Road joint undrained structure
The road joint non-drainage structure with a water-repellent aggregate layer and foam backup layers addresses water leakage and construction challenges by effectively preventing water ingress and maintaining water repellency.
Patent Information
- Application Number
- JP2021129962
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-08-06
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2041-08-06
AI Technical Summary
Conventional road joint non-drainage structures face issues with water leakage due to the slipping of binding materials and difficulty in construction, especially when the joint body expands and contracts with vehicle traffic and temperature changes.
A road joint non-drainage structure featuring a water-repellent aggregate layer sealed by foam backup layers and a waterproof sealing material, which prevents water ingress and is easy to construct.
The structure effectively suppresses water leakage and is easily constructed by using a water-repellent aggregate layer sealed from above and below with foam, maintaining water repellency and preventing water entry into the substructure.
Smart Images

Figure 0007588565000004 
Figure 0007588565000001 
Figure 0007588565000002
Abstract
Description
[Technical field]
[0001] The present invention relates to a road joint undrained structure that absorbs expansion and contraction displacement of a deck on which a road is provided. [Background technology]
[0002] The road joint body, which absorbs the expansion and contraction displacement of the deck on which the road is installed, has a problem that water leakage from the road joint body may cause damage such as rust corrosion, frost damage, and salt damage to the substructure of the deck. In response to this, non-drained road joint structures that are non-drained to prevent water leakage are beginning to appear. As a road joint non-drained structure, the following Patent Document 1 discloses a road joint non-drained structure in which a joint material made of a mixture of aggregate and an elastic binder that has elasticity after hardening is filled in a recess formed along the gap between the decks of the road joint body. In addition, the following Patent Document 2 discloses a road joint non-drained structure in which a rubber concrete made of a low-hardness rubber material that hardens at room temperature and aggregate is filled in the gap between the decks of the road joint body. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2014-240575 A [Patent Document 2] JP 2015-067982 A Summary of the Invention [Problem to be solved by the invention]
[0004] The road joint body expands and contracts repeatedly due to vibrations caused by vehicle traffic and temperature changes. Conventional road joint undrained structures use elastic binders or rubber materials as bonding materials, so there was a problem that the bonding material gradually peels off from the joint surface (butt surface) of the deck slabs of the road joint body due to expansion and contraction of the road joint body, and water may leak from the peeled part. In addition, conventional road joint undrained structures have the problem that they cannot be easily constructed because they are constructed by filling the gaps between the deck slabs with a bonding material made of a mixture of binder and aggregate.
[0005] The problem that the technology of this specification aims to solve has been made in consideration of the above-mentioned points, and has an object to provide a road joint undrained structure that can be easily constructed and suppresses water leakage. [Means for solving the problem]
[0006] The road joint undrained structure according to the embodiment of the present specification is a road joint undrained structure formed in a road joint body that joins adjacent deck slabs, The structure is characterized by comprising a water-repellent aggregate layer in which water-repellent aggregate with a water-repellent surface is enclosed in the gap between the adjacent deck slabs, and a backup material layer made of foam that seals the water-repellent aggregate layer from above and below.
[0007] According to the road joint undrained structure according to the embodiment of the present specification, a water-repellent aggregate layer is formed in the gap between the deck slabs, so that rainwater that seeps in from above the gap is repelled by the water-repellent aggregate layer, and water leakage to the substructure of the deck slab can be suppressed. In addition, the water-repellent aggregate is sealed from above and below with a backup material layer made of foam, so that the road joint undrained structure according to the embodiment can be easily constructed.
[0008] Here, in the above-mentioned road joint undrained structure, the water-repellent aggregate may have a water contact angle of 90° or more.
[0009] According to this, rainwater seeping in from above the gap is repelled by the water-repellent aggregate layer, thereby making it possible to suppress water leakage from the road joint undrained structure.
[0010] In the above-mentioned road joint undrained structure, the water-repellent aggregate may have an average particle size (median size D50) of 50 to 500 μm.
[0011] This allows the water-repellent aggregate to be packed densely and blocks the gaps through which rainwater can flow in the water-repellent aggregate layer, thereby further suppressing water leakage from the road joint undrained structure.
[0012] In addition, the above road joint undrained structure may be configured to have a waterproof sealant layer on the upper backup material layer.
[0013] According to this, the waterproof sealant layer prevents rainwater from penetrating into the water-repellent aggregate layer, thereby further suppressing water leakage from the road joint undrained structure. Effect of the Invention
[0014] According to the embodiment of the road joint undrained structure, construction can be easily performed and water leakage can be suppressed. [Brief description of the drawings]
[0015] [Figure 1] FIG. 2 is a cross-sectional view of the road joint undrained structure of the embodiment in the running direction of the road. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] Hereinafter, a road joint undrained structure according to an embodiment of the present specification will be described based on FIG. 1. The scope of the present invention is not limited to the scope disclosed in the embodiment. The road joint undrained structure 1 according to the embodiment includes a water-repellent aggregate layer 11 in which water-repellent aggregate 111 with a water-repellent surface is enclosed in a gap 22 between adjacent deck slabs 21, backup material layers 12 and 13 made of foam that seal the water-repellent aggregate layer 11 from above and below, and a waterproof seal material layer 14 provided on the upper backup material layer 13. The road joint undrained structure 1 absorbs the expansion and contraction displacement of the deck slab 21 on which the road R is provided, and suppresses water leakage to the substructure (not shown) of the deck slab 21.
[0017] The meanings of the terms in this specification are as follows. "Average particle size" means the median diameter (D50) obtained by the JIS standard sieve (JIS Z 8801-1:2019). In this specification, the up and down directions of the road joint undrained structure 1 refer to the up and down directions when the structure is installed on a substructure such as an abutment or pier, and the left and right directions refer to one side of the road R traveling direction as left and the other side as right. As used in the drawings, U indicates up, D indicates down, L indicates left, and R indicates right.
[0018] The water-repellent aggregate 111 is an aggregate whose surface has been treated to be water-repellent. The water-repellent treatment was performed by applying a water-repellent agent to the aggregate, coating it with the water-repellent agent, and forming a water-repellent agent layer. The water-repellent aggregate 111 is filled into the gaps 22 of the deck 21 (road R) on which the road joint undrained structure 1 is formed, thereby forming the water-repellent aggregate layer 11. Since the water-repellent aggregate layer 11 is a layer filled with the water-repellent aggregate 111, the water-repellent aggregate 111 can flow and follow the movement of the road joint body, such as expansion and contraction, and therefore there is little risk of losing water repellency. In addition, since the water-repellent aggregate layer 11 does not contain a binder such as a synthetic resin, there is little risk of losing water resistance due to resin deterioration.
[0019] The water contact angle of the water repellent aggregate 111 in the embodiment can be 90° or more. This is because the water repellent aggregate layer 11 formed from the water repellent aggregate 111 repels water and can suppress water leakage. In another embodiment, the water contact angle of the water repellent aggregate 111 can be 105° or more, and in yet another embodiment, the water contact angle can be 120° or more.
[0020] In an embodiment, the aggregate that is the base of the water-repellent aggregate 111 can be silica sand, kansui sand, feldspar, pyroxene, glass beads, or a mixture of these. In another embodiment, silica sand and kansui sand, which are widely distributed and easily available, can be used. In yet another embodiment, silica sand, which has high hardness, can be used.
[0021] The average particle diameter (median diameter D50) of the aggregate (water-repellent aggregate 111) in the embodiment is 50 to 500 μm. This is because the water-repellent aggregate 111 in the water-repellent aggregate layer 11 of the road joint undrained structure 1 is densely packed, the gaps in the water-repellent aggregate layer 11 through which rainwater flows are blocked, and water leakage from the road joint undrained structure 1 can be further suppressed. If the average particle diameter of the aggregate is less than 50 μm, there is a risk that fine particles will fly in the air when filling the road joint undrained structure 1. On the other hand, if it exceeds 500 μm, the water-repellent aggregate 111 cannot be densely packed in the water-repellent aggregate layer 11, and there is a risk that gaps through which rainwater flows will be generated in the water-repellent aggregate layer 11. In another embodiment, the average particle diameter of the aggregate can be 100 to 300 μm, and in yet another embodiment, 180 to 250 μm.
[0022] The water repellent may be an aqueous water repellent (aqueous emulsion type), a silane water repellent (silane compound), etc. Examples of the aqueous water repellent include DOWSIL Dry Seal S (manufactured by Dow Chemical Japan Co., Ltd.), WACKER HC 303 (manufactured by Asahi Kasei Wacker Silicone Co., Ltd.), Surfa Pore C (manufactured by Nanophos Japan (GLI Co., Ltd.)), AG-E061 (manufactured by AGC Co., Ltd.), and POLON-MK-206 (manufactured by Shin-Etsu Chemical Co., Ltd.). Examples of silane water repellents that can be used include methyltrimethoxysilane, dimethyldimethoxysilane, phenyltrimethoxysilane, dimethoxydiphenylsilane, tetraethoxysilane, methyltriethoxysilane, dimethyldiethoxysilane, phenyltriethoxysilane, n-propyltrimethoxysilane, n-propyltriethoxysilane, hexyltrimethoxysilane, hexyltriethoxysilane, octyltriethoxysilane, decyltrimethoxysilane, 1,6-bis(trimethoxysilyl)hexane, and 3,3,3-trifluoropropyltrimethoxysilane.
[0023] The water repellent agent can also be applied to the butt surfaces 211 of the deck slabs 21 on which the road joint undrained structure 1 is formed. By applying the water repellent agent to the butt surfaces 211, damage such as rust and corrosion of the butt surfaces 211 can be prevented, and the butt surfaces 211 have water repellency, so that leakage of water along the surfaces of the butt surfaces 211 can be prevented.
[0024] The back-up material is a material that seals the water-repellent aggregate layer 11 from above and below to form the back-up material layers 12 and 13, and is made of a resin foam. The back-up material has an apparent density of 20 to 500 kg / m 3 The back-up material can be used with an apparent density of 20 kg / m because it can suitably seal the water-repellent aggregate layer 11. 3 If the apparent density of the back-up material is less than 500 kg / m, the strength of the back-up material is weak and there is a risk that the back-up material cannot sufficiently seal the water-repellent aggregate layer 11. On the other hand, if the apparent density of the back-up material is less than 500 kg / m 3If it exceeds this range, the strength will be excessive and it may be uneconomical. In another embodiment, the apparent density of the backup material is 25 to 200 kg / m 3 In yet another embodiment, 33 to 100 kg / m 3 The foam material forming the backup material can be any common resin foam made of polyurethane, polystyrene, polyphenol, or the like.
[0025] The waterproof sealant layer 14 is provided on the upper backup material layer 13, and is a material that directly receives rainwater falling on the road joint undrained structure 1 and prevents the rainwater from flowing into the road joint undrained structure 1. Materials that can be used to form the waterproof sealant layer 14 include sealing materials such as silicone, asphalt, polybutadiene (polybutadiene-based elastic sealant), and the like.
[0026] Next, a construction method of the road joint undrained structure 1 according to the embodiment of the present specification will be described. The construction method of the road joint undrained structure 1 is a method of constructing the road joint undrained structure 1 in the gap 22 between adjacent deck slabs 21, and is composed of a water repellent application process of applying a water repellent to the butt surface 211 of the deck slabs 21 forming the gap 22, a lower backup material layer 12 installation process of installing the lower backup material layer 12 that seals the lower side of the water repellent aggregate layer 11, a water repellent aggregate layer 11 formation process of spreading the water repellent aggregate 111 on the upper side of the lower backup material layer 12, an upper backup material layer 13 installation process of installing the upper backup material layer 13 that seals the upper side of the water repellent aggregate layer 11 on the upper side of the water repellent aggregate layer 11, and a waterproof seal process of providing a waterproof seal material layer 14 on the upper side of the upper backup material layer 13.
[0027] When an elastic sealant layer 16 is provided below the lower back-up material layer 12 to further improve waterproofing, an elastic seal filling step of filling the elastic seal that forms the elastic sealant layer 16 can be included before the step of installing the lower back-up material layer 12. A commercially available elastic seal for road joint undrained structures (elastic seal for undrained steel expansion joints) can be used as the elastic seal, and the construction method follows that of the commercially available product.
[0028] The water repellent application process is a process of applying the water repellent to the butt surfaces 211 of the deck slabs 21 that form the gaps 22 where the road joint undrained structure 1 is formed. The water repellent may be the same as or different from the water repellent applied to the aggregate. By applying the water repellent to the butt surfaces 211 of the deck slabs 21, the butt surfaces 211 become water repellent, and water leakage along the surfaces of the butt surfaces 211 can be prevented. The water repellent can be applied by a general-purpose applicator such as a brush, spray, or roller. The application amount is 20 to 200 g / m in the case of a water-based water repellent. 2 In the case of silane water repellent, the coating thickness is 10 to 100 g / m 2 It can be said that:
[0029] The lower back-up material layer 12 installation process is a process of installing the lower back-up material layer 12 in the gap 22 between adjacent deck slabs 21. The back-up material forming the lower back-up material layer 12 is made of a foam, so it can be installed by shrinking it through compression deformation, loading it into the gap 22, and expanding it at the installation position within the gap 22. For this reason, by preparing a back-up material with a width that is 10 to 50% longer than the left-right width of the gap 22, it is possible to minimize the gap between the back-up material and the abutting surface 211. If a gap occurs between the back-up material and the abutting surface 211, the gap can be filled with a sealant such as silicone.
[0030] The water-repellent aggregate layer 11 forming process is a process of spreading the water-repellent aggregate 111 evenly on the upper side of the lower backup material layer 12. The thickness of the spread water-repellent aggregate 111 is 10 to 50 mm. This is because the water repellency of the road joint non-drained structure 1 can be favorably maintained. If the thickness of the water-repellent aggregate 111 is less than 10 mm, the water-repellent aggregate 111 may be biased due to repeated expansion and contraction of the road joint body, and the water repellency of the road joint non-drained structure 1 may not be maintained. On the other hand, if the thickness of the water-repellent aggregate 111 exceeds 50 mm, although the water repellency of the road joint non-drained structure 1 can be favorably maintained, the thickness may be excessive, which may be uneconomical. In another embodiment, the thickness of the spread water-repellent aggregate 111 may be 15 to 40 mm, and in yet another embodiment, 20 to 30 mm.
[0031] The upper back-up material layer 13 installation process is a process of installing the upper back-up material layer 13 from above the evenly spread water-repellent aggregate 111 (water-repellent aggregate layer 11) so as to cover the water-repellent aggregate 111. As with the lower back-up material layer 12, a back-up material layer 13 having a width 10 to 50% longer than the front-to-back width of the gap 22 is prepared, shrunk, and inserted into the gap 22, and then expanded at the installation position, thereby minimizing the gap between the back-up material and the butting surface 211. If a gap occurs between the back-up material and the butting surface 211, the gap can be filled with a sealant such as silicone.
[0032] The waterproof sealing process is a process in which a waterproof sealant is injected onto the upper side of the upper backup material layer 13 to form a waterproof sealant layer 14. The waterproof sealant layer 14 can be formed by filling with a caulking gun or a putty spatula. By forming the waterproof sealant layer 14 on the upper side of the upper backup material layer 13, the upper backup material layer 13 is fixed to the road joint undrained structure 1 in an expandable manner, and water leakage from the road joint undrained structure 1 can be suppressed.
[0033] In the road joint non-drainage structure 1 thus formed, the waterproof sealant layer 14 prevents rainwater from entering the water-repellent aggregate layer 11. When rainwater enters from above the gap 22, the rainwater is repelled by the water-repellent aggregate layer 11, and water leakage to the substructure of the deck can be suppressed. The water-repellent aggregate layer 11 filled with the water-repellent aggregate 11 is unlikely to lose its water repellency because the water-repellent aggregate 111 flows and the water-repellent aggregate layer 11 can follow the movement of the road joint body such as expansion and contraction. In addition, since the water-repellent aggregate layer 11 does not contain a binder such as synthetic resin, there is little risk of losing water resistance due to resin deterioration. In addition, since a water-repellent agent is applied to the butt surfaces 211 of the deck slabs 21, the butt surfaces 211 have water repellency, and water leakage along the surfaces of the butt surfaces 211 can be prevented. Furthermore, since the water-repellent aggregate layer 11 is formed by sealing the water-repellent aggregate 111 from above and below with backup material layers 12 and 13 made of foam, the road joint undrained structure 1 of the embodiment can be easily constructed. EXAMPLES
[0034] The present invention will be described in more detail below with reference to examples. The water-repellent aggregate 111 used in the road joint undrained structure 1 of the embodiment was prepared with different types of aggregate and water-repellent agent, and each was evaluated (tested). Examples of the water-repellent aggregate 111 are shown in Table 1, and the particle size distribution of the aggregate used is shown in Table 2. The water-repellent aggregate 111 was obtained by putting the aggregate and the water-repellent agent in the ratio shown in Table 1 into a mortar mixing bowl (JIS R 5201), stirring with a mortar mixing spoon (JIS R 5201), and then drying in the sun. The evaluation (test) method of the water-repellent aggregate 111 will be described below.
[0035] Water contact angle The water contact angle was measured using a test specimen other than the water-repellent aggregate 111 of the embodiment. A water-repellent agent was applied to a glass plate representing aggregate (quartz sand), and the water contact angle of the glass plate to which the water-repellent agent was applied was measured as the water contact angle of the water-repellent aggregate 111.
[0036] Water repellency 1 Water repellency 1 was evaluated by spreading water-repellent aggregate 111 to a height of 2.5 cm at the bottom of a glass beaker, adding water to a height of 2.5 cm above the water-repellent aggregate 111 (5 cm from the bottom of the glass beaker), and then evaluating the condition. The test results were evaluated as follows: ○: when water did not reach the bottom of the glass beaker, △: when water did not reach the bottom of the glass beaker immediately after adding water but reached the bottom of the glass beaker one day later, ×: when water reached the bottom of the glass beaker halfway through adding water.
[0037] Water repellency 2 For water repellency 2, road joint non-drained structures 1 with different water repellent aggregates 111 were constructed in the gaps 22 between adjacent deck slabs 21, and the condition was evaluated for one year. The test results were evaluated as follows: no water leakage from the road joint non-drained structures 1 and no traces of water getting into the substructure of the deck slab 21, marked O; and traces of water getting into the substructure of the deck slab 21, marked X. The configuration of the road joint non-drained structures 1 for water repellency 2 is shown in Table 3.
[0038] Fillability The filling property was evaluated by the filling property of the water-repellent aggregate 111 into the gap 22 of the deck 21 of the road R during construction of the water-repellent 2. The test results were evaluated as follows: ◯: it was possible to fill without difficulty; △: it was possible to fill but the fine water-repellent aggregate 111 flew around, which was not preferable in terms of the working environment; ×: it was difficult to fill because the water-repellent aggregate 111 did not roll well.
[0039] [Table 1]
[0040] [Table 2]
[0041] [Table 3]
[0042] Example 1 Example 1 is an example in which No. 8 silica sand is used as aggregate, and a water-repellent aggregate 111 using a silane water repellent agent is used. The water contact angle of the water-repellent aggregate 111 of Example 1 is 135°. The water-repellent aggregate 111 of Example 1 was confirmed to have good water repellency in a glass beaker (water repellency 1), with no water reaching the bottom of the glass beaker, and confirmed to have good water repellency in a road joint non-drained structure 1 (water repellency 2), with no water leakage from the road joint non-drained structure 1, and no traces of water repellency were observed on the lower structure of the deck 21. In addition, the filling property of the water-repellent aggregate 111 of Example 1 was good, with fine water-repellent aggregate 111 flying around the surroundings when filling the gap 22, although it could be filled.
[0043] Example 2 Example 2 is an example using No. 7 silica sand as aggregate and water-repellent aggregate 111 using a water-based water repellent agent. The water contact angle of the water-repellent aggregate 111 of Example 2 is 135°. The water-repellent aggregate 111 of Example 2 was confirmed to have good water repellency in a glass beaker (water repellency 1), with no water reaching the bottom of the glass beaker, and confirmed to have good water repellency in a road joint non-drained structure 1 (water repellency 2), with no water leakage from the road joint non-drained structure 1, and no traces of water having flowed into the lower structure of the deck 21. In addition, the filling property of the water-repellent aggregate 111 of Example 2 was such that it could be easily filled into the gap 22. Example 2 is the best mode example.
[0044] Example 3 Example 3 is an example in which No. 6 silica sand is used as the aggregate, and water-repellent aggregate 111 using a silane water repellent agent is used. The water contact angle of the water-repellent aggregate 111 of Example 3 is 135°. The water-repellent aggregate 111 of Example 3 showed good results in terms of water repellency 1, water repellency 2, and filling property.
[0045] Example 4 Example 4 is an example in which No. 5 silica sand is used as aggregate, and a water-repellent aggregate 111 using a water-based water repellent agent is used. The water contact angle of the water-repellent aggregate 111 of Example 4 is 135°. In the water-repellent confirmation (water repellency 1) of the water-repellent aggregate 111 of Example 4 in a glass beaker, the water did not reach the bottom of the glass beaker immediately after adding water, but after one day, the water reached the bottom of the glass beaker. However, in the water-repellent confirmation (water repellency 2) in the road joint non-drainage structure 1, there was no water leakage from the road joint non-drainage structure 1, and no trace of water reaching the lower structure of the deck 21 was observed, which was good. In addition, the filling property of the water-repellent aggregate 111 of Example 4 was such that it could be filled into the joint gap 22 without difficulty. [Explanation of symbols]
[0046] 1...road joint undrained structure, 11...water-repellent aggregate layer, 12...backup material layer, 13...backup material layer, 14...waterproof sealant layer, 16...elastic sealant layer, 21...deck slab, 22...gap, 111...water-repellent aggregate, 211...butt surface, R...road.
Claims
1. A road joint undrained structure formed in a road joint body that joins adjacent deck slabs, This non-drained structure is characterized by having a water-repellent aggregate layer in which water-repellent aggregate with a water-repellent surface is enclosed in the gap between adjacent deck slabs, and a backup material layer made of foam that seals the water-repellent aggregate layer from above and below.
2. 2. The non-drained structure according to claim 1, wherein the water-repellent aggregate has a contact angle of water of 90° or more.
3. The non-drainage structure according to claim 1, characterized in that the average particle diameter (median diameter D50) of the water-repellent aggregate is 50 to 500 μm.
4. 2. The undrained structure of claim 1, further comprising a waterproof sealant layer on the upper back-up material layer.
Citation Information
Patent Citations
JP1974122127A
Asphalt material and asphalt pavement body
JP2005325536A
Water cut-off structure and construction method thereof
JP2014055422A
Embedment type joint part structure for bridge and construction method therefor
JP2014240575A
Rubber concrete for road bridge and construction method therefor, and expansion device using rubber concrete for road bridge
JP2015067982A