Control device, control method, and control program

The control device for electric vehicles determines a second adjustment rate for charge/discharge control, enhancing their capacity to stabilize power system frequency, addressing the challenges of renewable energy and natural disaster-induced fluctuations.

WO2024247403A1PCT designated stage expired Publication Date: 2024-12-05SUMITOMO ELECTRIC INDUSTRIES LTD +1

Patent Information

Application Number
PCT/JP2024/006824
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-26
Filing Date
2024-02-26
Publication Date
2024-12-05

AI Technical Summary

Technical Problem

The increasing fluctuation in power supply and demand due to renewable energy sources and natural disasters poses challenges in maintaining power system frequency stability, requiring efficient frequency adjustment mechanisms.

Method used

A control device and method that manage the charging and discharging of electric vehicles to provide frequency adjustment power by determining a second adjustment rate for charge/discharge control, allowing for increased charge and discharge capacity compared to traditional first adjustment rates, thereby efficiently utilizing a small number of vehicles.

Benefits of technology

This approach enables efficient provision of frequency adjustment power using a small number of electric vehicles by expanding their charge and discharge capabilities, effectively addressing the challenges of power system frequency stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure JP2024006824_05122024_PF_FP_ABST
    Figure JP2024006824_05122024_PF_FP_ABST
Patent Text Reader

Abstract

A control device according to the present invention controls the charging and discharging of a vehicle group including a plurality of electric vehicles, said control device comprising: an acquisition unit for acquiring a requested adjustment amount indicating an output adjustable range, which is the range in which output power of a charging / discharging device for charging and discharging the electric vehicles can be adjusted in accordance with the frequency variation in a power system; and a determination unit for determining, on the basis of the requested adjustment amount acquired by the acquisition unit, a second adjustment rate that is smaller than a first adjustment rate established for the vehicle group to be the adjustment rate used in charge / discharge control of the electric vehicles included in the vehicle group.
Need to check novelty before this filing date? Find Prior Art

Description

Control device, control method, and control program

[0001] This application claims priority to Japanese Patent Application No. 2023-087046 filed on May 26, 2023, and incorporates by reference the entire contents of that application.

[0002] The frequency of the power grid fluctuates based on the balance of supply and demand for electricity, centered around a reference frequency (50 Hz in eastern Japan). The risk of an imbalance in the supply and demand of electricity is increasing due to the expanding adoption of renewable energy sources such as solar and wind power, which have fluctuating output, as well as natural disasters such as typhoons and earthquakes. Against this background, a supply and demand adjustment market has been operating in Japan since 2021.

[0003] In the supply and demand adjustment market, adjustment capacity is divided into three categories according to response time: primary adjustment capacity, secondary adjustment capacity, and tertiary adjustment capacity (Non-Patent Document 1). Tertiary adjustment capacity is adjustment capacity with a response time of 15 minutes or 45 minutes or less. Procurement of tertiary adjustment capacity (2) with a response time of 45 minutes began in 2021. Secondary adjustment capacity is adjustment capacity with a response time of 5 minutes or less, and primary adjustment capacity is adjustment capacity with a response time of 10 seconds or less. Procurement of secondary adjustment capacity and primary adjustment capacity is scheduled to begin in 2024.

[0004] "Trading Guide (All Products) April 1, 2023, First Edition, Revised Proposal," [online], [Retrieved February 8, 2023], Internet <URL: https: / / www.tdgc.jp / j_information / docs / guide_202304rev.pdf>

[0005] A control device according to one aspect of the present disclosure is a control device that controls the charging and discharging of a group of vehicles including a plurality of electric vehicles, and includes: an acquisition unit that acquires an adjustment request amount that indicates an output adjustable range, which is a range within which the output power of a charging and discharging device that charges and discharges the electric vehicles can be adjusted in accordance with frequency fluctuations in a power grid; and a determination unit that determines, based on the adjustment request amount acquired by the acquisition unit, a second adjustment rate that is smaller than a first adjustment rate set for the group of vehicles, as the adjustment rate to be used in controlling the charging and discharging of the electric vehicles included in the group of vehicles.

[0006] FIG. 1 is a diagram illustrating an example of a charge / discharge control system according to an embodiment. FIG. 2 is a block diagram illustrating an example of the hardware configuration of a control server according to an embodiment. FIG. 3 is a functional block diagram illustrating an example of the functions of the control server according to an embodiment. FIG. 4 is a diagram for explaining selection of a target vehicle. FIG. 5 is a graph illustrating an example of the provision of primary control reserve in a contracted vehicle group. FIG. 6 is a graph illustrating an example of frequency response in one electric vehicle when primary control reserve is equally divided among multiple electric vehicles. FIG. 7 is a graph illustrating an example of frequency response in one electric vehicle when primary control reserve is divided by a control server according to an embodiment. FIG. 8 is a graph illustrating another example of frequency response in one electric vehicle when primary control reserve is divided by a control server according to an embodiment. FIG. 9 is a graph illustrating another example of the provision of primary control reserve in a contracted vehicle group. FIG. 10 is a graph illustrating another example of frequency response in one electric vehicle when primary control reserve is equally divided among multiple electric vehicles. FIG. 11 is a graph illustrating yet another example of frequency response in one electric vehicle when primary control reserve is divided by a control server according to an embodiment. FIG. 12 is a flowchart illustrating an example of a control process by the control server according to the embodiment.

[0007] <Problem to be Solved by the Present Disclosure> When vehicles equipped with a traction battery, such as BEVs (Battery Electric Vehicles) and PHEVs (Plug-in Hybrid Electric Vehicles) (hereinafter also referred to as "electric vehicles"), are used for frequency adjustment capacity, it is necessary to efficiently use the few electric vehicles.

[0008] <Effects of the Present Disclosure> According to the present disclosure, frequency regulation capability can be efficiently provided with a small number of electric vehicles.

[0009] <Outline of Embodiments of the Present Disclosure> Below, an outline of embodiments of the present disclosure will be listed and described.

[0010] (1) A control device according to this embodiment controls charging and discharging of a group of electric vehicles, and includes: an acquisition unit that acquires an adjustment request amount indicating an output adjustable range, which is a range within which the output power of a charging / discharging device that charges and discharges the electric vehicles can be adjusted in response to frequency fluctuations in a power grid; and a determination unit that determines, based on the adjustment request amount acquired by the acquisition unit, a second adjustment rate that is smaller than a first adjustment rate determined for the group of vehicles as a adjustment rate to be used in controlling the charging and discharging of the electric vehicles included in the group of vehicles. Frequency adjustment capability (hereinafter simply referred to as "adjustment capability") requires a response based on the adjustment rate to provide adjustment capability in response to frequency fluctuations. With the above configuration, charging and discharging the electric vehicles using the second adjustment rate can increase the charging and discharging amounts of the electric vehicles compared to charging and discharging the electric vehicles using the first adjustment rate. This allows for efficient provision of adjustment capability with a small number of vehicles.

[0011] (2) In the above (1), the second adjustment rate may be a rate for adjusting the output power of the charging / discharging device to the limit value of the adjustment request amount when the frequency of the power grid fluctuates to a specific frequency, thereby enabling charging / discharging of the electric vehicle up to the limit value of the adjustment request amount in a frequency range defined by the specific frequency.

[0012] (3) In the above (2), the specific frequency may be a limit value of a frequency adjustment range of the charging / discharging device when the charging / discharging device adjusts the frequency according to the first adjustment rate within an output power adjustment range determined for the vehicle group. This allows charging / discharging of the electric vehicles up to the limit value of the adjustment request amount within the frequency adjustment range.

[0013] (4) In the above (2) or (3), the limit value of the adjustment request amount may be a rated output power of the charging / discharging device. This allows the electric vehicle to be charged / discharged up to the rated output power of the charging / discharging device.

[0014] (5) In any one of (1) to (3) above, the determination unit may determine the second adjustment ratio within a range defined by the first adjustment ratio and a predetermined lower limit value of the second adjustment ratio, thereby making it possible to determine the second adjustment ratio within an appropriate range.

[0015] (6) In the above (5), the determination unit may determine the second adjustment rate to be the lower limit value, thereby widening the range of output power of the charging / discharging device.

[0016] (7) In the above (6), the determination unit may determine a control limit value for the output power of the charging / discharging device that is different from a rated output power of the charging / discharging device. This allows the electric vehicle to be efficiently charged / discharged within a range defined by the control limit value.

[0017] (8) In the above (7), the control limit value may be an output power value of the charging / discharging device that corresponds to a specific frequency when the charging / discharging device operates in response to the frequency at the second regulation rate. This makes it possible to determine the control limit value for efficiently charging / discharging the electric vehicle based on the specific frequency.

[0018] (9) In the above (8), the specific frequency may be a limit value of a frequency adjustment range of the charging / discharging device when the charging / discharging device operates in response to frequency according to the first adjustment rate within an output power adjustment range determined for the vehicle group. This makes it possible to determine a control limit value for efficiently charging / discharging the electric vehicles within the frequency adjustment range.

[0019] (10) In any one of (1) to (9) above, the control device may further include a selection unit that selects a target vehicle that is an electric vehicle that is a target of charge / discharge control at the second adjustment rate, based on an output power adjustment range determined for the vehicle group and the adjustment request amount of each of the plurality of electric vehicles included in the vehicle group. This makes it possible to select a target vehicle that is used to provide adjustment power.

[0020] (11) In the above (10), the selection unit may select the target vehicles such that a sum of the adjustment request amounts of the target vehicles satisfies a condition based on the output power adjustment range. This makes it possible to appropriately set the number of target vehicles based on the output power adjustment range.

[0021] (12) A control method according to this embodiment is a control method for controlling charging and discharging of a group of vehicles including a plurality of electric vehicles, and includes the steps of: acquiring an adjustment request amount indicating an output adjustment range, which is a range within which output power of a charging / discharging device that charges and discharges the electric vehicles can be adjusted in response to frequency fluctuations in a power grid; and determining, based on the acquired adjustment request amount, a second adjustment rate that is smaller than a first adjustment rate determined for the group of vehicles as a adjustment rate to be used in controlling charging and discharging of the electric vehicles included in the group of vehicles. By charging and discharging the electric vehicles using the second adjustment rate, the amount of charge and discharge of the electric vehicles can be increased compared to when the electric vehicles are charged and discharged using the first adjustment rate. This makes it possible to efficiently provide adjustment power with a small number of vehicles.

[0022] (13) A control program according to this embodiment is a control program for controlling charging and discharging of a vehicle group including a plurality of electric vehicles, and causes a computer to execute the following steps: acquiring an adjustment request amount indicating an output adjustment range, which is a range within which output power of a charging / discharging device that charges and discharges the electric vehicles can be adjusted in response to frequency fluctuations in a power grid; and determining, based on the acquired adjustment request amount, a second adjustment rate that is smaller than a first adjustment rate determined for the vehicle group as a adjustment rate to be used in controlling charging and discharging of the electric vehicles included in the vehicle group. By charging and discharging the electric vehicles using the second adjustment rate, the amount of charge and discharge of the electric vehicles can be increased compared to when the electric vehicles are charged and discharged using the first adjustment rate. This makes it possible to efficiently provide adjustment power with a small number of vehicles.

[0023] The present disclosure can be realized not only as a control device having the above-described characteristic configuration, a control method having the above-described characteristic processing as steps, and a control program for causing a computer to execute the characteristic processing, but also as a charge / discharge control system including the control device, or as a semiconductor integrated circuit that realizes part or all of the control device.

[0024] <Details of the embodiments of the present disclosure> Hereinafter, the details of the embodiments of the present disclosure will be described with reference to the drawings. Note that at least some of the embodiments described below may be combined in any manner.

[0025] 1. Charge / Discharge Control System FIG. 1 is a diagram showing an example of a charge / discharge control system according to an embodiment.

[0026] The charge / discharge control system 10 includes a control server 100 , a plurality of electric vehicles 200 , and a plurality of charge / discharge devices 300 .

[0027] The electric vehicle 200 is owned by an electricity consumer (for example, an individual or a corporation). In this embodiment, the electric vehicle 200 is used as an energy resource for primary regulation capability, which is an example of frequency regulation capability.

[0028] The charging / discharging device 300 charges and discharges (the battery of) the electric vehicle 200. Specifically, the charging / discharging device 300 is connected to a power grid (not shown) operated and managed by a local TSO (Transmission System Operator) 30, and charges the electric vehicle 200 by a forward flow of power from the power grid, or discharges the electric vehicle 200 to cause a reverse flow of power to the power grid. The local TSO 30 is a general electricity transmission and distribution business operator in an area where consumer houses and the like are located. The charging / discharging device 300 is, for example, an off-board charger that is not mounted on the electric vehicle 200. As another example, the charging / discharging device 300 may be an on-board charger that is mounted on the electric vehicle 200.

[0029] The charging / discharging device 300 has a communication function. Specifically, the charging / discharging device 300 has a wired communication interface or a wireless communication interface, and is connected to the Internet 50 by wired communication or wireless communication.

[0030] The control server 100 is connected to the Internet 50. The control server 100 can communicate with the charging / discharging device 300 via the Internet 50.

[0031] The control server 100 is operated and managed by an aggregator 20. The aggregator 20 is a business operator that performs integrated control of electric vehicles 200 (and charging / discharging devices 300), which are distributed energy resources, and trades electricity with the electricity market 40 using a virtual power plant (VPP) or demand response (DR). The aggregator 20 provides primary control reserve to the local TSO 30 by charging and discharging the electric vehicles 200. The aggregator 20 has concluded a contract with a consumer who owns the electric vehicle 200 for a service to use the electric vehicle 200 to provide primary control reserve (hereinafter also referred to as a "primary control reserve provision service").

[0032] The aggregator 20 predetermines a balancing rate (first balancing rate) for providing primary control reserve. The aggregator 20 submits a bid to the electricity market 40 for the provision of primary control reserve at the first balancing rate. In the bid, a range (upper and lower limits) of power to be provided during the period (provision period) for providing primary control reserve is specified. When the bid is contracted, the range of power to be provided (contracted amount) is determined. In other words, the contracted amount is the range of charging and discharging power for the entire vehicle fleet made up of the electric vehicles 200 of all consumers who have concluded contracts with the aggregator 20.

[0033] When the bid is contracted, the control server 100 receives information about the contract (hereinafter also referred to as “contract information”) from a server (not shown) operated by the electricity market 40. The contract information includes the supply period and the contracted amount.

[0034] The control server 100 is an example of a "control device." The control server 100 determines a second adjustment rate using the received contract information. The second adjustment rate is an adjustment rate used by each charging / discharging device 300 for charge / discharge control. Furthermore, the control server 100 selects an electric vehicle 200 that is the target of charge / discharge control using the second adjustment rate from a vehicle group (hereinafter also referred to as a "contracted vehicle group") made up of all electric vehicles 200 owned by consumers who have contracted with the aggregator 20 for the primary control reserve supply service. Hereinafter, the selected electric vehicle 200 is also referred to as a "target vehicle," and the vehicle group made up of the target vehicles is also referred to as a "target vehicle group."

[0035] The control server 100 instructs each charging / discharging device 300 corresponding to the target vehicle group to charge / discharge using the second adjustment rate.

[0036] The charging / discharging device 300 includes a frequency sensor that detects the frequency of the power grid (grid frequency). Upon receiving a charge / discharge command, the charging / discharging device 300 charges / discharges the electric vehicle 200 at the second regulation rate based on the detected grid frequency during the supply period. This provides primary control reserve to the power grid.

[0037] For example, when the provision period ends, each charging / discharging device 300 corresponding to the target vehicle group transmits the results of the executed charging / discharging control (actual charging / discharging power performance and frequency) to the control server 100. The control server 100 compiles the results of the charging / discharging control received from each charging / discharging device 300 and transmits them to a server (not shown) operated by the local TSO 30.

[0038] 2. Hardware Configuration of Control Server] Fig. 2 is a block diagram showing an example of the hardware configuration of a control server according to an embodiment. The control server 100 includes a processor 101, a non-volatile memory 102, a volatile memory 103, and a communication interface 104.

[0039] The volatile memory 103 is, for example, a semiconductor memory such as an SRAM (Static Random Access Memory) or a DRAM (Dynamic Random Access Memory). The non-volatile memory 102 is, for example, a flash memory, a hard disk, a ROM (Read Only Memory), or the like. The non-volatile memory 102 stores a control program 110, which is a computer program, and data used to execute the control program 110. Each function of the control server 100 is achieved by the processor 101 executing the control program 110. The control program 110 can be stored in a recording medium such as a flash memory, a ROM, or a CD-ROM. The processor 101 can determine the second adjustment rate using the control program 110.

[0040] The processor 101 is, for example, a CPU (Central Processing Unit). However, the processor 101 is not limited to a CPU. The processor 101 may be a GPU (Graphics Processing Unit). The processor 101 is, for example, a multi-core processor. The processor 101 may be a single-core processor. The processor 101 may be, for example, an ASIC (Application Specific Integrated Circuit) or a programmable logic device such as a gate array or FPGA (Field Programmable Gate Array). In this case, the ASIC or programmable logic device is configured to be able to execute the same processing as the control program 110.

[0041] The communication interface 104 is, for example, an Ethernet interface ("Ethernet" is a registered trademark). The communication interface 104 is connected to the Internet 50. The communication interface 104 can send and receive packets of, for example, TCP / IP (Transmission Control Protocol / Internet Protocol).

[0042] The nonvolatile memory 102 stores contract information 111 received from the electricity market 40. The nonvolatile memory 102 stores a predetermined first contract rate 112.

[0043] The non-volatile memory 102 has a vehicle database (hereinafter also referred to as "vehicle DB") 113. The vehicle DB 113 stores information (hereinafter also referred to as "contracted vehicle information") on all electric vehicles 200 owned by consumers who have concluded contracts for the primary control reserve supply service with the aggregator 20. In a specific example, the contracted vehicle information includes the vehicle ID of the electric vehicle 200 and the rated output power of the charging / discharging device 300 (upper limit value, i.e., rated discharge power, and lower limit value, i.e., rated charge power).

[0044] The control server 100 may be a dedicated server for controlling the charging / discharging devices 300 of the contracted vehicle fleet to provide adjustment power, or may be used as a server for providing a service other than the provision of adjustment power. For example, the control server 100 may be a cloud server.

[0045] 3. Functions of the Control Server FIG. 3 is a functional block diagram showing an example of functions of the control server according to the embodiment.

[0046] When the processor 101 executes the control program 110 , the control server 100 executes the functions of an acquisition unit 121 , a selection unit 122 , a decision unit 123 , and an output unit 124 .

[0047] The acquisition unit 121 acquires an adjustment request amount indicating an output adjustable range, which is a range within which the output power of the charging / discharging device 300 can be adjusted in response to frequency fluctuations in the power grid. The adjustment request amount is a range defined by a limit value (upper limit value) of the discharge power of the charging / discharging device 300 and a limit value (lower limit value) of the charge power. An example of the limit value of the adjustment request amount is the rated output power of the charging / discharging device 300. In other words, an example of the upper limit value of the adjustment request amount is the rated discharge power of the charging / discharging device 300, and an example of the lower limit value of the adjustment request amount is the rated charge power of the charging / discharging device 300. The acquisition unit 121 can acquire the rated output power of the charging / discharging device 300 by referring to the vehicle DB 113.

[0048] For example, the acquisition unit 121 acquires the contract information 111 by receiving the contract information 111 transmitted from the electricity market 40. The contract information 111 is stored in the non-volatile memory 102.

[0049] The selection unit 122 selects a target vehicle from the contracted vehicle group based on the output power adjustment range defined for the contracted vehicle group and the adjustment request amount acquired by the acquisition unit 121. The contracted amount is an example of the output power adjustment range defined for the contracted vehicle group.

[0050] FIG. 4 is a diagram for explaining the selection of target vehicles. For the entire contracted vehicle group 400, it is required that the charging and discharging power be adjusted within a range (output power adjustment range) defined by the contracted quantity during the provision period in accordance with fluctuations in the grid frequency. The selection unit 122 selects target vehicles and determines the target vehicle group 410, which is a subset of the contracted vehicle group 400. In the following description, the contracted quantity is referred to as "PE1," and the rated output power of the entire contracted vehicle group 400, i.e., the sum of the rated output power of all electric vehicles 200 included in the contracted vehicle group 400, is referred to as "PE2."

[0051] Figure 5 is a graph illustrating an example of the provision of primary control reserve in a contracted vehicle group. In Figure 5, the horizontal axis represents frequency fluctuation [Hz], and the vertical axis represents output power [W] of the entire contracted vehicle group. As described above, the contracted vehicle group 400 is required to respond to the grid frequency within the output power adjustment range during the provision period. The frequency response of the output power of the entire contracted vehicle group 400 follows a first adjustment ratio. The first adjustment ratio is set to 5% or less.

[0052] The adjustment ratio is represented by a straight line in a Cartesian coordinate system of the frequency fluctuation amount and the output power. In the example of Figure 5, the response according to the first adjustment ratio is represented by a straight line connecting the points (-Δ1, +PE1) and (+Δ1, -PE1).

[0053] In the figure, the frequency fluctuation range of -0.01 Hz to +0.01 Hz is the dead band, in which no frequency response occurs.

[0054] In the figure, the frequency fluctuation range of -0.2 Hz or less is an abnormal region. In other words, if the system frequency drops by 0.2 Hz or more from the reference frequency, the power system is considered to be in an abnormal state. For example, if a large-scale power outage occurs or if the power generation capacity of some power plants drops to zero, the system frequency may drop significantly and enter the abnormal region. The frequency fluctuation range greater than -0.2 Hz is a normal region. In other words, if the deviation of the system frequency from the reference frequency is greater than -0.2 Hz, the power system is considered to be in a normal state.

[0055] When the grid frequency increases from the reference frequency, the output power (charging power) corresponding to the deviation of the grid frequency from the reference frequency is determined by the first adjustment ratio, and the contracted vehicles 400 as a whole charge the amount of this output power. In this case, power is supplied from the power grid to the contracted vehicles 400 (forward flow). Therefore, the output power from the contracted vehicles 400 becomes negative.

[0056] At the first adjustment ratio, when the deviation of the grid frequency from the reference frequency is +Δ1, the output power of the contracted vehicles 400 reaches -PE1. The rated charging power (-PE2) of the entire contracted vehicles 400 is smaller than -PE1. In other words, the contracted vehicles 400 can still be charged even if their charging power exceeds -PE1. However, when primary control reserve is provided, the charging power of the entire contracted vehicles 400 does not exceed -PE1. In other words, when the deviation exceeds +Δ1, the output power of the entire contracted vehicles 400 is controlled to maintain -PE1. The range in which the frequency fluctuation is greater than +Δ1 is the output fixed range in which the output power of the entire contracted vehicles 400 is fixed to -PE1.

[0057] When the grid frequency decreases from the reference frequency, the output power (discharge power) corresponding to the deviation of the grid frequency from the reference frequency is determined by the first adjustment rate, and the contracted vehicles 400 as a whole discharge the output power. In this case, power is supplied from the contracted vehicles 400 to the power grid (reverse power flow). Therefore, the output power from the contracted vehicles 400 becomes positive.

[0058] At the first adjustment rate, when the deviation of the grid frequency from the reference frequency is -Δ1, the output power of the contracted vehicles 400 reaches +PE1. The rated discharge power (+PE2) of the entire contracted vehicles 400 is greater than +PE1. In other words, the contracted vehicles 400 can still discharge even if their discharge power exceeds +PE1. However, when providing primary control reserve, the discharge power of the entire contracted vehicles 400 does not exceed +PE1. In other words, when the deviation exceeds -Δ1, the output power of the entire contracted vehicles 400 is controlled to maintain +PE1. The range in which the frequency fluctuation is less than -Δ1 is the output fixed range in which the output power of the entire contracted vehicles 400 is fixed to +PE1. The range in which the frequency fluctuation is greater than or equal to -Δ1 and less than or equal to Δ1 is the frequency adjustment range in which the output power of the entire contracted vehicles 400 is adjusted within the range from +PE1 to -PE1.

[0059] As described above, control server 100 commands each charging / discharging device 300 to charge / discharge so that the frequency of contracted vehicle fleet 400 as a whole changes in response to the first adjustment rate. For example, consider a case where the power output by each of electric vehicles 200 (i.e., primary control power) is equally divided among a plurality of electric vehicles 200. In this case, the number N of electric vehicles 200 to be charged / discharged is determined so that the upper limit value of the output power of each charging / discharging device 300 is not greater than the rated discharge power and the lower limit value of the output power of each charging / discharging device 300 is not less than the rated charge power.

[0060] 6 is a graph illustrating an example of frequency response in one electric vehicle when the primary control capacity is equally divided among a plurality of electric vehicles. In FIG. 6, the horizontal axis represents the frequency fluctuation amount [Hz], and the vertical axis represents the output power [W] of the charging / discharging device 300 corresponding to one electric vehicle 200. In this case, the range of output power for each electric vehicle 200 is the value obtained by dividing the contract amount by the number N of the target electric vehicles 200. In other words, the upper limit value PI1 and the lower limit value -PI1 of the output power adjustment range for one electric vehicle 200 are determined by PI1 = PE1 ÷ N.

[0061] The charging / discharging device 300 connected to the target electric vehicle 200 used to provide primary control reserve charges / discharges in response to fluctuations in the grid frequency according to the first regulation ratio. In the example of Fig. 6, it is assumed that the same first regulation ratio as that used for the entire contracted vehicle group 400 is used for each charging / discharging device 300. In the example of Fig. 6, the response according to the first regulation ratio is represented by a straight line connecting the point (-Δ1, +PI1) and the point (+Δ1, -PI1).

[0062] When the system frequency increases from the reference frequency, the output power (charging power) corresponding to the deviation of the system frequency from the reference frequency is determined by the first regulation ratio, and each charging / discharging device 300 charges for that output power.

[0063] At the first adjustment rate, when the deviation of the grid frequency from the reference frequency is +Δ1, the output power of one charging / discharging device 300 reaches -PI1. The rated charging power (-PI2) of the charging / discharging device 300 is smaller than -PI1. That is, each charging / discharging device 300 can still charge even if its charging power exceeds -PI1. However, to prevent the total charging power of the entire contracted vehicle fleet 400 from exceeding -PE1, the charging power of each charging / discharging device 300 must not exceed -PI1. That is, when the deviation exceeds +Δ1, the output power of the charging / discharging device 300 is controlled to maintain -PI1. The range in which the frequency fluctuation is greater than +Δ1 is the fixed output range in which the output power of the charging / discharging device 300 is fixed to -PI1.

[0064] When the system frequency decreases from the reference frequency, the output power (discharge power) corresponding to the deviation of the system frequency from the reference frequency is determined by the first regulation ratio, and each of the charging / discharging devices 300 discharges the output power.

[0065] At the first regulation rate, when the deviation of the grid frequency from the reference frequency is −Δ1, the output power of one charging / discharging device 300 reaches +PI1. The rated discharge power (+PI2) of the charging / discharging device 300 is greater than +PI1. That is, each charging / discharging device 300 can still discharge even if its discharge power exceeds +PI1. However, to prevent the total discharge power of the entire contracted vehicle fleet 400 from exceeding +PE1, the discharge power of each charging / discharging device 300 must not exceed +PI1. That is, when the deviation exceeds −Δ1, the output power of the charging / discharging device 300 is controlled to maintain +PI1. The range in which the frequency fluctuation is less than −Δ1 is the output fixed range in which the output power of the charging / discharging device 300 is fixed at +PI1. The range in which the frequency fluctuation is greater than or equal to −Δ1 and less than or equal to Δ1 is the frequency adjustment range in which the output power of the charging / discharging device 300 is adjusted between +PI1 and −PI1.

[0066] In this charge / discharge control, the output (discharge) of power exceeding +PI1 is limited, and the output (charge) of power exceeding −PI1 is limited. In other words, the charge / discharge device 300 cannot efficiently charge / discharge.

[0067] The control server 100 according to this embodiment provides primary control capacity by efficiently charging and discharging the charge / discharge devices 300. That is, the control server 100 expands the output power adjustment range of the charge / discharge devices 300 for providing primary control capacity.

[0068] 6, assuming that the output of charging / discharging device 300 is reduced to the rated value of −PI2 in accordance with the first regulation ratio, the output power reaches −PI2 when the frequency deviation is +Δ2. Assuming that the output of charging / discharging device 300 is increased to the rated value of +PI2 in accordance with the first regulation ratio, the output power reaches +PI2 when the frequency deviation is −Δ2.

[0069] 7 is a graph illustrating an example of frequency response in one electric vehicle 200 when the primary control capacity is divided by the control server according to the embodiment. In Fig. 7, the horizontal axis represents the frequency fluctuation amount [Hz], and the vertical axis represents the output power [W] of the charging / discharging device 300 corresponding to one electric vehicle 200.

[0070] The control server 100 determines the second adjustment ratio such that the upper limit value of the output power adjustment range is +PI2 and the lower limit value is −PI2, for example.

[0071] In the example of Figure 7, if the output of the charging / discharging device 300 is reduced to the rated value of -PI2 according to the second regulation ratio, the output power reaches -PI2 when the frequency deviation is +Δ1. If the output of the charging / discharging device 300 is increased to the rated value of +PI2 according to the second regulation ratio, the output power reaches +PI2 when the frequency deviation is -Δ1. In other words, the charging / discharging device 300 can perform frequency response within the range of the rated output power. Therefore, the charging / discharging device 300 can be used efficiently to provide primary control power.

[0072] Returning to FIG. 3 , the selection unit 122 selects target vehicles from the contracted vehicle group 400 so that the sum of the adjustment request amounts of the target vehicles satisfies a condition based on the output power adjustment range defined for the contracted vehicle group. In a specific example, the selection unit 122 selects target vehicles from the contracted vehicle group 400 so that the sum of the rated output powers of the target vehicles is equal to or greater than the contracted amount. That is, the condition in this case is that the sum of the rated output powers of the target vehicles is equal to or greater than the contracted amount. The rated output powers of the charging / discharging devices 300 may differ. That is, the rated output power of charging / discharging device A may differ from the rated output power of charging / discharging device B. For example, the selection unit 122 can select target vehicles so that the sum of the rated output powers of the charging / discharging devices 300 connected to the target vehicles included in the target vehicle group 410 matches the contracted amount.

[0073] When the sum of the rated output powers of the charging / discharging devices 300 connected to the target vehicle matches the contracted amount, each charging / discharging device 300 can charge / discharge the electric vehicle 200 within the range of its rated output power in accordance with fluctuations in the grid frequency. The determiner 123 determines a second regulating rate smaller than the first regulating rate as the regulating rate to be used in charge / discharge control of the target vehicle, based on the adjustment request amount acquired by the acquirer 121. In a specific example, the determiner 123 can determine the second regulating rate based on the first regulating rate, the contracted amount PE1, and the rated output power PE2 of the entire contracted vehicle group 400. That is, the determiner 123 determines a frequency (specific frequency) at which the output power of the entire contracted vehicle group 400 reaches the contracted amount, based on the first regulating rate and the contracted amount PE1. Furthermore, the determiner 123 calculates a regulating rate at which the rated output power PE2 is obtained at the specific frequency, and determines this regulating rate as the second regulating rate. In other words, the second adjustment rate is an adjustment rate in which the upper limit value of the output power adjustment range for the entire contracted vehicle group 400 is +PE2 and the lower limit value is -PE2. The rated output power PE2 is the sum of the rated output power of the charging / discharging devices 300 used for charging / discharging each of the electric vehicles 200 included in the contracted vehicle group 400, for example, the sum of the rated output power of the charging / discharging devices 300 used for charging / discharging each of the electric vehicles 200 included in the target vehicle group 410. In other words, the determination unit 123 determines the second adjustment rate based on the sum of the adjustment request amounts of the charging / discharging devices 300. In other words, the determination unit 123 determines the second adjustment rate based on the rated output power (adjustment request amount) of each charging / discharging device 300.

[0074] For example, the second adjustment rate is a rate for setting the output power of the charging / discharging device 300 to the limit value of the adjustment request amount when the system frequency fluctuates to a specific frequency. For example, the specific frequency is the limit value of the frequency adjustment range of the charging / discharging device 300 when the charging / discharging device 300 responds to the frequency according to the first adjustment rate within the output power adjustment range.

[0075] Please refer to FIG. 6. In the example of FIG. 6, the output power adjustment range is a power range (PI1 = PE1 ÷ N) determined from the contract amount. That is, the output power adjustment range in FIG. 6 corresponds to the contract amount. In the charging / discharging device 300, the range of frequencies that can respond to the first adjustment rate (frequency adjustment range) is a range of -Δ1 or more and Δ1 or less. That is, the limit values ​​(upper limit and lower limit values) of the frequency adjustment range are +Δ1 and -Δ1. Therefore, in the example of FIG. 6, the specific frequencies are +Δ1 and -Δ1.

[0076] Please refer to FIG. 7. In the example of FIG. 7, the upper limit value of the adjustment request amount is +PI2 and the lower limit value is -PI2. The second adjustment rate is a rate at which the output power of the charging / discharging device 300 is -PI2 when the amount of fluctuation in the grid frequency is +Δ1, and is +PI2 when the amount of fluctuation in the grid frequency is -Δ1. That is, in the example of FIG. 7, the second adjustment rate is represented as a straight line connecting the point (-Δ1, +PI2) and the point (+Δ1, -PI2). The determination unit 123 can determine the second adjustment rate as a straight line connecting the point (-Δ1, +PI2) and the point (+Δ1, -PI2).

[0077] The second regulation rate is smaller than the first regulation rate. In other words, the second regulation rate corresponds to a response that charges and discharges at a greater output than the first regulation rate under the same frequency fluctuation. Therefore, by responding to the frequency according to the second regulation rate, each charging / discharging device 300 can output power exceeding the above-mentioned PI1 and -PI1 and within the regulation request amount defined by PI2 and -PI2. Therefore, by efficiently charging and discharging each target vehicle within the rated power range, primary regulation power can be provided.

[0078] In this case, the rated output power (rated discharge power, rated charge power) varies depending on the charging / discharging device 300. Since the second regulating ratio is common to each charging / discharging device 300, when each charging / discharging device 300 responds to the frequency according to the second regulating ratio, the output power from each charging / discharging device 300 will be of a magnitude corresponding to its rated output power. That is, the output power from a charging / discharging device 300 with a high rated output power will be high, and the output power from a charging / discharging device 300 with a low rated output power will be low.

[0079] 3, the determination unit 123 may determine a second regulation rate for adjusting the frequency in response to a regulation request amount that is different from the range between the rated discharge power PI2 and the rated charge power - PI2. For example, the determination unit 123 may determine the second regulation rate within a range defined by the first regulation rate and a predetermined lower limit value of the second regulation rate.

[0080] 8 is a graph illustrating another example of frequency response in one electric vehicle when the primary control capacity is divided by the control server according to the embodiment. The adjustment request amount may be a range that is greater than the output power adjustment range of the charging / discharging device 300 corresponding to the contract amount (the range between the upper limit value PI1 and the lower limit value -PI1) and smaller than the range of the rated output power of the charging / discharging device 300 (the range between the upper limit value PI2 and the lower limit value -PI2). In other words, the adjustment request amount may be a range in which PI3, which is greater than PI1 and smaller than PI2, is set as the upper limit, and -PI3, which is smaller than -PI1 and larger than -PI2, is set as the lower limit.

[0081] In the example of Fig. 8, the upper limit value of the adjustment request amount is +PI3 and the lower limit value is -PI3. The second adjustment rate is a rate at which the output power of the charging / discharging device 300 is -PI3 when the amount of fluctuation in the grid frequency is +Δ1, and is +PI3 when the amount of fluctuation in the grid frequency is -Δ1. That is, in the example of Fig. 8, the second adjustment rate is represented as a straight line connecting the point (-Δ1, +PI3) and the point (+Δ1, -PI3). The determination unit 123 can determine the second adjustment rate as a straight line connecting the point (-Δ1, +PI3) and the point (+Δ1, -PI3).

[0082] 8, the second regulation rate is also smaller than the first regulation rate. Therefore, by adjusting the frequency in accordance with the second regulation rate, each charging / discharging device 300 can output power exceeding the above-mentioned PI1 and -PI1 and within the regulation request amount defined by PI3 and -PI3. Therefore, by efficiently charging and discharging each target vehicle within the rated power range, primary regulation power can be provided.

[0083] 9 is a graph illustrating another example of the provision of primary control reserve in a contracted vehicle fleet. In FIG. 9, the horizontal axis represents the frequency fluctuation amount [Hz], and the vertical axis represents the output power [W] of the entire contracted vehicle fleet.

[0084] When the contract amount is small, the output power adjustment range becomes narrow. In this case, when the frequency responds according to the first adjustment rate, the lower limit value of the output power -PE1 is reached with only a slight increase in the frequency, and the upper limit value of the output power +PE1 is reached with only a slight decrease in the frequency. In other words, the frequency adjustment range defined by +Δ1 and -Δ1 is narrow.

[0085] 10 is a graph illustrating another example of frequency response in one electric vehicle when the primary control capacity is equally divided among a plurality of electric vehicles. In Fig. 10, the horizontal axis represents the amount of frequency fluctuation [Hz], and the vertical axis represents the output power [W] of the charging / discharging device 300 corresponding to one electric vehicle 200. In this case, the upper limit value PI1 and the lower limit value -PI1 of the output power adjustment range for one electric vehicle 200 are determined by PI1 = PE1 ÷ N.

[0086] 10, the frequency adjustment range defined by +Δ1 and −Δ1 is small. Therefore, when the grid frequency increases slightly from the reference frequency (frequency fluctuation +Δ1), the output power of the charging / discharging device 300 reaches the rated charging power −PI2, and when the grid frequency decreases slightly from the reference frequency (frequency fluctuation −Δ1), the output power of the charging / discharging device 300 reaches the rated discharging power +PI2. In other words, it is necessary to change the output power sensitively to the amount of frequency fluctuation, and it becomes difficult to make the output power of the charging / discharging device 300 follow the frequency fluctuation.

[0087] Returning to FIG. 3 , as described above, the determination unit 123 may determine the second regulating rate within a range defined by the first regulating rate and the lower limit of the second regulating rate. In this case, the first regulating rate is the upper limit of the second regulating rate. The lower limit can be determined from the perspective of the feasibility of charge / discharge control by the charging / discharging device 300. In other words, the smallest value among the regulating rates that can cause the output power of the charging / discharging device 300 to follow frequency fluctuations can be set as the lower limit of the second regulating rate.

[0088] The determination unit 123 may determine the second adjustment rate to be the lower limit value.

[0089] Fig. 11 is a graph illustrating yet another example of frequency response in one electric vehicle when the primary control capacity is divided by the control server according to the embodiment. Fig. 11 shows a second regulating ratio determined as a lower limit value. The second regulating ratio shown in Fig. 11 indicates that the output power when the frequency fluctuation amount is -0.2 Hz is PI2 and the output power when the frequency fluctuation amount is +0.2 Hz is -PI2. In other words, this second regulating ratio is a straight line connecting the points (-0.2 Hz, +PI2) and (+0.2 Hz, -PI2).

[0090] Returning to FIG. 3 , the determination unit 123 can determine a control limit value for the output power of the charging / discharging device 300 that is different from the rated output power of the charging / discharging device 300. The control limit value includes an upper control limit value and a lower control limit value. The control limit value is, for example, an output power value of the charging / discharging device 300 that corresponds to a specific frequency when the charging / discharging device 300 responds to the frequency at the second regulating rate. That is, in the example of FIG. 11 , the upper control limit value is the output power value +PI4 of the charging / discharging device 300 that corresponds to −Δ1 when the charging / discharging device 300 responds to the frequency at the second regulating rate, and the lower control limit value is the output power value −PI4 of the charging / discharging device 300 that corresponds to +Δ1. With the second regulating rate in FIG. 11 , a frequency fluctuation of −Δ1 corresponds to a control upper limit value +PI4 that is smaller than the rated discharge power +PI2. Similarly, a frequency fluctuation +Δ1 corresponds to a control upper limit value −PI4 that is greater than the rated charge power −PI2. Therefore, the required adjustment amount falls within the range defined by the control upper limit value +PI4 and the control lower limit value -PI4.

[0091] The control upper limit value +PI4 is smaller than the rated discharge power +PI2, and the control upper limit value -PI4 is larger than the rated charge power -PI2. Therefore, with this second regulation ratio, it is not possible to use all of the rated output power of the charging / discharging device 300. However, since the second regulation ratio corresponds to a response in which charging / discharging is performed at a smaller output than the second regulation ratio shown in Figure 10 under the same frequency fluctuation, the ability of the output power to follow frequency fluctuations is improved. Therefore, the charging / discharging device 300 can respond accurately to the grid frequency.

[0092] Returning to Fig. 3 , the output unit 124 outputs a command for charge / discharge control at the second adjustment rate determined by the determination unit 123. For example, the output unit 124 can transmit a charge / discharge control command to the charge / discharge device 300. The charge / discharge control command is transmitted to the charge / discharge device 300 connected to the target vehicle selected by the selection unit. The charge / discharge control command includes information on the second adjustment rate, the provision period, and the adjustment request amount.

[0093] When the provision period arrives, the charging / discharging device 300 starts frequency-responsive charge / discharge control using the second regulation rate. That is, the charging / discharging device 300 detects the grid frequency and, at the second regulation rate, charges / discharges the electric vehicle 200 with output power corresponding to the grid frequency. When the provision period ends, the charging / discharging device 300 ends frequency-responsive charge / discharge of the electric vehicle 200.

[0094] 4. Operation of the Charge / Discharge Control System The processor 101 of the control server 100 executes the control program 110, which enables the control server 100 to perform the following control processing: Fig. 12 is a flowchart showing an example of the control processing performed by the control server according to the embodiment.

[0095] The aggregator 20 submits a bid to the electricity market 40. When the bid is contracted, contract information is transmitted from the electricity market 40, and the control server 100 receives the contract information 111. The processor 101 acquires the contract quantity included in the contract information 111 (step S101).

[0096] The processor 101 acquires from the vehicle DB 113 the rated output power (rated discharge power and rated charge power) of the charging / discharging device 300 corresponding to each electric vehicle 200 included in the contracted vehicle group 400 (step S102).

[0097] The processor 101 selects a target vehicle to be used for providing primary control reserve from the contracted vehicle group 400 (step S103).

[0098] Processor 101 determines the second adjustment ratio (step S104). Note that steps S103 and S104 do not have to be executed in this order. For example, processor 101 may execute step S103 after executing step S104. For example, in the example of FIG. 11 , processor 101 can select a target vehicle after determining the second adjustment ratio and determine the output power adjustment range of each charging / discharging device 300. In another example, processor 101 can alternately execute steps S103 and S104 multiple times. This allows the second adjustment ratio and the target vehicle to be determined in stages.

[0099] The processor 101 transmits a charge / discharge control command to the charging / discharging device 300 corresponding to the selected target vehicle (step S105). The charge / discharge control command includes information on the provision period, the adjustment request amount, the frequency adjustment range, and the second adjustment rate. This completes the control process.

[0100] When the charge / discharge device 300 receives the charge / discharge control command, it charges / discharges the electric vehicle 200 in accordance with the provision period, adjustment request amount, frequency adjustment range, and second adjustment rate included in the charge / discharge control command. Each target vehicle is charged / discharged, and a forward or reverse power flow to the power grid occurs according to the grid frequency, thereby providing primary control power.

[0101] [5. Supplementary Note] The embodiments disclosed herein are illustrative in all respects and are not restrictive. The scope of the present invention is defined by the claims, not the above-described embodiments, and includes meanings equivalent to the claims and all modifications within the scope thereof.

[0102] REFERENCE SIGNS LIST 10 Charging / discharging control system 20 Aggregator 30 Local TSO 40 Electricity market 50 Internet 100 Control server 101 Processor 102 Non-volatile memory 103 Volatile memory 104 Communication interface 110 Control program 111 Contract information 112 First adjustment rate 113 Vehicle database (vehicle DB) 121 Acquisition unit 122 Selection unit 123 Determination unit 124 Output unit 200 Electric vehicle 300 Charging / discharging device 400 Contract vehicle fleet 410 Target vehicle fleet

Claims

1. A control device that controls the charging and discharging of a vehicle group including a plurality of electric vehicles, comprising: an acquisition unit that acquires an adjustment request amount indicating an output adjustable range, which is a range within which the output power of a charging / discharging device that charges and discharges the electric vehicles can be adjusted in response to frequency fluctuations in a power system; and a determination unit that determines a second adjustment rate that is smaller than a first adjustment rate set for the vehicle group based on the adjustment request amount acquired by the acquisition unit, as a adjustment rate to be used in controlling the charging and discharging of the electric vehicles included in the vehicle group.

2. The control device according to claim 1, wherein the second adjustment rate is a adjustment rate for setting the output power of the charging / discharging device to the limit value of the adjustment request amount when the frequency of the power grid fluctuates to a specific frequency.

3. The control device according to claim 2, wherein the specific frequency is a limit value of a frequency adjustment range of the charging / discharging device when the charging / discharging device responds to frequency according to the first adjustment rate within an output power adjustment range determined for the vehicle group.

4. The control device according to claim 2, wherein the limit value of the adjustment request amount is a rated output power of the charge / discharge device.

5. The control device according to claim 1, wherein the determination unit determines the second adjustment ratio within a range defined by the first adjustment ratio and a predetermined lower limit value of the second adjustment ratio.

6. The control device according to claim 5, wherein the determination unit determines the second adjustment rate to be the lower limit value.

7. The control device according to claim 6, wherein the determination unit determines a control limit value of the output power of the charging / discharging device that is different from a rated output power of the charging / discharging device.

8. The control device according to claim 7, wherein the control limit value is an output power value of the charging / discharging device that corresponds to a specific frequency when the charging / discharging device responds to a frequency according to the second adjustment rate.

9. The control device according to claim 8, wherein the specific frequency is a limit value of a frequency adjustment range of the charging / discharging device when the charging / discharging device responds to frequency according to the first adjustment rate within an output power adjustment range determined for the vehicle group.

10. The control device according to any one of claims 1 to 9, further comprising a selection unit that selects a target vehicle that is an electric vehicle that is subject to charge / discharge control based on the second adjustment rate, based on an output power adjustment range determined for the vehicle group and the adjustment request amount of each of the plurality of electric vehicles included in the vehicle group.

11. The control device according to claim 10, wherein the selection unit selects the target vehicles such that a sum of the adjustment request amounts of the multiple target vehicles satisfies a condition based on the output power adjustment range.

12. A control method for controlling charging and discharging of a vehicle group including a plurality of electric vehicles, comprising: a step of acquiring an adjustment request amount indicating an output adjustable range within which the output power of a charging / discharging device that charges and discharges the electric vehicles can be adjusted in response to frequency fluctuations in a power grid; and a step of determining, based on the acquired adjustment request amount, a second adjustment rate that is smaller than a first adjustment rate determined for the vehicle group, as a adjustment rate to be used in controlling the charging and discharging of the electric vehicles included in the vehicle group.

13. A control program for controlling the charging and discharging of a vehicle group including a plurality of electric vehicles, the control program causing a computer to execute the steps of: acquiring an adjustment request amount indicating an output adjustable range within which the output power of a charging / discharging device that charges and discharges the electric vehicles can be adjusted in response to frequency fluctuations in a power grid; and determining, based on the acquired adjustment request amount, a second adjustment rate that is smaller than a first adjustment rate determined for the vehicle group, as the adjustment rate to be used in controlling the charging and discharging of the electric vehicles included in the vehicle group.

Citation Information

Patent Citations

  • Power supply system including battery energy storage system

    JP2016167965A

  • Method for controlling coordination system of storage battery and power conversion device, and power conditioning system

    JP2018121479A

  • Control device and program

    JP7174178B1

  • Control device, power storage device, control method and recording medium

    WO2016063739A1

Cited By

  • Planning system and planning method

    JP2026125521A

  • Planning System and Planning Method

    JP7683837B1