Old water supply network improvement construction planning method and device based on linking of gis road information and automatic pipe network analysis
By integrating GIS road information with network analysis, the method addresses traffic and water supply challenges in aging water networks, ensuring efficient and cost-effective construction planning.
Patent Information
- Application Number
- KR1020230178725
- Authority / Receiving Office
- KR · KR
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2026-11-11
- Estimated Expiration
- 2043-12-11
AI Technical Summary
Existing construction plans for aging water supply networks lack thorough on-site surveys and technical reviews, leading to potential traffic disruptions, water cutoffs, and turbidity issues, causing inconvenience to citizens and disputes between clients and contractors.
A method and apparatus that links network analysis with GIS road information to automatically classify construction zones, consider road characteristics, and derive optimal construction plans minimizing traffic disruptions and water supply issues, using an automated network analysis system to calculate construction periods and costs.
Enables detailed construction planning that minimizes traffic disruptions and water cutoffs, reduces project costs, and facilitates smooth communication among stakeholders by providing precise construction schedules and costs, thus reducing citizen inconvenience and potential disputes.
Smart Images

Figure 112023138593558-PAT00001_ABST
Abstract
Description
Technology Field
[0001] The present invention relates to a method and apparatus for planning construction for improving aging water supply networks based on GIS road information linkage and automatic network analysis. It relates to a method for deriving results by linking road information and network analysis results when establishing a construction plan for an aging water supply and water network improvement project. More specifically, it relates to a method for deriving a construction plan that minimizes the interruption of water supply to consumers and the occurrence of turbidity while minimizing inconvenience to citizens caused by road occupation construction by inputting the construction details to be performed for each pipe in the target network and the road information above into an invented algorithm, automatically classifying construction zones considering the applicable construction, road characteristics, and feasible scope of work based on this, and analyzing the water cutoff situation for each construction zone using an automated network analysis performance and result derivation function. Background Technology
[0002] Water supply and distribution networks are one of the core infrastructures of modern society. To improve the quality of life for citizens and ensure the stable operation of businesses, continuous management and repair work must be carried out to properly maintain and renovate pipelines within the network when they deteriorate or encounter problems. Accordingly, entities responsible for water supply networks—including local governments, the central government, and corporations—are investing significant budgets to properly carry out network maintenance and renovation projects. In particular, they are striving to ensure uninterrupted water supply to urban areas with a high concentration of consumers.
[0003] To improve aging water pipelines, appropriate action plans and design proposals for each section are required. Based on project proposals derived using the expertise of professional engineers, the client and the contractor establish a construction plan. This plan includes the establishment of procedures for the entire project area, such as permits, site control, construction, and restoration, as well as detailed construction plans for each stage, including construction duration, manpower, equipment, and safety measures. Based on this plan, the client and the contractor can derive detailed construction costs, which are then used to commission and proceed with the project.
[0004] As such, construction planning is a core task that significantly impacts the entire water network improvement project; however, without detailed on-site inspections, plans must inevitably be established based on data limited to water network maps and cadastral maps, as well as past performance records. Construction plans formulated based on such data establish standardized procedures for unit distances by simply comparing pipe information from network maps with road information on maps, and calculate construction time, manpower, equipment, and costs per unit distance using existing project data and standard unit prices. However, this approach carries a high risk of issues arising regarding road information and fluctuations in water supply during the construction phase. Consequently, this can lead to problems with the construction period and costs, and become a source of disputes between the client and the contractor.
[0005] Road control and water cutoff plans act as critical variables, particularly when carrying out construction in urban areas or complex industrial zones. Regarding road control, since most pipeline networks are buried beneath roads, excavation requires occupying the road to proceed with work; however, this process disrupts traffic flow and poses safety risks, necessitating the establishment of a control plan following a thorough review prior to construction. Therefore, it is essential to coordinate public cooperation in advance and minimize inconvenience for the private sector by formulating an optimal construction plan that includes detailed road control measures. As for water cutoff plans, since pipeline improvement projects involve sequentially excavating the target pipes within the existing network, areas may inevitably become isolated from water supply or experience water cutoffs due to insufficient pressure; thus, a construction plan that takes these factors into account is required. Furthermore, as water cutoffs caused by construction may lead to turbidity due to changes in water flow direction and velocity fluctuations, engineers must also review these factors when establishing the cutoff plan.
[0006] In order to establish a construction plan for network improvement that reflects the aforementioned requirements, this institution intends to incorporate technology that links a network analysis program with road conditions at each construction site. To achieve this, an online map containing road and topographic information of the target area is required. The Korean government produces and distributes the nation's 3D topographic information as general-purpose internet maps for free, and various internet companies also distribute online maps for free. However, there is currently a lack of technology capable of establishing construction plans based on network analysis in conjunction with such GIS information.
[0007] In addition, while general-purpose programs such as EPANET can be used for network analysis, there are limitations in manpower and time because, with currently available programs, engineers must repeatedly perform network analysis for every possible construction route and water cutoff point to establish the detailed construction plan required by this institution.
[0008] As mentioned above, if a construction plan is established without thoroughly reviewing road control and water cutoff plans during the planning stage for water supply and water network improvement projects, problems such as traffic flow obstruction, water cutoff, and water turbidity may occur.
[0009] However, construction plans established at the initial stage often lack thorough on-site surveys and technical reviews due to time and cost constraints, which can pose a threat to the convenience and safety of citizens. In particular, for conduit networks passing through high-difficulty construction zones, such as urban intersections, blocking traffic flow can cause significant congestion during peak hours. Furthermore, the lack of planned safety facilities, such as lane change guides, poses a risk of major accidents. Additionally, calculating construction time and costs based on a uniform division of construction zones derived from simple conduit length extensions can lead to construction delays and disputes between the client and the contractor. This is because the actual road sections available for occupancy during construction are inconsistent, resulting in significant discrepancies from the initially established plan.
[0010] In the case of water cutoff plans, it is necessary to formulate a plan that considers the impact on citizens' water usage convenience when constructing each section derived from the aforementioned construction plan. This should not be based merely on setting construction routes for the convenience of the contractor, but should be centered on minimizing water cutoffs for consumers and suppressing the occurrence of turbidity. However, existing construction plans do not perform pipe network analysis during the review process, making it impossible to formulate a plan that minimizes water cutoffs. Furthermore, by failing to consider the direction of water flow, which may change as construction progresses, reverse flow within the pipe network may occur during construction, potentially leading to a deterioration in the quality of the supplied water.
[0011] Therefore, there is a need for technology that enables the establishment of more realistic and precise construction plans, allowing for the review of road closures and water cutoff plans even at the initial stage of the project without direct site inspections. This not only minimizes inconvenience to citizens but also assists the client and contractor implementing the water network improvement project in calculating appropriate construction periods and costs.
[0012] The technology forming the background of the present invention is disclosed in Korean Registered Patent No. 10-1205103. The problem to be solved
[0013] The present invention aims to solve the problems of the aforementioned conventional technology by providing a method and device for planning construction for the improvement of aging water supply networks, which can suppress the occurrence of civil complaints and calculate appropriate construction periods and costs by establishing a construction plan that links network analysis technology with road information at the initial stage of project planning.
[0014] In addition, the present invention aims to provide a method and apparatus for planning construction for the improvement of aging water supply networks, which establishes construction plans for pipes in each road section by utilizing general-purpose GIS information to link pipe maps and road information in the process of establishing construction plans for water supply and water network improvement projects, thereby constructing an online map layer reflecting the network and actual road information and a pipe map layer for network analysis, and overlapping and utilizing them.
[0015] Furthermore, the present invention aims to provide a method and device for planning construction for the improvement of aging water supply networks, which links network maps with road information during the planning process for water supply and water network improvement projects, inputs information such as the number of lanes and intersections of each road into a program, and enables the separate establishment of construction plans according to the characteristics of these roads.
[0016] Furthermore, the present invention aims to provide a method and device for planning construction for the improvement of aging water supply networks, which links network maps and road information during the construction planning process for water supply and water network improvement projects to automatically divide construction sections in a program considering the feasible scope of work and work continuity, and utilizes the information regarding this in the construction plan.
[0017] Furthermore, the present invention aims to provide a method and device for planning construction for the improvement of aging water supply networks, which automatically performs network analysis for all possible work sequences to establish water cutoff plans for each divided construction area linked with road information during the process of establishing construction plans for water supply and water network improvement projects, and derives an optimal construction route aimed at minimizing areas with water supply problems and minimizing the occurrence of reverse flow.
[0018] Furthermore, the present invention aims to provide a method and apparatus for planning projects to improve aging water supply networks, which enables smooth communication in advance among licensing authorities, clients, and contractors by specifying detailed construction specifications, personnel, equipment, and construction periods for each project during the planning process and facilitating the easy sharing of this information.
[0019] However, the technical problems that the embodiments of the present invention aim to solve are not limited to the technical problems described above, and other technical problems may exist. means of solving the problem
[0020] As a technical means for achieving the above-mentioned technical task, a method for planning construction for improving an aging water supply network according to one embodiment of the present invention comprises: (a) a step of inputting information for a construction plan including the coordinates of an entire construction section and information related to construction applied within the entire construction section; (b) a step of producing a network map linked with road information based on the coordinates of the entire construction section; (c) a step of dividing the construction section based on the network map produced in step (b) and deriving at least one of the construction period and cost, wherein step (b) comprises: (b1) a step of creating a network map layer by inputting information about the network subject to construction; (b2) a step of creating a map layer containing road information by linking the coordinates of the entire construction section and the network map with a coordinate system. and (b3) a step of linking the above pipe network layer and the above map layer, and setting pipe-specific aging information and applied construction on the pipe network linked with road information, and the above step (c) includes (c1) a step of setting a high-difficulty construction section within the entire construction section, wherein the high-difficulty construction section may be determined by considering the difficulty of construction at the point where the pipe network and the road overlap.
[0021] In addition, according to one embodiment of the present invention, the information related to construction applied within the pipeline network in step (a) includes the necessary construction work within the pipeline network, including at least one of replacement, repair, or disposal of the pipeline, and the manpower and equipment required for each construction work. Step (a) can set the daily workable distance and day / night construction costs for each construction work based on the input information related to construction applied within the pipeline network.
[0022] Additionally, according to one embodiment of the present invention, step (c) may include: (c2) a step of calculating the applicable construction work and the time required for each high-difficulty construction point set in step (c1); (c3) a step of calculating the applicable construction work and the time required for each construction point excluding the high-difficulty construction point set in step (c1); and (c4) a step of dividing the entire construction section into sections based on the results calculated in steps (c2) and (c3).
[0023] In addition, according to one embodiment of the present invention, step (c) may further include: (c5) a step of calculating the required time and net construction cost for the construction section divided in step (c4); and (c6) a step of deriving the total construction period and total construction cost for the entire construction section based on weather data.
[0024] In addition, according to one embodiment of the present invention, the method for planning construction for improving an aging water supply network further includes (d) a step of deriving a construction path for a divided construction section based on the results of network analysis, wherein the step (d) can derive an optimal construction path from the results of network analysis considering the construction path determined for each applied construction section.
[0025] Additionally, according to one embodiment of the present invention, the step (d) may include: (d1) a step of setting sections by type of construction, in which the divided construction section is separated by type of construction; (d2) a step of repeatedly performing a pipe network analysis on a construction path that can be set according to the section by type of construction; and (d3) a step of deriving an optimal construction path in which the occurrence of reverse flow and the area where water supply problems occur are minimized from the pipe network analysis result of the step (d2).
[0026] In addition, according to one embodiment of the present invention, step (d2) calculates a section that can be continuously worked on according to the applied construction from the section for each type of work, calculates all possible construction paths based on the continuously workable section, and then repeatedly performs pipe network analysis for each construction path and records the results, and step (d3) can derive an optimal construction path by analyzing the results according to criteria set to minimize areas where water supply problems occur and reverse flow.
[0027] In addition, according to one embodiment of the present invention, the method for planning construction for improving an aging water supply network further includes the step of (e) deriving a construction plan report for the entire construction section, wherein the step (e) may include: (e1) deriving a detailed construction plan for each construction section divided in the step (c); (e2) calculating a work schedule and road occupancy plan for each construction section based on the optimal construction route derived in the step (d); and (e3) calculating a total construction schedule and total cost for the entire construction section.
[0028] In addition, an aging water supply network improvement construction planning device according to one embodiment of the present invention may include: an input unit provided for inputting information for a construction plan including the coordinates of the entire construction section and information related to construction applied within the entire construction section; a network map production unit that produces a network map linked with road information based on the coordinates of the entire construction section; a construction section calculation unit that divides the construction section based on the network map produced by the network map production unit and derives at least one of the construction period and cost; a construction path derivation unit that derives a construction path for the divided construction section based on the network analysis results; and a construction plan report derivation unit that derives a construction plan report for the entire construction section.
[0029] The means for solving the problem described above are merely exemplary and should not be interpreted as intended to limit the present invention. In addition to the exemplary embodiments described above, additional embodiments may exist in the drawings and the detailed description of the invention. Effects of the invention
[0030] According to the aforementioned means for solving the problem of the present institution, the institution can review detailed construction plans that require analysis based on existing long-term field surveys at the initial stage of the project. Through this, it is possible to classify the construction work to be performed for each pipe within the network and proactively consider locations with high construction difficulty and sensitivity to traffic flow, such as intersection sections. This goes beyond merely establishing detailed construction plans; by assisting in the derivation of appropriate construction costs, it can contribute to curbing disputes over construction time and costs between the client and the contractor, as well as preventing government budget waste caused by lax project planning.
[0031] In addition, by establishing construction routes and schedules based on network analysis results in comparison with existing water supply and water network improvement construction plans, the Institute can minimize the occurrence of water supply problem areas and turbidity that may arise during the construction process, thereby minimizing inconvenience to citizens caused by the construction.
[0032] Furthermore, when establishing construction plans for water supply and pipeline network improvement projects, this institution allows for the overlaying of a pipeline network layer generated by a pipeline analysis program with a map layer containing road information. Accordingly, it provides a function that enables the intuitive review of construction methods for each pipeline in conjunction with road information.
[0033] In addition, when establishing plans for water supply and water network improvement projects, this institution provides a function that allows for the input or setting of information on high-difficulty work sections, such as road lanes and intersections, for each target pipe, and enables the calculation of construction schedules and costs based on their construction characteristics.
[0034] In addition, when establishing plans for water supply and water network improvement projects, this institution automatically divides construction sections by classifying the work to be performed by pipe, linking pipe characteristics with road information, and considering the feasible scope of work and work continuity, and provides this information to the user.
[0035] Furthermore, this institution provides a function capable of automatically performing network analysis on all possible work sequences to establish water cutoff plans for each divided construction zone when planning water supply and pipeline network improvement projects, and deriving an optimal construction route that minimizes isolated water supply zones and reverse flow.
[0036] Furthermore, when establishing plans for water supply and pipeline network improvement projects, this institution provides a function that enables smooth communication in advance among licensing authorities, clients, and contractors by specifying detailed construction specifications, personnel, equipment, and construction periods for each project area and facilitating the easy sharing of this information.
[0037] Furthermore, this institution provides the effect of reducing the manpower and costs required for establishing construction plans by automating a significant portion of tasks related to project duration and cost estimation when planning water supply and pipeline network improvement projects.
[0038] However, the effects achieved by the embodiments of the present invention are not limited to the technical problems described above, and other effects may exist. Brief explanation of the drawing
[0039] FIG. 1 is a schematic flowchart of a method (S) for planning construction to improve an aging water supply network according to one embodiment of the present invention. FIG. 2 is a schematic diagram illustrating that aging information attributes for each pipeline are input on a pipeline network map linked with road information according to one embodiment of the present invention. FIG. 3 is a flowchart illustrating the procedure for performing automatic pipe network analysis to find the optimal construction path according to one embodiment of the present invention. FIG. 4 is an exemplary drawing of a construction plan report for each construction section derived according to one embodiment of the present invention. FIG. 5 is a schematic block diagram of an aging water supply network improvement construction planning device (500) according to one embodiment of the present invention. Specific details for implementing the invention
[0040] Embodiments of the present invention are described below with reference to the attached drawings to enable those skilled in the art to easily implement the invention. However, the present invention may be embodied in various different forms and is not limited to the embodiments described herein. Furthermore, in order to clearly explain the present invention in the drawings, parts unrelated to the explanation have been omitted, and similar parts throughout the specification are denoted by similar reference numerals.
[0041] Throughout the entire specification, when a part is described as being "connected" to another part, this includes not only cases where they are "directly connected," but also cases where they are "indirectly connected" with other components in between, or "electrically connected" with other elements in between.
[0042] Throughout the entire specification, when a component is described as being located "on," "on top," "on top," "under," "on bottom," or "on bottom" of another component, this includes not only cases where the component is in contact with the other component but also cases where another component exists between the two components.
[0043] Throughout this specification, when a part is described as "comprising" a certain component, this means that, unless specifically stated otherwise, it does not exclude other components but may include additional components.
[0044] Terms such as "First~" and "Second~" may be used to indicate the same or substantially identical compositions in a different order, and may be interpreted as substantially the same composition as one that does not indicate "First", "Second", etc.
[0045] In addition, terms related to direction or position (upper side, upper surface, lower side, etc.) in the description of the embodiments of the present invention are established based on the arrangement state of each component shown in the drawings.
[0046] Hereinafter, with reference to FIGS. 1 to 5, a method (S) for planning construction for improving an aging water supply network according to one embodiment of the present invention will be described. The method (S) for planning construction for improving an aging water supply network can be performed by an aging water supply network improvement planning device (500) described later, based on GIS road information linkage and automatic network analysis. In the process of the aging water supply network improvement project, measures are established to maintain smooth and safe traffic flow during construction by considering the road conditions at each construction site, and measures are presented to suppress water cutoff areas and turbidity that may occur depending on the work conditions of each pipe, thereby minimizing complaints and enabling efficient project implementation.
[0047] The method (S) for planning construction for improving aging water supply networks of the present invention enables the review and establishment of construction plans by linking road information and network analysis when improving aging water supply networks in urban areas with complex road conditions and water supply networks in complex factories. Compared to the conventional method of calculating construction plans based on the length of pipes relying on network maps, the method (S) for planning construction for improving aging water supply networks can help establish more practical construction plans by considering road conditions at the construction site and water supply issues based on GIS road information and network analysis results.
[0048] Referring to FIG. 1, a method (S) for planning construction for improving an aging water supply network according to one embodiment of the present invention can be performed by an aging water supply network improvement construction planning device (500) and may include the steps of: inputting basic information required for establishing a construction plan (S10); producing a network map linked with GIS road information (S20); dividing construction sections based on a detailed network map linked with GIS road information and deriving appropriate construction time and cost (S30); deriving a work schedule optimized for water supply and turbidity suppression for the divided construction sections based on network analysis results (S40); and deriving a construction plan report that integrates all secured information (S50).
[0049] Step S10 can be performed by the input unit (510) of the aging water supply network improvement construction planning device (500) described later, and can receive basic information for the construction plan. The basic information for the construction plan may include the coordinates of the entire construction section and information related to the construction applied within the entire construction section.
[0050] At this time, information related to construction applied within the above network may include necessary construction work within the network, including at least one of replacement, repair, or disposal of the pipeline, and manpower and equipment required for each construction work. In step S10, based on the input information related to construction applied within the network, the daily workable distance and day / night construction costs for each construction work may be set. Step S10 may include a step of securing the coordinates of the entire construction section (S11), a step of receiving information related to construction applied within the network (S12), and a step of setting information such as manpower and equipment required for construction applied within the network (S13).
[0051] In step S11, GIS coordinates for reference points of the aging water network improvement project, which is the subject of the project, can be secured and received. For example, serial numbers may be assigned to the pipes forming the network, and upstream and downstream nodes of the pipes may be designated; in step S11, information on these pipes can be input or transmitted, and reference points can be established. For example, a reference point may be the first pipe to be subjected to construction within the entire construction section of the water network improvement project, or a field office established for the construction to improve the water network, and reference points may also be established through other methods.
[0052] In one embodiment, the reference point of the aging water network improvement project may be set as a point on the road, taking into consideration the ease of linkage with a map layer including road information described below.
[0053] In step S12, the types of construction work required within the pipeline network subject to improvement projects, such as pipeline replacement, repair, or disposal, can be classified. Additionally, in step S12, the manpower and equipment required for each construction work can be input.
[0054] In step S13, based on information related to construction applied within the input network, the daily workable distance and day / night construction costs for each applied construction can be set.
[0055] The information for the construction plan received or transmitted in step S10 may be transmitted from files, databases, etc., containing information regarding the aging water network improvement project, or may be selectively received through a designated input program. However, the input of information for the construction plan by a user in step S10 is not excluded.
[0056] In addition, at stage S10, the necessary construction work within the network may be determined from a database storing accident rates, leakage rates, and complaint rates for the network, evaluation factors for selecting priorities for maintenance and improvement projects, and hydraulic or water quality information of the pipelines forming the network.
[0057] Step S20 can be performed by the network map production unit (520), and a network map linked with road information can be produced based on the coordinates of the entire construction section. As described below, the method (S) for planning construction to improve an aging water supply network of the present invention sets up a high-difficulty construction section within the network to be constructed, such as an intersection in an urban area, where blocking the direction of traffic flow can cause significant congestion during times of high traffic volume, and where construction safety facilities are not fully planned, which can lead to a major accident.
[0058] It is impossible to determine whether a specific construction section is difficult by referring only to conventional network maps. In the case of the present invention, the difficulty of construction in a construction section can be graded by considering road information by overlapping a network map layer with a map layer containing road information, and based on this, a high-difficulty construction section can be set. Step S20 may include a step of creating a network map layer (S21), a step of creating a map layer containing road information (S2), and a step of linking the network map layer and the map layer (S23).
[0059] In step S21, a pipe network map layer can be created by inputting information about the pipe network subject to construction. In step S21, a pipe network map can be produced on the pipe network analysis program for construction execution by inputting basic information about the pipe network map subject to construction. The basic information about the pipe network map may include information such as the serial number (pipeline number) of the pipe, upstream and downstream nodes of the pipe, pipe length, and pipe.
[0060] In step S22, a map layer containing road information can be created by linking the coordinates of the entire construction section with the coordinate system of the above-mentioned network map. More specifically, a GIS map layer containing road information can be created by linking the coordinate system of the GIS reference point set in step S11 with the reference point of the network map of the network analysis program.
[0061] In step S23, the pipe network layer and the map layer are linked, and aging information and construction work to be applied for each pipe can be set on the pipe network linked with road information. As shown in FIG. 2, the pipe network (N) and the map layer (M) can be linked and displayed overlaid, and through this, it is possible to identify how the roads are formed in correspondence with the pipe network. In addition, aging information attributes for each pipe can be entered on the pipe network, and construction work to be applied for each pipe can be set.
[0062] In one embodiment, when linking a map layer containing road information, traffic information including average traffic volume over time, along with the shape of the road, may also be linked. Pipelines forming a network in an urban environment are typically buried under roads, and construction work on the pipelines may involve traffic control. That is, in one embodiment of the present invention, when dividing the construction section and calculating the construction period and cost, it can be understood that a pipeline map linked with road information that considers traffic information, such as traffic volume, is applied.
[0063] Referring again to FIG. 1, step S30 can be performed by the construction section calculation unit (530), and the construction section can be divided and the construction period and cost can be derived based on the pipe network map produced in step S20. In S30, the construction section can be divided by inputting road conditions in more detail. At this time, the division of the construction section can be performed based on the pipe network map linked with road information, by classifying the difficulty of the construction to set a high-difficulty construction section, and based on the high-difficulty construction section. Step S30 may include a step of setting high-difficulty construction sections within the entire construction section (S31), a step of calculating the applicable construction and required time for each high-difficulty construction point (S32), a step of calculating the applicable construction and required time for each point excluding the high-difficulty construction point (S33), and a step of dividing the entire construction section into construction sections (S34); additionally, it may include a step of calculating the required time and net construction cost for the divided construction sections (S35) and a step of deriving the total construction period and total construction cost for the entire construction section based on weather data (S36).
[0064] In Step S31, high-difficulty construction zones can be established within the entire construction section, such as intersection points within the road network. As described above, high-difficulty construction zones can be designated as points with high construction difficulty and sensitivity to traffic flow, such as intersections or sections with high traffic volume during specific construction periods. More specifically, high-difficulty construction zones can be designated as sections where there is a risk of causing significant congestion during peak traffic hours by blocking the direction of traffic flow during construction, or where a major accident could result if construction safety facilities, such as lane change guidance lines, are not planned properly.
[0065] In step S32, the applicable construction work and required time can be calculated for each high-difficulty construction site set in step S31.
[0066] In step S33, the applicable construction work and required time can be calculated for each construction site, excluding the high-difficulty construction sites set in step S31. It can be understood that the calculation of the applicable construction work and required time is based on the information entered in steps S12 and S13.
[0067] In step S34, the results calculated in steps S32 and S33 can be integrated to divide the entire section into construction zones based on criteria such as applicable construction, work difficulty, and daily work distance. The construction zones may be divided according to the applicable construction performed on the pipeline, or by work difficulty by separating high-difficulty and low-difficulty construction zones, or further divided based on the daily work distance that allows for continuous operation.
[0068] In addition, the construction section may be divided by combining two or more of the aforementioned criteria. That is, the entire construction section may first be divided according to work difficulty, and then further divided according to applicable construction; or the daily construction section may be divided according to the daily workable distance for each work difficulty. Furthermore, after dividing the entire construction section according to work difficulty and applicable construction, it may be divided according to the daily workable distance. In step S34, the construction section may also be divided using criteria other than those described above.
[0069] In step S35, the required time and net construction cost for the divided construction sections can be calculated. In step S35, the required time and net construction cost for all divided construction sections can be calculated. Here, net construction cost can be understood as the sum of material costs, labor costs, and expenses.
[0070] In step S36, the total construction period and total construction cost for the entire construction section can be derived based on weather data. The total construction period can be calculated as an appropriate value by reflecting non-working days and a safety factor based on weather data, and the total construction cost can be calculated by additionally considering indirect costs, etc., to the calculated total construction period.
[0071] Step S40 can be performed by the construction path derivation unit (540), and can derive an optimal construction path for the divided construction section and the entire construction section based on the pipe network analysis results. That is, Step S40 can be understood as a step of deriving a work schedule for the divided construction section in conjunction with road information based on the pipe network analysis results.
[0072] Step S40 can derive an optimal construction path from the results of a pipe network analysis that considers the construction path determined for each applied construction project for the divided construction section. Pipe network analysis involves calculating the supplyable flow rate, demand flow rate, water pressure, etc. at the nodes by analyzing the flow rate of the fluid flowing through each pipe, and can be performed through a pipe network analysis system that simulates fluid flow. Such pipe network analysis can be performed using known methods such as Demand Driven Analysis (DDA) and Pressure Demand Analysis (PDA) techniques. Step S40 may include a step of setting sections by type of work by separating the divided construction section according to the applied construction project (S41), a step of repeatedly performing pipe network analysis on the construction paths that can be set according to the sections by type of work (S42), and a step of deriving an optimal construction path (S43).
[0073] In step S41, work-type sections can be established by separating the divided construction sections according to the applicable construction work. For example, the construction sections divided in step S34 can be separated according to the types of work applied to the sections. In other words, this can be understood as establishing work-type sections by further separating the divided construction sections according to applicable construction work, such as pipeline replacement, repair, or disposal. That is to say, by separating the divided construction sections according to the applicable construction work, work-type sections capable of continuous operation within the divided construction sections can be obtained.
[0074] Here, the division of the construction section in step S34 is performed based on the determination of whether the work is highly difficult in relation to the road information identified in step S31, and the applicable work and required time calculated in steps S32 and S33. In other words, the construction section divided in step S34 is determined by considering the classification of work to be performed by pipe, the feasible daily work range based on pipe characteristics, and the presence of highly difficult work in relation to the road information. By separating the construction section thus divided into sections by work type, sections by work type can be established that consider the feasible daily work range linked to road information and work continuity.
[0075] Step S42 allows for the iterative performance of network analysis on construction paths that can be set according to sections for each construction type. In this case, network analysis can be performed iteratively on all possible construction paths with priority given to the applicable construction. Through Step S42, network analysis can be automatically performed on all possible work sequences to establish water cutoff plans for each divided construction zone when planning water supply and network improvement projects. Furthermore, in Step S43 described later, an optimal construction path can be derived to achieve the minimization of isolated water supply zones and reverse flow.
[0076] Referring to FIG. 3, which is a flowchart illustrating the procedure for performing automatic network analysis to find the optimal construction route according to one embodiment of the present invention, in step S41, the construction section is divided according to the applicable construction (division of sections by type of work), and in step S42, the section where work can be performed continuously according to the applicable construction can be calculated from the section by type of work (S421). Subsequently, all possible construction routes can be calculated based on the section where work can be performed continuously according to the applicable construction (S422). Once the construction route is calculated, network analysis simulations are repeatedly performed for all construction routes (possible routes for construction) (S423), and the results of the analysis can be recorded along with the settings of the network analysis (S424).
[0077] In this case, the construction route can be understood as a chronological arrangement of the sections where the applied construction is performed, and the sections where construction is carried out can be understood as sections where water supply is interrupted.
[0078] In one embodiment, in step S42, network analysis can be performed on possible construction paths with priority given to the applied construction work. In step S42, network analysis is performed on all possible construction paths, but network analysis can be performed by setting construction paths for each applied construction work. For example, network analysis can be performed by calculating construction paths for each applied construction work that replaces a pipeline, an applied construction work that repairs a pipeline, or an applied construction work that decommissions a pipeline. As described above, the applied construction work serves as a criterion for separating the divided construction sections into sections by type of work, and since sections where continuous work is possible are set based on sections by type of work, it can be understood that in step S42, construction paths are calculated and network analysis is performed with priority given to sections where continuous work is practically possible.
[0079] In addition, in other embodiments, priority may be based on other priorities, such as the number of beneficiary customers resulting from the improvement of pipeline performance, project reliability based on the selection of maintenance and improvement projects, and construction costs associated with maintenance and improvement projects.
[0080] In Step S43, the optimal construction route can be derived from the network analysis results of Step S42 to minimize areas where water supply problems occur and reverse flow. Specifically, in Step S43, the optimal construction route can be derived by analyzing the above execution results according to established criteria to minimize areas where water supply problems occur and reverse flow.
[0081] Referring to Fig. 3, in step S43, the results of the pipe network analysis performed on the configurable construction path calculated based on the workable section in step S42 can be analyzed (S431). At this time, the analysis of the pipe network analysis results can be performed according to criteria set to calculate the optimal construction path, for example, input variable factors. The criteria set to calculate the optimal construction path may include the appropriate pressure range of the consumer, the reverse flow coefficient, and the number of construction sections. The appropriate pressure range of the consumer can be understood as the water pressure range at the consumer using water, and the reverse flow coefficient can be understood as a coefficient related to the occurrence of reverse flow caused by construction. In addition, the number of construction sections can be understood as the number of sections where continuous construction is possible during road construction. Based on such analysis of the pipe network analysis results, an optimal construction path can be derived to minimize areas where water supply problems occur and the occurrence of reverse flow (S432).
[0082] Step S50 can be performed by the construction plan report derivation unit (550), and can derive a construction plan report for the entire construction section by integrating all information obtained in steps S10 to S40. By deriving an integrated construction plan report for the entire construction section, when establishing a construction plan for water supply and water network improvement, detailed construction details, manpower, equipment, and construction period for each construction area can be specified, and by easily sharing this information, government agencies related to licensing, the client, and the construction company can communicate smoothly in advance.
[0083] First, a detailed construction plan can be derived for each divided construction section derived in step S30 (S51). In step S51, a detailed construction plan including the construction period, manpower, and equipment plan for each construction section can be derived.
[0084] Subsequently, the work schedule and road occupancy plan for each construction section can be calculated (S52). In step S52, the work schedule and road occupancy plan for each construction section can be calculated based on the construction route derived in step S40. The work schedule and road occupancy plan for each construction section calculated in this way can be displayed in conjunction with road information as shown in Fig. 4, and the detailed construction plan calculated in step S51 can also be displayed on a view map linked with road information.
[0085] Finally, all information from steps S10 to S40 can be integrated to calculate the total construction schedule and total cost for the entire construction section (S53).
[0086] A method (S) for planning construction to improve an aging water supply network according to one embodiment of the present invention may be implemented in the form of program instructions that can be executed through various computer means and recorded on a computer-readable medium. The computer-readable medium may include program instructions, data files, data structures, etc., either individually or in combination. The program instructions recorded on the medium may be those specifically designed and configured for the present invention, or those known and available to those skilled in the art of computer software. Examples of computer-readable recording media include magnetic media such as hard disks, floppy disks, and magnetic tapes; optical recording media such as CD-ROMs and DVDs; magneto-optical media such as floptical disks; and hardware devices specifically configured to store and execute program instructions, such as ROM, RAM, and flash memory. Examples of program instructions include machine code, such as that generated by a compiler, as well as high-level language code that can be executed by a computer using an interpreter, etc. The above-described hardware device may be configured to operate with one or more software modules to perform the operation of the present invention, and vice versa.
[0087] In addition, the aforementioned method for planning construction to improve an aging water supply network (S) can also be implemented in the form of a computer program or application executed by a computer stored on a recording medium.
[0088] In the foregoing description, each step may be further divided into additional steps or combined into fewer steps, depending on the embodiment of the present invention. Additionally, some steps may be omitted as necessary, the order of steps may be changed, or steps may be performed simultaneously.
[0089] Meanwhile, below, an aging water supply network improvement construction planning device (500) according to one embodiment of the present invention will be described. However, since the aging water supply network improvement construction planning device (500) is an invention that includes the same or corresponding technical features as the aging water supply network improvement construction planning method (S) described above, differing only in category, the same reference numerals will be used for configurations that are identical or similar to the configuration described above, and redundant descriptions will be simplified or omitted.
[0090] Referring to FIG. 5, the aging water supply network improvement construction planning device (500) may include an input unit (510), a network map production unit (520), a construction section calculation unit (530), a construction path derivation unit (540), and a construction plan report derivation unit (550).
[0091] The input unit (510) may be provided to input information for a construction plan, including the coordinates of the entire construction section and information related to the construction applied within the entire construction section, by user input. The information related to the construction may include the necessary applied construction within the pipe network, which includes at least one of the replacement, repair, or disposal of the pipes, and the manpower and equipment required for each applied construction. Additionally, the input unit (510) may set the daily workable distance and day / night construction costs for each applied construction based on the input information related to the construction applied within the pipe network. The input unit (510) can be understood as a configuration that performs a process corresponding to step S10.
[0092] The pipe network map production unit (520) can be understood as a configuration that produces a pipe network map linked with road information based on the coordinates of the entire construction section. The pipe network map production unit (520) can create a pipe network map layer by inputting information about the pipe network subject to construction, and can create a map layer containing road information by linking the coordinates of the entire construction section with the coordinate system of the pipe network map. In addition, the pipe network map production unit (520) can link the pipe network map layer and the map layer, and provide for setting aging information and applied construction for each pipe on the pipe network map linked with road information. The pipe network map production unit (520) can be understood as a configuration that performs a process corresponding to step S20.
[0093] The construction section calculation unit (530) may be configured to divide the construction section based on the pipe network map produced by the pipe network map production unit and to derive at least one of the construction period and cost. The construction section calculation unit (530) may determine the high-difficulty construction section by considering the difficulty of construction at the point where the pipe network and the road overlap. In addition, the construction section calculation unit (530) may calculate the applicable construction and required time for each construction point excluding the set high-difficulty construction point and / or the high-difficulty construction point, and divide the construction section for the entire construction section.
[0094] Furthermore, the construction section calculation unit (530) can calculate the time required and net construction cost for the divided construction section, and derive the total construction period and total construction cost for the entire construction section based on weather data. The construction section calculation unit (530) can be understood as a configuration that performs a process corresponding to step S30.
[0095] The construction path derivation unit (540) can derive a construction path for a divided construction section based on the pipe network analysis results. The construction path derivation unit (540) can derive an optimal construction path from the pipe network analysis results considering the construction path determined for each applied construction section for the divided construction section.
[0096] In one embodiment, the construction path derivation unit (540) sets sections by type of construction by separating the divided construction sections according to the applied construction, and can repeatedly perform pipe network analysis on the construction paths that can be set according to the sections by type of construction. Then, from the results of the pipe network analysis, it can derive an optimal construction path in which the occurrence of reverse flow and the areas where water supply problems occur are minimized. The construction path derivation unit (540) can be understood as a configuration that performs a process corresponding to step S40.
[0097] The construction plan report derivation unit (550) can derive a construction plan report for the entire construction section. The construction plan report derivation unit (550) derives a detailed construction plan for each construction section divided by the construction section calculation unit (530), and calculates the work schedule and road occupancy plan for each construction section based on the optimal construction route derived from the construction route derivation unit (540), and can display them as shown in FIG. 4. Furthermore, the construction plan report derivation unit (550) calculates the total construction schedule and total cost for the entire construction section, specifies the detailed construction details, manpower, equipment, and construction period for each construction area, and enables the permit-related government agency, the client, and the construction company to communicate smoothly in advance by easily sharing this information. The construction plan report derivation unit (550) can be understood as a component that performs a process corresponding to step S50.
[0098] The foregoing description of the present invention is for illustrative purposes only, and those skilled in the art will understand that other specific forms can be easily modified without altering the technical concept or essential features of the present invention. Therefore, the embodiments described above should be understood as illustrative in all respects and not restrictive. For example, each component described as a single unit may be implemented in a distributed manner, and components described as distributed may likewise be implemented in a combined form.
[0099] The scope of the present invention is defined by the claims set forth below rather than by the detailed description above, and all modifications or variations derived from the meaning and scope of the claims and the concept of equivalents thereof should be interpreted as being included within the scope of the present invention. Explanation of the symbols
[0100] 500: Aging Water Supply Network Improvement Construction Planning Device 510: Input section 520: Observation Map Production Department 530: Construction Section Calculation Section 540: Construction Route Derivation Section 550: Construction Plan Report Derivation Section S: Method for Planning Construction to Improve Aging Water Supply Networks
Claims
Claim 1 A method for planning construction for improving an aging water supply network, performed by a device for planning construction for improving an aging water supply network, comprises: (a) a step of inputting information for a construction plan including the coordinates of the entire construction section and information related to construction applied within the entire construction section; (b) a step of producing a network map linked with road information based on the coordinates of the entire construction section; (c) a step of dividing the construction section based on the network map produced in step (b) and deriving at least one of the construction period and cost; and (d) a step of deriving a construction path for the divided construction section based on the results of network analysis, wherein step (b) comprises: (b1) a step of creating a network map layer by inputting information about the network subject to construction; (b2) a step of creating a map layer containing road information by linking the coordinates of the entire construction section and the network map with a coordinate system. and (b3) a step of linking the above-mentioned pipe network layer and the above-mentioned map layer, and setting aging information and applicable construction work for each pipe on the pipe network linked with road information, wherein step (c) includes: (c1) a step of setting a high-difficulty construction section within the entire construction section; (c2) a step of calculating applicable construction work and required time for each high-difficulty construction point set in step (c1); (c3) a step of calculating applicable construction work and required time for each construction point excluding the high-difficulty construction point set in step (c1); and (c4) a step of dividing the entire construction section into construction sections based on the results calculated in steps (c2) and (c3), wherein the high-difficulty construction section is determined by considering the difficulty of construction at the point where the pipe network and the road overlap, and step (d) is a method of deriving an optimal construction path from the pipe network analysis results considering the construction path determined for each applicable construction section of the divided construction section. Claim 2 A method for planning construction to improve an aging water supply network, wherein, in claim 1, the information related to construction applied within the entire construction section of step (a) includes the necessary applied construction within the entire construction section, including at least one of the replacement, repair, or disposal of pipelines, and the manpower and equipment required for each applied construction, and step (a) sets the daily workable distance and day / night construction costs for each applied construction based on the input information related to construction applied within the entire construction section. Claim 3 delete Claim 4 A method for planning construction to improve an aging water supply network, wherein, in claim 1, step (c) further comprises: (c5) a step of calculating the required time and net construction cost for the construction section divided in step (c4); and (c6) a step of deriving the total construction period and total construction cost for the entire construction section based on weather data. Claim 5 delete Claim 6 A method for planning construction to improve an aging water supply network, wherein the step (d) comprises: (d1) a step of setting sections by type of work by separating the divided construction sections according to the applicable construction; (d2) a step of repeatedly performing network analysis on construction paths that can be set according to the sections by type of work; and (d3) a step of deriving an optimal construction path from the results of the network analysis of the step (d2) in which the occurrence of reverse flow and the area where water supply problems occur are minimized. Claim 7 In claim 6, the above step (d2) calculates a section that can be continuously worked on according to the applied construction from the above section for each type of work, calculates all possible construction paths based on the above section that can be continuously worked on, and then repeatedly performs network analysis for each of the above construction paths and records the results, and the above step (d3) derives an optimal construction path by analyzing the results according to criteria set to minimize the occurrence of reverse flow and areas where water supply problems occur. Claim 8 In claim 1, the method for planning construction for improving an aging water supply network further comprises the step of (e) deriving a construction plan report for the entire construction section, wherein the step (e) comprises: (e1) deriving a detailed construction plan for each construction section divided in the step (c); (e2) calculating a work schedule and road occupancy plan for each construction section based on the optimal construction route derived in the step (d); and (e3) calculating a total construction schedule and total cost for the entire construction section. Claim 9 As a construction planning device for improving an aging water supply network, the device comprises: an input unit provided for inputting information for a construction plan including the coordinates of the entire construction section and information related to construction applied within the entire construction section; a network map production unit that produces a network map linked to road information based on the coordinates of the entire construction section; a construction section calculation unit that divides the construction section based on the network map produced by the network map production unit and derives at least one of the construction period and cost; and a construction path derivation unit that derives a construction path for the divided construction section based on the results of network analysis. It includes a construction plan report derivation unit that derives a construction plan report for the entire construction section, and the pipe network map production unit is provided to create a pipe network map layer by inputting information about the pipe network subject to construction, create a map layer containing road information by linking the coordinates of the entire construction section with the pipe network map and coordinate system, link the pipe network map layer with the map layer, and set pipe-specific aging information and applicable construction on the pipe network map linked with road information, and the construction section calculation unit is provided to set high-difficulty construction sections within the entire construction section, calculate applicable construction and required time for each set high-difficulty construction point, calculate applicable construction and required time for each construction point excluding the set high-difficulty construction point, and divide the entire construction section into construction sections based on the results of calculating applicable construction and required time for each set high-difficulty construction point and the results of calculating applicable construction and required time for each construction point excluding the set high-difficulty construction point, and the high-difficulty construction section is provided to consider the difficulty of construction at the point where the pipe network and the road overlap. An aging water supply network improvement construction planning device, wherein the above-mentioned construction route derivation unit is determined and provided to derive an optimal construction route from the results of a network analysis considering the construction route determined for each applied construction section of the above-mentioned divided construction section.
Citation Information