Power-system protection system, power-system protection device, and power-system protection method
The power system protection system uses a commutator with semiconductor and mechanical switches to manage current flow and interrupt it swiftly, addressing the limitations of traditional circuit breakers in restoring power transmission after an arc is extinguished, thereby enhancing system stability and compliance with industry standards.
Patent Information
- Application Number
- PCT/JP2023/013601
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-03
AI Technical Summary
Conventional power system protection methods, relying on circuit breakers, face limitations in quickly restoring power transmission after an arc is extinguished due to the physical movement of movable contacts, resulting in prolonged no-voltage states and reduced system stability.
A power system protection system employing a system breaker and a commutator with semiconductor and mechanical switches, which reduces current flow to the fault location before interrupting it, allowing for faster restoration of power transmission by utilizing semiconductor switches to manage current flow more swiftly than traditional circuit breakers.
This approach enables quicker restoration of power transmission after an arc is extinguished, potentially reducing the time to resume normal operations by utilizing semiconductor switches to manage current flow more efficiently than traditional circuit breakers, aligning with industry standards for faster reclosing operations.
Smart Images

Figure JP2023013601_03102024_PF_FP_ABST
Abstract
Description
Power system protection system, power system protection device, and power system protection method
[0001] The present disclosure relates to a power system protection system, a power system protection device, and a power system protection method that protect a power system when an accident such as a ground fault or a short circuit occurs in a power transmission line.
[0002] Conventionally, in a power transmission system that transmits power generated by a generator to a load, a circuit breaker and a relay as disclosed in Patent Document 1 are installed in a power transmission line in preparation for the occurrence of an accident such as a short circuit or a ground fault. When a ground fault occurs in the power transmission line due to the influence of lightning or the like, the relay detects the accident and sends a break command to the circuit breaker. The circuit breaker, upon receiving the break command from the relay, opens its contacts, thereby interrupting the current flowing in the power transmission line. After the arc is extinguished by interrupting the current flowing in the power transmission line, the circuit breaker is closed, and the power transmission system returns to a state in which power is normally transmitted.
[0003] Japanese Patent Application Laid-Open No. 2004-281302
[0004] It is known that the insulation performance of the space around the ground fault location on a power transmission line recovers in a time equivalent to at most two AC cycles after the arc has extinguished. Therefore, if a ground fault occurs on a 60 Hz AC power transmission line, the insulation performance of the space around the ground fault location will recover 30 ms after the arc has extinguished.
[0005] During the opening of a circuit breaker, the transmission line is in a no-voltage power outage state, increasing the impedance of the power system and reducing the stability of the power system. Therefore, it is desirable to resume power transmission as soon as possible after the arc is extinguished. Circuit breakers open and close by physically moving a moving contact, so there is a limit to how fast they can be operated. Therefore, it takes approximately 300 ms to 1 second from the time the arc is extinguished by interrupting the current flowing through the transmission line with the circuit breaker to the time the circuit breaker closes and restores normal power transmission. Thus, when an arc is extinguished by interrupting the current with a circuit breaker installed on a transmission line, the operating speed of the circuit breaker becomes a bottleneck, making it difficult to shorten the time until power transmission is resumed.
[0006] The present disclosure has been made in consideration of the above, and aims to provide a power system protection system that can restore the power transmission system to a state in which power transmission is performed normally in a short time after an arc is extinguished.
[0007] In order to solve the above-mentioned problems and achieve the object, the power system protection system according to the present disclosure includes a system circuit breaker that is installed on a transmission line connecting a generator and a load to which power is supplied from the generator and that interrupts the current flowing through the transmission line when an abnormality occurs in the transmission line, and a commutator that is connected to a portion of the transmission line between the system circuit breaker and the load and to ground and that insulates the transmission line from ground in an off state and conducts the transmission line from ground in an on state. When the power system protection system detects an accident due to a ground fault or short circuit occurring in the transmission line, it turns on the commutator to commutate the current flowing through the transmission line to ground before the system circuit breaker interrupts the current flowing through the transmission line.
[0008] The present disclosure provides an advantageous effect of providing a power system protection system that can restore the power transmission system to a state in which power is transmitted normally in a short time after an arc is extinguished.
[0009] FIG. 1 is a diagram showing the configuration of a power transmission system according to embodiment 1; FIG. 2 is a functional block diagram of a relay of a power system protection device according to embodiment 1; FIG. 3 is a flowchart showing the operation flow of the power system protection device according to embodiment 1; FIG. 4 is a diagram showing a state in which a ground fault has occurred in a power transmission system according to embodiment 1; FIG. 5 is a diagram showing a state in which a mechanical switch of a commutator of a power system protection device according to embodiment 1 is turned on; FIG. 6 is a diagram showing a state in which a semiconductor switch of a commutator of a power system protection device according to embodiment 1 is turned on;
[0010] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A power system protection system, a power system protection device, and a power system protection method according to embodiments will be described in detail below with reference to the accompanying drawings.
[0011] First Embodiment. Figure 1 is a diagram showing the configuration of a power transmission system according to a first embodiment. The power transmission system 100 is a power system that transmits power generated by a generator 10 to a load 60. A transformer 30, a system circuit breaker 40, and a power system protection device 50 are installed on a power transmission line 20. The power system protection device 50 includes a commutator 51 and a relay 52. The commutator 51 is connected to a portion of the power transmission line 20 between the system circuit breaker 40 and the load 60 and to ground 80. In an OFF state, the commutator 51 insulates the power transmission line 20 from the ground 80, and in an ON state, the commutator 51 conducts power between the power transmission line 20 and the ground 80. The commutator 51 includes a semiconductor switch 511 and a mechanical switch 512 connected in series with the semiconductor switch 511. The power system protection device 50 is installed so as to connect the power transmission line 20 to the ground 80 via the commutator 51. The commutator 51 is installed so that the mechanical switch 512 is on the power transmission line 20 side and the semiconductor switch 511 is on the ground 80 side.
[0012] The semiconductor switch 511 is configured by connecting multiple switching elements in series or in parallel. Increasing the number of parallel-connected switching elements increases the current that can be passed through the semiconductor switch 511. Increasing the number of serial-connected switching elements also increases the withstand voltage of the semiconductor switch 511.
[0013] 2 is a functional block diagram of a relay of the power system protection device according to embodiment 1. The relay 52 includes a fault detection unit 521 that detects the occurrence of an abnormality due to an accident, such as a short circuit or a ground fault, in the power transmission line 20 based on the voltage value of the current flowing through the power transmission line 20, and a control unit 522 that controls the commutator 51 and the system breaker 40. When a ground fault occurs in the power transmission line 20 due to a lightning strike or the like, the fault detection unit 521 detects the occurrence of the accident and notifies the control unit 522. The control unit 522 includes a counter 523. In the following description, it is assumed that the count value N of the counter 523 has an initial value of 1.
[0014] In a normal state where no fault occurs on the power transmission line 20, both the semiconductor switch 511 and the mechanical switch 512 are turned off.
[0015] FIG. 3 is a flowchart showing the flow of operation of the power system protection device according to the first embodiment. In step S1, the control unit 522 determines whether or not the fault detection unit 521 has notified the control unit 522 that an accident has occurred. FIG. 4 is a diagram showing a state in which a ground fault has occurred in the power transmission system according to the first embodiment. In FIG. 4, the solid arrow indicates the path of the current transmitted from the generator 10. When a ground fault occurs in the power transmission line 20, the voltage value of the current flowing through the power transmission line 20 becomes an abnormal value, the fault detection unit 521 detects the occurrence of an accident, and the fault detection unit 521 notifies the control unit 522 of the occurrence of the accident. If the fault detection unit 521 has notified the control unit 522 that an accident has occurred, the result of step S1 is Yes, and the control unit 522 proceeds to step S2. If the fault detection unit 521 has not notified the control unit 522 that an accident has occurred, the result of step S1 is No, and the control unit 522 repeats the process of step S1.
[0016] In step S2, the control unit 522 sends a closing command to the mechanical switch 512 to turn on the mechanical switch 512. Fig. 5 is a diagram showing a state in which the mechanical switch of the commutator of the power system protection device according to embodiment 1 is turned on. In Fig. 5, the solid arrow indicates the path of the current transmitted from the generator 10. When the mechanical switch 512 is turned on, the semiconductor switch 511 remains off, and therefore the current flowing through the transmission line 20 continues to flow through the transmission line 20 without being commutated to the commutator 51.
[0017] In step S3, the control unit 522 sends a command to the semiconductor switch 511 to turn it on. Fig. 6 is a diagram showing a state in which the semiconductor switch of the commutator of the power system protection device according to embodiment 1 is turned on. In Fig. 6, the solid arrow indicates the path of the current transmitted from the generator 10. When the mechanical switch 512 and the semiconductor switch 511 are both turned on, the commutator 51 is turned on, and current flows from the transmission line 20 to the ground 80 via the commutator 51. Current no longer flows in the fault location, and the arc is extinguished.
[0018] In step S4, the control unit 522 waits for a time period equivalent to (N+1) cycles of the AC current flowing through the power transmission line 20. Here, N is the count value of the counter 523.
[0019] In step S5, the control unit 522 sends a command to the semiconductor switch 511 to turn it off. Fig. 7 is a diagram showing a state in which the semiconductor switch of the commutator of the power system protection device according to embodiment 1 is turned off. In Fig. 7, the solid arrow indicates the path of the current transmitted from the generator 10. When the semiconductor switch 511 is turned off, the commutator 51 is turned off, and no current flows through the commutator 51, but instead, current flows through the transmission line 20.
[0020] In step S6, the control unit 522 determines whether or not an accident has occurred from the accident detection unit 521. If an accident has occurred from the accident detection unit 521, the answer to step S6 is Yes, and the control unit 522 proceeds to step S7. If an accident has not occurred from the accident detection unit 521, the answer to step S6 is No, and the control unit 522 proceeds to step S9.
[0021] In the case of a ground fault, if no current flows through the transmission line 20 for a period of two cycles of the AC current flowing through the transmission line 20 as described above, the arc that has occurred in the space at the fault location will have disappeared, and the answer in step S6 is expected to be No.
[0022] In step S7, the control unit 522 determines whether the count value N of the counter 523 has reached a preset number. If the count value N of the counter 523 has not reached the preset number, the answer is No in step S7, and the control unit 522 proceeds to step S8. If the count value N of the counter 523 has reached the preset number, the answer is Yes in step S7, and the control unit 522 proceeds to step S10.
[0023] In step S8, the control unit 522 increments the count value N of the counter 523 by 1. After step S8, the control unit 522 advances the process to step S3.
[0024] In step S9, the control unit 522 sends a shutoff command to the mechanical switch 512 to turn off the mechanical switch 512. Since power transmission to the power transmission line 20 has resumed at the time when the semiconductor switch 511 was turned off in step S5, the mechanical switch 512 may be turned off at any timing. After step S9, the control unit 522 ends the process.
[0025] In step S10, the control unit 522 sends a break command to the system breaker 40, turning off the system breaker 40 and breaking the current. After step S10, the control unit 522 ends the process.
[0026] In the above operation, if the occurrence of an accident has been notified to the control unit 522 in step S6, and if the count value N of the counter 523 has not reached a preset number, the count value N of the counter 523 is incremented by 1 in step S8, the semiconductor switch 511 is turned on in step S3, and after waiting for a time equivalent to (N+1) cycles of the AC period in step S4, the semiconductor switch 511 is turned off in step S5. That is, if the answer is Yes in step S6, the determination of whether the occurrence of an accident has been notified is repeated while extending the time for which the semiconductor switch 511 is turned off. Therefore, even if the arc does not extinguish for some reason while the semiconductor switch 511 is turned on the first time, the arc can be extinguished during the period when the semiconductor switch 511 is turned off from the second time onwards.
[0027] In the case of a short-circuit fault, the cause of the short circuit will not be eliminated even if the time for which the semiconductor switch 511 is turned on is extended, and therefore faults will occur repeatedly if a current flows through the power transmission line 20. In this case, in step S7, when the count value N of the counter 523 reaches a preset number, the system breaker 40 is turned off and no current flows through the power transmission line 20, so that work can be done to remove the cause of the short circuit at the fault location.
[0028] In this way, the power system protection device 50 according to the first embodiment prevents current from flowing to the fault location by commutating the current to the commutator 51, and when the semiconductor switch 511 of the commutator 51 is turned off, the current is no longer commutated to the commutator 51, and power supply to the transmission line 20 is resumed. Therefore, the power transmission system 100 using the power system protection device 50 according to the first embodiment can reduce the time required to restore normal power transmission after an arc is extinguished, compared to a power transmission system that uses a circuit breaker to interrupt the current in the transmission line.
[0029] JEC-2300, an AC circuit breaker standard established by the Institute of Electrical Engineers of Japan, and IEEE37.09-2018, established by the Institute of Electrical and Electronics Engineers of America, stipulate that the standard operating duty of a high-speed reclosing circuit breaker is to perform a closing operation and an opening operation at a standard voltage-free time interval of 0.3 seconds. When interrupting the current flowing in a transmission line with a circuit breaker, it is difficult to perform a closing operation and an opening operation at intervals of less than 0.3 seconds. However, the power system protection device 50 according to the first embodiment opens and closes the transmission line 20 by turning on and off the semiconductor switch 511, and therefore can perform closing and opening at time intervals shorter than 0.3 seconds, thereby complying with the JEC-2300 and IEEE37.09-2018 standards.
[0030] Second Embodiment Fig. 8 is a diagram showing the configuration of a power transmission system according to a second embodiment. The power transmission system 100 according to the second embodiment differs from the power transmission system 100 according to the first embodiment in that a power transmission line 20 branches downstream of a transformer 30 into a branch path 20a connected to a load 60a, a branch path 20b connected to a load 60b, and a branch path 20c connected to a load 60c, and that system circuit breakers 40a, 40b, and 40c and power system protection devices 50a, 50b, and 50c are installed in the branch paths 20a, 20b, and 20c, respectively. The power system protection devices 50a, 50b, and 50c are similar to the power system protection device 50 provided in the power transmission system 100 according to the first embodiment.
[0031] In the power transmission system 100 according to the second embodiment, if an accident occurs in one of the branch paths 20a, 20b, and 20c, power transmission can be continued in the branch paths 20a, 20b, and 20c where no accident has occurred, thereby improving the stability of the power system.
[0032] Third Embodiment. Figure 9 is a diagram showing the configuration of a power transmission system according to a third embodiment. The power transmission system 100 according to the third embodiment includes a control device 70 that controls a commutator 51 and a grid circuit breaker 40. The commutator 51, the grid circuit breaker 40, and the control device 70 may be connected via a network or a dedicated line. The relay 52 includes a fault detection unit 521, like the relay 52 of the power transmission system 100 according to the first embodiment shown in Figure 2, but does not include a control unit 522. Instead, the control device 70 is provided with a control unit 71. The fault detection unit 521 notifies the control unit 71 of the control device 70 of the occurrence of a fault. The grid circuit breaker 40, the power system protection device 50, and the control device 70 form a power system protection system 90 that protects the power transmission system 100, which is a power system.
[0033] The operation of the power system protection system 90 according to the third embodiment is the same as the operation of the power system protection device 50 according to the first embodiment, except that the control of the commutator 51 and the system circuit breaker 40 is performed by the control unit 71 of the control device 70.
[0034] As with the power system protection device 50 according to the first embodiment, the power system protection system 90 according to the third embodiment prevents current from flowing to the fault location by commutating the current to the commutator 51, and therefore, when the semiconductor switch 511 of the commutator 51 is turned off, the current is no longer commutated to the commutator 51, and power supply to the transmission line 20 is resumed. Therefore, the power transmission system 100 using the power system protection system 90 according to the third embodiment can shorten the time until normal power transmission is restored after an arc is extinguished, compared to a power transmission system that uses a circuit breaker to interrupt the current in the transmission line.
[0035] 10 is a diagram showing the configuration of a power transmission system according to embodiment 4. In the power transmission system 100 according to embodiment 4, a power transmission line 20 branches downstream of a transformer 30 into a branch path 20a connected to a load 60a, a branch path 20b connected to a load 60b, and a branch path 20c connected to a load 60c, and system circuit breakers 40a, 40b, 40c and power system protection devices 50a, 50b, 50c are installed in the branch paths 20a, 20b, 20c, respectively, and the system circuit breakers 40a, 40b, 40c, the power system protection devices 50a, 50b, 50c, and the control device 70 form a power system protection system. The control device 70 is connected to the relays 52a, 52b, and 52c of the power system protection devices 50a, 50b, and 50c of the branch paths 20a, 20b, and 20c, respectively, and when the control device 70 is notified of the occurrence of an accident from any of the relays 52a, 52b, and 52c, it controls the commutators 51a, 51b, and 51c of the power system protection devices 50a, 50b, and 50c that are the same as the relays 52a, 52b, and 52c that notified the occurrence of the accident. The rest of the configuration is the same as that of the power transmission system 100 according to the third embodiment.
[0036] The power transmission system 100 according to the fourth embodiment can continue to transmit power through the branch paths 20a, 20b, and 20c where no accident has occurred in the event of an accident in one of the branch paths 20a, 20b, and 20c, thereby improving the stability of the power system.
[0037] Although the configuration described here is one in which one control device 70 centrally controls the system circuit breakers 40a, 40b, and 40c and the commutators 51a, 51b, and 51c, the system circuit breaker 40a and the commutator 51a, the system circuit breaker 40b and the commutator 51b, and the system circuit breaker 40c and the commutator 51c may be controlled by separate control devices 70.
[0038] The hardware configurations of the control units 522 of the power system protection devices 52a, 52b, and 52c of the power system protection devices 50, 50a, 50b, and 50c according to the first and second embodiments and the control unit 71 of the control device 70 according to the third and fourth embodiments will be described.
[0039] 11 is a diagram illustrating the hardware configuration of the control unit of the relay of the power system protection device according to Embodiments 1 and 2 and the control unit of the control device according to Embodiments 3 and 4. The control unit 522, 71 is realized by a processor 91 that executes various processes, a memory 92 that is a main memory, and a storage device 93 that stores information.
[0040] The processor 91 may be a computing device such as an arithmetic unit, a microprocessor, a microcomputer, a central processing unit (CPU), or a digital signal processor (DSP). The memory 92 may be a non-volatile or volatile semiconductor memory such as a random access memory (RAM), a read-only memory (ROM), a flash memory, an erasable programmable read-only memory (EPROM), or an electrically erasable programmable read-only memory (EEPROM). The storage device 93 stores programs for controlling the system circuit breakers 40, 40a, 40b, and 40c and the power system protection devices 50, 50a, 50b, and 50c. The processor 91 reads the programs stored in the storage device 93 into the memory 92 and executes them. The processor 91 reads the programs stored in the storage device 93 into the memory 92 and executes them, thereby realizing the functions of the control units 522 and 71.
[0041] The configurations shown in the above embodiments are merely examples of the content, and may be combined with other known technologies, or parts of the configurations may be omitted or modified without departing from the spirit of the invention.
[0042] 10 Generator, 20 Transmission line, 20a, 20b, 20c Branch, 30 Transformer, 40, 40a, 40b, 40c System circuit breaker, 50, 50a, 50b, 50c Power system protection device, 51, 51a, 51b, 51c Commutator, 52, 52a, 52b, 52c Relay, 60, 60a, 60b, 60c Load, 70 Control device, 71, 522 Control unit, 80 Ground, 90 Power system protection system, 91 Processor, 92 Memory, 93 Storage device, 100 Power transmission system, 511 Semiconductor switch, 512 Mechanical switch, 521 Fault detection unit, 523 Counter.
Claims
1. A power system protection system comprising: a system circuit breaker that is installed on a transmission line connecting a generator and a load to which power is supplied from the generator, and that cuts off the current flowing through the transmission line when an abnormality occurs in the transmission line; and a commutator that is connected to a portion of the transmission line between the system circuit breaker and the load and to ground, and that in its off state insulates the transmission line from the ground and in its on state conducts the transmission line from the ground, wherein when a ground fault or short circuit is detected in the transmission line, the commutator is turned on to commutate the current flowing through the transmission line to the ground before the system circuit breaker cuts off the current flowing through the transmission line.
2. The power system protection system according to claim 1, further comprising a control unit for controlling the on / off of the commutator and the system breaker.
3. The power system protection system according to claim 2, characterized in that the control unit determines whether the fault has been resolved based on the result of a fault resolution confirmation operation in which the control unit turns on the commutator if the fault is detected when the commutator is turned off a preset time after being turned on.
4. The power system protection system according to claim 3, characterized in that the control unit turns off the system breaker if the fault is not resolved even after performing the fault resolution confirmation operation a preset number of times.
5. The power system protection system according to claim 3 or 4, characterized in that the control unit extends the time for which the commutator is turned on in the fault elimination confirmation operation each time the fault elimination confirmation operation is performed.
6. The power system protection system according to any one of claims 3 to 5, characterized in that the commutator comprises a mechanical switch and a semiconductor switch connected in series to the mechanical switch, and is installed so that the mechanical switch is on the power transmission line side and the semiconductor switch is on the ground side, and the control unit, when turning on the commutator, turns on the mechanical switch and then turns off the semiconductor switch, and when turning off the commutator, turns off the semiconductor switch and then turns off the mechanical switch.
7. The power system protection system according to claim 6, wherein the semiconductor switch comprises a plurality of semiconductor elements connected in parallel or in series with each other.
8. The power system protection system according to any one of claims 1 to 7, characterized in that the transmission line has a plurality of branch paths, and the system circuit breaker and the commutator are installed in each of the plurality of branch paths.
9. A power system protection device installed in a portion of a power transmission line connecting a generator and a load to which power is supplied from the generator, between a system circuit breaker and the load, comprising a commutator connected to a portion of the power transmission line between the system circuit breaker and the load and to ground, and insulating the power transmission line from the ground in an off state and connecting the power transmission line to the ground in an on state, the power system protection device being characterized in that when an accident due to a ground fault or short circuit occurring in the power transmission line is detected, the commutator is turned on to commutate the current flowing through the power transmission line to the ground.
10. The power system protection device according to claim 9, further comprising a control unit for controlling the on / off of the commutator.
11. The power system protection device according to claim 10, characterized in that the control unit determines whether the fault has been resolved based on the result of a fault resolution confirmation operation in which the control unit turns on the commutator if the fault is detected when the commutator is turned off a predetermined time after the commutator is turned on.
12. The power system protection device according to claim 11, characterized in that the control unit extends the time for which the commutator is turned on in the fault elimination confirmation operation each time the fault elimination confirmation operation is performed multiple times.
13. The power system protection device according to any one of claims 10 to 12, characterized in that the commutator comprises a mechanical switch and a semiconductor switch connected in series to the mechanical switch, and is installed so that the mechanical switch is on the power transmission line side and the semiconductor switch is on the ground side, and the control unit, when turning on the commutator, turns on the mechanical switch and then turns off the semiconductor switch, and when turning off the commutator, turns off the semiconductor switch and then turns off the mechanical switch.
14. The power system protection device according to claim 13, wherein the semiconductor switch comprises a plurality of semiconductor elements connected in parallel or in series with each other.
15. A power system protection method using a power system protection system including a system circuit breaker installed on a transmission line connecting a generator and a load to which power is supplied from the generator, and a commutator connected to a portion of the transmission line between the system circuit breaker and the load and to ground, and which insulates the transmission line from the ground in an off state and conducts the transmission line from the ground in an on state, the power system protection method comprising the steps of: determining whether or not an accident due to a ground fault or short circuit has occurred in the transmission line; and, when it is determined that an accident has occurred, turning on the commutator to commutate the current flowing through the transmission line to the ground.
16. A power system protection method as claimed in claim 15, further comprising a step of judging whether or not the fault has been resolved based on the result of a fault resolution confirmation operation of turning on the commutator if the fault is detected when the commutator is turned off after a preset time has elapsed since the commutator was turned on.
17. The method for protecting a power system according to claim 16, further comprising turning off the system breaker if the fault is not resolved even after the fault resolution confirmation operation is performed a preset number of times.
18. The power system protection method according to claim 16 or 17, characterized in that the time for which the commutator is turned on in the fault removal confirmation operation is extended each time the fault removal confirmation operation is performed multiple times.
19. The power system protection method according to any one of claims 16 to 18, characterized in that the commutator comprises a mechanical switch and a semiconductor switch connected in series to the mechanical switch, and is installed so that the mechanical switch is on the power transmission line side and the semiconductor switch is on the ground side, and when the commutator is turned on, the mechanical switch is turned on and then the semiconductor switch is turned off, and when the commutator is turned off, the semiconductor switch is turned off and then the mechanical switch is turned off.
Citation Information
Patent Citations
Gas-insulated circuit breaker and gas-insulated switchgear
JP2004281302A
Ground fault protection device
JP1985059736U
Protector for distribution line
JP1992255421A
High rate current bypass unit
JP1993284641A