Step-by-step MRP method, system, equipment and medium
By using a step-by-step MRP method, combined with a BOM structure and an APS system, the problem of inaccurate material requirements in multi-variety, small-batch orders under traditional MRP was solved. This enabled precise matching of production plans and efficient collaboration in the supply chain, thereby enhancing the company's market competitiveness.
Patent Information
- Application Number
- CN202511602952.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-04
- Publication Date
- 2026-02-13
AI Technical Summary
Traditional MRP struggles to handle the complex relationships between multiple product types and small batch orders, leading to inaccurate material requirements calculations, inventory backlogs, and production interruptions, which negatively impact a company's competitiveness.
The step-by-step MRP method is adopted, which combines the product BOM structure, available inventory and safety stock to calculate the net demand for production parts. The production plan is formulated through the APS system, the start and completion times are generated, and the production and procurement are precisely matched by combining the workshop scheduling and supplier delivery plan.
It improved the accuracy and feasibility of production planning, enhanced the company's responsiveness to market changes, optimized the allocation of production resources, and reduced production costs and inventory backlog.
Smart Images

Figure CN121526152A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of order data processing, and in particular to a step-by-step MRP method, system, device and medium. Background Technology
[0002] In discrete manufacturing, material availability is crucial. Only with complete material availability can the continuity of the production process be ensured, interruptions caused by missing parts be prevented, the additional costs of emergency procurement be avoided, and thus the company's market competitiveness be enhanced. In manufacturing companies, Material Requirements Planning (MRP) is the core tool for ensuring accurate material requirements calculations and timely material supply.
[0003] Traditional modular MRP systems rely on unlimited resources and extend the lead time for materials at all levels, using high inventory levels to ensure sufficient materials. However, multi-variety, small-batch orders typically involve complex product structures and multi-level component supply relationships. The demand for components at different levels can vary due to adjustments in demand dates, making it difficult for traditional MRP systems to accurately handle such complex relationships. Summary of the Invention
[0004] In order to solve the problem that traditional MRP is difficult to handle multi-variety, small-batch orders, this application provides a step-by-step MRP method, system, device and medium.
[0005] In a first aspect, this application provides a step-by-step MRP method, including: Obtain order information and calculate the net required quantity of production parts by combining the product bill of materials (BOM) structure, available inventory, and safety stock. Based on the net demand quantity and production resource information, a production plan is formulated through the APS system to generate the start and completion times of the production parts. Based on the production plan, a workshop operation plan is formulated through workshop scheduling calculations; Based on the start and completion times and the material supply lead time of the production parts, calculate the demand time and quantity of the purchased parts, and formulate a procurement plan; Based on the procurement plan and the workshop operation plan, a supplier delivery plan is formulated.
[0006] By adopting the above technical solutions, and combining the product BOM structure, available inventory, and safety stock, the net demand for production parts is calculated to ensure an accurate match between the quantity of production parts and order information requirements, reducing ineffective production and inventory backlog. The introduction of an APS system to formulate production plans and generate start-up and completion times fully considers resource constraints such as equipment capacity and manpower hours, ensuring the production plan's executability in the time dimension. Linking the demand time of procured parts with the start-up and completion times of production parts, and coordinating workshop scheduling with supplier delivery plans, shortens the entire cycle from order receipt to product delivery. Addressing the characteristics of discrete manufacturing—multiple varieties and small batches of orders—the step-by-step process effectively handles complex product structures and multi-level component supply relationships by processing production parts and procured parts in a layered manner, improving the company's responsiveness to diverse orders.
[0007] In one specific implementation, the above method further includes: Collect workshop equipment data, including real-time operating data, historical fault data, process requirements for corresponding processes, and production task-related data; Construct a probability model for equipment failure, perform working condition clustering and failure time series correlation analysis on the workshop equipment data, and output the failure risk level and corresponding probability range of the equipment under different working conditions. Based on the aforementioned fault risk level and corresponding probability range, calculate the buffer capacity reservation ratio; Based on the production plan, the buffer capacity reservation ratio is converted into a corresponding buffer time, and the production plan is adjusted accordingly.
[0008] By adopting the above technical solutions and establishing a probabilistic model based on historical failure data, buffer capacity is reserved, allowing production plans to maintain a certain degree of flexibility in the face of equipment failures and reducing the disruption of the entire process caused by single-point failures. The buffer time setting provides a window for equipment maintenance and temporary resource allocation, avoiding production stoppages and order delays caused by sudden failures, reducing additional costs such as emergency procurement, and indirectly improving production efficiency and order fulfillment rates. The buffer capacity reservation ratio is dynamically calculated based on failure probability, rather than a fixed redundancy, avoiding resource waste caused by excessive reservation while ensuring the stability of key processes, achieving a balance between controllable risk and efficient resource utilization.
[0009] In one specific implementation, the above method further includes: Collect cyclical production data, including historical production cycle production plan data, actual execution data, order change data, and market demand forecast data; Based on the aforementioned periodic production data, combined with product demand characteristics and order priorities, the demand fluctuations for each of the aforementioned production parts are output; Calculate demand volatility over different periods by using a sliding time window; The demand volatility is converted into the corresponding volatility time, and the workshop operation plan is adjusted accordingly.
[0010] By adopting the above technical solution, demand volatility is calculated based on historical and latest plans, and this volatility is converted into volatility time. This allows workshop operation plans to anticipate demand changes in advance, reducing plan failures caused by order changes. The volatility time setting provides room for production adjustments. When demand volatility is low, plans remain stable to reduce resource waste; when demand volatility is high, capacity and material supply are adjusted based on volatility time to ensure production can respond quickly to market changes. Continuous calculation of demand volatility reflects market demand trends, providing data support for long-term capacity expansion, equipment procurement, and staffing, making capacity planning more aligned with actual needs and reducing resource idleness or insufficient capacity.
[0011] In a specific feasible implementation, the above calculation of the required time and quantity of the purchased parts includes: The required time of each of the purchased components is bound to the start time of each of the associated production components, and the associated production components are determined through BOM hierarchical mapping.
[0012] By adopting the above technical solutions, the BOM hierarchical mapping locks in the relationship between purchased parts and production parts, ensuring that the demand time of purchased parts strictly matches the start time of production parts, guaranteeing material availability and reducing inventory. It simplifies the management complexity of multi-level BOMs, clearly defining the relationships through BOM hierarchical mapping, allowing procurement plans to be directly traced to specific production stages, improving the transparency and traceability of plans, and reducing manual verification costs. The binding of purchased part demand time and production start time can be synchronously transmitted to suppliers, enabling them to accurately predict delivery nodes, allocate capacity and logistics resources in advance, reduce delivery delays caused by information asymmetry, and improve the responsiveness of the entire supply chain.
[0013] In one specific implementation, the above method further includes: Based on the lock-in period of the production part's online plan, the workshop operation plan is broken down into daily workshop operation plans; Based on the workshop daily operation plan and the material supply lead time, the supplier delivery plan is broken down into supplier daily delivery plans on a daily basis.
[0014] By adopting the above technical solutions, the workshop operation plan is broken down into daily operation plans, ensuring that the equipment, personnel, and material requirements for each process are accurate to the day. This guarantees that workshop production proceeds in an orderly manner on a daily basis, refining the granularity of the plan and improving execution accuracy. Supplier delivery plans are also broken down into daily delivery plans, combined with material supply lead times, to achieve just-in-time delivery and reduce inventory costs. By implementing a plan lock-in period, the stability of short-term daily operation and delivery plans is ensured, reducing the disruption to production and the supply chain caused by frequent changes, enabling suppliers to cooperate effectively, and improving overall collaborative efficiency.
[0015] In one specific implementation, the above method further includes: The production plan is updated on a rolling basis according to a preset cycle, and the final schedule of the production plan is updated at the beginning of each preset cycle.
[0016] By adopting the above technical solutions, production plans are updated on a rolling basis according to a preset cycle, ensuring that the plans can incorporate the latest orders, inventory changes, equipment status, and other information in a timely manner, maintaining the synchronization between the plan and the actual situation. In the rolling update mode, long-cycle plans provide an overall direction, while short-cycle updates focus on recent scheduling, ensuring long-term production stability. The rolling updated production plans can be simultaneously transmitted to suppliers, enabling them to adjust their capacity and supply plans in advance, ensuring smooth long-term supply chain collaboration.
[0017] In one specific implementation, the above method further includes: Receive production anomaly events reported by the system; Based on the aforementioned production anomalies and the lock-in period for the online schedule, the workshop operation plan and the supplier delivery plan are adjusted.
[0018] By adopting the above technical solutions, abnormal events are received in real time. Combined with the online plan lock-in period, workshop operation plans are optimized in a timely manner to avoid the spread of abnormalities and the resulting process shutdowns, thus reducing order delay losses. After production anomalies are adjusted, supplier delivery plans are adjusted simultaneously, enabling suppliers to be aware of changes in material demand in a timely manner, avoiding material waste or shortages caused by production adjustments, and ensuring that the supply chain and production rhythm are always matched. By establishing a closed-loop mechanism of anomaly detection—plan adjustment—supply chain linkage, the production system possesses self-healing capabilities.
[0019] Secondly, this application also provides a distributed MRP system, comprising: The calculation module is used to calculate the net demand quantity of production parts and the demand quantity of purchased parts; The scheduling module is used to create production plans, workshop operation plans, and procurement plans. The instruction generation module is used to formulate supplier delivery plans and issue them to suppliers; The dynamic adjustment module is used to adjust and update the production plan in real time.
[0020] By adopting the above technical solutions, the entire process of demand calculation, planning, and delivery instruction issuance for both production and procurement parts is automated, reducing errors caused by manual operation and improving planning efficiency. The linkage between the calculation module, scheduling module, and dynamic adjustment module enables real-time sharing of data such as inventory, capacity, orders, and production progress. This allows production plans, procurement plans, and supplier delivery plans to be formulated based on a unified data foundation, improving the consistency and accuracy of the plans. The dynamic adjustment module can respond in real-time to changes such as production anomalies and demand fluctuations, synchronously updating plans at each stage. This allows the system not only to formulate initial plans but also to continuously optimize throughout its entire lifecycle, meeting the complex production needs of discrete manufacturing industries characterized by diverse varieties, small batches, and high variability.
[0021] Thirdly, this application also provides an electronic device, including: a processor and a memory; wherein the memory stores a computer program adapted to be loaded by the processor and executed by the above-described method steps.
[0022] Fourthly, this application also provides a computer storage medium storing multiple instructions, which are adapted to be loaded by a processor and executed in accordance with the above-described method steps.
[0023] In summary, this application includes at least one of the following beneficial effects: 1. This application adopts a step-by-step decoupling and layered locking technical approach, which generates supplier delivery plans by accurately calculating production part requirements, scheduling production plans at the weekly granular level, dynamically back-calculating procurement part requirements, and rigidly locking daily workshop plans. This improves the accuracy and feasibility of production plans, enhances the company's responsiveness to market changes, optimizes the allocation of production resource information, and reduces production costs.
[0024] 2. This application achieves autonomous absorption of production disturbances through a three-tiered buffering mechanism based on equipment failure models, demand fluctuation algorithms, and anomaly response engines. It improves the plan achievement rate under sudden equipment failures, significantly enhancing supply chain resilience and system robustness.
[0025] 3. This application drives improvements in inventory turnover, reduces material availability waiting time, and lowers the frequency of plan rescheduling by using process-level time anchors as the central focus. This forms an efficiency-enhancing model of plan locking, resource matching, and execution collaboration, providing a replicable solution for the digitalization of manufacturing. Attached Figure Description
[0026] Figure 1 This is a flowchart illustrating a step-by-step MRP method provided in an embodiment of this application; Figure 2This is another flowchart illustrating a step-by-step MRP method provided in an embodiment of this application; Figure 3 This is a schematic diagram of a BOM hierarchy provided in an embodiment of this application; Figure 4 This is a schematic diagram of a production plan provided in an embodiment of this application; Figure 5 This is a schematic diagram of a procurement plan provided in an embodiment of this application; Figure 6 This is a schematic diagram of a workshop operation plan and supplier delivery plan provided in an embodiment of this application; Figure 7 This is a schematic diagram of the structure of an electronic device provided in an embodiment of this application.
[0027] Explanation of reference numerals in the attached figures: 600, electronic device; 601, processor; 602, communication bus; 603, user interface; 604, network interface; 605, memory. Detailed Implementation
[0028] The terminology used in the following embodiments of this application is for the purpose of describing particular embodiments only and is not intended to be limiting of this application. As used in the specification of this application, the singular expressions “a,” “an,” “the,” “the,” and “this” are intended to include the plural expressions as well, unless the context clearly indicates otherwise. It should also be understood that the term “and / or” as used in this application refers to any or all possible combinations including one or more of the listed items.
[0029] Hereinafter, the terms "first" and "second" are used for descriptive purposes only and should not be construed as implying or suggesting relative importance or implicitly indicating the number of indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature, and in the description of the embodiments of this application, unless otherwise stated, "multiple" means two or more.
[0030] The technical solutions in the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments.
[0031] Please see Figure 1 and Figure 2 , Figure 1 , Figure 2A flowchart illustrating a step-by-step MRP method according to an embodiment of this application is provided. This method can be implemented using a computer program, a microcontroller, or run on an enterprise-level recommendation system based on a large language model. The computer program can be integrated into a computer device or run as a standalone utility application. Specifically, the method includes steps S100 to S500, as follows: S100. Obtain order information and calculate the net demand quantity of production parts by combining the product BOM structure, available inventory, and safety stock. Specifically, in this embodiment of the application, the order information includes the quantity of products required by the customer and the delivery time; in this embodiment of the application, the product BOM refers to a tree structure used to express the hierarchical relationship and usage ratio between manufactured and purchased parts.
[0032] In this embodiment of the application, the available inventory refers to the actual amount of inventory that can be allocated. The available inventory is equal to the current inventory minus the frozen inventory, where the frozen inventory refers to the allocated but unused inventory.
[0033] In this embodiment of the application, safety stock refers to the amount of reserved inventory to cope with fluctuations. Since the production of parts may fluctuate during the production process, a certain amount of safety stock needs to be reserved. The safety stock of the production parts can be equal to the product of the standard deviation of the production parts in the previous 3 months and the safety factor, and the value of the safety factor can be 1.2-1.5.
[0034] In this embodiment of the application, net demand quantity refers to the quantity to be produced. Net demand quantity can be equal to gross demand quantity minus available inventory and safety stock. Gross demand quantity refers to the quantity of products to be produced in the order information.
[0035] refer to Figure 3 In the MRP (Material Requirements Planning) calculation stage for production parts, based on order information and the Bill of Materials (BOM) relationships of the product structure, the exact quantity of production parts necessary to meet order requirements is determined after deducting existing available inventory and safety stock. For example, if an order requires 100 units of product A, the BOM determines that each unit of product A requires one A1 semi-finished product, resulting in a gross requirement of 100 units of A1 semi-finished product. By querying the available inventory and safety stock of A1 semi-finished product, the net requirement of A1 semi-finished product is obtained by subtracting these from the gross requirement. For example, if the current inventory of A1 semi-finished product is 30 units, the frozen inventory is 5 units, the safety stock is 10 units, the available inventory is 25 units, and the net requirement is 65 units. After calculating the net requirement of A1 semi-finished product, the materials required for A1 semi-finished product can be obtained from the BOM, and the net requirement for each level of materials can be calculated progressively downwards.
[0036] S200. Based on the net demand quantity and production resource information, a production plan is formulated through the APS system to generate the start and completion times of the production parts. In this embodiment of the application, production resource information refers to the entities and capabilities required in the production process, including production equipment and its capacity, production personnel hours, the sequence of processes, and production lead time.
[0037] The Advanced Planning and Scheduling (APS) system in this embodiment includes two levels: production scheduling and shop floor scheduling. APS production scheduling belongs to the planning level and is used to generate start and completion times for production parts and to formulate production plans. The unit for start and completion times is typically weeks, and the time range of production scheduling is usually several weeks, such as 4 or 8 weeks, with weekly rolling scheduling.
[0038] refer to Figure 4 In this embodiment of the application, the production plan refers to a set of instructions that includes the start and completion times of the production parts, resource usage, and buffer time. The production plan can be divided into weekly plans and daily plans. In this embodiment of the application, the start and completion times include start time and completion time. Start time refers to the actual start time of the production part's process, and completion time refers to the theoretical end time of the production part's process.
[0039] Specifically, after receiving the net demand quantity and production resource information, the APS system parses the production resource information. For example, for wheel hub production, the process flow may include casting, machining, and painting. After obtaining the process flow, the APS system generates the standard working hours for each process based on the required production equipment, equipment capacity, production man-hours, sequence, and lead time. Based on the standard working hours and preset buffer times, the APS system generates start and completion times. The start time can be equal to the sum of the completion time of the previous process and the buffer time, and the completion time can be equal to the sum of the start time and the standard working hours.
[0040] S300. Based on the production plan, formulate a workshop operation plan through workshop scheduling calculation; In this embodiment of the application, workshop scheduling calculation refers to the optimization process of breaking down the production plan into process-level task sequences and resolving resource conflicts; in this embodiment of the application, workshop operation plan refers to the equipment or workstation instructions for executing production, which may include process flow and process time nodes.
[0041] After the APS system generates a production plan, it loads real-time resource status, including equipment availability and material conditions, through shop floor scheduling calculations, and breaks down the production plan into hourly task units. Simultaneously, the shop floor scheduling calculations need to detect dynamic conflicts; for example, when equipment overload is detected, buffer time can be inserted; when material shortage is detected, the sequence of that process in the process flow can be postponed. After decomposition and optimization, a shop floor work plan is generated, including the final process flow and hourly process time nodes. The process flow can include processing details, equipment arrangements, and operators for each process, guiding the orderly conduct of production activities on the shop floor; the process time nodes can include the start and completion times of each process.
[0042] S400. Based on the start and completion times and the material supply lead time of the production parts, calculate the demand time and quantity of the purchased parts, and formulate a procurement plan. In this embodiment of the application, the material supply lead time refers to the entire cycle time from the issuance of the procurement plan to the delivery of the procured parts and their readiness for production, which may include supplier response time and logistics time; the demand time for the procured parts in this embodiment of the application is the same as the start time of the corresponding production parts.
[0043] In this embodiment of the application, the required quantity of a purchased part can be equal to the net required quantity of the corresponding production part. Specifically, when it is detected that the available inventory of a certain production part is less than the safety stock, the required quantity can be equal to the difference between the safety stock and the available inventory of the corresponding production part.
[0044] refer to Figure 5 In this embodiment of the application, the procurement plan refers to the required quantity and time of each procured item. The issuance time of the procurement plan can be equal to the difference between the required time and the material supply lead time. For example, if the required time of a certain procured item is August 25th and the material supply lead time is seven days, then the issuance time of the procured item is August 18th. In this embodiment of the application, the issuance time of the procured item refers to the time point at which it is issued to the supplier.
[0045] Specifically, material supply lead time can be adjusted based on historical lead time and load factor. Historical lead time can be the average material supply lead time over historical periods, while the load factor can include supplier capacity factor and logistics factor. The supplier capacity factor is used to mitigate supplier capacity fluctuations, and the logistics factor is used to address transportation anomalies. The material supply lead time for the current period can be equal to the product of the historical lead time and the supplier capacity factor and logistics factor.
[0046] S500. Based on the procurement plan and the workshop operation plan, formulate a supplier delivery plan.
[0047] refer to Figure 6The system inputs the procurement plan, binds it to the shop floor operation plan, integrates material requirements, generates a supplier delivery plan, and implements plan locking and dynamic response. Specifically, after binding the procurement plan to the shop floor operation plan, the start-up time of the corresponding production part can be accurate to the minute. For example, the required time for the production part in the procurement plan can be accurate to the date, while the shop floor operation plan can include the equipment operating time and material loading and unloading time for each process, thus accurateing the start-up time of the production part to the minute.
[0048] In this embodiment of the application, material requirements consolidation refers to consolidating all materials that suppliers should provide each day, including the different quantities and timings required in various procurement plans. After consolidating material requirements, a supplier delivery plan is generated on a daily basis.
[0049] Specifically, the workshop operation plan may include a preset online plan lock-in period, typically 1-3 days. During the online plan lock-in period, the workshop operation plan is accurate to the minute, and the main body of the plan is generally unchangeable; the start and completion times, equipment, workstations, and materials for each process will be fixed. The supplier delivery plan is also locked in simultaneously, ensuring timely delivery of required materials during the online plan lock-in period. Outside the online plan lock-in period, suppliers are allowed to dynamically adjust the supply quantity and timing as needed. After making dynamic adjustments, suppliers send them to the system, triggering a dynamic response mechanism. The system can calculate the available inventory and safety stock levels outside the online plan lock-in period based on the expected production volume within the lock-in period, thereby updating the workshop operation plan and supplier delivery plan accordingly.
[0050] Based on the above embodiments, as another optional embodiment, the step-by-step MRP method may further include: collecting workshop equipment data, including real-time operating data, historical fault data, process requirements of corresponding processes, and production task-related data; constructing an equipment fault probability model, performing working condition clustering and fault time sequence correlation analysis on the workshop equipment data, and outputting the fault risk level and corresponding probability interval of the equipment under different working conditions; calculating the buffer capacity reservation ratio based on the fault risk level and corresponding probability interval; and converting the buffer capacity reservation ratio into the corresponding buffer time based on the production plan, and adjusting the production plan.
[0051] In some embodiments, multi-dimensional operational data of workshop equipment is collected and structured workshop equipment data is generated.
[0052] Specifically, multi-dimensional operational data of workshop equipment is collected through cross-system data interfaces. Data sources include equipment sensors, the MES system, the process management module, and the ERP production task module. Real-time operational data may include the equipment's real-time load rate; historical fault data may include fault types and durations over a preset historical period (e.g., 12 months); corresponding process requirements include process accuracy; and production task-related data includes the type of parts currently being produced by the equipment and order delivery deadlines. After collection, invalid data with abnormal sensor fluctuations is removed, and missing historical fault records are supplemented, forming structured workshop equipment data.
[0053] In some embodiments, operating condition clustering and fault time sequence correlation analysis are used to construct a device failure probability model.
[0054] Specifically, unsupervised learning algorithms are used to categorize equipment operating states into three types: high-load conditions (e.g., load rate > 80%), normal conditions (e.g., load rate 40%-80%), and low-load conditions (e.g., load rate < 40%). For each type, historical fault records are further linked to statistically analyze the frequency of faults and average fault intervals under different conditions. For example, under high-load conditions, the equipment experiences an average of one fault every 100 hours of operation; under normal conditions, one fault occurs every 300 hours; and under low-load conditions, one fault occurs every 500 hours.
[0055] After clustering operating conditions, the system associates these conditions with the changing trends of operating condition parameters within a preset failure time window (e.g., 2 hours) before the failure occurs, outputting the failure risk level under different operating conditions. The failure risk level is divided into three categories: high risk, medium risk, and low risk, with corresponding probability ranges provided. For example, under high-risk operating conditions, the probability of equipment failure is >20%; under medium-risk operating conditions, the probability of equipment failure is 10%-20%; and under low-risk operating conditions, the probability of equipment failure is <10%.
[0056] In some embodiments, the buffer capacity reservation ratio is calculated based on the fault risk level and the corresponding probability range, combined with the process importance weight and the real-time operating condition deviation coefficient.
[0057] The formula for calculating the buffer capacity reservation ratio includes: Buffer capacity reserve ratio = Basic ratio coefficient ÷ Production reliability target × Process importance weight × Real-time operating condition deviation coefficient.
[0058] In this embodiment, the buffer capacity reserve ratio is used to determine the proportion of capacity that needs to be reserved in production to cope with equipment failure risks; the basic ratio coefficient is a benchmark ratio value set according to the equipment failure risk level; the production reliability target is a target parameter used to ensure the executability and stability of the production plan; the process importance weight is determined according to the supply chain dependency of the production parts; the real-time operating condition deviation coefficient is calculated by the relative deviation between the current equipment operating condition parameters (such as load rate) and the standard operating condition parameters, and is used to reflect the degree of difference between the current operating condition and the standard operating condition.
[0059] Among them, the production reliability target can be 99.5%; the basic proportional coefficient is set based on the failure risk level, for example, the basic proportional coefficient for high risk is 2%, the basic proportional coefficient for medium risk is 1%, and the basic proportional coefficient for low risk is 0.5%; the process importance weight is determined according to the supply chain dependence of the production parts, for example, the processing process weight of key components is 1.5, and that of ordinary components is 1.0. If the delay of the target process will cause more than 3 subsequent processes to stop, the weight of the target process will be increased by an additional 0.3; the real-time operating condition deviation coefficient refers to the relative deviation between the current operating condition parameters and the standard operating condition parameters. The real-time operating condition deviation coefficient = (current load rate - standard load rate) / standard load rate. For example, if the current load rate is 85% and the standard load rate is 70%, then the deviation coefficient ≈ 0.21.
[0060] In some embodiments, the formula for calculating the buffer time includes: Buffer time = theoretical processing time of the process × buffer capacity reserve ratio.
[0061] In this embodiment of the application, the buffer time is used to adjust the production plan to cope with the risk of equipment failure, avoid process conflicts, and ensure the production plan's ability to resist disturbances; the theoretical processing time of a process refers to the preset time required for a process to complete the corresponding production task under standard operating conditions.
[0062] If the buffer time calculation result is a decimal, it will be rounded up to an integer multiple of 0.5 hours.
[0063] In some embodiments, the dependencies between the target process and its preceding and subsequent processes are analyzed. If the target process is a preceding process, the buffer time needs to be added to the completion time of the target process, and at the same time, it is checked whether the start time of the subsequent process needs to be adjusted synchronously.
[0064] For example, if the original completion time of the preceding process was 12:00 on August 22, and the buffer time is 13:00 on August 22, and the original start time of the following process was 12:30 on August 22, then the start time of the following process needs to be adjusted to 13:00 on August 22 to avoid process conflicts.
[0065] If the target process is a subsequent process, the buffer time only needs to adjust its own completion time without affecting the preceding processes. The adjusted production plan is synchronized to the APS system to update the start and completion times of the production parts. Based on the above embodiment, as another optional embodiment, the step-by-step MRP method may further include: collecting periodic production data, including historical production cycle production plan data, actual execution data, order change data, and market demand forecast data; based on the periodic production data, combined with product demand characteristics and order priorities, outputting the demand fluctuations for each production part; calculating the demand volatility rate under different cycles through a sliding time window; converting the demand volatility rate into the corresponding fluctuation time, and adjusting the shop floor operation plan.
[0066] In some embodiments, cyclical production data for a preset production cycle (e.g., three months) is collected. This includes historical production planning data (planned output and planned start / end times for each production unit within each cycle); actual execution data (actual output and actual start / end times for each production unit); order change data (time points of order changes and the number of production units involved in the changes within each cycle); and market demand forecast data (changes in the product's demand share). After data collection, cross-system data verification compares the ERP's planned data with the MES's actual data, eliminating inconsistent and abnormal records to form a complete cyclical production dataset.
[0067] In some implementations, the demand fluctuations for each production unit are output by combining product demand characteristics and order priorities. Product demand characteristics include the similarity of product family demand characteristics; for example, semi-finished products A1 and A2 from the same product series have similar demands and can be grouped into the same analysis group. Order priorities include order priority weights; for example, urgent orders have a priority weight of 1.2, while regular orders have a priority weight of 1.0.
[0068] In some embodiments, a weighted sliding time window is used to calculate demand volatility. Specifically, the sliding window size is set to three production cycles, and the weights of each cycle within the window are allocated according to the principle of recent priority. For example, the weight of the previous cycle is 0.5, the weight of the cycle before that is 0.3, and the total weight is 1.
[0069] In some embodiments, the formula for calculating demand volatility includes: Demand volatility = Sum of absolute values of weighted deviations across periods ÷ Number of periods within the window.
[0070] In this embodiment of the application, the demand volatility is used to reflect the amplitude of the demand fluctuation of the production parts; the weighted deviation value of each period is the value obtained by multiplying the demand fluctuation of the production parts in each production cycle by the corresponding weight of that period in the sliding window.
[0071] If the demand volatility is negative, its absolute value is taken to represent the magnitude of the demand volatility, without distinguishing between positive and negative directions; the cycle-weighted deviation value is the product of the cycle's demand volatility and its corresponding weight.
[0072] For example, if the deviation of semi-finished product A1 fluctuates by -5% in cycle 1 (weight 0.2), +2% in cycle 2 (weight 0.3), and -1.8% in cycle 3 (weight 0.5), then the weighted deviation value is -1.3%, and the demand volatility is approximately 0.43%.
[0073] In some embodiments, the formula for calculating the fluctuation time includes: Fluctuation time = Basic fluctuation time × Process complexity coefficient × Resource load coefficient.
[0074] In this embodiment, the fluctuation time is used to adjust the workshop operation plan to cope with demand fluctuations; the basic fluctuation time corresponds to the demand fluctuation rate; the process complexity coefficient is set according to the number of processing steps in the process and is used to adjust the fluctuation time; the resource load coefficient is set according to the current equipment utilization rate and is used to adjust the fluctuation time, reflecting the current equipment load.
[0075] Among them, the basic fluctuation time corresponds to the demand volatility. For example, a demand volatility of 0.1%-0.5% corresponds to 0.5 hours, 0.5%-1% corresponds to 1 hour, and 1%-2% corresponds to 2 hours. The process complexity coefficient corresponds to the number of processing steps in the process. For example, when the process contains more than 3 processing steps, the coefficient is 1.2, and when the process contains less than 2 processing steps, the coefficient is 1.0. The resource load coefficient corresponds to the current equipment utilization rate. For example, when the current equipment utilization rate is >90%, the coefficient is 1.5, when the current equipment utilization rate is 70%-90%, the coefficient is 1.2, and when the current equipment utilization rate is <70%, the coefficient is 1.0.
[0076] Adjusting workshop operation plans based on fluctuation time. For example, the fluctuation rate of semi-finished product A1 is 0.43%, the basic fluctuation time is 0.5 hours, the process complexity coefficient is 1.2, and the resource load coefficient is 1.5. The original completion time of the process is 12:00 on August 22nd. Then the fluctuation time = 0.9 hours, rounded to 1 hour, and the adjusted completion time of the process is 13:00 on August 22nd. Example 1 Real-time operating data of the A1 semi-finished product production line was collected. The current load is 85%, and the standard load is 70%. There were 4 failures when the load was >80% in the past 12 months, with an average failure duration of 2 hours. The process accuracy is ±0.03mm. The A1 semi-finished product is the only precursor to product A, and the delivery deadline for product A is August 30th.
[0077] Clustering classifies the current operating condition into a high-load condition. Based on historical failure statistics, the failure probability under this condition is 15%, classifying it as medium risk, with a failure probability range of 10%-20%. The base proportion coefficient is set to 1%, the process importance weight is set to 1.8, the real-time operating condition deviation coefficient is approximately 0.21, and the production reliability target is set to 99.5%, resulting in a buffer proportion of approximately 0.38%.
[0078] The theoretical processing time for the A1 semi-finished product process is 72 hours, with a buffer time of approximately 0.27 hours, rounded down to 0.5 hours. This process is the preceding process for product A. The original completion time was 12:00 on August 22nd, which has been adjusted to 12:30 on August 22nd. The original start time for product A was 13:00 on August 22nd, so no synchronous adjustment is needed. Update the APS production plan accordingly.
[0079] Production data for A1 semi-finished products was collected over the past three periods (April-June). Specifically, April's planned output was 100 units, with 95 units actually produced; May's planned output was 100 units, with 102 units actually produced; and June's planned output was 110 units, with 108 units actually produced. There was one order change in May, with an additional 10 units added. Market forecasts indicate a 5% month-on-month increase in component demand in July. Demand fluctuations included -5% in April, +2% in May, and -1.8% in June. The demand trend for A1 semi-finished products is similar to that of the related A2 semi-finished products. A1 semi-finished products correspond to core customer orders for product A, with a weight of 1.2.
[0080] The sliding window spans three periods, with weights of 0.5 (June), 0.3 (May), and 0.2 (April), resulting in a weighted deviation of approximately 0.43%.
[0081] A volatility of 0.43% corresponds to a base volatility time of 0.5 hours. With a process complexity coefficient of 1.2 and an equipment load coefficient of 1.5, the volatility time is 0.9 hours, rounded to 1 hour. The completion time for the A1 semi-finished product CNC lathe process is further adjusted to 13:30 on August 22nd, and there are no other tasks scheduled from 13:30 to 14:30 on August 22nd. This is ultimately updated to the workshop work plan and synchronized with the MES system to guide production.
[0082] By establishing equipment failure probability modeling and a dynamic buffer time injection mechanism, a disturbance-resistant production planning framework can be constructed. This enables proactive management of equipment stochastic risks, significantly enhances planning robustness, and ensures the continuous and stable operation of the manufacturing system.
[0083] Based on the above embodiments, as another optional embodiment, the step of calculating the required time and quantity of the purchased parts may further include: the start and completion time includes the start time, and the required time of each purchased part is bound to the start time of each associated production part of each purchased part, wherein the associated production parts are determined through BOM hierarchical mapping.
[0084] In this embodiment, the demand time for the procured component is directly derived from the start time of the associated production component. For example, if the start time for semi-finished product A1 is August 18th, the demand for semi-finished product A1 is obtained through the Bill of Materials (BOM) as A1 material 1 and A1 material 2. In this case, the demand time for A1 material 1 and A1 material 2 is the same as the start time of semi-finished product A1, i.e., August 18th. Specifically, the system obtains the production plan for the current period, decomposes it level by level through the BOM, locates the procurement components at the bottom level from the production components at the top level of the production plan, and maps the specific relationship between the procurement components and the production components. This specific relationship may include the demand ratio and the start time of the associated production component. The start time of the associated production component is extracted to obtain the demand time of the corresponding procurement component. After binding the demand time of the procurement component with the start time of the associated production component, the system can directly query the demand time of the procurement component when formulating a procurement plan again.
[0085] Based on the above embodiments, as another optional embodiment, the step-by-step MRP method may further include: splitting the workshop operation plan into daily workshop daily operation plans based on the production part's online plan lock-in period; and splitting the supplier delivery plan into daily supplier daily delivery plans based on the daily workshop operation plans and the material supply lead time.
[0086] In this embodiment of the application, the online plan lock-in period refers to a rigid period in the workshop production plan that is not allowed to be adjusted, usually 1-3 days in the future, to avoid frequent changes to the production line; the workshop daily operation plan in this embodiment of the application refers to breaking down the workshop operation plan by day, and the start and completion time of each process can be accurate to the minute, to achieve precise production of materials; the supplier daily delivery plan in this embodiment of the application refers to breaking down the supplier delivery plan by day, to coordinate with the workshop daily operation plan, to achieve precise distribution of materials, and to reduce warehousing costs by increasing the frequency of supplier deliveries.
[0087] Specifically, the system receives the workshop operation plan and divides it into daily workshop operation plans, while also identifying the lock status of the daily workshop operation plans. For daily workshop operation plans within the lock-up period, a strict supplier delivery plan can be formulated based on the start time of each process to ensure the smooth execution of the production plan within the lock-up period. For daily workshop operation plans outside the lock-up period, buffer optimization can be performed based on the workshop operation plan and the supplier delivery plan to ensure the reliability and continuity of production.
[0088] In this embodiment, the supplier delivery plan also needs to be combined with the material supply lead time. The material supply lead time can include supplier response time and logistics time. Supplier response time refers to the time from when the supplier receives the supplier delivery plan to when all materials are prepared; logistics time refers to the time it takes for materials to be delivered from the supplier to the production line. The supplier's daily delivery plan is issued to the supplier before the material supply lead time to ensure that the supplier has sufficient time to process the delivery plan. By developing daily shop floor operation plans and supplier daily delivery plans accurate to the minute, a high degree of planning transparency can be maintained, making it easier to reduce potential confusion among all parties during plan execution. This effectively controls inventory costs while improving the company's responsiveness to market changes and the overall supply chain efficiency, providing a competitive advantage for the company in a volatile market environment.
[0089] Based on the above embodiments, as another optional embodiment, the step-by-step MRP method may further include: the production plan is updated on a rolling basis according to a preset cycle, and the final schedule of the production plan is updated at the beginning of each preset cycle.
[0090] In this embodiment, a preset period refers to a fixed time window (e.g., 4 hours), serving as the smallest time unit for plan updates and balancing plan stability and flexibility. Because actual production of parts fluctuates in real time, at the start of each preset period, the actual production volume of parts in the previous preset period is statistically analyzed. This actual production volume is compared with the planned production volume, and the production schedule for the current preset period is updated, including the target quantity of parts. For example, for semi-finished product A1, if the actual production volume in the previous preset period is less than the planned production volume, and the difference is 2 units, the planned production volume for the current preset period is increased by 2 units.
[0091] The specific duration of the preset cycle can be adjusted according to the production parts and the process flow. When the process flow itself is a long process (e.g., 8 hours), the preset cycle can be set to 8 hours to match the process flow. When the production parts are multi-variety, small-batch production parts, such as A material 1, A material 2, and A material 3 of product A, the preset cycle can be set to 2 hours. By updating the production plan according to the preset cycle, real-time feedback and optimization loop can be achieved during the actual execution of the production plan, thereby improving the reliability and stability of the production plan.
[0092] Based on the above embodiments, as another optional embodiment, the step-by-step MRP method may further include: receiving production anomaly events fed back by the system; adjusting the shop floor operation plan and the supplier delivery plan based on the production anomaly events and the online plan lock-in period.
[0093] In this embodiment, a production anomaly refers to a sudden situation that deviates from the plan during production, and is used for rapid response to anomalies. Normally, the workshop operation plan within the lock-in period of the production line plan cannot be changed. When a production anomaly occurs, the anomaly is handled first, and the original workshop operation plan can be appropriately adjusted based on the principle of minimum change. The principle of minimum change means not changing the original process flow, and the corresponding time nodes of the original processes are postponed by no more than one hour. For workshop operation plans outside the lock-in period of the production line plan, the anomaly is handled first, and adjustments can be made according to the regular process, postponing the corresponding time nodes of the original processes. After adjusting the workshop operation plan, the supplier delivery plan needs to be adjusted accordingly.
[0094] Specifically, different response times are set for different production anomalies to differentiate their severity. For example, a 5-minute response time can be set for anomalies such as equipment malfunctions or safety accidents, requiring priority handling; a 15-minute response time can be set for anomalies such as material shortages or quality abnormalities. Timely response to anomalies ensures the accurate execution of workshop operation plans during the online plan lock-in period and prevents the spread of anomalies.
[0095] This application also provides a step-by-step MRP system applied to a step-by-step MRP method, wherein the system includes: The calculation module is used to calculate the net demand quantity of production parts and the demand quantity of purchased parts; The scheduling module is used to create production plans, workshop operation plans, and procurement plans. The instruction generation module is used to formulate supplier delivery plans and issue them to suppliers; The dynamic adjustment module is used to adjust and update the production plan in real time.
[0096] Optionally, the calculation module is also used to calculate the probability of equipment failure and the buffer capacity reservation ratio, and convert the buffer capacity reservation ratio into buffer time; the calculation module is also used to calculate the demand volatility of production parts, and convert the demand volatility into volatility time.
[0097] Optionally, the scheduling module is also used to break down the workshop operation plan into daily workshop operation plans; the instruction generation module is also used to break down the supplier delivery plan into daily supplier delivery plans.
[0098] Optionally, the dynamic adjustment module is also used to receive buffer time and fluctuation time, and adjust the workshop operation plan and supplier delivery plan.
[0099] Optionally, a distributed MRP system may also include an Enterprise Resource Planning (ERP) module, used to integrate various internal resources to achieve integrated management of logistics, capital flow, and information flow, ensuring efficient collaborative operation among various departments; a Manufacturing Execution System (MES) module, applied at the shop floor level, serving as the execution link between production planning and operational implementation. MES receives production orders from ERP and provides feedback to ERP on the detailed execution status of these orders, involving data on personnel, machines, materials, methods, environment, measurement, molds, and production. Some MES systems also include team management functions, effectively improving the scientific and standardized nature of grassroots management while outputting high-quality frontline data; and a Product Lifecycle Management (PLM) module, spanning the entire product lifecycle, from the product concept stage to post-discontinuation disposal. It manages product design data and the design process, and centrally manages product-related technical documents, BOMs, formulas, and other data.
[0100] Specifically, during production execution, the APS system adjusts and optimizes the production plan based on real-time production data fed back from the MES system. The MES system, in turn, allocates production tasks to specific production equipment and operators based on the workshop scheduling provided by the APS system. Simultaneously, it monitors quality and equipment operation information during production and feeds this information (especially output quantity, equipment time and abnormal status, and mold occupancy status) back to the APS system. This allows the APS system to promptly understand the actual production situation and make corresponding decisions, such as adjusting the production sequence and reallocating resources, to ensure the smooth execution of the production plan.
[0101] It should be noted that the system provided in the above embodiments is only illustrated by the division of the above functional modules. In actual applications, the above functions can be assigned to different functional modules as needed, that is, the internal structure of the device can be divided into different functional modules to complete all or part of the functions described above. In addition, the system and method embodiments provided in the above embodiments belong to the same concept, and the specific implementation process can be found in the method embodiments, which will not be repeated here.
[0102] This application also provides a computer storage medium that can store multiple instructions. The instructions are adapted to be loaded by a processor and executed as a step-by-step MRP method according to the above embodiments. For the specific execution process, please refer to the detailed description of the above embodiments, which will not be repeated here.
[0103] Please refer to Figure 7 This application also discloses an electronic device. Figure 7 This is a schematic diagram of the structure of an electronic device disclosed in an embodiment of this application. The electronic device 600 may include: at least one processor 601, at least one communication bus 602, a user interface 603, at least one network interface 604, and a memory 605.
[0104] The communication bus 602 is used to enable communication between these components.
[0105] The user interface 603 may include a display screen and a camera. Optionally, the user interface 603 may also include a standard wired interface and a wireless interface.
[0106] The network interface 604 may optionally include a standard wired interface or a wireless interface (such as a Wi-Fi interface).
[0107] The processor 601 may include one or more processing cores. The processor 601 connects to various parts of the server using various interfaces and lines, and performs various server functions and processes data by running or executing instructions, programs, code sets, or instruction sets stored in the memory 605, and by calling data stored in the memory 605. Optionally, the processor 601 may be implemented using at least one hardware form of Digital Signal Processing (DSP), Field-Programmable Gate Array (FPGA), or Programmable Logic Array (PLA). The processor 601 may integrate one or a combination of several of the following: Central Processing Unit (CPU), Graphics Processing Unit (GPU), and modem. The CPU primarily handles the operating system, user interface, and applications; the GPU is responsible for rendering and drawing the content required for display; and the modem handles wireless communication. It is understood that the modem may also not be integrated into the processor 601 and may be implemented as a separate chip.
[0108] The memory 605 may include random access memory (RAM) or read-only memory. Optionally, the memory 605 may include a non-transitory computer-readable storage medium. The memory 605 may be used to store instructions, programs, code, code sets, or instruction sets. The memory 605 may include a program storage area and a data storage area, wherein the program storage area may store instructions for implementing an operating system, instructions for at least one function (such as touch function, sound playback function, image playback function, etc.), instructions for implementing the above-described method embodiments, etc.; the data storage area may store data involved in the above-described method embodiments, etc. Optionally, the memory 605 may also be at least one storage device located remotely from the aforementioned processor 601. (Refer to...) Figure 7 The memory 605, which serves as a computer storage medium, may include an operating system, a network communication module, a user interface module, and an application program using a distributed MRP method.
[0109] exist Figure 7 In the illustrated electronic device 600, the user interface 603 is mainly used to provide an input interface for the user and to acquire user input data; while the processor 601 can be used to call an application program storing a step-by-step MRP method in the memory 605. When executed by one or more processors 601, the electronic device 600 performs one or more methods as described in the above embodiments. It should be noted that, for the foregoing method embodiments, for the sake of simplicity, they are all described as a series of actions. However, those skilled in the art should understand that this application is not limited to the described order of actions, because according to this application, some steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also understand that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily essential to this application.
[0110] In the above embodiments, the descriptions of each embodiment have different focuses. For parts not described in detail in a certain embodiment, please refer to the relevant descriptions in other embodiments.
[0111] In the various embodiments provided in this application, it should be understood that the disclosed apparatus can be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative; for instance, the division of units is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some service interface; the indirect coupling or communication connection between apparatuses or units may be electrical or other forms.
[0112] The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the units can be selected to achieve the purpose of this embodiment according to actual needs.
[0113] Furthermore, the functional units in the various embodiments of this application can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated unit can be implemented in hardware or as a software functional unit.
[0114] If the integrated unit is implemented as a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage device (CMD). Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, or all or part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a memory and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods of the various embodiments of this application. The aforementioned memory includes various media capable of storing program code, such as USB flash drives, portable hard drives, magnetic disks, or optical disks.
[0115] The above are merely exemplary embodiments of this disclosure and should not be construed as limiting the scope of this disclosure. Any equivalent changes and modifications made in accordance with the teachings of this disclosure shall still fall within the scope of this disclosure. Other embodiments of this disclosure will readily conceive of those skilled in the art upon consideration of the specification and the disclosure of practical truths.
[0116] This application is intended to cover any variations, uses, or adaptations of this disclosure that follow the general principles of this disclosure and include common knowledge or customary techniques in the art not described in this disclosure. The specification and embodiments are to be considered exemplary only, and the scope and spirit of this disclosure are defined by the claims.
Claims
1. A step-by-step MRP method, characterized in that, include: Obtain order information and calculate the net demand quantity of production parts by combining the product BOM structure, available inventory, and safety stock. Based on the net demand quantity and production resource information, a production plan is formulated through the APS system to generate the start and completion times of the production parts. Based on the production plan, a workshop operation plan is formulated through workshop scheduling calculations; Based on the start and completion times and the material supply lead time of the production parts, calculate the demand time and quantity of the purchased parts, and formulate a procurement plan; Based on the procurement plan and the workshop operation plan, a supplier delivery plan is formulated.
2. The step-by-step MRP method according to claim 1, characterized in that, Also includes: Collect workshop equipment data, including real-time operating data, historical fault data, process requirements for corresponding processes, and production task-related data; Construct a probability model for equipment failure, perform working condition clustering and failure time series correlation analysis on the workshop equipment data, and output the failure risk level and corresponding probability range of the equipment under different working conditions. Based on the aforementioned fault risk level and corresponding probability range, calculate the buffer capacity reservation ratio; Based on the production plan, the buffer capacity reservation ratio is converted into a corresponding buffer time, and the production plan is adjusted accordingly.
3. The step-by-step MRP method according to claim 2, characterized in that, Also includes: Collect cyclical production data, including historical production cycle production plan data, actual execution data, order change data, and market demand forecast data; Based on the aforementioned periodic production data, combined with product demand characteristics and order priorities, the demand fluctuations for each of the aforementioned production parts are output; Calculate demand volatility over different periods by using a sliding time window; The demand volatility is converted into the corresponding volatility time, and the workshop operation plan is adjusted accordingly.
4. The step-by-step MRP method according to claim 1, characterized in that, The calculation of the required time and quantity of the purchased items includes: The required time of each of the purchased components is bound to the start time of each of the associated production components, and the associated production components are determined through BOM hierarchical mapping.
5. The step-by-step MRP method according to claim 1, characterized in that, Also includes: Based on the lock-in period of the production part's online plan, the workshop operation plan is broken down into daily workshop operation plans; Based on the workshop daily operation plan and the material supply lead time, the supplier delivery plan is broken down into supplier daily delivery plans on a daily basis.
6. The step-by-step MRP method according to claim 1, characterized in that, Also includes: The production plan is updated on a rolling basis according to a preset cycle, and the final schedule of the production plan is updated at the beginning of each preset cycle.
7. The step-by-step MRP method according to claim 1, characterized in that, Also includes: Receive production anomaly events reported by the system; Based on the aforementioned production anomalies and the lock-in period for the online schedule, the workshop operation plan and the supplier delivery plan are adjusted.
8. A step-by-step MRP system, based on the step-by-step MRP method as described in claims 1-7, characterized in that, include: The calculation module is used to calculate the net demand quantity of production parts and the demand quantity of purchased parts; The scheduling module is used to create production plans, workshop operation plans, and procurement plans. The instruction generation module is used to formulate supplier delivery plans and issue them to suppliers; The dynamic adjustment module is used to adjust and update the production plan in real time.
9. An electronic device, characterized in that, It includes a processor, a memory, a user interface, and a network interface. The memory is used to store instructions, the user interface and the network interface are used to communicate with other devices, and the processor is used to execute the instructions stored in the memory to cause the electronic device to perform the method as described in any one of claims 1-7.
10. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores multiple instructions suitable for being loaded by a processor and executed as described in any one of claims 1-7.