Series-parallel manufacturing system unit construction method based on multi-dimensional process similarity

Through the analytic hierarchy process and improved genetic algorithm, the characteristics of parts, personnel and equipment are combined to realize the multi-dimensional process similarity division of the hybrid manufacturing system, which solves the problems of unreasonable resource allocation and unbalanced production lines, and improves resource utilization and production efficiency. , Promote the intelligent and flexible development of manufacturing industry.

CN118780529APending Publication Date: 2024-10-15UNIV OF ELECTRONICS SCI & TECH OF CHINA
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410814331.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-24
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing hybrid manufacturing system is difficult to reasonably allocate parts, personnel and equipment resources in a multi-variety and batch production environment, resulting in unbalanced production lines, low resource utilization, and serious waste of equipment resources.

Method used

The Analytical Hierarchy Process and improved genetic algorithm are used to combine the characteristics of parts, personnel and equipment. Through hierarchical structure division and fitness function optimization, multi-dimensional similarity division of resources and unit construction are achieved to ensure production line balance and resource utilization. of maximization.

Benefits of technology

It improves the production efficiency and resource utilization efficiency of the hybrid manufacturing system, solves the problems in traditional methods that the clustering results are deviated from actual production requirements, the production load balance adjustment is difficult to realize, and the equipment resources are wasted, and promotes the development of manufacturing industry towards intelligence and flexibility. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118780529A_ABST
    Figure CN118780529A_ABST
Patent Text Reader

Abstract

The invention discloses a hybrid manufacturing system unit construction method based on multi-dimensional process similarity, and the method comprises the steps: firstly obtaining related production resources of a workshop, and building a workshop production model which comprises production order information, workshop equipment information, workshop production unit information and worker information; performing similarity division on the parts according to the characteristics by using an analytic hierarchy process to obtain different part clusters; part characteristics, worker characteristics and equipment characteristics are combined by utilizing an improved genetic algorithm, unit construction and division of a manufacturing system are realized, and linear balance production is realized while the maximum resource utilization rate is ensured. Aiming at the three problems that a clustering result is separated from actual production requirements, production load balance adjustment is difficult to realize and equipment resources are seriously wasted in a traditional assembly workshop, part-based difficulty classification is obtained by using an analytic hierarchy process, and then construction and division of units are obtained by using an improved genetic algorithm; the unit construction problem of the series-parallel manufacturing system is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of workshop manufacturing systems, and specifically to a method for constructing a hybrid manufacturing system unit based on multi-dimensional process similarity. Background Art

[0002] In today's global manufacturing industry, with the accelerated development of market demand diversification and personalized trends, traditional large-scale batch production has gradually failed to meet the market's demand for fast delivery and customized products. In this context, hybrid manufacturing systems have received more and more attention as a new type of production method. Hybrid manufacturing systems have the advantages of flexible production and high resource utilization, and can effectively respond to changes in market demand. Existing manufacturing units can already achieve two production methods. One is that each unit independently completes the complete production process of a product, and the other is that the units are connected in series to form assembly line production. These two production methods are interspersed on the same production line to achieve hybrid production, which can solve the low equipment utilization rate while improving the robustness of the workshop. However, there are two major problems with this production method at present. First, the existing research on reconfigurable manufacturing theory mainly focuses on the reconstruction of static production tasks, without considering the characteristics of flexibility, dynamics and reliability; second, once many manufacturing units in the unit manufacturing system are built, it will be very difficult to update resources on this basis, and it cannot adapt to the current production characteristics of multiple varieties and variable batches.

[0003] Unit construction is the process of establishing a manufacturing unit from scratch. It needs to go through the process from completely decentralized and independent production tasks and manufacturing equipment, to the preliminary construction of task and equipment sets through cluster analysis, and finally to find the manufacturing unit division that meets production needs. However, the traditional unit construction method has the following three main problems in the above process. First, the existing clustering method based on process similarity relies solely on the process route to establish the correspondence between tasks and equipment, which easily leads to clustering results that are out of touch with actual production requirements; second, each unit operates independently, making it difficult to achieve balanced adjustment of production load and inefficient resource utilization; third, equipment is usually customized for a certain unit, making it difficult to share equipment, resulting in serious waste of equipment resources.

[0004] In the above context, the present invention utilizes hierarchical analysis method and improved genetic algorithm (GA) to organically combine the three important factors affecting workshop production: parts, personnel and equipment, to realize multi-dimensional process similarity division and unit construction, which can effectively improve the production efficiency and resource utilization efficiency of the hybrid manufacturing system, and promote the manufacturing industry to move towards intelligent and flexible development. Summary of the invention

[0005] The purpose of the present invention is to propose a method for constructing a hybrid manufacturing system unit based on multi-dimensional process similarity to address the problem that existing manufacturing workshops are unable to reasonably allocate and optimize the three manufacturing resources of parts, personnel and equipment in a multi-variety and variable batch production environment, so as to achieve production line balance and maximize resource utilization.

[0006] In order to solve the above technical problems, the present invention first obtains workshop-related production resources and establishes a workshop production model, which includes production order information, workshop equipment information, workshop production unit information and worker information; uses the hierarchical analysis method to divide the parts according to the similarity of the features to obtain different parts clusters; uses the improved genetic (GA) algorithm to combine the three characteristics of the parts, the characteristics of the workers and the characteristics of the equipment to realize the unit construction and division of the manufacturing system, ensuring the maximum resource utilization while achieving line balanced production. Therefore, the technical solution of the present invention is: a method for constructing a hybrid manufacturing system unit based on multi-dimensional process similarity, the method comprising:

[0007] Step 1: Workshop model construction;

[0008] N production units are arranged in sequence beside two conveyor belts. Different equipment is installed in the unit for different types of processing according to order requirements. At the same time, each unit can only accommodate one worker. Before the task starts, relevant information about workshop production is collected, including:

[0009] Related information of part P: There is a batch of specific parts that need to be processed, and each part may have different processing difficulty and time required;

[0010] Information about worker W: There are n workers in total, each of whom operates a unit. Each worker has a different proficiency S for different equipment, which will affect the processing time.

[0011] Information about equipment E: Different equipment is deployed in each unit, and each equipment is suitable for processing a specific type of parts;

[0012] Information about processing difficulty D: Each part has different processing difficulty;

[0013] Step 2: Use the analytic hierarchy process to classify the parts into different levels of difficulty;

[0014] Step 2.1: First, establish a hierarchical structure based on the obtained resource elements;

[0015] The base layer is the solution layer, including: the whole machine frame, movement board, power board, key board, and other parts; the middle layer is the standard layer, including: size, equipment action, material properties, connection method; the top layer is the target layer, which is the difficulty of part processing;

[0016] Step 2.2: Based on the information of the parts to be processed, the characteristics of the parts are abstracted into factors and divided into four types: size, assembly action difficulty coefficient, material properties, and connection method. The assembly actions are classified by difficulty coefficient. The higher the difficulty coefficient, the more difficult the action is to assemble.

[0017] Step 2.3: Set up a judgment matrix for each level of factors;

[0018] First, a reference table is established. The reference table is used to determine the scores corresponding to the relative importance of adjacent factors. The judgment matrix between the factors in step 2.2 is obtained based on the reference table. The judgment matrix represents the relative importance of the factors.

[0019] Step 2.4: consistency check;

[0020] The formula of consistency ratio CR is as follows:

[0021]

[0022] Among them, λ is the maximum characteristic root in the judgment matrix obtained in step 2.3, n is a non-zero characteristic root in the judgment matrix obtained in step 2.3, and RI is the random consistency index; passing the consistency test means relative trust in the part difficulty processing table to ensure the scientificity and accuracy of the decision; setting a threshold to detect whether the judgment matrix passes the consistency test, if not, return to step 2.2;

[0023] Step 2.5: Use the arithmetic mean method to calculate the weight of each factor in the judgment matrix; provide quantitative indicators for the subsequent construction of the parts-equipment processing table;

[0024] Step 3: Construct a hybrid manufacturing system unit;

[0025] Step 3.1: Associate different processing resources;

[0026] Associate parts and equipment to obtain the processing difficulty coefficient of each part;

[0027] Associate workers and equipment to get each worker's proficiency in different equipment;

[0028] Step 3.2: Define the objective function;

[0029] 1) The total processing time is shortest: the total time required to complete the processing of all parts should be the shortest;

[0030] 2) Equipment proficiency matching: High-difficulty parts are processed by workers with high proficiency in the corresponding equipment. The relevant thresholds are used to determine whether the parts have a high processing difficulty coefficient and whether the workers have a high proficiency in the equipment;

[0031] Step 3.3: Fitness function definition;

[0032] 1) Processing time fitness function f t (x):

[0033] For part p i , the time required to process the part is obtained through historical processing data; the total processing time T pwe is the sum of the processing time of all parts, and the fitness is the reciprocal of the total processing time, that is:

[0034]

[0035] 2) Proficiency matching fitness function f skill (x):

[0036] For each part p i , find the worker w assigned to it j and equipment k , use proficiency score S we To evaluate the fit; difficult parts should get higher fitness scores in the hands of highly skilled workers; the formula is as follows:

[0037]

[0038] Among them, n is the number of units, which is also the number of workers, and s i Represents the proficiency of workers in the current unit on the equipment, d i Represents the difficulty of assembling the part. The larger the value is when the two are multiplied, the higher the fitness is.

[0039] 3) The method for calculating comprehensive fitness is:

[0040] f(x)=α×f t (x)+β×f skill (x)

[0041] Where α and β are weight coefficients used to adjust the importance between the two objectives;

[0042] Step 3.4: Use the cross-compiled solution to calculate the comprehensive fitness function;

[0043] After the algorithm is finished, a set of solutions that are closest to line-balanced production and load balancing while meeting order requirements is obtained, which means that the unit construction is completed.

[0044] Furthermore, the specific method of step 3.4 is:

[0045] Step 3.4.1: Set parameters: Determine the population size, maximum number of iterations, crossover rate, and mutation rate parameters based on experience;

[0046] Step 3.4.2: Algorithm initialization: Generate initial population: Use chaos strategy to generate initial population, each individual in the population represents a possible solution for part processing;

[0047] Step 3.4.3: Calculate the comprehensive fitness: Use the comprehensive fitness formula in the pre-defined step 3.2 to calculate the comprehensive fitness of each individual;

[0048] Step 3.4.4: Crossover operation: two-segment crossover based on part similarity;

[0049] Step 3.4.5: Mutation operation: Randomly mutate individuals to increase the diversity of the population;

[0050] Step 3.4.6: Select operation: Since crossover always exchanges the worst node, you can directly compare the values ​​before and after the crossover and take the optimal solution; for mutation operation, if a mutation occurs on this node, you need to compare the calculation results of the comprehensive fitness function before and after the mutation, and select the better individuals to retain;

[0051] Step 3.4.7: Termination condition: The algorithm terminates when the preset maximum number of iterations is reached or the comprehensive fitness of the solution converges to the set threshold;

[0052] Furthermore, the specific steps of step 3.4.2 are as follows:

[0053] First, add all current orders of all types to the 12 units in order, and allocate the number of production units according to the proportion of the order quantity. Then, randomly assign the 12 workers to the 12 units as one individual.

[0054] Secondly, each unit contains different processes of different orders, and each process corresponds to a part. A1 to A7 represent all the processing processes of order A. According to the historical average of the processing time of each process, the process is evenly inserted into each production unit. If the processing time of A1 is similar to the sum of the processing time of A2A3, A1 is inserted into unit 1 and A2A3 is inserted into unit 2. The result is determined according to all the processes and the number of units. The method is as follows:

[0055] First calculate the processing time of all processes of a certain order, and then divide it by the number of units that can be used to obtain the average processing time t per unit. ave , and then fill the processes into each unit in sequence, while ensuring that the processing time required for the filled processes is equal to t ave The error is the smallest, and the situation where there is no process to be done in the last or last few units or the process does not fill the unit is ignored;

[0056] Then, on this basis, the following mapping function is used to initialize a large-scale population. The method is as follows: first, a 12-dimensional vector x0 is randomly generated, and each component of the vector is between 0 and 1; then the following mapping function is used to generate N vectors; the mapping function is as follows:

[0057] x i+1 =μ×x i ·(1-x i )

[0058] Among them, μ represents the function coefficient determined according to the actual situation, x i is the individual before mapping, x i+1 is the individual after mapping;

[0059] Finally, x i+1 Each component of is divided into 12 units according to its size.

[0060] The present invention aims to solve the three problems of traditional assembly workshops, namely, clustering results are divorced from actual production requirements, production load balancing adjustment is difficult to achieve, and equipment resources are seriously wasted. By using the hierarchical analysis method to obtain difficulty classification based on parts, and then using an improved genetic algorithm (GA) to obtain unit construction and division, the unit construction problem of the hybrid manufacturing system is solved. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] Figure 1 Abstract illustration for workshop production.

[0062] Figure 2 It is a part level analysis diagram.

[0063] Figure 3 Initialize the graph for the population.

[0064] Figure 4 This is the first cross diagram.

[0065] Figure 5 This is the second cross diagram.

[0066] Figure 6 This is a diagram of the variation mode.

[0067] Figure 7 The overall flow chart of the algorithm.

[0068] Figure 8 Solve the difficulty of parts assembly using the hierarchical analysis method.

[0069] Fig. 9 Improved genetic algorithm for the second layer. DETAILED DESCRIPTION

[0070] The implementation of the present invention comprises the following steps:

[0071] Step 1: Workshop model construction. The specific workshop production environment involved in the present invention is as follows: Figure 1 shown.

[0072] In the figure, 12 production units are arranged in sequence beside two conveyor belts. Different equipment can be installed in the unit for different types of processing according to order requirements. At the same time, each unit can only accommodate one worker. Before the task begins, we need to collect relevant information about the workshop production, including

[0073] Parts (P): There is a specific batch of parts that need to be processed, and each part may have different processing difficulty and time required.

[0074] Workers (W): There are 12 workers in total, each operating one unit. Each worker has different proficiency (S) on different equipment, which affects the processing time.

[0075] Equipment (E): Different equipment can be deployed in each cell. Each equipment is suitable for processing a specific type of parts.

[0076] Processing difficulty (D): Each part has different processing difficulty.

[0077] Step 2: After building the basic model of the workshop and obtaining the resource elements required for production, use the hierarchical analysis method to divide the parts into difficulty levels.

[0078] Step 2.1: First, establish a hierarchical structure based on the obtained resource elements. Figure 1 shown.

[0079] Step 2.2: According to Figure 1 The features of the parts are abstracted from the processing parts information and divided into four types, as shown in Table 1.

[0080] Table 1 Quantitative dimensions of parts

[0081]

[0082] As shown in Table 1, four features are added to the assembly parts, among which the assembly actions are classified by difficulty coefficient, as shown in Table 2. The higher the difficulty coefficient, the more difficult the action is to assemble.

[0083] Table 2 Assembly action difficulty coefficient

[0084] Basic Actions Difficulty Raise your hand 1 Crawl 1 Grip 1 Moving Objects 2 Letting go 1 Hold 3 Rotate 2 Insertion / installation 2 Connect / unplug 1 Paste 3 Interspersed 3 Trapped 2 Press Fit 3 Visual inspection 1 Label Scan 1 fixed 2

[0085] Step 2.3: Establish a judgment matrix for each level of factors. For each pair of factors, establish a judgment matrix to characterize the relative importance of the factors. At the same time, in order to quantify the judgment, introduce an importance reference table, namely Table 3.

[0086] Table 3 Importance reference table

[0087] Scale meaning 1 Indicates that two factors are equally important. 3 Indicates that one factor is slightly more important than the other factor. 5 Indicates that one factor is significantly more important than the other factor when compared with the other factor. 7 Indicates that one factor is more important than the other. 9 Indicates that one factor is extremely more important than the other. 2,4,6,8 The median of the above two adjacent judgments reciprocal If the scale of A compared to B is 3, then B is 1 / 3 compared to A.

[0088] According to Table 3, the judgment matrix is ​​obtained, as shown in Table 4

[0089] Table 4 Judgment Matrix

[0090] size Assembly Action Material properties Connection size 1 3 4 2 Assembly Action 1 / 3 1 2 1 / 3 Material properties 1 / 4 1 / 2 1 1 / 4 Connection 1 / 2 3 4 1

[0091] Step 2.4: Consistency test: Calculate the judgment matrix, judge the consistency of the matrix, and judge it through the consistency index. The formula of the consistency ratio CR is shown in formula 1.

[0092]

[0093] Among them, λ is the largest characteristic root; n is the only non-zero characteristic root; RI is the random consistency index, which can be found from the corresponding table. It is generally believed that when it is less than 0.1, the judgment matrix passes the consistency test.

[0094] Step 2.5: Use the arithmetic mean method to calculate the weights of each indicator in the judgment matrix. The results are shown in Table 5.

[0095] Table 5 Final weight index

[0096] size 1.801775899 Assembly Action 0.568174771 Material Characteristics 0.347343199 Connection 1.282706131

[0097] Step 3: In the unit hybrid manufacturing system, assembly personnel are assigned to each unit and play a vital role in the assembly process. Therefore, on the basis of the similarity division of parts, parts and personnel are associated through equipment, and the second-level algorithm is used to realize the unit construction and division of the unit hybrid manufacturing system. When performing the second-level algorithm, three important problems need to be solved. First, since it is more complicated to associate equipment, personnel and parts, it is a multi-dimensional problem; second, the solution obtained by the algorithm needs to reserve sufficient space for the subsequent dynamic reconstruction scheduling; third, in the hybrid manufacturing system, its production efficiency is often constrained by bottleneck processes and equipment resources. When searching the solution space, points with special areas (i.e., bottleneck processes) need to be explored in detail.

[0098] In view of the above problems, the present invention intends to use an improved genetic algorithm (GA) to obtain the optimal solution. Genetic algorithms are suitable for multivariable, highly nonlinear and complex optimization problems. They have good global search capabilities and use a population-based search to avoid falling into local optimal solutions. However, the search process of the genetic algorithm requires a large amount of computing resources and time. The selection, encoding, design of the fitness function and parameter setting of the problem require relatively rich data support. The results of the genetic algorithm are highly affected by the initial values ​​and algorithm parameters, and the parameters need to be adjusted and optimized to ensure convergence and search capabilities.

[0099] The production environment mentioned in this invention is limited in terms of resource constraints, only the worker resources and the order of process processing are restricted. The processes and steps involved in the production within and between units are different, and the generated initial solution greatly affects the convergence speed and convergence effect of the algorithm. Therefore, on this basis, according to the parts processing difficulty classification calculated by the hierarchical analysis method, the original SAGA algorithm is improved, and a population initialization strategy based on the chaos strategy and a two-stage crossover genetic algorithm with interchangeable processing levels are proposed. The steps are as follows:

[0100] Step 3.1: Associate different processing resources

[0101] 1) Parts-Equipment Association

[0102] Parts with high difficulty require longer processing time, especially in the hands of workers with low proficiency. Therefore, the present invention obtains the processing difficulty coefficient of each part based on the final weight index obtained in step 2. The calculation method is as follows:

[0103] Each part's size S, assembly action AA, material property MP, and connection method C have a quantitative value, as shown in Table 1. The quantitative standards have been listed. The four are normalized and multiplied by the corresponding weight coefficients to get the final weight coefficient. In order to make the result easier to read, the result is multiplied by the coefficient A. The coefficient A ensures that the final processing difficulty result is within 10. The calculation of the processing difficulty D is shown as follows:

[0104] D=(S*S Q +AA*AA Q +MP*MP Q +C*C Q )*A

[0105] The values ​​with subscripts are the corresponding coefficient weights, which are obtained from Table 5. The final difficulty coefficient can be shown in Table 6, and then it is matched with the required equipment.

[0106] Table 6 Parts-Processing Equipment Table

[0107] Part number / processing equipment 1 2 3 4 5 6 7 8 1 4 2 3 3 1 4 3 5 4 6 3 7 1

[0108] In Table 6, the columns represent the processed parts, the rows represent the processing equipment, and the places filled with numbers represent the processing difficulty of the processing equipment required for the parts.

[0109] 2) Worker-Equipment Association

[0110] Worker proficiency (S): Each worker has a proficiency score for each piece of equipment, which affects how quickly they can process parts using that equipment. The proficiency of each worker for different equipment is shown in Table 4.

[0111] Table 7 Personnel-Processing Equipment Table

[0112] Personnel / Processing Equipment 1 2 3 4 5 6 7 8 1 2 5 2 6 3 4 6 6 2 2 5 5 5 2 4 3 5 3 3 3 1 5 4 4 2 2 4 6 5 4 2 0 4 6 2 5 4 2 5 2 6 5 5 6 6 5 2 6 2 6 4 2 5 7 3 2 3 1 6 4 5 3 8 6 5 4 2 5 4 6 2 9 4 2 5 2 6 5 5 6 10 5 2 6 2 6 4 2 5 1 1 3 2 3 1 6 4 5 3 12 6 5 4 2 5 4 6 2

[0113] The columns represent workers, the rows represent equipment, and the values ​​represent proficiency, with 1 being the lowest and 6 being the highest.

[0114] Step 3.2: Define the objective function

[0115] 1) Shortest total processing time: The total time required to complete the processing of all parts should be the shortest.

[0116] 2) Equipment proficiency matching: High-difficulty parts should be processed by workers with higher proficiency in the corresponding equipment.

[0117] Step 3.3: Fitness function definition

[0118] 1) Processing time fitness function f t (x):

[0119] For each part p i , find the worker w assigned to it j and equipment k , calculate the time T required to process the part pwe The total processing time is the sum of the processing time of all parts, and the fitness is the reciprocal of the total time, that is,

[0120]

[0121] 2) Proficiency matching fitness function f skill (x):

[0122] For each part p i , find the worker w assigned to it j and equipment k , use proficiency score S we To evaluate the fit. High-difficulty parts should get higher fitness scores in the hands of highly skilled workers. The formula is as follows:

[0123]

[0124] Where n is the number of units, which is also the number of workers, s i Represents the proficiency of workers in the current unit with the equipment (there may be more than one equipment), d i Represents the difficulty of assembling the part. The larger the value is when the two are multiplied, the higher the fitness is.

[0125] 3) Comprehensive fitness function:

[0126] f(x)=α×f t (x)+β×f skill (x)

[0127] Where α and β are weight coefficients used to adjust the importance between the two objectives.

[0128] Step 3.4: Algorithm implementation

[0129] 1) Set parameters: Determine algorithm parameters such as population size, maximum number of iterations, crossover rate, mutation rate, etc. based on experience.

[0130] 2) Algorithm initialization: Generate the initial population: Use the chaos strategy to generate the initial population. Each individual in the population represents a possible solution for part processing. The specific steps are as follows:

[0131] First, add all current orders of all types to the 12 units in order, allocate the number of production units according to the proportion of the order quantity, and then randomly assign the 12 workers to the 12 units.

[0132] Secondly, each unit contains different processes of different orders, and each process corresponds to a part. A1 to A7 represent all the processing processes of order A. According to the historical average of the processing time of each process, the process is inserted into each production unit as evenly as possible. If the processing time of A1 is similar to the sum of the processing time of A2A3, A1 is inserted into unit 1 and A2A3 is inserted into unit 2. The actual result is determined by all the processes and the number of units. The method is as follows:

[0133] First calculate the processing time of all processes of a certain order, and then divide it by the number of units that can be used to obtain the average processing time t per unit. ave , and then fill the processes into each unit in sequence, while ensuring that the processing time required for the filled processes is equal to t ave The error is the smallest. Since this production line uses many processes and the processing time of each process is also short, the situation where the last one or several units have no process to do or the process does not fill the unit can be ignored.

[0134] Then, based on this, we use Logistic chaotic mapping to initialize a large population. The method is as follows: first, we randomly generate a 12-dimensional vector x0, where each component of the vector is between 0 and 1; then we use Logistic mapping to generate N vectors. The Logistic mapping is as follows:

[0135] x i+1 =μ×x i ·(1-x i )

[0136] Finally, x i Each component of can be transferred to the value interval [1,12] of the variable according to the size carrier.

[0137] 3) Calculate comprehensive fitness: Use the pre-defined fitness formula to calculate the comprehensive fitness of each individual.

[0138] 4) Crossover operation: two-segment crossover based on part similarity

[0139] In order to ensure the diversity of solutions, the first crossover is performed within the same fragment, such as Figure 2 As shown, the numbers in the units are worker numbers. Each worker has different proficiency in different equipment. When performing the first segment crossover, the processing time of each unit in different orders is first normalized. This ensures that the units of different orders can also be cross-linked. The method is as follows:

[0140] First, workers in the two units with the longest normalized processing time in the segment are selected for exchange. This is repeated in each iteration until a better solution is found. Figure 4 shown.

[0141] Before the second cross operation, all the processing parts are classified into assembly levels. In order to ensure the flexibility of the hybrid manufacturing system, assembly priorities are set for the assembly parts. Without strong priority constraints, two different assembly parts can be processed at the same time. For example, the movement board is directly installed on the base with a priority of 0, and the WIFI module is installed on the movement board. The priority is 1, but when installing the WIFI module, there is no need to pay attention to whether the movement board has been installed on the base, that is, the WIFI module is only responsible for its upper level, but the level that is not an integer must be installed in a strict hierarchical order, such as the keypad (level 0.5) must be installed after the movement board. This installation level feature reflects the flexibility of the hybrid manufacturing system in the assembly process.

[0142] Assembly level (AL), if it is directly installed on the TV base, the level is set to 0, if it is installed above level 0, the level is set to 1, and so on. Although some modules are not directly installed on level 0, they still need to be installed next to it after level 0, and the level is set to 0.5.

[0143] A second intra-segment crossover operation is performed on the parts whose processing sequence can be exchanged, such as Figure 3 As shown. A3 and A4 belong to the same assembly level, and the processing order is variable. The original processing order is A1A2A3A4A5A6A7, and now it becomes A1A2A4A3A5A6A7. Due to the different proficiency of different workers, the fitness function calculation results after the crossover will also be different, thus obtaining the second crossover result.

[0144] 5) Mutation operation: Randomly mutate individuals to increase the diversity of the population. Mutation methods such as Figure 4 As shown in the figure, the distribution of a certain order is randomly mutated. For example, originally A1 is produced by unit 1, A2A4 are produced by unit 2, and now process A2 is transferred to unit 1. In order to ensure that the line balance production will not be seriously damaged before and after the mutation, only one process is exchanged each time. Figure 6 shown.

[0145] 6) Selection operation: Since crossover exchanges the worst node, you can directly compare the values ​​before and after the crossover and take the optimal solution; for mutation operation, if a mutation occurs at this node, you need to compare the fitness function calculation results before and after the mutation, and select the better individuals to retain.

[0146] 7) Termination conditions

[0147] Check termination conditions: The algorithm terminates when the preset maximum number of iterations is reached or the fitness of the solution converges to the set threshold.

[0148] After the algorithm is finished, a set of solutions is finally obtained that are closest to line-balanced production and load balancing while meeting order requirements, which means that the unit construction is completed.

Claims

1. A method for constructing a hybrid manufacturing system unit based on multi-dimensional process similarity, the method comprising: Step 1: Workshop model construction; N production units are arranged in sequence beside two conveyor belts. Different equipment is installed in the unit for different types of processing according to order requirements. At the same time, each unit can only accommodate one worker. Before the task starts, relevant information about workshop production is collected, including: Information about part P: There is a batch of specific parts that need to be processed, and each part may have different processing difficulty and time required; Information about worker W: There are n workers in total, each of whom operates a unit. Each worker has a different proficiency S for different equipment, which will affect the processing time. Information about equipment E: Different equipment is deployed in each unit, and each equipment is suitable for processing a specific type of parts; Information about processing difficulty D: Each part has different processing difficulty; Step 2: Use the analytic hierarchy process to classify the parts into different levels of difficulty; Step 2.1: First, establish a hierarchical structure based on the obtained resource elements; The base layer is the solution layer, including: the whole machine frame, movement board, power board, key board, and other parts; the middle layer is the standard layer, including: size, equipment action, material properties, connection method; the top layer is the target layer, which is the difficulty of part processing; Step 2.2: Based on the information of the parts to be processed, the characteristics of the parts are abstracted into factors and divided into four types: size, assembly action difficulty coefficient, material properties, and connection method. The assembly actions are classified by difficulty coefficient. The higher the difficulty coefficient, the more difficult the action is to assemble. Step 2.3: Set up a judgment matrix for each level of factors; First, a reference table is established. The reference table is used to determine the scores corresponding to the relative importance of adjacent factors. The judgment matrix between the factors in step 2.2 is obtained based on the reference table. The judgment matrix represents the relative importance of the factors. Step 2.4: consistency check; The formula of consistency ratio CR is as follows: Among them, λ is the maximum characteristic root in the judgment matrix obtained in step 2.3, n is a non-zero characteristic root in the judgment matrix obtained in step 2.3, and RI is the random consistency index; passing the consistency test means relative trust in the part difficulty processing table to ensure the scientificity and accuracy of the decision; setting a threshold to detect whether the judgment matrix passes the consistency test, if not, return to step 2.2; Step 2.5: Use the arithmetic mean method to calculate the weight of each factor in the judgment matrix; provide quantitative indicators for the subsequent construction of the parts-equipment processing table; Step 3: Construct a hybrid manufacturing system unit; Step 3.1: Associate different processing resources; Associate parts and equipment to obtain the processing difficulty coefficient of each part; Associate workers and equipment to get each worker's proficiency in different equipment; Step 3.2: Define the objective function; 1) The total processing time is shortest: the total time required to complete the processing of all parts should be the shortest; 2) Equipment proficiency matching: High-difficulty parts are processed by workers with high proficiency in the corresponding equipment. The relevant thresholds are used to determine whether the parts have a high processing difficulty coefficient and whether the workers have a high proficiency in the equipment; Step 3.3: Fitness function definition; 1) Processing time fitness function f t (x): For part p i , the time required to process the part is obtained through historical processing data; the total processing time T pwe is the sum of the processing time of all parts, and the fitness is the reciprocal of the total processing time, that is: 2) Proficiency matching fitness function f skill (x): For each part p i , find the worker w assigned to it j and equipment k , use proficiency score S we To evaluate the fit; difficult parts should get higher fitness scores in the hands of highly skilled workers; the formula is as follows: Among them, n is the number of units, which is also the number of workers, and s i Represents the proficiency of workers in the current unit on the equipment, d i Represents the difficulty of assembling the part. The larger the value is when the two are multiplied, the higher the fitness is. 3) The method for calculating comprehensive fitness is: f(x)=α×f t (x)+β×f skill (x) Where α and β are weight coefficients used to adjust the importance between the two objectives; Step 3.4: Use the cross-compiled solution to calculate the comprehensive fitness function; After the algorithm is finished, a set of solutions that are closest to line-balanced production and load balancing while meeting order requirements is obtained, which means that the unit construction is completed.

2. A method for constructing a hybrid manufacturing system unit based on multi-dimensional process similarity according to claim 1, characterized in that: The specific method of step 3.4 is: Step 3.4.1: Set parameters: Determine the population size, maximum number of iterations, crossover rate, and mutation rate parameters based on experience; Step 3.4.2: Algorithm initialization: Generate initial population: Use chaos strategy to generate initial population, each individual in the population represents a possible solution for part processing; Step 3.4.3: Calculate the comprehensive fitness: Use the comprehensive fitness formula in the pre-defined step 3.2 to calculate the comprehensive fitness of each individual; Step 3.4.4: Crossover operation: two-segment crossover based on part similarity; Step 3.4.5: Mutation operation: Randomly mutate individuals to increase the diversity of the population; Step 3.4.6: Select operation: Since crossover always exchanges the worst node, you can directly compare the values ​​before and after the crossover and take the optimal solution; for mutation operation, if a mutation occurs on this node, you need to compare the calculation results of the comprehensive fitness function before and after the mutation, and select the better individuals to retain; Step 3.4.7: Termination condition: The algorithm terminates when the preset maximum number of iterations is reached or the comprehensive fitness of the solution converges to the set threshold.

3. A method for constructing a hybrid manufacturing system unit based on multi-dimensional process similarity according to claim 1, characterized in that: The specific steps of step 3.4.2 are as follows: First, add all current orders of all types to the 12 units in order, and allocate the number of production units according to the proportion of the order quantity. Then, randomly assign the 12 workers to the 12 units as one individual. Secondly, there are different processes for different orders in each unit, and each process corresponds to a part. A1 to A7 represent all the processing processes of order A. According to the historical mean of the processing time of each process, the processes are evenly inserted into each production unit. The result is determined by all the processes and the number of units. The method is as follows: First calculate the processing time of all processes of a certain order, and then divide it by the number of units that can be used to obtain the average processing time t per unit. ave , and then fill the processes into each unit in sequence, while ensuring that the processing time required for the filled processes is t ave The error is the smallest, and the situation where there is no process to be done in the last or last few units or the process does not fill the unit is ignored; Then, on this basis, the following mapping function is used to initialize a large-scale population. The method is as follows: first, a 12-dimensional vector x0 is randomly generated, and each component of the vector is between 0 and 1; then the following mapping function is used to generate N vectors; the mapping function is as follows: x i+1 =μ×x i ·(1-x i ) Among them, μ represents the function coefficient determined according to the actual situation, x i is the individual before mapping, x i+1 is the individual after mapping; Finally, x i+1 Each component of is divided into 12 units according to its size.

Citation Information

Cited By

  • Production line scheduling optimization method based on artificial intelligence

    CN121169006A