Performance evaluation method for multi-machine assembly line with line edge inventory

Calculate the repair rate and failure rate of equivalent machines through Markov chain and aggregation methods, and solve the problem of the inability to analyze the impact of line edge inventory on assembly line performance in the prior art, and realize the rapid and accurate performance evaluation of multi-machine assembly lines. Quantitative standards and decision-making basis.

CN119047985APending Publication Date: 2024-11-29NORTHEASTERN UNIV CHINA +1
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202410980225.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The existing performance evaluation methods cannot effectively analyze the impact of line edge inventory on assembly line performance, and the simulation method has problems such as model deployment difficulties and evaluation time-consuming.

Method used

Through the Markov chain, the system state transfer process consisting of line-side inventory and assembly machines is portrayed, the repair rate and failure rate of the equivalent machine are calculated, and the output rate of the assembly line and the product in production are calculated based on the aggregation method and iterative algorithm are updated. Levels and parts inventory levels.

Benefits of technology

It realizes rapid and precise quantification of the performance of multi-machine assembly lines, provides a decision-making basis for assembly line operation, reduces evaluation time and improves evaluation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119047985A_ABST
    Figure CN119047985A_ABST
Patent Text Reader

Abstract

The invention provides a multi-machine assembly line performance evaluation method with line edge inventory, and relates to the technical field of assembly line performance evaluation, the repair rate and failure rate of an equivalent machine equivalent by the line edge inventory and an assembly machine are calculated, and according to the repair rate and failure rate of the equivalent machine, based on an aggregation method and an iterative algorithm, the performance of the multi-machine assembly line is evaluated. According to the method, the fault rate of the forward aggregation, the fault rate of the backward aggregation, the repair rate of the forward aggregation and the repair rate of the backward aggregation of each equivalent machine on the assembly line are iteratively updated, so that the output rate, the work-in-process level of each equivalent machine and the part inventory level of each equivalent machine can be calculated on the basis. According to the technical scheme provided by the invention, key performance indexes such as the output rate, the product level and the part inventory level are quickly and accurately quantified, a technical means is provided for performance analysis of the multi-machine assembly line with line-side inventory, and a quantitative basis is provided for continuous improvement of subsequent system performance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of assembly line performance evaluation, and in particular to a multi-machine assembly line performance evaluation method with line-side inventory. Background Art

[0002] A manufacturing system is a complex system composed of machines and buffers in a specific topological structure, such as an assembly line. The assembly line is the most commonly used form of production organization in modern mass production and is widely used in the manufacturing process of new energy vehicles, household appliances, consumer electronics and other products. The assembly line is responsible for the assembly of parts and components, which is usually in the final stage of the product manufacturing process and is a key link in determining product performance and production capacity. Since the output capacity of the manufacturing system is limited by the random failures of the machines and the limited buffers, the coupling effect of the two makes the input-output relationship of the system show a nonlinear change relationship, making it difficult to accurately evaluate the output performance of the production system.

[0003] For the evaluation of manufacturing system performance, the operation process of the manufacturing system is first analyzed, that is, the operation rules and properties of the system are characterized, and then the system performance is quantified to provide a decision-making basis for lean design and continuous improvement of the manufacturing system. Common methods for evaluating the performance of manufacturing systems include simulation methods and analytical methods. The simulation method establishes a simulation model for the operation process of the manufacturing system, analyzes the system capacity through simulation experiments, or improves the system capacity through trial and error. The analytical method uses mathematical tools such as random processes to characterize the interactive relationship between material flow and machine status and buffer capacity, and quantifies system performance indicators based on machine and buffer characteristic parameters. Compared with simulation methods, analytical methods can quickly provide solutions to the same type of problems and reveal the operating mechanism of the system.

[0004] The analytical methods for performance evaluation include precise analytical methods and approximate analytical methods: 1) The precise analytical method is suitable for simple single-station or two-station manufacturing systems. It characterizes the system state transition process based on the Markov process, and then obtains the precise analytical expression of the performance index; 2) The approximate analytical method is suitable for more complex manufacturing systems. Based on the analytical results of simple manufacturing systems, the system performance indicators are approximately solved based on recursive iteration. There are mainly two methods: decomposition and aggregation.

[0005] For assembly lines, the output capacity of assembly lines is not only limited by equipment unreliability and limited buffering, but also affected by line-side inventory. However, existing performance evaluation analytical methods cannot analyze the impact of line-side inventory on assembly line performance. Although simulation methods can effectively analyze the performance of assembly lines with line-side inventory, there are problems such as difficulty in model deployment and long evaluation time. Summary of the invention

[0006] The existing performance evaluation analysis method cannot analyze the impact of line inventory on assembly line performance. Although the simulation method can effectively analyze the performance of assembly lines with line inventory, there are problems such as difficult model deployment and long evaluation time. The present invention provides a multi-machine assembly line performance evaluation method with line inventory, including:

[0007] Step 1: The state transition process of the system consisting of line-side inventory and assembly machines is characterized by a Markov chain, and the repair rate and failure rate of the equivalent machine are calculated. The equivalent machine is a machine equivalent to the line-side inventory and the assembly machine. The line-side inventory is used to store the parts to be assembled, and the assembly machine is used to install the parts on the work-in-progress.

[0008] Step 2: According to the repair rate and failure rate of the equivalent machines, based on the aggregation method and iterative algorithm, the forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line are iteratively updated to obtain the updated forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line;

[0009] Step 3: Based on the updated forward aggregate failure rate, backward aggregate failure rate, forward aggregate repair rate and backward aggregate repair rate of each equivalent machine in the assembly line, calculate the multi-machine assembly line output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine. The multi-machine assembly line output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine are used to provide quantitative standards and decision-making basis for cost reduction and efficiency improvement in the assembly line operation process.

[0010] Furthermore, step 1 specifically includes:

[0011] Step 1.1: Draw the state transition diagram of the system and construct the considerations based on the state transition diagram (s m ,S m )The system state transfer equilibrium equation of the inventory control strategy, the (s m ,S m ) The inventory control strategy is to set the number of parts in the line inventory to be less than the minimum threshold s m When the number of parts in the line inventory reaches the maximum threshold S m When , the parts replenishment system stops working, and the parts replenishment system is used to provide parts for the line side inventory; the system state transfer balance equation is:

[0012]

[0013]

[0014] Among them, (l m ,α m ) indicates the state of the system, l m Represents the mth line edge inventory L m The number of parts in , α m =1 means the parts replenishment system is line-side inventory L m Normal supply of parts, α m =0 means that the parts replenishment system stops as line side inventory L m Supply Parts, P m (l m ,α m ) represents the line inventory L m and assembly machine M m The system is in state (l m ,α m ), M m represents the mth assembly machine, P m (l m ,1) Characterize the line inventory L m and assembly machine M m The system is in line inventory L m The number of parts is l m And the parts supply system is line-side inventory L m The probability of a normal supply of parts, P m (l m ,0) represents the line side inventory L m and assembly machine M m The system is composed of line inventory L m The number of parts is l m And the parts replenishment system stops as line side inventory L m The probability of the state of supplying parts; γ m Indicates that the parts replenishment system at each moment is the line inventory L m The probability of supplying a part; p m For assembling machine M m Probability of being in working order;

[0015] Step 1.2: Consider (s m ,S m ) The system state transfer equilibrium equation of the inventory control strategy and the normalization equation of all states of the system are solved simultaneously to obtain the solution considering (s m ,S m ) The system state probability distribution of the inventory control strategy; the normalized equation of all states of the system is:

[0016]

[0017] The considerations(s m ,S m )The system state probability distribution of the inventory control strategy is:

[0018]

[0019]

[0020] in,

[0021] Step 1.3: Consider (s m ,S m ) The probability distribution of the system state of the inventory control strategy, the calculation of the equivalent machine The repair rate R m and failure rate P m , the equivalent machine The repair rate R m and failure rate P m for:

[0022] R m =γ m ,

[0023]

[0024] Among them, the equivalent machine represents the mth equivalent machine, R m represents the repair rate of the mth equivalent machine, P m represents the failure rate of the mth equivalent machine, P m (0,1) represents the line inventory L m and assembly machine M m The system is composed of line inventory L m The number of parts in is 0 and the parts replenishment system is line-side inventory L m The probability of a state in which parts are normally available.

[0025] Furthermore, step 2 specifically includes:

[0026] Step 2.1: Initialize according to the following formula:

[0027]

[0028]

[0029]

[0030] Where n represents the number of iterations, that is, the number of backward aggregation and forward aggregation; Represents an equivalent machine The failure rate of the nth forward aggregation; P1 is the equivalent machine failure rate; Represents an equivalent machine The failure rate of the nth backward aggregation; P M For equivalent machines failure rate; Represents an equivalent machine The repair rate of the nth forward aggregation; R1 is the equivalent machine The repair rate; For equivalent machines The repair rate of the nth backward aggregation; R M For equivalent machines The repair rate; Represents an equivalent machine The failure rate of the 0th forward aggregation; P m For equivalent machines The failure rate, Represents an equivalent machine The repair rate of the 0th forward aggregation; R m For equivalent machines The repair rate of m and R m By the equivalent machine The repair rate R m and failure rate P m The formula is calculated;

[0031] Among them, the equivalent machine represents the mth equivalent machine, the equivalent machine represents the first equivalent machine, the equivalent machine represents the Mth equivalent machine, and 1≤m≤M;

[0032] Step 2.2: Based on the initialized failure rate and repair rate, perform backward aggregation for all equivalent machines on the assembly line, and select the equivalent machines from the preset order of all equivalent machines on the assembly line. To the equivalent machine Updating the backward-aggregated failure rate and the backward-aggregated repair rate of each equivalent machine to obtain the updated backward-aggregated failure rate and the backward-aggregated repair rate of each equivalent machine on the assembly line after each iteration of backward aggregation;

[0033] Step 2.3: Based on the initialized failure rate and repair rate, perform forward aggregation for all equivalent machines on the assembly line, and select the equivalent machines from the preset order of all equivalent machines on the assembly line. To the equivalent machine The forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine are updated to obtain the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine on the assembly line after each iteration of the forward aggregation;

[0034] Step 2.4: Determine whether the updated backward aggregate failure rate and the backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine meet the convergence condition. If the updated backward aggregate failure rate and the backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine meet the convergence condition, the equivalent machine The failure rate of the nth backward aggregation as an equivalent machine The failure rate of backward aggregation Equivalent Machine The failure rate of the nth forward aggregation as an equivalent machine The failure rate of the forward aggregation Equivalent Machine The repair rate of the nth backward aggregation as an equivalent machine The repair rate of backward aggregation Equivalent Machine The repair rate of the nth forward aggregation as an equivalent machine The repair rate of forward aggregation Otherwise, return to step 2.2 until the updated backward aggregate failure rate and backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and forward aggregate repair rate of each equivalent machine meet the convergence condition;

[0035] Among them, the convergence condition is the equivalent machine The difference between the failure rate of the nth backward aggregation and the failure rate of the n+1th backward aggregation is less than the preset threshold, and the equivalent machine The difference between the failure rate of the nth forward aggregation and the failure rate of the n+1th forward aggregation is less than the preset threshold, and the equivalent machine The difference between the repair rate of the nth backward aggregation and the repair rate of the n+1th backward aggregation is less than the preset threshold, and the equivalent machine A difference between a repair rate of the nth forward aggregation and a repair rate of the (n+1)th forward aggregation is less than a preset threshold.

[0036] Furthermore, step 2.2 specifically includes:

[0037] According to the preset order of all equivalent machines on the assembly line, from back to front, for two adjacent equivalent machines, based on the initialized failure rate and repair rate, the equivalent machines are Equivalent Machine and buffer B m The two equivalent machine units are processed according to the equivalent machine The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the buffer B m capacity, and obtain the updated equivalent machine The backward aggregated failure rate and the backward aggregated repair rate of the equivalent machine are then iteratively updated for the backward aggregated failure rate and the backward aggregated repair rate of each equivalent machine on the assembly line. represents the m+1th equivalent machine, B m Represents the mth buffer.

[0038] Further, equivalent machines The backward aggregation failure rate and the backward aggregation repair rate are calculated and updated by the following formula:

[0039]

[0040]

[0041] in, Represents an equivalent machine The failure rate of the n+1th backward aggregation, P m Represents an equivalent machine The failure rate, R m Represents an equivalent machine The repair rate, Represents an equivalent machine The failure rate of the n+1th backward aggregation, Represents an equivalent machine The repair rate of the n+1th backward aggregation, Represents an equivalent machine The failure rate of the nth forward aggregation, Represents an equivalent machine The repair rate of the nth forward aggregation, N m Indicates the mth buffer B m The number of work in progress in; where Q2 is:

[0042]

[0043]

[0044]

[0045]

[0046]

[0047]

[0048]

[0049]

[0050]

[0051]

[0052] Among them, c1, c2, d1, d2, μ, Ω1, Ω2, Ω3, and Ω4 are parameters used to simplify the formula, and k is a summation formula parameter.

[0053] Furthermore, step 2.3 specifically includes:

[0054] According to the preset order of all equivalent machines on the assembly line, from front to back, for two adjacent equivalent machines, based on the initialized failure rate and repair rate, the equivalent machines are Equivalent Machine and buffer B m-1 Two equivalent machine units are composed of The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the buffer B m-1 capacity, and obtain the updated equivalent machine The forward aggregate failure rate and forward aggregate repair rate of the equivalent machine are then iteratively updated. represents the m-1th equivalent machine, B m-1 Indicates the m-1th buffer.

[0055] Further, equivalent machines The forward aggregation failure rate and forward aggregation repair rate are calculated and updated using the following formula:

[0056]

[0057]

[0058] in, Represents an equivalent machine The failure rate of the n+1th forward aggregation, P m Represents an equivalent machine The failure rate, R m Represents an equivalent machine The repair rate, Represents an equivalent machine The failure rate of the n+1th forward aggregation processing, Represents an equivalent machine The repair rate of the n+1th forward aggregation process, Represents an equivalent machine The failure rate of the n+1th backward aggregation processing, Represents an equivalent machine The repair rate of the n+1th backward aggregation process, Represents an equivalent machine The repair rate of the n+1th forward aggregation process, N m-1 Indicates the m-1th buffer B m-1 The number of work in progress in Q3 is:

[0059]

[0060]

[0061]

[0062]

[0063]

[0064]

[0065]

[0066]

[0067]

[0068]

[0069] Among them, g1, g2, h1, h2, θ, E, F, G, and H are parameters used to simplify the formula, and k is a summation formula parameter.

[0070] Furthermore, the multi-machine assembly line output rate PR in step 3 and the work-in-progress level of each equivalent machine and parts inventory levels for each equivalent machine Calculated by the following formula:

[0071]

[0072]

[0073]

[0074] in,

[0075]

[0076]

[0077]

[0078]

[0079]

[0080]

[0081]

[0082]

[0083]

[0084]

[0085]

[0086]

[0087] Among them, the equivalent machine represents the mth equivalent machine, the equivalent machine represents the first equivalent machine, the equivalent machine represents the Mth equivalent machine, equivalent machine represents the m+1th equivalent machine, Represents an equivalent machine Repair rate of forward aggregation; Represents an equivalent machine Failure rate of forward aggregation; Represents an equivalent machine The repair rate of backward aggregation; Represents an equivalent machine Failure rate of backward aggregation; Represents an equivalent machine Repair rate of forward aggregation; Represents an equivalent machine The repair rate of backward aggregation; Represents an equivalent machine Failure rate of backward aggregation; Represents an equivalent machine Failure rate of forward aggregation; N m represents the number of work-in-progress in the mth buffer; γm Indicates that the parts replenishment system at each moment is the line inventory L m The probability of supplying a part; p m For assembling machine M m The probability of being in working state; s m is the minimum threshold of the number of parts in the line inventory; S m is the maximum threshold of the number of parts in the line inventory, and k is the summation formula parameter.

[0088] The beneficial effects of adopting the above technical solution are:

[0089] The present invention provides a performance evaluation method for a multi-machine assembly line with line-side inventory. For a system composed of line-side inventory and assembly machines, the repair rate and failure rate of equivalent machines equivalent to the line-side inventory and the assembly machines are calculated. According to the repair rate and failure rate of the equivalent machines, based on an aggregation method and an iterative algorithm, the forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line are iteratively updated. Then, based on the updated forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line, the output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine can be calculated, providing quantitative standards and decision-making basis for cost reduction and efficiency improvement in the operation process of the assembly line. Compared with the prior art, the technical solution proposed by the present invention quickly and accurately quantifies key performance indicators such as the output rate, the work-in-process level and the parts inventory level, provides a technical means for performance analysis of a multi-machine assembly line with line-side inventory, and provides a quantitative basis for continuous improvement of subsequent system performance. BRIEF DESCRIPTION OF THE DRAWINGS

[0090] Figure 1 A schematic diagram of a multi-machine assembly line structure with line-side inventory in an embodiment of the present invention;

[0091] Figure 2 It is a schematic flow chart of a method for evaluating performance of a multi-machine assembly line with line-side inventory in an embodiment of the present invention;

[0092] Figure 3 :Consider(s m , S m ) Assembly station state transition diagram of inventory control strategy;

[0093] Figure 4 : Schematic diagram of equivalent process of assembly station;

[0094] Figure 5: Schematic diagram of the iterative process of the aggregation method, wherein Figure (a) is a schematic diagram of the backward aggregation iterative process, and Figure (b) is a schematic diagram of the forward aggregation iterative process. DETAILED DESCRIPTION

[0095] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0096] The present application provides a performance evaluation method for a multi-machine assembly line with line-side inventory, wherein the multi-machine assembly line consists of multiple assembly stations and a work-in-progress buffer, each assembly station may include an assembly machine, a line-side inventory and a parts replenishment system, combined with Figure 1 , where the line side inventory is used to store parts that are about to be assembled to the components to be assembled. Figure 1 In the figure, L1 represents the first line edge inventory, L2 represents the second line edge inventory, and L m represents the mth line-side inventory; the assembly machine is used to assemble the parts in the line-side inventory onto the components. Figure 1 It is represented by a rectangle, where M1 represents the first assembly machine, M2 represents the second assembly machine, and M m represents the mth assembly machine. The buffer includes an upstream buffer and a downstream buffer. The upstream buffer is used to store the work-in-progress that has been assembled at the upstream assembly station, and the downstream buffer is used to store the work-in-progress that has been assembled at the current assembly station. Figure 1 In the figure, circles are used to represent the first buffer, B1 represents the first buffer, B2 represents the second buffer, and B m Represents the mth buffer; Figure 1 The process in which the arrow points to the triangle represents the process of the parts replenishment system replenishing parts for the line side inventory. Figure 1 , the multi-machine assembly line takes the parts to be assembled as input. The first assembly machine assembles the parts in the first line-side inventory onto the parts to be assembled. After the assembly operation is completed, it is transported to the first buffer and the work-in-progress is obtained from the first buffer. The second assembly machine assembles the parts in the second line-side inventory onto the work-in-progress. After the assembly operation is completed, it is transported to the second buffer. The above operation is repeated until the last assembly station, which is the upstream assembly station for obtaining the finished product in the figure, obtains the work-in-progress from the m-1th buffer, and the mth assembly machine assembles the parts in the mth line-side inventory onto the work-in-progress to obtain the finished product output assembly line.

[0097] Among them, the line-side inventory adopts the (s,S) inventory control strategy to replenish parts. Specifically, when the number of parts in the line-side inventory is lower than the minimum threshold s, the parts replenishment system starts to produce parts. When the number of parts in the line-side inventory reaches the maximum threshold S, the parts replenishment system stops working.

[0098] Based on this, the present invention evaluates the performance of a multi-machine assembly line with line-side inventory by combining Figure 2 The present invention first initializes the assembly line parameters and the related parameters in the assembly line for subsequent calculations. Based on the initialization parameters, the steady-state probability distribution of the independent assembly station with line-side inventory is solved through the Markov chain, and then the independent assembly station with line-side inventory is equivalent to an independent machine, and the failure rate and repair rate of the independent machine are solved. Furthermore, the accurate performance evaluation index of the two-machine assembly line can be solved, based on which the performance evaluation index of the multi-machine assembly line can be calculated.

[0099] Based on the operation process of the above multi-machine assembly line, this application proposes the following assumptions when implementing a multi-machine assembly line performance evaluation method with line-side inventory:

[0100] (1) Assembly machine M m ,m=1,2,…,M means,M m represents the mth assembly machine, assembly machine M m The same and fixed assembly cycle can be understood as the time it takes for an assembly machine to complete the assembly of a work-in-progress or a component to be assembled. The time axis is segmented using the assembly cycle as the unit time.

[0101] (2) Assembly machine M m ,m=1,2,…,M,obeys the Bernoulli reliability model. At each moment, the assembly machine M m With p m The probability of being in working state is 1-p m For example, the first assembly machine M1 is in working state with probability p1 and in fault state with probability 1-p1, and the second assembly machine M2 is in working state with probability p2 and in fault state with probability 1-p2.

[0102] (3) Buffer B m ,m=1,2,…,M-1,means,B m Indicates the mth buffer, and the capacity of the buffer is N m Indicates that 0 <N m <∞. Buffer B m The number of work in process is expressed as n m To represent, 0≤n m ≤Nm .

[0103] (4) Line side inventory L m ,m=1,2,…,M,means,L m represents the mth line side inventory. Line side inventory L m Adopt (s m ,S m ) The inventory control strategy is line inventory L m Supplementary parts, of which s m represents the minimum threshold of the mth line inventory, S m represents the maximum threshold of the mth line inventory, and 0 m m , 0 m <∞. Line side inventory L m The number of parts in l m Indicates that 0≤l m ≤S m .

[0104] (5) The reliability parameter of the parts supply system is γ m ,m=1,2,…,M, Bernoulli distribution, that is, at each moment, γ m The probability of the line inventory L m Replenish a part. Based on the above theory, it can be calculated that the efficiency of the parts replenishment system is γ m , the efficiency of the assembly machine is p m Based on this, in order to ensure the normal operation of the assembly station, it is assumed that the efficiency of the parts supply system is greater than the efficiency of the assembly machine, that is, γ m >p m .

[0105] (6) At the beginning of each moment, if buffer B m ,m=1,2,…,M-1, the number of work-in-progress reaches the maximum value N m , assembly machine M m In working condition and machine M m+1 If the assembly operation cannot be completed, the assembly machine M m Therefore, this application assumes that the finished product inventory of the assembly line is infinite, so the last assembly machine M M It will not be in a blocked state.

[0106] (7) At the beginning of each moment, if buffer B m-1 ,m=2,3,…,the number of work-in-progress or line inventory L in M m The number of parts in is zero and the assembly machine M m In working state, the machine M m ​​​In a starving state. Among them, since the first assembly machine L1 has no upstream buffer, whether the first assembly machine M1 is in a starving state is only determined by the number of parts in the line inventory L1 and the number of parts to be assembled, and is not determined by the number of work-in-progress in the upstream buffer. When the number of parts in the line inventory L1 is zero, if the assembly machine M1 is in working condition, the machine M1 is in a starving state. Based on this, the present application assumes that the supply of parts to be assembled in the assembly line is unlimited, so that the assembly machine M1 will not be starved of parts to be assembled.

[0107] Based on the above assumptions, the present application provides a multi-machine assembly line performance evaluation method with line-side inventory, which may specifically include the following steps:

[0108] Step 1: Characterize the state transition process of the system through the Markov chain and calculate the equivalent machine The repair rate R m and failure rate P m .

[0109] Since the assembly machine M m It obeys the Bernoulli reliability model and is not affected by the control strategy. Therefore, the system state is determined by the parts level of the line inventory and the state of the parts replenishment system. Based on this, this application uses Markov chain to calculate the equivalent machine The repair rate R m and failure rate P m Calculation is performed, wherein this application uses (l m ,α m ) represents the state of the assembly station, using P m (l m ,α m ) indicates that the system is in state (l m ,α m ) probability. m ={0,1} represents the working state of the parts replenishment system, α m =1 means that the parts replenishment system supplies parts normally from the line side inventory, α m =0 means that the parts replenishment system stops supplying parts to the line side inventory. m (l m ,1)P m (l m ,0)

[0110] Based on this, the present application can be implemented through the following steps when implementing this step:

[0111] Step 1: Use Markov chains to characterize the state transition process of the system consisting of line inventory and assembly machines, and calculate the repair rate and failure rate of the equivalent machines.

[0112] The equivalent machine is a machine that is equivalent to a line-side inventory and an assembly machine, wherein the line-side inventory is used to store parts to be assembled, and the assembly machine is used to install the parts on the work-in-progress.

[0113] It should be noted that the assembly station mentioned in the previous article is a system consisting of line-side inventory and assembly machines in the steps.

[0114] Specifically, step 1 can be implemented through the following steps:

[0115] Step 1.1: Draw the state transition diagram of the system and construct the considerations based on the state transition diagram (s m ,S m )The system state transition equilibrium equation of the inventory control strategy.

[0116] Among them, the (s m ,S m ) The inventory control strategy is to set the number of parts in the line inventory to be less than the minimum threshold s m When the number of parts in the line inventory reaches the maximum threshold S m When the parts replenishment system stops working, the parts replenishment system is used to provide parts for line-side inventory.

[0117] Specifically, the state transition diagram is as follows Figure 3 , where the circular sum (0, 1) represents the state where the number of parts in the line-side inventory is 0 and the parts replenishment system is supplying parts to the line-side inventory normally, and the circular sum (s m +1, 0) represents the number of parts in the line inventory is s m +1 and the parts replenishment system stops supplying parts to the line side inventory normally. The circles and other numerical representations in the figure are the same. In the figure, the arrow pointing from the first circle to the second circle indicates that the state of the first circle is transferred to the state of the second circle, and the arrow pointing from the first circle to the first circle indicates that the state of the first circle is maintained.

[0118] Based on this, the considerations for construction (s m ,S m )The system state transfer equilibrium equation of the inventory control strategy is as follows:

[0119]

[0120]

[0121] It can also be expressed by the following formula:

[0122] P m (0,1)=(1-γ m ) m(0,1)+p m (1-c m )P m (1,1),

[0123] P m (1,1)=γ m P m (0,1)+[p m c m +(1-p m )(1-c m )]P m (1,1)+p m (1-c m )P m (2.1),

[0124] …

[0125] P m (s m ,1)=(1-p m )c m P m (s m -1,1)+[p m c m +(1-p m )(1-c m )]P m (s m ,1)

[0126] +p m (1-c m )P m (s m +1,1)+p m P m (s m +1.0),

[0127] P m (s m +1,1)=(1-p m )c m P m (s m ,1)+[p m c m +(1-p m )(1-c m )]P m (s m +1.1)

[0128] +p m (1-c m )P m (s m +2.1),

[0129] …

[0130] P m (S m -1,1)=(1-p m )γ m P m (S m -2,1)+[p m γ m +(1-p m )(1-γ m )]P m (S m -1,1),

[0131] P m (S m ,1)=(1-p m )γ m P m (S m -1,1)+(1-p m ) m (S m ,1),

[0132] P m (S m -1,0)=(1-p m ) m (S m -1,0)+p m P m (S m ,1),

[0133] …

[0134] P m (s m +1,0)=(1-p m )P(s m +1,0)+p m P m (s m +2,0).

[0135] Among them, (l m ,α m ) indicates the state of the system, l m Represents the mth line edge inventory L m The number of parts in α m =1 means the parts replenishment system is line-side inventory L m Normal supply of parts, α m =0 means that the parts replenishment system stops as line side inventory L m Supply Parts, P m (lm ,α m ) represents the line inventory L m and assembly machine M m The system is in state (l m ,α m ), M m represents the mth assembly machine, P m (l m ,1) Characterize the line inventory L m and assembly machine M m The system is composed of line inventory L m The number of parts is l m And the parts supply system is line-side inventory L m The probability of a normal supply of parts, P m (l m ,0) represents the line side inventory L m and assembly machine M m The system is in line inventory L m The number of parts is l m And the parts replenishment system stops as line side inventory L m The probability of the state of supplying parts; γ m Indicates that the parts replenishment system at each moment is the line inventory L m The probability of supplying a part; p m For assembling machine M m The probability of being in working order.

[0136] Among them, the line inventory L m where m=1,2,…,M; assembly machine M m where m=1,2,…,M; p m where m=1,2,…,M;γ m where m=1,2,…,M; l m Where m=1,2,…,M.

[0137] Step 1.2: Consider (s m ,S m ) The system state transfer equilibrium equation of the inventory control strategy and the normalization equation of all states of the system are solved simultaneously to obtain the solution considering (s m ,S m ) The probability distribution of the system state of the inventory control strategy; the normalized equation of all states of the system is:

[0138]

[0139] Based on this, we will consider (s m ,S m) The system state transfer equilibrium equation of the inventory control strategy and the normalization equation of all system states are solved simultaneously to obtain the solution considering (s m ,S m )The system state probability distribution of the inventory control strategy is specifically expressed by the following equation:

[0140]

[0141]

[0142] in,

[0143] Step 1.3: Consider (s m ,S m ) The probability distribution of the system state of the inventory control strategy, the calculation of the equivalent machine The repair rate R m and failure rate P m .

[0144] Among them, the present invention converts the line side inventory L m and assembly machine M m Equivalent to an independent machine, called an equivalent machine Combination Figure 4 , the line edge inventory L represented by the triangle on the left side of the figure m and the assembly machine M represented by the left box in the figure m Equivalent to an independent equivalent machine represented by the box on the right side of the figure Equivalent state diagram on the left to an equivalent machine The state diagram of the machine is defined as Ω = {U, D}, where U represents the equivalent machine Normal working state, D represents the equivalent machine The shutdown state, Figure 4 The probability that the U state points to the D state through the arrow is P m , that is, the failure rate P m , the probability that the D state points to the U state through the arrow is R m , which is the repair rate R m .

[0145] Based on this, the present invention is based on the above considerations (s m ,S m )The system state probability distribution of the inventory control strategy can be calculated to obtain the equivalent machine The repair rate R m and failure rate P m , the specific expression is as follows:

[0146] R m =γ m ,

[0147]

[0148] Among them, the equivalent machine represents the mth equivalent machine, then R m represents the repair rate of the mth equivalent machine, P m represents the failure rate of the mth equivalent machine, P m (0,1) represents the line inventory L m and assembly machine M m The system is in line inventory L m The number of parts in is 0 and the parts replenishment system is line-side inventory L m The probability of a state in which parts are normally available.

[0149] Furthermore, the present invention can be based on the repair rate R m and failure rate P m , calculate the output rate PR and average work-in-process level of the two machine assembly lines and average parts inventory levels The analytical expressions of performance indicators are as follows:

[0150] PR=e2[1-Q2(P1,R1,P2,R2,N1)],

[0151]

[0152] Among them, e2, β m , Q2(P1, R1, P2, R2, N1), a1, a2, b1, b2, σ, A, B, C, D are all parameters of the simplified formula, specifically expressed as:

[0153]

[0154] a1=P1+P2-P1P2-R1P2,

[0155] a2=P1+P2-P1P2-R2P1,

[0156] b1=R1+R2-R1R2-R2P1,

[0157] b2=R1+R2-R1R2-R1P2,

[0158]

[0159] A=P1R2a1a2b2(P2+b2),

[0160]

[0161]

[0162]

[0163] Among them, P1 represents the first equivalent machine The failure rate of R1 is the first equivalent machine The repair rate of P2 is the second equivalent machine The failure rate of the second equivalent machine The repair rate, N1 represents the capacity of the work-in-progress in the first buffer, and k is the parameter of the summation formula.

[0164] It should be noted that this part is for the assembly line of two equivalent machines, so m = 1, 2, and since the assembly line has only two equivalent machines, there is only one buffer B1, that is, the equivalent machine After assembly is completed, the product is placed in the first buffer B1, equivalent to the machine The finished product can be obtained by taking the work-in-progress from buffer B1 and assembling it, so there is no need for a second buffer.

[0165] Step 2: According to the repair rate and failure rate of the equivalent machines, based on the aggregation method and iterative algorithm, the forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line are iteratively updated to obtain the updated forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line.

[0166] It should be noted that when the assembly line contains multiple assembly stations, the number of system states will explode exponentially with the increase in the number of assembly machines and the number of buffers. In this case, the Markov chain model will encounter the problem of "dimensionality curse" during the modeling and solving process. Therefore, this application, based on the research on two-machine assembly lines, uses the aggregation method to approximate the production capacity of multi-machine assembly lines.

[0167] Among them, when implementing the aggregation method, multiple equivalent machines The assembly line is decomposed into two machines for calculation, and the impact of the blocking state on the system performance is considered. The assembly line is backward aggregated, considering the impact of starvation on system performance, and multiple equivalent machines are The assembly line is forward aggregated. Finally, this application uses forward aggregation and backward aggregation as a round of aggregation algorithm to perform forward aggregation and backward aggregation on multiple equivalent machines. The assembly line is iterated multiple times to make an approximate analysis of the production capacity of the multi-machine assembly line.

[0168] When performing the aggregation algorithm, for each assembly machine, the forward aggregation failure rate, the backward aggregation failure rate, the forward aggregation repair rate and the backward aggregation repair rate are configured to facilitate the subsequent backward aggregation and forward aggregation processing. At the same time, combined with the iterative algorithm, the present invention introduces in, Represents an equivalent machine Failure rate in the nth backward aggregation; Represents an equivalent machine The repair rate in the nth backward aggregation; Represents an equivalent machine Failure rate in the nth forward aggregation; Represents an equivalent machine The repair rate in the nth forward aggregation, based on this, step 2 in this application can be specifically implemented by the following steps:

[0169] Step 2.1: Initialize according to the following formula:

[0170]

[0171]

[0172]

[0173] Where n represents the number of iterations, that is, the number of backward aggregation and forward aggregation; Represents an equivalent machine The failure rate of the nth forward aggregation; P1 is the equivalent machine failure rate; Represents an equivalent machine The failure rate of the nth backward aggregation; P M For equivalent machines failure rate; Represents an equivalent machine The repair rate of the nth forward aggregation; R1 is the equivalent machine The repair rate; For equivalent machines The repair rate of the nth backward aggregation; R M For equivalent machines The repair rate; Represents an equivalent machine The failure rate of the 0th forward aggregation; P m For equivalent machines The failure rate, Represents an equivalent machine The repair rate of the 0th forward aggregation; R m For equivalent machines repair rate.

[0174] Where n = 0, 1, 2, ..., since m = 1 and m = M have been initialized before, m = 2, ..., M-1

[0175] Among them, P m and R m By the equivalent machine The repair rate R m and failure rate P m The formula is calculated, and according to the equivalent machine The repair rate R m and failure rate P m The formula can also calculate P1, P M , R1, R M Specifically, substitute m=1 into the repair rate R m The formula can be used to obtain R1, and m = 1 is substituted into the failure rate P m The formula can be used to obtain P1, and m = M is substituted into the repair rate R m The formula for R M , substitute m=M into the failure rate P m The formula can be used to obtain P M .

[0176] Among them, the equivalent machine represents the mth equivalent machine, the equivalent machine represents the first equivalent machine, the equivalent machine represents the Mth equivalent machine, and 1≤m≤M.

[0177] Step 2.2: Based on the initialized failure rate and repair rate, perform backward aggregation for all equivalent machines on the assembly line, and select the equivalent machines from the preset order of all equivalent machines on the assembly line. To the equivalent machine The backward aggregated failure rate and the backward aggregated repair rate of each equivalent machine are updated to obtain the updated backward aggregated failure rate and the backward aggregated repair rate of each equivalent machine on the assembly line after each iteration of backward aggregation.

[0178] Specifically, according to the preset order of all equivalent machines on the assembly line, from back to front, for two adjacent equivalent machines, based on the initialized failure rate and repair rate, the equivalent machines are Equivalent Machine and buffer B m The two equivalent machine units are processed according to the equivalent machine The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the buffer Bm capacity, and obtain the updated equivalent machine The backward aggregated failure rate and the backward aggregated repair rate of the equivalent machine are then iteratively updated for the backward aggregated failure rate and the backward aggregated repair rate of each equivalent machine on the assembly line. represents the m+1th equivalent machine, B m Represents the mth buffer.

[0179] In specific implementation, combined with Figure 5 (a), the present invention is from an equivalent machine Start aggregation, for equivalent machines Buffer B M-1 and equivalent machines Units composed of equivalent machines The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the equivalent machine The forward aggregate failure rate and forward aggregate repair rate, as well as the buffer B M-1 The capacity of the equivalent machine The failure rate and repair rate of backward aggregation are calculated in the same way as in the subsequent calculations.

[0180] in, Figure 5 In order to facilitate a better understanding of the backward aggregation usage data, in the equivalent machine f and b are added to the upper right corner of the symbol. f in the upper right corner is the calculation of the failure rate and repair rate of the forward aggregation of the equivalent machine, and b in the upper right corner is the calculation of the failure rate and repair rate of the backward aggregation of the equivalent machine; where, Represents an equivalent machine The failure rate of forward aggregation and the repair rate of forward aggregation, Represents an equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, Represents an equivalent machine The failure rate of forward aggregation and the repair rate of forward aggregation, Represents an equivalent machine The failure rate of forward aggregation and the repair rate of forward aggregation, Represents an equivalent machine The failure rate of forward aggregation and the repair rate of forward aggregation, Represents an equivalent machine The failure rate of forward aggregation and the repair rate of forward aggregation, Represents an equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation.

[0181] Among them, B M-1Indicates the M-1th buffer, B M-2 represents the M-2th buffer, B2 represents the second buffer, and B1 represents the first buffer.

[0182] It should be noted that Figure 5 It can be seen that the number of buffers is one less than the number of equivalent machines. Figure 5 The middle buffer is from B1 to B M-1 .

[0183] Figure 5 In the figure, the dashed box indicates that the calculation is performed on the unit consisting of two equivalent machines and a buffer in the dashed box, and the arrow indicates the calculation result. For example, the arrow points to express Represented by equivalent machine The forward aggregation failure rate and forward aggregation repair rate, as well as the efficiency of the machine The failure rate of backward aggregation and the repair rate of backward aggregation are obtained.

[0184] Based on the above calculation process, multiple iterations are performed, where the equivalent machine The update of the backward aggregation failure rate and the backward aggregation repair rate can be expressed by the following formula:

[0185]

[0186]

[0187] in, Represents an equivalent machine The failure rate of the n+1th backward aggregation, P m Represents an equivalent machine The failure rate, R m Represents an equivalent machine The repair rate, Represents an equivalent machine The failure rate of the n+1th backward aggregation, Represents an equivalent machine The repair rate of the n+1th backward aggregation, Represents an equivalent machine The failure rate of the nth forward aggregation, Represents an equivalent machine The repair rate of the nth forward aggregation, N m Indicates the mth buffer B m The number of work in progress in; where Q2 is:

[0188]

[0189]

[0190]

[0191]

[0192]

[0193]

[0194]

[0195]

[0196]

[0197]

[0198] Among them, c1, c2, d1, d2, μ, Ω1, Ω2, Ω3, and Ω4 are parameters used to simplify the formula, and k is a summation formula parameter.

[0199] It should be noted that the calculation method of Q2 in this step is similar to that of Q2 in step 1.3, and the same letters are used to represent it, but the calculation results are different.

[0200] Step 2.3: Based on the initialized failure rate and repair rate, perform forward aggregation for all equivalent machines on the assembly line, and select the equivalent machines from the preset order of all equivalent machines on the assembly line. To the equivalent machine The forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine are updated to obtain the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine on the assembly line after each iteration of the forward aggregation.

[0201] Specifically, according to the preset order of all equivalent machines on the assembly line, from front to back, for two adjacent equivalent machines, based on the initialized failure rate and repair rate, the equivalent machines are Equivalent Machine and buffer B m-1 Two equivalent machine units are composed of The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the buffer B m-1 capacity, and obtain the updated equivalent machine The forward aggregate failure rate and forward aggregate repair rate of the equivalent machine are then iteratively updated. represents the m-1th equivalent machine, B m-1 Indicates the m-1th buffer.

[0202] In specific implementation, combined with Figure 5 (b), the present invention is from an equivalent machine Start aggregation, for equivalent machines Equivalent Machine and buffer B1, through an equivalent machine The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate and repair rate of backward aggregation, as well as the capacity of buffer B1, give the equivalent machine The failure rate of forward aggregation and the repair rate of forward aggregation.

[0203] in, Figure 5 middle, Represents an equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, Represents an equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation. The explanations of other letters are the same as above.

[0204] Based on the above calculation process, multiple iterations are performed, where the equivalent machine The forward aggregation failure rate and forward aggregation repair rate are calculated and updated using the following formula:

[0205]

[0206]

[0207] in, Represents an equivalent machine The failure rate of the n+1th forward aggregation, P m Represents an equivalent machine The failure rate, R m Represents an equivalent machine The repair rate, Represents an equivalent machine The failure rate of the n+1th forward aggregation processing, Represents an equivalent machine The repair rate of the n+1th forward aggregation process, Represents an equivalent machine The failure rate of the n+1th backward aggregation processing, Represents an equivalent machine The repair rate of the n+1th backward aggregation process, Represents an equivalent machine The repair rate of the n+1th forward aggregation process, N m-1 Indicates the m-1th buffer B m-1 The number of work in progress in Q3 is:

[0208]

[0209]

[0210]

[0211]

[0212]

[0213]

[0214]

[0215]

[0216]

[0217]

[0218] Among them, g1, g2, h1, h2, θ, E, F, G, and H are parameters used to simplify the formula, and k is a summation formula parameter.

[0219] It should be noted that the calculation method of Q3 in this step is similar to that of Q2 in step 2.2, but different letters are used to represent the specific numerical values. In the specific implementation, the same letters can also be used to represent them.

[0220] Step 2.4: Determine whether the updated backward aggregate failure rate and the backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine meet the convergence condition. If the updated backward aggregate failure rate and the backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine meet the convergence condition, the equivalent machine The failure rate of the nth backward aggregation as an equivalent machine The failure rate of backward aggregation Equivalent Machine The failure rate of the nth forward aggregation as an equivalent machine The failure rate of the forward aggregation Equivalent Machine The repair rate of the nth backward aggregation as an equivalent machine The repair rate of backward aggregation Equivalent Machine The repair rate of the nth forward aggregation as an equivalent machine The repair rate of forward aggregation Otherwise, return to step 2.2 until the updated backward aggregate failure rate and backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and forward aggregate repair rate of each equivalent machine meet the convergence condition;

[0221] Among them, the convergence condition is the equivalent machine The difference between the failure rate of the nth backward aggregation and the failure rate of the n+1th backward aggregation is less than the preset threshold, and the equivalent machine The difference between the failure rate of the nth forward aggregation and the failure rate of the n+1th forward aggregation is less than the preset threshold, and the equivalent machine The difference between the repair rate of the nth backward aggregation and the repair rate of the n+1th backward aggregation is less than the preset threshold, and the equivalent machine A difference between a repair rate of the nth forward aggregation and a repair rate of the (n+1)th forward aggregation is less than a preset threshold.

[0222] The above convergence condition can be achieved by the following formula:

[0223]

[0224]

[0225] in, Represents an equivalent machine The failure rate of the n+1th backward aggregation, Represents an equivalent machine The failure rate of the nth backward aggregation, Represents an equivalent machine The difference between the failure rate of the nth backward aggregation and the failure rate of the n+1th backward aggregation; Represents an equivalent machine The failure rate of the n+1th forward aggregation; Represents an equivalent machine The failure rate of the nth forward aggregation, Represents an equivalent machine The difference between the failure rate of the nth forward aggregation and the failure rate of the n+1th forward aggregation; Represents an equivalent machine The repair rate of the n+1th backward aggregation, Represents an equivalent machine The repair rate of the nth backward aggregation, Represents an equivalent machine The difference between the repair rate of the nth backward aggregation and the repair rate of the n+1th backward aggregation; Represents an equivalent machine The repair rate of the n+1th forward aggregation; Represents an equivalent machine The repair rate of the nth forward aggregation, Represents an equivalent machine The difference between the repair rate of the nth forward aggregation and the repair rate of the n+1th forward aggregation.

[0226] Therefore, the preset threshold is 10 -6 , when the convergence condition is met, let

[0227] Step 3: Based on the updated forward aggregate failure rate, backward aggregate failure rate, forward aggregate repair rate and backward aggregate repair rate of each equivalent machine in the assembly line, calculate the multi-machine assembly line output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine. The multi-machine assembly line output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine are used to provide quantitative standards and decision-making basis for cost reduction and efficiency improvement in the assembly line operation process.

[0228] Specifically, it is calculated by the following formula:

[0229]

[0230]

[0231]

[0232] in,

[0233]

[0234]

[0235]

[0236]

[0237]

[0238]

[0239]

[0240]

[0241]

[0242]

[0243]

[0244]

[0245] Among them, the equivalent machine represents the mth equivalent machine, the equivalent machine represents the first equivalent machine, the equivalent machine represents the Mth equivalent machine, equivalent machine represents the m+1th equivalent machine, Represents an equivalent machine Repair rate of forward aggregation; Represents an equivalent machine Failure rate of forward aggregation; Represents an equivalent machine The repair rate of backward aggregation; Represents an equivalent machine Failure rate of backward aggregation; Represents an equivalent machine Repair rate of forward aggregation; Represents an equivalent machine The repair rate of backward aggregation; Represents an equivalent machine Failure rate of backward aggregation; Represents an equivalent machine Failure rate of forward aggregation; N m represents the number of work-in-progress in the mth buffer; γ m Indicates that the parts replenishment system at each moment is the line inventory L m The probability of supplying a part; p m For assembling machine M m The probability of being in working state; s m is the minimum threshold of the number of parts in the line inventory; S m is the maximum threshold of the number of parts in the line inventory, and k is the summation formula parameter.

[0246] It should be noted that for a multi-machine assembly line m = 1, 2, ..., M; the WIP level of a two-machine assembly line was calculated in the previous article and parts inventory levels for each equivalent machine The two indicators have the same sign, but they are not the same value.

[0247] In the embodiment of the present application, for an independent assembly station consisting of an assembly machine and line-side inventory, the influence of the inventory control strategy on the system state transition process is analyzed, and the system state transition equilibrium equation is established based on the Markov chain, and then the closed set expression of the steady-state probability distribution of the system state is obtained. Further, for the two-machine assembly line, the failure rate and repair rate parameters of the assembly station are fitted based on the performance evaluation results of the independent station, and the analytical expression of the main performance indicators is obtained using the Markov chain. Finally, for the multi-machine assembly line, the system is split into multiple two-machine assembly lines. Based on the analytical expression of the performance indicators of the two-machine assembly line, a performance evaluation aggregation method based on recursive iteration is proposed to approximate the main performance indicators such as output rate, work-in-process level and parts inventory level. Therefore, in the embodiment of the present application, the key performance indicators such as the output rate, work-in-process level and parts inventory level of the multi-machine assembly line with line-side inventory are quickly and accurately quantified, and then the performance of the multi-machine assembly line with line-side inventory can be improved according to the key performance indicators such as output rate, work-in-process level and parts inventory level.

[0248] Furthermore, in order to verify the accuracy of the present invention, the proposed performance evaluation method and simulation method are used to obtain performance index values ​​such as output rate, work-in-process level and parts inventory level for the same assembly line. The multi-machine assembly line with line-side inventory is simulated by software, and it is used as a benchmark to calculate the error percentage of the performance index values ​​obtained by the two methods as an evaluation index for evaluating the effectiveness of the proposed assembly line performance evaluation method. The calculation formula for the system performance index error percentage is as follows:

[0249]

[0250]

[0251] Among them, (·) and (·) Si m represents the performance index values ​​obtained by the proposed performance evaluation method and simulation method respectively.

[0252] Based on the above calculation formula, in order to ensure the objectivity and comprehensiveness of the effectiveness analysis, the present invention randomly generates 5,000 multi-machine assembly lines with line-side inventory for numerical experiments. The selection range of the parameters involved is as follows:

[0253] p m ∈(0.6,1),λ m ∈(0.6,1),N m ∈[2,10],

[0254] S m ∈[2,10],s m ∈[1,S m 1],M∈{2,4,6,8,10,12,14}

[0255] For each set of assembly line parameters, the proposed performance evaluation method and simulation method are used to obtain performance indicators. In the simulation method, each assembly line runs the simulation program 30 times. In each run, the first 5000 unit time is used as the preheating process of the assembly line, and the subsequent 50000 unit time is used to count the performance index values, and the output is the average value of the 30 performance indicators. The numerical experimental results are shown in Table 1:

[0256] Table 1. Accuracy analysis results of multi-machine performance evaluation methods

[0257]

[0258] Combined with the data in Table 1, the specific analysis is as follows:

[0259] (1) The proposed method has high evaluation accuracy for output rate, WIP level and parts inventory level. Specifically, the maximum errors of output rate and parts inventory level are no more than 1.5%, while the evaluation accuracy of WIP level is relatively low, but the maximum error is around 4%.

[0260] (2) The errors in both the output rate and the WIP level increase with the number of machines in the assembly line. The error in the parts inventory level fluctuates with the increase in the number of machines, and the error is greater than 1% only when the number of machines is 6 and 8.

[0261] According to the above analysis results, it can be seen that the method proposed in the present invention can accurately evaluate the performance indicators of a multi-machine assembly line with line-side inventory.

[0262] The present invention first analyzes the influence of inventory control strategy on the system state transition process for an independent assembly station consisting of an assembly machine and line-side inventory, establishes the system state transition equilibrium equation based on Markov chain, and then obtains the closed set expression of the steady-state probability distribution of the system state.

[0263] Secondly, for the two-machine assembly line, the failure rate and repair rate parameters of the assembly stations were fitted based on the performance evaluation results of independent stations, and the analytical expressions of the main performance indicators were obtained using Markov chains.

[0264] Thirdly, for multi-machine assembly lines, the system is split into multiple two-machine assembly lines. Based on the analytical expressions of the performance indicators of the two-machine assembly lines, a performance evaluation aggregation method based on recursive iteration is proposed to approximate solutions to major performance indicators such as output rate, work-in-process level and parts inventory level.

[0265] The above description is only a preferred embodiment of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above-mentioned technical features, but should also cover other technical solutions formed by any combination of the above-mentioned technical features or their equivalent features without departing from the above-mentioned inventive concept. For example, the above-mentioned features are replaced with the technical features with similar functions disclosed in the embodiments of the present disclosure (but not limited to) to form a technical solution.

Claims

1. A method for evaluating the performance of a multi-machine assembly line with line-side inventory, characterized in that: The method for evaluating the performance of a multi-machine assembly line with line-side inventory comprises: Step 1: The state transition process of the system consisting of line-side inventory and assembly machines is characterized by a Markov chain, and the repair rate and failure rate of the equivalent machine are calculated. The equivalent machine is a machine equivalent to the line-side inventory and the assembly machine. The line-side inventory is used to store the parts to be assembled, and the assembly machine is used to install the parts on the work-in-progress. Step 2: According to the repair rate and failure rate of the equivalent machines, based on the aggregation method and iterative algorithm, the forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line are iteratively updated to obtain the updated forward aggregated failure rate, backward aggregated failure rate, forward aggregated repair rate and backward aggregated repair rate of each equivalent machine on the assembly line; Step 3: Based on the updated forward aggregate failure rate, backward aggregate failure rate, forward aggregate repair rate and backward aggregate repair rate of each equivalent machine in the assembly line, calculate the multi-machine assembly line output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine. The multi-machine assembly line output rate, the work-in-process level of each equivalent machine and the parts inventory level of each equivalent machine are used to provide quantitative standards and decision-making basis for cost reduction and efficiency improvement in the assembly line operation process.

2. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 1, characterized in that: Step 1 specifically includes: Step 1.1: Draw the state transition diagram of the system and construct the considerations based on the state transition diagram (s m ,S m )The system state transfer equilibrium equation of the inventory control strategy, the (s m ,S m ) The inventory control strategy is to set the number of parts in the line inventory to be less than the minimum threshold s m When the number of parts in the line inventory reaches the maximum threshold S m When , the parts replenishment system stops working, and the parts replenishment system is used to provide parts for the line side inventory; the system state transfer balance equation is: Among them, (l m ,α m ) indicates the state of the system, l m Represents the mth line edge inventory L m The number of parts in , α m =1 means the parts replenishment system is line-side inventory L m Normal supply of parts, α m =0 means that the parts replenishment system stops as line side inventory L m Supply Parts, P m (l m ,α m ) represents the line inventory L m and assembly machine M m The system is in state (l m ,α m ), M m represents the mth assembly machine, P m (l m ,1) Characterize the line inventory L m and assembly machine M m The system is composed of line inventory L m The number of parts is l m And the parts supply system is line-side inventory L m The probability of a normal supply of parts, P m (l m ,0) represents the line side inventory L m and assembly machine M m The system is composed of line inventory L m The number of parts is l m And the parts replenishment system stops as line side inventory L m The probability of the state of supplying parts; γ m Indicates that the parts replenishment system at each moment is the line inventory L m The probability of supplying a part; p m For assembling machine M m Probability of being in working order; Step 1.2: Consider (s m ,S m ) The system state transfer equilibrium equation of the inventory control strategy and the normalization equation of all states of the system are solved simultaneously to obtain the solution considering (s m ,S m ) The system state probability distribution of the inventory control strategy; the normalized equation of all states of the system is: The considerations(s m ,S m )The system state probability distribution of the inventory control strategy is: in, Step 1.3: Consider (s m ,S m ) The probability distribution of the system state of the inventory control strategy, the calculation of the equivalent machine The repair rate R m and failure rate P m , the equivalent machine The repair rate R m and failure rate P m for: R m =c m , Among them, the equivalent machine represents the mth equivalent machine, R m represents the repair rate of the mth equivalent machine, P m represents the failure rate of the mth equivalent machine, P m (0,1) represents the line inventory L m and assembly machine M m The system is in line inventory L m The number of parts in is 0 and the parts replenishment system is line-side inventory L m The probability of a state in which parts are normally available.

3. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 2, characterized in that: Step 2 specifically includes: Step 2.1: Initialize according to the following formula: Where n represents the number of iterations, that is, the number of backward aggregation and forward aggregation; Represents an equivalent machine The failure rate of the nth forward aggregation; P1 is the equivalent machine failure rate; Represents an equivalent machine The failure rate of the nth backward aggregation; P M For equivalent machines failure rate; Represents an equivalent machine The repair rate of the nth forward aggregation; R1 is the equivalent machine The repair rate; For equivalent machines The repair rate of the nth backward aggregation; R M For equivalent machines The repair rate; Represents an equivalent machine The failure rate of the 0th forward aggregation; P m For equivalent machines The failure rate, Represents an equivalent machine The repair rate of the 0th forward aggregation; R m For equivalent machines The repair rate of m and R m All of the equivalent machines The repair rate R m and failure rate P m The formula is calculated; Among them, the equivalent machine represents the mth equivalent machine, the equivalent machine represents the first equivalent machine, the equivalent machine represents the Mth equivalent machine, and 1≤m≤M; Step 2.2: Based on the initialized failure rate and repair rate, perform backward aggregation for all equivalent machines on the assembly line, and select the equivalent machines from the preset order of all equivalent machines on the assembly line. To the equivalent machine Updating the backward-aggregated failure rate and the backward-aggregated repair rate of each equivalent machine to obtain the updated backward-aggregated failure rate and the backward-aggregated repair rate of each equivalent machine on the assembly line after each iteration of backward aggregation; Step 2.3: Based on the initialized failure rate and repair rate, perform forward aggregation for all equivalent machines on the assembly line, and select the equivalent machines from the preset order of all equivalent machines on the assembly line. To the equivalent machine The forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine are updated to obtain the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine on the assembly line after each iteration of the forward aggregation; Step 2.4: Determine whether the updated backward aggregate failure rate and the backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine meet the convergence condition. If the updated backward aggregate failure rate and the backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and the forward aggregate repair rate of each equivalent machine meet the convergence condition, the equivalent machine The failure rate of the nth backward aggregation as an equivalent machine The failure rate of backward aggregation Equivalent Machine The failure rate of the nth forward aggregation as an equivalent machine The failure rate of the forward aggregation Equivalent Machine The repair rate of the nth backward aggregation as an equivalent machine The repair rate of backward aggregation Equivalent Machine The repair rate of the nth forward aggregation as an equivalent machine The repair rate of forward aggregation Otherwise, return to step 2.2 until the updated backward aggregate failure rate and backward aggregate repair rate of each equivalent machine, as well as the updated forward aggregate failure rate and forward aggregate repair rate of each equivalent machine meet the convergence condition; Among them, the convergence condition is the equivalent machine The difference between the failure rate of the nth backward aggregation and the failure rate of the n+1th backward aggregation is less than the preset threshold, and the equivalent machine The difference between the failure rate of the nth forward aggregation and the failure rate of the n+1th forward aggregation is less than the preset threshold, and the equivalent machine The difference between the repair rate of the nth backward aggregation and the repair rate of the n+1th backward aggregation is less than the preset threshold, and the equivalent machine A difference between a repair rate of the nth forward aggregation and a repair rate of the (n+1)th forward aggregation is less than a preset threshold.

4. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 3, characterized in that: Step 2.2 specifically includes: According to the preset order of all equivalent machines on the assembly line, from back to front, for two adjacent equivalent machines, based on the initialized failure rate and repair rate, the equivalent machines are Equivalent Machine and buffer B m The two equivalent machine units are processed according to the equivalent machine The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the buffer B m capacity, and obtain the updated equivalent machine The backward aggregated failure rate and the backward aggregated repair rate of the equivalent machine are then iteratively updated for the backward aggregated failure rate and the backward aggregated repair rate of each equivalent machine on the assembly line. represents the m+1th equivalent machine, B m Represents the mth buffer.

5. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 4, characterized in that: Equivalent Machine The backward aggregation failure rate and the backward aggregation repair rate are calculated and updated by the following formula: in, Represents an equivalent machine The failure rate of the n+1th backward aggregation, P m Represents an equivalent machine The failure rate, R m Represents an equivalent machine The repair rate, Represents an equivalent machine The failure rate of the n+1th backward aggregation, Represents an equivalent machine The repair rate of the n+1th backward aggregation, Represents an equivalent machine The failure rate of the nth forward aggregation, Represents an equivalent machine The repair rate of the nth forward aggregation, N m Indicates the mth buffer B m The number of work in progress in; where Q2 is: Among them, c1, c2, d1, d2, μ, Ω1, Ω2, Ω3, and Ω4 are parameters used to simplify the formula, and k is a summation formula parameter.

6. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 3, characterized in that: Step 2.3 specifically includes: According to the preset order of all equivalent machines on the assembly line, from front to back, for two adjacent equivalent machines, based on the initialized failure rate and repair rate, the equivalent machines are Equivalent Machine and buffer B m-1 Two equivalent machine units are composed of The failure rate of the forward aggregation and the repair rate of the forward aggregation, as well as the equivalent machine The failure rate of backward aggregation and the repair rate of backward aggregation, as well as the buffer B m-1 capacity, and obtain the updated equivalent machine The forward aggregate failure rate and forward aggregate repair rate of the equivalent machine are then iteratively updated. represents the m-1th equivalent machine, B m-1 Indicates the m-1th buffer.

7. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 6, characterized in that: Equivalent Machine The forward aggregation failure rate and forward aggregation repair rate are calculated and updated using the following formula: in, Represents an equivalent machine The failure rate of the n+1th forward aggregation, P m Represents an equivalent machine The failure rate, R m Represents an equivalent machine The repair rate, Represents an equivalent machine The failure rate of the n+1th forward aggregation processing, Represents an equivalent machine The repair rate of the n+1th forward aggregation process, Represents an equivalent machine The failure rate of the n+1th backward aggregation processing, Represents an equivalent machine The repair rate of the n+1th backward aggregation process, Represents an equivalent machine The repair rate of the n+1th forward aggregation process, N m-1 Indicates the m-1th buffer B m-1 The number of work in progress in Q3 is: Among them, g1, g2, h1, h2, θ, E, F, G, and H are parameters used to simplify the formula, and k is a summation formula parameter.

8. The method for evaluating the performance of a multi-machine assembly line with line-side inventory according to claim 1, characterized in that: The multi-machine assembly line output rate PR in step 3 and the work-in-progress level of each equivalent machine and parts inventory levels for each equivalent machine Calculated by the following formula: in, Among them, the equivalent machine represents the mth equivalent machine, the equivalent machine represents the first equivalent machine, the equivalent machine represents the Mth equivalent machine, equivalent machine represents the m+1th equivalent machine, Represents an equivalent machine Repair rate of forward aggregation; Represents an equivalent machine Failure rate of forward aggregation; Represents an equivalent machine The repair rate of backward aggregation; Represents an equivalent machine Failure rate of backward aggregation; Represents an equivalent machine Repair rate of forward aggregation; Represents an equivalent machine The repair rate of backward aggregation; Represents an equivalent machine Failure rate of backward aggregation; Represents an equivalent machine Failure rate of forward aggregation; N m represents the number of work-in-progress in the mth buffer; γ m Indicates that the parts replenishment system at each moment is the line inventory L m The probability of supplying a part; p m For assembling machine M m The probability of being in working state; s m is the minimum threshold of the number of parts in the line inventory; S m is the maximum threshold of the number of parts in the line inventory, and k is the summation formula parameter.

Citation Information

Cited By

  • Assembly line bottleneck identification method, assembly line bottleneck identification device and assembly line bottleneck identification equipment based on industrial internet

    CN119721922A

  • Method, device and equipment for identifying bottlenecks in assembly lines based on industrial Internet

    CN119721922B