Construction structure and construction method for mounting prefabricated box girder under low-clearance high-voltage line

By using a combined structure of a bridge rig and a transverse device in bridge construction, the problem of box girder installation in low clearance and high voltage offline environment is solved, efficient and safe construction progress and quality are achieved, and the construction period and residents' lives are avoided. Influence.

CN119195004APending Publication Date: 2024-12-27CHINA CONSTR THIRD ENG BUREAU GRP CHANGJIANG CO LTD +1

Patent Information

Application Number
CN202411598204.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-11
Publication Date
2024-12-27

AI Technical Summary

Technical Problem

In bridge construction, the low clearance high-voltage offline construction environment causes conventional cranes and bridge builders to fail to meet the clearance requirements for box girder installation, and the power outage coordination is difficult and the approval period is long, which affects the construction period and residents' lives.

Method used

The low-head space and high-voltage offline prefabricated box girder installation construction structure including a bridge staircase and a transverse movement device is adopted. The box girder body is tilted through the bridge staircase and the transverse movement device is used to perform transverse top thrust and translation to realize the position installation of the box girder.

Benefits of technology

There is no need for large lifting equipment, avoid high-altitude operations, ensure construction quality and progress, reduce the impact of external environment and communication and coordination, shorten the construction period, and improve the safety and quality of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119195004A_ABST
    Figure CN119195004A_ABST
Patent Text Reader

Abstract

The invention discloses an installation construction structure and construction method of a prefabricated box girder under a low-clearance high-voltage line, the installation construction structure comprises a bridge girder erection machine and a transverse moving device, the bridge girder erection machine comprises a truss, a first crown block and a second crown block, the first crown block and the second crown block are both installed on the truss, and the transverse moving device is arranged at the bottom end of the truss; the transverse moving device comprises a mounting seat, a transverse jack, a connecting seat and a jacking jack, and the transverse jack is fixedly connected to the mounting seat; the box girder body is obliquely lifted by the bridge girder erection machine and then is transversely pushed and translated in place by the transverse moving device, and compared with the prior art, traffic under the bridge is not affected, large hoisting equipment is not needed, high-altitude operation is not needed, and the problem of erecting the viaduct under the low-clearance high-voltage line is solved; the beam sections are periodically constructed on the fixed site, so that the construction quality and the construction progress are easy to guarantee, meanwhile, the incremental launching construction is less restricted by the external environment, the communication and coordination cost with an external unit can be reduced, the construction period can be shortened, and the engineering safety quality can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction, and in particular to a prefabricated box girder installation construction structure and a construction method for a low-headroom high-voltage line. Background Art

[0002] With the continuous growth of my country's economy and the continuous improvement of transportation infrastructure, the number and scale of highway bridge construction are increasing. For the construction of modern bridges, it is often necessary to cross the elevated line. Due to the influence of planning and the current topography, the clearance under the high-voltage line is insufficient. The use of conventional cranes or direct use of bridge erection machines cannot meet the clearance requirements for box girder installation. The coordination of construction after power outages by the power department is often difficult, the approval cycle of construction procedures is long, and the on-site construction period requirements cannot be met, and the production and life of surrounding residents are affected.

[0003] During the construction of modern bridges, it is common to encounter construction under elevated lines. Due to the influence of planning and current topography, the clearance under the high-voltage line is insufficient. The use of conventional cranes or direct use of bridge erection machines cannot meet the clearance requirements for box girder installation. Coordination with the power department after a power outage often makes construction difficult, and the approval cycle for construction procedures is long. It cannot meet the on-site construction period requirements and affects the production and life of surrounding residents.

[0004] Therefore, in view of the above technical problems, it is necessary to propose a prefabricated box girder installation construction structure and construction method under low clearance high-voltage line Summary of the invention

[0005] The purpose of the present invention is to provide a prefabricated box girder installation construction structure and a construction method under a low-headroom high-voltage line to solve the problems raised in the above-mentioned background technology.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0007] A prefabricated box girder installation construction structure under a low-headroom high-voltage line comprises a bridge erecting machine and a transverse movement device. The bridge erecting machine comprises a truss, a first car and a second car, and the first car and the second car are both installed on the truss, and the transverse movement device is arranged at the bottom end of the truss.

[0008] Preferably, a middle leg is fixedly connected to the truss, a front leg is provided on one side of the middle leg, and a rear leg is provided on the other side, and both the front leg and the rear leg are fixedly connected to the truss.

[0009] Preferably, the transverse movement device includes a mounting seat, a transverse jack, a connecting seat and a lifting jack, and the transverse jack is fixedly connected to the mounting seat.

[0010] Preferably, both ends of the connecting seat are fixedly connected with lifting jacks, and one of the lifting jacks is fixedly connected to the output end of the transverse jack.

[0011] Preferably, the two lifting jacks are both slidably connected to the mounting seat.

[0012] A construction method for installing a prefabricated box girder construction structure under a low-headroom high-voltage line, characterized in that the method steps are as follows:

[0013] S1. Construction preparation;

[0014] S2, installation of bridge erecting machine and lifting of bridge erecting machine beam;

[0015] S3, drop the beam to the transverse track, push and move it transversely;

[0016] S4, cyclic pushing and transverse movement operation, transverse movement to the beam position;

[0017] S5, beam drop.

[0018] The horizontal movement steps of the falling beam

[0019] S21. The tail end of the box beam body is supported on the top surface of the cap beam (supporting pad stone or temporary support), and the beam shifting and pushing device is installed and the horizontal pushing cylinder is returned to the minimum extension;

[0020] S22, the vertical cylinder of the beam-moving and pushing device lifts up the box beam body, and the box beam body is detached from the temporary support at the tail end;

[0021] S23, the horizontal cylinder of the beam-moving and pushing device pushes the box beam body to move horizontally 300mm;

[0022] S24, the vertical oil cylinder of the beam shifting and pushing device returns oil, the box beam body is detached, and the tail of the box beam body falls on the temporary support;

[0023] S25, the horizontal pushing cylinder of the beam shifting and pushing device returns the oil and moves horizontally to the next cycle position; the next cycle and subsequent horizontal movement and erection of the box beam body are carried out.

[0024] The beneficial effects of the present invention are as follows: the present invention adopts a bridge erection machine to tilt the box girder body and then uses a transverse moving device to push and translate it into place laterally. Compared with the prior art, the present invention does not affect the traffic under the bridge, does not require large-scale lifting equipment, and does not involve high-altitude operations, thereby solving the problem of erecting elevated bridges under low-clearance high-voltage lines. Since the beam sections are constructed periodically on a fixed site, the construction quality and progress are easy to ensure. At the same time, the pushing construction is less restricted by the external environment, which can reduce the cost of communication and coordination with external units, and can shorten the construction period and improve the safety and quality of the project. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0026] Figure 1 It is a schematic diagram of the overall main structure of the present invention;

[0027] Figure 2 This is a schematic diagram of the main structure of the box girder body of the present invention when it is hoisted;

[0028] Figure 3 This is a schematic diagram of the main structure when the angle of the box beam body is adjusted according to the present invention;

[0029] Figure 4 It is a schematic diagram of the main structure of the box girder body of the present invention when it is on the bridge;

[0030] Figure 5 It is a schematic diagram of the main structure of the box girder body of the present invention when the girder is dropped;

[0031] Figure 6 It is a side view structural schematic diagram of the transverse shifting device of the present invention;

[0032] Figure 7 It is a schematic diagram of the front view structure of the transverse shifting device of the present invention;

[0033] Figure 8-Figure 12 It is a schematic diagram of the transverse movement process of the box beam body of the present invention.

[0034] The reference numerals in the figure are: 1. bridge erecting machine; 11. truss; 12. front outrigger; 13. middle outrigger; 14. rear outrigger; 15. first car; 16. second car; 2. transverse shifting device; 21. mounting seat; 22. transverse jack; 23. connecting seat; 24. lifting jack; 3. sleeper; 4. supporting column; 5. cap beam; 6. box beam body; 7. beam transport vehicle. DETAILED DESCRIPTION

[0035] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0036] Please refer to the attached Figure 1 -Attached Fig.12An embodiment of the present invention is as follows: a prefabricated box girder installation construction structure under a low-headroom high-voltage line comprises a bridge erecting machine 1 and a transverse moving device 2. The bridge erecting machine 1 comprises a truss 11, a first trolley 15 and a second trolley 16, and the first trolley 15 and the second trolley 16 are both installed on the truss 11. The transverse moving device 2 is arranged at the bottom end of the truss 11. A middle leg 13 is fixedly connected to the truss 11. A front leg 12 is arranged on one side of the middle leg 13, and a rear leg 14 is arranged on the other side. The front leg 12 and the rear leg 14 are both fixedly connected to the truss 11. The truss 11 is the main structure of the bridge erecting machine 1. The front leg 12, the middle leg 13 and the rear leg 14 are used to support the truss 11. The first car 15 and the second car 16 are used to lift the box girder body 6; the transverse movement device 2 includes a mounting seat 21, a transverse jack 22, a connecting seat 23 and a lifting jack 24, and the transverse jack 22 is fixedly connected to the mounting seat 21, and both ends of the connecting seat 23 are fixedly connected with the lifting jacks 24, one of the lifting jacks 24 is fixedly connected to the output end of the transverse jack 22, and the two lifting jacks 24 are both slidably connected to the mounting seat 21, the mounting seat 21 is used to install the transverse jack 22, the transverse jack 22 is used to push the lifting jack 24, the lifting jack 24 is used to lift the box girder body 6, and the connecting seat 23 is used to connect the lifting jack 24.

[0037] Working principle: When the present invention is used for bridge construction, the beam transporter 7 is started, the box beam body 6 is transported to the bottom of the bridge erecting machine 1, and the first and second carriages 15 and 16 are moved to the top of the lifting hole of the box beam body 6; the first carriage 15 is lowered, and the tail beam plate is lifted off the tail carriage by the wire rope, and after checking that all systems are correct, the tractor is put into neutral gear, and the box beam body 6 is slowly moved by the longitudinal drive of the first carriage 15; when the beam end is under the second carriage 16, the hook of the second carriage 16 is lowered, and the end beam plate is lifted off the beam transporter 7, and the beam transporter 7 is driven out, and the bridge erecting machine 1 takes over the box beam body 6, and the beam transporter 7 leaves, and the box beam body Flexible pads are used at the contact points between the two sides of the bottom of 6 and the wire rope to prevent the wire rope from being worn; the first car 15 and the second car 16 slowly lift the box beam body 6 at the same time. When the box beam body 6 is transported to a certain distance from the ground, the first car 15 is lifted and the second car 16 stops lifting, and the angle of the box beam body 6 is adjusted so that the box beam body 6 is 12° with the horizontal line; after the angle adjustment is completed, the first car 15 and the second car 16 continue to lift the box beam body 6 synchronously, the first car 15 lifts the end of the box beam body 6 over the top surface of the cap beam 5 on the support column 4, and the second car 16 lifts the box beam body 6 to the bottom surface of the cap beam 5 at the same time. 15 and the second car 16 move 2m to the side of the small pile number; because during this hoisting process, the box girder body 6 needs to be tilted 12° during the process of getting on the bridge, in order to balance the longitudinal component of the wire rope, a notch needs to be opened in advance on the flange plate of the box girder body 6 to be installed, and the wire rope should not be exposed outside the notch to limit the longitudinal slippage of the wire rope. The opening of the notch should avoid the steel bars and the rounded corners should be well processed to avoid the bending radius of the wire rope being too small; the first car 15 and the second car 16 are driven at the same time to transport the box girder body 6 to the installation position; then the bridge crane moves horizontally, and the shifting wheel group of the front leg 12 and the lower transverse shifting wheel group of the middle leg 13 move simultaneously in the same direction and at the same speed. The truss 11 is driven to move the entire truss 11 together with the box beam body 6 to the installation position laterally, and the box beam body 6 slowly falls on the sleeper 3 of the cap beam 5; the transverse movement device 2 is installed and the transverse jack 22 is returned to the minimum extension, the jacking jack 24 lifts the box beam body 6, the box beam body 6 is separated from the sleeper 3 temporarily supported at the tail end, the transverse jack 22 pushes the jacking jack 24, the jacking jack 24 slides along the connecting seat 23, and the box beam body 6 is moved laterally by 300mm, the jacking jack 24 returns oil, and the box beam body 6 is separated, and the tail of the box beam body 6 falls on the sleeper 3, the transverse jack 22 returns oil, and moves to the next cycle position laterally;There is a transverse block at the top of the cap beam 5. In order to make the transverse moving device 2 and the box beam body 6 pass over the block, it is necessary to lift up the box beam body 6 as a whole and then drop it as a whole after crossing the block. The specific operation process is as follows: 1. The lifting jack 24 lifts up the box beam body 6, and the box beam body 6 is separated from the sleeper 3 temporarily supported at the tail end; 2. The sleeper 3 temporarily supported at the tail end of the box beam body 6 is raised, and the lifting jack 24 returns oil; 3. The transverse moving device 2 is raised; 4. Repeat one to three until the transverse moving device 2 passes over the block. block height, five, according to the construction method of pushing and moving the box beam body 6, make the box beam body 6 step over the block, six, according to the reverse procedure of three to one, remove the temporary support sleepers 3 step by step, lower the box beam body 6 and the transverse movement device 2; when the box beam body 6 is pushed and moved, use hand chain hoists at both ends of the box beam body 6 to connect the flange steel bars of the box beam body 6 and the installed box beam body 6, when the box beam body 6 is moved transversely, adjust the hand chain hoists while moving transversely to ensure the overall stability.;

[0038] like Figures 8 to 12 As shown, a construction method for installing a prefabricated box girder construction structure under a low clearance high-voltage line, the method steps are as follows:

[0039] S1. Construction preparation;

[0040] S2, installation of bridge erecting machine and lifting of bridge erecting machine beam;

[0041] S3, drop the beam to the transverse track, push and move it transversely;

[0042] S4, cyclic pushing and transverse movement operation, transverse movement to the beam position;

[0043] S5, beam drop.

[0044] The horizontal movement steps of the falling beam

[0045] S21. The tail end of the box beam body is supported on the top surface of the cap beam (supporting pad stone or temporary support), and the beam shifting and pushing device is installed and the horizontal pushing cylinder is returned to the minimum extension;

[0046] S22, the vertical cylinder of the beam-moving and pushing device lifts up the box beam body, and the box beam body is detached from the temporary support at the tail end;

[0047] S23, the horizontal cylinder of the beam-moving and pushing device pushes the box beam body to move horizontally 300mm;

[0048] S24, the vertical oil cylinder of the beam shifting and pushing device returns oil, the box beam body is detached, and the tail of the box beam body falls on the temporary support;

[0049] S25, the horizontal pushing cylinder of the beam shifting and pushing device returns the oil and moves horizontally to the next cycle position; the next cycle and subsequent horizontal movement and erection of the box beam body are carried out.

[0050] Construction preparation

[0051] 1. Technical preparation

[0052] (1) Relevant personnel shall receive safety education and technical briefings, special operations personnel must be certified before taking up their posts, and special equipment must be inspected and qualified.

[0053] (2) The surveying team uses a total station to lay out the axis, longitudinal and transverse control points of the pier cap, and then uses ink lines to pop out the installation positions corresponding to the axis of the permanent support, the back wall of the cap beam and the box girder body one by one according to the design dimensions on the drawing, to ensure that the box girder body is vertical from top to bottom, has a flat surface and a smooth linear shape after it is in place.

[0054] (3) Elevation measurement: After the installation positions of the supports and box girder body are laid out, carefully measure and calculate the elevations of each point one by one. When the elevation of the supports or support pads is incorrect, strictly use anti-corrosion treated steel plates to pad under the supports and firmly bond them to the caps, cap beams or support pads.

[0055] (4) The beam can be lifted and moved only when the concrete strength of the main beam reaches more than 100% and the grouting strength of the hole reaches more than 40Mpa. During the movement, transportation, lifting and installation process, it is required to be placed at two points and adopt the lifting method of threading the rope to the bottom. The lifting point can be within a range of no more than 50cm inside the support, and holes can be left on the wing plate at the threading position.

[0056] (5) Before lifting, transporting and erecting beams, the beam transport vehicle and bridge erection machine should be thoroughly inspected and tested before operation to ensure that the equipment operates normally and safety can be ensured before the operation can be organized.

[0057] 2. Safety inspection before operation

[0058] (1) Operators must be certified before they can take up their posts;

[0059] (2) Operators should be familiar with the "bridge crane safety operation procedures", "Ten things not to do when lifting and hoisting", the technical performance and relevant parameters of the bridge crane, master the special construction plan for the bridge crane, understand the "hazard source identification" of the bridge crane construction, be familiar with the "emergency rescue plan" of the project, and understand the relevant systems and related work processes of the project department;

[0060] (3) Before operation, routine inspections must be conducted on the bridge crane, hoisting equipment, etc. If any faults are found, they can be repaired by themselves. If they cannot be repaired by themselves, they should be reported to the relevant personnel of the equipment management department in a timely manner, and the daily inspection records should be filled in truthfully. Understand and inspect the operation site and the conditions of the objects being hoisted. If any safety hazards that endanger the construction of the bridge crane are found during operation, the operator should stop the operation immediately and report the safety hazards to the site manager and the relevant personnel of the safety management department and the equipment management department.

[0061] Bridge erecting machine lifting beam, beam dropping

[0062] In the construction sequence of bridge-erecting machine, beams are generally transported from the bridge deck to the bottom of the bridge-erecting machine by a beam transporter. The bridge-erecting machine lifts and lowers the beams by a straight lifting method. The safe construction distance on the bridge deck is 6m, which does not support the bridge-erecting machine to transport beams below. Therefore, the beams are transported below the bridge deck, and the bridge-erecting machine lifts the beams by an oblique lifting method at a certain angle.

[0063] The bridge erecting machine uses an oblique lifting method at a certain angle to lift the beam. The specific operation process is as follows

[0064] 1. Feed beam

[0065] Beam transport by beam transport flat car: Start the beam transport flat car to transport the precast beam to the bottom of the bridge erection machine, and the mobile overhead crane is located above the lifting hole of the box beam.

[0066] 2. Handle

[0067] When the beam piece stops at the predetermined position, slowly lower the 1# overhead crane to lift the tail beam slab off the tail trolley. After checking that all systems are correct, put the tractor in neutral and slowly move the beam slab by the longitudinal drive of the 1# overhead crane. When the beam end is under the 2# overhead crane, lower the 2# overhead crane hook and lift the end beam slab until it is separated from the tractor. The beam transport vehicle drives out, the bridge erecting machine takes over the precast beam, and the beam transport vehicle leaves. Flexible pads are used on both sides of the beam bottom where the wire rope contacts to prevent the wire rope from wear.

[0068] 3. Go up the bridge

[0069] (1) Two overhead cranes slowly lift the beam slab at the same time. When the beam slab is transported to a certain distance from the ground, the first overhead crane starts lifting and the second overhead crane stops lifting. The angle of the small box beam is adjusted so that it is 12° with the horizontal line.

[0070] (2) After the angle adjustment is completed, the two overhead cranes continue to lift the small box girder synchronously. The first overhead crane lifts the end of the box girder over the top of the cap beam, and the second overhead crane lifts the small box girder to the ground position of the cap beam. At the same time, the first and second overhead cranes are driven to move 2m to the side of the small pile number.

[0071] (3) During this hoisting process, the box girder body needs to be tilted 12 degrees when it is on the bridge. In order to balance the longitudinal force of the wire rope, a 10*10cm notch needs to be opened in advance on the flange plate of the box girder body to be installed, and the wire rope should not be exposed outside the notch to limit the longitudinal slippage of the wire rope. The notch should be opened to avoid the steel bars and the corners should be rounded to avoid the bending radius of the wire rope being too small.

[0072] 4. Falling beam

[0073] Two overhead cranes are driven simultaneously to transport the beam slab to the beam slab installation position.

[0074] Bridge crane transverse movement: the front support transverse movement wheel group and the middle support lower transverse movement wheel group move in the same direction and speed at the same time, driving the entire bridge crane and the beam piece to move transversely to the beam plate installation position.

[0075] Beam dropping: The bridge erection machine moves horizontally to the center position of the beam and slab, and the box beam body slowly drops onto the support.

[0076] 5. Bridge crane returns

[0077] Transverse movement of the crane: remove the sling, retract the wire rope, and move the two cranes to the middle of the overhead crane beam. Transverse movement of the bridge crane: move the bridge crane to the beam feeding position.

[0078] Overhead crane returns: Overhead crane returns to the rear support position, ready to erect the next beam.

[0079] 6. Temporary fixation

[0080] After the first piece of each box girder is installed, it should be supported on the outside (guardrail side) with logs or steel pipes to prevent the box girder from tipping over due to eccentricity. After the two adjacent box girders in the same span are erected, they are welded and fixed with steel bars to form a whole, so as to increase the lateral stability of the box girder.

[0081] The lateral movement device adopts a hydraulic beam shifting device, which adopts intelligent control. The hydraulic transmission principle is to use oil as the working medium, transmit motion through the change of sealed volume, and transmit power through the pressure inside the oil. The hydraulic cylinder uses a manual booster rod (hydraulic manual pump) to allow the hydraulic oil to enter the cylinder through a one-way valve. At this time, the hydraulic oil entering the cylinder cannot be reversed due to the one-way valve, forcing the cylinder rod to rise, and then continue to allow the hydraulic oil to continue to enter the hydraulic cylinder during work, so that it continues to rise. When it is time to descend, open the hydraulic valve to return the hydraulic oil to the oil tank. The five basic components of the hydraulic cylinder are the cylinder barrel and cylinder head, piston and piston rod, sealing device, buffer device and exhaust device.

[0082] Precast beam moves across the stopper

[0083] There is a transverse block on the top of the cap beam of the bridge installation. In order to make the lateral movement device and the box beam body pass over the block, it is necessary to lift the whole body up and then drop the whole body after crossing the block. The specific operation process is as follows:

[0084] (1) The vertical cylinder of the beam shifting and pushing device lifts the box beam body, and the box beam body is detached from the temporary support at the tail end.

[0085] (2) The rear end of the box girder body is temporarily supported and raised, and the vertical cylinder of the beam shifting and pushing device returns oil.

[0086] (3) Raise the beam shifting and pushing device.

[0087] (4) Repeat steps (1) to (3) until the transverse lifting device returns to the height of the stop block.

[0088] (5) Follow the construction steps of pushing and shifting the beam plate to make the box beam body pass the block.

[0089] (6) Follow the reverse procedure from step (3) to step (1), remove the temporary supports step by step, and lower the box girder body and the jacking device.

[0090] When the small box girder is pushed and moved horizontally, hand winches are used at both ends of the small box girder to connect the small box girder flange steel bars and the installed small box girder. When the small box girder is moved horizontally, the hand winches are adjusted while moving to ensure overall stability.

[0091] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0092] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.

[0093] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A prefabricated box girder installation construction structure under a low-headroom high-voltage line, comprising a bridge erection machine (1) and a transverse movement device (2), characterized in that: The bridge erection machine (1) comprises a truss (11), a first trolley (15) and a second trolley (16), wherein the first trolley (15) and the second trolley (16) are both installed on the truss (11), and the transverse movement device (2) is arranged at the bottom end of the truss (11).

2. The low-headroom, high-voltage line prefabricated box girder installation construction structure according to claim 1 is characterized by: A middle leg (13) is fixedly connected to the truss (11), a front leg (12) is arranged on one side of the middle leg (13), and a rear leg (14) is arranged on the other side, and the front leg (12) and the rear leg (14) are both fixedly connected to the truss (11).

3. The low-headroom, high-voltage line prefabricated box girder installation construction structure according to claim 1 is characterized by: The transverse movement device (2) comprises a mounting seat (21), a transverse jack (22), a connecting seat (23) and a lifting jack (24), and the transverse jack (22) is fixedly connected to the mounting seat (21).

4. The low-headroom, high-voltage line prefabricated box girder installation construction structure according to claim 3 is characterized by: Both ends of the connection seat (23) are fixedly connected to lifting jacks (24), and one of the lifting jacks (24) is fixedly connected to the output end of the transverse jack (22).

5. The low-headroom, high-voltage line prefabricated box girder installation construction structure according to claim 3 is characterized by: The two lifting jacks (24) are both slidably connected to the mounting seat (21).

6. The construction method of a prefabricated box girder installation construction structure under a low clearance high-voltage line according to any one of claims 1 to 5, characterized in that: The method steps are: S1. Construction preparation; S2, installation of bridge erecting machine and lifting of bridge erecting machine beam; S3, drop the beam to the transverse track, push and move it transversely; S4, cyclic pushing and transverse movement operation, transverse movement to the beam position; S5, beam drop.

7. The construction method of the low-headroom, high-voltage line prefabricated box girder installation construction structure according to claim 6, characterized in that: The horizontal movement steps of the beam S21. The tail end of the box beam body is supported on the top surface of the cap beam (supporting pad stone or temporary support), and the beam shifting and pushing device is installed and the horizontal pushing cylinder is returned to the minimum extension; S22, the vertical cylinder of the beam shifting and pushing device lifts up the box beam body, and the box beam body is detached from the temporary support at the tail end; S23, the horizontal cylinder of the beam-moving and pushing device pushes the box beam body to move horizontally 300mm; S24, the vertical cylinder of the beam shifting and pushing device returns oil, the box beam body is separated, and the tail of the box beam body falls on the temporary support; S25, the horizontal pushing cylinder of the beam shifting and pushing device returns the oil and moves horizontally to the next cycle position; the next cycle and subsequent horizontal movement and erection of the box beam body are carried out.

Citation Information

Patent Citations

  • Cross sliding type erecting method for separated box girder of high speed railway

    CN101864734A

  • Large-tonnage box girder erection construction system capable of realizing height control, and erection method thereof

    CN111335185A

  • Beam plate inclined hoisting technology

    CN113445430A

  • Method for erecting precast beams in limited space

    CN117684456A

  • A beam shifting device with multi-directional adjustment structure

    CN221029670U

Cited By

  • Method for hoisting box girder of large-width double-layer bridge by using two gantry cranes

    CN120864370A