Method and apparatus for synchronizing measurement timing of branch measurement devices

By synchronizing branch measurement devices using a phase reference point in the busbar AC voltage, the method addresses installation and consistency issues, enhancing measurement accuracy and reducing costs in data centers and cloud servers.

KR103044930B1Active Publication Date: 2026-11-10DEESYS CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
KR1020260005270
Authority / Receiving Office
KR · KR
Patent Type
Patents
Current Assignee / Owner
Priority Date
2025-11-06
Filing Date
2026-01-12
Publication Date
2026-11-10
Estimated Expiration
2046-01-12

AI Technical Summary

Technical Problem

Conventional methods for synchronizing branch measurement devices in data centers and cloud servers face increased installation burdens, costs, and measurement time inconsistencies due to communication delays and jitter, necessitating a more efficient synchronization method.

Method used

A method and apparatus that synchronize branch measurement devices by identifying a phase reference point in the AC voltage of a busbar and transmitting a synchronization signal to multiple devices, aligning their measurement times without separate synchronization wiring or complex procedures.

Benefits of technology

This approach reduces system complexity and installation burdens while enhancing measurement time consistency and accuracy by aligning reference points across branch measurement devices, improving power calculation and analysis efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 112026004065311-PAT00002_ABST
    Figure 112026004065311-PAT00002_ABST
Patent Text Reader

Abstract

The present disclosure relates to a method and apparatus for synchronizing the measurement time of a branch measurement device. According to one embodiment of the present disclosure, a method for synchronizing the measurement time of a branch measurement device may be provided, comprising the steps of: identifying a phase reference point in the alternating voltage of a bus bar; and transmitting a synchronization signal to a plurality of branch measurement devices based on the identification of the phase reference point.
Need to check novelty before this filing date? Find Prior Art

Description

Technology Field

[0001] The present disclosure relates to a method and apparatus for synchronizing the measurement time of a branch measurement device. Background Technology

[0002] With the recent increase in demand for precise power data measurement of multiple branch circuits in data centers and cloud servers to optimize energy and analyze abnormal conditions, there is a growing need for synchronization technology to align the measurement times of branch currents with respect to busbar voltage.

[0003] According to conventional technology, in order to calculate power for each branch circuit, both voltage and current for each branch are often measured, or separate time synchronization means are applied to each branch measurement device. This leads to problems such as increased burdens and costs for installation, wiring, and insulation, as well as potential degradation of measurement time consistency due to communication delays and jitter.

[0004] Accordingly, there is a need to develop a technology that consistently synchronizes the measurement times of branch measurement devices by providing synchronization signals to multiple branch measurement devices based on the phase reference point identified in the AC voltage of the busbar.

[0005] The aforementioned background technology is technical information that the inventor possessed for the derivation of the present invention or acquired during the process of deriving the present invention, and it cannot be considered as prior art disclosed to the general public prior to the filing of the present invention. The problem to be solved

[0006] The present disclosure provides a method and apparatus for synchronizing the measurement time of a branch measurement device. The problems to be solved by the present disclosure are not limited to those mentioned above, and other problems and advantages of the present disclosure not mentioned can be understood from the following description and will be more clearly understood from the embodiments of the present disclosure. Furthermore, it will be understood that the problems and advantages to be solved by the present disclosure can be realized by the means and combinations thereof set forth in the claims. means of solving the problem

[0007] As a technical means for achieving the technical problem described above, the first aspect of the present disclosure may provide a method for synchronizing the measurement time of a branch measuring device, comprising: identifying a phase reference point in the alternating voltage of a bus bar; and transmitting a synchronization signal to a plurality of branch measuring devices based on the identification of the phase reference point.

[0008] A second aspect of the present disclosure may provide a computer-readable recording medium having a program for executing the method of the first aspect of the present disclosure on a computer.

[0009] A third aspect of the present disclosure may provide a device for synchronizing the measurement time of a branch measuring device, comprising: a communication module for performing communication; a memory in which at least one program is stored; and a processor that operates by executing the at least one program, wherein the processor identifies a phase reference point in the alternating voltage of a bus bar and controls the communication module to transmit a synchronization signal to a plurality of branch measuring devices based on the identification of the phase reference point.

[0010] Other aspects, features, and advantages other than those described above will become clear from the following drawings, claims, and detailed description of the invention. Effects of the invention

[0011] According to the means for solving the problem of the present disclosure described above, the measurement reference points of a plurality of branch measuring devices can be aligned with a common reference based on the phase reference point identified in the AC voltage of the busbar.

[0012] In addition, according to the means for solving the problem of the present disclosure, a synchronization signal can be provided without separate dedicated synchronization wiring or complex time synchronization procedures, thereby reducing the complexity of the system configuration and the burden of installation / maintenance.

[0013] The effects of the embodiments of the present disclosure are not limited to the effects mentioned above, and other unmentioned effects will be clearly understood by those skilled in the art from the description in this specification. Brief explanation of the drawing

[0014] The following drawings attached to this specification are intended to illustrate at least one embodiment according to the present disclosure and serve to further enhance understanding of the technical concept of the present disclosure together with the detailed description of the invention set forth below; therefore, the present disclosure should not be interpreted as being limited only to the matters described in the drawings. FIG. 1 is a schematic diagram illustrating a measurement system including a main measurement device and a plurality of branch measurement devices according to one embodiment. FIG. 2 is an example of a method in which a main measuring device operates according to one embodiment. FIG. 3 is an exemplary drawing for explaining a measurement method for a busbar and a branch circuit according to one embodiment. FIG. 4 is an exemplary drawing for explaining a phase reference point according to one embodiment. FIG. 5 is an exemplary diagram illustrating the process of transmitting and receiving a synchronization signal and a Modbus RTU frame through the same communication line according to one embodiment. FIGS. 6 and 7 are examples of a method of operation of a branch measurement device according to one embodiment. FIG. 8 is an exemplary diagram illustrating the process of generating a synchronization signal and a timer reset signal based on the detection of an alternating current voltage of a busbar according to one embodiment. FIG. 9 is a block diagram of a measuring device according to one embodiment. Specific details for implementing the invention

[0015] The advantages and features of the present disclosure and the methods for achieving them will become clear by referring to the embodiments described in detail together with the accompanying drawings. However, the present disclosure is not limited to the embodiments presented below, but can be implemented in various different forms and should be understood to include all modifications, equivalents, and substitutions that fall within the spirit and scope of the present disclosure. The embodiments presented below are provided to make the present disclosure complete and to fully inform those skilled in the art of the scope of the invention. In describing the present disclosure, detailed descriptions of related prior art are omitted if it is determined that such detailed descriptions may obscure the essence of the present disclosure.

[0016] The terms used herein are used merely to describe specific embodiments and are not intended to limit the disclosure. Unless otherwise defined, all terms used herein have the same meaning as generally understood by those skilled in the art to which this disclosure pertains.

[0017] In this specification, singular expressions include plural expressions unless the context clearly indicates otherwise. Furthermore, terms such as "comprising" or "having" are intended to specify the existence of the features, numbers, steps, actions, components, parts, or combinations thereof described in the specification, and should be understood as not precluding the existence or addition of one or more other features, numbers, steps, actions, components, parts, or combinations thereof.

[0018] Additionally, terms including ordinal numbers, such as "first" or "second" as used herein, may be used to describe various components, but the components should not be limited by the terms. The terms are used solely for the purpose of distinguishing one component from another.

[0019] Phrases such as "in one embodiment," "according to one embodiment," "related to one embodiment," or "according to an implementation of one embodiment" in this specification do not necessarily refer to the same embodiment. Furthermore, throughout this specification, "examples" are arbitrary distinctions to facilitate the description of the present disclosure, and each embodiment does not need to be mutually exclusive. For example, configurations mentioned for the description of one embodiment may be applied and / or implemented in other embodiments, and may be modified and applied and / or implemented to the extent that they do not depart from the scope of the present disclosure.

[0020] Some embodiments of the present disclosure may be represented by functional block configurations and various processing steps. Some or all of these functional blocks may be implemented by various numbers of hardware and / or software configurations that perform specific functions. For example, the functional blocks of the present disclosure may be implemented by one or more microprocessors or by circuit configurations for a specific function.

[0021] For example, the functional blocks of the present disclosure may be implemented in various programming or scripting languages. The functional blocks may be implemented as algorithms executed on one or more processors. Additionally, the present disclosure may employ prior art for electronic configuration, signal processing, and / or data processing, etc. Terms such as "mechanism," "element," "means," and "configuration" may be used broadly and are not limited to mechanical and physical configurations. Furthermore, terms such as "-part," "-module," etc. refer to a unit that processes at least one function or operation, which may be implemented in hardware or software, or as a combination of hardware and software.

[0022] Furthermore, the connecting lines or connecting members between the components depicted in the drawings are merely illustrative of functional connections and / or physical or circuit connections. In the actual device, connections between components may be represented by various alternative or added functional connections, physical connections, or circuit connections.

[0023] In addition, some components in the drawings may be depicted with their size or proportions slightly exaggerated. Also, components depicted in one drawing may not be depicted in another drawing.

[0024] Hereinafter, embodiments of the present disclosure will be described in detail with reference to the attached drawings.

[0025] FIG. 1 is a schematic diagram illustrating a measurement system including a main measurement device and a plurality of branch measurement devices according to one embodiment.

[0026] Referring to FIG. 1, the measurement system may include a main measurement device (110) and a plurality of branch measurement devices (120). In this case, the main measurement device (110) may include a device connected to a bus bar to measure power data of the bus bar (e.g., current, voltage, effective value calculated therefrom, phase, power factor, active power, etc.), and each of the plurality of branch measurement devices (120) may include a device connected to one of a plurality of branch circuits branched from the bus bar to measure power data of the corresponding branch circuit. The bus bar may be a conductor through which AC power is commonly distributed, and the branch circuit may be a circuit branched from the bus bar to supply power to a load.

[0027] In one embodiment, the main measuring device (110) can measure the current and voltage of the busbar. For example, the main measuring device (110) may include a voltage sensing unit for measuring the voltage of the busbar and a current sensing unit for measuring the current of the busbar. In one embodiment, the voltage sensing unit may include a voltage sensing circuit that converts the alternating current voltage of the busbar into a sampleable form, and the current sensing unit may include a converter (CT) or a current sensor (e.g., a Hall sensor, etc.) for measuring the alternating current flowing through the busbar, but is not limited thereto.

[0028] Each of the plurality of branch measuring devices (120) can measure the current of the branch circuit. In one embodiment, each of the plurality of branch measuring devices (120) may be configured to measure only the branch current without separately measuring the voltage of the branch circuit. For example, the first branch measuring device (121) may be configured to measure the branch current of the first branch circuit but not the voltage, and the second branch measuring device (122) may be configured to measure the branch current of the second branch circuit but not the voltage.

[0029] Through this, each of the multiple branch measuring devices (120) does not need to satisfy the requirements for circuits, wiring, and insulation for voltage measurement, so the configuration of the measuring device is simplified and the burden of installation and maintenance can be reduced.

[0030] Meanwhile, even if branch voltages are not measured individually at each branch circuit, it is necessary to synchronize the measurement timing of the bus voltage and branch currents in order to utilize the bus voltage for power calculation and analysis for each branch circuit.

[0031] In one embodiment, the main measuring device (110) measures the bus voltage, identifies a phase reference point from the alternating current voltage of the bus, and can provide a synchronization signal based on the phase reference point to a plurality of branch measuring devices (120). Accordingly, each of the plurality of branch measuring devices (120) can align the reference point for current sampling based on the synchronization signal and can consistently align the time reference for current measurement between branches.

[0032] Additionally, the main measuring device (110) and the plurality of branch measuring devices (120) may be interconnected via a wired communication network and / or a wireless communication network, and the wired communication network may be implemented as a communication line (130) that is commonly connected to the plurality of branch measuring devices (120), but is not limited thereto.

[0033] Synchronization signals and / or various data can be transmitted and received through the communication line (130). In one embodiment, the communication line (130) may include a bus-type communication line that implements the RS-485 communication method.

[0034] FIG. 2 is an example of a method in which a main measuring device operates according to one embodiment.

[0035] Referring to FIG. 2, in step 210, the main measuring device (110) can identify a phase reference point in the alternating voltage of the busbar.

[0036] In one embodiment, the alternating voltage may include a three-phase voltage, and the phase reference point may include a zero crossing point in at least one phase of the three-phase voltage.

[0037] In one embodiment, the zero crossing point may include at least one of a rising edge and a falling edge.

[0038] In step 220, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) based on the identified phase reference point.

[0039] In one embodiment, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) in a broadcast manner.

[0040] In one embodiment, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) via an RS-485 communication line.

[0041] For example, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) via a broadcast method through an RS-485 communication line.

[0042] In one embodiment, the main instrumentation device (110) can transmit or receive a Modbus RTU frame via an RS-485 communication line at a time that does not overlap with the transmission of a synchronization signal.

[0043] In one embodiment, each of the plurality of branch measurement devices (120) receives a reception signal of an RS-485 communication line through a GPIO pin and can perform a timer reset interrupt in response to an edge change of a synchronization signal detected at the GPIO pin.

[0044] In one embodiment, each of the plurality of branch measuring devices (120) can measure the current aligned at the phase reference point based on receiving a synchronization signal.

[0045] In one embodiment, each of the plurality of branch measurement devices (120) can generate a current sample sequence by resetting an internal timer based on receiving a synchronization signal and sampling the branch current.

[0046] In one embodiment, the synchronization signal may include a synchronization sequence number corresponding to a phase reference time.

[0047] In one embodiment, the synchronization sequence number may be a value generated based on a counter value accumulated according to the number of occurrences of the phase reference time.

[0048] FIG. 3 is an exemplary drawing for explaining a measurement method for a busbar and a branch circuit according to one embodiment. The main measurement device (310) shown in FIG. 3 may be an example of the main measurement device (110) shown in FIG. 1, and the plurality of branch measurement devices (320a, 320b, 320c, 320d) shown in FIG. 3 may be an example of the plurality of branch measurement devices (120) shown in FIG. 1.

[0049] Referring to FIG. 3, the busbar is a conductor through which AC power is commonly distributed and can be commonly connected to a plurality of branch circuits, and each branch circuit can be branched from the busbar to supply power to individual loads. Additionally, the branch circuit is a wiring section branched from the busbar and may include at least some of a circuit breaker, a distribution circuit, and / or a load-side connection section.

[0050] Meanwhile, the number of branch circuits and the arrangement of branch points shown in FIG. 3 are illustrated as examples, so the configuration of the busbar and branch circuits to be measured may vary depending on the phase configuration of the busbar, the power distribution structure, and / or the installation environment.

[0051] In one embodiment, each of the plurality of branch measuring devices (320a, 320b, 320c, 320d) is connected to different branch circuits branched from the busbar and can measure the branch current of the corresponding branch circuit. In addition, in one embodiment, the branch current may include a three-phase current. For example, each of the plurality of branch measuring devices (320a, 320b, 320c, 320d) can measure the branch current by sampling the three-phase current value of the corresponding branch circuit using an analog-to-digital converter (ADC).

[0052] Meanwhile, it should be noted that measuring branch current connected to a branch circuit may include not only direct connection to the conductor of the branch circuit, but also indirect measurement through a converter, current sensor, etc. inductively coupled to the branch circuit. Additionally, the branch circuit may be a single-phase or multi-phase circuit, and each of the plurality of branch measuring devices (320a, 320b, 320c, 320d) may be configured to measure single-phase current, multi-phase current, or a combination thereof.

[0053] In the present disclosure, the voltage of a branch circuit refers to a voltage formed at a predetermined point on the branch circuit, and the predetermined point may include a branch point, any wiring point on the branch circuit, a point after a circuit breaker, or a load input terminal. Generally, since the branch circuit is electrically connected to the busbar, the voltage of the branch circuit has the same frequency component as the busbar voltage and may share a phase reference defined by the busbar voltage.

[0054] In one embodiment, the main measuring device (310) can identify the phase reference point using the alternating current voltage of the busbar. At this time, the phase reference point represents the point in time when a preset phase condition (e.g., zero crossing condition, condition of reaching a specific phase angle, maximum / minimum condition, etc.) is established in the alternating current voltage of the busbar. For example, the main measuring device (310) can identify the phase reference point by detecting at least one of the phase voltage of the busbar, the inter-phase voltage, and / or the reference voltage derived therefrom.

[0055] In one embodiment, when the AC voltage includes a three-phase voltage, the phase reference point may include a zero-crossing point in at least one phase of the three-phase voltage, and at least one phase may be selected according to the installation environment, the measurement target, and / or the phase configuration of the branch circuit. As an example, the main measuring device (310) may detect the AC voltage by setting the phase that serves as the identification reference for the phase reference point to the R phase. At this time, the main measuring device (310) may identify the phase reference point in the R phase of the AC voltage.

[0056] Subsequently, the main measuring device (310) can generate a synchronization signal provided to a plurality of branch measuring devices (320a, 320b, 320c, 320d) based on the identified phase reference point. At this time, the synchronization signal represents a signal to notify the plurality of branch measuring devices (320a, 320b, 320c, 320d) of the occurrence of the phase reference point, and can be implemented, for example, as a pulse signal formed by a level switching on an RS-485 communication line, or a communication message including a pulse signal.

[0057] In one embodiment, the synchronization signal may include at least one of a synchronization sequence number corresponding to a phase reference point (e.g., a counter value accumulated according to the number of occurrences of the phase reference point), a timestamp of the corresponding phase reference point, and / or an accumulated count of synchronization events (e.g., a pulse count). Each of the plurality of branch measurement devices (320a, 320b, 320c, 320d) determines a period interval to be used for calculation in a current sample sequence based on information indicated by the synchronization signal, and can correct the sample index offset or perform resynchronization if there is a missing or duplicate synchronization event.

[0058] Each of the multiple branch measuring devices (320a, 320b, 320c, 320d) can align the reference point for branch current sampling based on the synchronization signal received from the main measuring device (310), and accordingly, even in a configuration where the voltage for each branch circuit is not measured separately, the time reference between the bus voltage and the branch current is consistently aligned, thereby improving the consistency of power calculation and analysis for each branch circuit.

[0059] FIG. 4 is an exemplary drawing for explaining a phase reference point according to one embodiment.

[0060] Referring to FIG. 4, the phase reference point identified in the AC voltage (400) of the busbar may include a zero crossing point, and the zero crossing point may include at least one of a rising edge (R) and a falling edge (F). At this time, the rising edge (R) may indicate a point in time when the AC voltage (400) passes the reference voltage (e.g., 0V, etc.) from downward to upward, and the falling edge (F) may indicate a point in time when the AC voltage (400) passes the reference voltage from upward to downward.

[0061] Referring together with FIG. 1, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) based on the identification of a phase reference point. In one embodiment, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) based on the identification of a rising edge (R) in the AC voltage (400). For example, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) based on the identification of a rising edge (R) of a zero crossing occurring in a specific phase (e.g., R phase, etc.) of the bus voltage.

[0062] In another embodiment, the main measuring device (110) may transmit a synchronization signal to a plurality of branch measuring devices (120) based on the identification of a falling edge (F) in the alternating voltage (400). In yet another embodiment, the main measuring device (110) may use both the rising edge (R) and the falling edge (F) as phase reference points. In this case, the phase reference point may occur at every half-cycle of the alternating voltage (400).

[0063] In one embodiment, the main measuring device (110) can transmit a synchronization signal to a plurality of branch measuring devices (120) in a broadcast manner. A broadcast method represents a communication method in which a single transmission reaches a plurality of receiving entities, and the main measuring device (110) can transmit the synchronization signal to a plurality of branch measuring devices (120) through a wired communication path or a wireless communication path.

[0064] Through this, notification of the phase reference time can be performed collectively without performing individual addressing or polling for each of the multiple branch measurement devices (120), so the efficiency and consistency of synchronization can be improved, and the error in power calculation and analysis per branch circuit can be reduced based on the time alignment of the bus voltage and branch current.

[0065] FIG. 5 is an exemplary diagram illustrating the process of transmitting and receiving a synchronization signal and a Modbus RTU frame through the same communication line according to one embodiment.

[0066] Referring to FIG. 5, the main measuring device (110) may include a signal selection circuit (510) and a transceiver (520). For example, the communication module of the main measuring device (110) may include a signal selection circuit (510) and a transceiver (520).

[0067] In one embodiment, the main measuring device (110) generates raw transmission data (Tx_1) and a synchronization signal (ZCD), and can select and convert a signal to be output to a communication line using a signal selection circuit (510) and a transceiver (520). Here, the raw transmission data (Tx_1) represents a communication frame according to a pre-configured communication protocol and may include, for example, transmission data according to a Modbus RTU frame.

[0068] Additionally, the synchronization signal (ZCD) is a signal for indicating the occurrence of a phase reference point identified in the AC voltage of the busbar, and may include, but is not limited to, a pulse signal generated based on the identification result of a zero-crossing point. It should be noted that in this specification, the synchronization signal may be used to include not only the synchronization pulse (or synchronization information) generated inside the main measuring device (110) upstream of the signal selection circuit (510), but also the signal selected and output as transmission data (Tx) by the signal selection circuit (510), the signal converted into an RS-485 differential signal (A, B) by the transceiver (520) and transmitted through the communication line, and the signal observed as reception data (Rx) at the branch measuring device (120).

[0069] In one embodiment, the main measuring device (110) can transmit a synchronization signal (ZCD) to a plurality of branch measuring devices (120) via an RS-485 communication line. As an example, the main measuring device (110) inputs the synchronization signal (ZCD) as transmission data (Tx) to a transceiver (520), and the transceiver (520) can output the transmission data (Tx) in the form of RS-485 differential signals (A, B) via an RS-485 communication line.

[0070] For example, the main measuring device (110) can transmit a synchronization signal (ZCD) to a plurality of branch measuring devices (120) via a broadcast method through an RS-485 communication line. At this time, the synchronization signal (ZCD) can be commonly observed by each of the plurality of branch measuring devices (120) connected to the RS-485 communication line.

[0071] In one embodiment, the main measurement device (110) can enable a plurality of branch measurement devices (120) to perform the same operation (e.g., applying the same setting value) simultaneously by transmitting a Modbus RTU write request frame set to a broadcast address. Through this, the main measurement device (110) can apply common settings (e.g., sampling period, operation parameters, operation mode, etc.) to a plurality of branch measurement devices (120) collectively without sequentially repeating write requests to individual branch measurement devices, thereby reducing the communication traffic and time required for control and setting, and suppressing errors in power calculation caused by setting inconsistencies between branch measurement devices.

[0072] Meanwhile, the RS-485 communication line can form a communication path shared by a general communication frame and a synchronization signal (ZCD). In one embodiment, the main instrument (110) can transmit or receive a Modbus RTU frame through the RS-485 communication line at a time that does not overlap with the transmission of the synchronization signal (ZCD).

[0073] For example, the main measurement device (110) can selectively transmit the synchronization signal (ZCD) and the communication frame through the same RS-485 communication line by temporally separating the period for transmitting the synchronization signal (ZCD) and the period for transmitting and receiving the Modbus RTU frame. As an example, the main measurement device (110) can create and set a communication schedule to prioritize the transmission of the synchronization signal (ZCD) when a phase reference point occurs, and to transmit or receive the Modbus RTU frame after the transmission of the synchronization signal (ZCD) is finished (or during an idle period that does not conflict with the synchronization signal (ZCD).

[0074] In one embodiment, the communication schedule may be configured to include a measurement communication mode and a synchronization mode. Here, the measurement communication mode refers to a period in which a Modbus RTU frame containing information used for power calculation, such as voltage RMS and / or inter-phase difference, is transmitted and received, and the synchronization mode refers to a period in which a synchronization signal (ZCD) is transmitted to indicate the occurrence of a phase reference point. For example, the main measurement device (110) may be operated to provide voltage-related information in a first period (e.g., hundreds of ms, etc.) in the measurement communication mode and to provide a synchronization signal (ZCD) in a second period (e.g., 1 second, etc.) in the synchronization mode, and the switching between the modes may be controlled according to a selection signal (S) and / or a pre-set scheduling logic.

[0075] In one embodiment, the signal selection circuit (510) selects either raw transmission data (Tx_1) or a synchronization signal (ZCD) based on a selection signal (S), and outputs the selected signal as transmission data (Tx). For example, the signal selection circuit (510) is implemented as a multiplexer and can operate to transmit raw transmission data (Tx) as transmission data (Tx) or to transmit the synchronization signal (ZCD) as transmission data (Tx) according to the selection signal (S).

[0076] At this time, the selection signal (S) can be generated by the pre-configured communication control logic of the main measurement device (110), and, for example, the selection signal (S) can be controlled according to a time division schedule so that the synchronization signal (ZCD) is selected during the synchronization signal transmission period and the raw transmission data (Tx_1) is selected during the Modbus RTU frame transmission and reception period.

[0077] This allows for the parallel synchronization and Modbus RTU-based data exchange to be performed in a time-division manner using the same RS-485 communication line, without the need for separate dedicated synchronization wiring or additional communication channels. Consequently, the number of wires and connectors is reduced, making installation and maintenance easier, and the current sampling reference points of branch measurement devices are aligned with a common phase reference point, thereby improving the consistency of power calculation and analysis.

[0078] Additionally, the transceiver (520) can convert the transmitted data (Tx) into RS-485 differential signals (A, B) and output them to the RS-485 communication line, and can convert the RS-485 differential signals (A, B) input from the RS-485 communication line into received data (Rx). That is, the synchronization signal (ZCD) and / or raw transmitted data (Tx_1) can be selected as transmitted data (Tx) through the signal selection circuit (510) and then output in the form of RS-485 differential signals (A, B) by the transceiver (520), and each of the plurality of branch measurement devices (120) can receive the synchronization signal (ZCD) and / or Modbus RTU frame through the RS-485 communication line.

[0079] As an example, a Modbus RTU frame transmitted by a main measuring device (110) to a plurality of branch measuring devices (120) may include voltage data that can be used for power calculation of the plurality of branch measuring devices (120). For example, the main measuring device (110) may provide the RMS value of each phase of the bus voltage and / or the phase difference between phases (e.g., RS, ST, TR angle difference) via Modbus.

[0080] Additionally, the Modbus RTU frame transmitted by each of the plurality of branch measuring devices (120) to the main measuring device (110) may include power data based on branch current sampling and calculation results (e.g., active power, power factor, and harmonic-related information).

[0081] Meanwhile, power calculation and analysis of the branch circuit may be performed by each branch measuring device, but may also be performed by the main measuring device (110) or by an electronic device other than the measuring system. At this time, each of the plurality of branch measuring devices (120) can transmit data regarding the measured current to the entity performing the power calculation, such as the main measuring device (110).

[0082] Additionally, in one embodiment, the synchronization signal (ZCD) may be implemented in the form of a physical signal or a communication message depending on the implementation layer. For example, the synchronization signal (ZCD) may be implemented as a pulse signal formed by a level transition on an RS-485 communication line, or as a synchronization notification message containing information indicating the occurrence of a phase reference point. Here, the synchronization notification message is a unit of data transmitted for notification of a synchronization event and may be implemented, for example, in a Modbus RTU frame format or a communication frame of a pre-configured format.

[0083] In one embodiment, the main instrumentation device (110) may switch the operating mode of a plurality of branch instrumentation devices (120) to a synchronization mode or apply a common setting using a Modbus RTU write request frame of a broadcast address so that a plurality of branch instrumentation devices (120) perform a synchronization operation based on a common standard. At this time, the write request frame may be intended to apply a common setting to the plurality of branch instrumentation devices or to instruct a mode switch for a synchronization operation. Meanwhile, the plurality of branch instrumentation devices (120) may not send a response frame in response to a write request frame transmitted to a broadcast address.

[0084] In one embodiment, the synchronization signal (ZCD) may be transmitted as a pulse signal formed by level switching on an RS-485 communication line, or in the form of a synchronization notification frame (e.g., a data frame in a pre-configured format such as a Modbus RTU format) that implements a communication message. For example, the synchronization signal (ZCD) may include information such as a sequence number indicating the identification result of a phase reference point, a pulse count, and / or a timestamp.

[0085] In one embodiment, the synchronization signal (ZCD) may include a synchronization sequence number corresponding to a phase reference time. For example, if the synchronization signal (ZCD) is implemented as a pulse signal, the synchronization sequence number may be represented by the number of pulse trains, the interval between pulses, the pulse width, or the repetition pattern of the pulse trains. As another example, if the synchronization signal (ZCD) is implemented as a synchronization notification message, the synchronization sequence number may be represented as a value included in a pre-configured field of the synchronization notification message. In one embodiment, the synchronization sequence number may be a value generated based on a counter value accumulated according to the number of occurrences of the phase reference time.

[0086] Through this, the branch measurement device can detect missing, duplicate, and sequence errors of synchronization events based on the synchronization sequence number, and if missing, etc. are detected, it can perform re-synchronization or timer correction (e.g., realignment of reference time), thereby suppressing the accumulation of synchronization errors caused by noise, transient communication load, and edge non-detection, and improving the reliability of current sampling time alignment even during long-term operation.

[0087] FIGS. 6 and 7 are examples of a method of operation of a branch measurement device according to one embodiment. Each step illustrated in FIGS. 6 and 7 can be implemented as an operation of any one of the plurality of branch measurement devices (120) illustrated in FIG. 1, etc. For example, each step illustrated in FIGS. 6 and 7 can be implemented as an operation performed by each of the plurality of branch measurement devices (120) illustrated in FIG. 1, etc.

[0088] Referring to FIG. 6, in step 610, the branch measuring device can receive a synchronization signal from the main measuring device (110). Here, the synchronization signal received by the branch measuring device may include a synchronization signal generated in response to the identification of the phase reference point on the side of the main measuring device (110), as described above with reference to FIG. 5, which has been converted into an RS-485 differential signal.

[0089] The branch measuring device can update the time reference for current sampling in response to receiving a synchronization signal. For example, the branch measuring device can align the start and / or end times of the current sampling interval by setting the time of reception of the synchronization signal as the reference time and updating an internal timer and / or counter that operates in conjunction with the reference time (e.g., initialization, loading of reference value, correction, etc.).

[0090] In step 620, the branch measuring device can measure the current aligned at the phase reference point based on receiving the synchronization signal.

[0091] Here, the current aligned with the phase reference point refers to a current sampled to have a pre-established relationship with respect to the phase reference point defined by the synchronization event. In one embodiment, the pre-established relationship may include, but is not limited to, sampling at a point substantially identical to the reference point, sampling at a point after a pre-established time offset from the reference point, or sampling within a time interval set relative to the reference point.

[0092] In one embodiment, the branch measuring device can measure a single-phase current or a multi-phase current of a branch circuit. When measuring a multi-phase current, the branch measuring device can perform current measurements such that the sampling of each phase current is aligned with the same reference point.

[0093] In one embodiment, the branch metering device may generate a current sample sequence by resetting an internal timer and sampling the branch current based on receiving a synchronization signal. For example, the branch metering device may construct a current sample sequence by accumulating samples at a preset sampling period after updating a reference point for each synchronization event. The generated current sample sequence may be transmitted to the main metering device (110) or used as an input for power data calculation within the branch metering device, and both methods may be applied selectively or in parallel.

[0094] Steps 710 to 750 illustrated in FIG. 7 are examples of implementing step 620 illustrated in FIG. 6 more specifically.

[0095] Referring to FIG. 7, in step 710, the branch instrumentation device may reset the internal timer based on receiving a synchronization signal. At this time, the internal timer refers to a timer that generates a reference time for current sampling or counts the sampling period. Additionally, resetting the internal timer may include operations such as initializing the counter value of the timer, loading a preset reference value, or synchronizing the operating phase of the timer.

[0096] In one embodiment, when the synchronization signal is implemented as a pulse signal, each of the plurality of branch measurement devices (120) receives the reception signal of the RS-485 communication line through a GPIO pin and can perform a timer reset interrupt in response to an edge change of the synchronization signal detected at the GPIO pin. For example, the reception data (Rx) output from the RS-485 transceiver of the branch measurement device may be connected in parallel to the UART reception pin and the GPIO input pin so that the reception of the communication frame and the detection of the synchronization edge can be performed in parallel.

[0097] In addition, in one embodiment, the branch instrumentation device may determine the period interval to be used for calculation among the current sample sequences (e.g., one period or N period intervals corresponding to the sequence number) based on the synchronization sequence number and / or the accumulated count included in the synchronization signal. Additionally, if a missing or duplicate is detected, the sample index offset may be corrected based on the sequence number and / or the accumulated count.

[0098] In step 720, the branch measuring device can sample the branch current at a predetermined period. Here, sampling refers to the operation of generating current samples by converting an analog current signal output from a current sensor (e.g., CT, Hall sensor, shunt-based sensing circuit, etc.) into a digital value.

[0099] In one embodiment, the branch measurement device may generate a current sample sequence consisting of a plurality of current samples arranged in chronological order as a result of sampling the branch current. For example, the branch measurement device may generate samples at a preset sampling period using an analog-to-digital converter and accumulate and store the generated samples in a memory buffer to construct the current sample sequence. The current sample sequence may be composed of a 1-period interval or an N-period interval. The length of the FFT operation (i.e., window length) described below in step 730 may be set to correspond to a 1-period or N-period interval.

[0100] In one embodiment, when the branch circuit is multi-phase, the branch measurement device may sample each phase current using a multi-channel analog-to-digital converter, a multiplexer, or a parallel sampling structure. For example, simultaneous sampling may be performed to align the sampling timing of each phase with respect to a synchronization event, or sampling delay between channels may be compensated when sequential sampling is performed.

[0101] In step 730, the branch instrumentation device can perform an FFT operation on the current sample sequence and extract the fundamental wave. At this time, the fundamental wave may refer to the component of the branch current frequency component that corresponds to the reference frequency of the power system (e.g., 50 Hz or 60 Hz).

[0102] In one embodiment, the branch measurement device performs a frequency transformation on a current sample sequence using an FFT, and calculates a magnitude value and / or phase value corresponding to the fundamental bin from the FFT result to use as a parameter of the fundamental component. Additionally, the branch measurement device may further extract at least one harmonic component in addition to the fundamental, or calculate a distortion index such as THD and include it in the power data of a subsequent stage.

[0103] In step 740, the branch meter can calculate power data based on the extracted fundamental wave.

[0104] In one embodiment, the branch measurement device can calculate power data such as active power / power factor based on the fundamental component of the branch current, the RMS and / or inter-phase difference of the bus voltage received via Modbus, and a reference point aligned by a synchronization signal.

[0105] Meanwhile, the power data calculated in step 740 may include at least one numerical value representing the power state of the branch circuit, and may include, for example, at least one of active power, reactive power, apparent power, power factor, harmonic-related data, demand power, or accumulated energy value, but is not limited thereto.

[0106] In another embodiment, the branch measurement device detects a current zero-crossing point from a current sample sequence (or the output data of a current sensor itself in which a timestamp is recorded) and can calculate a phase difference between voltage and current based on a timestamp (or sequence number) of a voltage phase reference point included in a synchronization signal. The phase difference thus calculated can be used to calculate power factor, active power, reactive power, etc.

[0107] For example, the branch measuring device can calculate a value corresponding to apparent power using the magnitude of the fundamental wave of the branch current and the RMS of the busbar AC voltage provided from the main measuring device (110), and can calculate a value corresponding to active power, reactive power, and / or power factor using the phase of the branch current fundamental wave and voltage phase information. Here, the voltage phase information may be defined based on the phase of the reference phase voltage and / or the inter-phase difference with respect to the reference point, or may be information provided from the main measuring device (110).

[0108] In step 750, the branch metering device may transmit a Modbus RTU frame containing calculated power data to the main metering device (110). In one embodiment, the branch metering device may transmit the power data by mapping it to a data field included in the payload of the Modbus RTU frame.

[0109] In addition, in one embodiment, the branch metering device may voluntarily transmit a frame containing power data according to a preset power data update cycle, event occurrence (e.g., exceeding a threshold of a specific value, change in load state, detection of missing synchronization, etc.), or preset reporting conditions, even without a polling request from the main metering device (110).

[0110] In one embodiment, the branch measurement device may schedule the transmission of a Modbus RTU frame to an idle period that does not overlap with the synchronization event period so that a general communication frame and a synchronization signal are processed temporally separated on the same communication line. For example, the branch measurement device may transmit the frame only within a preset transmission-available period after a synchronization event is detected, or delay transmission after a predetermined time from the synchronization event, to prevent the detection of the synchronization signal and the transmission of the frame from colliding.

[0111] FIG. 8 is an exemplary diagram illustrating the process of generating a synchronization signal and a timer reset signal based on the detection of an alternating current voltage of a busbar according to one embodiment.

[0112] Referring to FIG. 8, a rising edge (R) passing from a downward to an upward reference voltage (e.g., 0V) in a specific phase (e.g., R phase) of the AC voltage (810) of the busbar can be identified as a phase reference point (T_ZCD). The main instrument (110) can generate a synchronization signal (820) in response to the identification of the phase reference point (T_ZCD) and provide the generated synchronization signal (820) to a plurality of branch instrument (120) in a broadcast manner.

[0113] As shown in FIG. 8, the phase reference time (T_ZCD) may be implemented to be the same as the time of occurrence of the synchronization signal (820), and if necessary, a predetermined delay or offset may be added between the phase reference time (T_ZCD) and the time of occurrence of the synchronization signal (820).

[0114] In one embodiment, the synchronization signal (820) may include a signal in which a synchronization pulse generated within the main instrument (110) is output through a transmission data (Tx) path, converted into an RS-485 differential signal by an RS-485 transceiver, and propagated along an RS-485 communication line. As an example, the synchronization signal (820) may be implemented as a broadcast pulse signal observed as a level transition on an RS-485 communication line.

[0115] Meanwhile, each of the plurality of branch measurement devices (120) may receive a synchronization signal (820) from a communication line and generate a reset signal (830) of an internal timer in response to the received synchronization signal (820). In one embodiment, the reset signal (830) may be implemented as a pulse signal generated by an interrupt that detects an edge change of the synchronization signal (820), and an internal timer that counts the current sampling period may be initialized by the pulse signal. Accordingly, the plurality of branch measurement devices (120) may perform current sampling based on a time reference aligned with the same phase reference time (T_ZCD).

[0116] In another embodiment, the main measuring device (110) may generate a synchronization signal (820) by using a falling edge instead of a rising edge (R) or both the rising edge (R) and the falling edge as phase reference points, and may provide the synchronization signal (820) in the form of a communication message (e.g., a communication frame including a synchronization sequence number and / or timestamp) rather than a pulse signal.

[0117] In this case as well, each of the plurality of branch measurement devices (120) can generate a reset signal (830) to update the reference time of the internal timer based on the received synchronization information, or perform a reference time realignment operation having substantially the same effect as an internal timer reset.

[0118] FIG. 9 is a block diagram of a measuring device according to one embodiment. The device (900) shown in FIG. 9 may represent each of the main measuring device (110) or a plurality of branch measuring devices (120) shown in FIG. 1. For example, the main measuring device (110), the first branch measuring device (121), and the second branch measuring device (122) shown in FIG. 1 may all be implemented as the device (900) shown in FIG. 9.

[0119] Referring to FIG. 9, the device (900) may include a communication module (910), a processor (920), and a memory (930). Only the components related to the embodiment are illustrated in the device (900) of FIG. 9. Therefore, a person skilled in the art will understand that other general-purpose components may be included in the device (900) in addition to the components illustrated in FIG. 9.

[0120] The communication module (910) may include at least one component that enables the device (900) to perform wired / wireless communication with at least a part of the measurement system and / or other external devices. For example, the communication module (910) may include, but is not limited to, a signal input / output path, a wired transceiver, a wireless transceiver and / or a serial communication interface. As an example, the communication module (910) may include an RS-485 transceiver connected to an RS-485 communication line and a serial UART communication interface that implements serial communication with the processor (920).

[0121] The processor (920) controls the overall operation of the device (900). For example, the processor (920) can control the communication module (910), memory (930), input unit (not shown) and / or output unit (not shown), etc., by executing programs stored in memory (930). The processor (920) can control the operation of the device (900) by executing programs stored in memory (930).

[0122] A processor (920) can control at least some of the operations of the device (900) described above with reference to FIGS. 1 to 8, etc. For example, a processor (920) included in a device (900) implementing a main measuring device can identify a phase reference point in the AC voltage of a busbar and, based on the identification of the phase reference point, control a communication module (910) to transmit a synchronization signal to a plurality of branch measuring devices. As another example, a processor (920) included in a device (900) implementing a branch measuring device can control a communication module (910) to receive a synchronization signal from a main measuring device and, based on the reception of the synchronization signal, measure a current aligned to the phase reference point.

[0123] Meanwhile, a specific example of the operation of the processor (920) is the same as described above with reference to FIGS. 1 to 8. Therefore, a specific description of the operation of the processor (920) is omitted below.

[0124] The processor (920) may be implemented using at least one of ASICs (Application Specific Integrated Circuits), DSPs (Digital Signal Processors), DSPDs (Digital Signal Processing Devices), PLDs (Programmable Logic Devices), FPGAs (Field Programmable Gate Arrays), controllers, microcontrollers, microprocessors, and other electrical units for performing functions.

[0125] The memory (930) is hardware that stores various data processed within the device (900) and can store programs for various operations, processing, and control of the processor (920). The memory (930) may be integrated on the same chip as the processor (920) and may additionally include external memory as needed.

[0126] The memory (930) may include RAM (Random Access Memory), ROM (Read-Only Memory), EEPROM (Electrically Erasable Programmable Read-Only Memory), Blu-ray or other optical disc storage or flash memory, such as DRAM (Dynamic Random Access Memory), SRAM (Static Random Access Memory).

[0127] Meanwhile, embodiments according to the present disclosure may be implemented in the form of a computer program that can be executed through various components on a computer, and such a computer program may be recorded on a computer-readable medium. In this case, the medium may include, but is not limited to, magnetic media such as hard disks, floppy disks, and magnetic tapes, optical recording media such as CD-ROMs and DVDs, magneto-optical media such as floptical disks, and hardware devices specifically configured to store and execute program instructions such as ROM, RAM, and flash memory.

[0128] Meanwhile, the above computer program may be one specifically designed and configured for the present disclosure or one known and available to those skilled in the art of computer software. Examples of computer programs may include machine code, such as that produced by a compiler, as well as high-level language code that can be executed by a computer using an interpreter, etc.

[0129] According to one embodiment, the method according to various embodiments of the present disclosure may be provided by being included in a computer program product. The computer program product may be traded between a seller and a buyer as a product. The computer program product may be distributed in the form of a device-readable storage medium (e.g., compact disc read-only memory (CD-ROM)), or distributed online (e.g., download or upload) through an application store (e.g., Play Store™) or directly between two user devices. In the case of online distribution, at least a portion of the computer program product may be temporarily stored or temporarily created in a device-readable storage medium, such as the memory of a manufacturer's server, an application store's server, or a relay server.

[0130] Unless explicitly stated otherwise, the steps constituting the method according to the present disclosure may be performed in a suitable order. The present disclosure is not necessarily limited by the order in which the steps are described. The use of any examples or exemplary terms (e.g., etc.) in the present disclosure is merely for the purpose of describing the present disclosure in detail and, unless limited by the claims, the scope of the present disclosure is not limited by such examples or exemplary terms. Furthermore, those skilled in the art will understand that various modifications, combinations, and changes may be made according to design conditions and factors within the scope of the claims or equivalents to which they are added.

[0131] Accordingly, the scope of the present disclosure should not be limited to the embodiments described above, and all scopes equivalent to or equivalently modified from the claims set forth below, as well as the claims set forth below, shall be considered to fall within the scope of the scope of the present disclosure.

Claims

Claim 1 A method for synchronizing the measurement time of branch measuring devices, comprising: a step of identifying a phase reference point in the alternating voltage of a bus bar; and a step of transmitting a synchronization signal to a plurality of branch measuring devices based on the identification of the phase reference point; wherein the synchronization signal includes a synchronization sequence number corresponding to the phase reference point. Claim 2 A method according to claim 1, wherein the alternating current voltage includes a three-phase voltage, and the phase reference point includes a zero crossing point in at least one phase of the three-phase voltage. Claim 3 A method according to claim 2, wherein the zero crossing point comprises at least one of a rising edge and a falling edge. Claim 4 A method according to claim 1, wherein the transmitting step comprises the step of transmitting the synchronization signal to the plurality of branch measuring devices in a broadcast manner. Claim 5 A method according to claim 1, wherein the transmitting step comprises the step of transmitting the synchronization signal to the plurality of branch measuring devices via an RS-485 communication line. Claim 6 In claim 5, the method further comprises the step of transmitting or receiving a Modbus RTU frame through the RS-485 communication line at a time that does not overlap with the transmission of the synchronization signal. Claim 7 In claim 5, each of the plurality of branch measurement devices receives a reception signal of the RS-485 communication line through a GPIO pin and performs a timer reset interrupt in response to an edge change of the synchronization signal detected at the GPIO pin. Claim 8 A method according to claim 1, wherein each of the plurality of branch measuring devices measures a current aligned at the phase reference point based on receiving the synchronization signal. Claim 9 In claim 8, the method wherein each of the plurality of branch measuring devices generates a current sample sequence by resetting an internal timer and sampling a branch current based on receiving the synchronization signal. Claim 10 delete Claim 11 A method according to claim 1, wherein the synchronization sequence number is a value generated based on a counter value accumulated according to the number of occurrences of the phase reference time. Claim 12 A computer-readable recording medium storing a program for executing the method according to claim 1 on a computer. Claim 13 A device for synchronizing the measurement time of branch measurement devices, comprising: a communication module for performing communication; a memory in which at least one program is stored; and a processor that operates by executing the at least one program; wherein the processor identifies a phase reference point in the alternating voltage of a bus bar and, based on the identification of the phase reference point, controls the communication module to transmit a synchronization signal to a plurality of branch measurement devices, and the synchronization signal includes a synchronization sequence number corresponding to the phase reference point.

Citation Information

Patent Citations

  • Apparatus for instrumentation and controlling of single-phase shunt power

    KR1020110099469A

  • Method and apparatus for synchronizing status detection in a power system

    KR102089090B1

  • Synchronized metrology in power generation and distribution networks

    US20140340236A1