery 71 to a maximum current value or less. When the bidirectional DC / DC converter 73 receives a setting command for the maximum current value from the power management device 10, it sets the maximum current value specified by the setting command. When the bidirectional DC / DC converter 73 receives a setting command for the target voltage from the power management device 10, it sets the target voltage specified by the setting command. The target voltage (value) is a voltage (value) for keeping the voltage value of the bus voltage Vbus constant. The bidirectional DC / DC converter 73 has a function of trying to maintain the voltage value of the bus voltage Vbus at the target voltage (value) even when the power Wc is changed.

[0048] The bidirectional DC / DC converter 73 has a power measurement function for measuring the power Wc. The bidirectional DC / DC converter 73 measures the power Wc periodically, for example. The bidirectional DC / DC converter 73 transmits the measurement value of the power Wc to the power management device 10.

[0049] The power management device 10 is a device (controller) that manages the entire power supply system 1. The power management device 10 is also referred to as an EMS (Energy Management System). The power management device 10 is connected to the power supply device 3, the auxiliary power supply device 5, the converter 6, and the power storage device 7 via communication lines so that they can communicate with each other. The communication lines may be either wired or wireless. The power management device 10 may perform communication in accordance with standards such as RS-232C, RS-485, CAN (Controller Area Network), and Ethernet (registered trademark).

[0050] The power management device 10 performs a voltage measurement process to measure the bus voltage Vbus. The power management device 10 may directly measure the bus voltage Vbus. The bidirectional DC / DC converter 73 may measure the bus voltage Vbus and transmit the measurement value to the power management device 10, so that the power management device 10 may indirectly measure the bus voltage Vbus.

[0051] Power management device 10 transmits a start command and a stop command to each of power conditioner 32, AC / DC converter 52, converter 6, and bidirectional DC / DC converter 73. For example, power management device 10 transmits a start command to converter 6 to cause converter 6 to supply load voltage VL. Power management device 10 transmits a stop command to converter 6 to cause converter 6 to stop supplying load voltage VL. The same applies to the other converters.

[0052] The power management device 10 controls the bidirectional DC / DC converter 73 to perform a charge / discharge process for charging / discharging the storage battery 71. The power management device 10 performs a charge / discharge process according to the differential power. When the sum of the supply powers is greater than the sum of the load powers WL (when the differential power is greater than 0), the power management device 10 transmits a charge command to the bidirectional DC / DC converter 73 to cause the storage battery 71 to store the surplus power, which is the differential power. For example, power obtained by equally dividing the surplus power by the number of storage batteries 71 is stored in each storage battery 71. When the sum of the supply powers is less than the sum of the load powers WL (when the differential power is less than 0), the power management device 10 transmits a discharge command to the bidirectional DC / DC converter 73 to cause the storage battery 71 to release the shortage power. For example, power obtained by equally dividing the shortage power by the number of storage batteries 71 is released from each storage battery 71.

[0053] The power management device 10 performs a cell voltage equalization process (cell voltage equalization method) for equalizing the cell voltages of the battery cells included in the storage battery 71. For example, when the power supply system 1 is started up, the power management device 10 transmits a cell balancing permission signal to each BMU 72 to enable the cell balancing function of the BMU 72. When a BMU 72 with a cell balancing function that is always enabled is used, the power management device 10 does not need to transmit the cell balancing permission signal. The power management device 10 determines whether an implementation condition is satisfied in the cell voltage equalization process, and performs cell balancing implementation control to cause the BMU 72 to implement cell balancing when the implementation condition is satisfied. The implementation condition is a condition under which cell balancing of a plurality of battery cells included in the storage battery 71 should be implemented. The cell voltage equalization process will be described in detail later.

[0054] FIG. 2 is a hardware configuration diagram of the power management device shown in FIG. 1. As shown in FIG. 2, the power management device 10 may be physically configured as a computer including hardware such as a processor 101, a memory 102, and a communication interface 103. An example of the processor 101 is a CPU (Central Processing Unit). The number of processors 101 may be one or may be two or more. The memory 102 may include a main storage device and an auxiliary storage device. The main storage device is configured with a RAM (Random Access Memory) and a ROM (Read Only Memory), etc. Examples of the auxiliary storage device include a semiconductor memory and a hard disk device. The communication interface 103 is a device that transmits and receives data to and from other devices. The communication interface 103 is configured with, for example, a communication module, a network interface card (NIC), or a wireless communication module that complies with communication standards such as RS-232C, RS-485, and CAN.

[0055] The processor 101 reads and executes a program stored in the memory 102, whereby each piece of hardware operates under the control of the processor 101, and data is read from and written to the memory 102. In this way, each functional unit of the power management device 10 shown in FIG.

[0056] Fig. 3 is a functional block diagram of the power management device shown in Fig. 1. As shown in Fig. 3, power management device 10 functionally comprises an acquisition unit 11, a determination unit 12 (first determination unit), a determination unit 13 (second determination unit), and a control unit 14. The function (operation) of each functional unit will be described in detail in the description of the cell voltage equalization method described later, so the function of each functional unit will be briefly described here.

[0057] The acquisition unit 11 is a functional unit that acquires (receives) information necessary for the cell voltage equalization method. The acquisition unit 11 acquires battery information of each storage battery 71 and a measurement value of each power. The acquisition unit 11 acquires, from each BMU 72, battery information of the storage battery 71 managed by the BMU 72. For example, the acquisition unit 11 acquires a measurement value of the system power Ws from the AC / DC converter 52, and acquires a measurement value of the load power WL from the converter 6.

[0058] The determination unit 12 is a functional unit that determines whether or not the implementation condition is satisfied. The determination unit 12 determines whether or not the implementation condition is satisfied based on, for example, the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin among the cell voltages Vcell of the multiple battery cells included in the storage battery 71. The determination unit 12 may determine whether or not the implementation condition is satisfied based on the total power consumption (load power WL) consumed by the load devices L per day and the total system power Ws supplied by the auxiliary power supply 5 to the DC bus 2 per day. The determination unit 12 makes the above determination using the measurement values ​​acquired by the acquisition unit 11.

[0059] The determination unit 13 is a functional unit that determines whether or not the charging state of the storage battery 71 has reached a predetermined state. For example, the determination unit 13 determines whether or not the charging state of the storage battery 71 has reached a fully charged state or a completely discharged state. The determination unit 13 makes the above determination using the measurement value acquired by the acquisition unit 11.

[0060] The control unit 14 is a functional unit that performs cell balancing implementation control to cause the BMU 72 to perform cell balancing. The control unit 14 performs cell balancing implementation control when an implementation condition is satisfied and the charging state of the storage battery 71 becomes a predetermined state.

[0061] Here, the relationship between the cell balancing function and the cell voltage of the battery cell will be described with reference to FIG. 4. As shown in FIG. 4, each battery cell can be used with a cell voltage Vcell ranging from a minimum voltage Vmin to a maximum voltage Vmax. The maximum voltage Vmax is the maximum voltage to which the battery cell can be charged. The minimum voltage Vmin is the minimum voltage to which the battery cell can be discharged. If the battery cell is charged with the cell voltage Vcell exceeding the maximum voltage Vmax, the battery cell is overcharged. If the battery cell is discharged until the cell voltage Vcell falls below the minimum voltage Vmin, the battery cell is overdischarged.

[0062] Therefore, in consideration of safety, during normal operation, each battery cell is used with a cell voltage Vcell in the range from the lower limit voltage Vlim2 to the upper limit voltage Vlim1. The lower limit voltage Vlim2 is greater than the minimum voltage Vmin. The lower limit voltage Vlim2 is also referred to as a fully discharged voltage. The upper limit voltage Vlim1 is greater than the lower limit voltage Vlim2 and less than the maximum voltage Vmax. The upper limit voltage Vlim1 is also referred to as a fully charged voltage. The difference between the maximum voltage Vmax and the upper limit voltage Vlim1 and the difference between the lower limit voltage Vlim2 and the minimum voltage Vmin are set to, for example, about 5% of the maximum voltage Vmax.

[0063] The storage battery 71 includes a plurality of battery cells, and the cell voltage Vcell of each battery cell may vary. Therefore, when the maximum cell voltage Vcellmax reaches the upper limit voltage Vlim1, the state of charge of the storage battery 71 is considered to be a fully charged state. When the minimum cell voltage Vcellmin reaches the lower limit voltage Vlim2, the state of charge of the storage battery 71 is considered to be a fully discharged state. As the storage battery 71 is used, the cell voltages Vcell of each battery cell included in the storage battery 71 may vary more. When the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin becomes larger, the effective storage capacity of the storage battery 71 decreases.

[0064] The BMU 72, which operates the cell balancing function at the end of charging the storage battery 71, starts the cell balancing operation when the maximum cell voltage Vcellmax reaches the start voltage Vstr1, and ends the cell balancing operation when the maximum cell voltage Vcellmax reaches the completion voltage Vcomp1. The start voltage Vstr1 is greater than the upper limit voltage Vlim1 and less than the maximum voltage Vmax. The completion voltage Vcomp1 is greater than the start voltage Vstr1 and less than the maximum voltage Vmax. As will be described later, in the power supply system 1, the storage battery 71 is continuously charged while the cell balancing of the storage battery 71 is being performed. Therefore, while the cell balancing is being performed, the cell voltages Vcell of the multiple battery cells included in the storage battery 71 gradually increase and approach each other. The voltage value when the cell voltages Vcell become equal to each other is set to the completion voltage Vcomp1.

[0065] The BMU 72, which operates the cell balancing function at the end of discharging the storage battery 71, starts the cell balancing operation when the minimum cell voltage Vcellmin reaches the start voltage Vstr2, and ends the cell balancing operation when the minimum cell voltage Vcellmin reaches the completion voltage Vcomp2. The start voltage Vstr2 is greater than the minimum voltage Vmin and less than the lower limit voltage Vlim2. The completion voltage Vcomp2 is greater than the minimum voltage Vmin and less than the start voltage Vstr2. As will be described later, in the power supply system 1, while the cell balancing of the storage battery 71 is being performed, the storage battery 71 is continuously discharged. Therefore, while the cell balancing is being performed, the cell voltages Vcell of the multiple battery cells included in the storage battery 71 gradually decrease and approach each other. The voltage value when the cell voltages Vcell become equal to each other is set to the completion voltage Vcomp2.

[0066] Next, the cell voltage equalization method performed by the power management device 10 will be described with reference to FIG. 5. FIG. 5 is a flowchart showing a series of processes of the cell voltage equalization method performed by the power management device shown in FIG. 1. The cell voltage equalization method shown in FIG. 5 is performed on the BMU 72 in which the cell balance function operates at the end of charging the storage batteries 71. The series of processes in FIG. 5 is started by, for example, acquiring battery information of each storage battery 71, a measured value of the system power Ws, and a measured value of the load power WL. Note that while the series of processes shown in FIG. 5 are being performed, the acquisition unit 11 periodically acquires battery information of each storage battery 71, a measured value of the system power Ws, and a measured value of the load power WL.

[0067] First, the judgment unit 12 judges whether or not an implementation condition is satisfied (step S11). In step S11, the judgment unit 12 performs a first judgment and a second judgment. Note that the first judgment and the second judgment are performed using the measurement value acquired by the acquisition unit 11, but for convenience of explanation, the measurement value of the cell voltage Vcell is simply expressed as "cell voltage Vcell". Other parameters are expressed in the same manner.

[0068] <First judgment> The determination unit 12 calculates the ratio Rd of each storage battery 71 and compares each ratio Rd with a ratio threshold value Rdth. As shown in formula (1), the ratio Rd is obtained by dividing the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin by the theoretical cell voltage value Vcell_t.

number

[0069] The maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin are respectively the maximum cell voltage Vcell and the minimum cell voltage Vcell among the multiple cell voltages measured (acquired) simultaneously. The theoretical value Vcell_t is obtained, for example, by dividing the maximum voltage of the storage battery 71 by the number of battery cells connected in series. The maximum voltage of the storage battery 71 is the maximum voltage that can be charged. The theoretical value Vcell_t is equal to the maximum voltage Vmax, for example. The ratio threshold Rdth is set in advance. The ratio threshold Rdth is, for example, 2.0% or less. A method for determining the ratio threshold Rdth will be described later. When any ratio Rd is greater than the ratio threshold Rdth, the determination unit 12 determines that the implementation condition is satisfied for the storage battery 71 having the ratio Rd (step S11; YES). Then, the determination unit 12 determines the storage battery 71 as the target storage battery 71 for which cell balancing is to be performed (hereinafter, may be simply referred to as the "target storage battery 71").

[0070] <Second judgment> The determination unit 12 calculates the storage capacity rate Rc of the entire storage battery 71, and compares the storage capacity rate Rc with a capacity rate threshold value Rcth. As shown in formula (2), the storage capacity rate Rc is obtained by dividing the moving average value of the value obtained by subtracting the total amount Ws_total of the grid power Ws per day from the total amount WL_total of the load power WL (power consumption) per day by the theoretical value Cmod of the storage capacity of the entire storage battery 71.

number

[0071] The function SMA is a function for calculating a moving average value. Here, the moving average value for the most recent five days is calculated. The theoretical value Cmod is the sum of the rated capacities of all the storage batteries 71 included in the power supply system 1. The capacity rate threshold Rcth is set in advance. The capacity rate threshold Rcth is, for example, 65% or more. A method for determining the capacity rate threshold Rcth will be described later. When the storage capacity rate Rc is smaller than the capacity rate threshold Rcth, the determination unit 12 determines that the implementation condition is satisfied (step S11; YES). Then, the determination unit 12 determines an arbitrary storage battery 71 as the target storage battery 71 among all the storage batteries 71 included in the power supply system 1. For example, the determination unit 12 determines the target storage battery 71 from among all the storage batteries 71 according to a predetermined order. After all the storage batteries 71 have been selected as the target storage battery 71, the storage batteries 71 are selected again in order starting from the first storage battery 71.

[0072] That is, the determination unit 12 determines that the implementation condition is satisfied when the ratio Rd of any of the storage batteries 71 is greater than the ratio threshold Rdth or the storage capacity rate Rc is smaller than the capacity rate threshold Rcth (step S11; YES).On the other hand, the determination unit 12 determines that the implementation condition is not satisfied when the ratio Rd is smaller than the ratio threshold Rdth and the storage capacity rate Rc is greater than the capacity rate threshold Rcth for any of the storage batteries 71 (step S11; NO).

[0073] If it is determined in step S11 that the implementation condition is not satisfied (step S11; NO), the judgment unit 12 repeats the judgment in step S11 until the implementation condition is satisfied. For example, each time the acquisition unit 11 acquires each measurement value, the judgment unit 12 repeats the judgment in step S11 using the acquired measurement value. On the other hand, if it is determined in step S11 that the implementation condition is satisfied (step S11; YES), the judgment unit 12 outputs a judgment result indicating that the implementation condition is satisfied to the judgment unit 13 and the control unit 14. The judgment result includes identification information capable of identifying the target storage battery 71.

[0074] Next, when the determination unit 13 receives the determination result from the determination unit 12, the determination unit 13 determines whether the charging state of the target storage battery 71 identified by the identification information is a fully charged state (step S12). In this embodiment, the determination unit 13 determines whether the maximum cell voltage Vcellmax among the cell voltages Vcell of the multiple battery cells included in the target storage battery 71 is equal to or greater than the upper limit voltage Vlim1.

[0075] When the maximum cell voltage Vcellmax is less than the upper limit voltage Vlim1, the determination unit 13 determines that the state of charge of the target storage battery 71 is not a fully charged state (step S12; NO), and repeats the determination of step S12 until the state of charge of the target storage battery 71 becomes a fully charged state. For example, each time the acquisition unit 11 acquires measurement values ​​of multiple cell voltages Vcell included in the target storage battery 71, the determination unit 13 repeats the determination of step S12 using the acquired measurement values. On the other hand, when the maximum cell voltage Vcellmax is equal to or greater than the upper limit voltage Vlim1, the determination unit 13 determines that the state of charge of the target storage battery 71 is a fully charged state (step S12; YES), and outputs a determination result indicating that the state of charge of the target storage battery 71 is a fully charged state to the control unit 14.

[0076] Next, when the control unit 14 receives the above-mentioned determination result from the determination unit 12 and also receives the above-mentioned determination result from the determination unit 13, it performs cell balancing implementation control (step S13). In the cell balancing implementation control of step S13, the control unit 14 changes the target voltage of the bidirectional DC / DC converter 73 so that the state of charge of the target storage battery 71 becomes a state where the BMU 72 starts cell balancing. In this embodiment, the control unit 14 transmits a target voltage setting command to the bidirectional DC / DC converter 73 in order to lower the target voltage of the bidirectional DC / DC converter 73.

[0077] Furthermore, in the cell balancing implementation control in step S13, the control unit 14 transmits a maximum current value setting command to the bidirectional DC / DC converter 73 in order to reduce the maximum current value between the bidirectional DC / DC converter 73 and the target storage battery 71. Furthermore, the control unit 14 transmits a stop command to the power conditioner 32 in order to stop the power supply of the renewable energy power generation device 31, and transmits a start command to the AC / DC converter 52 in order to cause the auxiliary power supply 5 to supply power. If the auxiliary power supply 5 is already started, the start command is not transmitted.

[0078] By this cell balancing implementation control, the target storage battery 71 is preferentially charged over other storage batteries 71 without stopping the power supply to the load device L. Then, when the maximum cell voltage Vcellmax reaches the start voltage Vstr1, the BMU 72 performs cell balancing of the multiple battery cells included in the target storage battery 71. At this time, since the target storage battery 71 is continuously charged, the cell voltages Vcell of the multiple battery cells included in the target storage battery 71 continue to gradually increase so as to become equal to each other.

[0079] Next, the determination unit 13 determines whether or not cell balancing of the target storage battery 71 has been completed (step S14). In this embodiment, the determination unit 13 determines whether or not the maximum cell voltage Vcellmax of the cell voltages Vcell of the multiple battery cells included in the target storage battery 71 is equal to or greater than the completion voltage Vcomp1. If the maximum cell voltage Vcellmax is less than the completion voltage Vcomp1, the determination unit 13 determines that cell balancing of the target storage battery 71 has not been completed (step S14; NO), and repeats the determination of step S14 until cell balancing of the target storage battery 71 is completed. For example, every time the acquisition unit 11 acquires measurement values ​​of the multiple cell voltages Vcell included in the target storage battery 71, the determination unit 13 repeats the determination of step S14 using the acquired measurement values. On the other hand, if the maximum cell voltage Vcellmax is greater than or equal to the completion voltage Vcomp1, the judgment unit 13 judges that cell balancing of the target storage battery 71 has been completed (step S14; YES), and outputs a judgment result indicating that cell balancing of the target storage battery 71 has been completed to the control unit 14.

[0080] Next, when the control unit 14 receives the above-mentioned determination result from the determination unit 13, it restores the settings changed by the cell balance implementation control in step S13 to the original settings (step S15). Specifically, the control unit 14 transmits a target voltage setting command to the bidirectional DC / DC converter 73 in order to increase the target voltage of the bidirectional DC / DC converter 73 to the original target voltage. Furthermore, the control unit 14 transmits a maximum current value setting command to the bidirectional DC / DC converter 73 in order to increase the maximum current value between the bidirectional DC / DC converter 73 and the target storage battery 71 to the original maximum current value. Furthermore, the control unit 14 transmits a start command to the power conditioner 32 in order to resume the power supply of the renewable energy power generation device 31, and transmits a stop command to the AC / DC converter 52 in order to stop the power supply of the auxiliary power supply device 5.

[0081] This completes the series of processes of the cell voltage equalization method shown in FIG.

[0082] Next, with reference to FIG. 6, another cell voltage equalization method performed by the power management device 10 will be described. FIG. 6 is a flowchart showing a series of processes of another cell voltage equalization method performed by the power management device shown in FIG. 1. The cell voltage equalization method shown in FIG. 6 is performed on the BMU 72 in which the cell balance function operates at the end of discharging the storage battery 71. The series of processes in FIG. 6 is started by, for example, acquiring battery information of each storage battery 71, a measured value of the system power Ws, and a measured value of the load power WL. Note that while the series of processes shown in FIG. 6 are being performed, the acquisition unit 11 periodically acquires battery information of each storage battery 71, a measured value of the system power Ws, and a measured value of the load power WL.

[0083] First, the determination unit 12 determines whether or not an implementation condition is satisfied (step S21). Step S21 is similar to step S11, and therefore a detailed description thereof will be omitted here.

[0084] Next, when the determination unit 13 receives a determination result indicating that the implementation condition is satisfied from the determination unit 12, the determination unit 13 determines whether the state of charge of the target storage battery 71 identified by the identification information is a fully discharged state (step S22). In this embodiment, the determination unit 13 determines whether the minimum cell voltage Vcellmin of the cell voltages Vcell of the multiple battery cells included in the target storage battery 71 is equal to or lower than the lower limit voltage Vlim2.

[0085] When the minimum cell voltage Vcellmin is greater than the lower limit voltage Vlim2, the determination unit 13 determines that the state of charge of the target storage battery 71 is not a fully discharged state (step S22; NO), and repeats the determination of step S22 until the state of charge of the target storage battery 71 becomes a fully discharged state. For example, each time the acquisition unit 11 acquires measurement values ​​of multiple cell voltages Vcell included in the target storage battery 71, the determination unit 13 repeats the determination of step S22 using the acquired measurement values. On the other hand, when the minimum cell voltage Vcellmin is equal to or less than the lower limit voltage Vlim2, the determination unit 13 determines that the state of charge of the target storage battery 71 is a fully discharged state (step S22; YES), and outputs a determination result indicating that the state of charge of the target storage battery 71 is a fully discharged state to the control unit 14.

[0086] Next, when the control unit 14 receives the above-mentioned determination result from the determination unit 12 and also receives the above-mentioned determination result from the determination unit 13, it performs cell balancing implementation control (step S23). In the cell balancing implementation control of step S23, the control unit 14 changes the target voltage of the bidirectional DC / DC converter 73 so that the state of charge of the target storage battery 71 becomes a state where the BMU 72 starts cell balancing. In this embodiment, the control unit 14 transmits a target voltage setting command to the bidirectional DC / DC converter 73 in order to increase the target voltage of the bidirectional DC / DC converter 73.

[0087] Furthermore, in the cell balancing implementation control in step S23, the control unit 14 transmits a maximum current value setting command to the bidirectional DC / DC converter 73 in order to reduce the maximum current value between the bidirectional DC / DC converter 73 and the target storage battery 71. Furthermore, the control unit 14 transmits a stop command to the power conditioner 32 in order to stop the power supply of the renewable energy power generation device 31, and transmits a start command to the AC / DC converter 52 in order to cause the auxiliary power supply 5 to supply power. If the auxiliary power supply 5 is already started, the start command is not transmitted.

[0088] This cell balancing implementation control allows the target storage battery 71 to be discharged preferentially over other storage batteries 71, without stopping the power supply to the load device L. Then, when the minimum cell voltage Vcellmin reaches the start voltage Vstr2, the BMU 72 performs cell balancing of the multiple battery cells included in the target storage battery 71. At this time, since the target storage battery 71 continues to be discharged, the cell voltages Vcell of the multiple battery cells included in the target storage battery 71 continue to gradually decrease so as to become equal to each other.

[0089] Next, the determination unit 13 determines whether or not cell balancing of the target storage battery 71 has been completed (step S24). In this embodiment, the determination unit 13 determines whether or not the minimum cell voltage Vcellmin of the cell voltages Vcell of the multiple battery cells included in the target storage battery 71 is equal to or lower than the completion voltage Vcomp2. If the minimum cell voltage Vcellmin is greater than the completion voltage Vcomp2, the determination unit 13 determines that cell balancing of the target storage battery 71 has not been completed (step S24; NO), and repeats the determination of step S24 until cell balancing of the target storage battery 71 is completed. On the other hand, if the minimum cell voltage Vcellmin is equal to or lower than the completion voltage Vcomp2, the determination unit 13 determines that cell balancing of the target storage battery 71 has been completed (step S24; YES), and outputs a determination result indicating that cell balancing of the target storage battery 71 has been completed to the control unit 14.

[0090] Next, when the control unit 14 receives the above-mentioned determination result from the determination unit 13, it restores the settings changed by the cell balance implementation control in step S23 to the original settings (step S25). Specifically, the control unit 14 transmits a target voltage setting command to the bidirectional DC / DC converter 73 in order to lower the target voltage of the bidirectional DC / DC converter 73 to the original target voltage. Furthermore, the control unit 14 transmits a maximum current value setting command to the bidirectional DC / DC converter 73 in order to increase the maximum current value of the current between the bidirectional DC / DC converter 73 and the target storage battery 71 to the original maximum current value. Furthermore, the control unit 14 transmits a start command to the power conditioner 32 in order to resume the power supply of the renewable energy power generation device 31, and transmits a stop command to the AC / DC converter 52 in order to stop the power supply of the auxiliary power supply device 5.

[0091] This completes the series of processes of the cell voltage equalization method shown in FIG.

[0092] Next, an example of a method for determining the ratio threshold value Rdth will be described. First, ten units of each of the following four types of storage batteries 71 (battery modules) were prepared. <Battery module 1> Battery type: LFP (olivine iron lithium-ion battery), Number of battery cells (number of series): 16, Maximum module voltage (maximum voltage of 71 storage batteries): 57.6V, Maximum voltage of battery cell: 3.60V <Battery module 2> Battery type: LFP (olivine iron lithium-ion battery), Number of battery cells (number of series): 16, Maximum module voltage: 56.0V, Maximum battery cell voltage: 3.50V <Battery module 3> Battery type: NMC (ternary lithium-ion battery (nickel-manganese-cobalt)), Number of battery cells (number of series): 14, Maximum module voltage: 58.1V, Maximum battery cell voltage: 4.15V <Battery module 4> Battery type: LMO (lithium titanate + spinel manganese lithium-ion battery), Number of battery cells (number of series): 28, Maximum module voltage: 58.8V, Maximum battery cell voltage: 2.10V

[0093] Using 10 battery modules of each type, the ratio threshold Rdth was set to several values, and the power supply system 1 was operated at each ratio threshold Rdth. As a result, the frequency (number) and cumulative total of battery modules not meeting the function, as well as the operation frequency of the cell balance function, were obtained. The results are shown in Table 1. When the battery modules were repeatedly charged and discharged without the cell balance function being operated, a battery module that could not be charged and discharged was determined to be a battery module that did not meet the function. The test was performed in ascending order of ratio threshold, and the number of battery modules that did not meet the function at that ratio threshold was regarded as the frequency. The cumulative total is the sum of the frequencies at ratio thresholds below that ratio threshold.

[0094] The operation frequency is the ratio of the number of times the cell balancing function was operated to the number of times the charge state of the storage battery 71 reached a specified state (fully charged state or completely discharged state). When a BMU 72 that operates the cell balancing function is used in the final stage of charging the storage battery 71, the operation frequency is the ratio of the number of times the cell balancing function was operated to the number of times the charge state of the storage battery 71 reached a fully charged state. When a BMU 72 that operates the cell balancing function is used in the final stage of discharging the storage battery 71, the operation frequency is the ratio of the number of times the cell balancing function was operated to the number of times the charge state of the storage battery 71 reached a completely discharged state. [Table 1]

[0095] From the results shown in Table 1, it was confirmed that the power supply system 1 is not stopped if the ratio threshold Rdth is 2.0% or less. In the cell balance implementation control, the power supply of the renewable energy power generation device 31 is stopped, so if the operation frequency of the cell balance function is high (for example, the operation frequency is greater than 30%), the effective use of renewable energy by the renewable energy power generation device 31 is hindered. Therefore, it was confirmed that the renewable energy is effectively used if the ratio threshold Rdth is 0.3% or more. When the ratio threshold Rdth is 0.1%, the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin is about 5mV. When the ratio threshold Rdth is 0.2%, the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin is about 8mV. These differences are within the allowable range.

[0096] Next, an example of a method for determining the capacity rate threshold Rcth will be described. Using the above-mentioned battery module 1, the capacity rate threshold Rcth was set to several values, and the power supply system 1 was operated at each capacity rate threshold Rcth. As a result, the frequency (number) and cumulative total of battery modules not satisfying the function, as well as the operation frequency of the cell balance function, were obtained. The results are shown in Table 2. The tests were carried out in descending order of capacity rate threshold, and the number of battery modules not satisfying the function at that capacity rate threshold was regarded as the frequency. The cumulative total is the sum of the frequencies at capacity rate thresholds equal to or higher than that capacity rate threshold. [Table 2]

[0097] From the results shown in Table 2, it was confirmed that if the capacity rate threshold Rcth is 65% or more, the power supply system 1 is not shut down. As described above, if the operation frequency of the cell balancing function is high (for example, the operation frequency is greater than 30%), the effective use of renewable energy by the renewable energy power generation device 31 is hindered. Therefore, it was confirmed that if the capacity rate threshold Rcth is 90% or less, renewable energy is used effectively.

[0098] In the power management device 10 and power supply system 1 described above, when the conditions for performing cell balancing are satisfied, the target voltage of the bidirectional DC / DC converter 73 is changed so that the state of charge of the target storage battery 71 becomes a state where the BMU 72 starts cell balancing. By changing the target voltage of the bidirectional DC / DC converter 73, the target storage battery 71 connected to the bidirectional DC / DC converter 73 becomes more likely to be charged or discharged. Therefore, even if the storage battery 71 is used within a range that does not reach an end-of-charge state or an end-of-discharge state during normal operation, cell balancing can be performed. As a result, it is possible to suppress a decrease in the effective storage capacity of the storage battery 71.

[0099] The control unit 14 performs cell balancing control when the execution condition is satisfied and the state of charge of the target storage battery 71 becomes a predetermined state. When the execution condition is satisfied, the state of charge of the target storage battery 71 is not necessarily a fully charged state or a completely discharged state. According to the above configuration, for example, in the case where the BMU 72 that performs cell balancing when the storage battery 71 becomes a terminal charging state is used, the cell balancing control is performed when the state of charge of the target storage battery 71 becomes the upper limit of the normal use range (fully charged state). In other words, the power supply system 1 operates normally until the state of charge of the target storage battery 71 becomes a fully charged state. Similarly, for example, in the case where the BMU 72 that performs cell balancing when the storage battery 71 becomes a terminal discharging state is used, the cell balancing control is performed when the state of charge of the target storage battery 71 becomes the lower limit of the normal use range (fully discharged state). In other words, the power supply system 1 operates normally until the state of charge of the target storage battery 71 becomes a fully discharged state. Therefore, the power supply system 1 can be operated as normally as possible, and the stability of the power supply system 1 can be improved.

[0100] When the storage battery 71 reaches the final charging state, the BMU 72 may perform cell balancing. In this case, the control unit 14 performs cell balancing control when the execution condition is satisfied and the charging state of the target storage battery 71 reaches a fully charged state. In the cell balancing control, the control unit 14 lowers the target voltage of the bidirectional DC / DC converter 73. According to this configuration, the target storage battery 71 is further charged from the fully charged state by lowering the target voltage of the bidirectional DC / DC converter 73. As a result, the charging state of the target storage battery 71 can be set to a charging state at which the BMU 72 starts cell balancing, making it possible to suppress a decrease in the effective storage capacity of the target storage battery 71.

[0101] When the storage battery 71 reaches a final discharge state, the BMU 72 may perform cell balancing. In this case, the control unit 14 performs cell balancing control when the implementation condition is satisfied and the state of charge of the target storage battery 71 reaches a fully discharged state. In the cell balancing control, the control unit 14 increases the target voltage of the bidirectional DC / DC converter 73. According to this configuration, the target storage battery 71 is further discharged from the fully discharged state by increasing the target voltage of the bidirectional DC / DC converter 73. As a result, the state of charge of the target storage battery 71 can be set to a charging state at which the BMU 72 starts cell balancing, making it possible to suppress a decrease in the effective storage capacity of the target storage battery 71.

[0102] In the cell balancing implementation control, the control unit 14 reduces the maximum current value of the current between the bidirectional DC / DC converter 73 and the target storage battery 71. The cell balancing is implemented when the charge state of the storage battery 71 is a terminal charging state or a terminal discharging state. In the terminal charging state, if the storage battery 71 is charged suddenly, it may be in an overcharged state. Therefore, by reducing the maximum current value, the charging speed can be reduced, and the possibility of the target storage battery 71 being in an overcharged state can be reduced. Similarly, in the terminal discharging state, if the storage battery 71 is discharged suddenly, it may be in an overdischarged state. Therefore, by reducing the maximum current value, the discharging speed can be reduced, and the possibility of the target storage battery 71 being in an overdischarged state can be reduced.

[0103] When the maximum current value between the bidirectional DC / DC converter 73 and the target storage battery 71 is reduced, the amount of power that can be charged to the target storage battery 71 via the bidirectional DC / DC converter 73 decreases. Therefore, when the renewable energy power generation device 31 generates the generated power Wre, the amount of power received by the target storage battery 71 decreases, which may cause the power balance to be lost. In response to this, the control unit 14 stops the power supply to the renewable energy power generation device 31 in the cell balance implementation control. With this configuration, it is possible to maintain the power balance.

[0104] In the cell balancing implementation control, the control unit 14 causes the auxiliary power supply 5 to supply system power Ws. By performing cell balancing, the power Wc that can be supplied from the target storage battery 71 may decrease. For example, if the maximum current value of the current between the bidirectional DC / DC converter 73 and the target storage battery 71 is reduced, the power Wc that can be supplied from the target storage battery 71 may decrease. Therefore, by causing the auxiliary power supply 5 to supply system power Ws, it is possible to compensate for the decrease in the power Wc supplied from the target storage battery 71.

[0105] The determination unit 12 determines whether the implementation condition is satisfied based on the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin among the cell voltages Vcell of the multiple battery cells. It is considered that the greater the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin, the greater the variation in the state of charge among the multiple battery cells. Therefore, by taking the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin into consideration, it is possible to improve the accuracy of determining whether or not cell balancing should be performed.

[0106] Specifically, the determination unit 12 determines that the implementation condition is satisfied when the ratio Rd is greater than the ratio threshold value Rdth. The ratio Rd is obtained by dividing the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin by the theoretical value Vcell_t of the cell voltage. The magnitude of the difference between the maximum cell voltage Vcellmax and the minimum cell voltage Vcellmin, which can be determined as a variation in the state of charge among a plurality of battery cells, varies depending on the theoretical value Vcell_t of the cell voltage. For example, the larger the theoretical value Vcell_t of the cell voltage, the larger the magnitude of the difference, which can be determined as a variation. Therefore, by using the ratio Rd, it is possible to further improve the accuracy of determining whether or not cell balancing should be performed.

[0107] The ratio threshold Rdth is set to 0.3% or more and 2.0% or less. When the ratio threshold Rdth is 0.3% or more, renewable energy can be effectively used. When the ratio threshold Rdth is 2.0% or less, the possibility of the function of the battery cells being impaired can be reduced. As a result, cell balancing can be performed while effectively using renewable energy without impairing the function of any battery cell. Therefore, it is possible to further suppress the decrease in the effective storage capacity of the storage battery 71.

[0108] The determination unit 12 determines whether or not the implementation condition is satisfied based on the total WL_total of the load power WL consumed by all the load devices L per day and the total Ws_total of the system power Ws supplied by the auxiliary power supply 5 to the DC bus 2 per day. When the power Wc that can be supplied from the storage battery 71 is insufficient for the load power WL, the system power Ws is supplied from the auxiliary power supply 5. Therefore, a value obtained by subtracting the total Ws_total from the total WL_total can be estimated as the effective storage capacity of the storage battery 71. It is considered that the smaller the effective storage capacity is, the greater the variation in the state of charge among the multiple battery cells. Therefore, by considering the total WL_total and the total Ws_total, it is possible to improve the accuracy of determining whether or not cell balancing should be performed.

[0109] Specifically, the determination unit 12 determines that the implementation condition is satisfied when the storage capacity rate Rc is smaller than the capacity rate threshold value Rcth. The storage capacity rate Rc is obtained by dividing the moving average value of the value obtained by subtracting the total power Wc per day Ws_total from the total load power WL (power consumption) per day WL_total by the theoretical value Cmod. Since the power consumption, etc. may vary from day to day, the influence of the fluctuation can be reduced by using the moving average value of the value obtained by subtracting the total Ws_total from the total WL_total. Furthermore, the magnitude of the effective storage capacity at which it is possible to determine that the charge state variation occurs among the multiple battery cells varies depending on the theoretical value Cmod. For example, the larger the theoretical value Cmod, the larger the magnitude of the effective storage capacity at which it is possible to determine that the variation occurs. Therefore, by using the storage capacity rate Rc, it is possible to further improve the accuracy of determining whether or not cell balancing should be performed.

[0110] The capacity rate threshold Rcth is set to 65% or more and 90% or less. When the capacity rate threshold Rcth is 65% or more, the possibility of the battery cell function being impaired can be reduced. When the capacity rate threshold Rcth is 90% or less, renewable energy can be effectively utilized. As a result, cell balancing can be performed while effectively utilizing renewable energy without impairing the function of any battery cell. Therefore, it is possible to further suppress the decrease in the effective storage capacity of the storage battery 71.

[0111] The power management device and power supply system according to the present disclosure are not limited to the above-described embodiments.

[0112] Power management apparatus 10 may be configured as a single device that is physically or logically coupled, or may be configured as multiple devices that are physically or logically separated from each other. For example, power management apparatus 10 may be realized by multiple computers distributed over a network, such as in cloud computing.

[0113] At least one of the power conditioner 32, the AC / DC converter 52, the converter 6, and the bidirectional DC / DC converter 73 may not have a power measurement function. In this case, the power management device 10 may obtain the measurement value of each power from the measurement value of the voltage measured by the voltage sensor and the measurement value of the current measured by the current sensor.

[0114] The power supply device 3 may include another power generation device instead of the renewable energy power generation device 31.

[0115] The auxiliary power supply 5 may include a power generation device instead of the commercial power supply 51. An example of a power generation device is a diesel generator. In this case, the number of auxiliary power supplies 5 is not limited to one and can be changed appropriately as necessary. When the auxiliary power supply 5 does not include the commercial power supply 51, the power supply system 1 is also called an independent DC power supply system.

[0116] In the above embodiment, each of the power conditioner 32, the AC / DC converter 52, the converter 6, and the bidirectional DC / DC converter 73 operates on a DC voltage generated inside the device. Instead of this configuration, the power supply system 1 may include a power supply unit, and the power supply unit may generate a DC voltage having a constant voltage value from the bus voltage Vbus of the DC bus 2 or the commercial power supply 51, and supply the DC voltage (power) to each device.

[0117] In the above embodiment, the determination unit 12 determines that the implementation condition is satisfied when the ratio Rd of any of the storage batteries 71 is greater than the ratio threshold value Rdth or the storage capacity rate Rc is smaller than the capacity rate threshold value Rcth, but the method of determining whether the implementation condition is satisfied is not limited to this. For example, the determination unit 12 may determine that the implementation condition is satisfied when the ratio Rd of any of the storage batteries 71 is greater than the ratio threshold value Rdth and the storage capacity rate Rc is smaller than the capacity rate threshold value Rcth. The determination unit 12 may determine whether the implementation condition is satisfied using only one of the first determination and the second determination. The determination unit 12 may determine whether the implementation condition is satisfied using a determination other than the first determination and the second determination.

[0118] In the cell voltage equalization method shown in Fig. 5, step S12 may be omitted. In this case, the control unit 14 performs cell balancing implementation control in step S13 in response to receiving a determination result indicating that the implementation condition is satisfied from the determination unit 12. When the implementation condition is satisfied, the state of charge of the target storage battery 71 is not necessarily a fully charged state. Therefore, since there is no need to wait until the state of charge of the target storage battery 71 becomes a fully charged state, cell balancing can be implemented for the target storage battery 71 early. Therefore, a decrease in the effective storage capacity of the storage battery 71 can be eliminated early.

[0119] Similarly, in the cell voltage equalization method shown in Fig. 6, step S22 may be omitted. In this case, the control unit 14 performs cell balancing implementation control in step S23 in response to receiving a determination result indicating that the implementation condition is satisfied from the determination unit 12. When the implementation condition is satisfied, the state of charge of the target storage battery 71 is not necessarily a fully discharged state. Therefore, since there is no need to wait until the state of charge of the target storage battery 71 becomes a fully discharged state, cell balancing can be implemented for the target storage battery 71 early. Therefore, the decrease in the effective storage capacity of the storage battery 71 can be eliminated early.

[0120] In the cell balancing implementation control, the control unit 14 does not need to reduce the maximum current value of the current between the bidirectional DC / DC converter 73 and the target storage battery 71. In this case, in the cell balancing implementation control, the control unit 14 may continue the power supply of the renewable energy power generation device 31 without stopping it. In other words, the control unit 14 does not need to send a command to set the maximum current value to the bidirectional DC / DC converter 73, and does not need to send a stop command to the power conditioner 32. This configuration makes it possible to use renewable energy more effectively.

[0121] If sufficient power Wc can be supplied by a storage battery 71 other than the target storage battery 71, the control unit 14 does not need to cause the auxiliary power supply 5 to supply the system power Ws in the cell balancing implementation control. In other words, the control unit 14 does not need to send a startup command to the AC / DC converter 52. [Explanation of symbols]

[0122] 1...power supply system, 2...DC bus, 3...power supply unit, 5...auxiliary power supply unit, 6...converter (first converter), 10...power management unit, 12...judgment unit (first judgment unit), 13...judgment unit (second judgment unit), 14...control unit, 31...renewable energy power generation device (power generation device), 71...storage battery, 72...BMU (battery management unit), 73...bidirectional DC / DC converter (converter, second converter), L...load equipment, Vbat...battery voltage, Vbus...bus voltage, VL...load voltage, Wre...generated power, Ws...grid power (supplied power), WL...load power (power consumption).

Claims

1. a first determination unit that determines whether or not an implementation condition for performing cell balancing to equalize states of charge of a plurality of battery cells included in a storage battery connected to a DC bus via a converter is satisfied; a control unit that performs cell balancing implementation control to cause a battery management device that manages the storage battery to implement the cell balancing when the implementation condition is satisfied; Equipped with The control unit changes a target voltage of the converter in the cell balancing implementation control so that the state of charge of the storage battery becomes a state at which the battery management device starts the cell balancing.

2. The power management device according to claim 1 , wherein the control unit is configured to reduce a maximum current value of a current between the converter and the storage battery in the cell balancing implementation control.

3. The power management device according to claim 2 , wherein the control unit, in the cell balancing implementation control, stops power supply from a power generation device that supplies power to the DC bus.

4. 4. The power management device according to claim 1, wherein the control unit causes an auxiliary power supply device that supplies power to the DC bus to supply power during the cell balancing implementation control.

5. A second determination unit that determines whether or not the charging state of the storage battery has reached a predetermined state, 5. The power management device according to claim 1, wherein the control unit performs the cell balancing implementation control when the implementation condition is satisfied and the charging state becomes the predetermined state.

6. The second determination unit determines whether the state of charge of the storage battery has reached a fully charged state, The power management device according to claim 5 , wherein the control unit reduces the target voltage in the cell balancing implementation control.

7. The second determination unit determines whether the state of charge of the storage battery has reached a fully discharged state, The power management device according to claim 5 , wherein the control unit increases the target voltage in the cell balancing implementation control.

8. The power management device according to any one of claims 1 to 7, wherein the first determination unit determines whether the implementation condition is satisfied based on a maximum cell voltage and a minimum cell voltage among the cell voltages of the plurality of battery cells.

9. 9. The power management device according to claim 8, wherein the first determination unit determines that the implementation condition is satisfied when a ratio obtained by dividing the difference between the maximum cell voltage and the minimum cell voltage by the theoretical value of the cell voltage is greater than a preset ratio threshold value.

10. The power management apparatus of claim 9 , wherein the ratio threshold is equal to or greater than 0.3% and equal to or less than 2.0%.

11. A power management device as described in any one of claims 1 to 10, wherein the first judgment unit judges whether the implementation condition is satisfied based on the total amount of power consumed per day by load equipment receiving power from the DC bus and the total amount of power supplied per day to the DC bus by an auxiliary power supply device that supplies power to the DC bus.

12. The power management device according to claim 11, wherein the first determination unit determines that the implementation condition is satisfied when a storage capacity rate obtained by dividing a moving average value of a value obtained by subtracting the total supply power from the total power consumption by a theoretical value of the storage capacity of the storage battery is smaller than a predetermined capacity rate threshold value.

13. The power management apparatus of claim 12 , wherein the capacity rate threshold is equal to or greater than 65% and equal to or less than 90%.

14. a DC bus for supplying DC power; a power supply unit including a generator for supplying power to the DC bus; an auxiliary power unit providing power to the DC bus; a first converter connected to the DC bus and configured to convert a bus voltage supplied to the DC bus into a load voltage supplied to a load device; A storage battery including a plurality of battery cells; A battery management device that manages the storage battery; a second converter provided between the storage battery and the DC bus and capable of bidirectionally converting a bus voltage and a battery voltage of the storage battery; a power management device that charges and discharges the storage battery by controlling the second converter; Equipped with The power management device includes: determining whether or not a condition for performing cell balancing to equalize the states of charge of the plurality of battery cells is satisfied; and when the implementation condition is satisfied, the target voltage of the second converter is changed so that the state of charge of the storage battery becomes a state at which the battery management device starts the cell balancing.

Citation Information

Patent Citations

  • Storage battery charger

    JP2013031317A

  • Cell balance device for power storage device

    JP2015223058A

  • Power storage system

    JP2017085852A

  • Direct current power supply system

    WO2012057032A1

  • Storage battery management apparatus, method, and program

    WO2016147306A1