Manufacturing plan formulation method, manufacturing plan formulation system, program, and information terminal
The manufacturing planning method addresses the challenge of worker replacement and learning losses by using a proficiency-based index to generate more accurate and feasible manufacturing plans, enhancing production efficiency in line production systems.
Patent Information
- Application Number
- PCT/JP2024/024405
- Authority / Receiving Office
- WO · WO
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-07-10
- Filing Date
- 2024-07-05
- Publication Date
- 2025-01-16
AI Technical Summary
In manufacturing processes with multiple workers, especially in line production systems, the replacement of workers leads to learning losses and delays, making it challenging to accurately calculate takt time and maintain manufacturing plans, especially when inexperienced workers are involved.
A manufacturing planning method and system that uses a first index value to assess the degree of worker replacement and change in proficiency levels, generating a manufacturing plan based on this data to improve plan feasibility by accounting for changes in productivity over time.
This approach allows for more accurate and feasible manufacturing plans by identifying changes in worker proficiency and adjusting production schedules accordingly, reducing delays and improving overall manufacturing efficiency.
Smart Images

Figure JP2024024405_16012025_PF_FP_ABST
Abstract
Description
Manufacturing planning method, manufacturing planning system, program, and information terminal
[0001] The present disclosure relates to a manufacturing planning method, a manufacturing planning system, a program, and an information terminal.
[0002] Patent Document 1 provides a method for estimating takt time for each work process according to a product to be assembled and manufactured, taking into account work elements common to different product varieties. In Patent Document 1, the work processes are divided into work elements based on performance data of the work processes performed on an assembly production line to be handled by multiple workers, and work element learning curves are prepared for each worker, in which work times are calculated corresponding to each work element. When a product to be assembled and manufactured on the assembly production line is selected and workers to handle the process are assigned, the work time for the planned cumulative number of work operations is calculated for the worker of that work process from the work element learning curve, the calculated work times are tallied by product, and a predetermined calculation is performed based on the tallied times to calculate the takt time for the work process according to the product to be assembled and manufactured.
[0003] Patent No. 4655494
[0004] In manufacturing sites such as factories, there are processes that require manual labor, such as manufacturing. In particular, in line production, multiple workers are assigned to work on a single production line. In such cases, if one worker's work is delayed, the work of other workers will also be delayed. Workers on the production line are not necessarily full-time employees of the product manufacturer; they may also be temporary or part-time workers. When temporary or part-time workers are included in the production line work, workers are likely to be replaced at regular intervals (e.g., monthly). If a worker is inexperienced and has never performed the work, a training period is provided, but due to their unfamiliarity, work delays are likely to occur. Therefore, when a worker is replaced, there is a learning loss until the new worker becomes proficient in the work on the production line.
[0005] The technology described in Patent Document 1 makes it possible to calculate the takt time (required time) of a work process according to the product to be assembled by preparing a task element learning curve for each worker. However, when an inexperienced worker who has never performed the work joins the work, it is not possible to prepare a task element learning curve, and the required time of the work process cannot be calculated correctly. Therefore, even if a manufacturing plan is set based on the required time of such a work process, the plan is likely to be unlikely to be realized.
[0006] The present disclosure provides a manufacturing planning method, a manufacturing planning system, a program, and an information terminal that enable improvement in the feasibility of manufacturing plans.
[0007] A manufacturing plan formulation method according to one aspect of the present disclosure is executed by an arithmetic circuit to formulate a manufacturing plan for a product to be manufactured in a manufacturing process in which multiple execution entities perform work in sequence, identifies a first index value indicating the degree of turnover among the multiple execution entities during a first period, identifies changes in the proficiency levels of the multiple execution entities since the start of the first period based on the first index value, and outputs a manufacturing plan for the product for the first period based on the changes in proficiency.
[0008] According to one aspect of the present disclosure, there is provided a manufacturing planning system for formulating a manufacturing plan for a product to be manufactured in a manufacturing process in which multiple execution entities perform work in sequence, the system including a first arithmetic circuit, the first arithmetic circuit identifying a first index value indicating a degree of turnover among the multiple execution entities during a first period, identifying a change in proficiency of the multiple execution entities since the start of the first period based on the first index value, and outputting a manufacturing plan for the product for the first period based on the change in proficiency.
[0009] A program according to one aspect of the present disclosure is a program for causing an arithmetic circuit to execute the above-described manufacturing planning method.
[0010] An information terminal according to one aspect of the present disclosure is an information terminal communicatively connected to the manufacturing planning system, and includes an input device, an output device, a communication device, and a second arithmetic circuit that controls the input device, the output device, and the communication device. The second arithmetic circuit accepts an input of a first index value via the input device, transmits the first index value to the manufacturing planning system via the communication device to receive a manufacturing plan from the manufacturing planning system, and presents the manufacturing plan via the output device.
[0011] Aspects of the present disclosure enable improved feasibility of manufacturing projects.
[0012] Schematic diagram of a manufacturing system according to one embodiment. Schematic diagram of a manufacturing facility for the manufacturing system according to the embodiment. Block diagram of a manufacturing plan formulation system for the manufacturing system according to the embodiment. Block diagram of an information terminal for the manufacturing system according to the embodiment. Flowchart of a manufacturing plan formulation method using the manufacturing plan formulation system. Graph showing time-series data of required time. Graph showing a first example of changes in proficiency. Graph showing a second example of changes in proficiency. Bar graph showing the number of products manufactured per unit period according to the manufacturing plan. Bar graph showing the work time per unit period according to the manufacturing plan.
[0013] [1. Embodiments] Hereinafter, embodiments of the present disclosure will be described, with reference to the drawings where appropriate. However, the following embodiments are merely examples for explaining the present disclosure, and are not intended to limit the present disclosure to the following content (e.g., the shape, dimensions, and arrangement of each component). Positional relationships, such as up, down, left, and right, are based on the positional relationships shown in the drawings unless otherwise specified. Each figure described in the following embodiments is a schematic diagram, and the ratios of the size and thickness of each component in each figure do not necessarily reflect the actual dimensional ratios. Furthermore, the dimensional ratios of each element are not limited to the ratios shown in the drawings.
[0014] In the following description, when it is necessary to distinguish between multiple components, prefixes such as "first" and "second" are added to the names of the components. However, when the components can be distinguished from each other by the symbols attached to them, the prefixes such as "first" and "second" may be omitted in consideration of readability of the text.
[0015] In the following description, when it is necessary to distinguish between multiple components, suffixes such as "-1" and "-2" are added to the symbols of the components. However, when it is not necessary to distinguish between multiple components, the suffixes "-1" and "-2" may be omitted to improve readability.
[0016] [1.1 Configuration] Fig. 1 is a schematic diagram of a manufacturing system 1 according to this embodiment. The manufacturing system 1 is used to manufacture products in a planned manner. Products are manufactured from raw materials through multiple processes. Products are not particularly limited, but include various items such as food, pharmaceuticals, electrical appliances, jewelry, furniture, and vehicles. Products are not limited to finished products, and may also be parts. An example of a finished product is an automobile, and an example of a part is a core part of the automobile (such as a piston).
[0017] The manufacturing system 1 includes a manufacturing facility 2, a manufacturing planning system 3, and an information terminal 4. The manufacturing planning system 3 and the information terminal 4 constitute an information processing device.
[0018] The manufacturing facility 2 is a facility (e.g., a factory) that actually manufactures products. The manufacturing facility 2 includes a manufacturing line 20 for manufacturing products using a line production method. The manufacturing line 20 may include one or more manufacturing equipment that enables manufacturing using various manufacturing technologies. Examples of manufacturing technologies include additive manufacturing technologies (material extrusion, liquid bath photopolymerization, material jetting, binder jetting, powder bed fusion, sheet lamination, directed energy deposition, etc.), subtractive manufacturing technologies (cutting, grinding, electrical discharge machining, casting, die casting, pressing, forging, sheet metal processing, etc.), formative (forming) manufacturing technologies (injection molding, extrusion molding, etc.), surface treatment technologies (coating, painting, plating, polishing, etc.), heat treatment technologies (sintering, cooling, etc.), joining technologies (ultrasonic joining, thermal welding, mechanical joining, adhesives, etc.), and assembly technologies (part assembly, micro-imprinting, impregnation, etc.). The manufacturing line 20 is not limited to manufacturing equipment, but may also include measurement equipment, inspection equipment, and transport equipment. Examples of the manufacturing facility 2 include a factory, a store, and a building (an entire building or a floor).
[0019] FIG. 2 is a schematic diagram of a production line 20. The production line 20 realizes a manufacturing process in which multiple execution entities 21-1 to 21-N (N is an arbitrary integer) perform tasks in sequence. The execution entities 21-1 to 21-N perform their tasks in sequence, resulting in a finished product M3, via one or more work-in-progress items M2, starting from raw material M1. The execution entity 21 is, for example, a worker (person). The execution entity 21 is not limited to a person, as long as the concept of proficiency is applicable. In other words, as long as the speed at which tasks are completed is improved by repeating the same tasks, the execution entity 21 may be a machine using machine learning instead of a person. The machine learning device may be a work device such as a robot. Therefore, the production line 20 may be an automated production line using robots or the like.
[0020] The manufacturing planning system 3 is used to formulate a manufacturing plan for a product to be manufactured in a manufacturing process in which multiple execution entities 21 perform work in sequence. FIG. 3 is a block diagram of the manufacturing planning system 3. The manufacturing planning system 3 includes a first input device 31, a first output device 32, a first communication device 33, a first storage device 34, and a first arithmetic circuit 35. The manufacturing planning system 3 can be realized, for example, by one or more servers.
[0021] The first input device 31 includes one or more human-machine interfaces for inputting information. Examples of the human-machine interface include a keyboard, a pointing device (such as a mouse or a trackball), a touchpad, a position input device such as a touch panel display, etc. The one or more human-machine interfaces of the first input device 31 may be built into the manufacturing planning system 3 or may be externally attached. In other words, the first input device 31 may include a human-machine interface of the manufacturing planning system 3 itself and a human-machine interface connected to the manufacturing planning system 3.
[0022] The first output device 32 includes one or more human-machine interfaces for outputting information. Examples of the human-machine interface include a display, a speaker, a touch panel display, and other output interfaces. The one or more human-machine interfaces of the first output device 32 may be built into the manufacturing planning system 3 or may be externally attached. In other words, the first output device 32 may include a human-machine interface of the manufacturing planning system 3 itself and a human-machine interface connected to the manufacturing planning system 3.
[0023] The first communication device 33 is used for communication through a communication network. The first communication device 33 has one or more communication interfaces. The first communication device 33 is connectable to a communication network and has the function of communicating through the communication network. The first communication device 33 complies with a predetermined communication protocol. The predetermined communication protocol may be selected from various well-known wired and wireless communication standards.
[0024] The first storage device 34 includes one or more storages (non-transitory storage media). The storages may be, for example, hard disk drives, optical drives, or solid-state drives (SSDs). The storages may be internal, external, or network-attached storage (NAS).
[0025] The information stored in the first storage device 34 includes a manufacturing history database DB1 and a manufacturing plan D1. The manufacturing history database DB1 and the manufacturing plan D1 do not need to be stored in the first storage device 34 at all times, but only need to be stored in the first storage device 34 when needed by the first arithmetic circuit 35.
[0026] The manufacturing plan D1 is a manufacturing plan for a product to be manufactured in a manufacturing process in which a plurality of execution entities 21 perform work in sequence. In this embodiment, the manufacturing plan D1 is a plan for manufacturing a target number of products in a first period. Details of the manufacturing plan D1 will be described later.
[0027] The production history database DB1 is used to formulate the production plan D1. The production history database DB1 includes various information related to the production of products at the production facility 2. The production history database DB1 includes multiple pieces of production history data. For example, the production history database DB1 includes production history data for multiple different second periods for each production line 20 of the production facility 2. Each piece of production history data is configured to include, for the corresponding second period, time-series data on the actual production quantity of the product, time-series data on the target production quantity, time-series data on the actual work time, time-series data on the target work time, required time data indicating a change in required time, and a second index value. The second period begins with a change in the multiple execution entities 21. Therefore, the required time data indicates a change in the required time of the production process since the change in the multiple execution entities 21. The required time is the time required to complete a production process, i.e., the time from the start to the end of the production process. The required time may also be referred to as cycle time, pitch time, or takt time. In this embodiment, the change in required time is the change in required time relative to elapsed time. It is assumed that there is no replacement of the multiple execution agents 21 during the second period. The second period is, for example, one month, from the 1st to the last day of the target month. The second index value corresponds to attribute data of a group including multiple execution agents (workers). The attribute data includes the degree of replacement of the multiple execution agents (workers). Therefore, the second index value indicates the degree of replacement of the multiple execution agents 21 during the second period. The degree of replacement of the multiple execution agents 21 may be the number of replacements of the multiple execution agents 21 or the replacement rate of the multiple execution agents 21. For example, assume that six out of ten execution agents 21 have been replaced. In this case, the number of replacements of the multiple execution agents 21 is six, and the replacement rate of the multiple execution agents 21 is 60%.
[0028] The first arithmetic circuit 35 is connected to the first input device 31, the first output device 32, and the first communication device 33 and can access the first storage device 34. The first arithmetic circuit 35 may be realized by, for example, a computer system. The computer system includes one or more processors (microprocessors) and one or more memories. The one or more processors execute programs (stored in one or more memories or the first storage device 34) to realize various functions of the manufacturing planning system 3. The programs may be pre-recorded in the first storage device 34, or may be provided via a telecommunications line such as the Internet, or recorded on a non-transitory recording medium such as a memory card.
[0029] The first arithmetic circuit 35 acquires information relating to the production of products on each production line 20 of the production facility 2, for example, by communication via the first communication device 33, and updates the production performance database DB1. As an example, the first arithmetic circuit 35 can communicate with each production line 20 of the production facility 2 via the first communication device 33 and acquire history data indicating the production history (past log) at any time.
[0030] The first arithmetic circuit 35 generates and outputs a manufacturing plan D1 by executing a manufacturing plan formulation method described below.
[0031] The information terminal 4 is used for inputting information by the user 5 and presenting information to the user 5. FIG. 4 is a block diagram of the information terminal 4. The information terminal 4 includes a second input device 41, a second output device 42, a second communication device 43, a second storage device 44, and a second arithmetic circuit 45. The information terminal 4 may be realized, for example, by a personal computer (desktop computer, laptop computer), a mobile terminal (smartphone, tablet terminal, etc.), etc. The configurations of the second input device 41, the second output device 42, the second communication device 43, the second storage device 44, and the second arithmetic circuit 45 are similar to the configurations of the first input device 31, the first output device 32, the first communication device 33, the first storage device 34, and the first arithmetic circuit 35.
[0032] Next, a description will be given of a manufacturing planning method executed by the first arithmetic circuit 35. Fig. 5 is a flowchart of the manufacturing planning method.
[0033] When formulating the manufacturing plan D1, the first arithmetic circuit 35 displays the performance of the manufacturing line 20 to which the manufacturing plan D1 is applied so that the user 5 can understand the current situation (S11). More specifically, the first arithmetic circuit 35 transmits information about the performance of the manufacturing line 20 to the information terminal 4 via the first communication device 33. The information terminal 4 displays the performance of the manufacturing line 20 to the user 5 via the second output device 42. The performance information of the manufacturing line 20 is extracted from the manufacturing performance database DB1. The performance information of the manufacturing line 20 may include, for example, time-series data on the actual number of products manufactured, time-series data on the target number of products manufactured, time-series data on the actual work time, time-series data on the target work time, and required time data. This allows the user 5 to easily understand the difference between the actual number of products manufactured and the target number of products manufactured, and the difference between the actual work time and the target work time.
[0034] The first arithmetic circuit 35 identifies conditions for formulating the manufacturing plan D1 (S12). The conditions for formulating the manufacturing plan D1 include a first period, a first index value, a reference time, and an operation time.
[0035] The first period is a period during which products are manufactured according to the production plan D1. The first period begins with the replacement of the multiple execution entities 21. It is assumed that there is no replacement of the multiple execution entities 21 during the first period. The first period is, for example, one month, extending from the 1st to the last day of the target month. The first period is not limited to one month and may be any period, such as one week, three months, or one year. The first period includes multiple unit periods arranged in chronological order. If the first period is one month, each unit period corresponds to each working day in the month. For example, suppose the first period is from November 1st to 30th, with November 3rd and 23rd being national holidays. If November 1st is a Wednesday, the working days are November 1st, 2nd, 6th to 10th, 13th to 17th, 20th to 22nd, 24th, and 27th to 30th, for a total of 19 days.
[0036] The first index value indicates the degree of replacement of the multiple execution entities 21 during the first period. In other words, the first index value is information on the degree of replacement of the multiple workers. The degree of replacement of the multiple execution entities 21 may be the number of replacements of the multiple execution entities 21 or the rate of replacement of the multiple execution entities 21. The user 5 can determine the first index value based on the planned allocation of the execution entities 21 on the production line 20 of the manufacturing facility 2 during the first period.
[0037] The reference time is a target time for the required time of the production line 20. The reference time may correspond to the required time of the production line 20 when all of the multiple execution entities 21 are considered to be sufficiently proficient in the work on the production line 20. The user 5 can determine the reference time based on, for example, a display of the performance of the production line 20.
[0038] The operation time is the time used to manufacture a product in a first period. The first period includes multiple unit periods, and the operation time is allocated to the multiple unit periods as sub-operation times. In other words, the operation time is the sum of the sub-operation times. The operation time is given by the sum of the first operation time, which is a fixed value, and the second operation time, which is a variable value. The first operation time is a value determined for the length of the first period, and the second operation time is a variable value. Similarly, the sub-operation time is given by the sum of the first sub-operation time, which is a fixed value, and the second sub-operation time, which is a variable value. The first sub-operation time is the same across multiple unit periods, and the second sub-operation time can change value for each unit period. The first operation time is the sum of the first sub-operation times, and the second operation time is the sum of the second sub-operation times. Note that the second operation time can be 0.
[0039] For example, if the first period is one month and the unit period is one day, the first sub-task time is the time required to work in one day, and the second sub-task time is the time required to work in one day in addition to the first sub-task time. As an example, the first work time and the first sub-task time correspond to statutory working hours, and the second work time and the second sub-task time correspond to overtime working hours.
[0040] Table 1 below shows an example of setting the first period and work time. In Table 1, the sum of the column for the first sub-task time means the first work time, and the sum of the column for the second sub-task time means the second work time. In Table 1, the work time is the sum of the first work time and the second work time, which is 9,420 hours.
[0041]
[0042] The first arithmetic circuit 35 communicates with the second arithmetic circuit 45 of the information terminal 4 via the first communication device 33, and the second arithmetic circuit 45 displays an input screen on the second output device 42 for the user 5 to input conditions for formulating the manufacturing plan D1. While viewing the input screen, the user 5 uses the second input device 41 of the information terminal 4 to identify the manufacturing line 20 for which the manufacturing plan D1 is to be formulated. The manufacturing line 20 is identified by information such as the identification number and model of the manufacturing line 20. While viewing the input screen, the user 5 can input the first period, first index value, reference time, and operation time via the second input device 41 of the information terminal 4. The second arithmetic circuit 45 accepts the input of the first period, first index value, reference time, and operation time and transmits the first period, first index value, reference time, and operation time to the manufacturing plan formulation system 3 via the second communication device 43. The first arithmetic circuit 35 identifies the first period, the first index value, the reference time, and the operation time based on the first period, the first index value, the reference time, and the operation time received from the information terminal 4. In this way, in the manufacturing planning system 3, the second input device 41 and the first communication device 33 are used to acquire the first period, the first index value, the reference time, and the operation time.
[0043] The second arithmetic circuit 45 may further accept input of additional information via the input screen. The additional information may include, for example, the target number of products to be manufactured in the first period, the unit price of the products, and labor costs for manufacturing the products. The additional information may be input by the user 5 using the second input device 41. The second arithmetic circuit 45 transmits the additional information to the manufacturing planning system 3 via the second communication device 43.
[0044] After identifying the first index value, the first calculation circuit 35 acquires manufacturing history data corresponding to the first index value (S13). More specifically, the first calculation circuit 35 acquires manufacturing history data corresponding to the first index value from the manufacturing history database DB1. The first calculation circuit 35 compares the first index value with the second index values of the multiple manufacturing history data in the manufacturing history database DB1. The first calculation circuit 35 determines that the second index value having the smallest difference from the first index value among the multiple second index values of the manufacturing history data corresponds to the first index value. Therefore, the first calculation circuit 35 extracts the manufacturing history data having the smallest difference between the first index value and the second index value as the manufacturing history data corresponding to the first index value. If there is manufacturing history data including a second index value that matches the first index value, this manufacturing history data is extracted as the manufacturing history data corresponding to the first index value. If there is no manufacturing history data including a second index value that matches the first index value, the manufacturing history data including the second index value closest to the first index value among the multiple manufacturing history data is extracted as the manufacturing history data corresponding to the first index value.
[0045] The first calculation circuit 35 identifies a change in the proficiency of the plurality of execution entities 21 from the start of the first period (S14). The first calculation circuit 35 identifies the change in proficiency from the required time data included in the production performance data corresponding to the first index value.
[0046] FIG. 6 shows an example of required time data with different numbers of replacements of multiple execution entities 21. In FIG. 6, the horizontal axis represents time, and the vertical axis represents a moving average of the median required times. The period of the moving average is one day. In FIG. 6, the second index values corresponding to G1, G2, G3, G4, and G5 increase in this order, i.e., the degree of replacement increases. In FIG. 6, Ts represents the reference time for the required time of the production line 20. It can be seen from FIG. 6 that the larger the second index value, the longer the required time at the beginning of the cycle and the longer the time it takes for the required time to reach the reference time Ts.
[0047] The change in proficiency level is determined based on the length of the familiarization section from the time when the multiple execution entities 21 are replaced until the required time reaches the reference time Ts in the required time data, and the representative value of the required time within the familiarization section. In this embodiment, the representative value of the required time within the familiarization section is the maximum value. Note that, in addition to the maximum value, examples of the representative value include the median and the mode. Note that, in this embodiment, the change in the required time is a change over time, so the unit of the length of the familiarization section is time.
[0048] FIG. 7 is a graph showing a first example of changes in proficiency. In the first example, the required time is used as an index of proficiency. The shorter the required time, the higher the proficiency. The first example is suitable for cases where proficiency is considered to change linearly. In FIG. 7, ta is the time when multiple execution entities 21 are replaced, and ts is the time when the required time reaches the reference time Ts. The period from time ta to time ts is the familiarization interval. Ta is the representative value (maximum value in this embodiment) of the required time within the familiarization interval. If time is t and the required time is T, the graph in FIG. 7 is expressed by the following equations (1) and (2).
[0049]
[0050] FIG. 8 is a graph showing a second example of changes in proficiency. In the second example, the required time is used as an index of proficiency, just like in the first example. The second example is suitable for cases where the proficiency is considered to change in a curved line. The graph in FIG. 8 is expressed by the following equation (3). c in equation (3) 1 , c 2 is a parameter of proficiency, which can be identified by fitting to the time required data.
[0051]
[0052] The above formula (1), (2), or (3) can be considered a model that models the change in proficiency over a period of time for a group including multiple workers. The first arithmetic circuit 35 can compare the model based on the acquired degree of turnover of multiple workers and simulate the proficiency. The change in proficiency can be obtained by simulating the proficiency.
[0053] Referring again to FIG. 5, the first arithmetic circuit 35 generates a production plan D1 (S15). In generating the production plan D1, the planned number of products to be manufactured in the first period is calculated. The planned number is determined based on the work time used to manufacture the products in the first period and changes in proficiency. To reflect changes in proficiency in the planned number, the planned number is given as the total number of products to be manufactured in multiple unit periods. In each of the multiple unit periods, the number of products to be manufactured is given by the sub-task time in the unit period out of the work time and the proficiency in the unit period calculated from changes in proficiency.
[0054] For example, the first example shown in Figure 7 will be applied to changes in proficiency. When the reference time Ts is 60 seconds, the representative value Ta is 100 seconds, and the familiarization interval (the number of days between ts and ta) is 10 days, the change in the required time T, which indicates changes in proficiency, is as shown in Table 2 below. In Table 2 below, the familiarization ratio is given by T / Ts, and the familiarization loss ratio is given by Ts / T. The familiarization ratio and the familiarization loss ratio can be used as indicators of proficiency instead of the required time T.
[0055]
[0056] In this embodiment, when the required time T is used as the level of proficiency, the number of manufactured products is obtained by dividing the small task time by the required time T. When the learning loss ratio is used as the level of proficiency, the number of manufactured products is obtained by multiplying the value obtained by dividing the small task time by the reference time Ts by the learning loss ratio.
[0057] Table 3 below shows the number of products manufactured in each unit period obtained from Tables 1 and 2. Furthermore, Table 3 below shows the number of products manufactured in the first sub-task time and the number of products manufactured in the second sub-task time of each unit period. The number of products manufactured in each unit period is the sum of the number of products manufactured in the first sub-task time and the number of products manufactured in the second sub-task time of each unit period.
[0058]
[0059] The planned quantity is the total number of products to be manufactured over multiple unit periods, which is 8,249 units in the case of Table 3 below. The planned quantity includes a first planned quantity corresponding to a first working time and a second planned quantity corresponding to a second working time. The first planned quantity is 7,599 units, and the second planned quantity is 650 units. In this manner, the planned quantity of products to be manufactured in the first period is determined. The planned quantity is calculated using the change in proficiency level during the first period. Therefore, when products are actually manufactured according to the manufacturing plan D1, it is highly likely that a number of products that matches or is close to the planned quantity of the manufacturing plan D1 can be obtained. This makes it possible to improve the feasibility of the manufacturing plan D1.
[0060] The production plan D1 includes the planned number of products to be produced in the first period, as well as the number of products to be produced in each of multiple unit periods arranged in chronological order within the first period. The numbers of products to be produced in the multiple unit periods are determined in the process of calculating the planned numbers. The number of products to be produced in each unit period is calculated using changes in proficiency levels during the first period. Therefore, when products are actually produced according to the production plan D1, it is highly likely that the number of products obtained will match or be close to the number of products to be produced in each unit period of the production plan D1. This makes it possible to improve the feasibility of the production plan D1.
[0061] The production plan D1 includes sales of products based on the planned quantity. The sales of products based on the planned quantity are calculated from the planned quantity and the unit price of the products. For example, the sales of products based on the planned quantity are calculated by multiplying the planned quantity by the unit price of the products.
[0062] The production plan D1 includes a manufacturing cost of the product based on the second operation time and sales of the product based on the second planned quantity. The manufacturing cost of the product based on the second operation time is calculated from the second operation time and labor costs. As an example, the manufacturing cost of the product based on the second operation time is calculated by multiplying the second operation time by the labor costs. Sales of the product based on the second planned quantity is calculated from the second planned quantity and the unit price of the product. As an example, sales of the product based on the second planned quantity is calculated by multiplying the second planned quantity by the unit price of the product.
[0063] The production plan D1 further includes a target number of products to be produced in a first period and a target value of the work time for the first period, which are extracted from the additional information.
[0064] The manufacturing plan D1 may include conditions for formulating the manufacturing plan D1, a first period, a first index value, a reference time, and an operation time.
[0065] The first arithmetic circuit 35 outputs the manufacturing plan D1 obtained in this way (S16). The first arithmetic circuit 35 transmits information on the manufacturing plan D1 to the information terminal 4 via the first communication device 33.
[0066] The information terminal 4 presents the manufacturing plan D1 received from the manufacturing plan development system 3 to the user 5 via the second output device 42. In the information terminal 4, the second arithmetic circuit 45 can generate graph information or a GUI (graphical user interface) showing the manufacturing plan D1 by simulating the proficiency level.
[0067] The second calculation circuit 45 can present the planned number of products to be manufactured in the first period based on the production plan D1. The planned number may be displayed in association with the number of products to be manufactured in the second sub-task time. As an example, the planned number may be displayed together with the total number of second sub-task times and the number of products to be manufactured in the second sub-task time. In Table 1, the total operation time is 9,420 minutes, and the total number of second sub-task times is 720 minutes. In this case, Table 3 shows that the planned number is 8,249, of which 650 is the number of products to be manufactured in the second sub-task time. The second calculation circuit 45 may display results indicating the number of products to be manufactured and the operation time in the first period, as well as increments indicating the number of products to be manufactured in the second sub-task time and the total number of second sub-task times, in a table format, as shown in Table 4 below. This allows the user 5 to easily understand how much the second sub-task time should be adjusted to adjust the planned number of products, making it easier to consider revising the production plan D1.
[0068]
[0069] The planned quantity may be displayed in association with the target number of products to be manufactured in the first period. For example, the planned quantity may be displayed together with the difference between the planned quantity and the target quantity, and the work time corresponding to the difference between the target quantity and the planned quantity. The work time corresponding to the difference between the target quantity and the planned quantity is calculated from the difference between the target quantity and the planned quantity and the reference time. For example, if the target quantity is 8,000 units, the difference between the target quantity and the planned quantity is +249 units, and the work time corresponding to the difference between the characteristic quantity and the planned quantity is +249 minutes. The second calculation circuit 45 may display the planned quantity, the difference between the planned quantity and the target quantity, the work time, and the work time corresponding to the difference between the target quantity and the planned quantity in a table format, as shown in Table 5 below. This allows the user 5 to easily understand how much the work time needs to be adjusted to achieve the planned number of products as the target number, making it easier to consider revising the manufacturing plan D1.
[0070]
[0071] Based on the production plan D1, the second calculation circuit 45 presents the number of products to be produced for each of a plurality of unit periods arranged in chronological order within the first period. The number of products to be produced in a unit period may be divided into the number of products to be produced in a first sub-task period and the number of products to be produced in a second sub-task period. This allows the user 5 to easily understand the work time and easily consider revising the production plan D1. The second calculation circuit 45 may display the number of products to be produced in a unit period as a graph. Figure 9 is a bar graph showing the number of products to be produced in a unit period according to the production plan. In Figure 9, the white bars indicate the number of products to be produced in the first sub-task period, and the gray bars indicate the number of products to be produced in the second sub-task period.
[0072] The second calculation circuit 45 presents the sub-task times for each of a plurality of unit periods arranged in chronological order within the first period based on the manufacturing plan D1. In particular, the sub-task times may be divided into a first sub-task time and a second sub-task time. This allows the user 5 to easily understand the task times and easily consider revising the manufacturing plan D1. The second calculation circuit 45 may display the sub-task times for each unit period in a graph. FIG. 10 is a bar graph showing the sub-task times for each unit period according to the manufacturing plan. In FIG. 10, the white bars indicate the first sub-task times, and the gray bars indicate the second sub-task times.
[0073] The second arithmetic circuit 45 presents the sales amount of the product based on the planned number of units, based on the manufacturing plan D1, thereby allowing the user 5 to easily understand the sales amount of the product.
[0074] The second calculation circuit 45 presents the production cost of the product based on the second operation time and the sales amount of the product based on the second planned quantity based on the production plan D1, thereby enabling the user 5 to consider revising the production plan D1 based on a comparison between the production cost of the product based on the second operation time and the sales amount of the product based on the second planned quantity.
[0075] In this way, the user 5 can refer to the manufacturing plan D1 presented on the second output device 42 of the information terminal 4 and modify the manufacturing plan D1 by changing the conditions for formulating the manufacturing plan D1, the first period, the first index value, the reference time, and the operation time as necessary. In this embodiment, the operation time is divided into a first operation time, which is a fixed value, and a second operation time, which is a variable value, and the first operation time and the second operation time can be identified separately. Therefore, the user 5 can bring the operation time corresponding to the difference between the target number and the planned number closer to the target number by adjusting the second operation time so that the operation time corresponding to the difference between the target number and the planned number approaches 0 minutes. When adopting the manufacturing plan D1, the user 5 may output the manufacturing plan D1 from the information terminal 4 and apply it to an actual plan.
[0076] The manufacturing plan formulation method described above can identify changes in the proficiency of the manufacturing line 20 depending on the degree of replacement of the multiple execution entities 21 of the manufacturing line 20, and can therefore formulate a manufacturing plan D1 that can be executed by the manufacturing line 20. This makes it possible to accurately grasp the outlook for the plan for the entire factory or supply chain.
[0077] 1.2 Effects, etc. The manufacturing planning method described above is a manufacturing planning method executed by an arithmetic circuit (first arithmetic circuit 35) to formulate a manufacturing plan D1 for a product manufactured in a manufacturing process in which multiple execution entities 21 perform work in sequence, and includes identifying a first index value indicating the degree of turnover among the multiple execution entities 21 during a first period, identifying changes in the proficiency levels of the multiple execution entities since the start of the first period based on the first index value, and outputting a manufacturing plan D1 for the product for the first period based on the changes in proficiency. This configuration makes it possible to improve the feasibility of the manufacturing plan D1.
[0078] In the manufacturing plan development method, the arithmetic circuit (first arithmetic circuit 35) can access a manufacturing history database DB1 that includes multiple pieces of manufacturing history data. Each piece of manufacturing history data includes required time data indicating a change in the required time of a manufacturing process since the multiple execution entities 21 are replaced, and a second index value indicating the degree of replacement of the multiple execution entities 21. A change in proficiency is identified based on the required time data of the manufacturing history data that includes the second index value corresponding to the first index value among the multiple pieces of manufacturing history data. This configuration enables a further improvement in the feasibility of the manufacturing plan D1 because a change in proficiency is identified based on actual results.
[0079] In the manufacturing planning method, a change in proficiency level is determined based on the length of a familiarization period from when the multiple execution entities 21 are replaced until the required time reaches a reference time in the required time data, and a representative value of the required time within the familiarization period in the required time data. This configuration enables further improvement in the feasibility of the manufacturing plan D1.
[0080] In the manufacturing planning method, the representative value is the maximum value. This configuration enables further improvement in the feasibility of the manufacturing plan D1.
[0081] In the manufacturing plan formulation method, the second index value having the smallest difference from the first index value among the second index values of the plurality of manufacturing performance data is determined to correspond to the first index value. This configuration enables further improvement in the feasibility of the manufacturing plan D1.
[0082] In the manufacturing planning method, the manufacturing plan D1 includes the planned number of products to be manufactured in the first period. This configuration makes it easy to consider modifying the manufacturing plan D1.
[0083] In the manufacturing planning method, the manufacturing plan D1 includes a target number of products to be manufactured in the first period. This configuration makes it easy to consider modifying the manufacturing plan D1.
[0084] In the manufacturing planning method, the planned quantity is determined based on the operation time used to manufacture the product in the first period and changes in proficiency. This configuration enables further improvement in the feasibility of the manufacturing plan D1.
[0085] In the manufacturing planning method, the manufacturing plan includes the number of products to be manufactured for each of a plurality of unit periods arranged in chronological order within a first time period. In each of the plurality of unit periods, the number of products to be manufactured is given by the subtask time within the unit period out of the total work time and the proficiency level for the unit period calculated from changes in proficiency. This configuration makes it easy to consider revisions to the manufacturing plan D1.
[0086] In the manufacturing planning method, the manufacturing plan D1 includes sales figures for products based on the planned number. This configuration makes it easy to consider revisions to the manufacturing plan D1.
[0087] In the manufacturing planning method, the operation time is the sum of a first operation time, which is a fixed value, and a second operation time, which is a variable value. The first operation time and the second operation time are specified separately. This configuration makes it easy to consider modifying the manufacturing plan D1.
[0088] In the manufacturing planning method, the scheduled quantity includes a first scheduled quantity corresponding to a first operation time and a second scheduled quantity corresponding to a second operation time. The manufacturing plan includes a manufacturing cost of the product based on the second operation time and sales of the product based on the second scheduled quantity. This configuration makes it easy to consider revisions to the manufacturing plan D1.
[0089] The manufacturing plan formulation system 3 described above is a manufacturing plan formulation system for formulating a manufacturing plan D1 for a product manufactured in a manufacturing process in which multiple execution entities 21 perform work in sequence, and includes a first arithmetic circuit 35. The first arithmetic circuit 35 identifies a first index value indicating the degree of turnover among the multiple execution entities 21 during a first period, identifies changes in the proficiency of the multiple execution entities since the start of the first period based on the first index value, and outputs a manufacturing plan D1 for the product for the first period based on the changes in proficiency. This configuration makes it possible to improve the feasibility of the manufacturing plan D1.
[0090] The above-described program is a program for causing the first arithmetic circuit 35 to execute the manufacturing plan formulation method. This configuration makes it possible to improve the feasibility of the manufacturing plan D1.
[0091] The information terminal 4 described above is communicatively connected to the manufacturing planning system 3 and includes a second input device 41, a second output device 42, a second communication device 43, and a second arithmetic circuit 45 that controls the second input device 41, the second output device 42, and the second communication device 43. The second arithmetic circuit 45 accepts input of a first index value via the second input device 41, transmits the first index value to the manufacturing planning system 3 via the second communication device 43, receives the manufacturing plan D1 from the manufacturing planning system 3, and presents the manufacturing plan D1 via the second output device 42. This configuration makes it possible to improve the feasibility of the manufacturing plan D1.
[0092] [2. Modifications] The embodiments of the present disclosure are not limited to the above-described embodiments. The above-described embodiments can be modified in various ways depending on the design, etc., as long as the object of the present disclosure can be achieved. Modifications of the above-described embodiments are listed below. The modifications described below can be applied in appropriate combinations.
[0093] In one variation, the first calculation circuit 35 may use a trained model to identify changes in proficiency. The trained model may be stored in, for example, the first storage device 34, but is not particularly limited thereto. That is, the trained model may be stored in external storage, such as a server, as long as it is accessible to the first calculation circuit 35. As shown in FIG. 6 , it can be understood that the larger the second index value (the greater the degree of replacement), the longer the required time at the beginning of the period and the longer the time it takes for the required time to reach the reference time Ts. This suggests that there is a correlation between the degree of replacement, the elapsed time since replacement, and proficiency. Therefore, when determining changes in proficiency, a trained model that has learned such a correlation may be used. Specifically, the trained model may include one or more trained parameters generated by machine learning (e.g., supervised learning) using a training dataset and an inference program incorporating the one or more trained parameters. The first index value may be used to indicate the degree of replacement. The time elapsed since replacement may be determined by the time elapsed from the start of the first period. Thus, the training dataset receives the first index value and the time elapsed since the start of the first period as input, and includes as output a proficiency indicator. The proficiency indicator may be selected from the proficiency itself, the required time, the proficiency ratio, or the proficiency loss ratio. The inference program may be a known program, such as a logistic regression model or a neural network model. As described above, the first calculation circuit 35 may have access to a trained model. The trained model may include one or more trained parameters generated by machine learning using the training dataset and an inference program incorporating the one or more trained parameters. The training dataset may receive the first index value and the time elapsed since the start of the first period as input, and include as output a proficiency indicator. The first calculation circuit 35 may use the trained model to identify changes in proficiency. That is, the first calculation circuit 35 may input the first index value and the time elapsed since the start of the first period into the trained model, obtain a proficiency indicator as an output from the trained model, and thereby identify changes in proficiency.
[0094] In one modified example, when acquiring the production performance data corresponding to the first index value, it is preferable to use production performance data for the production line 20 for which the production plan D1 is being formulated. However, there is not necessarily preferable production performance data for the production line 20 for which the production plan D1 is being formulated. For example, if there is no production performance data for the production line 20 for which the production plan D1 is being formulated, in which the difference between the first index value and the second index value is equal to or less than a threshold, production performance data for a production line 20 that is considered to be the same as the production line 20 for which the production plan D1 is being formulated may be used. The production line 20 that is considered to be the same as the production line 20 for which the production plan D1 is being formulated may be, for example, a production line 20 of the same model as the production line 20 for which the production plan D1 is being formulated, or a production line 20 that shows a similar change in required time.
[0095] In one modified example, the reference time does not necessarily have to be input by the user 5. The reference time may be determined in advance for the model of the production line 20. In this case, by identifying the model of the production line 20, the reference time is identified from a table showing the relationship between the model of the production line 20 and the reference time.
[0096] In one variation, the first period, the first index value, the reference time, and the work time do not have to be input at the same time. Once the first index value is input, a change in proficiency level can be identified. Therefore, the input of the first period, the reference time, and the work time may be accepted after a graph of the change in proficiency level (see FIGS. 7 and 8 ) is presented.
[0097] In one modified example, the change in the required time may be a change in the required time relative to the number of times the product is manufactured. In this case, the length of the mastery period from the replacement of the multiple execution entities 21 to the time required to reach the reference time Ts is measured in units of the number of times, so the change in the mastery level also corresponds to a change relative to the number of times the product is manufactured.
[0098] In one modified example, the manufacturing plan D1 is not necessarily limited to the above embodiment, and may include at least the planned number of products to be manufactured in the first period. For example, the manufacturing plan D1 may not include the number of products to be manufactured in each of multiple unit periods arranged in chronological order in the first period. Furthermore, the manufacturing plan D1 may not include the target number of products to be manufactured in the first period. Furthermore, the manufacturing plan D1 may not include the first period, the first index value, the reference time, and / or the operation time. Furthermore, the manufacturing plan D1 may not include product sales based on the planned number, product manufacturing costs based on the second operation time, or product sales based on the second planned number. On the other hand, the manufacturing plan D1 may include information on changes in proficiency identified by the first index value, and such changes in proficiency may be presented to the user 5.
[0099] In one modified example, the manufacturing planning system 3 may be realized by a computer system such as a plurality of servers. It is not necessary that the plurality of functions (components) of the manufacturing planning system 3 be integrated into a single housing, and the components of the manufacturing planning system 3 may be distributed across a plurality of housings. Furthermore, at least some of the functions of the manufacturing planning system 3, for example, some of the functions of the first arithmetic circuit 35, may be realized by the cloud (cloud computing) or the like.
[0100] In one modified example, the manufacturing planning system 3 and the information terminal 4 may be implemented as a single computer system. For example, multiple functions (components) of the manufacturing planning system 3 and the information terminal 4 may be integrated into a single housing.
[0101] [3. Aspects] As is clear from the above-described embodiment and modifications, the present disclosure includes the following aspects.
[0102] [Aspect 1] A manufacturing planning method executed by an arithmetic circuit to formulate a manufacturing plan for a product manufactured in a manufacturing process in which multiple execution entities perform work in sequence, the manufacturing planning method comprising: identifying a first index value indicating the degree of turnover among the multiple execution entities during a first period; identifying a change in proficiency of the multiple execution entities since the start of the first period based on the first index value; and outputting a manufacturing plan for the product for the first period based on the change in proficiency.
[0103] [Aspect 2] The manufacturing plan development method of Aspect 1, wherein the arithmetic circuit is capable of accessing a manufacturing performance database including a plurality of pieces of manufacturing performance data, each of the plurality of pieces of manufacturing performance data including required time data indicating a change in required time for the manufacturing process since a change in the plurality of execution entities and a second index value indicating a degree of change in the plurality of execution entities, and the change in proficiency level is identified based on the required time data of the manufacturing performance data including the second index value corresponding to the first index value among the plurality of pieces of manufacturing performance data.
[0104] [Aspect 3] The manufacturing planning method of Aspect 2, wherein the change in proficiency level is determined based on a length of a familiarization period from when the multiple execution agents are replaced to when the required time reaches a reference time in the required time data, and a representative value of the required time within the familiarization period in the required time data.
[0105] [Aspect 4] The manufacturing planning method of aspect 3, wherein the representative value is a maximum value.
[0106] [Aspect 5] The manufacturing plan development method according to any one of Aspects 2 to 4, wherein a second index value among the second index values of the plurality of manufacturing performance data, which has the smallest difference from the first index value, is determined to correspond to the first index value.
[0107] [Aspect 6] The manufacturing planning method of Aspect 1, wherein the arithmetic circuit has access to a trained model, the trained model comprising one or more trained parameters generated by machine learning using a training dataset and an inference program incorporating the one or more trained parameters, the training dataset including the first index value and the elapsed time from the start of the first period as inputs and an index of the proficiency as output, and the arithmetic circuit uses the trained model to identify changes in the proficiency.
[0108] [Aspect 7] The manufacturing planning method according to any one of Aspects 1 to 6, wherein the manufacturing plan includes a planned number of the products to be manufactured in the first period.
[0109] [Aspect 8] The manufacturing planning method of aspect 7, wherein the manufacturing plan includes a target number of the products to be manufactured in the first period.
[0110] [Aspect 9] The manufacturing planning method of aspect 7 or 8, wherein the planned quantity is determined based on the operation time used to manufacture the product in the first time period and the change in the proficiency level.
[0111] [Aspect 10] The manufacturing plan development method of Aspect 9, wherein the manufacturing plan includes a number of the products to be manufactured for each of a plurality of unit periods arranged in chronological order within the first period, and the number of the products to be manufactured for each of the plurality of unit periods is given by a sub-task time within the unit period out of the working time and a proficiency level for the unit period calculated from changes in the proficiency level.
[0112] [Aspect 11] The manufacturing planning method according to any one of Aspects 7 to 10, wherein the manufacturing plan includes sales of the product based on the planned quantity.
[0113] [Aspect 12] The manufacturing planning method of Aspect 9 or 10, wherein the operation time is a sum of a first operation time that is a fixed value and a second operation time that is a variable value, and the first operation time and the second operation time are specified separately.
[0114] Aspect 13: The manufacturing plan formulation method of Aspect 12, wherein the scheduled number includes a first scheduled number corresponding to the first operation time and a second scheduled number corresponding to the second operation time, and the manufacturing plan includes a manufacturing cost of the product based on the second operation time and sales of the product based on the second scheduled number.
[0115] [Aspect 14] A manufacturing planning system for formulating a manufacturing plan for a product manufactured in a manufacturing process in which multiple execution entities perform work in sequence, the manufacturing planning system comprising: a first calculation circuit; the first calculation circuit: identifies a first index value indicating a degree of replacement of the multiple execution entities during a first period; identifies a change in proficiency of the multiple execution entities since the start of the first period based on the first index value; and outputs a manufacturing plan for the product for the first period based on the change in proficiency.
[0116] [Aspect 15] A program for causing the arithmetic circuit to execute the manufacturing planning method according to any one of aspects 1 to 13.
[0117] [Aspect 16] An information terminal communicatively connected to the manufacturing planning system of Aspect 14, comprising an input device, an output device, a communication device, and a second arithmetic circuit that controls the input device, the output device, and the communication device, wherein the second arithmetic circuit: accepts input of the first index value via the input device; transmits the first index value to the manufacturing planning system via the communication device to receive the manufacturing plan from the manufacturing planning system; and presents the manufacturing plan via the output device.
[0118] [Aspect 17] An information processing device comprising: a storage device that accumulates attribute data of a group including a plurality of workers who perform a manufacturing process; a model that models changes in proficiency over a period of time for the group including the plurality of workers throughout the entire manufacturing process; an input device or communication device that acquires information on the degree of turnover of the plurality of workers; and one or more arithmetic circuits that accumulate the acquired information on the degree of turnover of the plurality of workers in the storage device, compare the model based on the acquired degree of turnover of the plurality of workers to simulate proficiency, and generate graph information or a GUI that shows a manufacturing plan based on the simulated proficiency.
[0119] Aspects 2 to 13 are optional elements and are not essential. Aspects 2 to 13 can be appropriately combined with Aspects 14, 16, and 17.
[0120] The present disclosure is applicable to a manufacturing planning method, a manufacturing planning system, a program, and an information terminal. Specifically, the present disclosure is applicable to a manufacturing planning method, a manufacturing planning system, a program, and an information terminal for formulating a manufacturing plan for a product that is manufactured by multiple execution entities performing tasks sequentially.
[0121] 21 Execution entity 3 Manufacturing plan formulation system 35 First arithmetic circuit (arithmetic circuit) 4 Information terminal 41 Second input device (input device) 42 Second output device (output device) 43 Second communication device (communication device) 45 Second arithmetic circuit D1 Manufacturing plan
Claims
1. A manufacturing planning method executed by an arithmetic circuit to formulate a manufacturing plan for a product manufactured in a manufacturing process in which multiple executing agents perform work in sequence, the manufacturing planning method comprising: identifying a first index value indicating the degree of replacement of the multiple executing agents during a first period; identifying a change in proficiency of the multiple executing agents from the start of the first period based on the first index value; and outputting a manufacturing plan for the product for the first period based on the change in proficiency.
2. The manufacturing plan development method of claim 1, wherein the arithmetic circuit is capable of accessing a manufacturing performance database including a plurality of manufacturing performance data, each of the plurality of manufacturing performance data including required time data indicating a change in required time for the manufacturing process since a change in the plurality of execution entities and a second index value indicating a degree of change in the plurality of execution entities, and the change in proficiency is identified based on the required time data of manufacturing performance data including the second index value corresponding to the first index value among the plurality of manufacturing performance data.
3. The manufacturing planning method of claim 2, wherein the change in proficiency level is determined based on the length of a familiarization interval in the required time data from the change in the multiple execution entities to the required time reaching a reference time, and a representative value of the required time within the familiarization interval in the required time data.
4. The manufacturing planning method according to claim 3, wherein the representative value is a maximum value.
5. The manufacturing plan creation method according to claim 2, wherein a second index value having a smallest difference from the first index value among the second index values of the plurality of manufacturing performance data is determined to correspond to the first index value.
6. The manufacturing planning method of claim 1, wherein the arithmetic circuit has access to a trained model, the trained model comprising one or more trained parameters generated by machine learning using a training dataset and an inference program into which the one or more trained parameters are incorporated, the training dataset including the first index value and the elapsed time from the start of the first period as input, and an index of the proficiency as output, and the arithmetic circuit uses the trained model to identify changes in the proficiency.
7. The manufacturing planning method of claim 1, wherein the manufacturing plan includes a planned number of the products to be manufactured in the first time period.
8. The manufacturing planning method according to claim 7, wherein the manufacturing plan includes a target number of the products to be manufactured in the first time period.
9. The manufacturing planning method according to claim 8, wherein the planned quantity is determined based on the operation time used to manufacture the product in the first time period and the change in the proficiency level.
10. The manufacturing plan development method of claim 9, wherein the manufacturing plan includes a production number of the product for each of a plurality of unit periods arranged in chronological order in the first period, and in each of the plurality of unit periods, the production number of the product is given by a sub-task time for the unit period out of the working time and a proficiency level for the unit period calculated from the change in proficiency level.
11. The manufacturing planning method according to claim 7, wherein the manufacturing plan includes sales of the product based on the planned number.
12. The manufacturing planning method according to claim 9, wherein the operation time is the sum of a first operation time which is a fixed value and a second operation time which is a variable value, and the first operation time and the second operation time are specified separately.
13. The manufacturing plan development method of claim 12, wherein the scheduled numbers include a first scheduled number corresponding to the first operating time and a second scheduled number corresponding to the second operating time, and the manufacturing plan includes a manufacturing cost of the product based on the second operating time and sales of the product based on the second scheduled number.
14. A manufacturing plan creation system for creating a manufacturing plan for a product manufactured in a manufacturing process in which multiple execution entities perform work in sequence, the manufacturing plan creation system comprising: a first calculation circuit, the first calculation circuit identifying a first index value indicating a degree of replacement of the multiple execution entities during a first period, identifying a change in proficiency of the multiple execution entities from the start of the first period based on the first index value, and outputting a manufacturing plan for the product for the first period based on the change in proficiency.
15. A program for causing the arithmetic circuit to execute the manufacturing planning method according to any one of claims 1 to 13.
16. An information terminal communicatively connected to the manufacturing planning system of claim 14, comprising an input device, an output device, a communication device, and a second arithmetic circuit that controls the input device, the output device, and the communication device, wherein the second arithmetic circuit: accepts input of the first index value via the input device; transmits the first index value to the manufacturing planning system via the communication device, and receives the manufacturing plan from the manufacturing planning system; and presents the manufacturing plan via the output device.
Citation Information
Patent Citations
Method for estimating cycle times for each work process in an assembly manufacturing line, overall process organization method, apparatus, and program
JP4655494B2
Work procedure updating device, work procedure updating method, and program
WO2022091571A1