Nuclear power project design technology state change pushing system and method, storage medium and electronic equipment

By designing a nuclear power project design technology status change push system, the problem of inaccurate push of design technology status change information is solved, and the consistency of technical status and automatic collection and push of change information is achieved.

CN119671475APending Publication Date: 2025-03-21CHINA NUCLEAR POWER DESIGN COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411600188.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-08
Publication Date
2025-03-21

AI Technical Summary

Technical Problem

In nuclear power design projects, it is difficult to accurately and effectively push the relevant person in charge, resulting in inconsistent technical status problems.

Method used

A push system for the technical status change of nuclear power project design is designed, including the design input maintenance module, the technical status change data acquisition module, and the information processing and push module. The system receives and stores design file information and business relationship information through the information center database, and automatically collects business status update data, and pushes the change information to the target terminal after processing.

Benefits of technology

It realizes accurate push of design technical status changes, reduces the risk of inconsistent technical status, improves the efficiency of automatic collection and update of change information, and reduces human-causing risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119671475A_ABST
    Figure CN119671475A_ABST
Patent Text Reader

Abstract

The invention relates to a nuclear power project design technology state change pushing system and method, a storage medium and electronic equipment. The method comprises the steps that a design file information design input maintenance module is received; the technical state change data acquisition module is used for monitoring the service state of the data in the data table in each service system and acquiring corresponding service state update data when the service state of the data in the data table meets a write-in condition; the information processing and pushing module is used for reading the change data in the information center database, processing the change data, summarizing change information and pushing the change information to a target terminal; and the information center database is used for storing the design file information, the business association relationship information, the business state updating data and the processed data. According to the method, the problem of inconsistent technical states caused by project design technology change can be effectively solved, meanwhile, change information is automatically collected and updated and pushed to related persons in charge, and the human factor risk problem is effectively solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of nuclear power plant project design status change, and more specifically, to a nuclear power project design technical status change push system, method, storage medium and electronic equipment. Background Art

[0002] The technical status of a nuclear power plant refers to the functional characteristics and physical characteristics of the nuclear power plant. The nuclear power design technical status entity corresponds to the design documents, design changes, funding (information provided by upstream design to downstream design), interfaces (information exchange channels on the external supply side), etc. in the nuclear power design. In the nuclear power design process, there are a large number of changes in the design technical status. How to accurately and effectively push these changes to the relevant persons in charge is a problem that needs to be solved.

[0003] At present, the mainstream solution for technical status management is to adopt the technical status change information management system process, and the heads of relevant professional modules participate in the analysis, decision-making and execution of changes online. By comprehensively developing technical issues, this solution basically solves the complex problems of nuclear power technical status management.

[0004] Nuclear power design projects are highly complex, and the technical status information change process faces difficulties in scope analysis management. The analysis scope may even require multiple rounds of analysis to repeatedly determine the scope, but there are still certain human risks. There is a possibility that certain professional modules will be missed in the change analysis, which ultimately leads to incomplete coverage in the process and inconsistent technical status. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a system, method, storage medium and electronic device for pushing changes in the design technical status of a nuclear power project in view of the problems existing in the prior art.

[0006] The technical solution adopted by the present invention to solve the technical problem is to construct a nuclear power project design technical status change push system, including:

[0007] A design input maintenance module, which is used to receive design file information input by a user and write the design file information and business association relationship information into the information center database; the design file information includes: upstream funding information, interface data information and upstream file information;

[0008] A technical status change data collection module, which is used to monitor the business status of data in the data tables of each business system, and when the business status of the data in the data tables meets the writing conditions, collect the corresponding business status update data and write it into the information center database;

[0009] An information processing and push module, which is used to read the change data in the information center database, process the change data, summarize the change information, and push the change information to the target terminal; the change data includes: the design file information and / or the business status update data;

[0010] The information center database is used to store the design file information and business association information, the business status update data written by the technical status change data acquisition module, and the data processed by the information processing and push module.

[0011] In the nuclear power project design technical status change push system of the present invention, the design input maintenance module includes: a receiving unit, an association relationship identification unit, a keyword identification unit and an information writing unit;

[0012] The receiving unit is used to receive the design file information input by the user;

[0013] The association relationship identification unit is used to read the business association relationship information of the design file when the user inputs the design file information;

[0014] The keyword recognition unit is used to recognize keywords of the design file information and the business association relationship information to obtain the keywords of the design file information;

[0015] The information writing unit is used to write the design file information and the business association relationship information into the information center database based on the keyword.

[0016] In the nuclear power project design technical status change push system of the present invention, the technical status change data acquisition module includes: a data table monitoring unit;

[0017] The data table monitoring unit is used to monitor the business status of the data table in each business system, and output a business status change reminder when the business status of the data in the data table in each business system changes.

[0018] In the nuclear power project design technical status change push system of the present invention, the technical status change data acquisition module further includes: a business status identification unit;

[0019] The business status identification unit is used to identify the business status of the data in the changed data table according to the business status change reminder, so as to determine whether the business status of the data in the changed data table meets the writing condition, and obtain corresponding data when the business status of the data in the changed data table meets the writing condition; the corresponding data is the data whose business status meets the writing condition.

[0020] In the nuclear power project design technical status change push system of the present invention, the technical status change data acquisition module further includes: a data writing unit;

[0021] The data writing unit is used to write the corresponding data into the information center database.

[0022] In the nuclear power project design technical status change push system of the present invention, the information processing and push module includes: a data reading unit and a data processing unit;

[0023] The data reading unit is used to read the changed data in the information center database;

[0024] The data processing unit is used to process the changed data to obtain a keyword of the changed data.

[0025] In the nuclear power project design technical status change push system of the present invention, the information processing and push module further includes: an information matching unit and an information extraction unit;

[0026] The information matching unit is used to search the information center database according to the keyword of the changed data, and obtain the business association relationship information matching the keyword of the changed data in the information center database;

[0027] The information extraction unit is used to extract corresponding volume drawing information according to the business association relationship information.

[0028] In the nuclear power project design technical status change push system of the present invention, the information processing and push module further includes: an information aggregation unit and an information push unit;

[0029] The information summarizing unit is used to obtain and summarize the corresponding designer information according to the volume drawing information;

[0030] The information pushing unit is used to push the change information to the target terminal according to the summarized designer information.

[0031] The nuclear power project design technical status change push system of the present invention also includes: a personal subscription information module;

[0032] The personal subscription information module is used to match subscription information according to the keywords of the change data, obtain corresponding personal subscription information, and push change information based on the corresponding personal subscription information.

[0033] The present invention also provides a method for pushing changes in the design technology status of a nuclear power project, which is applied to the above-mentioned system for pushing changes in the design technology status of a nuclear power project, and comprises the following steps:

[0034] Acquire design file information and business association relationship information, and write the design file information and business association relationship information into the information center database;

[0035] Collecting business status update data and writing the business status update data into the information center database;

[0036] The change data in the information center database is read and processed to summarize the change information, and the change information is pushed to the target terminal; the change data includes: the design file information and / or the business status update data.

[0037] In the method for pushing a change in the design technical status of a nuclear power project according to the present invention, the obtaining of the design file information and the business association relationship information, and writing the design file information and the business association relationship information into an information center database comprises:

[0038] Receive design file information input by the user;

[0039] When the user inputs the design file information, the association relationship information of the design file is read;

[0040] Identifying keywords of the design file information and the business association relationship information to obtain the keywords of the design file information;

[0041] The design file information and the business association relationship information are written into the information center database based on the keyword.

[0042] In the method for pushing the change of the design technical status of a nuclear power project according to the present invention, the collecting of the business status update data and writing the business status update data into the information center database comprises:

[0043] Monitor the business status of the data tables in the business systems, and output a business status change reminder when the business status of the data in the data tables in the business systems changes;

[0044] Identify the business status of the data in the changed data table according to the business status change reminder, and obtain the business status of the changed data in the changed data table;

[0045] Determining whether the business status of the data in the changed data table meets the write condition according to the business status of the changed data;

[0046] If the write condition is met, the corresponding data is obtained; the corresponding data is data whose business status meets the write condition; if the write condition is not met, the data is written;

[0047] The corresponding data is written into the information center database.

[0048] In the method for pushing the change of the design technical status of a nuclear power project of the present invention, the reading of the change data in the information center database, processing the change data and summarizing the change information, and pushing the change information to the target terminal comprises:

[0049] Reading the changed data in the information center database;

[0050] Processing the changed data to obtain a keyword of the changed data;

[0051] Searching the information center database according to the keyword of the changed data to obtain the business association relationship information matching the keyword of the changed data in the information center database;

[0052] Extracting corresponding volume drawing information according to the business association relationship information;

[0053] Obtain and summarize the corresponding designer information according to the volume drawing information;

[0054] The change information is pushed to the target terminal according to the summarized designer information.

[0055] In the method for pushing a change in the design technical status of a nuclear power project according to the present invention, the method further includes:

[0056] Matching subscription information according to the keywords of the changed data to obtain corresponding personal subscription information;

[0057] Change information is pushed based on the corresponding personal subscription information.

[0058] The present invention also provides a storage medium storing a computer program, wherein the computer program is suitable for being loaded by a processor to execute the steps of the method for pushing changes in the design technical status of a nuclear power project as described above.

[0059] The present invention also provides an electronic device, comprising a memory and a processor, wherein the memory stores a computer program, and the processor executes the steps of the method for pushing changes in the design technical status of a nuclear power project as described above by calling the computer program stored in the memory.

[0060] The system, method, storage medium and electronic device for pushing the change of the design technical status of a nuclear power project implemented in the present invention have the following beneficial effects: including: a design input maintenance module for receiving design file information; a technical status change data acquisition module for monitoring the business status of data in the data table of each business system, and collecting the corresponding business status update data when the business status of the data in the data table meets the write condition; an information processing and push module for reading the change data in the information center database, processing the change data, and summarizing the change information, and pushing the change information to the target terminal; an information center database for storing design file information and business association relationship information, business status update data and processed data. The present invention can effectively solve the problem of inconsistent technical status caused by technical changes in project design, and automatically collect and update the change information, and push it to the relevant responsible persons, effectively solving the problem of human risk. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:

[0062] Figure 1 It is a principle block diagram of the nuclear power project design technical status change push system provided by the present invention;

[0063] Figure 2 It is a schematic diagram of the system architecture of the nuclear power project design technical status change push system provided by the present invention;

[0064] Figure 3 It is a flow chart of the method for pushing changes in the design technical status of a nuclear power project provided by the present invention. DETAILED DESCRIPTION

[0065] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0066] In order to solve the problem of how to timely and accurately push the upstream input technical status to the downstream relevant design persons in charge when changes occur in the design of nuclear power projects, and at the same time to solve the problem of inconsistent technical status caused by incomplete analysis of current technical status changes due to human factors, the present invention provides a nuclear power project design technical status change push system and method.

[0067] refer to Figure 1 , Figure 1 This is a principle block diagram of a preferred embodiment of a nuclear power project design technical status change push system provided by the present invention.

[0068] Specifically, Figure 1 As shown, the nuclear power project design technical status change push system includes: a design input maintenance module 100, a technical status change data acquisition module 200, an information processing and push module 300 and an information center database 400. Further, as Figure 1 As shown, the nuclear power project design technology status change push system also includes: a personal subscription information module 500. Among them, the system architecture of the nuclear power project design technology status change push system is as follows Figure 2 Among them, the technical status change data collection module 200 can be directly connected to various business systems, including but not limited to: funding system (a system for upstream design to provide information to downstream design), interface system (a system for information exchange channels of external suppliers), document review system (nuclear power project design document review system), etc.

[0069] In an embodiment of the present invention, the design input maintenance module 100 is used to receive design file information input by a user, and write the design file information and business association relationship information into the information center database 400; wherein the design file information includes: upstream funding information, interface material information and upstream file information.

[0070] Optionally, in an embodiment of the present invention, the design input maintenance module 100 includes: a receiving unit 101 , an association relationship identification unit 102 , a keyword identification unit 103 and an information writing unit 104 .

[0071] Among them, the receiving unit 101 is used to receive the design file information input by the user; the association relationship identification unit 102 is used to read the business association relationship information of the design file during the process of the user inputting the design file information; the keyword identification unit 103 is used to identify the keywords of the design file information and the business association relationship information to obtain the keywords of the design file information; the information writing unit 104 is used to write the design file information and the business association relationship information into the information center database 400 based on the keywords.

[0072] Specifically, designers can maintain the physical input of design files through the design input maintenance module 100, such as upstream professional funding (information provided by upstream design to downstream design), interface information (information exchange channel of external suppliers), upstream files, etc. Among them, the design file information input by the designer can be imported one by one, or can also be imported in batches. At the same time, in the process of the designer inputting the design file information, the association relationship identification unit 102 automatically identifies the business association relationship of the design file, and the data writing unit 203 writes the design file information and the corresponding business association relationship information into the information center database 400, which is stored and managed by the information center database 400. Further, in the embodiment of the present invention, it is also necessary to identify the keywords of the design file information and the keywords of the business association relationship information through the keyword identification unit 103, so that the corresponding data / information can be written into the information center database 400 through the keywords. For example, the keywords can be: funding code, interface code, file code + label. Among them, the funding code is the keyword of submission, the interface code is the keyword of the interface, and the file code + label is the keyword of the upstream sub-file. By writing the corresponding keywords, you can quickly match and obtain the files that may be affected by this change. After the keywords in the business association relationship, when a capital increase is upgraded, the two keywords (the code of the capital increase requirement (that is, the capital increase form minus the version number)) and the keywords written in the association relationship are matched. If they are the same, it means that the associated design files may be affected.

[0073] In an embodiment of the present invention, the technical status change data collection module 200 is used to monitor the business status of data in the data table of each business system, and collect the corresponding business status update data and write it into the information center database 400 when the business status of the data in the data table meets the writing condition.

[0074] Optionally, in an embodiment of the present invention, the technical status change data collection module 200 includes: a data table monitoring unit 201; the data table monitoring unit 201 is used to monitor the business status of the data tables in each business system, and output a business status change reminder when the business status of the data in the data tables in each business system changes.

[0075] Furthermore, the technical status change data acquisition module 200 also includes: a business status identification unit 202; the business status identification unit 202 is used to identify the business status of the data in the changed data table according to the business status change reminder, so as to determine whether the business status of the data in the changed data table meets the writing condition, and obtain the corresponding data when the business status of the data in the changed data table meets the writing condition; the corresponding data is the data whose business status meets the writing condition.

[0076] Furthermore, the technical status change data collection module 200 also includes: a data writing unit 203; the data writing unit 203 is used to write the corresponding data into the information center database 400.

[0077] Specifically, in the embodiment of the present invention, a data change trigger is established in a database of each business system (such as a capital raising system, an interface system, a file review system, etc.) with multiple data tables (including but not limited to a capital raising data master table, an interface data master table, a file data master table, etc.). When the data in the data table changes, a change reminder is automatically triggered. At this time, the data table monitoring unit 201 can monitor the change of the data business status in the data table, and then output a business status change reminder; then, the business status identification unit 202 identifies the business status of the changed data based on the business status change reminder. If its business status is updated and the updated status is effective, it is judged that the write condition is met. At this time, the relevant data (i.e., the data whose status is changed and the updated status is effective) can be written into the information center database 400. Among them, the data table trigger in the database of each business system is an event that is automatically triggered after the table data changes (including adding, modifying, and deleting data). The business status identification unit 202 can compare the data before and after the update of a field. For example, if the status before the update is in approval and the status after the update is effective, it can be judged that the data has just taken effect and meets the write condition. Finally, the data writing unit 203 can collect and write the relevant data into the information center database 400. The written data includes but is not limited to: code, version, title, keyword, change content description, etc. The business rules of the keywords of the changed data are the same as the business rules of the keywords in the design input maintenance module 100.

[0078] In an embodiment of the present invention, the information processing and push module 300 is used to read the change data in the information center database 400, process the change data, summarize the change information, and push the change information to the target terminal; the change data includes: design file information and / or business status update data.

[0079] Optionally, in an embodiment of the present invention, the information processing and push module 300 includes: a data reading unit 301 and a data processing unit 302; the data reading unit 301 is used to read the change data in the information center database 400; the data processing unit 302 is used to process the change data and obtain keywords of the change data.

[0080] Furthermore, the information processing and push module 300 also includes: an information matching unit 303 and an information extraction unit 304; the information matching unit 303 is used to search in the information center database 400 according to the keywords of the change data, and obtain business association relationship information in the information center database 400 that matches the keywords of the change data; the information extraction unit 304 is used to extract corresponding volume drawing information according to the business association relationship information.

[0081] Furthermore, the information processing and pushing module 300 also includes: an information aggregation unit 305 and an information pushing unit 306; the information aggregation unit 305 is used to obtain and aggregate the corresponding designer information according to the volume drawing information; the information pushing unit 306 is used to push the change information to the target terminal according to the aggregated designer information.

[0082] Specifically, the data reading module first reads the collected change data, then the data processing module identifies the corresponding keywords, and then the information matching unit 303 retrieves the keywords input by the design input maintenance module 100 in the information center database 400 according to the keywords, and then the information extraction unit 304 quickly and accurately extracts the volume drawing information according to the corresponding business association information, and finally the information aggregation unit 305 aggregates the information according to the designer of the volume drawing, and pushes the change information to the aggregated designer through the information push unit 306 (that is, pushes it to the target terminal, where the target terminal is the terminal used by the corresponding designer, which can be a mobile phone, tablet, computer, etc.).

[0083] In the embodiment of the present invention, the information center database 400 is used to store design file information and business association relationship information, business status update data written by the technical status change data collection module 200, and data processed by the storage information processing and push module 300.

[0084] Specifically, the information center database 400 can store the business relationship between the design files input by the design input maintenance module 100 and their design inputs, store various types of technical status change information collected by the technical status change data acquisition module 200, and store data processed by the information processing and push module 300. At the same time, it can also provide the information processing and push module 300 with the business relationship between the stored design files and their design inputs, various types of technical status change information, etc.

[0085] The personal subscription information module 500 is used to match subscription information according to keywords of the change data, obtain corresponding personal subscription information, and push change information based on the corresponding personal subscription information.

[0086] refer to Figure 3 , Figure 3A method for pushing changes in the design technical status of a nuclear power project provided by the present invention can be applied to a system for pushing changes in the design technical status of a nuclear power project disclosed in an embodiment of the present invention.

[0087] Specifically, Figure 3 As shown, the method for pushing the design technical status change of the nuclear power project includes the following steps:

[0088] Step S301: obtaining design file information and business association relationship information, and writing the design file information and business association relationship information into the information center database 400.

[0089] In an embodiment of the present invention, obtaining design file information and business association relationship information, and writing the design file information and business association relationship information into the information center database 400 includes: receiving design file information input by a user; reading the association relationship information of the design file during the process of the user inputting the design file information; identifying keywords of the design file information and the business association relationship information to obtain the keywords of the design file information; and writing the design file information and the business association relationship information into the information center database 400 based on the keywords.

[0090] Step S302: Collecting business status update data, and writing the business status update data into the information center database 400.

[0091] In an embodiment of the present invention, collecting business status update data and writing the business status update data into the information center database 400 includes: monitoring the business status of the data tables in each business system, and outputting a business status change reminder when the business status of the data in the data tables in each business system changes; identifying the business status of the data in the changed data table according to the business status change reminder, and obtaining the business status of the changed data in the changed data table; judging whether the business status of the data in the changed data table meets the write condition according to the business status of the changed data; if the write condition is met, obtaining the corresponding data; the corresponding data is the data whose business status meets the write condition; if the write condition is not met, writing; and writing the corresponding data into the information center database 400.

[0092] Step S303: Read the change data in the information center database 400, process the change data, summarize the change information, and push the change information to the target terminal. The change data includes: design file information and / or business status update data.

[0093] In an embodiment of the present invention, reading the change data in the information center database 400, processing the change data, and summarizing the change information, and pushing the change information to the target terminal includes: reading the change data in the information center database 400; processing the change data to obtain keywords of the change data; searching the information center database 400 according to the keywords of the change data to obtain business association relationship information in the information center database 400 that matches the keywords of the change data; extracting corresponding volume drawing information according to the business association relationship information; obtaining corresponding designer information according to the volume drawing information and summarizing it; and pushing the change information to the target terminal according to the summarized designer information.

[0094] Furthermore, in an embodiment of the present invention, the method for pushing changes in the design technical status of a nuclear power project also includes: matching subscription information according to keywords of the change data to obtain corresponding personal subscription information; and pushing the change information based on the corresponding personal subscription information.

[0095] It should be noted that, in the embodiment of the present invention, there is no sequence relationship among step S301, step S302 and step S303, and the specific sequence is based on the actual design information maintenance and the triggering of the changes of each entity.

[0096] The present invention can effectively reduce the problem of inconsistent technical status caused by technical changes in the design field of nuclear power plants. By maintaining the technical information of the design technology input of the design document, the present invention constructs an entity upstream and downstream relationship system in the nuclear power design field based on the design document as the core, and automatically collects the change information of each entity through information technology means. The information of both is concentrated in the information center database 400, and after being processed and summarized by the information processing and push module 300, the change information is pushed to the relevant responsible persons in a timely and accurate manner. At the same time, it can also solve the problem of inconsistent technical status caused by incomplete analysis of technical status changes caused by human factors in the existing solution. For the changes triggered in the technical change process, the present invention can automatically collect relevant change information and push it to the personnel who did not participate in the change process due to human errors. Furthermore, due to the use of keyword matching technology, the matching efficiency of the present invention is improved compared with the traditional multi-field classification query matching method by type, which can be improved by at least 75%.

[0097] In addition, an electronic device of the present invention includes a memory and a processor; the memory is used to store a computer program; the processor is used to execute the computer program to implement a method for pushing a change in the design technical status of a nuclear power project as described in any one of the above. Specifically, according to an embodiment of the present invention, the process described with reference to the flowchart above can be implemented as a computer software program. For example, an embodiment of the present invention includes a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program contains a program code for executing the method shown in the flowchart. In such an embodiment, the computer program can be downloaded and installed by an electronic device and when executed, it executes the above functions defined in the method of the embodiment of the present invention. The electronic device in the present invention can be a terminal such as a notebook, a desktop, a tablet computer, a smart phone, or a server.

[0098] In addition, a storage medium of the present invention stores a computer program thereon, and when the computer program is executed by a processor, it implements any one of the above methods for pushing the design technical status change of a nuclear power project. Specifically, it should be noted that the above storage medium of the present invention may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present invention, a computer-readable storage medium may be any tangible medium containing or storing a program, which may be used by an instruction execution system, device or device or used in combination with it. In the present invention, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. Such propagated data signals may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer readable signal media may also be any computer readable medium other than computer readable storage media, which may send, propagate, or transmit programs for use by or in conjunction with an instruction execution system, apparatus, or device. The program code contained on the computer readable medium may be transmitted using any suitable medium, including but not limited to: wires, optical cables, RF (radio frequency), etc., or any suitable combination of the above.

[0099] The computer-readable medium may be included in the electronic device, or may exist independently without being incorporated into the electronic device.

[0100] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.

[0101] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0102] The steps of the method or algorithm described in conjunction with the embodiments disclosed herein may be implemented directly using hardware, a software module executed by a processor, or a combination of the two. The software module may be placed in a random access memory (RAM), a memory, a read-only memory (ROM), an electrically programmable ROM, an electrically erasable programmable ROM, a register, a hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.

[0103] The above embodiments are only for illustrating the technical concept and features of the present invention, and their purpose is to enable people familiar with the technology to understand the content of the present invention and implement it accordingly, and they cannot limit the scope of protection of the present invention. All equivalent changes and modifications made to the scope of the claims of the present invention should fall within the scope of the claims of the present invention.

Claims

1. A system for pushing changes in design technical status of nuclear power projects, characterized in that: include: A design input maintenance module, the design input maintenance module is used to receive the design file information input by the user, and write the design file information and business association relationship information into the information center database; The design file information includes: upstream funding information, interface data information and upstream file information; A technical status change data collection module, which is used to monitor the business status of data in the data tables of each business system, and when the business status of the data in the data tables meets the writing conditions, collect the corresponding business status update data and write it into the information center database; An information processing and push module, which is used to read the change data in the information center database, process the change data, summarize the change information, and push the change information to the target terminal; the change data includes: the design file information and / or the business status update data; The information center database is used to store the design file information and business association information, the business status update data written by the technical status change data acquisition module, and the data processed by the information processing and push module.

2. The nuclear power project design technical status change push system according to claim 1, characterized in that: The design input maintenance module includes: a receiving unit, an association relationship identification unit, a keyword identification unit and an information writing unit; The receiving unit is used to receive the design file information input by the user; The association relationship identification unit is used to read the business association relationship information of the design file when the user inputs the design file information; The keyword recognition unit is used to recognize keywords of the design file information and the business association relationship information to obtain the keywords of the design file information; The information writing unit is used to write the design file information and the business association relationship information into the information center database based on the keyword.

3. The nuclear power project design technical status change push system according to claim 1, characterized in that: The technical status change data acquisition module includes: a data table monitoring unit; The data table monitoring unit is used to monitor the business status of the data table in each business system, and output a business status change reminder when the business status of the data in the data table in each business system changes.

4. The nuclear power project design technical status change push system according to claim 3 is characterized in that: The technical status change data acquisition module also includes: a business status identification unit; The business status identification unit is used to identify the business status of the data in the changed data table according to the business status change reminder, so as to determine whether the business status of the data in the changed data table meets the writing condition, and obtain corresponding data when the business status of the data in the changed data table meets the writing condition; the corresponding data is the data whose business status meets the writing condition.

5. The nuclear power project design technical status change push system according to claim 4 is characterized in that: The technical status change data acquisition module also includes: a data writing unit; The data writing unit is used to write the corresponding data into the information center database.

6. The nuclear power project design technical status change push system according to claim 1, characterized in that: The information processing and pushing module includes: a data reading unit and a data processing unit; The data reading unit is used to read the changed data in the information center database; The data processing unit is used to process the changed data to obtain a keyword of the changed data.

7. The nuclear power project design technical status change push system according to claim 6, characterized in that: The information processing and pushing module also includes: an information matching unit and an information extraction unit; The information matching unit is used to search the information center database according to the keyword of the changed data, and obtain the business association relationship information matching the keyword of the changed data in the information center database; The information extraction unit is used to extract corresponding volume drawing information according to the business association relationship information.

8. The nuclear power project design technical status change push system according to claim 7, characterized in that: The information processing and pushing module also includes: an information aggregation unit and an information pushing unit; The information summarizing unit is used to obtain and summarize the corresponding designer information according to the volume drawing information; The information pushing unit is used to push the change information to the target terminal according to the summarized designer information.

9. The nuclear power project design technical status change push system according to claim 1, characterized in that: Also includes: Personal subscription information module; The personal subscription information module is used to match subscription information according to the keywords of the change data, obtain corresponding personal subscription information, and push change information based on the corresponding personal subscription information.

10. A method for pushing changes in the design technical status of a nuclear power project, applied to the system for pushing changes in the design technical status of a nuclear power project according to any one of claims 1 to 9, characterized in that: The following steps are involved: Acquire design file information and business association relationship information, and write the design file information and business association relationship information into the information center database; Collecting business status update data and writing the business status update data into the information center database; Read the changed data in the information center database, process the changed data, summarize the changed information, and push the changed information to the target terminal; The change data includes: the design file information and / or the business status update data.

11. The method for pushing the change of design technical status of a nuclear power project according to claim 10, characterized in that: The obtaining of the design file information and the business association relationship information, and writing the design file information and the business association relationship information into the information center database includes: Receive design file information input by the user; When the user inputs the design file information, the association relationship information of the design file is read; Identifying keywords of the design file information and the business association relationship information to obtain the keywords of the design file information; The design file information and the business association relationship information are written into the information center database based on the keyword.

12. The method for pushing the change of design technical status of a nuclear power project according to claim 10, characterized in that: The collecting of service status update data and writing the service status update data into the information center database comprises: Monitor the business status of the data tables in the business systems, and output a business status change reminder when the business status of the data in the data tables in the business systems changes; Identify the business status of the data in the changed data table according to the business status change reminder, and obtain the business status of the changed data in the changed data table; Determining whether the business status of the data in the changed data table meets the write condition according to the business status of the changed data; If the write condition is met, the corresponding data is obtained; the corresponding data is data whose business status meets the write condition; if the write condition is not met, the data is written; The corresponding data is written into the information center database.

13. The method for pushing the change of design technical status of a nuclear power project according to claim 10, characterized in that: The reading of the change data in the information center database, processing the change data and summarizing the change information, and pushing the change information to the target terminal includes: Reading the changed data in the information center database; Processing the changed data to obtain a keyword of the changed data; Searching the information center database according to the keyword of the changed data to obtain the business association relationship information matching the keyword of the changed data in the information center database; Extracting corresponding volume drawing information according to the business association relationship information; Obtain and summarize the corresponding designer information according to the volume drawing information; The change information is pushed to the target terminal according to the summarized designer information.

14. The method for pushing the change of design technical status of a nuclear power project according to claim 10, characterized in that: The method further comprises: Matching subscription information according to the keywords of the changed data to obtain corresponding personal subscription information; Change information is pushed based on the corresponding personal subscription information.

15. A storage medium, characterized in that: The storage medium stores a computer program, and the computer program is suitable for being loaded by a processor to execute the steps of the method for pushing changes in the design technical status of a nuclear power project as described in any one of claims 10 to 14.

16. An electronic device, characterized in that: It comprises a memory and a processor, wherein the memory stores a computer program, and the processor executes the steps of the method for pushing changes in the design technical status of a nuclear power project as described in any one of claims 10 to 14 by calling the computer program stored in the memory.