Charge / discharge test system

The charge/discharge test system addresses data acquisition and analysis challenges by adjusting sampling intervals and using machine-learned models to detect abnormalities, enhancing the evaluation of battery behavior and reducing analysis time.

WO2024204146A1PCT designated stage expired Publication Date: 2024-10-03TOKYO SEIMITSU CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2024/011859
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-03-30
Filing Date
2024-03-26
Publication Date
2024-10-03

AI Technical Summary

Technical Problem

Conventional charge/discharge test systems face challenges in efficiently acquiring and analyzing detailed data from secondary batteries due to coarse sampling intervals, leading to missed events and increased storage and analysis time, especially during long-term testing of electric vehicle batteries.

Method used

A charge/discharge test system that acquires measurement data at a first sampling interval and outputs evaluation data at a second sampling interval, adjustable based on user requests or conditions, using a large-capacity storage device connected via a network, with a prediction unit to detect abnormal patterns using machine-learned models.

Benefits of technology

Enables detailed evaluation of battery behavior and timely detection of abnormalities, reducing storage needs and analysis time while providing comprehensive data analysis capabilities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2024011859_03102024_PF_FP_ABST
    Figure JP2024011859_03102024_PF_FP_ABST
Patent Text Reader

Abstract

This charge / discharge test system includes a test device 20-1 that connects secondary batteries 15-1 … 15-n and performs a charge / discharge test, wherein the charge / discharge test system generates measurement data DT1 from signals indicating battery states generated by the test devices 20-1 … 20-m and analyzes the measurement data to determine characteristics of the batteries. According to the charge / discharge test system comprising: the test device that acquires the measurement data at a first sampling interval f1; a large-capacity storage device 1(100) that stores the measurement data; and an evaluation data output means for extracting the measurement data at a second sampling interval f2 that is A times the first sampling interval (A represents an integer of 2 or more) on the basis of the stored measurement data, and outputting the measurement data as evaluation data DT2, detailed data for long-term tests and abnormal conditions can be output arbitrarily, and current, voltage, temperature, etc. can be evaluated in detail.
Need to check novelty before this filing date? Find Prior Art

Description

Charge / Discharge Test System

[0001] The present invention relates to a charge / discharge test system for performing a charge / discharge test on a charge target such as a secondary battery.

[0002] In recent years, the demand for electric vehicles has been increasing due to the trend of strengthening environmental regulations worldwide and reducing energy costs. Electric vehicles (EVs) and fuel cell vehicles (FCVs) emit carbon dioxide (CO 2 ), demand for electric vehicles is rapidly increasing due to the global movement towards decarbonization. Electric vehicles are vehicles that can run using only the driving force of an electric motor, and are classified into electric vehicles (EVs) that use secondary batteries (batteries) as the power source for the high-output motor used for driving, and fuel cell vehicles (FCVs) that use fuel cells. Secondary batteries, which support electric vehicle (EV) technology, are also seeing a significant increase in demand as key devices, while the total infrastructure supporting electric vehicles, from the mining of raw materials to manufacturing and reuse, is also becoming increasingly CO2-free. 2 , and the demand for energy conservation is increasing.

[0003] The same applies to testing facilities after battery production, and as the facilities expand, further reductions in the running costs and energy savings of the equipment itself are required. Large-capacity secondary batteries used for vehicle electrification, etc., are subjected to long-term testing to ensure reliability, and evaluation tests are conducted to determine their characteristics from the resulting vast amounts of data. For example, secondary batteries are used under harsh conditions, such as frequent repetition of charging and discharging and sudden fluctuations in load, and therefore, charging tests and discharging tests (referred to as charge-discharge tests) are conducted using charge-discharge test equipment during production, and quality is strictly controlled.

[0004] Patent Document 1 describes that since charging and discharging tests on secondary batteries are tests that take a long time and the transfer speed and acquisition frequency are limited, the system provides a low-speed measurement mode in which the characteristics of the secondary battery are measured and transmitted and received via LAN to a charging and discharging test device, and a high-speed measurement mode in which the measurement results are stored in a memory unit as analog signals via a system bus inside the control device.

[0005] Patent document 2 describes that in order to ensure improved equipment availability, a setting unit sets a charge / discharge pattern corresponding to a test charge / discharge body that is the target of a charge / discharge test among charge / discharge bodies, and generates a power prediction pattern based on the charge / discharge pattern.

[0006] JP 2016-121931 A JP 2023-10581 A

[0007] In the above-mentioned conventional technology, the output data from the charge / discharge test system is stored in a HDD, which is a storage device of a control personal computer dedicated to the device, and is used for data analysis and diagnosis. Typically, data is acquired at a predetermined time interval (sampling interval) and recorded sequentially in the HDD.

[0008] Generally, battery evaluation tests using charge / discharge test equipment are often long-term tests, and if the sampling interval is shortened, the amount of acquired data tends to become enormous, causing problems such as putting pressure on the HDD storage area and making data analysis too complicated. For this reason, the sampling interval is sometimes set to a certain length (rough), for example, several seconds to several tens of seconds.

[0009] However, if the sampling interval is too long, there is a problem that events that occur between two sampling times (times) are not recorded. For example, even if a signal important for evaluating battery performance occurs between sampling times, the signal is not recorded (because it is not a sampling time) and is overlooked. Furthermore, even if the device stops due to some abnormality and attempts are made to trace back the cause, if the sampling interval is too long, it is difficult to find signs that may have caused the abnormality (specific event).

[0010] On the other hand, shortening the sampling interval poses the problem of enormous amounts of data. The increased data volume not only puts strain on storage space, but also increases the time required for data analysis (to extract specific events). Generally, battery evaluation tests are often conducted simultaneously on the same or different batteries. In this case, an increase in the amount of test data for a single secondary battery significantly increases the amount of data handled in the entire evaluation test. Charge / discharge tests on secondary batteries are sometimes conducted continuously for several months, making it cumbersome for users to analyze the vast amounts of data obtained, resulting in the problem of a long time required to obtain evaluation results.

[0011] The object of the present invention is to solve the problems of the prior art by providing a charge / discharge test system that is capable of long-term testing, can output detailed data on transient and abnormal conditions at will after the test, and can also perform detailed evaluation of changes in battery behavior (current, voltage, temperature, etc.) during the test.

[0012] The present invention that achieves the above object is as follows.

[0013] [1] A charge / discharge test system that connects a secondary battery to perform a charge / discharge test and outputs evaluation data based on measurement data indicating a battery state for characteristic analysis of the secondary battery obtained by the test device, the charge / discharge test system comprising: the test device that acquires the measurement data at a first sampling interval, a large-capacity storage device that stores the measurement data, and evaluation data output means that extracts the measurement data at a second sampling interval that is A times the first sampling interval (A is an integer of 2 or greater) based on the stored measurement data and outputs the measurement data as evaluation data. [2] The charge / discharge test system according to [1], characterized in that the test device has an AC power supply, an AC / DC converter, a plurality of charge / discharge devices connected via a bus to the AC / DC converter, and a controller that controls the charge / discharge devices to perform a charge / discharge test of the secondary battery, and further comprises: a control device connected to the test device via the controller and that outputs an instruction to set a charge / discharge pattern for the secondary battery to the controller; and the large-capacity storage device connected to the test device. [3] The charge / discharge test system according to [2], characterized in that the mass storage device is connected to the test device via a network. [4] The charge / discharge test system according to [2], characterized in that the mass storage device is connected to the test device via the control device. [5] The charge / discharge test system according to [1], wherein the evaluation data output means adjusts the magnitude of A based on a user request or predetermined conditions. [6] The charge / discharge test system according to [1], wherein the evaluation data output means re-extracts data from the measurement data for a predetermined time period at a third sampling interval that is B times the first sampling interval (B represents an integer greater than or equal to 1 and less than A) based on a user request or predetermined conditions, and outputs the data as second evaluation data. [7] The charge / discharge test system according to [6], further comprising a prediction unit that determines an abnormal characteristic pattern based on the measurement data by comparing it with a predetermined standard, and predicts an abnormal tendency or issues a warning.[8] The charge / discharge test system according to [7], wherein the prediction unit includes a trained model that has been machine-learned in advance using a training data set that is labeled with the occurrence status of an abnormality in relation to the time-dependent changes in the measurement data, and predicts the abnormal tendency using the trained model based on the measurement data acquired by the test device.

[0014] According to the present invention, it is possible to provide a charge / discharge test system that is capable of long-term testing, can output detailed data on transient and abnormal conditions at will after the test, and can also perform detailed evaluation of changes in battery behavior (current, voltage, temperature, etc.) during the test.

[0015] FIG. 1 is a block diagram showing the main parts according to one embodiment of the present invention. FIG. 2 is a block diagram showing the flow up to outputting evaluation data according to one embodiment of the present invention. FIG. 3 is an explanatory diagram showing the acquisition state of evaluation data and measurement data due to differences in sampling intervals. FIG. 4 is an explanatory diagram showing the acquisition state of measurement data according to one embodiment of the present invention. Graphs of battery voltage and current versus time showing examples of measurement data and evaluation data according to one embodiment. FIG. 5 is an explanatory diagram showing an example of acquisition of second evaluation data in the event of an abnormality according to one embodiment. FIG. 6 is an explanatory diagram showing details of an example of acquisition of second evaluation data in the event of an abnormality according to one embodiment. FIG. 7 is a diagram showing voltage versus time showing an example of acquisition of measurement data according to one embodiment. FIG. 8 is a block diagram showing the main parts according to another embodiment of the present invention.

[0016] An embodiment of the present invention will now be described in detail with reference to the drawings. Fig. 1 is a block diagram showing the main components of an embodiment of the present invention. A charge / discharge test system 10 performs charge / discharge tests in parallel on a plurality of secondary batteries 15-1, 15-2, 15-3, ... 15-n (n is an integer) that are to be subjected to the charge / discharge tests.

[0017] The secondary batteries 15-1, 15-2, 15-3, ... 15-n are various known secondary batteries such as lithium ion batteries, nickel metal hydride batteries, and all-solid-state N batteries, and are cell batteries that make up high-voltage batteries that supply power to the drive motors of electric vehicles, etc., and for example, the cell batteries are stacked to produce a high voltage (100V or more, for example 200 to 400V) to form an in-vehicle battery pack.

[0018] Each of the test devices 20-1 to 20-m (m represents an integer) includes an AC (alternating current) power supply 11, an AC / DC (alternating current / direct current) converter 12, a controller 13, and a plurality of ET (Energy Testing System) devices (charging / discharging devices) 14-1, 14-2, 14-3, ..., 14-n. The test devices 20-1 to 20-m are connected to a network 2 via the controller 13. Note that the numbers represented by n and m may be the same or different.

[0019] The control device 3 is connected to the network 2 and inputs test conditions etc. to the test devices 20-1 to 20-m. The AC / DC converter 12 is bus-connected to each of the plurality of ET devices 14-1, 14-2, 14-3, ... 14-n.

[0020] The controller 13 is a control device such as a programmable logic controller (PLC) that controls the multiple ET devices 14-1, 14-2, 14-3, ..., 14-n, and has a static RAM or SSD cache memory for temporarily storing data, a network controller, etc. The secondary batteries 15-1, 15-2, 15-3, ..., 15-n are connected to the ET devices 14-1, 14-2, 14-3, ..., 14-n, respectively.

[0021] Based on input instructions from the control device 3, the controller 13 controls the AC / DC converter 12 and each of the ET devices 14-1, 14-2, 14-3, . . . 14-n to perform charge / discharge tests on the secondary batteries 15-1, 15-2, 15-3, .

[0022] The control device 3 is, for example, a PC, a terminal other than a PC, a mobile terminal, or a tablet. The control device 3 is connected to the controller 13 via a network, and includes an operation unit such as a keyboard and a mouse, and a display unit such as a display.

[0023] The control device 3 outputs to the controller 13, via an operation unit, instructions to set each charge / discharge pattern for the secondary batteries 15-1, 15-2, 15-3, ..., 15-n of the ET devices 14-1, 14-2, 14-3, ..., 14-n. This causes the controller 13 to set each charge / discharge pattern for the secondary batteries 15-1, 15-2, 15-3, ..., 15-n to be tested for the ET devices 14-1, 14-2, 14-3, ..., 14-n.

[0024] The control device 3 is used for various operations of the test device 20-1, and its display unit is used for displaying various information, in addition to setting operations for individually setting the charge / discharge patterns of the secondary batteries 15-1, 15-2, 15-3, ..., 15-n using an operation unit. The control device 3 also manages information on devices present on the network 2 and configuration information for related services (IP addresses, port connection information, line information, etc.).

[0025] The secondary batteries 15-1, 15-2, 15-3, ..., 15-n are placed in a thermostatic chamber 16 and are connected to the controller 13 via a temperature measurement unit 18 for temperature management. The temperature of the thermostatic chamber 16 is controlled by the controller 13 via a thermostatic chamber control unit 17. The ET devices 14-1, 14-2, 14-3, ..., 14-n charge and discharge (or perform charge and discharge tests) on the secondary batteries 15-1, 15-2, 15-3, ..., 15-n in the thermostatic chamber 16 in accordance with the charge and discharge patterns of the secondary batteries 15-1, 15-2, 15-3, ..., 15-n set by the controller 13.

[0026] The NAS server 1 is a storage device with a RAID function that can save and share files via the network 2, and is a large-capacity storage device equipped with a HDD or SSD with a capacity of several terabytes or more, with functions specialized for file management. The NAS server 1 also preferably has functions for managing backups and access rights, and the ability to connect to the network 2 from a remote location and enable remote access as a virtual network or remote desktop. These functions may also be provided by the control device 3.

[0027] Furthermore, the NAS server 1 may be used as cloud storage that provides computer resources and a service for saving and sharing files over the Internet by communicating with client terminals 4 and 5 via the network 2. In this case, files are uploaded and downloaded via a web browser or an app.

[0028] When a virtual network is constructed on the NAS server 1 or the control device 3, recorded information is converted into a database by inserting data into a database management system within the virtual network, searching, etc., and various services are provided that allow objects such as HTML and images to be viewed and modified using a web browser on terminals 4 and 5.

[0029] FIG. 2 is a block diagram showing the process up to the output of evaluation data. Test conditions are first input by the control device 3 (arrow AR1). The test conditions may include the overall test time, a first sampling interval (period) for acquiring measurement data, and the like. The first sampling interval is the shortest compared to the second and third sampling intervals described below, and serves as the basic sampling interval. The first sampling interval is not particularly limited and may be set appropriately depending on the hardware and software limitations of each component and the capacity of the mass storage device. The first sampling interval may be a predetermined fixed value, in which case the first sampling interval need not be included in the test conditions.

[0030] Next, the test devices 20-1 to 20-m perform charge / discharge tests on the secondary batteries 15-1, 15-2, 15-3, ..., 15-n (arrow AR2). Next, the test devices 20-1 to 20-m obtain signals indicating the battery state, such as voltage and temperature, from the secondary batteries 15-1, 15-2, 15-3, ..., 15-n at a first sampling interval, and acquire measurement data DT1 (arrow AR3).

[0031] Next, the control device 3 extracts measurement data at a second sampling interval based on the measurement data DT1 acquired at the first sampling interval to generate evaluation data DT2 (arrow AR4). Here, the second sampling interval is set to A times the first sampling interval (A is an integer equal to or greater than 2). For example, if the first sampling interval is 100 milliseconds, the second sampling interval can be set to 10 times that interval, or 1000 milliseconds.

[0032] By the above process, the number of data points included in the evaluation data DT2 is set to 1 / A times that of the measurement data DT1, making it easier for the user to evaluate. The obtained evaluation data DT2 is then output (arrow AR5). Note that the second sampling interval may be set and stored in advance by the user, or may be predetermined.

[0033] The evaluation data DT2 is more suitable for overlooking changes in measured values ​​over time because the sampling interval (cycle) is set relatively long (rough). On the other hand, events that occur between sampling times are not reflected. Therefore, if an abnormality occurs and the test is terminated, and you want to go back in time to investigate signs of the abnormality, evaluation using data with shorter sampling intervals is more suitable.

[0034] 3A and 3B are explanatory diagrams showing the acquisition state of evaluation data and measurement data depending on the sampling interval. Fig. 3A is an explanatory diagram of evaluation data DT2 extracted at a second sampling interval f2. The horizontal axis represents time T, and data is extracted at the second sampling interval f2 in the order of times t1, t2, and t3, resulting in the evaluation data DT2. If the second sampling interval f2 is set sufficiently long, the evaluation data DT2 allows for an understanding of the overall data trends throughout the entire test period.

[0035] On the other hand, if some kind of abnormality occurs at a certain time tx, the measurement value at the time of the abnormality occurrence may not be included in the evaluation data DT2. If an abnormality occurs (at time tx) after time t2 and the charge / discharge test system stops, data for time t3 is not included in the evaluation data DT2, so it can be understood that "some kind of abnormality occurred after time t2 but before time t3, and the test ended." However, it is difficult to obtain information from the evaluation data DT2 as to when the abnormality actually occurred and the time ty at which the symptom of the abnormality appeared. In other words, if the test ends normally without any problems, it can be said that sufficient data has been obtained for evaluating the performance of the secondary battery if the evaluation data DT2 provides an overview of the entire test time. However, if an abnormality occurs, the evaluation data DT2 alone may not be sufficient for determining the cause.

[0036] FIG. 3B is an explanatory diagram of measurement data DT1 measured at a first sampling interval f1. Similarly, the horizontal axis represents time T, and data is acquired from time t1 to tq (q represents an integer) at the first sampling interval f1. The measurement data DT1 likely contains data acquired at or immediately before the occurrence of an abnormality (time tx). Furthermore, by tracing back in time, it is possible to determine the time ty when the symptom occurred. However, because all data is stored in the memory device 50, conventional charge / discharge test systems (with built-in memory devices) tend to have insufficient data capacity. Furthermore, because a large amount of data is acquired, analysis can be cumbersome when attempting to obtain data that provides an overview of the entire system.

[0037] Furthermore, even if a user wishes to obtain measurement data within a specific range, for example, around time t3, the user must search for measurement data around time t3 from a vast amount of data, which can be a cumbersome operation.

[0038] 4 is an explanatory diagram showing the state of measurement data acquisition in an embodiment of the charge / discharge test system of the present invention. Test devices 20-1 to 20-m acquire measurement data DT1 according to a first sampling interval and store it in a mass storage device 100. The mass storage device 100 corresponds to the NAS server 1 in the example shown in FIG.

[0039] The control device 3, which includes an evaluation data output means, extracts data from the measurement data DT1 stored in the large-capacity storage device 100 at a second sampling interval in response to a request (arrow C1) from the terminals 4 and 5 or in response to predetermined conditions, and outputs the extracted data as evaluation data DT2. For example, if the second sampling interval is 10 times the first sampling interval, the evaluation data DT2 is output as data d-f10; if it is 100 times the first sampling interval, the evaluation data DT2 is output as data d-f100; if it is 1000 times the first sampling interval, the evaluation data DT2 is output as data d-f1000.

[0040] Since the evaluation data DT2 is extracted based on the already acquired measurement data DT1, it can be output again as needed from a single measurement result. For example, if relatively rough evaluation data DT2 is initially output as data d-f1000, and it is determined that detailed evaluation data DT2 during transient or abnormal conditions is needed, a finer (narrower) second sampling interval can be specified, and the evaluation data DT2 can be output as, for example, data d-f100 or data d-f10. In other words, detailed evaluation data on overall characteristics and battery abnormalities and transient changes can be obtained even after the test with a single evaluation data. Because charge / discharge tests are performed over a long period of time, the ability to obtain a variety of data in a single test can be an important performance feature.

[0041] FIG. 5 is a graph of battery voltage and current versus time showing examples of measurement data and evaluation data. FIG. 5(A) is a graph of measurement data DT1 obtained at a first sampling interval f1. This result allows detailed understanding of changes in the voltage and current of the secondary battery during the observation time (test time) of 0 to 1000 ms. On the other hand, FIG. 5(B) is a graph of evaluation data DT2 obtained at a second sampling interval f2. This result allows understanding that there are no significant changes overall in the voltage and current of the secondary battery during the observation time (test time) of 0 to 1000 ms. If there is no abnormality in the battery state (each measurement data), obtaining evaluation data DT2 is often sufficient for evaluating the performance of the secondary battery.

[0042] 6A and 6B are explanatory diagrams of an example of output of second evaluation data, in which Fig. 6A is an explanatory diagram of measurement data DT1 measured at a first sampling interval f1, and Fig. 6B is an explanatory diagram of evaluation data DT2 extracted based on the measurement data DT1 at a second sampling interval f2 that is A times the first sampling interval f1 (A is an integer of 2 or more).

[0043] The relationship between the measurement data DT1 and the evaluation data DT2 has already been explained. Data is extracted from the measurement data DT1 at a second sampling interval f2, which is A times the first sampling interval f1, by the control device 3 (whose evaluation data output means is implemented as application software or the like), and the extracted data is converted into evaluation data DT2, which includes measurement values ​​at times t1, t2, and t3.

[0044] 6C is an explanatory diagram of the second evaluation data generated by re-extracting data at a third sampling interval f3 from the measurement data DT1 around the time tx when the abnormality occurred and the time ty when the signal predicting the abnormality was obtained. The above processing is performed by the control device 3 (in which the evaluation data output means is implemented as application software or the like).

[0045] The second evaluation data DT3-1 is data extracted from the measurement data DT1 for a time period around time tx when the abnormality occurred. The third sampling interval f3 is set to be equal to or greater than the first sampling interval f1 and shorter than the second sampling interval f2. Specifically, the third sampling interval f3 is adjusted to be B times the first sampling interval f1. Here, B is an integer that satisfies 1≦B<A, so the third sampling interval f3 is shorter than the second sampling interval f2. Furthermore, the second evaluation data DT3-2 is extracted from the measurement data DT1 around time ty when a signal indicating a symptom of the cause of the abnormality was obtained.

[0046] Since the re-extraction range of the second evaluation data DT3-1 and DT3-2 is limited to a predetermined time period (a range of interest), even if the third sampling interval f3 is made closer to the first sampling interval f1, the number of data points to be evaluated is kept small, making analysis easier. The re-extraction time period may be specified by the user. Furthermore, the third sampling interval f3 may be determined by a user request or may be determined in advance.

[0047] Even if the user evaluates the characteristics of secondary batteries 15-1, 15-2, 15-3, ... 15-n at the second sampling interval f2, when the user notices an abnormality, the user can specify a predetermined time range and obtain detailed measurement data immediately before the abnormality from the mass storage device 100 as second evaluation data DT3-1, DT3-2.

[0048] With the above configuration, the user can analyze data on an abnormal battery using a single evaluation data set. Furthermore, the user can obtain measurement data from several cycles prior to the abnormality, as shown in FIG. 6C. This allows the user to explore trends in the measurement data prior to the abnormality using a single evaluation data set, thereby gaining insights into predictions and warnings.

[0049] 7A and 7B are explanatory diagrams showing details of an example of acquisition of second evaluation data during an abnormality. Fig. 7A is a diagram showing the change in voltage over time of secondary batteries 15-1, 15-2, 15-3, ..., 15-n. On the X-axis (time T), a first sampling interval f1 and a second sampling interval f2 are plotted.

[0050] Here, voltages V1 and V2 are data extracted at the second sampling interval f2. That is, the evaluation data DT2 includes the extracted measured values ​​of (time T, voltage V) (ta, V1) (tb, V2). The abnormal value occurred at time tx (voltage V3), so it does not appear in the evaluation data DT2. In this case, the abnormal value can be detected by setting the third sampling interval f3 to an appropriate value smaller than the second sampling interval f2 and generating the second evaluation data within the target range of times ta to tb. Specifically, the abnormal value can be detected as a voltage change ΔV / Δt, etc. Note that this voltage change ΔV / Δt may be monitored and saved by the control device 3, allowing warnings and cautions to be displayed during testing.

[0051] FIG. 7B shows a case where the voltage of the secondary battery gradually increases and changes over time. The mass storage device 100 stores the measurement data DT1 at a first sampling interval f1. Therefore, the control device 3, which has machine learning capabilities, can predict the trend (abnormal trend) of the measurement values ​​over the subsequent period td2 from the data at the initial measurement time td1 using a trained model pre-machined from a training data set labeled with the trend of the changing measurement data DT1 (the change in the measurement data DT1 over time) and the presence or absence of an abnormality (occurrence status), and generate a warning of the occurrence of an abnormality ab1. Note that in the above example, the occurrence of an abnormality ab1 is predicted from the data at the initial measurement time td1. However, the trained model can also predict and generate an abnormality warning from data for any period.

[0052] Since the control device 3 manages the multi-channel test devices 20-1 to 20-m, it can statistically compare, analyze, and interpret abnormal characteristic patterns from the same test cycle to predict and warn of future characteristics and abnormal trends.In addition, the control device 3's machine learning function makes it possible to output diagnostic evidence and quantitative data after the test is completed.

[0053] The battery status measurement items of the secondary batteries 15-1, 15-2, 15-3, ..., 15-n based on the evaluation data are voltage (V), current (A), power (W), charge current amount (Ah), discharge current amount (Ah), balance current amount (Ah), charge electric energy amount (Wh), discharge electric energy amount (Wh), balance electric energy amount (Wh), and temperature (°C). Abnormalities in the secondary batteries 15-1, 15-2, 15-3, ..., 15-n include when the voltage (V) is outside the upper or lower limit, when the current (A) exceeds the upper limit, when the power (W) exceeds the upper limit, when the charge current amount (Ah), the discharge current amount (Ah), or the balance current amount (Ah) reaches its upper limit, when the charge electric energy amount (Wh), the discharge electric energy amount (Wh), or the balance electric energy amount (Wh) reaches its upper limit, and when the temperature (°C) is outside the upper or lower limit, and each of these abnormalities is detected during and after the test.

[0054] FIG. 8 is a time-voltage diagram illustrating an example of measurement data acquisition. Each line in FIG. 8 shows a comparison of voltage, which is one of the measurement data, between secondary batteries 15-1, 15-2, 15-3, ... 15-n being tested by multiple test devices 20-1, 20-2, 20-3, 20-m. This comparison function compares measurement data from multiple test devices 20-1, 20-2, 20-3, 20-m, which are other channels during test operation, and issues a notification of an abnormality or warning if a difference ΔV occurs in any of the data. The basis for the abnormality or warning determination can be clearly indicated along with this notification, and can be output as detailed evaluation data, or second evaluation data. Note that comparison of data between secondary batteries 15-1, 15-2, 15-3, ..., 15-n is possible between different test devices 20-1, 20-2, 20-3, 20-m, and also between secondary batteries 15-1, 15-2, 15-3, ..., 15-n of test devices 20-1, 20-2, 20-3, 20-m. Comparing many secondary batteries 15-1, 15-2, 15-3, ..., 15-n (between the same or different test devices) may enable more accurate determination.

[0055] Fig. 9 is a block diagram showing the main components according to another embodiment. In Fig. 1, the controllers 13 provided in the test devices 20-1 to 20-m are connected to the control device 3 via the network 2, but in Fig. 9, the controllers 13 provided in the test devices 20-1 to 20-m are connected to the control device 3 via a bus, and the control device 3 is connected to the network 2, but the rest is the same as Fig. 1. A network controller, etc. is provided in the control device 3, and also manages service configuration information (IP addresses, port connection information, line information, etc.).

[0056] The charge / discharge test system is a computer system, and has the following functions: (1) a function to output the evaluation data DT2 described in FIG. 2; (2) a function to extract data from the measurement data DT1 stored in the mass storage device 100 described in FIG. 4 at a second sampling interval f2 specified in advance or in response to a user request, and output the extracted data as evaluation data DT2; and a function to display the measurement data DT1 and the evaluation data DT2 within a predetermined time range, as shown in FIG. 5; (3) a function to output second evaluation data DT3-1 and DT3-2 in order to obtain detailed data in the event of an abnormality, as described in FIG. 6; (4) a function to determine an abnormal characteristic pattern based on the amount of change in the measurement data of the secondary batteries 15-1, 15-2, 15-3, ... 15-n described in FIG. 7, and to predict and warn of future characteristics and abnormal trends; (5) A function of comparing voltages, which are one of the measurement data, of secondary batteries 15-1, 15-2, 15-3, ..., 15-n being tested by the multiple test devices 20-1, 20-2, 20-3, 20-m described in Figure 8 and clearly indicating the basis for determining an abnormality or warning. The hardware configuration for realizing each of the above functions can be flexibly changed. Furthermore, the present invention can also be realized by supplying a computer program that implements each of the functions described in the above embodiments to a computer, and having one or more processors of the computer read and execute the program.

[0057] For example, in the description of FIG. 1, the mass storage device 100 in FIG. 4 is the NAS server 1 connected to the test devices 20-1, 20-2, 20-3, and 20-m via the network 2, but the mass storage device 100 may be provided in the controller 13 or the control device 3. Furthermore, the mass storage device 100 is not limited to storage with a RAID function, and may be an NVMe-connected M.2 SSD or cloud storage available on the Internet.

[0058] Furthermore, it is preferable that the application software or library, which is a computer program that realizes the above-mentioned functions (1) to (5), be installed in the control device 3 and used by the terminals 4 and 5, but some or all of it may be provided by the controller 13 or the NAS server 1. In this case, the NAS server 1 may provide each function as a cloud service as cloud storage.

[0059] Furthermore, the machine learning function described in Figure 7 may be configured as a cloud service in which measurement data is sent from the control device 3 via the network 2 to a server computer capable of high-speed processing, and the results of statistically comparing, analyzing, and analyzing abnormal characteristic patterns are received.

[0060] 1 NAS server, 2 network, 3 control device, 4 terminal, 5 terminal, 10 charge / discharge test system, 11 (AC) power supply, 12 AC / DC converter, 12 (AC / DC) converter, 13 controller, 14-1 to 14-n ET device, 15-1 to 15-n secondary battery, 16 thermostatic chamber, 17 thermostatic chamber control unit, 18 temperature measurement unit, 20-1 to 20-m test device, 50 storage device, 100 mass storage device

Claims

1. A charge / discharge test system that connects a secondary battery to a test device for performing a charge / discharge test, and outputs evaluation data based on measurement data obtained by the test device that indicates the battery state for characteristic analysis of the secondary battery, the charge / discharge test system comprising: the test device that obtains the measurement data at a first sampling interval; a large-capacity storage device that stores the measurement data; and an evaluation data output means that extracts the measurement data at a second sampling interval that is A times the first sampling interval (A is an integer equal to or greater than 2) based on the stored measurement data, and outputs the measurement data as evaluation data.

2. The charge / discharge test system according to claim 1, characterized in that the test equipment comprises an AC power source, an AC / DC converter, a plurality of charge / discharge devices bus-connected to the AC / DC converter, and a controller that controls the charge / discharge devices to perform a charge / discharge test on the secondary battery, a control device that is connected to the test equipment via the controller and outputs to the controller an instruction to set a charge / discharge pattern for the secondary battery, and the large-capacity storage device that is connected to the test equipment.

3. The charge / discharge test system according to claim 2, wherein the large-capacity storage device is connected to the test device via a network.

4. The charge / discharge test system according to claim 2, wherein the large-capacity storage device is connected to the test device via the control device.

5. The charge / discharge test system according to claim 1, wherein said evaluation data output means adjusts the magnitude of A based on a request from a user or on a predetermined condition.

6. The charge / discharge test system according to claim 1, wherein the evaluation data output means re-extracts data from the measurement data for a predetermined time period at a third sampling interval that is B times the first sampling interval (B is an integer equal to or greater than 1 and less than A) based on a request from a user or on predetermined conditions, and outputs the data as second evaluation data.

7. The charge / discharge test system according to claim 6, further comprising a prediction unit which judges an abnormal characteristic pattern based on the measurement data by comparing it with a predetermined standard, and predicts an abnormal tendency or issues a warning.

8. The charge / discharge test system of claim 7, wherein the prediction unit includes a trained model that has been machine-learned in advance using a training data set in which the occurrence of anomalies in relation to the time-dependent changes in the measurement data is labeled, and the trained model predicts the abnormal tendency based on the measurement data acquired by the test device.

Citation Information

Patent Citations

  • Charge-discharge test system, charge-discharge test device, and measurement method

    JP2016121931A

  • Digital oscilloscope

    JP1993157769A

  • Waveform measuring apparatus

    JP2003279599A

  • Recording instrument, recording method, and recording program

    JP2014169875A

  • Data transmission device, data transmission method, computer program, data transmission system, and data reception device

    JP2020046862A