Bridge erecting machine column stress monitoring equipment
By using pressure sensors and isolation devices in the bridge rig, the force under the legs is monitored in real time, which solves the problem of excessive force under the flange plate during construction of the single guide beam bridge rig, and significantly improves construction safety and detection accuracy.
Patent Information
- Application Number
- CN202421302902.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-07
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-06-07
AI Technical Summary
During construction of existing single-guided beam bridge stairs, the bridge flange plates are under too much force and are prone to collapse or fragmentation, causing the bridge stairs to overturn, posing a greater safety risk.
A bridge-building machine column stress monitoring device is designed, using pressure sensors to monitor the stress of the legs in real time, isolate dust by fixing and movable shells, reduce temperature influence, and ensure detection accuracy.
The safety and reliability of the bridge staircase vias are improved, and the bridge flange plate fracturing and the bridge staircase rollover are avoided. The investment is small, which significantly improves the safety benefits.
Smart Images

Figure CN222027823U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway beam erection construction, in particular to a bridge erection machine column force monitoring device. Background Art
[0002] At present, the construction equipment used by domestic construction companies to erect highway beams is generally the DJ series single-beam bridge erecting machine (mainly including DJ180, DJ168 and other series), because it can erect bridges with a maximum curve radius of 300 meters, the equipment structure is simple, and the transfer and transportation are convenient. However, in the existing technology, during construction, the single-beam bridge erecting machine is a step-by-step through-hole method, and the 3# column of the bridge erecting machine is supported at the flange plate position of the bridge. Due to excessive force at the flange plate position, it will cause collapse and fragmentation, and then cause the bridge erecting machine to roll over, which poses a great safety risk. Utility Model Content
[0003] In view of the deficiencies in the prior art, the utility model provides a bridge erection machine column force monitoring device to solve the existing problems raised in the above background technology.
[0004] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:
[0005] A bridge-erecting machine column force monitoring device comprises a bridge-erecting machine leg and a base, wherein the bottom of the bridge-erecting machine leg is fixedly connected with a first flange, the top of the base is fixedly connected with a second flange, a monitoring device is arranged between the opposite surfaces of the first flange and the second flange, mounting screws are arranged in the through holes of the first flange and the second flange, the monitoring device comprises a pressure sensor, a third flange and a fourth flange, the upper surface of the third flange is fixedly connected with a fixed sleeve, the outer surface of the fixed sleeve is sleeved with a movable sleeve, the inner surface of the fixed sleeve is fixedly connected with a second thermal insulation cotton, and the inner surface of the movable sleeve is fixedly connected with a first thermal insulation cotton.
[0006] Preferably, the first flange is connected to the third flange via mounting screws, and the second flange is connected to the fourth flange via mounting screws.
[0007] Preferably, the bottom of the pressure sensor is fixedly connected to the middle of the upper surface of the third flange, the top of the pressure sensor is fixedly connected to the middle of the lower surface of the fourth flange, and the pressure sensor is arranged in the inner cavity of the fixed shell and the movable shell.
[0008] Preferably, a slide groove is provided on the outer surface of the fixed housing, a connecting slider is fixedly connected to the inner surface of the movable housing, and the outer surface of the connecting slider is slidably connected to the inside of the slide groove.
[0009] Preferably, a second magnetic ring is fixedly connected to the top of the movable shell, and a first magnetic ring is fixedly connected to the lower surface of the fourth flange, and the first magnetic ring is arranged directly above the second magnetic ring. Beneficial Effects
[0010] The utility model provides a bridge erection machine column force monitoring device, which has the following beneficial effects:
[0011] (1) The bridge-erecting machine column force monitoring equipment is equipped with a pressure sensor, which makes the bridge-erecting machine passing through the hole safer and more reliable. During the bridge and hole-passing process, the operator observes the pressure condition of column No. 3 measured in real time by the pressure sensor, and adjusts the force of the outriggers in time to ensure the safety of the bridge-erecting machine passing through the hole. This can avoid problems such as bridge flange fracturing and bridge-erecting machine rollover. The investment is small and the safety benefit is very significant.
[0012] (2) The bridge crane column force monitoring device can isolate dust from the external environment through the fixed shell and the movable shell, and prevent large dust from the construction site from entering the pressure sensor and affecting its detection results. The first thermal insulation cotton and the second thermal insulation cotton can reduce the temperature change around the pressure sensor, reduce the impact of temperature change on the detection accuracy, and make the detection result more accurate. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0014] Figure 2 For this utility model Figure 1 A is a schematic diagram of the enlarged structure of the middle part;
[0015] Figure 3 It is a schematic diagram of the structure of the monitoring device of the utility model;
[0016] Figure 4 It is a schematic diagram of the cross-sectional structure of the monitoring device of the utility model.
[0017] In the figure: 1. Bridge erecting machine support leg; 2. Base; 3. First flange; 4. Second flange; 5. Monitoring device; 501. Pressure sensor; 502. Third flange; 503. Fourth flange; 504. Fixed casing; 505. Slide groove; 506. Movable casing; 507. Connecting slider; 508. First thermal insulation cotton; 509. Second thermal insulation cotton; 510. First magnetic ring; 511. Second magnetic ring; 6. Mounting screws. DETAILED DESCRIPTION
[0018] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0019] like Figure 1-Figure 4 As shown, the bridge-erecting machine column force monitoring equipment includes a bridge-erecting machine leg 1 and a base 2, the bottom of the bridge-erecting machine leg 1 is fixedly connected with a first flange 3, the top of the base 2 is fixedly connected with a second flange 4, a monitoring device 5 is arranged between the opposite surfaces of the first flange 3 and the second flange 4, mounting screws 6 are arranged in the through holes of the first flange 3 and the second flange 4, the monitoring device 5 includes a pressure sensor 501, a third flange 502 and a fourth flange 503, the upper surface of the third flange 502 is fixedly connected with a fixed shell 504, the outer surface of the fixed shell 504 is sleeved with a movable shell 506, the inner surface of the fixed shell 504 is fixedly connected with a second thermal insulation cotton 509, and the inner surface of the movable shell 506 is fixedly connected with a first thermal insulation cotton 508.
[0020] Specifically, the first flange 3 is connected to the third flange 502 by means of mounting screws 6 , and the second flange 4 is connected to the fourth flange 503 by means of mounting screws 6 .
[0021] Specifically, the bottom of the pressure sensor 501 is fixedly connected to the middle of the upper surface of the third flange 502 , the top of the pressure sensor 501 is fixedly connected to the middle of the lower surface of the fourth flange 503 , and the pressure sensor 501 is arranged in the inner cavity of the fixed shell 504 and the movable shell 506 .
[0022] Specifically, a slide groove 505 is formed on the outer surface of the fixed shell 504 , and a connecting slider 507 is fixedly connected to the inner surface of the movable shell 506 . The outer surface of the connecting slider 507 is slidably connected to the inside of the slide groove 505 .
[0023] Specifically, the top of the movable shell 506 is fixedly connected with the second magnetic ring 511 , the lower surface of the fourth flange 503 is fixedly connected with the first magnetic ring 510 , and the first magnetic ring 510 is arranged right above the second magnetic ring 511 .
[0024] The working principles and beneficial effects of the above embodiments.
[0025] When in use, a set of pressure sensors 501 are installed between the first flange 3 and the second flange 4 at the bottom of the No. 3 column leg, and the pressure sensors 501 are installed on the first flange 3 and the second flange 4 through the third flange 502 and the fourth flange 503 using the mounting screws 6. The stress condition of the No. 3 column is monitored in real time through the pressure sensor 501, and the monitored information is directly uploaded to the control system of the bridge erection machine. When the pressure exceeds the limit value, the jacking cylinder of the No. 3 column will stop working, and the system will alarm to ensure construction safety, and the movable cover 506 will be moved upward until the second magnetic ring 511 It is adsorbed together with the first magnetic ring 510. At this time, the fixed shell 504 and the movable shell 506 jointly cover the pressure sensor 501, which can isolate the dust in the external environment. The first thermal insulation cotton 508 and the second thermal insulation cotton 509 can reduce the temperature change around the pressure sensor 501 and reduce the influence of temperature change on the detection accuracy. The second magnetic ring 511 is separated from the first magnetic ring 510 by moving the movable shell 506 downward until the connecting slider 507 moves to the bottom of the slide groove 505. At this time, the pressure sensor 501 can be exposed for easy maintenance.
[0026] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions. The sentence "includes an element defined by ... does not exclude the existence of other identical elements in the process, method, article or device including the element".
[0027] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A bridge erection machine column force monitoring device, comprising a bridge erection machine support leg (1) and a base (2), characterized in that: The bottom of the bridge-building machine leg (1) is fixedly connected to a first flange (3), the top of the base (2) is fixedly connected to a second flange (4), a monitoring device (5) is arranged between the opposing surfaces of the first flange (3) and the second flange (4), mounting screws (6) are arranged in the through holes of the first flange (3) and the second flange (4), the monitoring device (5) comprises a pressure sensor (501), a third flange (502) and a fourth flange (503), the upper surface of the third flange (502) is fixedly connected to a fixed casing (504), the outer surface of the fixed casing (504) is sleeved with a movable casing (506), the inner surface of the fixed casing (504) is fixedly connected to a second thermal insulation cotton (509), and the inner surface of the movable casing (506) is fixedly connected to a first thermal insulation cotton (508).
2. The bridge erection machine column force monitoring device according to claim 1 is characterized in that: The first flange (3) and the third flange (502) are connected via mounting screws (6), and the second flange (4) and the fourth flange (503) are connected via mounting screws (6).
3. The bridge erection machine column force monitoring device according to claim 1 is characterized in that: The bottom of the pressure sensor (501) is fixedly connected to the middle of the upper surface of the third flange (502), the top of the pressure sensor (501) is fixedly connected to the middle of the lower surface of the fourth flange (503), and the pressure sensor (501) is arranged in the inner cavity of the fixed casing (504) and the movable casing (506).
4. The bridge erection machine column force monitoring device according to claim 1 is characterized in that: The outer surface of the fixed casing (504) is provided with a sliding groove (505), the inner surface of the movable casing (506) is fixedly connected with a connecting slider (507), and the outer surface of the connecting slider (507) is slidably connected to the inside of the sliding groove (505).
5. The bridge erection machine column force monitoring device according to claim 1 is characterized in that: The top of the movable casing (506) is fixedly connected to a second magnetic ring (511), the lower surface of the fourth flange (503) is fixedly connected to a first magnetic ring (510), and the first magnetic ring (510) is arranged directly above the second magnetic ring (511).