Communication method and apparatus, communication device, and communication system

By sending power level information between terminals and network equipment and using the PHR mechanism, the problem of terminal transmission power adjustment affecting network scheduling is solved, achieving better network scheduling and resource saving.

WO2025015537A1PCT designated stage expired Publication Date: 2025-01-23BEIJING XIAOMI MOBILE SOFTWARE CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2023/108009
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-07-18
Publication Date
2025-01-23

AI Technical Summary

Technical Problem

The adjustment of the transmission power by the terminal during uplink transmission affects the uplink scheduling of the network equipment, making it difficult for the network equipment to achieve better scheduling and suitable for service transmission needs.

Method used

By sending power level information, the power margin report (PHR) mechanism is used to enable network devices to determine the power level of the terminal, thereby optimizing the scheduling of the upper link.

Benefits of technology

It achieves better scheduling decisions for network equipment, improves system throughput and user coverage, reduces invalid scheduling of network equipment, and saves terminal power consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023108009_23012025_PF_FP_ABST
    Figure CN2023108009_23012025_PF_FP_ABST
Patent Text Reader

Abstract

The present disclosure relates to a communication method and apparatus, a communication device, and a communication system. The communication method comprises: sending first information, the first information being used to represent a power level, and the first information being sent by means of a power headroom report (PHR). The present disclosure helps to implement better scheduling of a network, and is more suitable for service sending requirement scheduling.
Need to check novelty before this filing date? Find Prior Art

Description

Communication method and device, communication equipment, and communication system Technical Field

[0001] The present disclosure relates to the field of communication technologies, and in particular to communication methods and devices, communication equipment, and communication systems. Background Art

[0002] Terminals participating in uplink transmissions must comply with regulatory constraints. For example, they are required to maintain radio frequency (RF) exposure limits during uplink transmissions. Consequently, terminals often need to adjust their transmit power during uplink transmissions.

[0003] Summary of the Invention

[0004] Adjustment of the transmit power by the terminal during uplink transmission affects uplink scheduling by the network device.

[0005] The embodiments of the present disclosure provide a communication method and apparatus, a communication device, and a communication system.

[0006] According to a first aspect of an embodiment of the present disclosure, a communication method is provided, the method comprising: sending first information, where the first information is used to indicate a power level, and the first information is sent via a power headroom report (PHR).

[0007] According to a second aspect of an embodiment of the present disclosure, a communication method is provided, the method comprising: receiving first information, the first information being used for a power level, the first information being sent via a power headroom report (PHR).

[0008] According to a third aspect of an embodiment of the present disclosure, a communication method is provided, the method comprising: a terminal sending first information to a network device, the first information being used for a power level, the first information being sent via a power headroom report PHR.

[0009] According to a fourth aspect of an embodiment of the present disclosure, a terminal is provided, comprising: a transceiver module; the transceiver module is used to send first information, the first information is used for power level, and the first information is sent via a power headroom report PHR.

[0010] According to a fifth aspect of an embodiment of the present disclosure, a network device is provided, comprising: a transceiver module; the transceiver module is used to receive first information, the first information is used for power level, and the first information is sent via a power headroom report PHR.

[0011] According to a sixth aspect of an embodiment of the present disclosure, a terminal is provided, comprising: one or more processors; the processors are configured to call instructions so that the terminal executes the communication method described in the first aspect.

[0012] According to a seventh aspect of an embodiment of the present disclosure, a network device is provided, comprising: one or more processors; the processors are configured to call instructions so that the network device executes the communication method described in the second aspect.

[0013] According to an eighth aspect of an embodiment of the present disclosure, a communication system is provided, comprising a terminal and a network device, wherein the terminal is configured to implement the communication method described in any one of the first aspects, and the network device is configured to implement the communication method described in the second aspect.

[0014] According to a ninth aspect of an embodiment of the present disclosure, a storage medium is provided, wherein the storage medium stores instructions, and wherein when the instructions are executed on a communication device, the communication device executes the communication method described in any one of the first and second aspects.

[0015] The solution provided by the embodiments of the present disclosure is conducive to achieving better scheduling of the network and is more suitable for scheduling of business transmission needs. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the following drawings required for describing the embodiments are introduced. The following drawings are merely some embodiments of the present disclosure and do not impose specific limitations on the protection scope of the present disclosure.

[0017] FIG1a is a schematic diagram showing the architecture of a communication system according to an embodiment of the present disclosure.

[0018] FIG1b is a schematic diagram showing a terminal cumulative transmission power control according to an embodiment of the present disclosure.

[0019] FIG1c is a schematic diagram showing a terminal cumulative transmission power control according to an embodiment of the present disclosure.

[0020] FIG1d is a schematic diagram showing a terminal cumulative transmission power control according to an embodiment of the present disclosure.

[0021] FIG1e is a schematic diagram showing a PHR configuration format of a single carrier according to an embodiment of the present disclosure.

[0022] FIG1f is a schematic diagram of a multi-carrier PHR configuration format according to an embodiment of the present disclosure.

[0023] FIG2 is a schematic diagram showing interaction of a communication method according to an embodiment of the present disclosure.

[0024] FIG3 a is a flow chart showing a communication method according to an embodiment of the present disclosure.

[0025] FIG3 b is a flow chart showing a communication method according to an embodiment of the present disclosure.

[0026] FIG4 a is a flow chart of a communication method according to an embodiment of the present disclosure.

[0027] FIG4 b is a flow chart of a communication method according to an embodiment of the present disclosure.

[0028] FIG5 is a flow chart showing a communication method according to an embodiment of the present disclosure.

[0029] FIG6 a is a schematic diagram of a terminal according to an embodiment of the present disclosure.

[0030] FIG6 b is a schematic diagram of a network device according to an embodiment of the present disclosure.

[0031] Fig. 7a is a schematic diagram showing a communication device according to an exemplary embodiment.

[0032] FIG7 b is a schematic diagram showing a chip structure according to an exemplary embodiment. DETAILED DESCRIPTION

[0033] The embodiments of the present disclosure provide a communication method and apparatus, a communication device, and a communication system.

[0034] In a first aspect, an embodiment of the present disclosure proposes a communication method, which includes: sending first information, where the first information is used to indicate a power level, and the first information is sent via a power headroom report (PHR).

[0035] In the above embodiment, the terminal sends the first information so that the network determines the power level of the terminal, so that the network can achieve better scheduling and be more suitable for scheduling of service transmission requirements.

[0036] In combination with some embodiments of the first aspect, in some embodiments, the sending of the first information includes: sending the first information when at least one of the following conditions is met; the power level falls back to the first power level, the first power level is lower than the second power level, the second power level is the power level defined by the terminal and / or initially reported by the terminal; the power level is restored.

[0037] In the above embodiment, the transmission power level is provided under various conditions to ensure that the network equipment can better perform communication scheduling under different conditions.

[0038] In combination with some embodiments of the first aspect, in some embodiments, the power level fallback is determined in the following manner: the uplink transmission duty cycle corresponding to the physical uplink shared channel PUSCH sent by the terminal is greater than the first threshold corresponding to the current power level, and the power level fallback is determined, wherein different power levels correspond to different first thresholds.

[0039] In the above embodiment, the terminal can determine whether the power level is backed off according to different situations, so that the terminal can trigger the sending of the first information based on the power level backed off, thereby ensuring better network scheduling in most cases.

[0040] In combination with some embodiments of the first aspect, in some embodiments, the power level recovery is determined by at least one of the following methods: the terminal starts the next evaluation cycle to determine the power level recovery; the uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is less than or equal to the second threshold, and the power level recovery is determined.

[0041] In the above embodiment, the terminal can determine the power level recovery according to different situations, so that the terminal can trigger the sending of the first information based on the power level fallback, thereby ensuring better network scheduling in most cases.

[0042] In combination with some embodiments of the first aspect, in some embodiments, the terminal starts a next evaluation cycle, and determining the power level recovery includes: the power level recovery is the power level defined by the terminal and / or initially reported by the terminal.

[0043] In the above embodiment, the terminal starts the next evaluation cycle, and the power level is restored to the power level defined by the terminal and / or initially reported by the terminal, so that uplink transmission can be performed based on the power level defined by the terminal and / or initially reported by the terminal in the new evaluation cycle, thereby improving communication efficiency.

[0044] In combination with some embodiments of the first aspect, in some embodiments, the first information includes at least one of the following: a first power level after the power level falls back; a third power level after the power level is restored; a power level change of the terminal; an evaluation period of the terminal; a first duration corresponding to at least one of the first power level and the third power level, the first duration being used to represent an estimated duration of at least one of the first power level and the third power level.

[0045] In the above embodiment, the first information sent by the terminal may include at least one of the multiple first information, and the number and content of the reported amounts may be flexibly adjusted, thereby achieving better network scheduling while saving resources as much as possible.

[0046] In combination with some embodiments of the first aspect, in some embodiments, the evaluation period includes a first starting time, which is the starting time of the evaluation period; the first starting time includes at least one of the following: the time corresponding to the system frame number SFN being 0; the time corresponding to the SFN being 0 and after the offset offset.

[0047] In the above embodiment, the terminal can determine the start time of the evaluation period in different ways, and different determination methods can ensure that the terminal can flexibly report the start time of the evaluation period, thereby achieving more accurate or efficient reporting of the start time of the evaluation period.

[0048] In combination with some embodiments of the first aspect, in some embodiments, the evaluation cycle includes a first duration, which is the duration of the evaluation cycle; the first duration is expressed in at least one of the following ways: expressing the first duration based on the number of a first granularity, wherein the first granularity corresponds to a second duration; expressing the first duration based on a first value, wherein the first value corresponds to a first duration interval, the first duration interval is a duration range of a pre-set evaluation cycle, the first duration is within the duration range, and the first duration is expressed by the duration range; expressing the first duration based on a second value, wherein the second value corresponds to a pre-set evaluation cycle duration.

[0049] In the above embodiment, the duration of the evaluation period reported by the terminal can be determined in different ways, and different determination methods can ensure that the terminal can flexibly report the duration of the evaluation period, so as to achieve more accurate or efficient reporting of the duration of the evaluation period.

[0050] In combination with some embodiments of the first aspect, in some embodiments, the first duration includes a second starting moment; the second starting moment includes at least one of the following: the sending moment of the PHR; the first starting moment corresponding to the evaluation period; the moment determined based on the number of first reference points and second granularities, wherein the first reference point is the moment corresponding to SFN equal to 0, and the second granularity corresponds to the third duration; the moment determined based on the second reference point, wherein the second reference point is a reference point adjacent to the moment of sending the PHR among the reference points obtained by dividing the evaluation period based on the third granularity, and the third granularity corresponds to the fourth duration; the sending moment of the PUSCH.

[0051] In the above embodiment, the terminal may determine the starting time of the first duration reported by the terminal in different ways, and different determination ways may ensure that the terminal can flexibly report the starting time of the first duration, thereby achieving more accurate or efficient reporting of the starting time of the first duration.

[0052] In combination with some embodiments of the first aspect, in some embodiments, the second starting moment includes a moment determined based on the first reference point and the number of second granularities; the method also includes: sending second information, wherein the second information is used to indicate the number of second granularities.

[0053] In the above embodiment, the terminal may report the number of the second granularity so that the network can achieve better scheduling and improve communication efficiency according to the determination method of the second starting time.

[0054] In combination with some embodiments of the first aspect, in some embodiments, the first duration includes a fifth duration; the fifth duration is expressed in at least one of the following ways: expressing the fifth duration based on the quantity of the third granularity, wherein the third granularity corresponds to the sixth duration; expressing the fifth duration based on a third value, wherein the third value corresponds to a second duration interval, the second duration interval is a duration range of a pre-set power level, the fifth duration is within the duration range, and the fifth duration is expressed by the duration range; expressing the fifth duration based on a fourth value, wherein the fourth value corresponds to a pre-set power level duration.

[0055] In the above embodiment, the duration of the first duration reported by the terminal can be determined in different ways, and different determination ways can ensure that the terminal can flexibly report the duration of the first duration, so as to achieve more accurate or more efficient reporting of the duration of the first duration.

[0056] In combination with some embodiments of the first aspect, in some embodiments, the first information includes the maximum output power of the terminal, and the maximum output power is determined based on the first output power, the power change and the maximum power attenuation MPR, wherein the first output power is determined based on the second power level, the power change and the MPR are determined based on the second power level, or the power change and the MPR are determined based on the third power level.

[0057] In the above embodiments, the terminal determines the maximum output power in different ways, thereby adapting to different situations and improving communication efficiency.

[0058] In a second aspect, an embodiment of the present disclosure proposes a communication method, which includes: receiving first information, where the first information is used for a power level, and the first information is sent via a power headroom report PHR.

[0059] In combination with some embodiments of the second aspect, in some embodiments, the first information is generated under at least one of the following conditions: the power level falls back to the first power level, the first power level is lower than the second power level, and the second power level is the power level defined by the terminal and / or initially reported by the terminal; the power level is restored.

[0060] In combination with some embodiments of the second aspect, in some embodiments, the power level fallback is determined in the following manner: the uplink transmission duty cycle corresponding to the physical uplink shared channel PUSCH sent by the terminal is greater than the first threshold corresponding to the current power level, and the power level fallback is determined, wherein different power levels correspond to different first thresholds.

[0061] In combination with some embodiments of the second aspect, in some embodiments, the power level recovery is determined by at least one of the following methods: the terminal starts the next evaluation cycle to determine the power level recovery; the uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is less than or equal to the second threshold, and the power level recovery is determined.

[0062] In combination with some embodiments of the second aspect, in some embodiments, the terminal starts a next evaluation cycle, and determining the power level recovery includes: the power level recovery is the power level defined by the terminal and / or initially reported by the terminal.

[0063] In combination with some embodiments of the second aspect, in some embodiments, the first information includes at least one of the following reported quantities: the first power level after the power level falls back; the third power level after the power level is restored; the power level change of the terminal; the evaluation period of the terminal; the first duration corresponding to at least one of the first power level and the third power level, the first duration being used to represent the estimated duration of at least one of the first power level and the third power level.

[0064] In combination with some embodiments of the second aspect, in some embodiments, the evaluation period includes a first starting time, which is the starting time of the evaluation period; the first starting time includes at least one of the following: the time corresponding to the system frame number SFN being 0; the time corresponding to the SFN being 0 and after the offset offset.

[0065] In combination with some embodiments of the second aspect, in some embodiments, the evaluation cycle includes a first duration, which is the duration of the evaluation cycle; the first duration is expressed in at least one of the following ways: expressing the first duration based on the number of a first granularity, wherein the first granularity corresponds to a second duration, and the second duration is less than or equal to the first duration; expressing the first duration based on a first value, wherein the first value corresponds to a first duration interval, and the first duration interval is a duration range of a pre-set evaluation cycle, and the first duration is within the duration range, and the first duration is expressed by the duration range; expressing the first duration based on a second value, wherein the second value corresponds to a pre-set evaluation cycle duration.

[0066] In combination with some embodiments of the second aspect, in some embodiments, the first duration includes a second starting moment; the second starting moment includes at least one of the following: the sending moment of the PHR; the first starting moment corresponding to the evaluation period; the moment determined based on the number of first reference points and second granularities, wherein the first reference point is the moment corresponding to SFN equal to 0, and the second granularity corresponds to the third duration; the moment determined based on the second reference point, wherein the second reference point is a reference point adjacent to the moment of sending the PHR among the reference points obtained by dividing the evaluation period based on the third granularity, and the third granularity corresponds to the fourth duration; the sending moment of the PUSCH.

[0067] In combination with some embodiments of the second aspect, in some embodiments, the second starting moment includes a moment determined based on the first reference point and the number of second granularities; the method also includes: receiving second information, the second information being used to indicate the number of second granularities.

[0068] In combination with some embodiments of the second aspect, in some embodiments, the first duration includes a fifth duration; the fifth duration is expressed in at least one of the following ways: expressing the fifth duration based on the number of the third granularity, wherein the third granularity corresponds to the sixth duration, and the sixth duration is less than or equal to the fifth duration; expressing the fifth duration based on the third value, wherein different third values ​​correspond to different second duration intervals, and the second duration interval is the interval in which the power level corresponds to the pre-set duration; expressing the fifth duration based on the fourth value, wherein different fourth values ​​correspond to different durations corresponding to the pre-set power level.

[0069] In combination with some embodiments of the second aspect, in some embodiments, the first information includes the maximum output power of the terminal, and the maximum output power is determined based on the first output power, the power change and the maximum power attenuation MPR, wherein the first output power is determined based on the second power level, the power change and the MPR are determined based on the second power level, or the power change and the MPR are determined based on the third power level.

[0070] In a third aspect, an embodiment of the present disclosure proposes a communication method, which includes: a terminal sending first information to a network device, where the first information is used for a power level, and the first information is sent via a power headroom report PHR.

[0071] In a fourth aspect, an embodiment of the present disclosure proposes a terminal, which includes a transceiver module; wherein the terminal is used to execute the first aspect and the optional implementation method of the first aspect.

[0072] In a fifth aspect, an embodiment of the present disclosure proposes a network device, including a transceiver module; wherein the above-mentioned network device is used to execute the second aspect and the optional implementation method of the second aspect.

[0073] In a sixth aspect, an embodiment of the present disclosure proposes a terminal, comprising: one or more processors; wherein the above-mentioned terminal is used to execute the first aspect and the optional implementation method of the first aspect.

[0074] In a seventh aspect, an embodiment of the present disclosure proposes a network device, comprising: one or more processors; wherein the above-mentioned network device is used to execute the second aspect and the optional implementation method of the second aspect.

[0075] In the eighth aspect, an embodiment of the present disclosure proposes a communication system, which includes: a terminal and a network device; wherein the terminal is configured to execute the method described in the first and third aspects, and the optional implementation methods of the first and third aspects, and the network device is configured to execute the method described in the second and third aspects, and the optional implementation methods of the second and third aspects.

[0076] In the ninth aspect, an embodiment of the present disclosure proposes a storage medium, which stores instructions. When the instructions are executed on a communication device, the communication device executes the method described in the optional implementation of the first and third aspects, and the second and third aspects.

[0077] In a tenth aspect, an embodiment of the present disclosure proposes a program product. When the program product is executed by a communication device, the communication device executes the method described in the optional implementation of the first and third aspects, and the second and third aspects.

[0078] In an eleventh aspect, an embodiment of the present disclosure proposes a computer program, which, when executed on a computer, enables the computer to execute the method as described in the first and third aspects, and the optional implementation of the second and third aspects.

[0079] It is understandable that the above-mentioned terminals, network devices, communication devices, communication systems, storage media, program products, and computer programs are all used to execute the methods proposed in the embodiments of the present disclosure. Therefore, the beneficial effects that can be achieved can refer to the beneficial effects of the corresponding methods and will not be repeated here.

[0080] In some embodiments, the terms communication method and information processing method are interchangeable, the terms communication device and information processing device are interchangeable, and the terms information processing system and communication system are interchangeable.

[0081] The embodiments of the present disclosure are not exhaustive and are merely illustrative of some embodiments, and are not intended to be a specific limitation on the scope of protection of the present disclosure. In the absence of contradiction, each step in a certain embodiment can be implemented as an independent embodiment, and the steps can be arbitrarily combined. For example, a solution after removing some steps in a certain embodiment can also be implemented as an independent embodiment, and the order of the steps in a certain embodiment can be arbitrarily exchanged. In addition, the optional implementation methods in a certain embodiment can be arbitrarily combined; in addition, the embodiments can be arbitrarily combined. For example, some or all steps of different embodiments can be arbitrarily combined, and a certain embodiment can be arbitrarily combined with the optional implementation methods of other embodiments.

[0082] In each embodiment of the present disclosure, unless otherwise specified or provided for by logic, the terms and / or descriptions between the embodiments are consistent and can be referenced by each other. The technical features in different embodiments can be combined to form a new embodiment based on their inherent logical relationships.

[0083] The terms used in the embodiments of the present disclosure are only for the purpose of describing specific embodiments and are not intended to limit the present disclosure.

[0084] In the embodiments of the present disclosure, unless otherwise specified, elements expressed in the singular, such as "a", "an", "the", "above", "said", "the", "the", etc., may mean "one and only one", or "one or more", "at least one", etc. For example, when using articles such as "a", "an", "the" in English in translation, the noun following the article may be understood as a singular expression or a plural expression.

[0085] In the embodiments of the present disclosure, “plurality” refers to two or more.

[0086] In some embodiments, the terms "at least one," "one or more," "a plurality of," "multiple," etc. may be used interchangeably.

[0087] In some embodiments, descriptions such as "at least one of A and B," "A and / or B," "A in one case, B in another case," or "in response to one case A, in response to another case B" may include the following technical solutions depending on the situation: in some embodiments, A (A is executed independently of B); in some embodiments, B (B is executed independently of A); in some embodiments, execution is selected from A and B (A and B are selectively executed); and in some embodiments, A and B (both A and B are executed). The above is also applicable when there are more branches such as A, B, and C.

[0088] In some embodiments, "A or B" and other descriptions may include the following technical solutions depending on the situation: in some embodiments, A (A is executed independently of B); in some embodiments, B (B is executed independently of A); in some embodiments, execution is selected from A and B (A and B are selectively executed). The above is also applicable when there are more branches such as A, B, C, etc.

[0089] The prefixes such as "first" and "second" in the embodiments of the present disclosure are only used to distinguish different description objects and do not constitute any restriction on the position, order, priority, quantity or content of the description objects. For the statement of the description object, please refer to the description in the context of the claims or embodiments, and no unnecessary restriction should be constituted due to the use of prefixes. For example, if the description object is a "field", the ordinal number before the "field" in the "first field" and the "second field" does not limit the position or order between the "fields". "First" and "second" do not limit whether the "fields" they modify are in the same message, nor do they limit the order of the "first field" and the "second field". For another example, if the description object is a "level", the ordinal number before the "level" in the "first level" and the "second level" does not limit the priority between the "levels". For another example, the number of description objects is not limited by the ordinal number and can be one or more. Taking "first device" as an example, the number of "devices" can be one or more. In addition, the objects modified by different prefixes can be the same or different. For example, if the description object is "device", then the "first device" and the "second device" can be the same device or different devices, and their types can be the same or different; for another example, if the description object is "information", then the "first information" and the "second information" can be the same information or different information, and their contents can be the same or different.

[0090] In some embodiments, “including A,” “comprising A,” “used to indicate A,” and “carrying A” can be interpreted as directly carrying A or indirectly indicating A.

[0091] In some embodiments, terms such as "in response to...", "in response to determining...", "in the case of...", "at the time of...", "when...", "if...", "if...", etc. can be used interchangeably.

[0092] In some embodiments, terms such as "greater than", "greater than or equal to", "not less than", "more than", "more than or equal to", "not less than", "higher than", "higher than or equal to", "not less than", and "above" can be replaced with each other, and terms such as "less than", "less than or equal to", "not greater than", "less than", "less than or equal to", "not more than", "lower than", "lower than or equal to", "not higher than", and "below" can be replaced with each other.

[0093] In some embodiments, devices, etc. can be interpreted as physical or virtual, and their names are not limited to the names recorded in the embodiments. Terms such as "device", "equipment", "device", "circuit", "network element", "node", "function", "unit", "section", "system", "network", "chip", "chip system", "entity", and "subject" can be used interchangeably.

[0094] In some embodiments, "network" can be interpreted as devices included in the network (eg, access network equipment, core network equipment, etc.).

[0095] In some embodiments, the terms "access network device (AN device)", "radio access network device (RAN device)", "base station (BS)", "radio base station" "fixed station", "node", "access point", "transmission point (TP)", "reception point (RP)", "transmission / reception point (TRP)", "panel", "antenna panel", "antenna array", "cell", "macro cell", "small cell", "femto cell", "pico cell", "sector", "cell group", "serving cell", "carrier", "component carrier", "bandwidth part (BWP)" and the like may be used interchangeably.

[0096] In some embodiments, the terms "terminal", "terminal device", "user equipment (UE)", "user terminal", "mobile station (MS)", "mobile terminal (MT)", subscriber station, mobile unit, subscriber unit, wireless unit, remote unit, mobile device, wireless device, wireless communication device, remote device, mobile subscriber station, access terminal, mobile terminal, wireless terminal, remote terminal, handset, user agent, mobile client, client, etc. can be used interchangeably.

[0097] In some embodiments, the access network device, the core network device, or the network device can be replaced by a terminal. For example, the various embodiments of the present disclosure can also be applied to a structure in which the communication between the access network device, the core network device, or the network device and the terminal is replaced by communication between multiple terminals (for example, device-to-device (D2D), vehicle-to-everything (V2X), etc.). In this case, it is also possible to set the structure in which the terminal has all or part of the functions of the access network device. In addition, terms such as "uplink" and "downlink" can also be replaced by terms corresponding to communication between terminals (for example, "side"). For example, uplink channels, downlink channels, etc. can be replaced by side channels, and uplinks, downlinks, etc. can be replaced by side links.

[0098] In some embodiments, the terminal may be replaced by an access network device, a core network device, or a network device. In this case, the access network device, the core network device, or the network device may have a structure that has all or part of the functions of the terminal.

[0099] In some embodiments, obtaining data, information, etc. may comply with the laws and regulations of the country where the data is obtained.

[0100] In some embodiments, data, information, etc. may be obtained with the user's consent.

[0101] In addition, each element, each row, or each column in the table of the embodiment of the present disclosure can be implemented as an independent embodiment, and the combination of any elements, any rows, and any columns can also be implemented as an independent embodiment.

[0102] FIG1a is a schematic diagram showing the architecture of a communication system according to an embodiment of the present disclosure.

[0103] As shown in FIG. 1 a , a communication system 100 includes a terminal 101 and a network device 102 .

[0104] In some embodiments, the terminal 101 includes, for example, a mobile phone, a wearable device, an Internet of Things device, a car with communication function, a smart car, a tablet computer, a computer with wireless transceiver function, a virtual reality (VR) terminal device, an augmented reality (AR) terminal device, a wireless terminal device in industrial control, a wireless terminal device in self-driving, a wireless terminal device in remote medical surgery, a wireless terminal device in a smart grid, a wireless terminal device in transportation safety, a wireless terminal device in a smart city, and at least one of a wireless terminal device in a smart home, but is not limited thereto.

[0105] In some embodiments, the network device 102 may include at least one of an access network device and a core network device.

[0106] In some embodiments, the terminal 101 includes, for example, a mobile phone, a wearable device, an Internet of Things device, a car with communication function, a smart car, a tablet computer, a computer with wireless transceiver function, a virtual reality (VR) terminal 101 device, an augmented reality (AR) terminal 101 device, a wireless terminal 101 device in industrial control, a wireless terminal 101 device in self-driving, a wireless terminal 101 device in remote medical surgery, a wireless terminal 101 device in a smart grid, a wireless terminal 101 device in transportation safety, a wireless terminal 101 device in a smart city, and at least one of a wireless terminal 101 device in a smart home, but is not limited thereto.

[0107] In some embodiments, the access network device is, for example, a node or device that accesses the terminal 101 to the wireless network. The access network device may include an evolved NodeB (eNB), a next generation evolved NodeB (ng-eNB), a next generation NodeB (gNB), a node B (NB), a home node B (HNB), a home evolved nodeB (HeNB), a wireless backhaul device, a radio network controller (RNC), a base station controller (BSC), a base transceiver station (BTS), a base band unit (BBU), a mobile switching center, a base station in a 6G communication system, an open base station (Open RAN), a cloud base station (Cloud RAN), a base station in other communication systems, and at least one of an access node in a wireless fidelity (WiFi) system, but is not limited thereto.

[0108] In some embodiments, the technical solution of the present disclosure can be applied to the Open RAN architecture. In this case, the interfaces between or within the access network devices involved in the embodiments of the present disclosure can be transformed into internal interfaces of the Open RAN, and the processes and information interactions between these internal interfaces can be implemented through software or programs.

[0109] In some embodiments, the access network device can be composed of a centralized unit (CU) and a distributed unit (DU), where the CU can also be called a control unit. The CU-DU structure can be used to split the protocol layer of the access network device, with the functions of some protocol layers centrally controlled by the CU, and the functions of the remaining part or all of the protocol layers distributed in the DU, which is centrally controlled by the CU, but is not limited to this.

[0110] In some embodiments, the core network device may be a device including one or more network elements, or may be multiple devices or a group of devices including one or more network elements, or may be physical. The core network may include, for example, at least one of an evolved packet core (EPC), a 5G core network (5GCN), and a next generation core (NGC).

[0111] It can be understood that the communication system described in the embodiment of the present disclosure is for the purpose of more clearly illustrating the technical solution of the embodiment of the present disclosure, and does not constitute a limitation on the technical solution proposed in the embodiment of the present disclosure. Ordinary technicians in this field can know that with the evolution of the system architecture and the emergence of new business scenarios, the technical solution proposed in the embodiment of the present disclosure is also applicable to similar technical problems.

[0112] The following embodiments of the present disclosure may be applied to the communication system 100 shown in FIG1a, or a portion thereof, but are not limited thereto. The entities shown in FIG1a are illustrative only. The communication system may include all or part of the entities shown in FIG1a, or may include other entities other than those shown in FIG1a. The number and form of the entities may be arbitrary, and the entities may be physical or virtual. The connection relationship between the entities is illustrative only. The entities may be connected or disconnected, and the connection may be in any manner, including direct or indirect, wired or wireless.

[0113] The embodiments of the present disclosure can be applied to Long Term Evolution (LTE), LTE-Advanced (LTE-A), LTE-Beyond (LTE-B), SUPER 3G, IMT-Advanced, 4th generation mobile communication system (4G), 5th generation mobile communication system (5G), 5G new radio (NR), future radio access (FRA), new radio access technology (RAT), new radio (NR), new radio access (NX), future generation radio access (FX), Global System for Mobile communications (GSM (registered trademark)), CDMA2000, Ultra Mobile Broadband (UMB), IEEE 802.11 (Wi-Fi (registered trademark)), IEEE 802.16 (WiMAX (registered trademark)), IEEE 802.20, Ultra-WideBand (UWB), Bluetooth (registered trademark), Public Land Mobile Network (PLMN) networks, Device-to-Device (D2D) systems, Machine-to-Machine (M2M) systems, Internet of Things (IoT) systems, Vehicle-to-Everything (V2X), systems utilizing other communication methods, and next-generation systems based on and extending these methods. Furthermore, multiple systems may be combined (for example, a combination of LTE or LTE-A with 5G).

[0114] In some embodiments, the terminal can be enhanced to achieve higher transmit power under carrier aggregation (CA) / dual connectivity (DC). For terminals equipped with dual power amplifiers (PAs), CA / DC can be supported. For example, for a terminal with a power class (PC2) defined as PC2, the terminal's PA capabilities can vary across different frequency bands. For example, Table 1 shows the terminal power configuration.

[0115] Table 1

[0116] As shown in Table 1, carrier X and carrier Y are used to represent different bands. Table 1 shows that if the terminal's power level on one frequency band is limited to 23 decibel milliwatts (dBm), and the power level on another frequency band is also limited to 23dBm, the terminal's power level is limited to a maximum of 26dBm. For example, in combinations b and c, if the terminal's power level on one frequency band is limited to 23dBm and the power level on another frequency band is limited to 26dBm, the terminal's power level is limited to a maximum of 26dBm due to relevant protocol regulations. Combination d, similarly, is limited to a maximum of 26dBm due to relevant protocol regulations. In other words, the terminal's maximum transmit power is limited to the terminal power level specified in the protocol. In the Release 17 work item (WI) on increasing the terminal power cap for CA / DC, for a band combination where one band supports power levels up to PC3 (23dBm) and the other band supports power levels up to PC2 (26dBm), it can be assumed that the total power associated with the band combination is the sum of the power levels.

[0117] In some embodiments, the power level of the terminal is specified, so in some cases, a new capability signaling is introduced for each frequency band combination. That is, a new maximum output power (MOP) capability signaling is introduced to support this relaxed signaling, for example, the signaling can be HigherPowerLimitCADC. This signaling can be applicable to terminals in a CA scenario, where the power level sent in one frequency band supports PC3 and the power level sent in another frequency band supports PC2. The frequency band can, for example, be a frequency band using time division duplexing (TDD) or frequency division duplexing (FDD). The terminal can use the new MOP capability and use the full power from the two PAs corresponding to a maximum composite power of 27.8dBm. However, the terminal relative to R16 will be limited to PC2 in the CA / DC configuration.

[0118] In some embodiments, the key to enabling simultaneous transmission across multiple frequency bands is that terminals must comply with regulatory constraints when participating in uplink transmissions. Regulatory constraints on the total RF exposure experienced by users require terminals to determine a safe transmit power level for each frequency band, i.e., the RF exposure level. When a terminal approaches or exceeds the permitted RF exposure level, the terminal needs to recalculate the safe transmit power for each frequency band in use, and uplink transmissions will also result in a change in transmit power. Of course, in some cases, the terminal can set its transmit power to have a fixed limit so that the terminal never exceeds the RF exposure level limit.

[0119] However, because changes in terminal transmit power are transparent to network devices, meaning they are unaware of the reasons for these changes, these changes can affect their perception of link quality and link adaptation, which can subsequently lead to fluctuations in uplink throughput. Clearly, enabling network devices to better understand these constraints and their impact on terminal behavior can help them make more nuanced and accurate scheduling decisions.

[0120] In some embodiments, two types of RF exposure level limit indicators can be used, depending on the combination of frequency bands. For example, one type can use the specific absorption rate (SAR) as a metric, which is mainly applicable to frequency bands below 6 GHz, such as frequency range (FR)1. The other type can use the power density (PD) measurement and the calculation of the maximum permissible exposure (MPE) as a metric. This type of standard is mainly used in millimeter wave bands, such as FR2. Both of these indicators use a time-averaged method to limit RF exposure. That is, the average RF exposure measured using these indicators and within a specific event window must remain below a specific threshold. However, it is understandable that the protocol specifies average RF exposure, not instantaneous RF exposure. Of course, there may be some exceptions in specific areas. The time-averaged nature of the above constraints is particularly important when implementing high-power transmission at the terminal. This means that while the terminal cannot always transmit at full power on all frequency bands, it can transmit at a higher transmit power for a short period of time.

[0121] During uplink transmission, a terminal determines the maximum uplink duty cycle (UL duty cycle) it can support, also known as the maximum UL duty cycle, during the initial access phase based on SAR / MPE requirements within the uplink evaluation period. It then reports maxUplinkDutyCycle to the network device. After establishing a communication connection with the network device, the network device configures the terminal based on the reported maximum uplink duty cycle. This value, referred to as maxULdutycycle or maxUplinkDutyCycle, is used in subsequent transmissions. During the uplink evaluation period, the terminal controls actual uplink transmissions based on the symbol percentage corresponding to the maximum uplink duty cycle configured by the network device. However, these adjustments are transparent to the network device. Furthermore, because some countries / regions may specify mandatory SAR / MPE radiation exposure requirements for terminals in different frequency bands, terminals must meet the UL duty cycle requirements through actual transmission during the uplink evaluation period to comply with SAR / MPE requirements.

[0122] For example, Figure 1b shows a schematic diagram of terminal cumulative transmit power control. The gray area indicates that the terminal's total transmit power must meet the transmit power limit within a UL duty cycle. It can be understood that this transmit power limit is a power limit (e.g., 23dBm) determined on the carrier / cell to meet SAR / MPE requirements. It can be understood that this power limit can be either a SAR limit or an MPE limit. In Figure 1b, the terminal maintains an average transmit power within the UL duty cycle that meets the transmit power limit.

[0123] In practice, the terminal's transmit power can be below the transmit power limit in some transmit timeslots and above it in other transmit timeslots, as shown in Figure 1c. As Figure 1c shows, the terminal only needs to ensure that the average transmit power per uplink transmission symbol corresponding to the actual UL duty cycle percentage within the uplink evaluation period does not exceed the transmit power limit. Of course, while the instantaneous transmit power in a timeslot can exceed the transmit power limit, it must still meet the terminal's maximum transmit power requirement and cannot exceed the maximum transmit power.

[0124] In some cases, as shown in Figure 1d, the terminal may use the maximum transmit power to transmit uplink data in some time slots. To ensure that the average transmit power per uplink transmission symbol corresponding to the actual UL duty cycle ratio within the uplink evaluation period meets the transmit power limit, the terminal will be unable to transmit uplink data during the subsequent transmission time. That is, the terminal suspends transmission during this period. Even if the terminal may need to send data during this period, it cannot continue to send data.

[0125] In some embodiments, the terminal may use maxUplinkDutyCycle to avoid non-CA SAR / MPE issues for high power user equipment (HPUE). For CA scenarios, this issue can be avoided by the UE.

[0126] In some embodiments, due to high-order modulation and transmission bandwidth configuration, the terminal is allowed to reduce the maximum transmission power. For example, for terminal PC2, Table 2 defines the maximum power reduction (MPR) allowed for channel bandwidths that meet the following two criteria; for terminal PC3, Table 3 defines the maximum power reduction (MPR) allowed for channel bandwidths that meet the following two criteria.

[0127] Table 2

[0128] Table 3

[0129] Wherein, Pi in Table 2 and / or Table 3 may be π.

[0130] In some embodiments, the additional emission requirement may be notified to the terminal via network signaling. Each additional emission requirement is associated with a unique network signaling (NS) value, which is indicated by the NR band number of the applicable operating frequency band and the associated value in the field in the radio resource control (RRC) signaling. For example, the NR band number of the applicable operating frequency band and the associated value in the field may be additional spectrum emission.

[0131] For example, to meet additional requirements, additional maximum power reduction is allowed for the maximum output power specified in Table 2 and / or Table 3.

[0132] (Additional Maximum Power Reduction, A-MPR). Unless otherwise specified, the total reduction in maximum transmission power of a terminal is the maximum of MPR and A-MPR. MPR refers to the above description.

[0133] In some embodiments, the terminal is allowed to set the configured maximum output power for the carrier of the serving cell in each time slot. For example, the configured maximum output power P is set for the carrier f of the serving cell c. CMAX,f,c .

[0134] Optionally, P CMAX,f,c The value of P CMAX_L,f,c and P CMAX_H,f,c Between. That is Among them, P CMAX,f,c is the maximum transmit power, P CMAX_L,f,c is the lower value of the maximum transmit power, P CMAX_H,f,c The high value of the maximum transmit power.

[0135] Optionally, P CMAX_L,f,c Determined based on Formula 1: P CMAX_L,f,c =MIN{P EMAX,c -ΔT C,c (P PowerClass -ΔP PowerClass )-MAX(MAX(MPR c +ΔMPR c ,A-MPR c )+ΔT IB,c +ΔT C,c +ΔT RxSRS ,P-MPR c)} Formula 1

[0136] Where, f represents the carrier frequency, c represents the serving cell, and P EMAX,c Indicates the maximum allowable power of the network device configuration, P PowerClass Indicates the terminal defined power without considering other non-ideal factors (tolerance), ΔP PowerClass Indicates that the maximum power of the terminal is reduced or the power fallback value is configured based on the duty cycle to ensure RF radiation exposure, MPR c Indicates the maximum power reduction due to modulation mode and transmission bandwidth configuration factors, A-MPR c Indicates the additional power backoff required by network signaling to ensure the relevant radiation requirements of different operating frequency bands, ΔT IB,c Indicates the additional power back-off value under multi-carrier, ΔT C,c Indicates the additional power backoff value corresponding to the transmission of special edge configuration, ΔT RxSRS Indicates the terminal power adjustment value related to SRS antenna switching, P-MPR c Indicates the maximum power reduction of power management.

[0137] Optionally, P CMAX_H,f,c Determined based on Formula 2: P CMAX_H,f,c =MIN{P EMAX,c ,P PowerClass -ΔP PowerClass} Formula 2

[0138] In some embodiments, it is considered that the actual uplink transmission controlled by the terminal may change based on the terminal implementation, and these operations are transparent to the network device. Therefore, the terminal can report to the network device the instantaneous transmit power of the physical uplink shared channel (PUSCH) transmission. For example, the network device is reported by means of a power headroom report (PHR). The PHR may include power headroom (PH), maximum transmit power PCMAX,f,c and power-maximum power reduction (P-MPR). Among them, the power headroom reflects the amount of additional transmit power that the terminal can deliver with reference to the current PUSCH power level, and PCMAX,f,c reflects the maximum power that the terminal can deliver in this case, and the current protocol stipulates that P-MPR is only reported for the FR2 band. It can be understood that the PHR provides an instantaneous snapshot of a set of parameters for reporting specific PUSCH transmissions of the network device.

[0139] For example, Figure 1e shows the currently specified PHR configuration format for a single carrier. The P indication field is used to indicate whether there is MPE; the reserved bit can be denoted as R. It can be understood that the reserved bit does not usually contain any information and is mainly used to record the corresponding newly added data when necessary. The power margin is the above-mentioned PH, where in the case of a single carrier, the PH information corresponds to the PUSCH of the terminal, that is, type 1. At the same time, the PH is the PH corresponding to the primary cell (PCell). MPE or reserved bit indicates that this field can be MPE-related information or a reserved bit. Among them, the MPE-related information is used to record P-MPR in the case of FR2.

[0140] For another example, Figure 1f shows the PHR configuration format in a multi-carrier case. Among them, C1 to C7 can be used to indicate the PHR corresponding to different carriers respectively. It can be understood that the multi-carrier PHR can be regarded as a combination of multiple single-carrier PHRs. Type 2 can correspond to the physical uplink control channel (PUCCH), and the special cell (SpCell) can include a PCell and a primary secondary cell (PSCell). The serving cell can be a PCell, a secondary cell (SCell), a PSCell, or a SpCell, etc.

[0141] In some implementations, uplink coverage has long been a bottleneck for system performance, impacting signal quality and user experience. Operators, including operators, have a strong demand for enhanced uplink coverage. In the R18 coverage enhancement (CE) research, power domain enhancement is a worthy topic, as it has the most direct impact on improving both coverage and spectral efficiency (SE).

[0142] In NR uplink CA / DC, the maximum transmit power defined on a BC is limited by the UE transmit power class defined on that BC. However, the RAN4 enhancements in Release 17 support HPUEs to better utilize the UE's independent PA to achieve higher transmit power, primarily by enhancing the PC2+PC3 configuration.

[0143] During actual uplink transmission, terminals are limited by SAR requirements for FR1 and MPE requirements for FR2, limiting their actual transmit power. Transmit power adjustments based on SAR / MPE requirements may also cause significant fluctuations or interruptions in transmit power. Based on the RAN4 protocol, terminals define this type of implementation as transparent to network equipment. These power limits and adjustments, as well as the ability of HPUEs to achieve high-power transmission, significantly impact network equipment scheduling and directly influence the effectiveness of R17 enhancements deployed in network equipment. By enabling network equipment to understand terminal power information and its corresponding behavior, network equipment can make better scheduling decisions.

[0144] Obviously, how to enable network equipment to obtain power-related information of the terminal is a problem that needs to be solved.

[0145] Therefore, the present disclosure facilitates better network scheduling by transmitting the terminal's power level, which is more suitable for the scheduling of service transmission needs. This in turn improves system throughput and user coverage, helps improve system efficiency, reduces ineffective scheduling of network equipment, and saves unnecessary power consumption for terminals.

[0146] FIG2 is an interactive diagram of a communication method according to an embodiment of the present disclosure. As shown in FIG2 , the embodiment of the present disclosure relates to a communication method for use in a communication system 100, the method comprising:

[0147] Step S2101 , the terminal 101 sends second information to the network device 102 .

[0148] In some embodiments, the network device 102 receives the second information sent by the terminal 101 .

[0149] In some embodiments, terms such as "send", "transmit", "report", "download", "transmit", "bidirectional transmission", "send and / or receive" can be used interchangeably.

[0150] In some embodiments, "obtain", "get", "get", "receive", "transmit", "bidirectional transmission", "send and / or receive" can be interchangeable, and can be interpreted as receiving from other entities, obtaining from protocols, obtaining from higher layers, obtaining by self-processing, autonomous implementation, etc.

[0151] In some embodiments, the second information is used to indicate the amount of the second granularity.

[0152] In some embodiments, the second granularity amount is used to determine a second starting time of the first duration of the terminal.

[0153] For example, assuming that the number of second granularities is M, the third duration corresponding to the second granularity is K. The second starting time is the time corresponding to when the SFN is 0 and M*K has passed.

[0154] For example, when the third duration K corresponding to the second granularity is 100 ms and the number of second granularities M is 1, the second starting time is the moment 100 ms after SFN reaches 0. When the number of second granularities M is 2, the second starting time is the moment 200 ms after SFN reaches 0.

[0155] It can be understood that when the number of the second granularity can also be 0, the second starting time is the time corresponding to SFN 0.

[0156] In some embodiments, the second granularity may be equal to the third duration.The second starting time may be a time determined based on the number of reference points and the third duration.

[0157] For example, assuming that the number of the third durations is M, and the size of the third duration is K. The second starting time is the time corresponding to when the SFN is 0 and M*K has passed.

[0158] The first duration of the terminal is used to represent an estimated duration of at least one of the first power level and the third power level of the terminal.

[0159] The first power level is used to indicate the power level of the terminal after the power level falls back to a low level, and the third power level is used to indicate the power level of the terminal after the power level is restored.

[0160] For example, when the terminal experiences power level fallback, the first duration may be used to indicate an estimated duration of the first power level.

[0161] For another example, when the power level of the terminal is restored, the first duration may be used to indicate an estimated duration of the third power level.

[0162] In some embodiments, the terminal 101 sends second information to the network device, and the network device 102 can determine the number of second granularities based on the second information, and then determine the second starting time of the power level duration after the power level changes, so as to facilitate better scheduling of the network.

[0163] In some embodiments, the name of the second information is not limited, and it can be, for example, "granularity information", " ", etc.

[0164] In some embodiments, the names of information, etc. are not limited to the names described in the embodiments, and terms such as "information", "message", "signal", "signaling", "report", "configuration", "indication", "instruction", "command", "channel", "parameter", "domain", "field", "symbol", "symbol", "codeword", "codebook", "codeword", "codepoint", "bit", "data", "program", etc. can be used interchangeably.

[0165] In some embodiments, terms such as "certain", "preset", "preset", "setting", "indicated", "a certain", "any", and "first" can be interchangeable. "Specific A", "preset A", "preset A", "setting A", "indicated A", "a certain A", "any A", and "first A" can be interpreted as A pre-specified in a protocol, etc., or as A obtained through setting, configuration, or indication, etc., or as specific A, a certain A, any A, or first A, etc., but not limited to this.

[0166] In some embodiments, terms such as "moment", "time point", "time", and "time position" can be replaced with each other, and terms such as "duration", "period", "time window", "window", and "time" can be replaced with each other.

[0167] Step S2102 , the terminal 101 sends first information to the network device 102 .

[0168] In some embodiments, the network device 102 receives the first information sent by the terminal 101 .

[0169] In some embodiments, the terminal 101 sends the first information via the PHR.

[0170] For example, the PHR includes the first information.

[0171] Optionally, in response to a power level fallback, the terminal triggers a PHR report.

[0172] Optionally, in response to the transmit power level recovery, the terminal triggers PHR reporting.

[0173] For example, the PHR reporting is triggered when the terminal undergoes level fallback, which may be after the terminal undergoes level fallback.

[0174] For another example, the PHR report is triggered when the terminal undergoes level fallback. This may be when the terminal is about to undergo level fallback but has not yet undergone level fallback, thus triggering the PHR report.

[0175] For another example, the PHR reporting is triggered when the terminal recovers its level. This may be after the terminal recovers its level and then triggers the PHR reporting.

[0176] For another example, the PHR reporting is triggered when the terminal undergoes level recovery. This may be when the terminal is about to undergo level recovery but has not yet undergone level recovery, thus triggering the PHR reporting.

[0177] For example, the power level of the terminal may be PC1.5, PC2, PC3, etc. Among them, the maximum transmit power of the terminal of PC1.5 is 29dBm, the maximum transmit power of the terminal of PC2 is 26dBm, and the maximum transmit power of the terminal of PC3 is 23dBm.

[0178] Of course, the above-mentioned PC1.5, PC2, PC3, etc. are only illustrative examples, and the power levels are not limited thereto, and this disclosure does not give examples one by one.

[0179] Optionally, the power level fallback may be a fallback to a first power level, where the first power level is lower than a second power level, and the second power level is used to represent a power level defined and / or initially reported by the terminal.

[0180] The power level defined by the terminal and the power level initially reported by the terminal may be the same or different.

[0181] For example, if the terminal defines a power level of PC1.5, but the terminal falls back to PC2 after power level fallback, the power level initially reported by the terminal may be PC2. In this case, the power level defined by the terminal and the power level initially reported by the terminal are different.

[0182] For example, the power level fallback may be to fall back to any power level lower than the power level defined and / or initially reported by the terminal.

[0183] For example, the power level fallback may be from PC1.5 to PC2, or from PC1.5 to PC3.

[0184] Optionally, the power level fallback may be a step-by-step fallback or an alternate-level fallback.

[0185] For example, rolling back from PC1.5 to PC3 can be done from PC1.5 to PC2, and then from PC2 to PC3. This can be considered a step-by-step rollback.

[0186] For another example, rolling back from PC1.5 to PC3 can also be done directly from PC1.5 to PC3. In this case, it can be considered as a step-by-step rollback.

[0187] For another example, the power level recovery may be recovery from the current power level to a power level defined by the terminal, or recovery to a power level initially reported by the terminal.

[0188] Optionally, the power level recovery may be performed step by step or alternately.

[0189] For example, restoring from PC3 to PC1.5 can be done from PC3 to PC2, and then from PC2 to PC1.5. This can be considered a step-by-step recovery.

[0190] For another example, restoring from PC3 to PC1.5 can be done directly from PC3 to PC1.5, which can be considered as a step-by-step restoration.

[0191] It can be understood that the above-mentioned power level fallback and power level recovery are merely illustrative examples, and the present disclosure does not limit them.

[0192] Optionally, when an uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is greater than a first threshold corresponding to the current power level, it is determined that a power level fallback occurs.

[0193] Optionally, when an uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is greater than a first threshold corresponding to the current power level, it is determined that a power level fallback occurs.

[0194] For example, the first threshold may be the configured maxUplinkDutyCycle. That is, when the actual duty cycle exceeds the configured maxUplinkDutyCycle, power level fallback occurs.

[0195] Optionally, when an uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is less than a first threshold corresponding to the current power level, it is determined that a power level fallback occurs.

[0196] Optionally, when an uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is equal to a first threshold corresponding to the current power level, it is determined that power level fallback occurs.

[0197] For example, when the actual duty cycle does not exceed the configured maxUplinkDutyCycle, power level recovery occurs.

[0198] For example, the actual duty cycle is the duty cycle counted in real time during the current evaluation period.

[0199] Optionally, when the terminal enters a next evaluation period, the power level is restored.

[0200] It is understood that when the uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is greater than the first threshold corresponding to the current power level, it can be determined that a power level fallback or a power level recovery has occurred. For example, the power level fallback or the power level recovery can be determined based on the terminal implementation. For another example, the power level fallback or the power level recovery can be determined based on a pre-determined rule.

[0201] For example, when the terminal enters the next evaluation period, it transmits according to the power level defined by the terminal, that is, the power level is restored to the power level defined by the terminal.

[0202] In some embodiments, terms such as "uplink", "uplink", "physical uplink" can be interchangeable with each other, and terms such as "downlink", "downlink", "physical downlink" can be interchangeable with each other, and terms such as "side", "sidelink", "side communication", "sidelink communication", "direct connection", "direct link", "direct communication", "direct link communication" can be interchangeable with each other.

[0203] In some embodiments, terms such as "physical downlink shared channel (PDSCH)" and "DL data" can be used interchangeably, and terms such as "physical uplink shared channel (PUSCH)" and "UL data" can be used interchangeably.

[0204] In some embodiments, the first information is used to indicate a power level of the terminal.

[0205] Optionally, the first information may include a first power level.

[0206] Optionally, the first information may include a third power level.

[0207] The first power level is used to indicate the power level of the terminal after the power level falls back to a low level, and the third power level is used to indicate the power level of the terminal after the power level is restored.

[0208] Optionally, the third power level after the power level is restored may be the second power level, that is, the third power level may be the same as the second power level.

[0209] Optionally, the power level after power level recovery may be a power level other than the second power level. That is, the third power level may be different from the second power level. For example, if the terminal defines a power level of PC1.5 and the terminal's current power level is PC3, the power level after power level recovery may be PC2, rather than the terminal's defined power level of PC1.5.

[0210] Optionally, the first information may include a power level change.

[0211] For example, the power level change amount may include a power change amount based on a maxUplinkDutyCycle requirement.

[0212] It is understood that the power level change can be used to represent the power level. For example, if the terminal last reported a power level of PC1.5 and the terminal reported a power level change of -3dB, the network can determine that the terminal's current power level is PC2 based on PC1.5 and -3dB. For another example, if the terminal last reported a power level of PC2 and the terminal reported a power level change of 3dB, the network can determine that the terminal's current power level is PC1.5 based on PC2 and 3dB.

[0213] Of course, the above example of determining the current power level of the terminal based on the power level change is only for the convenience of explanation, and the present disclosure does not limit this. Optionally, the first information may include an evaluation period of the terminal.

[0214] In some embodiments, the first information is used to indicate a change in the power level of the terminal.

[0215] For example, the terminal sends first information, where the first information is used to indicate a power level change of the terminal, so that the network device can determine the power level change of the terminal.

[0216] For another example, the terminal sends first information, where the first information is used to indicate a power level change of the terminal, so that the network can determine the current power level of the terminal according to the power level change of the terminal.

[0217] Optionally, the evaluation periods of the various carriers are consistent, and the evaluation period in the first information is applied to each carrier.

[0218] Optionally, each carrier evaluation period is different, and each carrier evaluation period in the first information is reported independently together with the PH.

[0219] Optionally, the first information may include a first duration of at least one of the first power level and the third power level.

[0220] In some embodiments, the first duration is used to represent an estimated duration of at least one of the first power level and the third power level.

[0221] For example, when the terminal experiences power level fallback, the first duration may be used to indicate an estimated duration of the first power level.

[0222] For another example, when the power level of the terminal is restored, the first duration may be used to indicate an estimated duration of the third power level.

[0223] In some embodiments, the first information of each carrier is reported together with the power headroom.

[0224] Optionally, the power level and power headroom of each carrier are reported together.

[0225] Optionally, the power level change and power headroom of each carrier are reported together.

[0226] Optionally, the power level, power level change, and power headroom of each carrier are reported together.

[0227] In some embodiments, the terminal triggers PHR reporting in response to power level fallback, and the code point corresponding to the power level change in the PHR only includes support for the power level fallback situation.

[0228] For example, when the terminal triggers PHR reporting in response to power level fallback, the terminal may refer to Table 4-1, Table 4-2, Table 4-3, and Table 5 to determine the code point indication corresponding to the power level change in the PHR.

[0229] Table 4-1

[0230] or

[0231] Table 4-2

[0232] or

[0233] Table 4-3

[0234] Table 5

[0235] Tables 4-1, 4-2, and 4-3 illustrate the correspondence between the power level change indication field information reported in the PHR and the power level change amount. Tables 4-1, 4-2, and 4-3 support terminal capability levels up to PC1.5. The maximum transmit power of a PC1.5 terminal is 29 dBm. Table 5 illustrates the correspondence between the power level change indication field information reported in the PHR and the power level change amount. Table 5 supports terminal capability levels up to PC1. The maximum transmit power of a PC1 terminal is 31 dBm.

[0236] For example, when a terminal falls back from PC2 to PC3, the maximum transmit power of the terminal on PC2 is 26dBm, and the maximum transmit power of the terminal on PC3 is 23dBm. The power level change can be considered to be 3dB. In this case, the PHR reports the power level change corresponding to code point 01.

[0237] For example, when a terminal falls back from PC1.5 to PC3, the maximum transmit power of the terminal at PC1.5 is 29dBm, and the maximum transmit power of the terminal at PC3 is 23dBm. The power level change can be considered to be 6dB. In this case, the PHR reports the power level change corresponding to code point 02.

[0238] It is understood that the power level change of the terminal may be 0dB, 1dB, 3dB, 6dB, or 8dB, and different power level changes are indicated by different indicator code points. The indicator code point corresponding to the power level change in the PHR can be determined by referring to any of the above tables. The above table is only exemplary and is not limited in this disclosure.

[0239] For example, code point 03 can be used as a reserved code point, as shown in Table 4-1 and Table 4-3. It can also be used to indicate a power change of 0 dB, as shown in Table 4-2. It can also be used to indicate 8 dB, as shown in Table 5.

[0240] Optionally, the code point corresponding to the power level change amount reported by the PHR may be a code point corresponding to the power level change amount carried in a medium access control element (MAC-CE) corresponding to the PHR report.

[0241] In some embodiments, the terminal triggers PHR reporting in response to transmission power level fallback and power level recovery, and the code point corresponding to the power level change in the PHR includes support for power level fallback and power level recovery.

[0242] Exemplarily, when the terminal triggers PHR reporting in response to power level fallback and power level recovery, the terminal may refer to Table 6 to determine the code point indication corresponding to the power level change in the PHR.

[0243] Table 6

[0244] Table 7-1

[0245] Table 7-2

[0246] Among them, Table 6, Table 7-1 and Table 7-2 are used to represent the correspondence between the power level change indication field information reported in the PHR and the power level change.

[0247] For example, when a terminal falls back from PC2 to PC3, the maximum transmit power of the terminal on PC2 is 26dBm, and the maximum transmit power of the terminal on PC3 is 23dBm. The power level change can be considered to be -3dB. In this case, the PHR reports the power level change corresponding to code point 03.

[0248] For example, when a terminal falls back from PC1.5 to PC3, the maximum transmit power of the terminal at PC1.5 is 29dBm, and the maximum transmit power of the terminal at PC3 is 23dBm. The power level change can be considered to be -6dB. In this case, the PHR reports the power level change corresponding to code point 04.

[0249] For another example, when the terminal recovers from PC3 to PC2, the power level change can be considered to be 3dB. In this case, the PHR reports the power level change corresponding to code point 01.

[0250] For another example, when the terminal recovers from PC3 to PC1.5, the power level change can be considered to be 6 dB. In this case, the PHR reports the power level change corresponding to code point 02.

[0251] For example, code points 05 and 06 can be used as reserved code points, as shown in Table 6. They can also be used to indicate power changes of 8 dB and -8 dB, as shown in Table 7-1 and Table 7-2.

[0252] In some embodiments, the terms "codebook," "codeword," and "precoding matrix" may be used interchangeably. For example, a codebook may be a collection of one or more codewords / precoding matrices.

[0253] In some embodiments, the first information includes a first starting time of an evaluation period of the terminal.

[0254] In some embodiments, the first starting time is used to indicate a starting time of an evaluation period of the terminal.

[0255] In some embodiments, the evaluation period mentioned in the above embodiments may be an evaluation period of a transmission duty cycle of the terminal. The transmission duty cycle evaluation period may also be referred to as a duty cycle evaluation period of the terminal.

[0256] Optionally, the first starting time includes a time corresponding to a system frame number SFN (SFN) of 0.

[0257] The system frame number can be understood as the number of the wireless frame.

[0258] Optionally, the first starting time includes the time corresponding to when the SFN is 0 and after an offset.

[0259] For example, the offset may be predefined by a protocol or configured by network signaling, and the unit may be a radio frame / subframe / time slot / ms / s, such as directly predefined as 100ms, 200ms, etc., which is not limited in this disclosure.

[0260] For another example, the offset can be determined based on the number of granularities. For example, the default starting time of SFN=0 is the preset reference point, and the duration corresponding to the granularity is 100ms. When the number of granularities is 1, the actual offset is 100ms relative to the preset reference point. That is, in this case, the starting time of the terminal's duty cycle evaluation period is the reference point position 100ms after the starting time of SFN=0.

[0261] Of course, the above examples of 100ms and 200ms are just illustrative examples, and the present disclosure does not limit them.

[0262] In some embodiments, the first information includes a first duration of an evaluation period of the terminal.

[0263] In some embodiments, the first duration is used to represent the duration of an evaluation period of the terminal.

[0264] Optionally, the first duration is based on a quantity representation of a first granularity.

[0265] The first granularity corresponds to the second duration.

[0266] In some embodiments, the first granularity may be equivalent to the second duration, ie, the first duration is expressed based on a quantity of the second duration.

[0267] In some embodiments, the first granularity may represent a unit duration, that is, the first duration is represented based on the number of unit durations.

[0268] For example, if the duration corresponding to one granularity is preset, when the number of granularities is 2, the first duration is twice the duration corresponding to one granularity; and when the number of granularities is 3, the first duration is three times the duration corresponding to one granularity.

[0269] For example, if the first duration corresponding to the preset granularity number of 1 is 100ms, then when the granularity number is 2, the first duration can be determined to be 200ms; when the granularity number is 3, the first duration can be determined to be 300ms.

[0270] For another example, if the second duration is preset and the number of the second durations is 2, then the first duration is twice the second duration. For example, if the second duration is preset to 100ms, then when the number of the second durations is 2, then the first duration is 200ms.

[0271] For another example, if the unit duration is preset and the number of unit durations is 2, the first duration is twice the unit duration. For example, if the unit duration is preset to 100ms, then when the number of unit durations is 2, the first duration is 200ms.

[0272] Of course, the above examples of 100ms, 200ms, and 300ms are only for the convenience of explanation, and the present disclosure does not limit them.

[0273] Optionally, the first duration is represented based on the first value, and different first values ​​correspond to different preset first duration intervals.

[0274] For example, different first duration intervals A, B, and C are pre-set. A first value X is associated with the first duration interval A; a first value Y is associated with the first duration interval B; and a first value Z is associated with the first duration interval C. Therefore, when the first information includes the first value X, it can indicate that the first duration is interval A.

[0275] For example, the preset interval (100-200ms) corresponds to the first value 1, the preset interval (200-300ms) corresponds to the first value 2, and the preset interval (300-400ms) corresponds to the first value 3. When the first information includes the first value 1, it can indicate that the duration of the evaluation period is the duration interval (100-200ms). That is, the duration of the evaluation period may be a value between 100-200ms. When the first information includes the first value 2, it can indicate that the duration of the evaluation period is the duration interval (200-300ms).

[0276] Of course, the intervals given in the above examples are only for the convenience of explanation, and the present disclosure does not limit the size of the duration interval.

[0277] Optionally, the first duration is represented based on the second value, and different second values ​​correspond to different preset second durations.

[0278] For example, different durations are preset and associated with the second value. When the first information includes the second value, it can be indicated that the first duration is the duration corresponding to the second value.

[0279] For example, a first duration of 100ms is preset to correspond to a second value A, a first duration of 200ms is preset to correspond to a second value B, and a first duration of 300ms is preset to correspond to a second value C. When the first information includes the second value A, it can indicate that the duration of the evaluation period is 100ms. When the first information includes the second value B, it can indicate that the duration of the evaluation period is 200ms. When the first information includes the second value C, it can indicate that the duration of the evaluation period is 300ms.

[0280] Of course, the above examples of 100ms, 200ms, and 300ms are only exemplary and are not limited in this disclosure.

[0281] It can be understood that the first value and the second value can be in any form, such as numbers, letters, symbols, etc., and this disclosure does not limit them.

[0282] In some embodiments, the first information includes a second starting time of the first duration of the terminal.

[0283] In some embodiments, the second starting time is used to indicate the starting time of the first duration.

[0284] Optionally, the second starting time may be the time at which the PHR is sent.

[0285] Optionally, the second starting time may be the first starting time corresponding to the evaluation period.

[0286] Optionally, the second starting time may be determined based on the time when the SFN is 0 and the number of second granularities, wherein the second granularity corresponds to the third duration.

[0287] For example, assuming that the number of second granularities is M, the third duration corresponding to the second granularity is K. The second starting time is the time corresponding to when the SFN is 0 and M*K has passed.

[0288] For example, when the third duration K corresponding to the second granularity is 100 ms and the number of second granularities M is 1, the second starting time is the moment 100 ms after SFN reaches 0. When the number of second granularities M is 2, the second starting time is the moment 200 ms after SFN reaches 0.

[0289] It can be understood that when the number of the second granularity can also be 0, the second starting time is the time corresponding to SFN 0.

[0290] In some embodiments, the second granularity may be equal to the third duration.The second starting time may be a time determined based on the number of reference points and the third duration.

[0291] For example, assuming that the number of the third durations is M, and the size of the third duration is K. The second starting time is the time corresponding to when the SFN is 0 and M*K has passed.

[0292] In some embodiments, the terminal may send second information to the network device, where the second information is used to indicate the amount of granularity.

[0293] Optionally, the terminal may send the second information first and then send the first information.

[0294] Optionally, the terminal may send the second information and the first information simultaneously.

[0295] Optionally, the terminal may send the second information first, and there is no need to send the second information again subsequently.

[0296] Optionally, the terminal may send the second information each time it sends the first information.

[0297] Optionally, the second starting time may be a time determined based on a second reference point. The second reference point is a reference point adjacent to the time of sending the PHR among reference points obtained by dividing the evaluation period based on a third granularity. The third granularity corresponds to the fourth duration.

[0298] For example, assuming that the evaluation period is divided into N reference points based on the third granularity, the third granularity corresponds to the fourth duration. The PHR is sent between the i-th reference point and the i+1-th reference point, then the second starting moment can be the moment corresponding to the i-th reference point or the moment corresponding to the i+1-th reference point. The moment corresponding to the i-th reference point is the moment after the start moment of the evaluation period passes through i third granularities. The moment corresponding to the i+1-th reference point is the moment after the start moment of the evaluation period passes through i+1 granularities.

[0299] For example, assuming N is 5, the evaluation period is divided into 5 reference points, and the fourth duration corresponding to the third granularity is 100 ms. In this case, if the PHR is sent between the second and third reference points, that is, i is 2, the second starting time of the power level change duration can be determined based on the second reference point and be 200 ms. Alternatively, it can be determined based on the third reference point and be 300 ms.

[0300] In some embodiments, the third granularity may be equal to the fourth duration.The second starting time may be a time determined based on the fourth duration.

[0301] For example, assuming that the evaluation period is divided into N fourth durations based on the size of the fourth duration, if the PHR is sent between the second and third fourth durations, that is, i is 2, then the second starting time of the power level change duration can be determined based on the second fourth duration, i.e., 200 ms. Alternatively, it can be determined based on the third fourth duration, i.e., 300 ms.

[0302] Optionally, the second starting time may be a PUSCH sending time.

[0303] It can be understood that the way of expressing the duration of the power level change is the same as the way of expressing the duration of the power level, and the present disclosure will not elaborate on them here.

[0304] In some embodiments, the first information includes a fifth duration of the first duration of the terminal.

[0305] In some embodiments, the fifth duration is used to indicate the duration of the first duration.

[0306] Optionally, the fifth duration is represented based on a number of third granularities, wherein each third granularity corresponds to the same sixth duration, and the sixth duration is less than or equal to the fifth duration.

[0307] Optionally, the fifth duration is represented by the third value, wherein different third values ​​correspond to different second duration intervals, and the second duration interval is an interval in which the power level corresponds to a preset duration.

[0308] Optionally, the fifth duration is represented by the fourth value based on the fifth duration, wherein different fourth values ​​correspond to different durations corresponding to preset power levels.

[0309] It can be understood that the specific representation of the fifth duration can refer to the specific representation of the first duration mentioned above, and the present disclosure will not elaborate on it here.

[0310] In some embodiments, the first information further includes a maximum output power configured for the terminal. The maximum output power is determined based on the first output power, the power variation, and the MPR. The first output power is determined based on the second power level, the power variation and the MPR are determined based on the second power level, or the power variation and the MPR are determined based on the third power level.

[0311] For example, the maximum output power is determined based on the above-mentioned Formula 1 and Formula 2.

[0312] In some embodiments, the first output power may be P in Formula 1 PowerClass , the power change can be ΔP in formula 1 PowerClass The first output power level is determined based on the second power level, where the second power level is used to represent a power level defined by the terminal and / or initially reported by the terminal.

[0313] The power level defined by the terminal and the power level initially reported by the terminal may be the same or different.

[0314] Optionally, when the UL duty cycle of the terminal exceeds the maximum UL duty cycle and power level fallback occurs, the terminal may determine the power variation and the MPR based on the power level defined by the terminal.

[0315] For example, when the power level falls back from PC2 to PC3, the power change is determined based on the second power level, that is, the power change at this time does not include the power change corresponding to the power level fallback. The terminal refers to Table 2 above and determines the MPR based on PC2.

[0316] Optionally, when the UL duty cycle of the terminal exceeds the maximum UL duty cycle and power level fallback occurs, the terminal may determine the maximum transmit power based on the power level after the power level change.

[0317] For example, when the power level falls back from PC2 to PC3, the power change is determined based on the second power level, that is, the power change at this time includes the power change corresponding to the power level fallback. The terminal refers to Table 3 above and determines the maximum transmit power based on PC3.

[0318] The communication method involved in the embodiment of the present disclosure may include at least one of steps S2101 to S2102. For example, step S2101 may be implemented as an independent embodiment.

[0319] In some embodiments, steps S2101 and S2102 may be executed in an interchanged order or simultaneously.

[0320] In some embodiments, step S2102 is optional and can be omitted or replaced in different embodiments.

[0321] In some embodiments, reference may be made to other optional implementations described before or after the description corresponding to FIG. 2 .

[0322] FIG3a is a flow chart of a communication method according to an embodiment of the present disclosure. As shown in FIG3a, the present disclosure embodiment relates to a communication method, which is executed by terminal 101 and includes:

[0323] Step S3101, sending the second information.

[0324] The optional implementation of step S3101 can refer to the optional implementation of step S2101 in Figure 2 and other related parts in the embodiment involved in Figure 2, which will not be repeated here.

[0325] In some embodiments, the terminal 101 sends the second information to the network device 102, but is not limited thereto and the second information may also be sent to other entities.

[0326] The communication method involved in the embodiment of the present disclosure may include at least one of steps S3101 to S3102. For example, step S3101 may be implemented as an independent embodiment.

[0327] Step S3102, sending the first information.

[0328] The optional implementation of step S3102 can refer to the optional implementation of step S2102 in Figure 2 and other related parts in the embodiment involved in Figure 2, which will not be repeated here.

[0329] In some embodiments, the terminal 101 sends the first information to the network device 102, but is not limited thereto and may also send the second information to other entities.

[0330] In some embodiments, steps S3101 and S3102 may be executed in an interchanged order or simultaneously.

[0331] In some embodiments, step S3101 is optional and can be omitted or replaced in different embodiments.

[0332] In some embodiments, reference may be made to other optional implementations described before or after the description corresponding to FIG. 2 .

[0333] FIG3b is a flow chart of a communication method according to an embodiment of the present disclosure. As shown in FIG3b, the embodiment of the present disclosure relates to a communication method, which is executed by terminal 101 and includes:

[0334] Step S3201, sending the first information.

[0335] Optional implementations of step S3201 can be found in step S2102 of FIG. 2 , optional implementations of step S3102 of FIG. 3 a , and other related parts in the embodiments involved in FIG. 2 and FIG. 3 a , which will not be described in detail here.

[0336] In some embodiments, sending the first information includes: sending the first information when at least one of the following conditions is met; the power level falls back to the first power level, the first power level is lower than the second power level, and the second power level is the power level defined by the terminal and / or initially reported by the terminal; and the power level is restored.

[0337] In some embodiments, the power level fallback is determined by: the uplink transmission duty cycle corresponding to the physical uplink shared channel PUSCH sent by the terminal is greater than the first threshold corresponding to the current power level, and the power level fallback is determined, where different power levels correspond to different first thresholds.

[0338] In some embodiments, power level recovery is determined by at least one of the following methods: the terminal starts the next evaluation cycle to determine power level recovery; the terminal sends the PUSCH and the uplink transmission duty cycle corresponding to the duty cycle is less than or equal to the second threshold, and the power level recovery is determined.

[0339] In some embodiments, the terminal starts a next evaluation cycle, and determining that the power level is restored includes: the power level is restored to a power level defined by the terminal and / or initially reported by the terminal.

[0340] In some embodiments, the first information includes at least one of the following: a first power level after the power level falls back; a third power level after the power level is restored; a power level change of the terminal; an evaluation period of the terminal; a first duration corresponding to at least one of the first power level and the third power level, the first duration being used to represent an estimated duration of at least one of the first power level and the third power level.

[0341] In some embodiments, the evaluation period includes a first starting time, which is the starting time of the evaluation period; the first starting time includes at least one of the following: the time corresponding to the system frame number SFN being 0; the time corresponding to the SFN being 0 and after the offset offset.

[0342] In some embodiments, the evaluation period includes a first duration, which is the duration of the evaluation period; the first duration is expressed in at least one of the following ways: expressing the first duration based on a quantity of a first granularity, wherein the first granularity corresponds to a second duration; expressing the first duration based on a first value, wherein the first value corresponds to a first duration interval, the first duration interval is a duration range of a pre-set evaluation period, the first duration is within the duration range, and the first duration is expressed by the duration range; expressing the first duration based on a second value, wherein the second value corresponds to a pre-set evaluation period duration.

[0343] In some embodiments, the first duration includes a second starting moment; the second starting moment includes at least one of the following: the sending moment of PHR; the first starting moment corresponding to the evaluation period; the moment determined based on the first reference point and the number of second granularities, wherein the first reference point is the moment corresponding to SFN equal to 0, and the second granularity corresponds to the third duration; the moment determined based on the second reference point, wherein the second reference point is the reference point adjacent to the moment of sending PHR among the reference points obtained by dividing the evaluation period based on the third granularity, and the third granularity corresponds to the fourth duration; the sending moment of PUSCH.

[0344] In some embodiments, the second starting time includes a time determined based on the first reference point and the number of the second granularity; the method further includes: sending second information, where the second information is used to indicate the number of the second granularity.

[0345] In some embodiments, the first duration includes a fifth duration; the fifth duration is expressed in at least one of the following ways: expressing the fifth duration based on the quantity of the third granularity, wherein the third granularity corresponds to the sixth duration; expressing the fifth duration based on the third value, wherein the third value corresponds to the second duration interval, the second duration interval is the duration range of a pre-set power level, the fifth duration is within the duration range, and the fifth duration is expressed by the duration range; expressing the fifth duration based on the fourth value, wherein the fourth value corresponds to the pre-set power level duration.

[0346] In some embodiments, the first information includes the maximum output power of the terminal, and the maximum output power is determined based on the first output power, the power change and the maximum power attenuation MPR, wherein the first output power is determined based on the second power level, the power change and the MPR are determined based on the second power level, or the power change and the MPR are determined based on the third power level.

[0347] FIG4a is a flow chart of a communication method according to an embodiment of the present disclosure. As shown in FIG4a, the embodiment of the present disclosure relates to a communication method, and the method includes:

[0348] Step S4101, obtain second information.

[0349] The optional implementation of step S4101 can refer to the optional implementation of step S2101 in Figure 2 and other related parts in the embodiment involved in Figure 2, which will not be repeated here.

[0350] In some embodiments, step S4101 is optional and can be omitted or replaced in different embodiments.

[0351] In some embodiments, the network device receives the second information sent by the terminal, but is not limited thereto and may also receive the second information sent by other entities.

[0352] In some embodiments, the network device 102 receives the second information sent by the terminal 101, but is not limited thereto and may also receive the second information sent by other entities.

[0353] In some embodiments, the network device 102 obtains second information specified by the protocol.

[0354] In some embodiments, the network device 102 obtains the second information from upper layer(s).

[0355] In some embodiments, the network device 102 performs processing to obtain the second information.

[0356] In some embodiments, step S4101 is omitted, and the network device 102 autonomously implements the function indicated by the second information, or the above function is default or by default.

[0357] Step S4102, obtaining first information.

[0358] The optional implementation of step S4102 can refer to the optional implementation of step S2102 in Figure 2 and other related parts in the embodiment involved in Figure 2, which will not be repeated here.

[0359] FIG4b is a flow chart of a communication method according to an embodiment of the present disclosure. As shown in FIG4a, the embodiment of the present disclosure relates to a communication method, which includes:

[0360] Step S4201, obtain first information.

[0361] The optional implementation of step S4201 can refer to the optional implementation of step S2102 in Figure 2 and other related parts in the embodiment involved in Figure 2, which will not be repeated here.

[0362] In some embodiments, the network device receives the first information sent by the terminal, but is not limited thereto and may also receive the first information sent by other entities.

[0363] In some embodiments, the network device receives the first information sent by the terminal, but is not limited thereto and may also receive the first information sent by other entities. In some embodiments, the network device 102 receives the first information sent by the terminal 101, but is not limited thereto and may also receive the first information sent by other entities.

[0364] In some embodiments, the network device 102 obtains first information specified by the protocol.

[0365] In some embodiments, the network device 102 obtains the first information from an upper layer(s).

[0366] In some embodiments, the network device 102 performs processing to obtain the first information.

[0367] In some embodiments, step S4201 is omitted, and the network device 102 autonomously implements the function indicated by the first information, or the above function is default or by default.

[0368] In some embodiments, the network device 102 receives the first information sent by the terminal 101, but is not limited thereto and may also receive the first information sent by other entities. In some embodiments, the network device 102 obtains the first information specified by the protocol.

[0369] In some embodiments, the network device 102 obtains the first information from an upper layer(s).

[0370] In some embodiments, the network device 102 performs processing to obtain the first information.

[0371] In some embodiments, step S4102 is omitted, and the network device 102 autonomously implements the function indicated by the first information, or the above function is default or by default.

[0372] In some embodiments, the first information is generated when at least one of the following conditions is met: the power level falls back to the first power level, the first power level is lower than the second power level, the second power level is the power level defined by the terminal and / or initially reported by the terminal; the power level is restored.

[0373] In some embodiments, the power level fallback is determined by: the uplink transmission duty cycle corresponding to the physical uplink shared channel PUSCH sent by the terminal is greater than the first threshold corresponding to the current power level, and the power level fallback is determined, where different power levels correspond to different first thresholds.

[0374] In some embodiments, power level recovery is determined by at least one of the following methods: the terminal starts the next evaluation cycle to determine power level recovery; the terminal sends the PUSCH and the uplink transmission duty cycle corresponding to the duty cycle is less than or equal to the second threshold, and the power level recovery is determined.

[0375] In some embodiments, the terminal starts a next evaluation cycle, and determining that the power level is restored includes: the power level is restored to a power level defined by the terminal and / or initially reported by the terminal.

[0376] In some embodiments, the first information includes at least one of the following reported quantities: the first power level after the power level falls back; the third power level after the power level is restored; the power level change of the terminal; the evaluation period of the terminal; the first duration corresponding to at least one of the first power level and the third power level, the first duration being used to represent the estimated duration of at least one of the first power level and the third power level.

[0377] In some embodiments, the evaluation period includes a first starting time, which is the starting time of the evaluation period; the first starting time includes at least one of the following: the time corresponding to the system frame number SFN being 0; the time corresponding to the SFN being 0 and after the offset offset.

[0378] In some embodiments, the evaluation period includes a first duration, which is the duration of the evaluation period; the first duration is expressed in at least one of the following ways: expressing the first duration based on a quantity of a first granularity, wherein the first granularity corresponds to a second duration, and the second duration is less than or equal to the first duration; expressing the first duration based on a first value, wherein the first value corresponds to a first duration interval, and the first duration interval is a duration range of a pre-set evaluation period, and the first duration is within the duration range, and the first duration is expressed by the duration range; expressing the first duration based on a second value, wherein the second value corresponds to a pre-set evaluation period duration.

[0379] In some embodiments, the first duration includes a second starting moment; the second starting moment includes at least one of the following: the sending moment of PHR; the first starting moment corresponding to the evaluation period; the moment determined based on the first reference point and the number of second granularities, wherein the first reference point is the moment corresponding to SFN equal to 0, and the second granularity corresponds to the third duration; the moment determined based on the second reference point, wherein the second reference point is the reference point adjacent to the moment of sending PHR among the reference points obtained by dividing the evaluation period based on the third granularity, and the third granularity corresponds to the fourth duration; the sending moment of PUSCH.

[0380] In some embodiments, the second starting time includes a time determined based on the first reference point and the amount of the second granularity; the method further includes: receiving second information, the second information being used to indicate the amount of the second granularity.

[0381] In some embodiments, the first duration includes a fifth duration; the fifth duration is expressed in at least one of the following ways: expressing the fifth duration based on the quantity of the third granularity, wherein the third granularity corresponds to the sixth duration, and the sixth duration is less than or equal to the fifth duration; expressing the fifth duration based on the third value, wherein different third values ​​correspond to different second duration intervals, and the second duration interval is the interval in which the power level corresponds to the pre-set duration; expressing the fifth duration based on the fourth value, wherein different fourth values ​​correspond to different durations corresponding to the pre-set power level.

[0382] In some embodiments, the first information includes the maximum output power of the terminal, and the maximum output power is determined based on the first output power, the power change and the maximum power attenuation MPR, wherein the first output power is determined based on the second power level, the power change and the MPR are determined based on the second power level, or the power change and the MPR are determined based on the third power level.

[0383] FIG5 is a flow chart of a communication method according to an embodiment of the present disclosure. As shown in FIG5 , the embodiment of the present disclosure relates to a communication method, and the method includes:

[0384] In step S5101, the terminal 101 sends first information, where the first information is used to indicate a full power mode corresponding to different power levels of the terminal.

[0385] Optional implementations of step S5101 may refer to step S2102 in FIG. 2 , step S3102 in FIG. 3 , and other related parts in the embodiments involved in FIG. 2 and FIG. 3 a , which will not be described in detail here.

[0386] In some embodiments, the above method may include the method of the above embodiments related to the communication system 100, the terminal 101, the network device 102, etc., which will not be repeated here.

[0387] In some embodiments, the above method may include the method of the above embodiments related to the communication system 100, the terminal 101, the network device 102, etc., which will not be repeated here.

[0388] The present disclosure also provides a communication method as follows:

[0389] In some embodiments, based on the PHR measurement report, the terminal reports terminal power information related to the current power level or the power level change.

[0390] In some embodiments, reporting may also be sending.

[0391] In some embodiments, the triggering condition for PHR reporting is: a change in power level.

[0392] Optionally, PHR reporting is triggered only when power level fallback occurs (i.e., when the actual duty cycle value exceeds the configured maxUplinkdutycycle value);

[0393] Optionally, a PHR report is triggered when power level fallback or power level recovery occurs (i.e., when the actual duty cycle value exceeds the configured maxUplinkdutycycle value);

[0394] Optionally, the condition for restoring the power level may be that the terminal starts a new evaluation period and resumes sending according to the power level defined by the terminal.

[0395] Optionally, the condition for power level recovery may be when the actual duty cycle value counted does not exceed the configured maxUplinkdutycycle value.

[0396] In some embodiments, the specific instruction method for reporting information is:

[0397] Report content 1: Power class reporting. Each carrier reports power headroom (PH) together with the power class.

[0398] Report content 2: Power level change, only report the power level change (ΔP PowerClass ); also report for each carrier and PH together.

[0399] Optionally, based on triggering a PHR reporting indication only when a power level fallback occurs, the corresponding change amount for the corresponding code point only includes the situation corresponding to the power level fallback. Based on different situations and terminal implementation methods, the power level fallback can be a step-by-step fallback method, such as PC2 fallback to PC3, or a step-by-step fallback method, such as PC1.5 directly fallback to PC3.

[0400] For the case where the reported code point only includes the fallback power level change, the terminal capability level supported by Table 4-1, Table 4-2, and Table 4-3 is up to PC1.5 (29dBm), and the terminal capability level supported by Table 5 is up to PC1 (31dBm).

[0401] As shown in Tables 4-1, 4-2, 4-3, and 5, when the terminal at PC2 falls back to PC3, the MAC-CE corresponding to the PHR report carries the code point 01 corresponding to the power level change. The defined table can be used to look up the fallback power level and determine that the power level reported by the terminal has a 3dB change.

[0402] Optionally, based on the occurrence of power level fallback or power level recovery, a PHR reporting indication is triggered, and the corresponding code point corresponding to the corresponding change amount considers the support of both power level fallback and power level recovery. Based on different situations and terminal implementation methods, power level fallback can be a step-by-step fallback method, such as PC2 falls back to PC3, or a step-by-step fallback method. For example, PC1.5 falls back directly to PC3. Accordingly, power level recovery can be a step-by-step recovery method, such as PC3 recovers to PC2, or a step-by-step recovery method, such as PC3 recovers directly to PC1.5.

[0403] As shown in Table 6, Table 7-1, and Table 7-2, when a terminal on PC 2 falls back to PC 3, the MAC-CE corresponding to the PHR report carries the code point 03, corresponding to the power level change. The defined table shows that the fallback power level corresponds to a -3dB change in the power level reported by the terminal. When a terminal on PC 3 returns to PC 2, the MAC-CE corresponding to the PHR report carries the code point 01, corresponding to the power level change. The defined table shows that the fallback power level corresponds to a 3dB change in the power level reported by the terminal.

[0404] Reporting content three: optional reporting evaluation period starting point T and time length L.

[0405] In some embodiments, the evaluation period starting point T may be a first starting time.

[0406] In some embodiments, the time length L may be a first duration.

[0407] Reporting method:

[0408] Optionally, the evaluation period of each carrier is consistent, and the reported value is applied to each carrier.

[0409] Optionally, the evaluation period of each carrier is different, and each carrier is reported independently together with the PH corresponding to each carrier.

[0410] Start Time:

[0411] 1)SFN=0.

[0412] 2) Starting from SFN=0 and passing through the offset offset.

[0413] length:

[0414] 1) If the granularity X of the predefined / configured duration is X=100ms and the reported duration Y is Y=3, then the corresponding reported duration is 300ms.

[0415] 2) Report the absolute value / mapped value based on the reporting time. For example, if the reporting time is in the corresponding mapping interval, such as 300ms is in the predefined interval 3 (corresponding to 300-400ms), then the mapping value 3 corresponding to interval 3 is reported.

[0416] Optionally, it is defined as selecting to report from a set of optional values.

[0417] Report content 4: Simultaneously report the estimated duration of the power level or power level change, which may include:

[0418] Start time predefined or reported: unit is time slot / frame:

[0419] 1) PHR reporting time;

[0420] 2) The starting point of the evaluation cycle; (valid when reporting content 3 is defined)

[0421] 3) Starting from SFN=0, the predefined or configured granularity K is used as the reference point. The specific starting point can be configured by the network. For example, if it is M, it starts at M*K. It can also be determined by other methods. For example, the starting point is determined by the PHR reporting time. If the PHR reporting time is between reference points i and i+1, it can start at i*K or (i+1)*K. It is similarly determined by the PUSCH transmission time.

[0422] 4) PUSCH transmission time.

[0423] Duration length reporting:

[0424] 1) If the granularity X of the predefined / configured duration is X=100ms and the reported duration Y is Y=3, then the corresponding reported duration is 300ms;

[0425] 2) Report the absolute value / mapped value based on the reporting time. For example, if the reporting time is in the corresponding mapping interval, such as 300ms is in the predefined interval 3 (corresponding to 300-400ms), then the mapping value 3 corresponding to interval 3 is reported;

[0426] 3) Defined as a set of optional values ​​to be reported;

[0427] In some embodiments, the duration estimate may be a first duration.

[0428] In some embodiments, the duration length may be the duration of the first duration.

[0429] It can be understood that the above examples of 100ms, 200ms, and 300ms are all illustrative examples, and the present disclosure does not limit them.

[0430] In some embodiments, when the terminal's transmission duty cycle exceeds the maximum transmission duty cycle (maxDutyCycle) capability and the PC changes, the network cannot determine the maximum transmit power (P) actually used by the terminal to report the corresponding carrier. CMAX,f, ) corresponds to the actual terminal power level, so it is necessary to determine the reported P CMAX,f, Rules that apply:

[0431] Optionally, the terminal power level remains unchanged and reports ΔP PowerClass Therefore, the MPR table corresponding to the MPR still corresponds to the power class configured by the terminal.

[0432] Optionally, the terminal power level remains unchanged and reports ΔP PowerClass , use the MPR table corresponding to the changed power level to calculate the configured transmission power.

[0433] In some embodiments, the MPR tables may be, for example, Table 2 and Table 3. Table 2 is the MPR table corresponding to PC2, and Table 3 is the MPR table corresponding to PC3.

[0434] The embodiments of the present disclosure further provide an apparatus for implementing any of the above methods. For example, an apparatus is provided, comprising units or modules for implementing each step performed by a terminal in any of the above methods. For another example, another apparatus is provided, comprising units or modules for implementing each step performed by a network device (e.g., an access network device, a core network function node, a core network device, etc.) in any of the above methods.

[0435] It should be understood that the division of the various units or modules in the above device is merely a division of logical functions. In actual implementation, they may be fully or partially integrated into a physical entity, or they may be physically separated. In addition, the units or modules in the device may be implemented in the form of a processor calling software: for example, the device includes a processor, the processor is connected to a memory, and the memory stores instructions. The processor calls the instructions stored in the memory to implement any of the above methods or implement the functions of the various units or modules of the above device, wherein the processor is, for example, a general-purpose processor, such as a central processing unit (CPU) or a microprocessor, and the memory is a memory within the device or a memory outside the device. Alternatively, the units or modules in the device can be implemented in the form of hardware circuits, and the functions of some or all of the units or modules can be realized by designing the hardware circuits. The above-mentioned hardware circuits can be understood as one or more processors; for example, in one implementation, the above-mentioned hardware circuit is an application-specific integrated circuit (ASIC), and the functions of some or all of the above units or modules are realized by designing the logical relationship of the components in the circuit; for example, in another implementation, the above-mentioned hardware circuit can be realized by a programmable logic device (PLD), taking a field programmable gate array (FPGA) as an example, which can include a large number of logic gate circuits, and the connection relationship between the logic gate circuits is configured by configuring the configuration file, thereby realizing the functions of some or all of the above units or modules. All units or modules of the above devices can be realized in the form of software called by the processor, or in the form of hardware circuits, or in part by software called by the processor, and the rest by hardware circuits.

[0436] In the embodiments of the present disclosure, the processor is a circuit with signal processing capabilities. In one implementation, the processor can be a circuit with instruction reading and execution capabilities, such as a CPU, a microprocessor, a graphics processing unit (GPU) (which can be understood as a microprocessor), or a digital signal processor (DSP); in another implementation, the processor can implement certain functions through the logical relationship of the hardware circuit. The logical relationship of the above-mentioned hardware circuit is fixed or reconfigurable. For example, the processor is a hardware circuit implemented by an application-specific integrated circuit (ASIC) or a programmable logic device (PLD), such as an FPGA. In a reconfigurable hardware circuit, the process of the processor loading a configuration document and implementing the hardware circuit configuration can be understood as the process of the processor loading instructions to implement the functions of some or all of the above units or modules. In addition, it can also be a hardware circuit designed for artificial intelligence, which can be understood as an ASIC, such as a neural network processing unit (NPU), a tensor processing unit (TPU), a deep learning processing unit (DPU), etc.

[0437] Figure 6a is a schematic diagram of the structure of a terminal proposed in an embodiment of the present disclosure. As shown in Figure 6a, terminal 6100 may include a transceiver module 6101. In some embodiments, the transceiver module is configured to transmit first information, which indicates the terminal's full power mode corresponding to different power levels. Optionally, the transceiver module is configured to perform at least one of the communication steps S2101 and S2102, such as sending and / or receiving, performed by terminal 101 in any of the above methods, and will not be further described here.

[0438] Figure 6b is a schematic diagram of the structure of a network device proposed in an embodiment of the present disclosure. As shown in Figure 6b, network device 6200 may include a transceiver module 6201. Transceiver module 6201 is configured to receive first information indicating a full-power mode for a terminal corresponding to different power levels. Optionally, the transceiver module is configured to perform at least one of the communication steps S2101 and S2102, such as sending and / or receiving, performed by terminal 101 in any of the above methods, and will not be further described here.

[0439] In some embodiments, the transceiver module may include a transmitting module and / or a receiving module, and the transmitting module and the receiving module may be separate or integrated. Optionally, the transceiver module may be interchangeable with the transceiver.

[0440] Figure 7a is a schematic diagram of the structure of a communication device 7100 proposed in an embodiment of the present disclosure. Communication device 7100 can be a network device, such as an access network device or a core network device, or a terminal, such as a user equipment. It can also be a chip, chip system, or processor that supports a network device in implementing any of the above methods, or a chip, chip system, or processor that supports a terminal in implementing any of the above methods. Communication device 7100 can be used to implement the methods described in the above method embodiments. For details, please refer to the description of the above method embodiments.

[0441] As shown in Figure 7a, the communication device 7100 includes one or more processors 7101. The processor 7101 can be a general-purpose processor or a dedicated processor, for example, a baseband processor or a central processing unit. The baseband processor can be used to process communication protocols and communication data, and the central processing unit can be used to control the communication device (such as a base station, baseband chip, terminal device, terminal device chip, DU or CU, etc.), execute programs, and process program data. The communication device 7100 is used to perform any of the above methods.

[0442] In some embodiments, the communication device 7100 further includes one or more memories 7102 for storing instructions. Optionally, all or part of the memories 7102 may be located outside the communication device 7100.

[0443] In some embodiments, the communication device 7100 further includes one or more transceivers 7103. When the communication device 7100 includes one or more transceivers 7103, the transceiver 7103 performs at least one of the communication steps S2101 and S2102, such as sending and / or receiving, in the above method, and the processor 7101 performs the other steps.

[0444] In some embodiments, a transceiver may include a receiver and / or a transmitter. The receiver and transmitter may be separate or integrated. Optionally, the terms transceiver, transceiver unit, transceiver, and transceiver circuit may be used interchangeably; the terms transmitter, transmitting unit, transmitter, and transmitting circuit may be used interchangeably; and the terms receiver, receiving unit, receiver, and receiving circuit may be used interchangeably.

[0445] In some embodiments, the communication device 7100 may include one or more interface circuits 7104. Optionally, the interface circuit 7104 is connected to the memory 7102. The interface circuit 7104 may be configured to receive signals from the memory 7102 or other devices, and may be configured to send signals to the memory 7102 or other devices. For example, the interface circuit 7104 may read instructions stored in the memory 7102 and send the instructions to the processor 7101.

[0446] The communication device 7100 described in the above embodiment may be a network device or a terminal, but the scope of the communication device 7100 described in the present disclosure is not limited thereto, and the structure of the communication device 7100 may not be limited by FIG. 7a. The communication device may be an independent device or may be part of a larger device. For example, the communication device may be: 1) an independent integrated circuit IC, or a chip, or a chip system or subsystem; (2) a collection of one or more ICs, optionally, the above IC collection may also include a storage component for storing data or programs; (3) an ASIC, such as a modem; (4) a module that can be embedded in other devices; (5) a receiver, a terminal device, an intelligent terminal device, a cellular phone, a wireless device, a handheld device, a mobile unit, an in-vehicle device, a network device, a cloud device, an artificial intelligence device, etc.; (6) others, etc.

[0447] FIG7 b is a schematic diagram of the structure of a chip 7200 according to an embodiment of the present disclosure. If the communication device 7100 can be a chip or a chip system, reference can be made to the schematic diagram of the structure of the chip 7200 shown in FIG7 b , but the present disclosure is not limited thereto.

[0448] The chip 7200 includes one or more processors 7201 , and the chip 7200 is configured to execute any of the above methods.

[0449] In some embodiments, the chip 7200 further includes one or more interface circuits 7202. Optionally, the interface circuit 7202 is connected to the memory 7203. The interface circuit 7202 can be used to receive signals from the memory 7203 or other devices, and can be used to send signals to the memory 7203 or other devices. For example, the interface circuit 7202 can read instructions stored in the memory 7203 and send the instructions to the processor 7201.

[0450] In some embodiments, the interface circuit 7202 executes at least one of the communication steps S2101 and S2102 such as sending and / or receiving in the above method, and the processor 7201 executes at least one of the other steps S2101 and S2102.

[0451] In some embodiments, terms such as interface circuit, interface, transceiver pin, and transceiver may be used interchangeably.

[0452] In some embodiments, the chip 7200 further includes one or more memories 7203 for storing instructions. Alternatively, all or part of the memories 7203 may be located outside the chip 7200.

[0453] The present disclosure also proposes a storage medium having instructions stored thereon. When the instructions are executed on the communication device 7100, the communication device 7100 executes any of the above methods. Optionally, the storage medium is an electronic storage medium. Optionally, the storage medium is a computer-readable storage medium, but is not limited thereto and may also be a storage medium readable by other devices. Optionally, the storage medium may be a non-transitory storage medium, but is not limited thereto and may also be a temporary storage medium.

[0454] The present disclosure also provides a program product, which, when executed by the communication device 7100, enables the communication device 7100 to perform any of the above methods. Optionally, the program product is a computer program product.

[0455] The present disclosure also proposes a computer program, which, when executed on a computer, causes the computer to perform any one of the above methods.

Claims

1. A communication method, characterized in that: The method comprises: Sending first information, where the first information is used to indicate a power level, and the first information is sent via a power headroom report PHR.

2. The method according to claim 1, characterized in that The sending of the first information includes: If at least one of the following conditions is met, the first message is sent; The power level falls back to a first power level, where the first power level is lower than a second power level, where the second power level is a power level defined by the terminal and / or initially reported by the terminal; The power level is restored.

3. The method according to claim 2, characterized in that The power level fallback is determined by: The uplink transmission duty cycle corresponding to the physical uplink shared channel PUSCH sent by the terminal is greater than a first threshold corresponding to the current power level, and the power level fallback is determined, wherein different power levels correspond to different first thresholds.

4. The method according to claim 2 or 3, characterized in that: The power level recovery is determined by at least one of the following methods: The terminal starts a next evaluation cycle and determines that the power level is restored; The uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is less than or equal to the second threshold, and it is determined that the power level is restored.

5. The method according to claim 4, characterized in that The terminal starts a next evaluation cycle, and the determining that the power level is restored includes: The power level is restored to the power level defined by the terminal and / or initially reported by the terminal.

6. The method according to any one of claims 1 to 5, characterized in that: The first information includes at least one of the following: The first power level after the power level falls back; The third power level after the power level is restored; The power level change of the terminal; an evaluation period of the terminal; A first duration corresponding to at least one of the first power level and the third power level, wherein the first duration is used to represent an estimated duration of at least one of the first power level and the third power level.

7. The method according to claim 6, characterized in that The evaluation period includes a first starting time, and the first starting time is the starting time of the evaluation period; The first starting time includes at least one of the following: The time when the system frame number SFN is 0; The time corresponding to the SFN being 0 after the offset offset.

8. The method according to claim 6 or 7, characterized in that: The evaluation period includes a first duration, and the first duration is the duration of the evaluation period; The first duration is expressed in at least one of the following ways: The first duration is represented by a quantity based on a first granularity, wherein the first granularity corresponds to a second duration; The first duration is represented based on a first value, wherein the first value corresponds to a first duration interval, the first duration interval is a duration range of a preset evaluation period, the first duration is within the duration range, and the first duration is represented by the duration range; The first duration is represented based on a second value, wherein the second value corresponds to a preset evaluation cycle duration.

9. The method according to any one of claims 6 to 8, characterized in that: The first duration includes a second starting time; The second starting time includes at least one of the following: The sending time of the PHR; The first starting time corresponding to the evaluation period; A moment determined based on a first reference point and a second granularity, wherein the first reference point is a moment corresponding to SFN equal to 0, and the second granularity corresponds to a third duration; A moment determined based on a second reference point, wherein the second reference point is a reference point adjacent to the moment of sending the PHR among reference points obtained by dividing the evaluation period based on a third granularity, and the third granularity corresponds to a fourth duration; The transmission time of PUSCH.

10. The method according to claim 9, characterized in that The second starting time includes a time determined based on the first reference point and the number of second granularities; the method further includes: Second information is sent, where the second information is used to indicate the amount of the second granularity.

11. The method according to any one of claims 6 to 10, characterized in that: The first duration includes a fifth duration; The fifth duration is represented by at least one of the following methods: A quantity based on a third granularity represents the fifth duration, wherein the third granularity corresponds to a sixth duration; The fifth duration is represented based on a third value, wherein the third value corresponds to a second duration interval, the second duration interval is a duration range of a preset power level, the fifth duration is within the duration range, and the fifth duration is represented by the duration range; The fifth duration is represented based on a fourth value, wherein the fourth value corresponds to a preset power level duration.

12. The method according to any one of claims 1 to 11, characterized in that: The first information includes the maximum output power of the terminal, and the maximum output power is determined based on the first output power, the power change and the maximum power attenuation MPR, wherein the first output power is determined based on the second power level, the power change and the MPR are determined based on the second power level, or the power change and the MPR are determined based on a third power level.

13. A communication method, characterized in that: The method comprises: First information is received, where the first information is used for a power level, and the first information is sent via a power headroom report (PHR).

14. The method according to claim 13, characterized in that The first information is generated when at least one of the following conditions is met: The power level falls back to a first power level, where the first power level is lower than a second power level, where the second power level is a power level defined by the terminal and / or initially reported by the terminal; The power level is restored.

15. The method according to claim 14, characterized in that The power level fallback is determined by: The uplink transmission duty cycle corresponding to the physical uplink shared channel PUSCH sent by the terminal is greater than a first threshold corresponding to the current power level, and the power level fallback is determined, wherein different power levels correspond to different first thresholds.

16. The method according to claim 14 or 15, characterized in that The power level recovery is determined by at least one of the following methods: The terminal starts a next evaluation cycle and determines that the power level is restored; The uplink transmission duty cycle corresponding to the PUSCH sent by the terminal is less than or equal to the second threshold, and it is determined that the power level is restored.

17. The method according to claim 16, characterized in that The terminal starts a next evaluation cycle, and the determining that the power level is restored includes: The power level is restored to the power level defined by the terminal and / or initially reported by the terminal.

18. The method according to any one of claims 13 to 17, characterized in that: The first information includes at least one of the following: The first power level after the power level falls back; The third power level after the power level is restored; The power level change of the terminal; an evaluation period of the terminal; A first duration corresponding to at least one of the first power level and the third power level, wherein the first duration is used to represent an estimated duration of at least one of the first power level and the third power level.

19. The method according to claim 18, characterized in that The evaluation period includes a first starting time, and the first starting time is the starting time of the evaluation period; The first starting time includes at least one of the following: The time when the system frame number SFN is 0; The time corresponding to the SFN being 0 after the offset offset.

20. The method according to claim 18 or 19, characterized in that The evaluation period includes a first duration, and the first duration is the duration of the evaluation period; The first duration is expressed in at least one of the following ways: The first duration is represented by a quantity based on a first granularity, wherein the first granularity corresponds to a second duration; The first duration is represented based on a first value, wherein the first value corresponds to a first duration interval, the first duration interval is a duration range of a preset evaluation period, the first duration is within the duration range, and the first duration is represented by the duration range; The first duration is represented based on a second value, wherein the second value corresponds to a preset evaluation cycle duration.

21. The method according to any one of claims 18 to 20, characterized in that: The first duration includes a second starting time; The second starting time includes at least one of the following: The sending time of the PHR; The first starting time corresponding to the evaluation period; A moment determined based on a first reference point and a second granularity, wherein the first reference point is a moment corresponding to SFN equal to 0, and the second granularity corresponds to a third duration; A time determined based on a second reference point, wherein the second reference point is obtained by dividing the evaluation period based on a third granularity. Among the reference points, a reference point adjacent to the moment of sending the PHR, the third granularity corresponds to a fourth duration; The transmission time of PUSCH.

22. The method according to claim 21, characterized in that The second starting time includes a time determined based on the first reference point and the number of second granularities; the method further includes: Second information is received, where the second information is used to indicate the amount of second granularity.

23. The method according to any one of claims 18 to 22, characterized in that: The first duration includes a fifth duration; The fifth duration is represented by at least one of the following methods: A quantity based on a third granularity represents the fifth duration, wherein the third granularity corresponds to a sixth duration; The fifth duration is represented based on a third value, wherein the third value corresponds to a second duration interval, the second duration interval is a duration range of a preset power level, the fifth duration is within the duration range, and the fifth duration is represented by the duration range; The fifth duration is represented based on a fourth value, wherein the fourth value corresponds to a preset power level duration.

24. The method according to any one of claims 13 to 23, characterized in that: The first information includes the maximum output power of the terminal, and the maximum output power is determined based on the first output power, the power change and the maximum power attenuation MPR, wherein the first output power is determined based on the second power level, the power change and the MPR are determined based on the second power level, or the power change and the MPR are determined based on a third power level.

25. A communication method, characterized in that: The method comprises: The terminal sends first information to the network device, where the first information is used for the power level and the first information is sent via a power headroom report PHR.

26. A terminal, characterized in that: include: Transceiver module; The transceiver module is used to send first information, where the first information is used for power level, and the first information is sent via a power headroom report PHR.

27. A network device, characterized in that: include: Transceiver module; The transceiver module is used to receive first information, where the first information is used for power level, and the first information is sent via a power headroom report PHR.

28. A terminal, characterized in that: include: one or more processors; The terminal is used to execute the communication method according to any one of claims 1 to 12.

29. A network device, characterized in that: include: one or more processors; Wherein, the network device is used to execute the communication method described in any one of claims 13-24.

30. A communication system, characterized in that: It comprises a terminal and a network device, wherein the terminal is configured to implement the communication method according to any one of claims 1 to 12, and the network device is configured to implement the communication method according to any one of claims 13 to 24.

31. A storage medium storing instructions, characterized in that: When the instruction is executed on a communication device, the communication device is caused to execute the communication method according to any one of claims 1-12 or 13-24.

Citation Information

Patent Citations

  • Information transmission method and device, and terminal

    CN110720241A

  • Method and apparatus for adjusting terminal power level, and computer storage medium

    CN111543092A

  • Method for reporting power headroom, method for acquiring power headroom report and related equipment

    CN113676991A

  • Power headroom report (PHR) reporting determination

    US20210204227A1