Construction system and method and connection system therefor

The connection system using engagement members in dynamic equilibrium addresses the challenges of erecting multi-story buildings by enabling fastenerless assembly of lightweight materials, enhancing construction efficiency and safety.

US20260357569A1Pending Publication Date: 2026-11-12PARKD LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
US19/475197
Authority / Receiving Office
US · United States
Patent Type
Applications(United States)
Current Assignee / Owner
Priority Date
2023-04-14
Filing Date
2024-04-12
Publication Date
2026-11-12

AI Technical Summary

Technical Problem

Erecting multi-story building structures is cumbersome and time-consuming due to the assembly of heavy materials and the need for large numbers of construction workers, particularly in constructing floor structures that require fastener-based connections.

Method used

A connection system using engagement members that achieve dynamic equilibrium through fastenerless engagements, allowing for the assembly of lightweight materials that can sustain large loads, facilitating the construction of floor structures with reduced labor and time.

Benefits of technology

The system enables swift assembly of floor structures with increased strength over time, reducing the need for construction workers and equipment, while ensuring safety and efficiency in building construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure US20260357569A1-D00000_ABST
    Figure US20260357569A1-D00000_ABST
Patent Text Reader

Abstract

A support bracket (46) (engagement member) engageable at an end (38) of a panel (42) to support a panel structure (34) on beams (30a, 30b), without requiring fastening the support bracket to the panel or to the beam, for structural / permanent formwork, such as prior to pouring concrete onto the panel structure, for a composite floor. The support bracket (46) can have a slot (66) to slidingly receive a portion of the end of the panel. A lift arrangement (90) can connect to a number of the support brackets at each end of the panel structure. The bracket (46) can include a receiver (73) for engagement with a connection member (81). The connection member (81) can include an elongate member e.g. metal rod / bar. A retainer (83) can engage onto a respective end of the connection member (81) and can be locked to the adjacent bracket (46) by a locking means (85).
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present invention relates to building systems and method for their construction.

[0002] Embodiments of the present invention has been devised particularly, although not necessarily solely, in relation to a building system and method, in particular to engagement members for use in the construction of flooring for building structures, such as composite steel-concrete floor structures having permanent metal formwork supporting concrete.BACKGROUND

[0003] The following discussion of the background art is intended to facilitate an understanding of the present invention only. The discussion is not an acknowledgement or admission that any of the material referred to is or was part of the common general knowledge as at the priority date of the application.

[0004] Erecting multi-story building structure is a relatively cumbersome and time-consuming exercise, thus increasing the costs for erecting these particular building structures. This is particularly true due to the fact that a plurality of relatively heavy building materials is needed to be assembled together with the help of heavy machinery such as cranes and concrete trucks having concrete placing booms. Also, a relatively large number of construction workers are needed for assembly of, for example, the floor and wall structures.

[0005] In particular, in conventional building structures (for example, the ones that are typically used as parking facilities and thus capable of sustaining relatively large loads) the floor structures may be defined by floor panels spanning between a plurality of hollow core planks (defining the support beams) joined together to create a support structure onto which a concrete mixture will be poured on for defining the floor structures.

[0006] Installation of the floor panels (spanning between the support beams) to define the support structures currently requires a relatively large number of constructions workers and is a cumbersome and time-consuming exercise.

[0007] It is against this background that the present invention has been developed.SUMMARY OF INVENTION

[0008] According to a first aspect of the invention there is provided a connection system for connecting a construction element to a supporting construction element, the connection system comprising at least one engagement member configured for defining a fastenerless engagement with the supporting construction element and / or the construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the supporting construction element and / or construction element through the fastenerless engagement.

[0009] Preferably, the engagement member comprises a first end for engagement to the supporting construction element and a second end for engaging the construction element, the first end being configured for engagement to the supporting construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the supporting construction element through a fastenerless engagement, the second end being configured for engagement to the construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the construction element through a fastenerless engagement.

[0010] Preferably, the engagement member comprises a body comprising a lower bar assembly and an upper bar assembly, the upper bar assembly, when attached to the lower bar assembly, defining an engaging unit adapted to receive a first end portion of the construction element.

[0011] Preferably, the upper bar assembly comprises one first bar, and the lower bar assembly comprises a plurality of spaced apart bars partially fixed to the first bar to form spacing between the first bar and the plurality of spaced apart bars defining a first slot in the engaging unit at a receiving end for engaging at least partially an end of the construction element engaging with the engagement member.

[0012] Preferably, the lower and upper bar assemblies are attached to each other via a fixing system, the fixing system being located between the first end and the second end of the engagement members. complete penetration butt weld.

[0013] Preferably, the first end of the engagement member comprises a second slot for receiving a shim.

[0014] In an alternative arrangement, the engaging unit comprises a finger element mounted to the lower bar assembly and partially fixed to the lower bar assembly to form a spacing between the finger element and the lower bar defining a slot for engagement at least partially to a portion of the end of the panel engaging with the engagement member.

[0015] In this alternative arrangement, the lower bar assembly comprises a plurality of bars spaced apart with respect to each other via one or more spacing bars, each bar of the lower bar assembly comprising an engaging unit attached thereto.

[0016] According to a second aspect of the invention there is provided an engagement member configured for engagement to a supporting construction element and / or a construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the supporting construction element and / or the construction element through a fastenerless engagement.

[0017] Preferably, the engagement member comprises a first end for engagement to the supporting construction element and a second end for engaging the construction element, the first end being configured for engagement to the supporting construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the supporting construction element through a fastenerless engagement, the second end being configured for engagement to the construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the construction element through a fastenerless engagement.

[0018] Preferably, the engagement member comprises a body comprising a lower bar assembly and an upper bar assembly, the upper bar assembly, when attached to the lower bar assembly, defining an engaging unit adapted to receive a first end portion of the construction element.

[0019] Preferably, the upper bar assembly comprises one first bar, and the lower bar assembly comprises a plurality of spaced apart bars partially fixed to the first bar to form spacing between the first bar and the plurality of spaced apart bars defining a first slot in the engaging unit at a receiving end for engaging at least partially an end of the construction element engaging with the engagement member.

[0020] Preferably, the lower and upper bar assemblies are attached to each other via a fixing system, the fixing system being located between the first end and the second end of the engagement member.

[0021] Preferably, the fixing system may be defined by a screw assembly or via a complete penetration butt weld.

[0022] Preferably, the first end of the engagement member comprises a second slot for receiving a shim.

[0023] In an alternative arrangement, the engaging unit comprises a finger element mounted to the lower bar assembly and partially fixed to the lower bar assembly to form a spacing between the finger element and the lower bar defining a slot for engagement at least partially a portion of the end of the panel engaging with the engagement member.

[0024] In this alternative arrangement, the lower bar assembly comprises a plurality of bars spaced apart with respect to each other via one or more spacing bars, each bar of the lower bar assembly comprising an engaging unit attached thereto.

[0025] According to a third aspect of the invention there is provided a construction system for defining a support structure comprising at least one supporting construction elements and at least one construction element spanning between the supporting construction elements, the construction system comprising engagement members configured to be engaged to the supporting construction elements and to the construction element such that the engagement member is in a state of dynamic equilibrium whilst being engaged to the supporting construction elements and construction element through a fastenerless engagement.

[0026] Preferably, the least one engagement member comprises at least one engagement member in accordance with the second aspect of the invention.

[0027] Preferably, the engagement members comprise engagement members according to the second aspect of the invention.

[0028] Preferably, the supporting construction element comprises a beam.

[0029] Preferably, the beam comprises a continuously voided beam or a prestressed hollowcore precast beam.

[0030] Preferably, the construction element comprises a preformed sheeting.

[0031] Preferably, the construction element comprises one or more preformed metal formwork members. Multiple such preformed metal formwork members may be connected together before installation to form permanent formwork to support poured concrete.

[0032] According to a fourth aspect of the invention there is provided a method for defining a support structure as defined in the third aspect of the invention, the method comprises the steps of:

[0033] a. engaging the engagement members to the construction element through a fastenerless engagement such that the engagement members are in a dynamic equilibrium whilst being engaged to the construction element;

[0034] b. mounting the construction element between the supporting construction elements such that the engagement members engage the supporting construction elements such that the engagement members are in a dynamic equilibrium whilst being engaged through a fastenerless engagement to the supporting construction elements;

[0035] c. optionally fixing the engagement members to the supporting construction elements; and

[0036] d. pouring a concrete mixture onto the support structure and letting it cure.

[0037] Preferably, the least one engagement member comprises at least one engagement member in accordance with the second aspect of the invention.

[0038] Preferably, the engagement members comprise engagement members according to the second aspect of the invention.

[0039] Preferably, the supporting construction element comprises a beam.

[0040] Preferably, the beam comprises a continuously voided beam or a prestressed hollowcore precast beam.

[0041] Preferably, the construction element comprises a preformed sheeting. Preferably, the construction element comprises metal decking / sheeting, e.g. acting as permanent formwork for a poured concrete slab floor construction.

[0042] One or more aspects of the present invention may provide a support bracket configured for engagement with a floor member to support the floor member between structural floor supports of a building structure.

[0043] The floor member may include a panel configured to support poured concrete of a floor construction. One or more embodiments of the bracket may include spaced engaging members defining at least one space therebetween to receive an end portion of the respective floor member for relative sliding engagement with the floor member.

[0044] Embodiments of the bracket may include at least one upper bar and at least one lower bar providing the at least one space therebetween to receive therein at least part of the end portion of the floor member.

[0045] Embodiments of the bracket may include a sleeve, such as providing reinforcement, within which the at least one upper bar and the at least one lower bar extend. The sleeve may be welded or otherwise fastened to the respective bar(s). Embodiments may include at least one spacer within the sleeve, the spacer separating the at least one upper bar and the at least one lower bar. The sleeve may be configured to support the bracket, and thereby the flooring member, by resting directly or indirectly on the respective structural floor support.

[0046] Embodiments of the bracket may be arranged and configured for fastenerless engagement with the floor member to at least initially provide structural support between the floor member and the supporting structural floor support.

[0047] Embodiments of the bracket may include a receiver to receive a connection member. The respective receiver may include a hole, groove, notch or other aperture through a portion of the bracket to receive an elongate said connection member therethrough.

[0048] Another aspect of the present invention provides a flooring system for a building structure, the flooring system including one or more brackets described and / or defined herein.

[0049] The floor member may be part of a panel structure (floor panel structure) for spanning between spaced support beams of a floor support structure. The panel structure may include a plurality of panels located side by side and spanning between the spaced support beams.

[0050] The respective bracket may include a receiver for engagement with a connection member, wherein the connection member includes or is an elongate member, such as a metal rod, bar or length of rebar. The system may include at least one retainer connectable onto a respective end of the connection member. The respective may be configured so as to lock to the adjacent bracket by a locking means such as a pin, screw or other fastener to prevent premature release of the connection member from engagement with the floor members.

[0051] Another aspect of the present invention provides a method for constructing a floor structure: the method including engaging a number of brackets to respective floor members of a floor panel structure through fastenerless engagement therewith; mounting the floor panel structure between opposed supporting floor supports of a building structure such that each said bracket is supported on the respective floor support with the floor members supported therebetween spanning a space between the opposed supporting floor supports.

[0052] Embodiments may include subsequently fixing each bracket to the respective floor member when engaged therewith. Embodiments may include pouring a concrete mixture onto the floor panel structure and letting the concrete cure.

[0053] Embodiments may include engaging the brackets to the panel structure prior to lifting into place with a lift arrangement and subsequently placing the panel structure supported on the supporting floor supports by the brackets.

[0054] Embodiments may include a retainer engageable onto a respective end of the connection member. The retainer may be locked to the adjacent bracket by a locking means e.g. a pin, screw or other fastener, to restrict / prevent premature release of the connection member from engagement with the floor members.

[0055] A number of the floor members can be connected together to form a panel structure, such as a number of metal deck components connected together. A number of the brackets can be engaged on opposed ends of the panel structure. The connection member can be engaged with the brackets at a respective end of the panel structure.

[0056] Embodiments may include a lift arrangement, such as to engage with the respective connection member to lift the panel structure into position to be supported on the structural floor supports, which can be prior to fastening the brackets with fasteners and / or subsequently concrete being poured onto the panel structure.

[0057] The lift arrangement can include suspension members releasably attachable to the connection members, such as by cables, chains or other elongate suspension members. A spreader bar can be used to connect the suspension members (e.g. elongate members) to a lift means, such as a crane / crane hook.BRIEF DESCRIPTION OF THE DRAWINGS

[0058] Further features of the present invention are more fully described in the following description of several non-limiting embodiments thereof. This description is included solely for the purposes of exemplifying the present invention. It should not be understood as a restriction on the broad summary, disclosure or description of the invention as set out above. The description will be made with reference to the accompanying drawings in which:

[0059] FIG. 1 is a schematic cross-sectional view of a particular arrangement of a building structure in accordance with an embodiment of the invention used as a parking structure.

[0060] FIG. 2 is schematic plan view of a particular arrangement of a floor structure of a building structure.

[0061] FIG. 3 is a schematic plan view of the support surface defining the floor structure of the type shown in FIG. 2.

[0062] FIG. 4 is a schematic view of the detail A shown in FIG. 3.

[0063] FIG. 5 is a schematic plan view of a panel structure for defining the floor structure of the type shown in FIG. 2.

[0064] FIG. 6 is a schematic cross-sectional view along the line A-A′ of a particular bay section of the floor structure shown in FIG. 2.

[0065] FIG. 7 is a schematic end view of a panel incorporating a first arrangement of engagement member in accordance with the present embodiment of the invention.

[0066] FIGS. 8 to 11 are schematic plan, front, side and bottom view of a first arrangement of engagement member in accordance with the present embodiment of the invention.

[0067] FIG. 12 is a schematic cross-sectional view of a particular of support structure.

[0068] FIG. 13 is a schematic plan view of a particular of support structure.

[0069] FIG. 14 is a schematic end view of a pair of panels incorporating second arrangements of engagement members in accordance with the present embodiment of the invention.

[0070] FIGS. 15 to 18 are schematic plan, front, side and bottom views of two second options of second arrangements of engagement member in accordance with the present embodiment of the invention.

[0071] FIG. 19 is perspective view of a support structure in accordance with the present embodiment of the invention.

[0072] FIGS. 20 and 21 show examples of engagement members (also referred to as support brackets Type 1 and Type 2, respectively) in accordance with the present embodiments of the invention.

[0073] FIG. 22 shows the engagement members shown in FIGS. 20 and 21 in use.

[0074] FIG. 23 shows a free body diagram of the support bracket Type 1 in unclamped condition during installation.

[0075] FIG. 24 shows a free body diagram of the support bracket Type 1 in clamped condition during construction.

[0076] FIGS. 25 to 27 show views of an engagement member (such as a support bracket) according to an alternative embodiment of the present invention. FIG. 25 shows a side view. FIG. 26 shows an end view and FIG. 27 shows a top (plan) view.

[0077] FIG. 28 shows a view of an arrangement incorporating an engagement member shown supporting a panel on supporting construction elements (such as support beams) according to an embodiment of the present invention.

[0078] FIG. 29 shows an aerial (plan) view of a number of the engagement members supporting construction elements (such as panels) on supporting construction elements (such as beams) according to an arrangement of the present invention.

[0079] FIG. 30 shows an end view showing a number of the engagement members (e.g. support brackets) connected to construction elements according to an embodiment of the present invention.

[0080] FIGS. 31 and 32 show a modular arrangement according to an alternative embodiment of the present invention. FIG. 31 shows a number of the engagement members mounted to each end of a series of construction elements and arranged with connection members connecting the engagement members along respective ends of the construction elements, according to at least one embodiment of the present invention. FIG. 32 shows a lift arrangement for transporting the modular connected construction elements and engagement members arrangement of FIG. 31.

[0081] FIG. 33 shows a view of an engagement member with facility to receive a connection member according to an embodiment of the present invention.

[0082] FIG. 34 shows a retainer arrangement for releasably retaining the connection member to a respective engagement member (e.g. support bracket) according to an embodiment of the present invention.DESCRIPTION OF EMBODIMENT(S)

[0083] The present invention relates to a connection system and method for connecting a construction element (such as a panel or sheeting or metal decking e.g. preformed metal decking providing permanent formwork to support a concrete slab) to a supporting construction element (a beam such as a continuously voided beam or a prestressed hollowcore precast beam) using an engagement member that is configured in such a manner that it is in a state of dynamic equilibrium when being engages, for example, to these elements through a fastenerless engagement.

[0084] By dynamic equilibrium is meant the state of a body (whilst for example being at rest) in which the forces applied to a body do not produce either translational acceleration or angular acceleration due to the total sum of the forces (applied to the body) being zero. Thus, whilst an engagement member is attached to, for example, the supporting construction element and the engagement members, the engagement member will stay engaged to these elements.

[0085] By fastenerless engagement is meant an engagement between two elements (such as a supporting construction element and a construction element) which is such that the engagement between these elements locate the elements in a dynamic equilibrium without the need of fasteners.

[0086] It is particularly advantageous that the connection system in accordance with the present embodiment of the invention comprises one or more engagement members configured in such a manner that when the engagement members are initially engaged to, for example, the supporting construction and / or construction element, the engagement members are in a state of dynamic equilibrium without the need of fasteners. This is particularly true because due to being in a state of dynamic equilibrium (without the need of fasteners) the engagement members stay static facilitating erection of building structures such as for example their floor structures; in particular, for defining a floor structure using relatively lightweight materials but being able to sustain relatively large loads. Facilitation occurs because the step of applying fasteners to define the joint between both elements can be omitted until the support structure has been defined.

[0087] Floor structures made out of relatively lightweight materials and easy to assembly have been become popular for erecting building structures such as parking facilities as shown in FIG. 1.

[0088] As shown by way of example in FIG. 1, the building structure 10 comprises a main area 12 and an access area 14. The access area 14 comprises staircases and ramps allowing the vehicles and pedestrians access to the main area 12 of the building structure 10.

[0089] The main area 12 comprises floor structures 16 defining the parking bays 18 for parking of the vehicles as well as aisles 20 and footpaths 22 to permit the vehicles and the pedestrians to gain access to the parking bays for parking and retrieving the

[0090] FIG. 2 shows a schematically plan view of a floor structure 16 comprising a plurality of group of bays spaced apart by an aisle 20. The floor structure 16 is defined by a support structure 24 onto which a concrete mixture is poured and let to cure.

[0091] The support structure 24 shown in FIG. 5 comprises two sections 26 and 28 located side by side. Each section 26 and 28 comprises a plurality of beams 30 (the supporting construction elements) arranged in a spaced apart relationship with respect to each other defining, between neighbouring beams (e.g.: 30a and 30b) spacing 32 (e.g. 32a) for containment of a panel structure 34 (see FIG. 5).

[0092] The panel structure 34 extends between sides 38 of the beams 30. As will be described with reference to the method of construction of the floor structure 16, the ends 38a and 38b (see FIG. 5) of the panel structure 34, are attached via a connection system and method in accordance with the present embodiment of the invention.

[0093] The particular arrangement of panel structure 34 shown in FIG. 5, comprises a plurality of panels 42 (the construction elements) located side by side; in particular, there are four panels 42a to 42d. Other arrangements of panel structure 34 may comprise a single panel 42 or any number of panels 42.

[0094] In the particular arrangement of floor structures 16 described herein, each panel 42 comprises a sheeting structure 44 (a construction element), such as an elongated sheet configured for reinforcement of the sheeting structure 44. FIG. 7 shows such a sheeting structure 44. A particular example of a sheeting structure 44 to be used is preformed metal decking acting as permanent formwork.

[0095] Referring now to FIG. 6, as mentioned before, the support structure 24 of the floor structure 16 is defined by supporting the ends of the panel structure 34 to the sides 38 of the beams 30 via a connection system incorporating engagement members 46 which, once engaged are in state of dynamic equilibrium facilitating defining the support structure 24. Once the support structure 24 is defined as shown in FIG. 19, a concrete layer 40 (see FIG. 6) is poured over the panel structure 34 and the beams 30 for completion of the floor structure 16. One or more restraint straps 35 can support edge form 37 relative to outer longitudinal sides of the panel structure. The edge form can constrain poured concrete at the outer side edges of the panel structure.

[0096] As shown in FIGS. 5 and 6, each end 38 of each panel 42 incorporate an engagement member 46 to permit engagement of the ends 38 of each panel 42 with the sides 38 of the beams 30. The panel structure 34 is defined between neighbouring beams 30, such as beams 30a and 30b, by locating the panel structure 34 (defined by one or more panels 42 located side by side) between the beams 30 and to permit engagement to occur between the ends 38 of panel 42 and the sides 38 of the beams 30.

[0097] In accordance with the present embodiment of the invention, the engagement members 46 are adapted to engage the ends 38 of the panels 42 in such a manner that engagement with the ends 38 occurs relatively easy taking a relatively short period of time but ensuring that the engagement members 46 are properly secured to the panels 42 ensuring they are in a state of dynamic equilibrium whilst engaged to the panels 42. In this manner, the panels 42 may be get ready swiftly for assembly of the panel structure 34 spanning between the beams 30a.

[0098] Further, the engagement members 46 are also adapted to engage the sides 38 of the beams 30 in a swift manner and in a single step resting on the sides 38 in a state of dynamic equilibrium when mounted on the sides 38 whilst being engaged to the panels 42.

[0099] FIGS. 8 to 11 show a first arrangement of an engagement member 46 in accordance with the present embodiment of the invention.

[0100] As shown in FIG. 8, the engagement member 46 comprises a body defined by a receiving end 48 (the second end) and a supporting end 50 (the first end). The receiving end 48 is adapted to engage the end 38 of a panel 42 and the supporting end 50 is adapted to engage the side 36 of a beam 30.

[0101] In the particular arrangement shown in the figures, for example, 8 to 11, the body of the engagement member 46 is defined spaced apart engaging bars 52a and 52b (defining a lower bar assembly) and spacing bars 54a and 54b.

[0102] The engaging bars 52 comprise each a supporting end 50 (the first end) and a receiving end 48 (the second end) of the engagement member 46. The spacing bars 54a and 54b are attached to the inner sides 60 of the engaging bars 52, respectively, at ends 56 and 58 of the engaging bars 52.

[0103] As mentioned before, the receiving end 48 of the engagement member 46, is adapted to engage the ends 38 of the panels 42. For this, at the receiving end 48 of each engaging bar 52 is provided with an engaging unit 62 attached to each engaging bar 52. Each engaging unit 52 is adapted to receive the end 38 (the first end portion) of the panels 42.

[0104] FIGS. 9 and 10 show, respectively, a rear view and a side view of the engaging unit 62.

[0105] The engaging unit 62 comprises a finger element 64 mounted to the engaging bar 52 and partially fixed to the engaging bar 52 to form a spacing between the finger element 64 and the engaging bar 52. The spacing defines a slot 66 for receiving and securing at least partially a portion of the end 38 of the panel 42 engaging with the engagement member 46.

[0106] In the arrangement shown in FIGS. 8 to 11, a distal end 68 of the finger element 64 is fixed to the engaging bar 52 with the remaining portion (referred to as the proximal end 70) spaced apart from the engaging bar 52 defining the slot 66. Fixing of the distal end 68 may be done via welding or any other suitable fixing system 72.

[0107] Furthermore, the engaging unit 62 may be secured to the panel 42, for example, in the arrangement shown in FIG. 10, via a fastening system 74 based, for example, on a screw for traversing the end 38 of the panel 42 and screwed into the engaging bar 52. Alternatively, any other suitable fastening system may be used.

[0108] Referring now to FIG. 12, as mentioned before, in use, the panel structure 34 spans between beams 30 to defining the support structure 34. The panel structure 34 may comprise one panel 42 only, or alternatively a plurality of panels 42 located side by side as shown in FIG. 5.

[0109] In accordance with the present embodiment of the invention there is provided a method for assembling the support structure 24.

[0110] The method of assembly comprises (once the beams 30 have been arranged in spaced arrangement such as shown in FIGS. 3 and 4) the step of mounting one or more panels 42 using the engagement members 46 onto neighbouring beams 30 (such as beams 30a and 20b of FIG. 4) in such a manner that the panels 42 are arranged side by side and spanning between neighbouring beams 30. The panels 42 (having the engagement members 46 attached thereto in a state of dynamic equilibrium) are mounted onto the beams 30 one by one ensuring the sides of neighbouring panels 42 are properly engaged to each other (see FIG. 14) and that the engagements elements 46 also properly engage the sides 16 of the beams 30 as shown in FIGS. 6 and 12. In this respect, the engagement members 46 are mounted onto the sides 38 of the beams 30 with the engagement members 46 being in a state of dynamic equilibrium whilst engaging the sides 38 of the beams.

[0111] The connection between the panels 42 and the engagement members 46 is considered as a moment connection in-plane, as the in-plane moment will be resisted by the engaging unit 62 (the upper bar assembly), self-drilling screws and the stiffness of each element at the connection.

[0112] In this respect, the behaviour of the engagement members 46 according to theoretical analysis predicts that once the panels 42 (in particular the sheeting metal decking 210) are slotted into the engagement members 46 and placed onto the sides 38 of the beams 30, the engagement members 46 will rotate about the bearing pad edge due to the self-weight of the panels 42 (0.133, 0.159 and 0.197 KN / m2 for 1.0, 1.2 and 1.5 BMT, respectively). However, the rotation will be restrained by the panels 42 through the engagement of the engagement members 46. Thus, the engagement members 46 (the panels 42) will be in a state of dynamic equilibrium.

[0113] One the support structure 24 is defined with the panel structure 34 spanning between the beams 30, a construction worker may confirm that the support structure 24 has been correctly assembled; and, the worker may now fix (via screwing work) the engagement member 46 to the sides 38 of the beams 30.

[0114] The maximum potential load from the panels 42 during screwing work is to be transferred to the beams 30 through the engagement members 46 as shown in FIG. 20. The rotation due to the clockwise moment generated by the load from the panels 42 and the beams 30 reaction is to be resisted by the anticlockwise moment generated by the engaging unit 62. Due to the engagement members 46 are in dynamic equilibrium, the support structure 46 remains in the static condition under the load during the screwing work.

[0115] Subsequently, the concrete layer 40 is applied (see FIG. 6) to define the floor structure 16 as shown in FIG. 6.

[0116] The method in accordance with the present embodiment of the is particularly advantageous because it greatly facilitates assembly of the floor structure 16. This is particularly true because the assembly of the floor structure 16 is done using a particular construction process, wherein the strength of the floor structure 16 that is being constructed gradually is increased as the construction process progresses by conducting the construction steps in a sequential manner.

[0117] For example, in the present arrangement of the method of constructing the floor structure 16, the construction process includes the following steps:

[0118] a. mounting the panels 42 (comprising the engagement member 46) onto the beams 30 one by one such that the engagement member 46 engage the sides 38 of the beams 30 and the sides of neighbouring panels 42 engage each other;

[0119] b. securing the engagement members 46 to the beams 30 via fastening system 74; and

[0120] c. pouring a concrete mixture onto the support structure 34 and letting it cure.

[0121] It is evident that as the construction process of the floor structure 16 progresses, the strength of the support structure 34 increases, in particular, from:

[0122] a. the engagement members 46 being attached to the ends of the panels 42 such that the engagement members 46 are in a state of dynamic equilibrium;

[0123] b. the panels 42 being supported on the beams through the engagement members 46 being in a state of dynamic equilibrium;

[0124] c. the engagement members 46, whilst being in a state of dynamic equilibrium, may be secured to the beams 30 via the fastening system74; and

[0125] d. ultimately forming a concrete layer onto the support structure 24 being in a state of dynamic equilibrium to define the floor structure 16.

[0126] This is possible due to the engagement members 46 being configured to be in a state of dynamic equilibrium whilst the engagement members 46 are engaged through a fastenerless engagement (absent of fastening systems) to the ends of the panels 42 and the resting on the sides 38 of the beams 30.

[0127] This progressively strengthening process expedites the construction process and reduces the number of construction workers required for safely erecting a building structure. In fact, for example, defining the panel structure 34 spanning between the beams (supported on engagement members 46 being in a state of dynamic equilibrium) will not compromise the safety of construction workers and equipment and save time.

[0128] Once the panel structure 34 spans between the beams 30 solely supported on the beams 30 via the engagement members 46, only a few construction workers (one or more) may swiftly secure the panels 42 via fastening system 74 permitting, subsequently, pouring the concrete mixture on the support structure 24 for defining the floor structure 16.

[0129] Referring now to FIGS. 14 to 18, FIGS. 14 to 18 depict second arrangements of the engagement member 46. The second arrangements of engagement member 46 comprise a single engaging unit 62 (the upper bar assembly) adapted to receive ends 38 of the panels 42. This is in contrast with the first arrangement of engagement member 46 wherein a plurality of engaging units 62 are used.

[0130] In particular, as shown in the FIGS. 14 to 18, each engaging unit 62 comprises a plurality of supporting bars 52 with a finger member 64 attached to the supporting bars 52 spaced apart with respect to each other defining a gap 76 (see FIG. 16).

[0131] The finger member 64 is partially attached via fixing system 72 (see FIG. 20) to the plurality of supporting members 52 for defining the slot 66 adapted to receive a portion of the ends 58 of the panels 42 as was discussed earlier with reference to FIG. 5.

[0132] In the particular arrangement shown in FIGS. 15 and 16, the fixing system 72 is defined by a screw assembly. In the particular arrangement shown in FIGS. 17 and 18, the fixing system 72 is defined by a complete penetration butt weld.

[0133] The proximal end 68 of the finger member 64 extends away from (1) the location of the attachment point of the finger member 64 and the supporting bars 52 to (2) the end 78 of the supporting bars 52 defining at that location the entrance of the slot 66 for receiving the ends 38 of the panels 42. In this manner, the slot 66 has a greater depth than the slot 66 of first arrangement of engaging unit 62 shown in FIG. 10.

[0134] Further, the end 70 of the finger member 64 extend above the supporting end 50 of the supporting bars 52 defining a further slot for receiving a shim 80.

[0135] In use, typically there will be a pair of engagement members 46 in accordance with second arrangement of the present embodiment of the invention attached to end 38 of the panels 42 as shown in FIG. 14. And, the method of assembly of the support structure 24 will be substantially the same than when using the engagement members 46 in accordance with the first arrangement shown in FIGS. 8 to 11.

[0136] FIGS. 20 and 21 show examples of engagement members 46 (also referred to support brackets Type 1 and Type 2, respectively) in accordance with the present embodiments of the invention. It should be understood that the scope of protection sought is not limited to these two examples. FIG. 22 shows the engagement members 46 in use attached to the panels 42.

[0137] FIG. 23 shows a free body diagram of the support bracket Type 1 (the engagement member 46 shown in FIG. 20) in unclamped condition during installation.

[0138] FIG. 24 shows a free body diagram of the support bracket Type 1(the engagement member 46 shown in FIG. 20) in clamped condition during construction.

[0139] Modifications and variations as would be apparent to a skilled addressee are deemed to be within the scope of the present invention.

[0140] In this respect, the particular arrangement of support structure 24 (excluding the panel structure 34) shown in FIG. 3 is defined by a plurality of single beams 30 arranged in a spaced apart relationship with respect to each other.

[0141] However, in alternative arrangements, the particular support structures 24 may be defined by a group of beams 30 arranged in a spaced apart relationship with respect to each other, with each group comprising a plurality of beams 30 attached to each side by side as shown in FIG. 6.

[0142] An interface 47, such as a resilient pad, can be provided between the respective engagement member 46 (e.g. support bracket) and the supporting construction element 30 (such as a concrete beam or other fixed structure).

[0143] Embodiments of the engagement member 46 can include reinforcement 71, such as a sleeve, preferably at least at one end of the engagement member. The reinforcement can be provided at an end of the engagement member / bracket 46 that is supported on the supporting construction element 30 (such as a concrete beam or other structural member of a building.

[0144] The bracket 46 can include a receiver 73 for engagement with a connection member 81. The connection member 81 can include or be an elongate member, such as a metal rod, bar or length of rebar.

[0145] A retainer 83 can be engaged onto a respective end of the connection member 81. The retainer 83 can be locked to the adjacent bracket 46 by a locking means 85, such as a pin, screw or other fastener to prevent premature release of the connection member 81 from engagement with the floor members.

[0146] A number of the floor members can be connected together to form a panel structure, such as a number of metal deck components connected together. A number of the brackets can be engaged on opposed ends of the panel structure e.g. by way of example in FIG. 31. The connection member 81 can be engaged with the brackets 46 at a respective end of the panel structure.

[0147] A lift arrangement 90 can engage with the connection member 81 to lift the panel structure into position supported on the structural floor supports prior to fastening the brackets with fasteners and subsequently concrete being poured onto the panel structure. The lift arrangement can include suspension members 95 releasably attachable at attachment positions 91 to the connection members 81, e.g. cables, chains or other elongate suspension members. A spreader bar can be used to connect the elongate members to a lift means, such as a crane hook.

[0148] Further, it should be appreciated that the scope of the invention is not limited to the scope of the embodiments disclosed. These embodiments are intended for the purpose of exemplification only. Functionally equivalent products, formulations and methods are clearly within the scope of the invention as described herein.

[0149] Reference to positional descriptions, such as lower and upper, or inner and outer, are to be taken in context of the embodiments depicted in the figures, and are not to be taken as limiting the invention to the literal interpretation of the term but rather as would be understood by the skilled addressee.

[0150] The terminology used herein is for the purpose of describing particular example embodiments only and is not intended to be limiting. As used herein, the singular forms “a”, “an” and “the” may be intended to include the plural forms as well, unless the context clearly indicates otherwise. The terms “comprise”, “comprises”, “comprising”, “including”, and “having”, or variations thereof are inclusive and therefore specify the presence of stated features, integers, steps, operations, elements, and / or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and / or groups thereof.

[0151] Although terms such as first, second, third, etc. may be used herein to describe various elements, components, regions, layers and / or sections, these elements, components, regions, layers and / or sections should not be limited by these terms. These terms may be only used to distinguish one element, component, region, layer or section from another region, layer or section. Terms such as “first”, “second”, and other numerical terms when used herein do not imply a sequence or order unless clearly indicated by the context. Thus, a first element, component, region, layer or section discussed below could be termed a second element, component, region, layer or section without departing from the teachings of the example embodiments.

[0152] Spatially relative terms, such as “inner”, “outer”, “beneath”, “below”, “lower”, “above”, “upper” and the like, may be used herein for ease of description to describe one element or feature's relationship to another element(s) or feature(s) as illustrated in the figures. Spatially relative terms may be intended to encompass different orientations of the device in use or operation in addition to the orientation depicted in the figures. For example, if the device in the figures is turned over, elements described as “below” or “beneath” other elements or features would then be oriented “above” the other elements or features. Thus, the example term “below” can encompass both an orientation of above and below. The device may be otherwise oriented (rotated 90 degrees or at other orientations) and the spatially relative descriptors used herein interpreted accordingly.

[0153] Throughout this specification, unless the context requires otherwise, the word “comprise” or variations such as “comprises” or “comprising”, will be understood to imply the inclusion of a stated integer or group of integers but not the exclusion of any other integer or group of integers.

Claims

1. A support bracket configured for engagement with a floor member of metal decking / formwork to support the floor member between opposed sides of structural floor supports of a building structure, the support bracket including a receiving end and a supporting end, the receiving end including spaced engagement members including at least one upper bar and at least one lower bar, the at least one upper bar and the at least one lower bar defining at least one space therebetween providing at least one slot to receive an end portion of the respective floor member of metal decking / formwork and be supported on the end portion of the floor member in a state of dynamic equilibrium whilst the support bracket is engaged to the end portion prior to the supporting end of the support bracket being supported on the respective structural floor support, the support bracket, in use, extending between the end portion of the floor member and the structural floor support, the support bracket being in a supporting state of dynamic equilibrium without the respective floor member resting on the respective structural floor support.

2. The bracket of claim 1, wherein the floor member of the metal decking / formwork includes a panel configured to support poured concrete of a floor construction.

3. The bracket of claim 1, wherein the at least one lower bar includes a lower bar assembly including spaced lower bars.

4. The bracket of claim 3, the engagement members including a finger element mounted to the lower bar assembly and partially fixed to the lower bar assembly to provide the at least one space between the finger element and the lower bar to receive therein at least part of the end portion of the floor member.

5. The bracket of claim 1, including a sleeve within which the at least one upper bar and the at least one lower bar extend.

6. The bracket of claim 5, including at least one spacer within the sleeve, the spacer separating the at least one upper bar and the at least one lower bar.

7. The bracket of claim 5, wherein the sleeve is configured to support the bracket, and thereby the flooring member, by resting directly or indirectly on the respective structural floor support.

8. The bracket of claim 1, wherein the bracket is configured for fastenerless engagement with the floor member to at least initially provide structural support between the floor member and the supporting structural floor support.

9. The bracket of claim 1, including a receiver to receive a connection member.

10. The bracket of claim 9, wherein the receiver includes a hole or aperture through a portion of the bracket to receive an elongate said connection member therethrough.

11. A flooring system for a building structure, the flooring system including a bracket according to claim 1.

12. The system of claim 11, wherein the floor member is part of a panel structure of metal decking / formwork for spanning between spaced support beams of a floor support structure.

13. The system of claim 12, wherein the panel structure includes a plurality of panels located side by side and spanning between the spaced support beams.

14. The system of claim 11, wherein the respective bracket includes a receiver for engagement with a connection member, wherein the connection member includes or is an elongate member, such as a metal rod, bar or length of rebar.

15. The system of claim 14, including a retainer connectable onto a respective end of the connection member.

16. The system of claim 15, wherein the retainer is configured to lock to the adjacent bracket by a locking means such as a pin, screw or other fastener to prevent premature release of the connection member from engagement with the floor members.

17. A method for constructing a floor structure:engaging a number of support brackets to respective floor members of a floor panel structure of metal decking / formwork through fastenerless engagement therewith prior to mounting the floor panel structure between opposed supporting floor supports of a building structure, the support brackets each including a receiving end and a supporting end, the receiving end including spaced engagement members including at least one upper bar and a lower bar assembly providing at least one space therebetween providing at least one slot to receive an end portion of the respective floor member such that the respective floor member supports the respective support bracket with the support bracket being in dynamic equilibrium;mounting the floor panel structure between opposed supporting floor supports of the building structure such that each said support bracket extends between a said floor member and the respective floor support to support a said floor member to span a space between the opposed supporting floor supports, such that the support brackets are in a state of dynamic equilibrium without the respective floor member resting on the respective structural floor support, and the support brackets being in a state of supporting dynamic equilibrium.

18. The method of claim 17, including subsequently fixing each bracket to the respective floor member when engaged therewith.

19. The method of claim 17 including pouring a concrete mixture onto the floor panel structure and letting the concrete cure.

20. The method of claim 17, including engaging the brackets to the panel structure prior to lifting into place with a lift arrangement and subsequently placing the panel structure supported on the supporting floor supports by the brackets.