Power sharing planning device, power sharing planning method, and program

The power interchange planning device optimizes renewable energy usage in off-grid EV charging stations by calculating and managing power distribution among EVs based on their usage schedules and SOC levels, ensuring efficient energy transfer without hindering their mobility.

WO2024247051A1PCT designated stage expired Publication Date: 2024-12-05NT T INC
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
PCT/JP2023/019951
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-29
Publication Date
2024-12-05

AI Technical Summary

Technical Problem

Off-grid EV charging stations powered by solar carports face challenges in utilizing renewable energy efficiently, as EVs cannot be charged at night using PV power, and existing technologies lack a systematic approach to manage power interchange between EVs to avoid hindering their usage.

Method used

A power interchange planning device that calculates future power consumption based on usage schedules and SOC levels of multiple EVs, creating a plan to distribute power without affecting mobility, using parameters like distance to the destination and SOC fluctuation to optimize renewable energy utilization.

Benefits of technology

Enables efficient power interchange between EVs, maximizing renewable energy usage without impacting their mobility, by determining the right amount of power to transfer between vehicles based on their scheduled usage and stored energy levels.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2023019951_05122024_PF_FP_ABST
    Figure JP2023019951_05122024_PF_FP_ABST
Patent Text Reader

Abstract

Provided is a power sharing planning device for creating a plan for sharing power among a plurality of electric mobile devices, the power sharing planning device comprising: a usage schedule acquisition unit that acquires a usage schedule of each electric mobile device; and a plan creation unit that calculates an amount of future power consumption of each electric mobile device on the basis of the usage schedule, and creates a power sharing plan among the plurality of electric mobile devices on the basis of the amount of future power consumption and an amount of power stored in each electric mobile device.
Need to check novelty before this filing date? Find Prior Art

Description

Power interchange planning device, power interchange planning method, and program

[0001] The present invention relates to a technology for exchanging power between EVs (Electronic Vehicles).

[0002] To make effective use of renewable energy (e.g., photovoltaic power generation (PV)), the introduction of off-grid EV charging stations (not connected to the power company's power grid) powered by solar carports is progressing. However, because PV can only generate electricity during the day, EVs that return to solar carports at night cannot be charged with PV power. Therefore, it is generally necessary to charge EVs using power from the grid.

[0003] When there are two or more EVs in a solar carport, a technology is known that enables the improvement of renewable energy utilization rate without using electricity from the grid by transferring (supplying) electricity from an EV charged by PV during the day to an EV that returns at night (Non-Patent Documents 1 and 2).

[0004] Hioki E.E. Corporation and Yanekara Co., Ltd. will begin demonstration of an off-grid EV charging system utilizing V2V charging technology. https: / / prtimes.jp / main / html / rd / p / 000000005.000067381.html Solar charging and discharging system for EVs that enables peak power cuts with optimal charging and discharging control / Standard EV charging outlet. https: / / www.nedo.go.jp / content / 100953986.pdf

[0005] When electric vehicles share power between EVs, it is necessary to do so in a way that does not interfere with the use of the EVs supplying the power. However, there is no established technology for creating a power exchange plan that determines how much power should be exchanged from which EV to which other EV. For example, if the total remaining energy (e.g., SOC: State Of Charge) of all EVs staying in a solar carport is exchanged so that the SOC of all EVs is equal, some EVs may not have enough power.

[0006] The present invention has been made in view of the above points, and has an object to provide a technique for exchanging power between EVs while minimizing the disruption to the use of the EVs.

[0007] According to the disclosed technology, there is provided a power interchange planning device that creates a plan for power interchange between a plurality of electric mobile devices, the power interchange planning device comprising: a usage schedule acquisition unit that acquires a usage schedule for each electric mobile device; and a plan creation unit that calculates the future power consumption of each electric mobile device based on the usage schedule, and creates a power interchange plan between the plurality of electric mobile devices based on the power consumption and the amount of power stored in each electric mobile device.

[0008] The disclosed technology provides a technology for power interchange between EVs while minimizing disruption to EV use.

[0009] FIG. 1 is a diagram showing an example of the configuration of an EV-to-EV power interchange system in the present embodiment. FIG. 2 is a flowchart for explaining an example of the operation of the power interchange planning device 100. FIG. 3 is a diagram showing an example of an interchange policy. FIG. 4 is a diagram showing an example of usage schedule information. FIG. 5 is a diagram showing an image of the usage schedule. FIG. 6 is a diagram showing an example of an interchange plan. FIG. 7 is a diagram showing an example of the configuration of the power interchange planning device 100. FIG. 8 is a diagram showing an example of the hardware configuration of the power interchange planning device 100.

[0010] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. The embodiment described below is merely an example, and the embodiment to which the present invention is applied is not limited to the following embodiment.

[0011] In the following description, the target of power interchange is an EV. An EV may also be called an electric vehicle. In this embodiment, the EV is assumed to be a vehicle used for business purposes, but the EV is not limited to an automobile. The EV may also be an agricultural machine, a motorcycle, a work vehicle (forklift), a ship, an airplane, or the like.

[0012] In the example described below, the planned use is the planned use for the day after the day of the plan creation, but this is just an example. The planned use is not limited to the planned use for the day after.

[0013] (Outline of the embodiment) In this embodiment, a situation is assumed in which one or more EVs are used. When each EV is not in use, it is placed in a solar carport equipped with a PV device, and is charged by PV during the day. When charging by PV is not possible, such as at night, power is shared between two or more EVs placed in the solar carport.

[0014] Specifically, first, the power interchange planning device 100 sets an interchange policy based on the planned use of each EV for the next day. The interchange policy is a policy regarding how power should be interchanged between two or more EVs. The parameters and calculation methods used in calculations to create the interchange plan are determined according to the interchange policy.

[0015] The power interchange planning device 100 calculates the SOC (corresponding to the amount of power consumption P) required for each EV on the next day from reference parameters (parameters based on the interchange policy, for example, the distance L from the departure point to the destination on the next day) obtained from the planned use of each EV on the next day. For example, the SOC required for the next day may be calculated by "distance L / electricity cost d" using the electricity cost listed in the EV's catalog, or the SOC required for the next day may be calculated from past history.

[0016] The power interchange planning device 100 creates a plan for interchange of power between EVs based on the calculation results of the SOC required for each EV on the following day, and executes interchange based on the plan.

[0017] For example, the power interchange planning device 100 may calculate the total SOC (amount of stored power) of all EVs belonging to a solar carport and create a plan for power distribution among the EVs based on that total amount. The power interchange planning device 100 interchanges power among the EVs according to this plan so as not to affect mobility use the next day. For example, EVs that are not scheduled to be used the next day may be discharged until their SOC reaches 0%.

[0018] The above process allows EVs to share power without affecting the mobility of each EV, maximizing the utilization rate of renewable energy.

[0019] (Optional Functions) As parameters corresponding to the accommodation policy, parameters that provide a margin, such as an SOC fluctuation parameter, may be added in addition to the reference parameters.

[0020] The SOC fluctuation parameter is a parameter for reflecting fluctuations in the future power consumption of the EV (which may also be called uncertainty in the calculated value of the power consumption) in the calculated power consumption.

[0021] For example, the SOC fluctuation parameter is a value proportional to the distance L to the destination, or a coefficient (proportional coefficient) by which the distance L is multiplied. For example, by using the SOC fluctuation parameter when calculating (estimating) the SOC required for the EV on the next day, the power interchange planning device 100 can estimate a small SOC margin required for the next day if the distance to the destination is short, and can estimate a large SOC margin required for the next day if the distance to the destination is long.

[0022] It is conceivable that the margin for the SOC required for the next day, calculated from "distance / electricity cost," will change depending on the environment in which the EV is traveling. Therefore, the power interchange planning device 100 may use different values ​​as the SOC fluctuation parameters depending on the environment in which the EV is traveling. Examples of the environment in which the EV is traveling include whether there is traffic congestion, whether air conditioning is being used, whether a highway is being used, road conditions such as slopes, and the route.

[0023] For example, if a weather forecast predicts that the temperature on the next day will be 30°C or higher, when the power interchange planning device 100 acquires this information (= the temperature on the next day will be 30°C or higher), it determines that the air conditioner will be used when the EV is used on the next day, and adds a larger margin than the margin when the air conditioner is not used to the amount of power consumption on the next day calculated from, for example, "distance / electricity cost."

[0024] The power interchange planning device 100 can determine a margin according to SOC fluctuations by using at least one or more pieces of information obtained from the next day's usage plan. The multiple pieces of information obtained from the next day's usage plan include, for example, the destination, the distance to the destination (which can also be estimated from an existing navigation system), the scheduled departure time, the scheduled return time, and the travel time (which can also be estimated from the difference between the reservation time and the required time, or from the scheduled departure (return) time using an existing navigation system). The configuration and operation of the system / device according to this embodiment will be described in detail below.

[0025] (System Configuration Example) A configuration example of an EV-to-EV power interchange system according to this embodiment is shown in Fig. 1. As shown in Fig. 1, the EV-to-EV power interchange system according to this embodiment includes a power interchange planning device 100 and an interchange execution system 40.

[0026] The power interchange execution system 40 includes a PV device 30 and one or more chargers / dischargers 20. An EV 10 can be connected to each charger / discharger 20. The charger / discharger 20 supplies the EV 10 with power generated by the PV device 30. The charger / discharger 20 can also interchange power between the EVs 10 based on instructions from the power interchange planning device 100. Note that a configuration in which multiple EVs 10 are connected to one charger / discharger 20 may also be adopted.

[0027] The power exchange planning device 100 includes a usage schedule storage unit 110, a usage schedule acquisition unit 120, an SOC fluctuation acquisition unit 130, an exchange policy determination unit 140, a margin assignment unit 150, an SOC acquisition unit 160, an exchange plan creation unit 170, an exchange plan recording unit 180, and an exchange execution unit 190.

[0028] The power interchange planning device 100 may not include the interchange execution unit 190. For example, the interchange plan created by the power interchange planning device 100 may be notified to another device that includes the interchange execution unit 190.

[0029] (Example of Operation of Power Interchange Planning Apparatus 100) Next, an example of operation of the power interchange planning apparatus 100 will be described in accordance with the procedure of the flowchart in FIG.

[0030] <S1, S2> In S1, the accommodation policy determination unit 140 determines an accommodation policy. The determined accommodation policy is passed to the accommodation plan creation unit 170. The accommodation policy determination unit 140 may determine the accommodation policy based on an instruction from a user, or may determine the accommodation policy automatically.

[0031] Figure 3 shows examples of three interchange policies. In the example of Figure 3, all of cases 1 to 3 use the distance (L) to the destination on the next day as the reference parameter. For the SOC fluctuation parameter, "none" is used in case 1, a value proportional to the distance is used in case 2, and a value proportional to the average speed is used in case 3.

[0032] For example, multiple exchange policies such as those shown in Figure 3 may be stored in a storage device such as a memory in the power exchange planning device 100, and the exchange policy determination unit 140 may select one exchange policy from the multiple exchange policies.

[0033] In this embodiment, it is assumed that Case 2 is determined as the interchange policy. That is, in this embodiment, the explanation will be given assuming that the amount of energy consumption required for each EV on the next day is calculated by adding a margin according to the distance to the destination to the amount of energy consumption calculated from the distance to the destination.

[0034] In S2, the accommodation plan creation unit 170 determines that the reference parameter is to be "distance to the destination on the next day" based on the determined accommodation policy.

[0035] <S3> In S3, the usage schedule acquisition unit 120 acquires the reference parameters (reference parameter values) of each EV 10 from the usage schedule storage unit 110. Here, the usage schedule acquisition unit 120 acquires the distances to the destinations of all EVs 10 on the next day from the usage schedule storage unit 110. The acquired information is passed to the interchange plan creation unit 170.

[0036] 4 shows an example of information about the usage schedule for EV1 to EV3 stored in the usage schedule storage unit 110. FIG. 4 shows the usage schedule for the day after the interchange plan is created (e.g., the point in time after all EVs have returned on a certain day).

[0037] As shown in Fig. 4, in this example, the usage schedule includes a "priority of use for the next day." In the example of Fig. 4, EV3 has the highest priority.

[0038] A usage schedule (which may also be called a reservation) written on a time axis (a usage schedule image) is shown in Fig. 5. As shown in Fig. 5, in addition to the EV reservation itself, information linked to the reservation may also be used.

[0039] 2, the SOC fluctuation acquisition unit 130 acquires SOC fluctuation parameters based on the interchange policy determined by the interchange policy determination unit 140. The acquired SOC fluctuation parameters are passed to the interchange plan creation unit 170.

[0040] Here, the SOC fluctuation parameter is a parameter that increases the margin as the distance to the destination increases and decreases the margin as the distance to the destination decreases. For example, if the fluctuation (margin) is proportional to the distance, the SOC fluctuation acquisition unit 130 acquires a coefficient α, which is a proportionality coefficient for the distance. The SOC fluctuation acquisition unit 130 may acquire the coefficient α from the interchange policy determination unit 140, or the user may specify the coefficient α to the SOC fluctuation acquisition unit 130. The SOC fluctuation parameter may be the margin value itself instead of a coefficient.

[0041] <S5, S6> In S5, the margin allocation unit 150 calculates the amount of power consumption required for each EV 10 on the next day by adding a value (margin) obtained by multiplying the distance to the destination on the next day, obtained in S3, by a coefficient α to a value calculated by, for example, “distance / electricity cost” (L / d).

[0042] In S6, the amount of power consumption calculated in S5 that each EV 10 needs for the next day is recorded in the interchange plan recording unit 180.

[0043] <S7, S8> In S7, the SOC acquisition unit 160 acquires the current SOC (corresponding to the amount of stored electricity) of each EV 10, and in S8, records the current SOC of each EV 10 acquired in S7 in the interchange plan recording unit 180.

[0044] <S9> In S9, the interchange plan creation unit 170 calculates the sum of the amounts of power consumption required for all EVs 10 on the following day calculated in S5 (total power consumption) and the sum of the current SOCs for all EVs 10 obtained in S7 (total current SOC).

[0045] <S10, S11> In S10, the interchange plan creation unit 170 compares the total power consumption calculated in S9 with the current total SOC. If the current total SOC is smaller than the total power consumption (Yes in S11), the process proceeds to S12. If the current total SOC is greater than the total power consumption (No in S11), the process proceeds to S13.

[0046] <S12> In S12, which is the case when the total current SOC is smaller than the total power consumption, the interchange plan creation unit 170 reads the charging priority of each EV 10 for the next day from the usage schedule storage unit 110, and determines an interchange plan regarding how much power should be interchanged from which EV 10 to which EV 10, with the policy of interchange (supplying) power from EV 10 with lower priority to EV 10 with higher priority, so that the SOC after charging of the EV 10 with higher priority is as close as possible to the amount of power consumption required for the next day.

[0047] In the case of S12, since the current sum of SOCs is small, there is a high possibility that the amount of power that can be interchanged (supplied) will be limited. Even in this case, an interchange plan is created so that power is supplied preferentially to EVs 10 with the highest possible priority.

[0048] <S13> In S13, which is a case where the current sum of SOCs is greater than the sum of power consumption, the interchange plan creation unit 170 determines an interchange plan regarding how much power should be interchanged from which EV 10 to which EV 10.

[0049] In S13, as in S12, the priority is taken into consideration and an interchange plan may be created with the policy of interchange (supply) power from EV 10 with a lower priority to EV 10 with a higher priority, so that the SOC after charging of EV 10 with a higher priority is as close as possible to the amount of power consumption required for the next day.

[0050] In the case of S13, since the current sum of SOCs is large, even EVs 10 with low priority are more likely to be able to retain the amount of power consumption required for the next day and to be able to exchange power than in the case of S12.

[0051] <S14> In S14, the interchange plan creation unit 170 records the interchange plan determined in S12 or S13 in the interchange plan recording unit 180.

[0052] Fig. 6 shows an example of an interchange plan (which may also be called a distribution plan) recorded in the interchange plan recording unit 180. Fig. 6 shows an interchange plan among EV1, EV2, and EV3.

[0053] 6, the maximum battery capacity of each EV is 60 kWh. EV3 has the highest priority and will require 90% SOC (P = 60 kWh × 0.9) the next day. However, its current SOC is 20%, so it is determined that it needs to receive power from another EV.

[0054] For EV1, the SOC required the next day is 10% (P = 60 kWh × 0.1), and the current SOC is 80%, so there is a surplus of power. Therefore, it is decided to "supply power from EV1 to EV3." For EV2, the SOC required the next day is 30% (P = 60 kWh × 0.3), and the current SOC is 50%, so there is also a surplus of power. Therefore, it is decided to "supply power from EV1 to EV3."

[0055] More specifically, in the example of FIG. 6 , in order to cover the amount of electricity required for the next day by EV3, which has the highest priority, and to avoid interfering with the use of EV1 and EV2, the interchange plan creation unit 170 determines, for example, to supply electricity equivalent to 60% of SOC from EV1 to EV3 and to supply electricity equivalent to 10% of SOC from EV2 to EV3.

[0056] 6 , for example, if the margin (additional required amount of power) for EV3 is 10% SOC, the SOC required the next day will be 100% (P = 60 kWh × 1). In this case, the interchange plan creation unit 170 determines, for example, to supply power equivalent to 70% SOC from EV1 to EV3, and to supply power equivalent to 10% SOC from EV2 to EV3.

[0057] <S15> In S15, the interchange execution unit 190 reads the interchange plan from the interchange plan recording unit 180 and causes the interchange execution system 40 to interchange power between EVs 10. As an example, when executing power interchange from EV1 to EV3, the interchange execution unit 190 instructs the charger / discharger connected to EV1 to discharge power from EV1, and instructs the charger / discharger connected to EV3 to charge EV3 with the discharged power. For example, when the interchange execution unit 190 detects that the SOC of EV3 has reached the planned SOC, it instructs the charger / discharger to stop discharging and charging.

[0058] (Other Configuration Examples) The configuration of the power interchange planning device 100 is not limited to the configuration shown in Fig. 1. For example, as shown in Fig. 7, the power interchange planning device 100 may have a usage schedule acquisition unit 110 and an interchange plan creation unit 170.

[0059] The power interchange planning device 100 is a device that creates a plan for power interchange among a plurality of electric vehicles.

[0060] The usage schedule acquisition unit 110 acquires the usage schedule of each electric vehicle. The interchange plan creation unit 170 calculates the future power consumption of each electric vehicle based on the usage schedule, and creates a power interchange plan between the multiple electric vehicles based on the power consumption and the amount of power stored in each electric vehicle.

[0061] (Hardware Configuration Example) The power interchange planning device 100 described in this embodiment can be realized, for example, by causing a computer to execute a program. This computer may be a physical computer or a virtual machine on the cloud.

[0062] That is, the power interchange planning device 100 can be realized by using hardware resources such as a CPU and memory built into a computer to execute a program corresponding to the processing performed by the power interchange planning device 100. The program can be recorded on a computer-readable recording medium (such as a portable memory) and can be saved or distributed. The program can also be provided via a network such as the Internet or email.

[0063] Fig. 8 is a diagram showing an example of the hardware configuration of the computer. The computer in Fig. 8 includes a drive device 1000, an auxiliary storage device 1002, a memory device 1003, a CPU 1004, an interface device 1005, a display device 1006, an input device 1007, an output device 1008, and the like, all of which are interconnected by a bus BS. The computer may further include a GPU.

[0064] The program that realizes the processing on the computer is provided by a recording medium 1001, such as a CD-ROM or a memory card. When the recording medium 1001 storing the program is set in the drive device 1000, the program is installed from the recording medium 1001 to the auxiliary storage device 1002 via the drive device 1000. However, the program does not necessarily have to be installed from the recording medium 1001, but may be downloaded from another computer via a network. The auxiliary storage device 1002 stores the installed program as well as necessary files, data, etc.

[0065] The memory device 1003 reads out and stores the program from the auxiliary storage device 1002 when an instruction to start the program is received. The CPU 1004 realizes functions related to the power interchange planning device 100 in accordance with the program stored in the memory device 1003. The interface device 1005 is used as an interface for connecting to a network or the like. The display device 1006 displays a GUI (Graphical User Interface) or the like according to the program. The input device 1007 is composed of a keyboard, mouse, buttons, a touch panel, or the like, and is used to input various operation instructions. The output device 1008 outputs the results of calculations.

[0066] (Summary, effects, etc. of the embodiment) As described above, the technology described in this embodiment makes it possible to improve the renewable energy utilization rate without interfering with the use of EVs by providing power interchange based on the planned use for the next day.

[0067] The following additional notes are provided regarding the above-described embodiments.

[0068] <Additional Notes> (Additional Item 1) A power interchange planning device that creates a plan for power interchange between a plurality of electric mobile devices, comprising: a memory; and at least one processor connected to the memory, wherein the processor acquires a usage schedule for each electric mobile device, calculates the future power consumption of each electric mobile device based on the usage schedule, and creates a power interchange plan between the plurality of electric mobile devices based on the power consumption and the amount of power stored in each electric mobile device. (Additional Item 2) The power interchange planning device according to Additional Item 1, wherein the power consumption includes a margin corresponding to fluctuations in power consumption. (Additional Item 3) The power interchange planning device according to Additional Item 2, wherein the margin for a certain traveling distance is larger than the margin for a traveling distance smaller than the certain traveling distance. (Additional Item 4) A power interchange planning device according to any one of Additional Items 1 to 3, wherein priorities are assigned among the plurality of electric mobile devices, and the processor creates the power interchange plan based on the priorities. (Supplementary Item 5) The power interchange planning device according to any one of Supplementary Items 1 to 4, further comprising: an interchange execution unit that instructs a charger / discharger connected to at least one of the plurality of electric mobility devices to execute power interchange based on the power interchange plan. (Supplementary Item 6) A power interchange planning method executed by a power interchange planning device that creates a plan for power interchange between a plurality of electric mobility devices, comprising: a usage schedule acquisition step of acquiring a usage schedule for each electric mobility device; and a plan creation step of calculating future power consumption of each electric mobility device based on the usage schedule, and creating a power interchange plan between the plurality of electric mobility devices based on the power consumption and the amount of power stored in each electric mobility device. (Supplementary Item 7) A non-transitory storage medium that stores a program for causing a computer to function as each unit in the power interchange planning device according to any one of Supplementary Items 1 to 5.

[0069] Although the present embodiment has been described above, the present invention is not limited to such a specific embodiment, and various modifications and changes are possible within the scope of the gist of the present invention described in the claims.

[0070] REFERENCE SIGNS LIST 10 EV 20 Charger / Discharger 30 PV Device 40 Power Exchange Execution System 100 Power Exchange Planning Device 110 Use Schedule Storage Unit 120 Use Schedule Acquisition Unit 130 SOC Fluctuation Acquisition Unit 140 Power Exchange Policy Determination Unit 150 Margin Granting Unit 160 SOC Acquisition Unit 170 Power Exchange Plan Creation Unit 180 Power Exchange Plan Recording Unit 190 Power Exchange Execution Unit 1000 Drive Device 1001 Recording Medium 1002 Auxiliary Storage Device 1003 Memory Device 1004 CPU 1005 Interface Device 1006 Display Device 1007 Input Device 1008 Output Device

Claims

1. A power exchange planning device that creates a plan for power exchange between a plurality of electric mobility devices, comprising: a usage schedule acquisition unit that acquires a usage schedule for each electric mobility device; and a plan creation unit that calculates the future power consumption of each electric mobility device based on the usage schedule, and creates a power exchange plan between the plurality of electric mobility devices based on the power consumption and the amount of power stored in each electric mobility device.

2. The power interchange planning device according to claim 1, wherein the power consumption amount includes a margin according to fluctuations in the power consumption amount.

3. The power interchange planning device according to claim 2, wherein the margin for a certain travel distance is larger than the margin for a travel distance smaller than the certain travel distance.

4. The power interchange planning device according to claim 1, wherein priorities are assigned among the plurality of electric mobile devices, and the plan creation unit creates the power interchange plan based on the priorities.

5. The power interchange planning device according to claim 1, further comprising an interchange execution unit that instructs a charger / discharger connected to at least one of the plurality of electric mobile devices to execute power interchange based on the power interchange plan.

6. A power exchange planning method executed by a power exchange planning device that creates a plan for power exchange between a plurality of electric mobility devices, comprising: a usage plan acquisition step of acquiring a usage plan for each electric mobility device; and a planning step of calculating the future power consumption of each electric mobility device based on the usage plan, and creating a power exchange plan between the plurality of electric mobility devices based on the power consumption and the amount of power stored in each electric mobility device.

7. A program for causing a computer to function as each unit in the power interchange planning device according to any one of claims 1 to 5.

Citation Information

Patent Citations

  • Regional energy management device and regional energy management method

    JP2021052529A

  • Power supply plan management device, power supply plan management method, and program for power supply plan management device

    JP2021145444A

  • Management system, management method, power device, vehicle-mounted device, and management server

    WO2019176192A1