Display system, and display program

The display system and program enhance the utility of process charts in construction by associating and displaying additional information, enabling effective management and comparison of construction processes through standard and performance data integration.

JP7712810B2Active Publication Date: 2025-07-24TAKENAKA CORP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
JP2021122086
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-07-27
Publication Date
2025-07-24
Estimated Expiration
2041-07-27

AI Technical Summary

Technical Problem

Existing techniques for displaying process charts in construction work lack the ability to effectively utilize additional information, such as standard and performance data, which hinders effective management and comparison of construction processes.

Method used

A display system and program that associate and display additional information, including standard and performance data, with each process in a construction schedule, utilizing a first storage unit for process identification, a second storage unit for additional information identification, and a management unit to display this information alongside the process chart.

Benefits of technology

Enables effective utilization of process schedules by allowing for the confirmation and comparison of standard and performance data, facilitating better management and utilization of construction work.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007712810000001
    Figure 0007712810000001
  • Figure 0007712810000002
    Figure 0007712810000002
  • Figure 0007712810000003
    Figure 0007712810000003
Patent Text Reader

Abstract

To provide a display system and a display program capable of making a construction schedule more useful.SOLUTION: An information processing system 100 for associating additional information with each step in a construction schedule of a construction and displaying it includes first storage means for storing construction specific information being information showing the construction schedule, second storage means for storing information for additional information specification to specify additional information on the basis of the construction specific information stored in the first storage means, a specification part 231 for specifying additional information on the basis of the construction specific information of the first storage means and the information for additional information specification of the second storage means, and a management part 232 for displaying the additional information specified by the specification part 231 in association with the constitution schedule.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a display system and a display program.

Background Art

[0002] Conventionally, a technique for displaying a process chart showing the processes of construction work has been known (see, for example, Patent Document 1).

Prior Art Documents

Patent Documents

[0003]

Patent Document 1

Summary of the Invention

Problems to be Solved by the Invention

[0004] By the way, a technique for effectively utilizing a process chart has been demanded.

[0005] The present invention has been made in view of the above facts, and an object thereof is to provide a display system and a display program capable of making a process chart more useful.

Means for Solving the Problems

[0006] In order to solve the above-described problems and achieve the object, the display system according to claim 1 is a display system that displays additional information in association with each process in a process chart of construction work, and includes a first storage unit that stores process identification information, which is information indicating each process; a second storage unit that stores additional information identification information for identifying the additional information based on the process identification information stored in the first storage unit; an identification unit that identifies the additional information based on the process identification information of the first storage unit and the additional information identification information of the second storage unit; and a management unit that displays the additional information identified by the identification unit in association with each process of the process chart. That is, the specifying means specifies, as the additional information, the standard additional information regarding the standard of the construction work and the performance additional information regarding the performance of the construction work for each of the steps in the process table, and the management means combines the standard additional information specified by the specifying means and the information indicating that it is the standard additional information to form first information, and combines the performance additional information specified by the specifying means and the information indicating that it is the performance additional information to form second information, and displays the first information and the second information.

[0007] The display system according to claim 2 is the display system according to claim 1, wherein The management means further includes third storage means for storing the additional information specified by the specifying means, and the management means displays the additional information stored in the third storage means in association with each of the steps in the process table.

[0008] The display system according to claim 3 is the display system according to claim 1 or 2, wherein the specifying means specifies specifiable information which is information specifiable by the process specifying information, and then specifies the additional information based on the specifiable information.

[0009] The display system according to claim 4 is the display system according to claim 3, wherein the specifying means specifies, as the specifiable information, at least information indicating the job type in the construction work.

[0010] The display system according to claim 5 is the display system according to any one of claims 1 to 4, wherein the second storage means stores, as the additional information specifying information, accumulation-related information regarding the accumulation of the construction work, contract-related information regarding the contract for the construction work, or daily report-related information regarding a daily report which is a daily report on the work for the construction work.

[0011] The display system according to claim 6 is the display system according to any one of claims 1 to 5, wherein the management means displays information regarding quality records or safety records related to the work of each process in association with each of the processes in the process table in addition to the additional information.

[0012] The management program according to claim 7 is a display program that associates and displays additional information for each process in the construction process schedule, and causes a computer to function as a first storage means storing process identification information which is information indicating each of the processes, a second storage means storing additional information identification information for identifying the additional information based on the process identification information stored in the first storage means, a specifying means for specifying the additional information based on the process identification information of the first storage means and the additional information identification information of the second storage means, and a management means for displaying the additional information specified by the specifying means in association with each of the processes in the process schedule. That is, the specifying means specifies, as the additional information, the standard additional information regarding the standard of the construction work and the performance additional information regarding the performance of the construction work for each of the steps in the process table, and the management means combines the standard additional information specified by the specifying means and the information indicating that it is the standard additional information to form first information, and combines the performance additional information specified by the specifying means and the information indicating that it is the performance additional information to form second information, and displays the first information and the second information.

Advantages of the Invention

[0013] According to the display system described in claim 1 and the display program described in claim 7, by associating and displaying additional information with each process in the process schedule, for example, it is possible to confirm the additional information in the process schedule, so that the process schedule can be effectively utilized. In addition, by specifying the standard additional information regarding the standard of the construction work and the performance additional information regarding the performance of the construction work, for example, it is possible to compare and consider the standard and performance of the construction work, and it is possible to utilize the result of the comparison and consideration in subsequent construction work.

[0015] According to the display system described in claim 3, by specifying the specifiable information and then specifying the additional information based on the specifiable information, for example, it is possible to appropriately specify the additional information.

[0016] According to the display system described in claim 4, by specifying information indicating the job types in the construction as the specifiable information, for example, it is possible to appropriately specify the additional information in consideration of the job types.

[0017] According to the display system described in claim 5, since the accumulation-related information, contract-related information, or daily report-related information is stored as the additional information identification information, for example, it is possible to appropriately specify the additional information using these information.

[0018] According to the display system described in claim 6, by associating and displaying information related to quality records or safety records regarding the operations of a process with each process in the process table, for example, it is possible to check the information related to quality records or safety records in the process table, thus enabling effective utilization of the process table.

Brief Description of the Drawings

[0019]

Figure 1

Figure 2

Figure 3

Figure 4

Figure 5

Figure 6

Figure 7

Figure 8

Figure 9

Figure 10

Figure 11

Figure 12

Figure 13

Figure 14

Modes for Carrying Out the Invention

[0020] Hereinafter, with reference to the accompanying drawings, embodiments of the display system and the display program according to this invention will be described in detail.

[0021] 〔I〕Basic Concept of the Embodiment First, the basic concept of the embodiment will be described. The embodiment relates to a display system and a display program. The display system according to the present invention is a system that associates and displays additional information for each process in a construction schedule.

[0022] "Process" is a concept indicating the stage when the construction work of a building is divided into multiple stages. "Schedule" is a concept including a diagram showing each process of the construction work based on time (including date).

[0023] "Additional information" is information related to each process added to each process, and is a concept including, for example, reference additional information and actual performance additional information, and as an example, is a concept including quantity information, man-hour information, cost information, etc.

[0024] "Reference additional information" is additional information related to the construction standard, and is, for example, information related to each process in the schedule, and as an example, is a concept including information expected in the construction, information serving as a standard in the construction, information serving as a goal in the construction, etc.

[0025] "Actual performance additional information" is additional information related to the actual performance of the construction, and is a concept including, for example, information on the actual performance of the construction.

[0026] "Quantity information" is information indicating the amount of work performed in the construction process, and is, for example, information indicating the quantity of materials and equipment targeted for the work (as an example, the amount of steel bars used in the work, etc.). "Man-hour information" is information indicating the man-hours of the work performed in the construction process. "Cost information" is information indicating the cost of the work performed in the construction process (for example, the cost of labor, the cost of materials and equipment, or the cost of materials and equipment and labor, etc.).

[0027] And in the following embodiments, the case of using the quantity information, man-hour information, and cost information expected in the construction of a building, and the man-hour information on the actual performance of the construction as "additional information" will be exemplified and described.

[0028] [II] Specific Content of Embodiment Next, the specific content of the embodiment will be described.

[0029] (Configuration) First, FIG. 1 is a block diagram conceptually showing the information processing system according to this embodiment. The information processing system 100 includes, for example, a terminal device 1 and a server device 2, and these devices can communicate with each other. In the information processing system 100, a plurality of terminal devices 1 carried by various users (for example, employees of the general contractor company, foremen of subcontractor companies, etc.) are included.

[0030] The "general contractor company" is a concept indicating a company that undertakes work directly from the orderer (i.e., the client), and the "subcontractor company" is a concept indicating a company that undertakes work from the general contractor company. Hereinafter, the "subcontractor company" will be appropriately referred to as the "cooperating company" for explanation.

[0031] (Configuration - Terminal Device) The terminal device 1 in FIG. 1 is a device carried by a user, for example, a tablet terminal or a smartphone. As an example, it includes a communication unit 11, a touch pad 12, a display 13, a recording unit 14, and a control unit 15.

[0032] The communication unit 11 is a communication means for communicating with external devices (for example, the server device 2). The touch pad 12 is an operation means for receiving various operation inputs from the user. The display 13 is an image display means for displaying various images. For example, the above touch pad 12 and the display 13 are integrally formed as a touch panel. The recording unit 14 is a recording means for recording programs and various data. The control unit 15 is a control means for controlling the terminal device 1, and is configured using internal memories such as a CPU, a RAM, and a ROM, for example.

[0033] (Configuration - Server Device) The server device 2 is the aforementioned display system, and includes, for example, a communication unit 21, a recording unit 22, and a control unit 23.

[0034] (Configuration - Server Device - Communication Unit) The communication unit 21 in FIG. 1 is a communication means for communicating with an external device (for example, the terminal device 1).

[0035] (Configuration - Server Device - Recording Unit) The recording unit 22 in FIG. 1 is a recording means for recording programs and various data necessary for the operation of the server device 2. This recording unit 22 includes, for example, a process identification information database 221 (hereinafter, the database is referred to as "DB") (the first storage means), a process table additional information DB 222, a process name - occupation type related information DB 223 (the second storage means), an accumulation related information DB 224 (the second storage means), a contract related information DB 225 (the second storage means), and a daily report related information DB 226 (the second storage means).

[0036] (Configuration - Server Device - Recording Unit - Process Identification Information DB) The process identification information database 221 in FIG. 1 is a storage means for storing process identification information.

[0037] FIG. 2 is a diagram illustrating process identification information, and FIG. 3 is a diagram illustrating a process table. In this embodiment, the case of processing the process table in FIG. 3 will be exemplified and described. "Process identification information" is information indicating a process table. Specifically, it is information indicating each process in the process table showing each process of the construction work. For example, it is a concept including information necessary for displaying each process of the process table shown in FIG. 3, etc. Also, the information of each item shown in FIG. 2 is mutually associated. Note that, from the perspective of the information already held by the process table, the process identification information may also be referred to as "already held information".

[0038] The process ID in FIG. 2 is identification information that uniquely identifies a process (hereinafter, the identification information is also referred to as "ID"). The process name information in FIG. 2 is information indicating the name of the process, and for example, information including the name of the work performed in the process or the name of the part to be worked on may be used. The start / end date information in FIG. 2 is information indicating the start date and end date of the process. The other process relationship information in FIG. 2 is information indicating the relationship with other processes, and for example, information indicating the previous process and the subsequent process, etc. The floor number information in FIG. 2 is information indicating the floor number of the object of the work performed in the process. The work area information in FIG. 2 is information indicating the work area of the object of the work performed in the process.

[0039] And in FIG. 2, for example, it is shown that the name of the process identified by "ID001" is "Beam reinforcement", and it is also shown that the start date and end date of the said process are "April 2nd" and "April 4th", and it is also shown that the previous process and the subsequent process of the said process are "Formwork" and "Stop frame·Step frame", and it is also shown that the floor number and the work area of the object of the work performed in the said process are "2nd floor" and "Area A".

[0040] Note that such process identification information is stored based on, for example, information from a process table management system (not shown) for managing the process table, or information input by an administrator who manages the process table.

[0041] (Configuration - Server device - Recording section - Process table additional information DB) The process table additional information DB222 in FIG. 1 is a storage means for storing process table additional information.

[0042] FIG. 4 is a diagram illustrating process table additional information. The "process table additional information" is information indicating additional information for each process, and for example, the information of each item shown in FIG. 4 is associated with each other.

[0043] The process ID in Fig. 4 is the same as the information with the same name in Fig. 2. The quantity information in Fig. 4 is information indicating the amount of work done in the construction process. Specifically, it is information indicating the quantity of materials and equipment used in the work done in the construction process. For example, it is reference additional information indicating the planned quantity in the construction. The man-hour information in Fig. 4 is information indicating the man-hours of the work done in the construction process. For example, it is reference additional information indicating the planned man-hours in the construction and actual additional information indicating the actual man-hours in the construction. The cost information in Fig. 4 is information indicating the cost of the work done in the construction process. For example, it is reference additional information indicating the planned cost of the work fee in the construction.

[0044] Note that in this embodiment, an example is shown in which only the man-hour information includes information regarding the plan and the actual situation, but other information may be configured to include information regarding the plan and the actual situation.

[0045] And in Fig. 4, for example, it is shown that the reference additional information of the quantity information added to the process identified by "ID001" is "10 tons", and the reference additional information of the man-hour information added to the said process is "7.5 man-days" and the actual additional information is "8 man-days", and the reference additional information of the cost information added to the said process is shown to be "400,000 yen".

[0046] Note that such process table additional information is stored, for example, by executing the process table display process described later.

[0047] (Configuration - Server Device - Recording Unit - Process Name and Occupation Type Related Information DB) The process name and occupation type related information DB223 in Fig. 1 is a storage means for storing process name and occupation type related information. The "process name and occupation type related information" is information for specifying the occupation type based on the process name. The "occupation type" is a concept indicating the type based on the work related to the construction, that is, a concept indicating the type of work, and can also be referred to as the "work type".

[0048] Regarding the "process name and job type related information", for example, the name of the work performed in the process and the name of the job type are associated with each other. For example, it includes information such as "the name of the work performed in the process" = "reinforcement placement" and "job type" = "rebar worker" being associated with each other. Note that such process name and job type related information is stored, for example, based on the information input by the administrator.

[0049] (Configuration - Server Device - Recording Unit - Accumulation Related Information DB) The accumulation related information DB224 in FIG. 1 is an accumulation related information storage means for storing accumulation related information. The "accumulation related information" is additional information specifying information used to specify additional information from process specific information (or optionally specifiable information). The "accumulation related information" is, for example, information specifiable by an accumulation statement used in a construction project, information specifiable by any function related to accumulation (as an example, an accumulation function implemented in a BIM (Building Information Modeling) system, etc.), or a concept including information on accumulation condensed in a quotation or a contract. However, in this embodiment, it will be described as information specifiable by an accumulation statement. The "accumulation related information" includes, for example, information indicating the planned usage location (i.e., floor, work area, part) and the planned usage quantity for "rebar", which is a capital equipment and materials for the "job type" = "rebar worker", and information on capital equipment and materials of other job types.

[0050] Note that such accumulation related information is stored based on the information input by the administrator or information obtained from other databases (the same applies to the contract related information and daily report related information described later).

[0051] Also, the "specifiable information" is information that can be specified based on process specific information (that is, information already possessed), and includes, for example, information indicating job type, cooperating company, and part.

[0052] (Configuration - Server Device - Recording Unit - Contract Related Information DB) The contract-related information DB225 in FIG. 1 is a contract-related information storage means for storing contract-related information. "Contract-related information" is additional information specifying information used to specify additional information from process-specific information (or optionally specifiable information). "Contract-related information" is a concept that includes information corresponding to information described in, for example, a contract between the client and the main contractor regarding construction, or a contract between the main contractor and a plurality of cooperating companies regarding construction. In this embodiment, the latter case will be described. "Contract-related information" includes, for example, information indicating the name of the cooperating company, job type, each work location (i.e., floor, work area), the agreed-upon rate (hereinafter also referred to as "contract rate"), the total quantity of the contracted work (i.e., the total work volume, that is, the total quantity of the capital equipment to be worked on) (hereinafter also referred to as "contract total quantity"), and the total amount of the contracted work cost (hereinafter also referred to as "contract total amount"). Note that the information indicating the work location may also include information indicating the part in addition to the floor and the work area.

[0053] (Configuration - Server Device - Recording Unit - Daily Report Related Information DB) The daily report-related information DB226 in FIG. 1 is a daily report-related information storage means for storing daily report-related information. "Daily report-related information" is additional information specifying information used to specify additional information from process-specific information (or optionally specifiable information). "Daily report-related information" is a concept that includes information corresponding to information described in a daily report indicating the work results by the cooperating company for the construction. "Daily report information" includes, for example, information indicating the date, the name of the cooperating company, job type, each work location (i.e., floor, work area, part), the number of workers, and the working hours.

[0054] (Configuration - Server Device - Control Unit) The control unit 23 in FIG. 1 is a control means for controlling the server device 2, and conceptually includes, for example, a specifying unit 231 and a management unit 232. The specifying unit 231 is a specifying means for specifying additional information based on the process specifying information of the first storage means and the information specifying information for additional information of the second storage means. The management unit 232 is a management means for associating and displaying the additional information specified by the specifying means with each process in the process table. Note that the processing performed by each part of this control unit 23 will be described later.

[0055] (Processing) Subsequently, the process table display process executed by the information processing system 100 according to the present embodiment will be described. FIG. 5 is a flowchart of the process table display process (in the following description of each process, steps are abbreviated as "S"). The process table display process is a process for displaying a process table, additional information, etc., and is, for example, a process executed by the server device 2.

[0056] This process table display process starts execution, for example, when the user performs an operation for displaying information via their terminal device 1, and will be described from the point where the process is started. Regarding SA1 to SA3 in FIG. 5, the process will be repeatedly executed for each process specified by the process specifying information in FIG. 2, but the process regarding the process of "ID001" will be described as a representative. That is, the case where the process of "ID001" is the processing target will be described.

[0057] ===SA1=== In SA1 of FIG. 5, the specifying unit 231 of the server device 2 executes quantity information storage processing. FIG. 6 is a flowchart of the quantity information storage processing, and FIG. 7 is a diagram showing a specific example of the quantity. The "quantity information storage processing" is a process for storing quantity information.

[0058] =SB1= In SB1 of FIG. 6, the specifying unit 231 of the server device 2 roughly specifies the job type corresponding to the process to be processed based on the process specifying information and the process name - job type related information. For example, in the process specifying information of FIG. 2, "beam reinforcement" associated with "ID001" is obtained, and based on the "beam reinforcement", "reinforcement" is specified as the name of the work performed in the process to be processed. Then, referring to the process name - job type related information stored in the process name - job type related information DB223 of FIG. 1, "steelworker" is specified as the job type associated with "reinforcement".

[0059] Note that as a method for specifying the job type, any other arbitrary method may be used. For example, when process name information is input, an algorithm for outputting information indicating the job type corresponding to the input process name information may be generated, and the specification may be performed based on the generated algorithm. Note that this algorithm may be generated using machine learning techniques.

[0060] =SB2= In SB2 of FIG. 6, the specifying unit 231 of the server device 2 roughly specifies the quantity based on the process specifying information, the information of the job type specified in SB1, and the integration - related information. For example, "beam reinforcement" associated with "ID001" in FIG. 2 is obtained, and based on the "beam reinforcement", "beam" is specified as the part to be worked on. Next, "2nd floor" and "Area A" associated with "ID001" in the process specifying information of FIG. 2 are specified. Next, referring to the integration - related information in the integration - related information DB224 of FIG. 1, as the information indicating the usage quantity associated with the job type "steelworker" specified in SB1, the part "beam", "2nd floor", and "Area A" specified above, for example, the planned quantity of "steel bars" as a capital equipment and materials is specified as "10 (tons)".

[0061] =SB3= In SB3 of FIG. 6, the specific part 231 of the server device 2 stores quantity information. For example, in the process table addition information of FIG. 4, "ID001" indicating the process to be processed is stored as the process ID, and "Scheduled: 10 tons" is stored based on "10 (tons)", which is the scheduled quantity specified by SB2, as the quantity information. Thus, the quantity information storage process returns.

[0062] ===SA2=== In SA2 of FIG. 5, the specific part 231 of the server device 2 executes a man-hour information storage process. FIG. 8 is a flowchart of the man-hour information storage process, and FIG. 9 is a diagram showing a specific example of man-hours. Note that FIG. 9(a) shows a specific example of the scheduled man-hours, and FIG. 9(b) shows a specific example of the actual man-hours. The "man-hour information storage process" is a process for storing man-hour information.

[0063] =SC1= In SC1 of FIG. 8, the specific part 231 of the server device 2 performs the same process as SB1 in FIG. 6 to identify the job type. For example, it identifies "rebar worker".

[0064] =SC2= In SC2 of FIG. 8, the specific part 231 of the server device 2 performs a process for identifying the scheduled man-hours and a process for identifying the actual man-hours.

[0065] <Process for identifying the scheduled man-hours> Regarding the process for identifying the scheduled man-hours, generally, the scheduled man-hours are identified based on the process identification information, the information on the job type identified by SC1, the contract-related information, and the quantity specified by SB2.

[0066] Specifically, for example, in the process identification information of FIG. 2, "2nd floor" and "Area A" associated with "ID001" are identified.

[0067] Next, identify the cooperating company responsible for the work in the process of "ID001". Note that this identification method is arbitrary. For example, it is assumed that information indicating the cooperating company responsible for the work is further associated with the process identification information in Figure 2, and it may be identified based on such information. Alternatively, it is assumed that information indicating the work location (i.e., floor number and work area) of the work in each process, the job type, and the cooperating company responsible for the work at the work location is stored, and based on such information, identify the cooperating company responsible for the work of "rebar worker" at the work location corresponding to "2nd floor" and "Work Area A". For example, identify "Company A".

[0068] Next, referring to the contract-related information in the contract-related information DB225 of Figure 1, identify, as the contract rate (i.e., the planned rate) associated with the "rebar worker" which is the job type identified by SC1, the aforementioned identified "Company A", and the aforementioned identified "2nd floor" and "Work Area A", for example, "0.75 (man-days / ton)".

[0069] Next, based on the specifically identified "0.75 (man-days / ton)" and the quantity of "10 (tons)" identified by SB2 in Figure 6, perform a predetermined calculation (specifically, 0.75 (man-days / ton) × 10 (tons)), and identify the calculation result of "7.5 (man-days)" as the planned man-hours.

[0070] <Process of identifying actual man-hours> Regarding the process of identifying the actual man-hours, generally, based on the process identification information, the information of the job type identified by SC1, and the daily report-related information, identify the planned man-hours.

[0071] Specifically, for example, obtain "beam reinforcement" associated with "ID001" in the process identification information of Figure 2, and identify "beam" as the part to be worked on based on the "beam reinforcement". Next, identify the "2nd floor" and "Work Area A" associated with "ID001" in the process identification information of Figure 2.

[0072] Next, in the same manner as in the case of the process of identifying the planned man-hours, identify the cooperating company responsible for the work in the process of "ID001". For example, identify "Company A".

[0073] Next, referring to the daily report related information in the daily report related information DB226 of FIG. 1, based on the information indicating the number of workers and working hours associated with the occupation of "rebar worker" specified in SC1, the aforementioned "Company A" specified, and the aforementioned "beam", "2nd floor", and "Work Area A", for example, "8 man-days" is specified as the actual man-hours.

[0074] =SC3= In SC3 of FIG. 8, the specific part 231 of the server device 2 stores man-hour information. For example, in the process table additional information of FIG. 4, "ID001" indicating the process to be processed is stored as the process ID, and based on the planned man-hours of "7.5 man-days" and the actual man-hours of "8 man-days" specified in SC2, "Planned: 7.5 man-days, Actual: 8 man-days" is stored. With this, the man-hour information storage process returns.

[0075] ===SA3=== In SA3 of FIG. 5, the specific part 231 of the server device 2 executes the cost information storage process. FIG. 10 is a flowchart of the cost information storage process, and FIG. 11 is a diagram showing a specific example of cost. The "cost information storage process" is a process for storing cost information.

[0076] =SD1= In SD1 of FIG. 10, the specific part 231 of the server device 2 performs the same process as SB1 in FIG. 6 to identify the occupation. For example, "rebar worker" is identified.

[0077] =SD2= In SD2 of FIG. 10, generally, based on the process identification information, the information on the occupation identified in SD1, the contract-related information, and the quantity identified in SB2, the planned cost is identified.

[0078] Specifically, for example, in the process identification information of FIG. 2, "2nd floor" and "Work Area A" associated with "ID001" are identified.

[0079] Next, in the same manner as in the case of SC2 in FIG. 8, identify the cooperating company responsible for the work in the process of "ID001". For example, identify "Company A".

[0080] Next, referring to the contract-related information in the contract-related information DB225 in FIG. 1, identify, as the "contract total quantity" and "contract total amount" associated with the "rebar worker", which is the job type identified in SD1, and the aforementioned identified "Company A", for example, "50 (tons)" and "2,000,000 (yen)".

[0081] Next, based on the identified "50 (tons)" and "2,000,000 (yen)" and the quantity of "10 (tons)" identified in SB2 in FIG. 6, perform a predetermined calculation (specifically, 2,000,000 (yen) × (10 (tons) / 50 (tons)) and identify the calculation result of "400,000 (yen)" as the planned cost.

[0082] =SD3= In SD3 of FIG. 8, the specifying unit 231 of the server device 2 stores cost information. For example, in the process table additional information in FIG. 4, store "ID001", which indicates the process to be processed as the process ID, and also store "Estimated: 400,000 yen" based on the planned cost of "400,000 (yen)" identified in SD2 as the cost information. Thus, return the cost information.

[0083] Then, by repeatedly executing the processing for each process in SA1 to SA3 in FIG. 5, store the process table additional information for each process.

[0084] ===SA4=== In SA4 of FIG. 5, the management unit 232 of the server device 2 displays the process table screen. FIG. 12 is an example of the display of the process table screen, and FIG. 13 is an example of the display of the additional information display column.

[0085] =Process Table Screen= The process table screen is a screen for displaying a process table, additional information, etc. For example, as shown in FIG. 12, it includes an additional information display column G1. In FIG. 12, only the additional information display column G1 related to "beam reinforcement" is shown representatively, but actually, additional information display columns for other processes will also be displayed.

[0086] =Processing= Based on the process display specific information in FIG. 2 and the process table additional information in FIG. 4, the management unit 232 of the server device 2 generates screen information for displaying the process table screen in FIG. 12, and by transmitting the generated screen information to the terminal device 1, the process table screen is displayed on the display 13.

[0087] For example, based on the process display specific information in FIG. 2, screen information for displaying the process table screen in FIG. 12 including the process table in FIG. 3 is generated. Also, for example, by referring to the process table additional information in FIG. 4, quantity information, man-hour information, and cost information are acquired, and by referring to the process specific information in FIG. 2, the process with the same process ID as the process ID associated with each of the acquired information is identified, and screen information for displaying the additional information display column G1 for displaying information corresponding to the acquired quantity information, man-hour information, and cost information for the identified process is generated for the process table screen in FIG. 12.

[0088] Regarding the additional information display column G1, for example, since "Scheduled: 10 tons", "Scheduled: 7.5 man-days, Actual: 8 man-days", and "Scheduled: 400,000 yen" in FIG. 4 are associated with "ID001", the process corresponding to "beam reinforcement" in FIG. 2 is identified, and as shown in FIG. 12, screen information including the additional information display column G1 for the "beam reinforcement" is generated.

[0089] Specifically, for example, as shown in FIG. 13(a), screen information including the additional information display column G1 for displaying the scheduled additional information (the "10 tons" corresponding to "Scheduled: 10 tons", the "7.5 man-days" corresponding to "Scheduled: 7.5 man-days", and the "400,000 yen" corresponding to "Scheduled: 400,000 yen") may be generated.

[0090] Alternatively, for example, as shown in FIG. 13(b), generate screen information including an additional information display column G1 that displays planned additional information (such as "10 tons" corresponding to "planned: 10 tons", "7.5 person-days" corresponding to "planned: 7.5 person-days", and "400,000 yen" corresponding to "planned: 400,000 yen"), actual additional information (such as "8 person-days" corresponding to "actual: 8 person-days"), "(pre)" indicating that it is planned additional information, and "(act)" indicating that it is actual additional information.

[0091] Note that information indicating the job type specified by SB1 etc. in FIG. 6 is recorded in the recording unit 22, and as shown in FIGS. 13(a) and (b), generate screen information including the additional information display column G1 so as to also display information indicating the job type (in FIG. 13, "rebar worker").

[0092] Then, by performing the above-described processing for all processes, additional information for each process will be displayed on the process schedule screen. Thus, the process schedule display processing is terminated.

[0093] (Effect of the present embodiment) According to the present embodiment, by associating and displaying additional information with each process in the process schedule, for example, it is possible to check the additional information in the process schedule, so that the process schedule can be effectively utilized.

[0094] [III] Modification examples of the embodiment Although the embodiments according to the present invention have been described above, the specific configurations and means of the present invention can be arbitrarily modified and improved within the scope of the technical idea of each invention described in the claims.

[0095] (Regarding additional information (Part 1)) In the above implementation, the standard additional information and the actual additional information are used as the man-hour information, and the standard additional information is used as the quantity information and the cost information. However, the present invention is not limited to this. For example, as the man-hour information, either one of the standard additional information or the actual additional information may be used, and as the quantity information and the cost information, only the actual additional information or both the standard additional information and the actual additional information may be used.

[0096] (Additional Information (Part 2)) In the above embodiment, the scheduled man-hour information is specified based on the information corresponding to the information described in the contract between the general contractor and the plurality of cooperating companies regarding the construction work, and the actual man-hour information is specified based on the information corresponding to the information described in the daily report indicating the work results by the cooperating companies. However, the present invention is not limited to this. For example, the scheduled man-hour information may be specified based on the information corresponding to the contract between the client and the general contractor regarding the construction work, and the actual man-hour information may be specified based on the information corresponding to the information described in the contract between the general contractor and the plurality of cooperating companies regarding the construction work.

[0097] (Other Information (Part 1)) In the above embodiment, other information may be additionally displayed for the additional information display column G1 in FIG. 13. FIG. 14 is an example of the display of the additional information display column. For example, the quality record image G11 and the safety record image G12 shown in FIG. 14 may be configured to be displayed.

[0098] The "quality record image" G11 is information regarding the quality record of the work in each process. Specifically, it is information displayed in association with each process. For example, it is image information linked to the information recorded in the recording unit 22 of the server device 2 (for example, quality information indicating the results of quality inspections for the work in each process).

[0099] The "safety record image" G12 is information regarding safety images related to the work of each process. Specifically, it is information that is displayed in association with each process. For example, it is image information linked to the information recorded in the recording unit 22 of the server device 2 (e.g., safety information indicating the results of safety inspections related to the work of each process).

[0100] And, based on the information recorded in these recording units 22, the management unit 232 of the server device 2 uses any technology (e.g., technology corresponding to mouse over, etc.). When the quality record image G11 is tapped, quality information regarding the work of "beam reinforcement" is displayed, and when the safety record image G12 is tapped, safety information regarding the work of "beam reinforcement" is displayed. The process table screen may also be displayed.

[0101] Or, for example, the quality information and safety information are recorded in the recording unit 22 of the server device 2 in a predetermined file format (e.g., the format of a PDF file, etc.). The management unit 232 of the server device 2 is configured such that when the quality record image G11 is tapped, a PDF file of the quality information regarding the work of "beam reinforcement" is displayed, and when the safety record image G12 is tapped, a PDF file of the safety information regarding the work of "beam reinforcement" is displayed.

[0102] (Regarding other information (Part 2)) Also, in "(Regarding other information (Part 1))", as shown in FIG. 14, the case of displaying both the quality record image G11 and the safety record image G12 was described, but it is not limited to this, and it may be configured to display only one of them.

[0103] (Regarding each additional information) Also, reference additional information and performance additional information may be accumulated, and each piece of information may be compared with each other and displayed in an arbitrary format (e.g., graph format, or table format, etc.).

Explanation of reference numerals

[0104] 1 Terminal device 2 Server device 11 Communication unit 12 Touch pad 13 Display 14 Recording unit 15 Control unit 21 Communication unit 22 Recording unit 23 Control unit 100 Information processing system 221 Process identification information DB 222 Process table additional information DB 223 Process name and occupation related information DB 224 Accumulation related information DB 225 Contract related information DB 226 Daily report related information DB 231 Specific unit 232 Management unit G1 Additional information display column G11 Quality record image G12 Safety record image

Claims

1. A display system for associating and displaying additional information for each process in a construction process schedule, a first storage means storing process identification information which is information indicating each of the processes, a second storage means storing additional information specifying information for specifying the additional information based on the process identification information stored in the first storage means, a specifying means for specifying the additional information based on the process identification information of the first storage means and the additional information specifying information of the second storage means, and a management means for displaying the additional information specified by the specifying means in association with each of the processes in the process schedule, wherein the specifying means specifies, as the additional information for each of the processes in the process schedule, reference additional information regarding a reference of the construction and performance additional information regarding a performance of the construction, the management means, a first information obtained by combining the reference additional information specified by the specifying means and information indicating that it is the reference additional information, and a second information obtained by combining the performance additional information specified by the specifying means and information indicating that it is the performance additional information, and displays them, a display system.

2. A third storage means for storing the additional information specified by the specifying means, further comprising, wherein the management means displays the additional information stored in the third storage means in association with each of the processes in the process schedule, The display system according to claim 1.

3. The specifying means specifies specifiable information which is information specifiable by the process identification information, and then specifies the additional information based on the specifiable information, The display system according to claim 1 or 2.

4. The specifying means specifies, at least, information indicating an occupation type in the construction as the specifiable information, The display system according to claim 3.

5. In the second storage means, accumulation related information regarding the accumulation of the construction, contract related information regarding a contract for the construction, or daily report related information regarding a daily report which is a daily report on work regarding the construction is stored as the additional information specifying information, The display system according to any one of claims 1 to 4.

6. The management means displays information regarding quality records or safety records related to the work of each process in association with each of the processes in the process schedule in addition to the additional information, The display system according to any one of claims 1 to 5.

7. A display program for associating and displaying additional information for each process in a construction process schedule, causing a computer to function as a first storage means storing process identification information which is information indicating each of the processes, a second storage means storing additional information specifying information for specifying the additional information based on the process identification information stored in the first storage means, a specifying means for specifying the additional information based on the process identification information of the first storage means and the additional information specifying information of the second storage means, and a management means for displaying the additional information specified by the specifying means in association with each of the processes in the process schedule, wherein the specifying means specifies, as the additional information, reference additional information regarding the standard of the construction and performance additional information regarding the performance of the construction for each of the processes in the process schedule, the management means displays first information which is a combination of the reference additional information specified by the specifying means and information indicating that it is the reference additional information, and second information which is a combination of the performance additional information specified by the specifying means and information indicating that it is the performance additional information. Display program.

Citation Information

Patent Citations

  • Construction work managing and supporting device, and system

    JP1997256635A

  • System and method for confirming building situation

    JP2001282911A